Tunnel structure construction method for underpinning pile foundation based on mining method
Through the mine method of underpinning pile foundation construction, combined with stress analysis and conversion structure design, the problem of changes in the bearing capacity of the pile raft foundation and the buoyancy of the soil layer during tunnel construction was solved, and the stable stress conversion of the pile foundation and construction safety were achieved. It is suitable for tunnel construction under super high-rise buildings.
Patent Information
- Application Number
- CN202410934917.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-12
- Publication Date
- 2024-10-15
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During tunnel construction, changes in the bearing capacity of the pile raft foundation and the buoyancy of the soil layer cause the groundwater level to rise, causing the complexity and instability of pile foundation underpinning. Especially in super high-rise buildings, it is difficult to effectively consider the distance between piles with existing technology. The combined effects of soil and buoyancy.
The mining method is used to underpin the pile foundation construction method. Through force analysis, conversion structure design, monitoring and support measures, the force conversion and overall stability check of the pile foundation are gradually completed to ensure construction safety and structural stability.
It achieves stable stress conversion of pile foundations, ensures the overall stability of the tunnel structure and construction safety, avoids the defects of insufficient direct support or large earthwork construction in traditional methods, and is suitable for tunnel construction under super-high-rise buildings.
Smart Images

Figure CN118774869A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of tunnel structure construction, and in particular to a tunnel structure construction method based on a mining method to underpin a pile foundation. Background Art
[0002] With the increase of urban traffic pressure, subways, as a fast transportation method in cities, are generally built underground in existing buildings, especially in urban areas. The bottom of many high-rise or super-high-rise buildings is often equipped with relatively long pile foundations or pile raft foundations. In the construction of pile raft foundations, the bearing capacity and buoyancy of the pile raft foundation will be changed due to the passage of the tunnel. In addition, the construction of the tunnel will change the path of groundwater, causing the groundwater level to rise. At present, China and foreign countries have accumulated rich experience in dealing with the pile foundation of subway tunnels passing through buildings, mainly using ground pile foundation underpinning and in-hole pile foundation underpinning. Among them, the passive underpinning method of the pile foundation in the tunnel of the mining method has the advantages of simple construction, no need to dismantle the upper structure, and no restrictions on the ground environment. How to consider the comprehensive influence of the soil between the piles and the buoyancy of the underpinning pile foundation has become the main difficulty in the current construction. Summary of the invention
[0003] In order to solve the above technical problems, the present invention provides a tunnel structure construction method based on the mining method to underpin the pile foundation, which is implemented by the following technical solutions:
[0004] A tunnel structure construction method based on the mining method to underpin pile foundation, wherein the tunnel structure is located in the middle of the pile body to be underpinned of the super-high-rise pile raft foundation, and the force conversion is completed by underpinning the pile foundation when the construction reaches the raft foundation pile, characterized in that the steps include:
[0005] Step 1: Force analysis. First, the internal force analysis of the tunnel structure, pile raft foundation and soil between piles is carried out through the working condition model of the mining method. The anti-buoyancy of the pile raft foundation and the force of the single pile are verified. During the tunnel excavation process, a small advance grouting pipe is set up to inject cement grout into the tunnel section to ensure the stability of the excavation.
[0006] Step 2: Initial excavation and support. The tunnel is excavated using the mining method. During construction, grouting steel pipes are buried radially in the arch. A steel mesh is set at the excavated section and reinforced with sprayed concrete to complete the primary lining construction. When the tunnel is excavated to the pile body that needs to be replaced according to the mining method, a conversion structure is constructed at the section of the pile body, and the cross-section of the conversion structure matches the cross-section of the tunnel.
[0007] Step 3: Secondary lining construction. The secondary lining construction is carried out after the conversion structure construction is completed. The conversion structure includes a transfer column and a top beam. The shape of the transfer column and the top beam close to the tunnel matches the tunnel cross-section. The depth of the transfer column exceeds the buried depth of the tunnel bottom. During the construction of the top beam, its main steel bars are embedded in the pile body to be replaced and cast as a whole to form a T-shaped support. The replacement lining is then used to construct the secondary lining. The replacement lining adopts an assembled lining and is supported by a construction trolley or a full-floor scaffolding. After installation, the gap between the secondary lining and the inner wall of the tunnel is filled with concrete slurry.
[0008] Step 4: Pile cutting and monitoring. After the secondary lining construction is completed, the upper part of the pile body that needs to be replaced in the tunnel is connected to the top beam. When cutting the pile, a monitoring sleeve is set in the middle of the pile body that needs to be replaced. After the cutting machine cuts off the piles at the upper and lower sections of the monitoring sleeve, the monitoring sleeve is used to wrap and fix the broken pile to prevent the broken pile from being fractured. A strain gauge is set at the broken pile. The strain gauge is used to detect the stress condition of the upper structure and transmit it to the visual mobile terminal for monitoring through the detection device to complete the secondary lining construction of the entire tunnel;
[0009] Step 5: Pile-soil verification and anti-floating analysis. Due to the deep burial depth of the tunnel, the tunnel structure and pile raft foundation are connected as one through the conversion structure. The groundwater on the tunnel plane will generate buoyancy on the tunnel and react to the pile raft foundation of the super-high-rise. At this time, modeling analysis is performed through verification software; the reaction force F0 of the buoyancy of the tunnel on the pile raft foundation of the super-high-rise is calculated according to the overall stress of the structure and the change of the groundwater level, and it is used as the pile body safety value;
[0010] Step 6: Remove the broken piles and cut and trim them. The strain gauge detects the force of the upper structure as F, and the value of the test is included in the test every 5 hours. The stress curve of the broken pile is obtained by fitting calculation. When the force F is a negative value, it is considered to be in a compressive state. Since the load of the upper structure in the early stage of support has not been completely transferred to the conversion structure, it is considered to wait for the settlement of the overall structure; when the force F is a positive value, it is considered to be in a tensile state. The conversion structure and the pile body to be replaced complete the force conversion. If the force F shows a logarithmic growth, it is considered that the structure is unstable, which requires the reinforcement of temporary support to ensure the stability of the cut pile; when the strain gauge curve presents a stable curve without obvious fluctuations, the broken pile can be removed, and the broken pile can be taken out after the detection sleeve is removed. At this time, the broken pile and the monitoring sleeve as a whole no longer bear the upper force, and the force at the broken pile is all transmitted to the soil layer through the top beam and the transfer column;
[0011] Step 7: Demolish the temporary support and complete the tunnel construction. Gradually demolish the temporary support. The demolition sequence is to first demolish the support at non-broken pile locations. After the upper part of the broken pile is repaired and re-sprayed with concrete, ensure that the broken pile location is flush with the top lining. Connect the top lining of the tunnel through steel bar implantation and pouring. Construct waterproof mortar on the surface of the secondary lining. When the tunnel lining forms a closed loop and reaches a certain strength, inject expansive cement slurry behind it, and then demolish the support structure at the broken pile location to complete the overall construction of the tunnel structure with the replaced pile foundation.
[0012] The conversion structure includes a transfer column and a top beam. The transfer column includes an upper column body and a lower column body. The upper column body matches the cross-section of the tunnel, and the depth of the lower column body is deeper than the original depth of the pile to be replaced.
[0013] The lower column body is a steel pipe pile. When constructing the lower column body in the form of an excavation pile in the tunnel, first drill a hole at the bottom of the tunnel with a drill rig, and gradually place steel pipes of the designed depth section by section using the steel pipe splicing method. After welding, fill it with concrete to form the steel pipe pile, which serves as the construction support for the upper column body.
[0014] In the pile-soil check calculation and anti-floating analysis, the stability check calculation of the pile body of the steel pipe pile includes performing a stability check calculation when the pile body is under the action of lateral pressure to prevent the pile body from losing stability. The lateral pressure formula is: P = FstA, where P is the total pressure on the pile body, A is the cross-sectional area of the pile body, and Fst is the stability bearing capacity of the pile body; the pile body safety value correction formula is P0 = uF0, F0 is the reaction force of the buoyancy of the tunnel on the pile raft foundation of the super high-rise building, and u is an empirical coefficient with a value range of 1 - 1.5. If P > P0, consider increasing anti-floating measures by setting anti-floating anchor rods at the tunnel bottom slab; when P < P0, it meets the condition for removing the broken pile.
[0015] After adopting the above technical solutions, the beneficial effects of the present invention are as follows:
[0016] 1. In the traditional pile cutting construction of beam replacement with pile, generally, the secondary lining is directly used as the support, or large-scale earthwork construction is required, and the transfer column is set as a stress system unrelated to the tunnel. In this application, through the comprehensive correlation setting of the tunnel, pile cutting, and conversion structure, and considering the integrated stress of the pile raft foundation of the super high-rise building, the tunnel, and the conversion structure, the stability of the overall structure is ensured.
[0017] 2. This application adopts the method of continuing to be used as a support after cutting, ensuring the support safety of the tunnel. When removing the cut pile, first construct the conversion structure well, analyze and determine the conditions for removing the cut pile by monitoring and comparing the stress conditions of the strain gauges, and ensure the construction safety and support requirements during the dynamic construction process.
[0018] 3. The transfer column of the present application includes an upper column and a lower column, wherein the upper column can be set to match the cross-sectional shape of the tunnel, and the top beam can also be set to a tunnel arch beam structure, which is beneficial to the force on the tunnel and pile soil, and the lower column can be set to a friction pile body, which is beneficial to exerting maximum force during the settlement process after tunnel construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the technical solutions in the implementation modes of the present application, the drawings required for use in the description of the implementation modes will be briefly introduced below. Obviously, the drawings described below are only some implementation modes of the present application. For those skilled in the art, other drawings can be obtained based on these drawings without creative work.
[0020] Figure 1 A flow chart of the construction method for this application;
[0021] Figure 2 This is a schematic diagram of the tunnel and piled raft foundation for this application;
[0022] Figure 3 A schematic diagram of the tunnel and the piles to be replaced for this application;
[0023] Figure 4 Schematic diagram of the pile cutting and monitoring sleeve for this application;
[0024] Figure 5 This is a schematic diagram of pile cutting for this application.
[0025] Figure 6 Schematic diagram of the pile cut completed for this application. DETAILED DESCRIPTION
[0026] The following description of the embodiments will help the public better understand the present invention, but the specific embodiments given by the applicant cannot and should not be regarded as limitations on the technical solutions of the present invention. Any changes to the definitions of components or technical features, or formal rather than substantive changes to the overall structure should be regarded as the scope of protection defined by the technical solutions of the present invention.
[0027] In this application, unless otherwise clearly specified or limited, the terms "installation", "connection", "fixation" and the like should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be internal communication between two elements, or it can be only surface contact, or surface contact connection through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0028] The present invention is implemented by the following technical solutions:
[0029] like Figure 1-Figure 5 As shown, a tunnel structure construction method based on the mining method to underpin pile foundation, wherein the tunnel structure 1 is located in the middle of the pile body 2 to be underpinned of the super-high-rise pile raft foundation, and the force conversion is completed by underpinning the pile foundation when the raft foundation pile is constructed, characterized in that the steps include:
[0030] Step 1: Force analysis: First, the internal force analysis of the tunnel structure 1, pile raft foundation 3 and inter-pile soil 4 is carried out through the working condition model of the mining method, and the anti-buoyancy of the pile raft foundation and the force of the single pile are verified. During the tunnel excavation process, a small advance grouting pipe is set up to inject cement grout into the tunnel section to ensure the stability of the excavation;
[0031] Step 2: Initial excavation and support. The tunnel is excavated using the mining method. During construction, grouting steel pipes are buried radially in the arch. A steel mesh is set at the excavated section and reinforced with sprayed concrete to complete the primary lining construction. When the tunnel is excavated to the pile body that needs to be replaced according to the mining method, a conversion structure is constructed at the section of the pile body, and the cross-section of the conversion structure matches the cross-section of the tunnel.
[0032] Step 3: Secondary lining construction. The secondary lining construction is carried out after the conversion structure construction is completed. The conversion structure 5 includes a transfer column 51 and a top beam 52. The shape of the transfer column and the top beam close to the tunnel matches the tunnel cross-section. The depth of the transfer column exceeds the buried depth of the tunnel bottom. During the construction of the top beam, its main steel bars are embedded in the pile body to be replaced and cast as a whole to form a T-shaped support. The secondary lining 6 is then constructed by using a replacement lining. The replacement lining adopts an assembled lining and is supported by a construction trolley or a full-floor scaffolding. After installation, the gap between the secondary lining and the inner wall of the tunnel is filled with concrete slurry.
[0033] Step 4: Pile cutting and monitoring. After the secondary lining construction is completed, the upper part of the pile body 2 to be replaced in the tunnel is connected to the top beam 52. When cutting the pile, a monitoring sleeve 21 is set in the middle of the pile body 2 to be replaced. After the cutting machine cuts off the piles of the upper and lower sections of the monitoring sleeve, the monitoring sleeve is used to wrap and fix the broken pile 22 to prevent the broken pile from being fractured. A strain gauge 23 is set at the broken pile. The strain gauge is used to detect the stress condition of the upper structure and transmit it to the visual mobile terminal for monitoring through the detection device to complete the secondary lining construction of the entire tunnel;
[0034] Step 5: Pile-soil verification and anti-floating analysis. Due to the deep burial depth of the tunnel, the tunnel structure and pile raft foundation are connected as one through the conversion structure. The groundwater on the tunnel plane will generate buoyancy on the tunnel and react to the pile raft foundation of the super-high-rise. At this time, modeling analysis is performed through verification software; the reaction force F0 of the buoyancy of the tunnel on the pile raft foundation of the super-high-rise is calculated according to the overall stress of the structure and the change of the groundwater level, and it is used as the pile body safety value;
[0035] Step 6: Remove the broken piles and cut and trim them. The strain gauge detects the force of the upper structure as F, and the value of the test is included in the test every 5 hours. The stress curve of the broken pile is obtained by fitting calculation. When the force F is a negative value, it is considered to be in a compressive state. Since the load of the upper structure in the early stage of support has not been completely transferred to the conversion structure, it is considered to wait for the settlement of the overall structure; when the force F is a positive value, it is considered to be in a tensile state. The conversion structure and the pile body to be replaced complete the force conversion. If the force F shows a logarithmic growth, it is considered that the structure is unstable, which requires the reinforcement of temporary support to ensure the stability of the cut pile; when the strain gauge curve presents a stable curve without obvious fluctuations, the broken pile can be removed, and the broken pile can be taken out after the detection sleeve is removed. At this time, the broken pile and the monitoring sleeve as a whole no longer bear the upper force, and the force at the broken pile is all transmitted to the soil layer through the top beam and the transfer column;
[0036] Step 7: Remove temporary supports and complete tunnel construction. Remove temporary supports gradually. Remove the supports at non-broken piles first. After the upper part of the broken piles is repaired and re-sprayed with concrete, ensure that the broken piles are flush with the top lining, and connect the top lining of the tunnel by planting reinforcement and pouring. Construct waterproof mortar on the surface of the secondary lining. When the tunnel lining is closed into a ring and reaches a certain strength, inject expansive cement slurry into the back, and then remove the support structure at the broken piles to complete the overall construction of the tunnel structure that supports the pile foundation.
[0037] The conversion structure 5 includes a transfer column 51 and a top beam 52. The transfer column includes an upper column 511 and a lower column 512. The upper column matches the cross section of the tunnel, and the depth of the lower column is deeper than the original depth of the pile to be replaced.
[0038] Preferably, the top beam is configured as a saddle-shaped structure, whose upper surface is a plane that is higher in the middle and lower at both ends, and whose lower surface is arc-shaped and has the same curvature as the top surface of the tunnel. During the construction of the top beam, a groove is first opened in the cross section at the intersection of the pile body to be replaced and the tunnel. After the casting groove is formed, a non-detachable steel plate is set in the groove as a support and top mold, and the side support template is not required. The tunnel rock mass and the side lining are directly used as the side template. During casting, first, holes are drilled on the side of the pile body to be replaced to set connecting steel bars, and stress-bearing steel bars and stirrups are set in the grooves on both sides of the pile body to be replaced. After completion, the lower template is installed, and the lower template is provided with casting holes.
[0039] Preferably, the monitoring sleeve is in the form of two semi-circular split sleeves. Fixed side plates are arranged at the end sides, and the side plates are fixed by high-strength bolts to fix the two split sleeves on the pile to be replaced. Connecting bosses are arranged at the upper and lower positions of the sleeve. When connecting, the upper and lower connecting bosses of the sleeve are in contact connection with the upper and lower positions of the broken pile. That is to say, the setting of the upper and lower connecting bosses ensures that the stress points of the sleeve are not on the broken pile, but on the upper and lower parts of the broken pile. In this way, the strain gauges arranged on the sleeve can sense the stress changes in the upper structure of the broken pile. In another embodiment, the strain gauges can also be directly arranged at the incision between the broken pile and the upper pile body, and the monitoring sleeve then plays the role of fixing the broken pile and the original pile body.
[0040] The lower column body is a steel skeleton pile. When constructing the lower column body, the form of excavating piles in the tunnel is adopted. First, drill holes at the bottom of the tunnel with a drill rig, and gradually place steel pipes of the designed depth section by section in the way of connecting steel pipes. After welding, fill the steel pipes with concrete to form the steel skeleton pile, which serves as the construction support for the upper column body.
[0041] In actual construction, there are multiple piles to be replaced in the tunnel. When carrying out pile foundation replacement, it should be carried out according to the principle of dealing with one pile at a time. Each time, force calculation is required, and the piles invading the tunnel are chiseled and cut step by step and one by one, and the bearing capacity of the initial support and conversion device of the tunnel is utilized to achieve the effective transfer of the self-load and dynamic load of the upper structure.
[0042] In the pile-soil check calculation and anti-floating analysis, the check calculation of the pile body stability of the steel skeleton pile includes carrying out the stability check calculation when the pile body is subjected to lateral pressure to prevent the pile body from losing stability. The lateral pressure formula is: P = FstA, where P is the total pressure on the pile body, A is the cross-sectional area of the pile body, and Fst is the stability bearing capacity of the pile body; the pile body safety value correction formula is P0 = uF0, F0 is the reaction force of the buoyancy of the tunnel on the pile raft foundation of the super high-rise building, and u is an empirical coefficient with a value range of 1 - 1.5. If P > P0, anti-floating measures are considered to be added, such as setting anti-floating anchor rods at the tunnel floor; when P < P0, the condition for removing the broken pile is satisfied.
[0043] Considering that during construction, in the construction of the steel skeleton pile of the conversion device, the construction space of the tunnel is reduced, and steel pipes need to be set in sections. The positions of the drill holes at the bottom of the tunnel are set outside the tunnel soil layer offset, so as to ensure the cross-sectional size requirements of the overall tunnel. When installing the steel pipes, workers can enter the steel pipes for welding one by one to ensure the integrity requirements of the steel pipes.
[0044] The above describes the preferred embodiments of the present invention. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in a common manner in the art; any technician familiar with the art can use the above-disclosed methods and technical contents to make many possible changes and modifications to the technical solutions of the present invention without departing from the scope of the technical solutions of the present invention, or modify them into equivalent embodiments of equivalent changes, which does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solutions of the present invention are still within the scope of protection of the technical solutions of the present invention.
Claims
1. A tunnel structure construction method based on the mining method to underpin pile foundation, wherein the tunnel structure is located in the middle of the pile body to be underpinned of the super-high-rise pile raft foundation, and the force conversion is completed by underpinning the pile foundation when the raft foundation pile is constructed, characterized in that: the steps include: Step 1: Force analysis. First, the internal force analysis of the tunnel structure, pile raft foundation and soil between piles is carried out through the working condition model of the mining method. The anti-buoyancy of the pile raft foundation and the force of the single pile are verified. During the tunnel excavation process, a small advance grouting pipe is set up to inject cement grout into the tunnel section to ensure the stability of the excavation. Step 2: Initial excavation and support. The tunnel is excavated using the mining method. During construction, grouting steel pipes are buried radially in the arch. A steel mesh is set at the excavated section and reinforced with sprayed concrete to complete the primary lining construction. When the tunnel is excavated to the pile body that needs to be replaced according to the mining method, a conversion structure is constructed at the section of the pile body, and the cross-section of the conversion structure matches the cross-section of the tunnel. Step 3: Secondary lining construction. The secondary lining construction is carried out after the conversion structure construction is completed. The conversion structure includes a transfer column and a top beam. The shape of the transfer column and the top beam close to the tunnel matches the tunnel cross-section. The depth of the transfer column exceeds the buried depth of the tunnel bottom. During the construction of the top beam, its main steel bars are embedded in the pile body to be replaced and cast as a whole to form a T-shaped support. The replacement lining is then used to construct the secondary lining. The replacement lining adopts an assembled lining and is supported by a construction trolley or a full-floor scaffolding. After installation, the gap between the secondary lining and the inner wall of the tunnel is filled with concrete slurry. Step 4: Pile cutting and monitoring. After the secondary lining construction is completed, the upper part of the pile body that needs to be replaced in the tunnel is connected to the top beam. When cutting the pile, a monitoring sleeve is set in the middle of the pile body that needs to be replaced. After the cutting machine cuts off the piles at the upper and lower sections of the monitoring sleeve, the monitoring sleeve is used to wrap and fix the broken pile to prevent the broken pile from being fractured. A strain gauge is set at the broken pile. The strain gauge is used to detect the stress condition of the upper structure and transmit it to the visual mobile terminal for monitoring through the detection device to complete the secondary lining construction of the entire tunnel; Step 5: Pile-soil verification and anti-floating analysis. Due to the deep burial depth of the tunnel, the tunnel structure and pile raft foundation are connected as one through the conversion structure. The groundwater on the tunnel plane will generate buoyancy on the tunnel and react to the pile raft foundation of the super-high-rise. At this time, modeling analysis is performed through verification software; the reaction force F0 of the buoyancy of the tunnel on the pile raft foundation of the super-high-rise is calculated according to the overall stress of the structure and the change of the groundwater level, and it is used as the pile body safety value; Step 6: Remove the broken piles and cut and trim them. The strain gauge detects the force of the upper structure as F, and the value of the test is included in the test every 5 hours. The stress curve of the broken pile is obtained by fitting calculation. When the force F is a negative value, it is considered to be in a compressive state. Since the load of the upper structure in the early stage of support has not been completely transferred to the conversion structure, it is considered to wait for the settlement of the overall structure; when the force F is a positive value, it is considered to be in a tensile state. The conversion structure and the pile body to be replaced complete the force conversion. If the force F shows a logarithmic growth, it is considered that the structure is unstable, which requires the reinforcement of temporary support to ensure the stability of the cut pile; when the strain gauge curve presents a stable curve without obvious fluctuations, the broken pile can be removed, and the broken pile can be taken out after the detection sleeve is removed. At this time, the broken pile and the monitoring sleeve as a whole no longer bear the upper force, and the force at the broken pile is all transmitted to the soil layer through the top beam and the transfer column; Step 7: Remove temporary supports and complete tunnel construction. Remove temporary supports gradually. Remove the supports at non-broken piles first. After the upper part of the broken piles is repaired and re-sprayed with concrete, ensure that the broken piles are flush with the top lining, and connect the top lining of the tunnel by planting reinforcement and pouring. Construct waterproof mortar on the surface of the secondary lining. When the tunnel lining is closed into a ring and reaches a certain strength, inject expansive cement slurry into the back, and then remove the support structure at the broken piles to complete the overall construction of the tunnel structure that supports the pile foundation.
2. The tunnel structure construction method based on the mining method to underpin pile foundation according to claim 1 is characterized by: The conversion structure includes a transfer column and a top beam, the transfer column includes an upper column and a lower column, the upper column matches the cross section of the tunnel, and the depth of the lower column is deeper than the original depth of the pile body to be replaced.
3. The tunnel structure construction method based on the mining method to underpin pile foundation according to claim 2 is characterized by: The top beam is configured as a saddle-shaped structure, the upper surface of which is a plane that is high in the middle and low at both ends, and the lower surface is arc-shaped and has the same curvature as the top surface of the tunnel. When constructing the top beam, a groove is first opened in the cross section at the intersection of the pile body to be replaced and the tunnel. After the casting groove is formed, a non-detachable steel plate is set in the groove as a support and top mold, and the side does not need to be set with a supporting template. The tunnel rock mass and the side lining are directly used as the side mold. When pouring, first drill holes in the side of the pile body to be replaced to set connecting steel bars, and stress-bearing steel bars and stirrups are set in the grooves on both sides of the pile body to be replaced. After completion, the lower template is installed. The lower template is provided with casting holes. After the casting is completed, the two sides of the top beam and the upper part of the pile body to be replaced form an inverted Y-shaped stable structure. After the casting is completed, the two sides of the top beam and the upper part of the pile body to be replaced form an inverted Y-shaped stable structure.
4. The tunnel structure construction method based on the mining method to underpin pile foundation according to claim 2 is characterized by: The lower column is a steel pile. When constructing the lower column, a pile is excavated in the tunnel. First, a hole is drilled at the bottom of the tunnel by a drilling rig, and steel pipes of designed depth are placed in sections by using a steel pipe pile connection method. After welding, concrete is filled in to form the steel pile, which serves as the construction support for the upper column.
5. The tunnel structure construction method based on the mining method to underpin pile foundation according to claim 1 is characterized by: In the pile-soil checking calculation and anti-floating analysis, the checking calculation of the pile body stability of the steel pipe pile includes performing the stability checking calculation when the pile body is subjected to lateral pressure to prevent the pile body from losing stability. The lateral pressure formula is: P = F st A, where P is the total pressure on the pile body, A is the cross-sectional area of the pile body, and F st is the stability bearing capacity of the pile body; the correction formula for the pile body safety value is P0 = uF0, where F0 is the reaction force of the buoyancy of the tunnel on the pile raft foundation of the super high-rise building, and u is the empirical coefficient with a value range of 1 - 1.
5. If P > P0, anti-floating measures are considered to be increased by setting anti-floating anchor rods at the bottom plate of the tunnel; when P < P0, the condition for removing the broken pile is satisfied.