Charging pile control method and system with load control function, medium and product

By analyzing historical power consumption data and multiple data sources to determine the power limit value of the charging pile, precise control of the power of the charging pile is achieved, solving the problem of low load management accuracy in the existing technology, and improving the safety of the power grid and equipment. sex and stability.

CN118769968AActive Publication Date: 2024-10-15SICON CHAT UNION ELECTRIC CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411166294.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-23
Publication Date
2024-10-15
Estimated Expiration
2044-08-23

AI Technical Summary

Technical Problem

Load management of charging piles needs to comprehensively consider the real-time status of the power system, user needs and charging facility availability. However, existing technologies rely on manual experience or fixed rules, resulting in low accuracy of regulation and may pose a threat to the safety of the power grid system and equipment.

Method used

By analyzing historical power consumption data, control serial port communication data, and control network port operation data, the screen power limit, EMS power limit, and operation power limit of the charging pile are determined, and a multi-dimensional consideration method is used to set the target power limit value to accurately control charging. The power of the pile ensures the stability and security of the power grid.

Benefits of technology

It improves the accuracy of charging pile power control, reduces the load pressure on the power grid, enhances the safety and compliance of the charging process, and ensures the stability of the power grid system and equipment safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118769968A_ABST
    Figure CN118769968A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of charging pile control, in particular to a charging pile control method and system with load control, a medium and a product, and the method comprises the steps: obtaining a screen limited power value of a to-be-regulated charging pile based on the current moment; identifying a regulation serial port number corresponding to the to-be-regulated charging pile, acquiring regulation serial port communication data corresponding to the to-be-regulated charging pile based on the regulation serial port number, and determining an EMS limited power value of the to-be-regulated charging pile based on the regulation serial port communication data; identifying a regulation and control network port number corresponding to the to-be-regulated and controlled charging pile, obtaining regulation and control network port operation data corresponding to the to-be-regulated and controlled charging pile based on the regulation and control network port number, and determining an operation limited power value of the to-be-regulated and controlled charging pile based on the regulation and control network port operation data; and the screen limited power value, the EMS limited power value and the operation limited power value are compared to determine a target limited power value, and the charging pile to be regulated and controlled is regulated and controlled based on the target limited power value. According to the invention, the accuracy of regulating and controlling the load of the charging pile is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of charging pile control technology, and in particular to a charging pile control method, system, medium and product with load control. Background Art

[0002] With the rapid development and popularization of the electric vehicle industry, charging piles, as an important infrastructure for charging electric vehicles, are also expanding in scale. At the same time, the large-scale application of charging piles has also brought huge load pressure and energy management problems to the power system. The use of charging piles is often affected by various factors such as users' work and living habits, so the charging demand of electric vehicles is uncertain and unpredictable. In addition, the load characteristics of charging piles are also different from those of traditional electrical equipment. The load of charging piles during use has large power fluctuations and peak-to-valley differences. When a large number of charging piles are in operation at the same time, it will pose a severe test to the stability and power supply capacity of the power system.

[0003] In the related art, the load of the charging pile is generally adjusted based on manual experience or fixed rules. However, the load management of the charging pile usually needs to comprehensively consider factors such as the real-time status of the power system, the user's charging needs, and the availability of charging facilities. Using manual experience to control the load of the charging pile may result in low control accuracy, which may pose a threat to the safety of the power grid system and equipment such as charging piles. Summary of the invention

[0004] In order to improve the accuracy of regulating the load of a charging pile, the present application provides a charging pile control method, system, medium and product with load control.

[0005] In a first aspect, the present application provides a charging pile control method with load control, which adopts the following technical solution: A charging pile control method with load control, comprising: Acquire a screen power limit value of the charging pile to be regulated based on the current moment, wherein the screen power limit value is determined according to historical power consumption data, wherein the historical power consumption data includes historical power values ​​of each charging pile in a historical time period; Identify the control serial port number corresponding to the charging pile to be regulated, obtain the control serial port communication data corresponding to the charging pile to be regulated based on the control serial port number, and determine the EMS power limit value of the charging pile to be regulated based on the control serial port communication data; Identify the control network port number corresponding to the charging pile to be regulated, obtain the control network port operation data corresponding to the charging pile to be regulated based on the control network port number, and determine the operation power limit value of the charging pile to be regulated based on the control network port operation data; The screen power limit value, the EMS power limit value and the operation power limit value are compared to determine a target power limit value, and the charging pile to be regulated is regulated based on the target power limit value.

[0006] By adopting the above technical solution, by analyzing the historical power values ​​of each charging pile in the historical time period, it is convenient to more accurately predict and set the screen power limit value of the current charging pile to be regulated. In addition, by analyzing the control serial port communication data corresponding to the charging pile to be regulated and the control network port operation data corresponding to the charging pile to be regulated, the EMS power limit value corresponding to the control serial port and the operation power limit value corresponding to the control network port are respectively determined. Through multi-dimensional consideration, it is convenient to more comprehensively predict the appropriate power limit value of the charging pile to be regulated, that is, through multi-dimensional consideration, it is convenient to improve the accuracy of determining the power regulation of the charging pile to be regulated, thereby also facilitating the improvement of the stability and safety of equipment such as the charging pile to be regulated and the power grid system.

[0007] In a possible implementation manner, comparing the screen power limit value, the EMS power limit value, and the operation power limit value to determine a target power limit value includes: Acquire the actual working power, and determine the timing duration corresponding to the charging pile to be regulated based on the timing mapping relationship and the actual working power, wherein the timing mapping relationship is the corresponding relationship between the actual working power and the timing duration corresponding to the charging pile to be regulated; Obtain the current time, and determine whether the timing is over based on the current time and the timing duration, and if so, determine whether the screen power limit value is less than the operating power limit value; If the screen power limit value is less than the operation power limit value, determine whether the screen power limit value is less than the EMS power limit value, if so, determine the screen power limit value as the target power limit value, if not, determine the EMS power limit value as the target power limit value; If the screen power limit value is not less than the operation power limit value, determine whether the operation power limit value is less than the EMS power limit value. If so, determine the operation power limit value as the target power limit value. If not, determine the EMS power limit value as the target power limit value.

[0008] By adopting the above-mentioned technical solution, the embodiment of the present application provides a method for determining the target power limit value from the screen power limit value, the EMS power limit value and the operation power limit value, and determines the minimum power limit value as the target power limit value so as to reduce the pressure on the power grid caused by the actual charging power, and also facilitates meeting the user's charging needs while ensuring the safety and compliance of the entire charging process.

[0009] In a possible implementation, the determining the EMS power limit value of the charging pile to be regulated based on the regulated serial port communication data includes: Writing the regulated serial port communication data into a first preset circular buffer, and identifying communication features contained in the regulated serial port communication data; Determine a first resolution protocol corresponding to the communication feature based on the communication feature and the first preset protocol mapping relationship, wherein the first preset protocol mapping relationship is a correspondence relationship between the communication feature and the first resolution protocol; The control serial port communication data is parsed based on the first parsing protocol to obtain the EMS power limit value of the charging pile to be regulated.

[0010] By adopting the above technical solution, by writing the control serial port communication data into the circular buffer, it is convenient to temporarily store and orderly process the control serial port communication data. In addition, by writing the control serial port communication data into the circular buffer, the delay problem of the control serial port communication data in the transmission process can be effectively solved, ensuring that the control serial port communication data will not be lost due to untimely processing speed. The corresponding parsing protocol is determined according to the communication characteristics, and the control serial port communication data is parsed based on the parsing protocol degree, which is convenient to improve the flexibility in obtaining communication data. In addition, it also helps to improve the accuracy in determining the EMS power limit value.

[0011] In a possible implementation, the determining the operating power limit value of the charging pile to be regulated based on the regulated network port operation data includes: Writing the control network port operation data into a second preset circular buffer, and identifying the operation characteristics contained in the control network port operation data; Determine, based on the mapping relationship between the operation feature and the second preset protocol, a second resolution protocol corresponding to the communication feature, wherein the preset protocol mapping relationship is a corresponding relationship between the communication feature and the second resolution protocol; The operation power limit value of the charging pile to be regulated is obtained by parsing the operation data of the regulation network port based on the second analysis protocol.

[0012] By adopting the above technical solution, by writing the control network port operation data into the circular buffer, it is convenient to temporarily store and orderly process the control network port operation data. In addition, by writing the control network port operation data into the circular buffer, the delay problem of the control network port operation data in the transmission process can be effectively solved, ensuring that the control network port operation data will not be lost due to untimely processing speed. The corresponding parsing protocol is determined according to the operation characteristics, and the control network port operation data is parsed based on the parsing protocol degree, which is convenient to improve the flexibility in obtaining operation data. In addition, it also helps to improve the accuracy in determining the operation limit power value.

[0013] In a possible implementation manner, when the target power limit value is the EMS power limit value or the operation power limit value, the method further includes: Obtaining device parameters and charging records, wherein the device parameters are standard power ranges corresponding to devices that are charged using the charging pile to be regulated; When the target power limit value exceeds the standard power range, determining the time required to complete charging according to the charging record; Acquire the operating parameters of the charging pile to be regulated, and simulate the operating conditions of the charging pile to be regulated within a first preset time period based on the operating parameters and the device parameters to obtain simulated operating data, wherein the first preset time period is a predicted duration after the current moment, wherein the predicted duration is consistent with the duration required for charging to be completed; Identify the simulated power value contained in the simulated operation data, and when the simulated power value is within a preset limit range and the time required to complete charging is lower than the preset limit time, regulate the charging pile to be regulated based on the target limit power value in a second preset time period.

[0014] By adopting the above technical scheme, after determining the appropriate target power limit value of the charging pile to be regulated, the charging pile to be regulated is not directly regulated based on the target power limit, but it is judged based on the parameters of the charging equipment in use and the charging record whether the charging equipment will be affected after the target power limit value of the charging pile to be regulated is replaced. If the replacement of the power limit may have an impact on the equipment being charged, the possible abnormalities are evaluated according to the operation simulation results, and then it is determined whether the charging pile to be regulated needs to be regulated based on the evaluation results. If the risk level corresponding to the evaluation result is low, the charging pile to be regulated can be regulated after the charging equipment is charged. In addition, by adding the feature of preset limit time, the safety of the charging pile during the charging process can be ensured while also improving the safety and stability of the charging pile.

[0015] In a possible implementation, when the simulated power value exceeds a preset limit range, or the time required for charging to be completed is not less than a preset limit time, the method further includes: Determine at least one associated charging pile of the charging pile to be regulated based on the control network port number, each associated charging pile having the same control network port number as that corresponding to the charging pile to be regulated; Obtaining the associated use record of each associated charging pile, and determining the power margin corresponding to each associated charging pile based on each associated use record, and determining the associated charging pile with the highest power margin as the target associated charging pile; A power difference is determined according to the actual power value of the charging pile to be regulated and the corresponding target power limit value, and an associated power limit value of the target associated charging pile is determined based on the power difference.

[0016] By adopting the above technical solution, if the risk level corresponding to the evaluation result is high, the load pressure of the power grid can be alleviated by reducing the power limit of the associated charging piles of the charging piles to be regulated, thereby facilitating the safety and stability of the charging piles to be regulated, the power grid and the charging equipment during the charging of the charging equipment. In addition, the target associated charging piles are regulated based on the power difference, which facilitates improving the regulation rate and regulation accuracy.

[0017] In a second aspect, the present application provides a control system, which adopts the following technical solution: A control system, the control system comprising: at least one processor; Memory; At least one application, wherein the at least one application is stored in a memory and configured to be executed by at least one processor, and the at least one application is configured to: execute the above-mentioned charging pile control method with load control.

[0018] In a third aspect, the present application provides a computer-readable storage medium, which adopts the following technical solution: A computer-readable storage medium includes: a computer program that can be loaded by a processor and execute the above-mentioned charging pile control method with load control.

[0019] In a fourth aspect, the present application provides a computer program product, which adopts the following technical solution: A computer program product includes a computer program, and when the computer program is executed by a processor, the charging pile control method with load control is implemented.

[0020] In summary, the present application includes at least one of the following beneficial technical effects: By analyzing the historical power values ​​of each charging pile in the historical time period, it is convenient to more accurately predict and set the screen power limit value of the current charging pile to be regulated. In addition, by analyzing the control serial port communication data corresponding to the charging pile to be regulated and the control network port operation data corresponding to the charging pile to be regulated, the EMS power limit value corresponding to the control serial port and the operation power limit value corresponding to the control network port are determined respectively. Through multi-dimensional consideration, it is convenient to more comprehensively predict the appropriate power limit value of the charging pile to be regulated, that is, through multi-dimensional consideration, it is convenient to improve the accuracy of determining the power regulation of the charging pile to be regulated, thereby also facilitating the improvement of the stability and safety of equipment such as the charging pile to be regulated and the power grid system.

[0021] After determining the appropriate target power limit value for the charging pile to be regulated, the charging pile to be regulated is not directly regulated based on the target power limit, but it is judged based on the parameters of the charging equipment in use and the charging record whether the charging equipment will be affected after the target power limit value of the charging pile to be regulated is changed. If the changing of the power limit may have an impact on the equipment being charged, the possible abnormalities are evaluated according to the operation simulation results, and then it is determined whether the charging pile to be regulated needs to be regulated based on the evaluation results. If the risk level corresponding to the evaluation result is low, the charging pile to be regulated can be regulated after the charging equipment is charged. In addition, by adding the feature of preset limit time, the safety of the charging pile during the charging process can be ensured while improving the safety and stability of the charging pile. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a flow chart of a charging pile control method with load control in an embodiment of the present application; Figure 2 This is a schematic diagram of a judgment process map in an embodiment of the present application; Figure 3 It is a schematic diagram of a flow chart of simulation control in an embodiment of the present application; Figure 4 It is a structural schematic diagram of a control system in an embodiment of the present application. DETAILED DESCRIPTION

[0023] The following is combined with Figure 1-4 This application is described in further detail.

[0024] After reading this specification, those skilled in the art may make non-creative modifications to this embodiment as needed, but such modifications are protected by patent law as long as they are within the scope of the claims of this application.

[0025] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0026] It should be noted that in the optional embodiments of the present application, the object information and other related data involved, when the embodiments in the present application are applied to specific products or technologies, need to obtain the permission or consent of the object, and the collection, use and processing of the relevant data need to comply with the relevant laws, regulations and standards of the relevant countries and regions. In other words, if the embodiments of the present application involve data related to the object, it needs to be obtained with the authorization and consent of the object, the authorization and consent of the relevant departments, and in compliance with the relevant laws, regulations and standards of the country and region. If personal information is involved in the embodiments, the acquisition of all personal information needs to obtain the consent of the individual. If sensitive information is involved, the separate consent of the information subject needs to be obtained. The embodiments also need to be implemented with the authorization and consent of the object.

[0027] Specifically, the embodiment of the present application provides a charging pile control method with load control, which is executed by a control system, and the control system can be a server or a terminal device, wherein the server can be an independent physical server, or a server cluster or distributed system composed of multiple physical servers, or a cloud server providing cloud computing services. The terminal device can be a smart phone, a tablet computer, a laptop computer, a desktop computer, etc., but is not limited thereto. The terminal device and the server can be directly or indirectly connected via wired or wireless communication, and the embodiment of the present application does not limit this.

[0028] refer to Figure 1 , Figure 1 : is a flow chart of a charging pile control method with load control in an embodiment of the present application, the method comprises steps S110 to S140, wherein: Step S110: based on the current moment, the screen power limit value of the charging pile to be regulated is obtained, where the screen power limit value is determined based on historical power consumption data, and the historical power consumption data includes historical power values ​​of each charging pile in a historical time period.

[0029] Specifically, the charging pile to be regulated will generally display its power limit intuitively through the display screen, so as to remind relevant users to choose a suitable charging pile for charging. Different types of charging piles to be regulated have different screen power limit values. For example, when the type of charging pile to be regulated is a slow charging type, the corresponding screen power limit value may be 3.3 kilowatts or 7 kilowatts; when the type of charging pile to be regulated is a fast charging type, the corresponding screen power limit value may be more than 60 kilowatts. Among them, the slow charging type of charging pile to be regulated may be suitable for long-term charging scenarios such as homes, while the fast charging type of charging pile to be regulated may be suitable for places that require fast charging, such as highway service areas and shopping malls.

[0030] The screen power limit value of the charging pile to be regulated can be determined based on the historical electricity consumption data, where the historical electricity consumption data includes the charging records of each charging pile to be regulated within the historical time period, including the start time, end time, charging amount and charging power value of each charging, etc., which can be obtained from the background management system of the charging pile to be regulated. In addition, it is necessary to collect the compliance data of the power grid in each charging stage to analyze the carrying capacity and fluctuation of the power grid. Finally, the user's demand for charging power values ​​in different time periods can be analyzed. For example, a higher power value may be required during the peak charging period to meet the needs of fast charging, while the power value can be reduced during the charging trough period to save power grid resources. Based on the analysis results, the screen limit power values ​​corresponding to the charging pile to be regulated in different time periods are determined. The screen limit power value corresponding to the charging pile to be regulated in any time period must not only meet the user's charging needs, but also cannot cause excessive load pressure on the power grid. For example, based on the historical electricity consumption data, it is determined that there are two power values ​​that can meet the user's charging needs in the xx time period, namely power value a and power value b. Among them, when the power value a or power value b is used as the power limit value in the historical xx time period, when the load pressure caused to the power grid is lower than the preset pressure threshold, the power value a or power value b can be determined as the screen limit power value corresponding to the charging pile to be regulated in the xx time period; when the power value a is used as the power limit value in the historical xx time period, the load pressure caused to the power grid is lower than the preset pressure threshold, and when the power value b is used as the power limit value in the historical xx time period, when the load pressure caused to the power grid is not lower than the preset pressure threshold, the power value a can be determined as the screen limit power value corresponding to the charging pile to be regulated in the xx time period.

[0031] Step S120: Identify the control serial port number corresponding to the charging pile to be regulated, obtain the control serial port communication data corresponding to the charging pile to be regulated based on the control serial port number, and determine the EMS power limit value of the charging pile to be regulated based on the control serial port communication data.

[0032] Specifically, each charging pile to be regulated corresponds to a regulation serial port number. The actual power usage values ​​of all devices belonging to the same regulation serial port number can be received through the regulation serial port number corresponding to the charging pile to be regulated. Among them, in addition to receiving the actual power usage value of the corresponding charging pile to be regulated, the same regulation serial port number can also receive the actual power usage values ​​of other devices. Other devices may include environmental monitoring equipment, safety protection equipment and auxiliary equipment. The environmental monitoring equipment is used to monitor the temperature, humidity and air quality around the regulated charging pile to ensure the safety of the charging process. The safety protection equipment may include overcurrent protector, leakage protector and lightning protection equipment, etc., which are used for the safety of the charging equipment. The auxiliary equipment may be a display screen, a card reader, etc., which is used to provide information interaction functions for users.

[0033] The control serial port communication data contains the actual power values ​​of the charging piles and other devices to be controlled. Since each control serial port corresponds to a control power limit, that is, when the sum of the actual power limits of all power-consuming devices corresponding to the control serial port is not higher than the control power limit during use, the load pressure on the power grid is low. Therefore, all power-consuming devices corresponding to the same control serial port need to be allocated power values ​​based on the control power limit. The EMS power limit value of the control charging pile is obtained after the power value allocation. Since different control serial ports correspond to different power-consuming devices, the power value allocation method of the control power display corresponding to different control serial ports is different.

[0034] Furthermore, in order to improve the accuracy of determining the EMS power limit value, determining the EMS power limit value of the charging pile to be regulated based on the regulated serial port communication data may specifically include: The control serial port communication data is written into a first preset circular buffer, and the communication characteristics contained in the control serial port communication data are identified; based on the communication characteristics and the first preset protocol mapping relationship, the first resolution protocol corresponding to the communication characteristics is determined, and the first preset protocol mapping relationship is the correspondence between the communication characteristics and the first resolution protocol; based on the first resolution protocol, the control serial port communication data is parsed to obtain the EMS power limit value of the charging pile to be regulated.

[0035] Specifically, the first preset circular buffer may be a circular buffer pool for storing the control serial port communication data. The use of the circular buffer pool to store the control serial port communication data facilitates effective management of storage space, thereby facilitating data overflow. In addition, by writing the control serial port communication data into the circular buffer, the delay problem of the control serial port communication data in the transmission process can be effectively solved, ensuring that the control serial port communication data will not be lost due to untimely processing speed. Since different charging piles to be regulated or other devices belonging to the same control serial port as the charging piles to be regulated have different manufacturers, the data forms of the control serial port communication data corresponding to different charging piles to be regulated or other devices belonging to the same control serial port as the charging piles to be regulated may be different. Based on the communication features contained in different control serial port communication data, it is convenient to quickly locate the first resolution protocol corresponding to the control serial port communication data. Different communication features correspond to different first resolution protocols. According to the first preset protocol mapping relationship, the first resolution protocol corresponding to any communication feature can be determined. The first preset protocol mapping relationship can be determined by relevant staff based on historical experimental data and then uploaded to the control system. The specific content is not specifically limited in the embodiment of the present application.

[0036] After determining the first parsing protocol corresponding to the control serial port communication data, the control serial port communication data is parsed based on the first parsing protocol to obtain the control parsing data. Based on the above method, the control parsing data corresponding to the charging pile to be regulated and each other device belonging to the same control serial port as the charging pile to be regulated can be determined. The power value allocation method of the control power display corresponding to the control serial port is stored in the corresponding control parsing data. By performing feature recognition on the control parsing data of the charging to be regulated, the EMS power limit value corresponding to the charging pile to be regulated can be determined.

[0037] Step S130: Identify the control network port number corresponding to the charging pile to be regulated, obtain the control network port operation data corresponding to the charging pile to be regulated based on the control network port number, and determine the operation power limit value of the charging pile to be regulated based on the control network port operation data.

[0038] Specifically, a control network port can receive the control network port operation data corresponding to multiple charging piles to be regulated. For the convenience of management, a factory area or a parking lot is generally divided into multiple areas, each area corresponds to a control network port, and a control operation power limit is set for each control network port. All charging piles to be regulated belonging to the same control network port need to be allocated power values ​​based on the control operation power limit. The operation limit power value of the charging pile to be regulated is obtained after the power value allocation. Due to the different types and performances of different charging piles to be regulated, the operation limit power values ​​corresponding to different charging piles to be regulated in the same control network port are different. Each charging pile to be regulated corresponds to a different control network port number. Based on the control network port number, the control network port operation data corresponding to the charging pile to be regulated can be accurately determined from the operation data of multiple control network ports. By performing feature recognition on the control network port operation data, the operation limit power value corresponding to the charging pile to be regulated can be determined.

[0039] Furthermore, in order to improve the accuracy of determining the operating power limit value, determining the operating power limit value of the charging pile to be regulated based on the regulated network port operation data may specifically include: The control network port operation data is written into a second preset circular buffer, and the operation characteristics contained in the control network port operation data are identified; based on the mapping relationship between the operation characteristics and the second preset protocol, the second parsing protocol corresponding to the communication characteristics is determined, and the preset protocol mapping relationship is the correspondence between the communication characteristics and the second parsing protocol; based on the second parsing protocol, the control network port operation data is parsed to obtain the operation limit power value of the charging pile to be regulated.

[0040] Specifically, the second preset circular buffer is consistent with the first preset circular buffer, and is a circular buffer pool. By writing the control network port operation data into the second preset circular buffer, the control network port operation data can be stored in an orderly manner, and the overflow of the control network port operation data during the transmission process can be reduced, thereby facilitating the improvement of the integrity of the control network port operation data. Since different charging posts to be regulated correspond to different manufacturers, the data format of the control network port operation data corresponding to different charging posts to be regulated may be different. Based on the operation characteristics contained in different control network port operation data, it is convenient to quickly locate the second resolution protocol corresponding to the control network port operation data. Different operation characteristics correspond to different second resolution protocols. According to the second preset protocol mapping relationship, the second resolution protocol corresponding to any operation characteristic can be determined. The second preset protocol mapping relationship can be determined by relevant staff based on historical experimental data and uploaded to the control system. The specific content is not specifically limited in the embodiments of this application.

[0041] Step S140: Compare the screen power limit value, the EMS power limit value and the operation power limit value to determine a target power limit value, and regulate the charging pile to be regulated based on the target power limit value.

[0042] Specifically, after determining the screen power limit value, EMS power limit value, and operation power limit value of the charging pile to be regulated, the corresponding power limit values ​​of the three can be directly compared to determine the target power limit value, which can be a minimum value. The embodiment of the present application provides a method for determining the target power limit value from the screen power limit value, EMS power limit value, and operation power limit value of the charging pile to be regulated, which can specifically include: The actual working power is obtained, and the timing duration corresponding to the charging pile to be regulated is determined based on the timing mapping relationship and the actual working power. The timing mapping relationship is the corresponding relationship between the actual working power and the timing duration corresponding to the charging pile to be regulated.

[0043] Specifically, the actual working power is the working power corresponding to the charging pile to be regulated at the current moment. Different actual working powers correspond to different timing durations. The greater the actual working power, the shorter the corresponding timing duration. The timing mapping relationship contains timing durations corresponding to different actual working powers. A period of timing duration represents a judgment cycle. After the judgment cycle ends, the target power limit value needs to be re-determined from the screen power limit value, the EMS power limit value, and the operation power limit value. For example, according to the actual working power corresponding to the charging pile a to be regulated, it is determined that the timing duration corresponding to the charging pile a to be regulated is 500 milliseconds.

[0044] Get the current time, and determine whether the timing has ended based on the current time and the timing duration. If so, determine whether the screen power limit value is less than the operating power limit value; if the screen power limit value is less than the operating power limit value, determine whether the screen power limit value is less than the EMS power limit value. If so, determine the screen power limit value as the target power limit value; if not, determine the EMS power limit value as the target power limit value; if the screen power limit value is not less than the operating power limit value, determine whether the operating power limit value is less than the EMS power limit value. If so, determine the operating power limit value as the target power limit value; if not, determine the EMS power limit value as the target power limit value.

[0045] Before each judgment, it is necessary to determine whether the current time has ended. Only after the time has ended will the power limit value comparison process be started. Figure 2 As shown, Figure 2 A judgment flow map is provided for the embodiment of the present application. The judgment flow map contains multiple judgment execution flow lines. If the timing corresponding to the current moment has not ended, it can be directly executed to the end node. If the timing corresponding to the current moment has ended, the screen power limit value can be compared with the EMS power limit value first, or the screen power limit value can be compared with the operation power limit value first. The order of comparing the three is not specifically limited in the embodiment of the present application, such as Figure 2 As shown, Figure 2 First, the screen power limit value is compared with the operation power limit value. When the screen power limit value is less than the operation power limit value, the smaller screen power limit value is compared with the EMS power limit value. If the screen power limit value is still less than the EMS power limit value, the screen power limit value is directly determined as the target power limit value. Similarly, the specific execution process of other judgment execution flow lines in the judgment process map can refer to the execution method of the judgment execution flow line that determines the screen power limit value as the target power limit value, which will not be repeated here.

[0046] For the embodiment of the present application, by analyzing the historical power values ​​of each charging pile within the historical time period, it is convenient to more accurately predict and set the screen power limit value of the current charging pile to be regulated. In addition, by analyzing the control serial port communication data corresponding to the charging pile to be regulated and the control network port operation data corresponding to the charging pile to be regulated, the EMS power limit value corresponding to the control serial port and the operation power limit value corresponding to the control network port are respectively determined. Through a multi-dimensional consideration method, it is convenient to more comprehensively predict the appropriate power limit value of the charging pile to be regulated, that is, through a multi-dimensional consideration method, it is convenient to improve the accuracy of determining the power regulation of the charging pile to be regulated, thereby also facilitating the improvement of the stability and safety of equipment such as the charging pile to be regulated and the power grid system.

[0047] Furthermore, in order to improve the safety and stability of the charging pile, the method provided in the embodiment of the present application further includes steps S1 to S4, such as Figure 3 As shown, where: Step S1: Obtain device parameters and charging records, where the device parameters are the standard power range corresponding to the device that is charged using the charging pile to be regulated.

[0048] Specifically, the device parameters are devices that are being charged by the charging pile to be regulated, including but not limited to electric vehicles, electric motorcycles, and electric vehicles, etc. Different charging devices have different standard power ranges. For example, the standard power range corresponding to electric vehicle a is 120 kW to 350 kW; the standard power range corresponding to electric vehicle b is 50 kW to 100 kW, etc. By obtaining the parameters of each device, the standard power range corresponding to each charging device can be determined. The charging record contains the charging start time and charging end time of the charging pile to be regulated.

[0049] Step S2: When the target power limit value exceeds the standard power range, the time required to complete charging is determined according to the charging record.

[0050] Specifically, the target power limit value of the charging pile to be regulated may change. At the beginning of charging of the charging equipment, the target power limit value of the charging pile to be regulated may be within the standard power range. At this time, using the charging pile to be regulated can make the actual charging power of the charging equipment within the standard power range. If after a certain adjustment it is determined that the target power limit value of the charging pile to be regulated is outside the standard power range of the charging equipment, at this time, the charging equipment may not be able to make the actual charging power within the standard power range. If charging is carried out in this situation for a long time, the battery performance of the charging equipment is likely to be damaged.

[0051] When it is detected that the target power limit value of the charging pile to be regulated exceeds the standard power range, the time required to complete charging can be determined based on the charging record of the charging device when the charging device needs to be charged at the current actual charging power.

[0052] Step S3: Obtain the operating parameters of the charging pile to be regulated, and simulate the operating conditions of the charging pile to be regulated within a first preset time period based on the operating parameters and equipment parameters to obtain simulated operating data. The first preset time period is a predicted duration after the current moment, wherein the predicted duration is consistent with the duration required to complete charging.

[0053] Specifically, the operating parameters of the charging pile to be regulated may include charging power, input voltage, output voltage, and the type of charging pile, wherein the charging power is the actual power value corresponding to the current moment, and a simulation charging pile model of the charging pile to be regulated may be constructed based on the operating parameters of the charging pile to be regulated, and the operation of the charging pile to be regulated in a preset time period may be simulated based on the simulation charging pile model, wherein the specific content of the operating parameters of the charging pile to be regulated is not specifically limited in the embodiment of the present application. The duration of the preset time period is consistent with the duration required for charging to be completed. For example, it is detected that it will take 30 minutes from the current moment until charging is completed, and the current moment is 10 o'clock, then the preset time period is between 10 o'clock and 10:30. When the target power limit value exceeds the standard power range, simulation prediction is used to facilitate the assessment of the risk that may be caused by not switching the target power limit value of the charging pile to be regulated in time, and the simulation operation data is the risk assessment result.

[0054] Step S4: Identify the simulated power value contained in the simulated operation data. When the simulated power value is within the preset limit range and the time required to complete charging is lower than the preset limit time, the charging pile to be regulated is regulated based on the target limit power value in the second preset time period.

[0055] Specifically, feature recognition can be used to identify the simulated power value contained in the simulated operation data, that is, the simulated power usage value of the charging pile to be regulated during the simulated operation. When the simulated power usage value is within the preset limit range, it indicates that the risk level caused by not timely regulating the charging pile to be regulated according to the target power limit value is low. The preset limit range can be determined by relevant staff based on historical experimental data and uploaded to the control system. The specific content is not limited in the embodiment of the present application.

[0056] Since the target power limit value is determined based on multi-dimensional considerations, the power limit value that is most suitable for the current operating conditions of the charging pile to be regulated, that is, after the charging pile to be regulated is regulated according to the target power limit value, the charging pile to be regulated and the power grid system are more stable and safe. If the charging pile to be regulated is not adjusted in time according to the target power limit value, the probability of abnormalities in subsequent use will increase. Through predictive simulation, the risk of not timely adjusting the charging pile to be regulated according to the target power limit value can be evaluated. In addition, it is also necessary to analyze the time required for charging to complete. Only when the simulated power value is within the preset limit range and the time required for charging to complete is lower than the preset limit time, the charging pile to be regulated can be regulated based on the target power limit value after charging is completed. The second preset time period is a period of time after charging is completed. The specific duration is not specifically limited in the embodiment of this application and can be set by relevant technical personnel.

[0057] When the simulated power value exceeds the preset limit range, or the time required to complete charging is not less than the preset limit time, the method provided in the embodiment of the present application further includes: Based on the control network port number, at least one associated charging pile of the charging pile to be regulated is determined, and each associated charging pile has the same control network port number as the charging pile to be regulated; the associated use record of each associated charging pile is obtained, and the power margin corresponding to each associated charging pile is determined based on each associated use record, and the associated charging pile with the highest power margin is determined as the target associated charging pile; the power difference is determined according to the actual use power value of the charging pile to be regulated and the corresponding target limited power value, and the associated limited power value of the target associated charging pile is determined based on the power difference.

[0058] Specifically, when the simulated power value exceeds the preset limit range, or the time required to complete charging is not less than the preset limit time, it indicates that if the charging pile to be regulated is not adjusted according to the target power limit value in time, the probability of abnormality occurring in the subsequent use of the charging pile to be regulated is relatively high. If the charging pile to be regulated is adjusted according to the target power limit value at this time, the safety of the charging equipment may be affected. At this time, at least one associated charging pile corresponding to the charging pile to be regulated can be identified and determined through the control network port number, and the associated power limit value of at least one associated charging pile of the charging pile to be regulated can be further adjusted to alleviate the load pressure on the power grid, thereby facilitating the maintenance of the safety of the charging pile to be regulated and the charging equipment within the first preset time period.

[0059] There is an association relationship between the charging piles to be regulated that belong to the same control network port. Therefore, it is convenient to accurately identify at least one associated charging pile corresponding to the charging pile to be regulated based on the control network port number. After determining at least one associated charging pile of the charging pile to be regulated, it is not to directly adjust the at least one associated charging pile at will, but first determine the power margin of each associated charging pile according to the associated use record of each associated charging pile. The power margin is the difference between the limited power value and the actual power value used, and the sum of the power margin and the actual power value used is the limited power value. Based on the power margin of each associated charging pile, the target associated charging pile is determined from all associated charging piles, wherein the number of target associated charging piles is not specifically limited in the embodiment of the present application. The power difference is determined according to the actual power value used by the charging pile to be regulated and the corresponding target limited power value, and finally the associated limited power value of the target associated charging pile is adjusted based on the power difference, so as to improve the accuracy and speed of the power value adjustment process.

[0060] By lowering the power limit of the associated charging piles of the charging pile to be regulated, the load pressure on the power grid can be alleviated, thereby ensuring the safety and stability of the charging pile to be regulated, the power grid and the charging equipment during the charging of the charging equipment. In addition, the target associated charging piles are regulated based on the power difference, which facilitates improving the regulation rate and regulation accuracy.

[0061] In an embodiment of the present application, a control system is provided, such as Figure 4 As shown, Figure 4 The control system 400 shown includes: a processor 401 and a memory 403. The processor 401 and the memory 403 are connected, such as through a bus 402. Optionally, the control system 400 may also include a transceiver 404. It should be noted that in actual applications, the transceiver 404 is not limited to one, and the structure of the control system 400 does not constitute a limitation on the embodiments of the present application.

[0062] Processor 401 may be a CPU (Central Processing Unit), a general-purpose processor, a DSP (Digital Signal Processor), an ASIC (Application Specific Integrated Circuit), an FPGA (Field Programmable Gate Array) or other programmable logic devices, transistor logic devices, hardware components or any combination thereof. It may implement or execute various exemplary logic blocks, modules and circuits described in conjunction with the disclosure of this application. Processor 401 may also be a combination that implements computing functions, such as a combination of one or more microprocessors, a combination of a DSP and a microprocessor, etc.

[0063] The bus 402 may include a path to transmit information between the above components. The bus 402 may be a PCI (Peripheral Component Interconnect) bus or an EISA (Extended Industry Standard Architecture) bus. The bus 402 may be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Figure 4 The fact that only one line is used in the diagram does not mean that there is only one bus or only one type of bus.

[0064] The memory 403 may be a ROM (Read Only Memory) or other types of static storage devices that can store static information and instructions, a RAM (Random Access Memory) or other types of dynamic storage devices that can store information and instructions, or an EEPROM (Electrically Erasable Programmable Read Only Memory), a CD-ROM (Compact Disc Read Only Memory) or other optical disk storage, optical disk storage (including compressed optical disk, laser disk, optical disk, digital versatile disk, Blu-ray disk, etc.), a magnetic disk storage medium or other magnetic storage device, or any other medium that can be used to carry or store the desired program code in the form of instructions or data structures and can be accessed by a computer, but is not limited thereto.

[0065] The memory 403 is used to store the application code for executing the solution of the present application, and the execution is controlled by the processor 401. The processor 401 is used to execute the application code stored in the memory 403 to implement the contents shown in the above method embodiment.

[0066] The control system includes, but is not limited to, mobile terminals such as mobile phones, laptop computers, digital broadcast receivers, PDAs (personal digital assistants), PADs (tablet computers), PMPs (portable multimedia players), vehicle-mounted terminals (such as vehicle-mounted navigation terminals), and fixed terminals such as digital TVs, desktop computers, etc. It can also be a server, etc. Figure 4 The control system shown is merely an example and should not bring any limitation to the functions and scope of use of the embodiments of the present application.

[0067] An embodiment of the present application provides a computer-readable storage medium, on which a computer program is stored. When the computer-readable storage medium is run on a computer, the computer can execute the corresponding content in the aforementioned method embodiment.

[0068] An embodiment of the present application provides a computer program product, which includes a computer program. When the computer program is executed by a processor, the method in any of the above embodiments is implemented.

[0069] It should be understood that, although the steps in the flowchart of the accompanying drawings are displayed in sequence as indicated by the arrows, these steps are not necessarily executed in sequence in the order indicated by the arrows. Unless otherwise specified herein, there is no strict order restriction on the execution of these steps, and they can be executed in other orders. Moreover, at least a part of the steps in the flowchart of the accompanying drawings may include multiple sub-steps or multiple stages, and these sub-steps or stages are not necessarily executed at the same time, but can be executed at different times, and their execution order is not necessarily sequential, but can be executed in turn or alternately with other steps or at least a part of the sub-steps or stages of other steps.

[0070] The above description is only a partial implementation method of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present application. These improvements and modifications should also be regarded as the scope of protection of the present application.

Claims

1. A charging pile control method with load control, characterized in that: include: Acquire a screen power limit value of the charging pile to be regulated based on the current moment, wherein the screen power limit value is determined according to historical power consumption data, wherein the historical power consumption data includes historical power values ​​of each charging pile in a historical time period; Identify the control serial port number corresponding to the charging pile to be regulated, obtain the control serial port communication data corresponding to the charging pile to be regulated based on the control serial port number, and determine the EMS power limit value of the charging pile to be regulated based on the control serial port communication data; Identify the control network port number corresponding to the charging pile to be regulated, obtain the control network port operation data corresponding to the charging pile to be regulated based on the control network port number, and determine the operation power limit value of the charging pile to be regulated based on the control network port operation data; The screen power limit value, the EMS power limit value and the operation power limit value are compared to determine a target power limit value, and the charging pile to be regulated is regulated based on the target power limit value.

2. A charging pile control method with load control according to claim 1, characterized in that: The comparing the screen power limit value, the EMS power limit value, and the operation power limit value to determine a target power limit value includes: Acquire the actual working power, and determine the timing duration corresponding to the charging pile to be regulated based on the timing mapping relationship and the actual working power, wherein the timing mapping relationship is the corresponding relationship between the actual working power and the timing duration corresponding to the charging pile to be regulated; Obtain the current time, and determine whether the timing is over based on the current time and the timing duration, and if so, determine whether the screen power limit value is less than the operating power limit value; If the screen power limit value is less than the operation power limit value, determine whether the screen power limit value is less than the EMS power limit value, if so, determine the screen power limit value as the target power limit value, if not, determine the EMS power limit value as the target power limit value; If the screen power limit value is not less than the operation power limit value, determine whether the operation power limit value is less than the EMS power limit value. If so, determine the operation power limit value as the target power limit value. If not, determine the EMS power limit value as the target power limit value.

3. A charging pile control method with load control according to claim 1, characterized in that: The determining the EMS power limit value of the charging pile to be regulated based on the regulated serial port communication data includes: Writing the regulated serial port communication data into a first preset circular buffer, and identifying communication features contained in the regulated serial port communication data; Determine a first resolution protocol corresponding to the communication feature based on the communication feature and the first preset protocol mapping relationship, wherein the first preset protocol mapping relationship is a correspondence relationship between the communication feature and the first resolution protocol; The control serial port communication data is parsed based on the first parsing protocol to obtain the EMS power limit value of the charging pile to be regulated.

4. A charging pile control method with load control according to claim 1, characterized in that: The determining the operating power limit value of the charging pile to be regulated based on the regulated network port operation data includes: Writing the control network port operation data into a second preset circular buffer, and identifying the operation characteristics contained in the control network port operation data; Determine, based on the mapping relationship between the operation feature and the second preset protocol, a second resolution protocol corresponding to the communication feature, wherein the preset protocol mapping relationship is a corresponding relationship between the communication feature and the second resolution protocol; The operation power limit value of the charging pile to be regulated is obtained by parsing the operation data of the regulation network port based on the second analysis protocol.

5. A charging pile control method with load control according to claim 1, characterized in that: When the target power limit value is the EMS power limit value or the operation power limit value, the method further includes: Obtaining device parameters and charging records, wherein the device parameters are standard power ranges corresponding to devices that are charged using the charging pile to be regulated; When the target power limit value exceeds the standard power range, determining the time required to complete charging according to the charging record; Acquire the operating parameters of the charging pile to be regulated, and simulate the operating conditions of the charging pile to be regulated within a first preset time period based on the operating parameters and the device parameters to obtain simulated operating data, wherein the first preset time period is a predicted duration after the current moment, wherein the predicted duration is consistent with the duration required for charging to be completed; Identify the simulated power value contained in the simulated operation data, and when the simulated power value is within a preset limit range and the time required to complete charging is lower than the preset limit time, regulate the charging pile to be regulated based on the target limit power value in a second preset time period.

6. A charging pile control method with load control according to claim 5, characterized in that: When the simulated power value exceeds the preset limit range, or the time required for charging to be completed is not less than the preset limit time, the method further includes: Determine at least one associated charging pile of the charging pile to be regulated based on the control network port number, each associated charging pile having the same control network port number as that corresponding to the charging pile to be regulated; Obtaining the associated use record of each associated charging pile, and determining the power margin corresponding to each associated charging pile based on each associated use record, and determining the associated charging pile with the highest power margin as the target associated charging pile; A power difference is determined according to the actual power value of the charging pile to be regulated and the corresponding target power limit value, and an associated power limit value of the target associated charging pile is determined based on the power difference.

7. A control system, characterized in that: The control system includes: at least one processor; Memory; At least one application, wherein the at least one application is stored in a memory and configured to be executed by at least one processor, and the at least one application is configured to: execute a charging pile control method with load control according to any one of claims 1-6.

8. A computer-readable storage medium, characterized in that: include: A computer program is stored which can be loaded by a processor and executes a charging pile control method with load control as described in any one of claims 1 to 6.

9. A computer program product, characterized in that It includes a computer program, which, when executed by a processor, implements the steps of a charging pile control method with load control according to any one of claims 1 to 6.

Citation Information

Patent Citations

  • Charging pile control method, controller and charging pile system

    CN115782641A

  • Charging pile charging and discharging power determination method and device, and charging pile

    CN117301929A

  • Market charging pile charging system

    CN118038604A

  • Energy storage power station SOC calibration method and system, electronic equipment and readable medium

    CN118465581A

  • Charging-pile-based coordinated charging method under power demand response condition

    WO2022193395A1