Fuel cell cooling system part test system
By designing a fuel cell cooling system component testing system, using sensors and auxiliary condensation boxes to simulate the cooling water flow resistance and heating power of the stack, the complex problem of subsystem component testing in fuel cell system testing is solved, and an independent and simple system is achieved. testing and performance monitoring, reducing testing costs.
Patent Information
- Application Number
- CN202410782790.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-17
- Publication Date
- 2024-10-15
AI Technical Summary
In fuel cell system testing, it is difficult to avoid involving other subsystems when testing subsystem components individually, resulting in complexity and non-independence of the test bench, making it difficult to ensure the simplicity and independence of the test.
A fuel cell cooling system component testing system is designed, including a heating water tank, an electronic water pump, an expansion kettle, an electronic three-way valve, a PTC heater, a radiator, a filter and a deionizer. By setting up a turbine flow meter and a pressure sensor , temperature sensor, conductivity meter and other sensors to simulate the cooling water flow resistance and heating power of the stack, conduct cooling system tests independently, and use auxiliary condensation boxes and condensation copper sheets for steam condensation processing, simplifying the test structure.
It realizes independent testing of fuel cell cooling system components, simplifies the test system structure, ensures the independence and simplicity of testing, and monitors the performance indicators of components through sensors, reducing testing costs.
Smart Images

Figure CN118782836A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of new energy technology, and in particular to a fuel cell cooling system component testing system. Background Art
[0002] In the fuel cell system test, it is inevitable to face the test of system components, but the subsystems of the fuel cell are interrelated and need to be tested through electrochemical reactions based on the stack, but this often involves too many and too complicated parts, and the test bench is also relatively complicated. How to test the components of a separate subsystem without involving other subsystems to ensure the independence and simplicity of the bench test. Summary of the invention
[0003] In view of the above problems, the present invention provides a fuel cell cooling system component testing system, which is as follows:
[0004] It includes a heating water tank, an electronic water pump, an expansion kettle, an electronic three-way valve, a PTC heater, a radiator, a filter and a deionizer, wherein the inlet end of the heating water tank is provided with a turbine flowmeter and an electronic water pump, the outlet end of the heating water tank is provided with an electronic three-way valve, the other two interfaces of the electronic three-way valve are respectively connected to the PTC heater and the radiator, the outlet ends of the PTC heater and the radiator are respectively connected to the outlet end pipeline and the inlet end of the filter, the outlet end of the filter is provided with a pipeline connected to the inlet end of the electronic water pump to complete the circulation in sequence, the radiator is also provided with an exhaust pipeline connected to the expansion kettle, and a hand valve and an auxiliary condensation box are arranged on the pipeline, the water outlet of the auxiliary condensation box is provided with a pipeline connected to the connecting pipeline between the filter and the radiator, and a water pump is arranged at the water outlet;
[0005] The auxiliary condensation box is provided with a plug hole on both sides, and a condensation copper sheet is inserted into the plug hole. The condensation copper sheet is divided into two types: one is a straight strip inserted into the plug hole, and the other is a ring-shaped condensation copper sheet that fits the outer wall of the auxiliary condensation box, and the two ends of the straight strip condensation copper sheet extend from the plug hole to connect the ring-shaped condensation copper sheet;
[0006] A guide protrusion is provided at the bottom of the straight strip-shaped condensing copper sheet, a water receiving tray is provided below the guide protrusion, and a plurality of water leakage holes are opened on the water receiving tray.
[0007] Furthermore, an exhaust branch is provided on the pipeline connecting the heating water tank and the electronic three-way valve to connect the ionizer and the expansion kettle, and a receiving valve is provided at the water inlet end of the ionizer.
[0008] Furthermore, a conductivity meter and a pressure sensor are provided between the electronic water pump and the turbine flowmeter.
[0009] Furthermore, a pressure sensor is provided on each connecting pipe between the heating water tank, the electronic water pump, the electronic three-way valve, the PTC heater, the radiator and the filter.
[0010] Furthermore, two water outlet ports of the electronic three-way valve are respectively provided with turbine flowmeters.
[0011] Furthermore, temperature sensors are provided on the connecting pipes at both ends of the PTC heater, the heating water tank and the radiator.
[0012] Furthermore, the radiator is also provided with an exhaust pipeline connected to the expansion kettle and a hand valve is arranged on the pipeline.
[0013] Furthermore, the expansion kettle is also provided with a pipe connected to the water outlet pipeline of the filter.
[0014] Furthermore, the pressure sensor at the inlet end of the electronic water pump is closer to the inlet of the electronic water pump than the connection point between the PTC heater and the expansion kettle and the inlet pipeline of the electronic water pump and the inlet of the electronic water pump.
[0015] Furthermore, the turbine flowmeter is located between the electronic water pump and the heating water tank.
[0016] Beneficial effects of the present invention:
[0017] 1. The test system replaces the fuel cell stack with a heating water tank, so that the flow resistance curve of its cooling water at various flow rates and pressures is similar to that of the stack, and it has a heating function, and its heating power is close to the heat generation power of the stack under various working conditions.
[0018] 2. The test system tests the cooling system independently, without involving the fuel cell stack, hydrogen and air systems, thus simplifying the test system structure.
[0019] 3. The test system has a reasonable layout and is easy to operate. It can accurately test and verify whether the main performance indicators of the main components meet the requirements of the fuel cell system of the corresponding power.
[0020] 4. The condensation copper sheet in the auxiliary condensation box is used to condense the steam that cannot be processed in time during the heat dissipation process of the radiator. The structure is simple and the cost is not too expensive. Even if more are added, the cost will not increase too much. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is an overall schematic diagram of the fuel cell cooling system component testing system of the present invention;
[0022] Figure 2 It is an overall schematic diagram of the auxiliary condensation box of the present invention;
[0023] Figure 3 It is a schematic diagram of the auxiliary condensation box of the present invention;
[0024] Figure 4 It is a schematic diagram of the internal structure of the auxiliary condensation box of the present invention.
[0025] In the figure: 1. Heating water tank; 2. Ionizer; 3. Expansion kettle; 4. Radiator; 5. Filter; 6. PTC heater; 7. Electronic water pump; 8. Electronic three-way valve; 9. Conductivity meter; 10. Turbine flowmeter; 11. Temperature sensor; 12. Pressure sensor; 13. Hand valve; 14. Auxiliary condensation box; 1401, jack; 15. Condensation copper sheet; 1501, diversion protrusion; 16. Water tray. DETAILED DESCRIPTION
[0026] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples.
[0027] It illustrates the present invention but is not intended to limit the scope of the present invention.
[0028] according to Figure 1 As shown in the content, a fuel cell cooling system component testing system is characterized in that: it includes specific testable main components including an electronic water pump 7, an expansion kettle 3, an electronic three-way valve 8, a PTC heater 6, a radiator 4, a filter 5 and a deionizer 2, the expansion kettle 3 is provided with a water inlet and an outlet, the outlet end is connected to the water inlet of the electronic water pump 7 through a connecting pipeline, and during operation, the electronic water pump 7 is operated to pressurize and transport cooling water to various parts of the system and circulate it, and the inlet and outlet connecting pipelines of the electronic water pump 7 are equipped with pressure sensors 12 to monitor the inlet and outlet cooling water pressures and obtain the pressure difference, thereby determining the head of the electronic water pump 7 at various speeds (operating conditions); the turbine flowmeter 10 in the outlet connecting pipeline of the electronic water pump 7 is used to monitor the corresponding flow rate at various speeds (operating conditions) of the system, thereby determining the flow parameters of the electronic water pump 7.
[0029] The test system is an independent cooling system and does not require the assistance of a hydrogen system or an air system.
[0030] The cooling water used in the test system is a mixture of deionized water and ethylene glycol, which is injected at the water inlet of the expansion kettle 3;
[0031] A conductivity meter 9 and a pressure sensor 12 are provided between the electronic water pump 7 and the turbine flow meter 10;
[0032] Conductivity meter 9, its function is to test the conductivity of the system cooling water to ensure the insulation of the water system;
[0033] The pressure sensor 12 is used to detect the water pressure after the electronic water pump 7 discharges water.
[0034] In this test system, a heating water tank 1 is used to replace the fuel cell stack. The flow resistance curve of the cooling water at various flow rates and pressures is similar to that of the stack, thereby ensuring that it can simulate the flow resistance of the stack. It also has a heating function, and its heating power is close to the heat generation power of the stack under various working conditions, thereby ensuring that it can simulate the heat generation capacity of the stack. A pressure sensor 12, a temperature sensor 11 and a turbine flowmeter 10 are respectively installed on the inlet and outlet connecting pipes of the heating water tank 1 to monitor the pressure, temperature and flow of the inlet and outlet cooling water, obtain the pressure difference, temperature difference and flow, and thus determine the flow resistance and heating power of the heating water tank 1 under different flow rates (working conditions).
[0035] There is an exhaust branch branched on the hot tank outlet pipeline, in which a hand valve 13 and a deionizer 2 are installed, and the gas and cooling water in the exhaust branch eventually enter the expansion kettle 3. The deionizer 2 mentioned above is used to adsorb ions in the cooling water to ensure that the ion concentration therein is within a limited range. It is associated with a conductivity meter on the outlet connection pipeline of the electronic water pump 7 for monitoring the ion concentration in the cooling water. In the early stage of system operation, when the ion concentration of the cooling water is low, the hand valve 13 can be closed, and there is no need to pass through the exhaust branch where the deionizer 2 is located (the exhaust has been completed at this time), which can reduce the branching of the main flow. When the ion concentration of the cooling water rises to the set value, the hand valve 13 can be opened to allow the cooling water to flow through the deionizer 2 for ion adsorption, thereby reducing the ion concentration of the cooling water. At the same time, the adsorption efficiency and service life of the deionizer 2 are judged according to the change of the ion concentration monitored by the conductivity meter: the deionizer 2 with better adsorption capacity can reduce the ion concentration of the cooling water to the required range in a shorter time, whereas the deionizer 2 with poorer adsorption capacity takes longer time or cannot reduce it to the required range; and when the deionizer 2 is unable to reduce the cooling concentration to the required range after the system has been running for a period of time, the deionizer 2 needs to be replaced, and its service life can be compared according to the length of the replacement time.
[0036] The three interface pipelines of the electronic three-way valve 8 are respectively installed with a pressure sensor 12 and a turbine flowmeter 10, and the pressure and flow of the three interfaces in the large and small circulation of the system are monitored together with the turbine flowmeter 10 to obtain the pressure difference and flow difference, so as to determine the flow and flow resistance of the large and small circulation paths of the electronic three-way valve 8 at different openings under different flow rates (operating conditions), thereby determining the relevant performance parameters of the electronic three-way valve 8. At the same time, the opening and internal leakage of the electronic three-way valve 8 can be verified according to the values of the turbine flowmeter 10 of the large and small circulation paths.
[0037] The inlet and outlet connecting pipes of the PTC heater 6 are respectively installed with a pressure sensor 12, a temperature sensor 11 and a turbine flowmeter 10. The flow resistance of the heater under different flow rates (operating conditions) can be determined according to the value of the turbine flowmeter and the difference between the inlet and outlet pressures; the heating capacity of the PTC heater 6 can be determined according to the difference between the inlet and outlet water temperatures under a fixed flow rate.
[0038] The radiator 4 includes a cooling water tank and an electronic fan. High-temperature cooling water circulates in the cooling water tank, and the electronic fan cools the water by blowing or sucking air. A pressure sensor 12, a temperature sensor 11 and a turbine flowmeter 10 are respectively installed on the inlet and outlet connecting pipes of the radiator 4 to monitor the pressure, temperature and flow of the inlet and outlet cooling water. The flow resistance of the radiator 4 under different flow rates (operating conditions) can be determined based on the value of the turbine flowmeter 10 and the difference between the inlet and outlet pressures; the heat dissipation capacity of the radiator 4 can be determined based on the difference between the inlet and outlet water temperatures under a fixed flow rate.
[0039] The radiator 4 is also provided with an exhaust pipeline connected to the expansion kettle 3, and a hand valve 13 and an auxiliary condensation box 14 are arranged on the pipeline. The water outlet of the auxiliary condensation box 14 is provided with a pipeline connected to the connecting pipeline between the filter 5 and the radiator 4, and a water pump is arranged at the water outlet;
[0040] The auxiliary condensation box 14 is provided with a plug hole 1401 on both sides, and a condensation copper sheet 15 is inserted into the plug hole. The condensation copper sheet 15 is divided into two types: one is a straight strip inserted into the plug hole 1401, and the other is a ring-shaped condensation copper sheet 15 that is attached to the outer wall of the auxiliary condensation box 14, and the two ends of the straight strip condensation copper sheet 15 extend from the plug hole 1401 to connect the ring-shaped condensation copper sheet 15;
[0041] A guide protrusion 1501 is provided at the bottom of the straight strip-shaped condensing copper sheet 15 , and a water receiving tray 16 is provided below the guide protrusion 1501 , and a plurality of water leakage holes are opened on the water receiving tray.
[0042] The two shapes and structures of the condensing copper sheets 15 are respectively inside and outside the auxiliary condensing box 14. When the radiator 4 dissipates heat, the hot air rises and is sent to the expansion kettle 3. It is impossible for the radiator 4 to condense and dissipate all the water and water vapor that enters at the same time. Therefore, when the steam enters the auxiliary condensing box 14, the straight strip-shaped condensing copper sheets 15 will condense the steam, converting the steam into water droplets hanging on the surface of the condensing copper sheets 15. When the accumulated water droplets reach a certain amount, they will drip onto the water receiving tray 16 along the guide protrusion 1501, and then be placed in the water receiving tray for cooling, and finally flow out from the leakage hole on the water receiving tray, and accumulate at the bottom of the inner cavity of the auxiliary condensing box 14. After accumulating to a certain amount, the water pump set at the water outlet of the auxiliary condensing box 14 is turned on to discharge the accumulated liquid into the filter 5. In this process, excess water vapor will also be discharged to the expansion kettle 3.
[0043] The auxiliary condensation box 14 can be provided in multiple configurations.
[0044] The straight strip-shaped condensing copper sheet 15 absorbs heat inside, and conducts the heat through the outer annular condensing copper sheet 15, thereby accelerating the cooling process.
[0045] Pressure sensors 12 are installed on the inlet and outlet connecting pipes of the filter 5. When the system is in the large circulation mode, the pressure difference between the front and rear ends of the filter 5 can be measured to determine the flow resistance of the filter 5 under different flow rates (operating conditions). At the same time, the filtering capacity and service life of the filter 5 can be judged according to the curve of the change of flow resistance over time: the filter 5 with high filtering accuracy (small filter mesh aperture) has more particulate matter in the filter mesh, and its flow resistance will increase faster; conversely, the filter 5 with low filtering accuracy (large filter mesh aperture) has relatively fewer particulate matter in the filter mesh, and its flow resistance will increase relatively slowly; and when the flow resistance of the filter 5 increases to a limited value after the system has been running for a period of time, the filter 5 needs to be replaced to avoid excessive overall flow resistance of the water channel, which affects the heat dissipation capacity. At this time, its service life can be compared by the length of replacement time.
[0046] This test system tests the cooling system independently, without involving the fuel cell stack, hydrogen and air systems, thus simplifying the test system structure.
[0047] The above description is only a preferred embodiment of the present disclosure and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the embodiments of the present disclosure is not limited to the technical solutions formed by a specific combination of the above-mentioned technical features, but should also cover other technical solutions formed by any combination of the above-mentioned technical features or their equivalent features without departing from the above-mentioned inventive concept, such as a technical solution formed by replacing the above-mentioned features with technical features with similar functions disclosed in the embodiments of the present disclosure (but not limited to).
Claims
1. A fuel cell cooling system component testing system, characterized in that: The invention comprises a heating water tank (1), an electronic water pump (7), an expansion kettle (3), an electronic three-way valve (8), a PTC heater (6), a radiator (4), a filter (5) and a deionizer (2), wherein the inlet end of the heating water tank (1) is provided with a turbine flowmeter (10) and an electronic water pump (7), the outlet end of the heating water tank (1) is provided with an electronic three-way valve (8), the other two interfaces of the electronic three-way valve (8) are respectively connected to the PTC heater (6) and the radiator (4), the outlet ends of the PTC heater (6) and the radiator (4) are respectively connected to the outlet end pipeline and the inlet end of the filter (5), and the outlet end of the filter (5) is provided with a pipeline connected to the inlet end of the electronic water pump (7) to complete the circulation in sequence; The radiator (4) is also provided with an exhaust pipeline connected to the expansion kettle (3), and a hand valve (13) and an auxiliary condensation box (14) are arranged on the pipeline; the water outlet of the auxiliary condensation box (14) is provided with a pipeline connected to the connecting pipeline between the filter (5) and the radiator (4), and a water pump is arranged at the water outlet; The auxiliary condensation box (14) is provided with a plug hole (1401) on both sides, and a condensation copper sheet (15) is inserted into the plug hole. The condensation copper sheet (15) is divided into two types: one is a straight strip inserted into the plug hole (1401), and the other is a ring-shaped condensation copper sheet (15) that fits the outer wall of the auxiliary condensation box (14), and the two ends of the straight strip condensation copper sheet (15) extend from the plug hole (1401) to connect to the ring-shaped condensation copper sheet (15); A guide protrusion (1501) is provided at the bottom of the straight strip-shaped condensing copper sheet (15), and a water receiving tray (16) is provided below the guide protrusion (1501), and a plurality of water leakage holes are opened on the water receiving tray.
2. A fuel cell cooling system component testing system according to claim 1, characterized in that: An exhaust branch is provided on the pipeline connecting the heating water tank (1) and the electronic three-way valve (8) to connect the ionizer (2) and the expansion kettle (3), and a receiving valve is provided at the water inlet end of the ionizer (2).
3. A fuel cell cooling system component testing system according to claim 1, characterized in that: A conductivity meter (9) and a pressure sensor (12) are provided between the electronic water pump (7) and the turbine flow meter (10).
4. A fuel cell cooling system component testing system according to claim 1, characterized in that: A pressure sensor (12) is provided on each connecting pipe between the heating water tank (1), the electronic water pump (7), the electronic three-way valve (8), the PTC heater (6), the radiator (4) and the filter (5).
5. A fuel cell cooling system component testing system according to claim 1, characterized in that: Two water outlet ports of the electronic three-way valve (8) are respectively provided with turbine flowmeters (10).
6. A fuel cell cooling system component testing system according to claim 1, characterized in that: Temperature sensors (11) are also provided on the connecting pipes at both ends of the PTC heater (6), the heating water tank (1) and the radiator (4).
7. A fuel cell cooling system component testing system according to claim 6, characterized in that: The condensing copper sheet (15) and the water receiving tray (16) are arranged in multiple layers.
8. A fuel cell cooling system component testing system according to claim 2, characterized in that: The expansion kettle (3) is also provided with a pipe connected to the water outlet pipeline of the filter (5).
9. A fuel cell cooling system component testing system according to claim 1, characterized in that: The pressure sensor (12) at the inlet end of the electronic water pump (7) is closer to the inlet of the electronic water pump (7) than the connection point between the PTC heater (6) and the expansion kettle (3) and the inlet pipeline of the electronic water pump (7) and the inlet of the electronic water pump (7).
10. A fuel cell cooling system component testing system according to claim 3, characterized in that: The turbine flowmeter (10) is located between the electronic water pump (7) and the heating water tank (1).
Citation Information
Cited By
Battery cooling liquid leakage test system and test method
CN120195550A