Modularized structure of coke oven gas collecting pipe and operation platform and construction method thereof
Through the design of modular structures and connectors, the problems of independent structures, occupying the main line construction period and high-altitude operations in the construction of traditional coke oven gas collecting pipes and operating platforms are solved. The modular production and combination of the gas collecting pipes and operating platforms are realized, which improves the construction efficiency. Efficiency and safety.
Patent Information
- Application Number
- CN202410778272.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-17
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2044-06-17
Smart Images

Figure CN118757010A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of coke oven construction engineering, and more specifically, to a modular structure of a coke oven gas collecting pipe and an operating platform and a construction method thereof. Background Art
[0002] Coke oven is a device used to produce coke from coal, and is the main thermal equipment for coking. The construction process of coke oven involves various construction disciplines and processes such as civil foundation, furnace refractory material body, steel structure installation, pipeline installation, electrical and instrumentation equipment, etc. Among them, the construction of coke oven top gas collecting pipe and its operating platform is an important construction link in the coke oven pipeline installation.
[0003] In the design and construction of the existing coke oven gas collecting pipe and operating platform, the gas collecting pipe and the operating platform are independent structures without any connection between the structures. During the specific construction, the gas collecting pipe seat is installed on the coke oven top column corbel, and the gas collecting pipe is installed on the pipe seat. After the gas collecting pipe is installed and adjusted, the platform columns are installed on the column corbel and on both sides of the gas collecting pipe until the steel structure operating platform is completed. However, the traditional scattered construction has the problems of occupying the main line construction period, being highly dependent on the masonry greenhouse, and having many high-altitude operations. Therefore, it is urgent to develop a modular structure and construction method of the coke oven gas collecting pipe and operating platform to overcome the problems brought by traditional construction. Summary of the invention
[0004] In view of the above-mentioned defects in the prior art, the present invention provides a modular structure of a coke oven gas collecting pipe and an operating platform and a construction method thereof. Through the structural design of the connecting parts between the gas collecting pipe and the operating platform, it is ensured that the gas collecting pipe and the operating platform meet the modular processing and manufacturing requirements, so that the production of the coke oven gas collecting system and the operating platform can be started in time, and the overall structural hoisting stability requirements with the gas collecting pipe as the hoisting force-bearing structure are met.
[0005] To achieve the above-mentioned objectives, on the one hand, the present invention provides a modular structure of a coke oven gas collecting pipe and an operating platform, wherein the operating platform is constructed by means of columns on both sides of the gas collecting pipe and a crossbeam on the top; it is characterized in that, for the gas collecting pipe and the operating platform in the segmented module, the columns and the gas collecting pipe are detachably fixedly connected by means of a transverse perforated steel plate and a first bolt assembly matched therewith; the crossbeam and the gas collecting pipe are detachably fixedly connected by means of a longitudinal perforated steel plate and a second bolt assembly matched therewith; one side of the transverse perforated steel plate or the longitudinal perforated steel plate is fitted into the surface of the connecting object; the selection of the thickness of the transverse perforated steel plate and the longitudinal perforated steel plate and the specifications of the bolt assembly meets the requirement that the gas collecting pipe serves as a hoisting force-bearing structure and bears the entire weight of the segmented module; the shear bearing capacity F of the perforated steel plate is greater than the distribution force G of the total weight of the segmented module on the perforated steel plate; the ratio of the length dimension of the perforated steel plate in the compressive direction to the plate thickness is not greater than 20.
[0006] Furthermore, the two transverse perforated steel plates are respectively welded on the opposite sides of the middle of the column and the gas collecting pipe, and are connected to the column and the gas collecting pipe in cooperation with the bolt assembly; the two longitudinal perforated steel plates are respectively welded on the opposite sides of the middle of the crossbeam and the gas collecting pipe, and are connected to the crossbeam and the gas collecting pipe in cooperation with the bolt assembly.
[0007] Furthermore, the thickness of the transverse perforated steel plate and the longitudinal perforated steel plate is 10 mm respectively, the first bolt assembly includes 5 M20 bolts with a spacing of 100 mm; the second bolt assembly includes 3 M20 bolts with a spacing of 100 mm.
[0008] On the other hand, the present invention provides a modular construction method for a coke oven gas collecting pipe and an operating platform, characterized in that the modular structure of the coke oven gas collecting pipe and the operating platform as described above is implemented, comprising the following steps:
[0009] Step S1, performing force verification on the weight of the segmented modules of the gas collecting pipe and the operating platform, and calculating the model and specifications of the perforated steel plate and bolt assembly between the gas collecting pipe and the operating platform when the gas collecting pipe is used as a hoisting force-bearing structure;
[0010] Step S2, processing and manufacturing the perforated steel plate and bolt assembly according to the model and specifications determined in step S1;
[0011] Step S3, the two transverse perforated steel plates are respectively welded to the middle opposite sides of the upright column and the gas collecting pipe; the two longitudinal perforated steel plates are respectively welded to the middle opposite sides of the crossbeam and the gas collecting pipe; the perforated steel plates are welded on each span according to the above welding positions to complete the welding of the perforated steel plates in the segmented module;
[0012] Step S4, connecting the two transverse perforated steel plates with a first bolt assembly, and connecting the two longitudinal perforated steel plates with a second bolt assembly, until all perforated steel plates in the segment module are connected;
[0013] Step S5: After the segment modules are completed, they are hoisted in sections, and finally the segment modules are connected and assembled into a whole.
[0014] Furthermore, the thickness of the transverse perforated steel plate and the longitudinal perforated steel plate is 10 mm respectively, the first bolt assembly includes 5 M20 bolts with a spacing of 100 mm; the second bolt assembly includes 3 M20 bolts with a spacing of 100 mm.
[0015] Compared with the prior art, the above invention has the following advantages or beneficial effects:
[0016] (1) The present invention replaces the use of a crane in a masonry greenhouse to carry out the scattered assembly process of the gas collecting pipe and the operating platform, and realizes the modular production and installation of the gas collecting pipe and the operating platform. The processing and production can be started in a timely manner, reducing the dependence on the masonry greenhouse and avoiding conflicts with other types of work on the use of the greenhouse crane. The construction hardly occupies the main line construction period, which significantly shortens the construction period.
[0017] (2) The specifications of the perforated steel plate and the connecting bolts of the present invention are ingeniously designed to meet the hoisting stability requirements of the overall structure with the gas collecting pipe as the hoisting force-bearing structure.
[0018] (3) The present invention can carry out most of the processes on the ground, which is convenient for construction, has simple and reasonable structural connections, reduces high-altitude operations, reduces safety risks, and improves project quality. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The present invention and its features, appearance and advantages will become more apparent by reading the detailed description of non-limiting embodiments with reference to the following drawings. The same reference numerals indicate the same parts in all the drawings. The drawings are not drawn to scale, and emphasis is placed on illustrating the subject matter of the present invention.
[0020] Figure 1 It is a side structural schematic diagram of an independent coke oven gas collecting pipe and an operating platform according to an embodiment of the present invention;
[0021] Figure 2 A side structural schematic diagram of a coke oven gas collecting pipe and an operating platform connected in one embodiment of the present invention;
[0022] Figure 3 It is a structural schematic diagram of a connecting piece between a coke oven gas collecting pipe and an operating platform according to an embodiment of the present invention;
[0023] Figure 4 It is a three-dimensional structural schematic diagram of a coke oven gas collecting pipe and an operating platform segment module according to an embodiment of the present invention;
[0024] Among them, 1. column; 2. crossbeam; 3. gas collecting pipe; 4. longitudinal connecting piece; 5. first transverse connecting piece; 6. second transverse connecting piece; 4-1. first longitudinal perforated steel plate; 4-2. second longitudinal perforated steel plate; 4-3. first bolt assembly; 5-1. first transverse perforated steel plate on the left; 5-2. second transverse perforated steel plate on the left; 5-3. second bolt assembly on the left; 6-1. first transverse perforated steel plate on the right; 6-2. second transverse perforated steel plate on the right; 6-3. second bolt assembly on the right. DETAILED DESCRIPTION
[0025] The following is a further description of the structure of the present invention in conjunction with the accompanying drawings and specific embodiments, but it is not intended to limit the present invention. The execution order of actions, steps, etc. in the devices and methods shown in the claims, specifications and drawings of the present invention can be implemented in any order as long as there is no special explicit limitation on the order and the output of the previous processing is not used in the subsequent processing.
[0026] It should also be noted that in the description of this application, the terms "up", "down", "left", "right", "top", "bottom", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and do not require that the present invention must be constructed and operated in a specific direction. Therefore, they should not be understood as limitations on the present invention.
[0027] It should be understood that the terms "first" and "second" described in this application are only used for descriptive purposes and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features.
[0028] The technical solution of the present invention is described in detail below with specific embodiments and examples.
[0029] Example
[0030] See also Figure 1 The conventional operating platform is constructed by the columns 1 on both sides of the gas collecting pipe 3 and the crossbeam 2 on the top. There is no connection between the conventional operating platform and the gas collecting pipe. This embodiment relates to the modular structure of the coke oven gas collecting pipe and the operating platform. Figure 2 For the gas collecting pipe and the operating platform in the segmented module, the column 1 and the gas collecting pipe 3 are detachably fixedly connected by the first transverse connecting member 5 and the second transverse connecting member 6; the crossbeam 2 and the gas collecting pipe 3 are detachably fixedly connected by the longitudinal connecting member 4. Figure 3, the longitudinal connector 4 includes a first longitudinal perforated steel plate 4-1, a second longitudinal perforated steel plate 4-2 and a first bolt assembly 4-3. The first transverse connector 5 includes a first transverse perforated steel plate 5-1 on the left, a second transverse perforated steel plate 5-2 on the left and a second bolt assembly 5-3 on the left; the second transverse connector 6 includes a first transverse perforated steel plate 6-1 on the right, a second transverse perforated steel plate 6-2 on the right and a second bolt assembly 6-3 on the right. One side of the first transverse perforated steel plate 5-1 on the left and the second transverse perforated steel plate 6-2 on the right are in contact with the column 2; one side of the second transverse perforated steel plate 5-2 on the left and the first transverse perforated steel plate 6-1 on the right are in contact with the surface of the gas collecting pipe 3. The first longitudinal perforated steel plate 4-1 is longitudinally in contact with the axial surface of the gas collecting pipe 3. The thickness of the transverse and longitudinal perforated steel plates and the specifications of the bolt assemblies are selected to meet the requirements that the collecting pipe 3 serves as a lifting load-bearing structure and bears the entire weight of the segmented module; the shear bearing capacity F of the perforated steel plate is greater than the distribution force G of the total weight of the segmented module on the perforated steel plate; the ratio of the length dimension of the perforated steel plate in the compressive direction to the plate thickness is not greater than 20.
[0031] The following is an exemplary description of the construction process of the modular structure of the coke oven gas collecting pipe and the operating platform.
[0032] Step S1, perform force verification on the weight of the segmented modules of the gas collecting pipe and the operating platform, and calculate the model specifications of the longitudinal connector 4, the first transverse connector 5 and the second transverse connector 6 of the connecting structure between the gas collecting pipe and the operating platform when the gas collecting pipe is used as a hoisting force-bearing structure. There are two principles for calculating the specifications of the connectors: First, the strength of the connecting plate meets the load-bearing requirements, that is, the shear bearing capacity F of the connecting plate is greater than the force G allocated to the connecting plate by the weight of the segmented module. G = h*l*f v , where h is the thickness of the connecting plate, l is the length of the connecting plate, and f v is the shear strength of the connecting plate. Since l is determined by the connection length between the connecting plate and the gas collecting pipe or column or beam, the shear strength of the connecting plate f v Determined by the material of the connecting plate (a steel connecting plate is used in this embodiment), when F>G, h>G / l*f v。 Secondly, the connecting plate meets the principles of compressive stability and structural requirements. During the installation of the gas collecting pipe, the connecting plate is squeezed by the structural support. To ensure the compressive stability of the connecting plate, the ratio of the length dimension of the plate in the compressive direction to the plate thickness is not greater than 20, that is, h>l / 20. In this embodiment, the maximum compressive dimension of the connecting plate is 185mm, and according to the above principle, the plate thickness is not less than 10mm. According to the principle of material saving, this embodiment uses a 10mm thick steel plate as a connecting piece.
[0033] Step S2, according to the model and specification determined in step S1, the first longitudinal perforated steel plate 4-1, the second longitudinal perforated steel plate 4-2, the first bolt assembly 4-3, the first transverse perforated steel plate 5-1 on the left, the second transverse perforated steel plate 5-2 on the left, the second bolt assembly 5-3 on the left, the first transverse perforated steel plate 6-1 on the right, the second transverse perforated steel plate 6-2 on the right, and the second bolt assembly 6-3 on the right are manufactured;
[0034] Step S3, two transverse perforated steel plates are welded to the opposite sides of the middle of the column 1 and the gas collecting pipe 3; two longitudinal perforated steel plates are welded to the opposite sides of the middle of the crossbeam 2 and the gas collecting pipe 3; the perforated steel plates are welded on each span according to the above welding positions to complete the welding of the perforated steel plates in the segmented module. Figure 2 , add structural connectors, weld the upper part of the second longitudinal perforated steel plate 4-2 to the middle bottom of the crossbeam 2 along the longitudinal direction of the gas collecting pipe 3, and weld the first longitudinal perforated steel plate 4-1 to the top of the gas collecting pipe 3 along the longitudinal direction of the gas collecting pipe 3 and the corresponding part of the second longitudinal perforated steel plate 4-2. The first transverse perforated steel plate 5-1 on the left is welded to the middle part of the column 1 corresponding to the gas collecting pipe 3, and the second transverse perforated steel plate 5-2 on the left is welded to the gas collecting pipe 3 and the corresponding part of the second transverse perforated steel plate 5-2 on the left. The second transverse perforated steel plate 6-2 on the right is welded to the side of the column 1 corresponding to the gas collecting pipe 3, and the first transverse perforated steel plate 6-1 on the right is welded to the gas collecting pipe 3 and the corresponding part of the second transverse perforated steel plate 6-2 on the right. According to the above welding positions, the first longitudinal perforated steel plate 4-1, the second longitudinal perforated steel plate 4-2, the first transverse perforated steel plate 5-1 on the left, the second transverse perforated steel plate 5-2 on the left, the first transverse perforated steel plate 6-1 on the right, and the second transverse perforated steel plate 6-2 on the right are welded on each span. All the first longitudinal perforated steel plate 4-1, the second longitudinal perforated steel plate 4-2, the first transverse perforated steel plate 5-1 on the left, the second transverse perforated steel plate 5-2 on the left, the first transverse perforated steel plate 6-1 on the right, and the second transverse perforated steel plate 6-2 on the right in the segmented module are welded.
[0035] Step S4, use the first bolt assembly 4-3 of M20 to connect the first longitudinal perforated steel plate 4-1 and the second longitudinal perforated steel plate 4-2, use the second bolt assembly 5-3 on the left side of M20 to connect the first transverse perforated steel plate 5-1 on the left side and the second transverse perforated steel plate 5-2 on the left side, use the second bolt assembly 6-3 on the right side of M20 to connect the first transverse perforated steel plate 6-1 on the right side and the second transverse perforated steel plate 6-2 on the right side, and complete the connection of all the first longitudinal perforated steel plate 4-1, the second longitudinal perforated steel plate 4-2, the first transverse perforated steel plate 5-1 on the left side, the second transverse perforated steel plate 5-2 on the left side, the first transverse perforated steel plate 6-1 on the right side, and the second transverse perforated steel plate 6-2 on the right side in the modular segment. The structure is as follows Figure 4As shown. The remaining modular segments are processed and manufactured according to the above steps. Further preferably, the first bolt assembly includes 5 M20 bolts with a spacing of 100 mm; the second bolt assembly includes 3 M20 bolts with a spacing of 100 mm.
[0036] Step S5: After the segment modules are completed, they are hoisted in sections, and finally the segment modules are connected and assembled into a whole.
[0037] From the above description, it can be seen that the modular structure of the coke oven gas collecting pipe and the operating platform provided by the present invention is easy to construct, the structural connection is simple and reasonable, and the modular production and installation of the gas collecting pipe and the operating platform can be realized. It is more economical and efficient to use the gas collecting pipe to bear the force when lifting the module.
[0038] Those skilled in the art should understand that those skilled in the art can implement variations by combining the prior art and the above embodiments, which will not be described in detail here. Such variations do not affect the essential content of the present invention, and will not be described in detail here.
[0039] The above describes the preferred embodiments of the present invention. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in a common manner in the art; any technician familiar with the art can use the above-disclosed methods and technical contents to make many possible changes and modifications to the technical solutions of the present invention without departing from the scope of the technical solutions of the present invention, or modify them into equivalent embodiments of equivalent changes, which does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solutions of the present invention are still within the scope of protection of the technical solutions of the present invention.
Claims
1. A modular structure of a coke oven gas collecting pipe and an operating platform, wherein the operating platform is constructed by pillars (1) on both sides of the gas collecting pipe (3) and a crossbeam (2) on the top; It is characterized in that For the gas collecting pipe and the operating platform in the segmented module, the upright column (1) and the gas collecting pipe (3) are detachably fixedly connected by a transverse perforated steel plate and a first bolt assembly matched therewith; the crossbeam (2) and the gas collecting pipe (3) are detachably fixedly connected by a longitudinal perforated steel plate and a second bolt assembly matched therewith; one side of the transverse perforated steel plate or the longitudinal perforated steel plate is in contact with the surface of the connecting object; the size of the transverse perforated steel plate and the longitudinal perforated steel plate and the specification of the bolt assembly are selected to meet the requirement that the gas collecting pipe (3) serves as a lifting load-bearing structure and bears the entire weight of the segmented module; the shear bearing capacity F of the perforated steel plate is greater than the distribution force G of the total weight of the segmented module on the perforated steel plate; The ratio of the length dimension of the perforated steel plate in the compression direction to the plate thickness shall not exceed 20.
2. The modular structure of the coke oven gas collecting pipe and the operating platform according to claim 1, It is characterized in that The two transverse perforated steel plates are respectively welded to the opposite sides of the middle of the column (1) and the gas collecting pipe (3), and are used in conjunction with a bolt assembly to achieve a connection between the column (1) and the gas collecting pipe (3); the two longitudinal perforated steel plates are respectively welded to the opposite sides of the middle of the crossbeam (2) and the gas collecting pipe (3), and are used in conjunction with a bolt assembly to achieve a connection between the crossbeam (2) and the gas collecting pipe (3).
3. The modular structure of the coke oven gas collecting pipe and the operating platform according to claim 1, It is characterized in that The thickness of the transverse perforated steel plate and the longitudinal perforated steel plate is 10 mm respectively. The first bolt assembly includes 5 M20 bolts with a spacing of 100 mm; the second bolt assembly includes 3 M20 bolts with a spacing of 100 mm.
4. Modular construction method of coke oven gas collecting pipe and operating platform, It is characterized in that Implementing the modular structure of the coke oven gas collecting pipe and the operating platform as claimed in any one of claims 1 to 3 comprises the following steps: Step S1, performing force verification on the weight of the segmented modules of the gas collecting pipe and the operating platform, and calculating the model and specifications of the perforated steel plate and bolt assembly between the gas collecting pipe and the operating platform when the gas collecting pipe is used as a hoisting force-bearing structure; Step S2, processing and manufacturing the perforated steel plate and bolt assembly according to the model and specifications determined in step S1; Step S3, the two transverse perforated steel plates are respectively welded to the opposite sides of the middle of the column (1) and the gas collecting pipe (3); the two longitudinal perforated steel plates are respectively welded to the opposite sides of the middle of the crossbeam (2) and the gas collecting pipe (3); the perforated steel plates are welded on each span according to the above welding positions to complete the welding of the perforated steel plates in the segmented module; Step S4, connecting the two transverse perforated steel plates with a first bolt assembly, and connecting the two longitudinal perforated steel plates with a second bolt assembly, until all perforated steel plates in the segment module are connected; Step S5: After the segment modules are completed, they are hoisted in sections, and finally the segment modules are connected and assembled into a whole.
5. The modular construction method of the coke oven gas collecting pipe and the operating platform according to claim 4, It is characterized in that The thickness of the transverse perforated steel plate and the longitudinal perforated steel plate is 10 mm respectively. The first bolt assembly includes 5 M20 bolts with a spacing of 100 mm; the second bolt assembly includes 3 M20 bolts with a spacing of 100 mm.
Citation Information
Patent Citations
Modular filtration frame assembly
CN104888518A
Device for assembling and hoisting large-scale structure and pipeline
CN201502166U
Device for take gas collection of central bearing
CN204530963U
Portable pump line switching platform
CN206233591U
Detachable quick moving platform