Device and method for measuring lifting force of lifting steel wire rope of mining excavator
By using the inclination sensor, push stroke sensor and rotary encoder on the mining excavator, combined with the structural parameters, the effective length change of the wire rope is measured in real time, solving the accuracy of the lifting force measurement and sensor installation problems, and achieving high reliability. Lifting force measurement.
Patent Information
- Application Number
- CN202410695355.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-31
- Publication Date
- 2024-10-18
AI Technical Summary
The existing technology has poor accuracy when measuring the lifting force of the lifting wire rope of a mining excavator, and it is difficult to install sensors near the bucket to achieve real-time and long-term operation, and the impact of ore rocks on the sensors is highly destructive.
Using an inclination sensor, a pushing stroke sensor and a rotary encoder, combined with the structural parameters of the mining excavator, the effective length change of the wire rope is calculated to measure the lifting force in real time, avoiding the difficulty of installing sensors near the bucket and the impact of ore rocks. question.
It achieves accurate real-time measurement of the lifting wire rope of a mining excavator, improves the reliability of the measurement, avoids impact damage to the sensor, and does not rely on empirical parameters.
Smart Images

Figure CN118794580A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a device and a method for measuring the lifting force of a lifting wire rope of a mining excavator, and belongs to the field of mining excavators. Background Art
[0002] Mining excavators, also known as electric shovels, are the core equipment for large-scale open-pit mining. The bucket of a mining excavator completes the shoveling operation under the coordinated action of the lifting wire rope and the pushing bucket arm. The lifting force of the lifting wire rope is a key indicator to measure the production capacity of a mining excavator, and it is also an indispensable parameter of the real-time weighing system of mining excavators.
[0003] Currently, there are two main ways to measure the lifting force of the lifting wire rope. One is to calculate by combining the power and speed of the lifting motor with the size of the lifting wire rope drum, the transmission ratio of the transmission mechanism, the transmission efficiency, etc. This method requires the motor efficiency and the transmission chain efficiency to be assumed in advance based on experience, and it is difficult to accurately separate the power used to drive the lifting wire rope drum, the sky wheel and other devices to rotate, so the accuracy is poor. Another way is to install a tension sensor between the lifting wire rope and the bucket for measurement. Although this method can directly measure the lifting force of the lifting wire rope, it requires the use of wireless power supply and signal transmission mode, and it is impossible to complete long-term, real-time measurement during actual operation. There is also a lack of feasible calibration solutions for the lifting wire rope. Summary of the invention
[0004] The purpose of the present invention is to provide a method for measuring the lifting force of a lifting wire rope of a mining excavator. Based on the large rigidity of the push bucket arm, the method uses a rotary encoder installed on the lifting wire rope drum and an inclination sensor and a push stroke sensor installed on the saddle, and according to the inherent structural parameters of the mining excavator itself, calculates the effective length change of the lifting wire rope at different times, and then calculates the real-time lifting force of the lifting wire rope. Compared with the existing direct measurement method by adding a tension sensor between the lifting wire rope and the bucket, the present invention avoids the difficulty of installing a real-time, long-time working sensor near a large-scale moving bucket, and at the same time avoids the impact damage of the ore rock on the sensor during the bucket shoveling operation, and has higher reliability.
[0005] In order to achieve the above technical objectives, the present invention will adopt the following technical solutions:
[0006] A lifting force measuring device for a lifting wire rope of a mining excavator is used to measure the lifting force of the lifting wire rope of the mining excavator. The mining excavator includes a body, a pushing mechanism, a lifting mechanism and a bucket; the lifting mechanism includes a lifting motor, a sheave, a lifting wire rope drum and a lifting wire rope; the pushing mechanism includes a pushing motor, a pushing bucket rod and a saddle; the lifting force measuring device for the lifting wire rope includes a sensor system and a data processing device; wherein:
[0007] The sensor system includes an inclination sensor, a push stroke sensor and a rotary encoder;
[0008] The inclination sensor is installed on the saddle and is used to detect the inclination value of the push rod and can convert the inclination value θ detected at any data detection time t into t Transmit to a data processing device;
[0009] The pushing stroke sensor is installed on the saddle and is used to detect the pushing stroke value of the pushing bucket rod and can detect the pushing stroke value L at any data detection time t. t Transmit to a data processing device;
[0010] The rotary encoder is installed on the hoisting wire rope drum to detect the rotation angle of the hoisting wire rope drum and can convert the rotation angle α detected at any data detection time t into t Transmit to a data processing device;
[0011] The data processing device calculates the lifting force of the lifting wire rope at the current moment based on the inclination angle value, the pushing stroke value and the rotation angle fed back at the same data detection moment received.
[0012] Preferably, the data processing device comprises a wire rope effective length elongation calculation module and a lifting force calculation module;
[0013] The wire rope effective length elongation calculation module is used to calculate the change in the effective length of the lifting wire rope at time t relative to the effective length of the lifting wire rope at time t1, and output it to the lifting force calculation module;
[0014] The wire rope effective length extension calculation module calculates the effective length extension of the lifting wire rope at time t by the following formula:
[0015]
[0016] The lifting force calculation module is used to calculate the lifting force of the lifting wire rope at time t; the lifting force calculation module calculates the lifting force of the lifting wire rope at time t by the following formula:
[0017] F t =k×ΔS t
[0018] Where: k represents the elastic parameter of the lifting wire rope itself; It represents the length of the arc segment BC of the hoisting wire rope at time t, which is calculated by the inclination angle value and the pushing stroke value fed back at time t; It represents the length of the straight line segment CE of the hoisting wire rope from the crown sheave to the bucket at time t, which is calculated by the inclination angle value and the pushing stroke value fed back at time t; It represents the length of the arc segment BC of the hoisting wire rope at time t1, which is calculated by the inclination angle value and the pushing stroke value fed back at time t1; It represents the length of the straight line segment CE from the crown sheave to the bucket at time t1, which is calculated by the inclination angle value and the pushing stroke value fed back at time t1; R represents the radius of the hoisting wire rope drum; α1 represents the rotation angle detected by the rotary encoder at time t1; α t Represents the rotation angle detected by the rotary encoder at time t;
[0019] In the wire rope effective length elongation calculation module, time t1 is the time corresponding to when the bucket is unloaded, the pushing bucket arm is in a horizontal state, and the straight line segment CE from the lifting wire rope sheave to the bucket is in a vertical state.
[0020] Preferably, the steel wire rope effective length elongation calculation module includes a first calculation module and a second calculation module;
[0021] The first calculation module is used to calculate the length of the arc segment BC of the hoisting wire rope at time t1. The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t1 The input of the first calculation module is the inclination value fed back by the inclination sensor at time t1 and the pushing stroke value fed back by the pushing stroke sensor, and the output is the length of the arc segment BC of the hoisting wire rope at time t1. The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t1
[0022] The second calculation module is used to calculate the length of the arc segment BC of the hoisting wire rope at time t. The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t The input of the second calculation module is the inclination value fed back by the inclination sensor at time t and the pushing stroke value fed back by the pushing stroke sensor, and the output is the length of the arc segment BC of the hoisting wire rope at time t. The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t
[0023] The first calculation module and the second calculation module are both constructed by the same calculation model M, and the calculation model M includes three submodules, corresponding to the first to third calculation submodules; wherein:
[0024] The first calculation submodule is used to sequentially calculate the length of the line segment OE, the angle of ∠EOD, and the length of the line segment DE, and can transmit the calculated length of the line segment OE and the angle of ∠EOD to the third calculation submodule, and transmit the calculated length of the line segment DE to the second and third calculation submodules respectively;
[0025] The first calculation submodule calculates the length of the line segment OE, the angle of ∠EOD, and the length of the line segment DE in sequence according to the pushing stroke L of the pushing bucket arm detected by the pushing stroke sensor and the inclination angle θ of the pushing bucket arm detected by the inclination sensor through the following formulas:
[0026]
[0027] The second calculation submodule is used to calculate the length S of the straight line segment CE. CE , and can calculate the length S of the straight line segment CE CE The second calculation submodule calculates the length S of the straight line segment CE according to the length of the line segment DE transmitted from the first calculation submodule by the following formula: CE :
[0028]
[0029] The third calculation submodule is used to calculate the length S of the arc segment BC. BC , and the calculated length S of the arc segment BC can be BC The third calculation submodule calculates the length of the straight line segment CE transmitted from the first calculation submodule according to the angle of ∠EOD, the length of the line segment OE, the length of the line segment DE, and the length S of the straight line segment CE transmitted from the second calculation submodule. CE , calculate the length S of the arc segment BC by the following formula BC :
[0030]
[0031] The coordinate system XOY is constructed with the rotation center O of the saddle as the origin;
[0032] In the above formula: A is the tangent point between the lifting wire rope and the lifting wire rope drum; B and C are the two tangent points between the lifting wire rope and the sheave respectively; D is the rotation center of the sheave; E is the hinge point between the lifting wire rope and the bucket;
[0033] The line segment OH is a perpendicular line to the upper surface of the push arm, and the line segment EF is parallel to the line segment OH; the lengths of the line segment OH and the line segment EF are both constant values;
[0034] θ is the inclination angle of the push arm, which is detected by the inclination sensor;
[0035] L is the pushing stroke of the pushing bucket arm, which is detected by the pushing stroke sensor; C is a constant.
[0036] Preferably, at time t1, the rotation angle α1 detected by the rotary encoder satisfies:
[0037]
[0038] In the formula: k is the elastic coefficient of the lifting wire rope, R is the radius of the lifting wire rope drum; G represents the resultant force of the push bucket arm-bucket gravity; L3 represents the distance between the resultant force G and the saddle rotation center when the push bucket arm is in a horizontal state and the straight line segment CE from the lifting wire rope sheave to the bucket is in a vertical state; L4 represents the distance of the lifting force relative to the saddle rotation center when the push bucket arm is in a horizontal state and the straight line segment CE from the lifting wire rope sheave to the bucket is in a vertical state.
[0039] Another technical purpose of the present invention is to provide a method for measuring the lifting force of a lifting wire rope of a mining excavator, which is implemented based on the above-mentioned lifting force measuring device for a lifting wire rope of a mining excavator. The lifting force measurement of the lifting wire rope specifically includes the following steps:
[0040] S201, obtain the readings of the inclination sensor, the push stroke sensor, and the rotary encoder at time t1, which are L1, α1;
[0041] S202: The reading of the inclination sensor obtained in step S201 The reading of the push stroke sensor L1 is used to calculate the length of the arc segment BC of the hoisting wire rope at time t1 by the following formula: The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t1
[0042] HF1=L1+C
[0043]
[0044] ∠EOD1=∠DOX+θ1-∠EHF1-∠HEO1
[0045]
[0046] ∠BDC1=2π-∠ODB-∠EDO1-∠EDC1
[0047]
[0048] In the above formula: O is the rotation center of the saddle, A is the tangent point between the lifting wire rope and the lifting wire rope drum; B and C are the two tangent points between the lifting wire rope and the sheave respectively; D is the rotation center of the sheave; E is the hinge point between the lifting wire rope and the bucket; line segment OH is the vertical line of the upper surface of the push bucket rod, and line segment EF is parallel to line segment OH;
[0049] S203, obtaining the readings of the inclination sensor, the push stroke sensor, and the rotary encoder at time t, which are respectively L t , α t ;
[0050] S204: The reading of the inclination sensor obtained in step S203 Reading of the push stroke sensor L t , calculate the length of the arc segment BC of the hoisting wire rope at time t by the following formula: The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t
[0051] HF t =L t +C
[0052]
[0053] ∠EOD t =∠DOX+θ t -∠EHF t -∠HEO t
[0054]
[0055] ∠BDC t =2π-∠ODB-∠EDO t -∠EDC t
[0056]
[0057] S204: the reading α1 of the rotary encoder obtained in step S201 and the reading α of the rotary encoder obtained in step S203 t , combined with the length of the arc segment BC of the hoisting wire rope calculated in step S202 The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t1 and the length of the arc segment BC of the hoisting wire rope at time t calculated in step S203 The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t The change ΔS of the effective length of the lifting wire rope at time t relative to the effective length of the lifting wire rope at time t1 is calculated by the following formula: t :
[0058]
[0059] S205. Calculate the lifting force of the lifting wire rope at time t by the following formula:
[0060] F t =k×ΔS t
[0061] Where: k represents the elastic parameter of the lifting wire rope itself.
[0062] Preferably, before measuring the lifting force of the lifting wire rope, it is necessary to calibrate the effective length of the lifting wire rope using a calibration rotary encoder when the mining excavator is in an unloaded state, which specifically includes the following steps:
[0063] S101: starting the pushing motor until the pushing stroke of the pushing bucket arm reaches the preset pushing stroke L2;
[0064] S102: Start the lifting motor and adjust the length of the lifting wire rope according to the reading of the inclination sensor until the reading of the inclination sensor indicates that the push bucket arm is in a horizontal state. At this time, the lifting wire rope only provides a vertical upward lifting force F to the bucket. The distance between the combined force G of the push bucket arm and the bucket gravity and the rotation center of the saddle is recorded as distance L3, and the distance between the lifting force F provided by the lifting wire rope to the bucket and the rotation center of the saddle is recorded as L4;
[0065] S103: Calculate the lifting force F by the following formula:
[0066]
[0067] Where: G represents the resultant force of the push arm and the bucket gravity; L3 represents the distance between the resultant force G and the saddle rotation center when the push arm is in a horizontal state and the straight line segment CE from the lifting wire rope sheave to the bucket is in a vertical state; L4 represents the distance relative to the saddle rotation center when the push arm is in a horizontal state and the straight line segment CE from the lifting wire rope sheave to the bucket is in a vertical state;
[0068] S104: Calibrate the rotation angle α1 of the rotary encoder so that the rotation angle α1 satisfies:
[0069]
[0070] Where: k is the elastic coefficient of the lifting wire rope, R is the radius of the lifting wire rope drum;
[0071] The time t1 of step S201 is the time corresponding to the rotation angle α1 of the rotary encoder calibrated in step S104.
[0072] Based on the above technical objectives, the present invention has the following advantages over the prior art:
[0073] The present invention utilizes the inclination sensor, the push stroke sensor, the rotary encoder and the inherent structural parameters of the mining excavator itself to complete the calibration of the lifting wire rope and the lifting force measurement without relying on any empirical parameters. Compared with the existing direct measurement method of installing a tension sensor between the lifting wire rope and the bucket, the present invention avoids the difficulty of installing a real-time, long-time working sensor near a large-scale moving bucket, and at the same time avoids the impact damage of the ore rock on the sensor during the bucket shoveling operation, and has higher reliability. BRIEF DESCRIPTION OF THE DRAWINGS
[0074] Figure 1 It is a structural schematic diagram of the lifting force measuring device of the lifting wire rope of the mining excavator according to the present invention;
[0075] Figure 2 It is a structural schematic diagram of the lifting force measuring device for lifting wire rope of mining excavator of the present invention when being calibrated;
[0076] Figure 3 It is a structural schematic diagram of the lifting force measuring device for lifting steel wire rope of mining excavator of the present invention when calculating the effective length of the lifting steel wire rope;
[0077] Figures 1 to 3 Middle: 1. Bucket, 2. Saddle, 3. Pushing bucket arm, 4. Lifting wire rope drum, 5. Lifting wire rope, 6. Inclination sensor, 7. Pushing stroke sensor, 8. Rotary encoder;
[0078] G is the combined force of the push arm and the bucket gravity, F is when the push arm is in a horizontal state and the lifting wire rope only provides a vertical upward lifting force to the bucket, L1 is the total stroke of the push arm, L2 is a specific stroke of the push arm, L3 represents the distance between the combined force G and the saddle rotation center when the push arm is in a horizontal state and the straight line segment CE from the lifting wire rope sheave to the bucket is in a vertical state; L4 represents the distance of the lifting force relative to the saddle rotation center when the push arm is in a horizontal state and the straight line segment CE from the lifting wire rope sheave to the bucket is in a vertical state;
[0079] O is the rotation center of the saddle, A is the tangency point between the lifting wire rope and the lifting wire rope drum; B and C are the two tangency points between the lifting wire rope and the crown sheave respectively; D is the rotation center of the crown sheave; E is the hinge point between the lifting wire rope and the bucket; line segment OH is the vertical line of the upper surface of the push arm, and line segment EF is parallel to line segment OH; the plane coordinate system XOY is constructed with the rotation center O of the saddle as the origin. DETAILED DESCRIPTION
[0080] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. The following description of at least one exemplary embodiment is actually only illustrative and is by no means any limitation to the present invention and its application or use. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Unless otherwise specified, the relative arrangement, expressions and numerical values of the components and steps described in these embodiments do not limit the scope of the present invention. The techniques, methods and equipment known to ordinary technicians in the relevant fields may not be discussed in detail, but in appropriate cases, the techniques, methods and equipment should be regarded as part of the specification. In all examples shown and discussed here, any specific value should be interpreted as merely exemplary, rather than as a limitation. Therefore, other examples of the exemplary embodiments may have different values.
[0081] For ease of description, spatially relative terms such as "above", "above", "on the upper surface of", "above", etc. may be used here to describe the spatial positional relationship between a device or feature and other devices or features as shown in the figure. It should be understood that spatially relative terms are intended to include different orientations of the device in use or operation in addition to the orientation described in the figure. For example, if the device in the accompanying drawings is inverted, the device described as "above other devices or structures" or "above other devices or structures" will be positioned as "below other devices or structures" or "below other devices or structures". Thus, the exemplary term "above" can include both "above" and "below". The device can also be positioned in other different ways (rotated 90 degrees or in other orientations).
[0082] Example 1
[0083] The lifting force measuring device for lifting wire rope of mining excavator of the present invention is used to measure the lifting force of lifting wire rope of mining excavator, such as Figures 1 to 3 As shown, the mining excavator comprises a machine body, a pushing mechanism, a lifting mechanism and a bucket 1; the lifting mechanism comprises a lifting motor, a sheave, a lifting wire rope drum 4 and a lifting wire rope 5; the pushing mechanism comprises a pushing motor, a pushing bucket rod 3 and a saddle 2; in the figure, one end of the lifting wire rope 5 is hinged to the bucket 1, and the other end is wound on the lifting wire rope drum 4; the bucket 1 and the pushing bucket rod 3 are rigidly connected and can move linearly along the fixed direction of the saddle 2; the saddle 2 can rotate around a fixed point under the action of the pushing motor and the lifting wire rope;
[0084] The lifting wire rope lifting force measuring device comprises a sensor system and a data processing device; wherein:
[0085] The sensor system includes an inclination sensor 6, a pushing stroke sensor 7 and a rotary encoder 8. The inclination sensor 6 and the pushing stroke sensor 7 are installed on the saddle 2, and can obtain the inclination value and the pushing stroke value of the pushing bucket rod 3 respectively. The lifting wire rope drum 4 is equipped with a rotary encoder 8, which can obtain the drum rotation angle. The inclination sensor 6, the pushing stroke sensor 7 and the rotary encoder 8 correspond to the collected inclination value, the pushing stroke value and the drum rotation angle respectively, and can be transmitted to the data processing device through the data line. The data processing device calculates the lifting force of the lifting wire rope at the current moment according to the inclination value, the pushing stroke value and the rotation angle fed back at the same data detection moment received.
[0086] The data processing device described in the present invention first calculates the change in the effective length of the lifting wire rope by combining the inherent design parameters of the mining excavator structure, using the rotation angle of the lifting wire rope drum 4, the inclination angle of the pushing bucket 3 and the pushing stroke, and then calculates the lifting force of the lifting wire rope at the current moment based on the elastic relationship between the lifting force of the lifting wire rope and the change in its length.
[0087] Specifically, the data processing device of the present invention includes a wire rope effective length elongation calculation module and a lifting force calculation module; wherein:
[0088] The wire rope effective length elongation calculation module is used to calculate the change in the effective length of the lifting wire rope at time t relative to the effective length of the lifting wire rope at time t1, and output it to the lifting force calculation module.
[0089] The effective length of the lifting wire rope consists of three parts. Figure 3 , including the straight segment AB from the hoisting wire rope drum to the sheave, the arc segment BC wound on the sheave, and the straight segment CE from the sheave to the bucket. Usually, when the effective length of the hoisting wire rope changes, we believe that the length of the straight segment AB remains unchanged, while the lengths of the arc segment BC and the straight segment CE will change. At the same time, the change in the effective length of the hoisting wire rope also includes changes caused by its own elastic deformation. Based on this, the wire rope effective length extension calculation module of the present invention calculates the effective length extension of the hoisting wire rope at time t through the following formula:
[0090]
[0091] In the above formula: It represents the length of the arc segment BC of the hoisting wire rope at time t, which is calculated by the inclination angle value and the pushing stroke value fed back at time t; It represents the length of the straight line segment CE of the hoisting wire rope from the crown sheave to the bucket at time t, which is calculated by the inclination angle value and the pushing stroke value fed back at time t; It represents the length of the arc segment BC of the hoisting wire rope at time t1, which is calculated by the inclination angle value and the pushing stroke value fed back at time t1; It represents the length of the straight line segment CE from the crown sheave to the bucket at time t1, which is calculated by the inclination angle value and the pushing stroke value fed back at time t1; R represents the radius of the hoisting wire rope drum; α1 represents the rotation angle detected by the rotary encoder at time t1; α t Indicates the rotation angle detected by the rotary encoder at time t.
[0092] The time t1 is the time corresponding to the effective length of the calibrated lifting wire rope. At the time t1, the bucket is unloaded, the push arm is in a horizontal state, and the lifting wire rope is in a vertical state in the straight line segment CE from the crown wheel to the bucket. At this time: the lifting force F generated by the lifting wire rope is vertically upward, and the component force in the horizontal direction is 0. The rotation angle α1 detected by the rotary encoder satisfies:
[0093]
[0094] In the formula: k is the elastic coefficient of the lifting wire rope, R is the radius of the lifting wire rope drum; G represents the resultant force of the push bucket arm-bucket gravity; L3 represents the distance between the resultant force G and the saddle rotation center when the push bucket arm is in a horizontal state and the straight line segment CE from the lifting wire rope sheave to the bucket is in a vertical state; L4 represents the distance of the lifting force relative to the saddle rotation center when the push bucket arm is in a horizontal state and the straight line segment CE from the lifting wire rope sheave to the bucket is in a vertical state.
[0095] The theoretical basis for calculating the effective length elongation of the wire rope is:
[0096] S301: With the calibration time as time t1, the readings of the inclination sensor 6, the push stroke sensor 7, and the rotary encoder 8 are obtained respectively. L1, α1.
[0097] S302: Calculate the effective length S1 of the lifting wire rope 5 at time t1 according to formula (3):
[0098]
[0099] Where: The length of the lifting wire rope AB section S AB Fixed, S1 BC is the length of the arc segment BC of the sky wheel at time t1, S1CE S1 is the length of the CE section from the crown wheel to the bucket at time t1. BC and S1 CE The segment length can be based on L1 is calculated.
[0100] S303: Calculate the effective length S0 of the lifting wire rope 5 when the lifting force is 0. At time t1, the lifting force of the lifting wire rope is F, and the reading of the calibrated rotary encoder 8 is α1. Combined with formula (2), when the lifting force of the lifting wire rope is 0, the length change is also 0, and the effective length of the lifting wire rope can be calculated according to formula (4).
[0101] S0=S1-R×α1 (4)
[0102] S304: At time t, the readings of the inclination sensor 6, the push stroke sensor 7, and the rotary encoder 8 are obtained respectively. L t , α t . At the lifting force F t Under the action of, the effective length of the lifting wire rope can be calculated by formula (5):
[0103]
[0104] In the formula, S t BC , S t CE according to L t Calculated.
[0105] Assuming that the lifting force of the lifting wire rope is 0 at this time, the change in the effective length of the lifting wire rope is only caused by the retraction and release of the lifting wire rope on the lifting wire rope drum, which can be calculated by the change in the reading of the rotary encoder 8 according to formula (6):
[0106]
[0107] In fact, due to the lifting force, the change in the effective length of the lifting wire rope also includes the elastic elongation part. At this time, the elongation of the effective length of the lifting wire rope under the lifting force can be calculated by formula (7):
[0108]
[0109] The lifting force calculation module is used to calculate the lifting force of the lifting wire rope at time t; the lifting force calculation module calculates the lifting force of the lifting wire rope at time t by the following formula:
[0110]
[0111] Where: k represents the elastic parameter of the lifting wire rope itself.
[0112] According to formula (8), the lifting force F of the lifting wire rope is t It can be calculated by the change of the arc segment BC of the hoisting wire rope, the straight segment CE from the hoisting wire rope to the bucket, and the change value of the rotary encoder on the hoisting wire rope drum.
[0113] In order to obtain the variation of the sheave arc segment BC of the lifting wire rope and the variation of the sheave to bucket straight segment CE, the wire rope effective length elongation calculation module of the present invention includes a first calculation module and a second calculation module; wherein:
[0114] The first calculation module is used to calculate the length of the arc segment BC of the hoisting wire rope at time t1. The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t1 The input of the first calculation module is the inclination value fed back by the inclination sensor at time t1 and the pushing stroke value fed back by the pushing stroke sensor, and the output is the length of the arc segment BC of the hoisting wire rope at time t1. The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t1
[0115] The second calculation module is used to calculate the length of the arc segment BC of the hoisting wire rope at time t. The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t The input of the second calculation module is the inclination value fed back by the inclination sensor at time t and the pushing stroke value fed back by the pushing stroke sensor, and the output is the length of the arc segment BC of the hoisting wire rope at time t. The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t
[0116] The first calculation module and the second calculation module are both constructed by the same calculation model M, and the calculation model M includes three submodules, corresponding to the first to third calculation submodules; wherein:
[0117] The first calculation submodule is used to sequentially calculate the length of the line segment OE, the angle of ∠EOD, and the length of the line segment DE, and can transmit the calculated length of the line segment OE and the angle of ∠EOD to the third calculation submodule, and transmit the calculated length of the line segment DE to the second and third calculation submodules respectively;
[0118] The first calculation submodule calculates the length of the line segment OE, the angle of ∠EOD, and the length of the line segment DE in sequence according to the pushing stroke L of the pushing bucket arm detected by the pushing stroke sensor and the inclination angle θ of the pushing bucket arm detected by the inclination sensor through the following formulas:
[0119]
[0120] The second calculation submodule is used to calculate the length S of the straight line segment CE. CE , and can calculate the length S of the straight line segment CE CE The second calculation submodule calculates the length S of the straight line segment CE according to the length of the line segment DE transmitted from the first calculation submodule by the following formula: CE :
[0121]
[0122] The third calculation submodule is used to calculate the length S of the arc segment BC. BC , and the calculated length S of the arc segment BC can be BC The third calculation submodule calculates the length of the straight line segment CE transmitted from the first calculation submodule according to the angle of ∠EOD, the length of the line segment OE, the length of the line segment DE, and the length S of the straight line segment CE transmitted from the second calculation submodule. CE , calculate the length S of the arc segment BC by the following formula BC :
[0123]
[0124] The coordinate system XOY is constructed with the rotation center O of the saddle as the origin;
[0125] In the above formula: A is the tangent point between the lifting wire rope and the lifting wire rope drum; B and C are the two tangent points between the lifting wire rope and the sheave respectively; D is the rotation center of the sheave; E is the hinge point between the lifting wire rope and the bucket;
[0126] The line segment OH is a perpendicular line to the upper surface of the push arm, the line segment EF is parallel to the line segment OH; the lengths of the line segment OH and the line segment EF are both constants; and DC is the radius of the crown wheel.
[0127] θ is the inclination angle of the push arm, which is detected by the inclination sensor;
[0128] L is the pushing stroke of the pushing bucket arm, which is detected by the pushing stroke sensor; C is a constant.
[0129] Example 2
[0130] Based on the above-mentioned device for measuring the lifting force of a lifting wire rope of a mining excavator, the present invention provides a method for measuring the lifting force of a lifting wire rope of a mining excavator.
[0131] Before using this method to calculate the lifting force of the lifting wire rope, the length of the lifting wire rope needs to be calibrated. Figure 2 Schematic diagram of the lifting wire rope calibration method. In the figure, the bucket 1 is unloaded, the push bucket 3 is in a horizontal state, G is the combined force of the push bucket and the bucket gravity, F is the lifting force of the lifting wire rope, L1 is the total stroke of the push bucket, and L2 is a specific pushing stroke of the push bucket, which can make the distance between the lifting force F of the lifting wire rope and the saddle rotation center be L4, and at this time, the distance between the combined force G of the push bucket and the bucket gravity and the saddle rotation center is L3. The above L1, L2, L3, and L4 are all fixed parameters related to the push bucket-bucket structure.
[0132] When the bucket 1 is unloaded, the effective length of the lifting wire rope 5 is calibrated by calibrating the rotary encoder 8, and step S100 is as follows:
[0133] S101: The pushing motor of the mining excavator is working, and the pushing stroke of the pushing bucket arm is adjusted to L2. The pushing bucket arm is locked by the brake on the pushing motor to prevent the pushing bucket arm from sliding freely in the saddle.
[0134] S102: The lifting motor of the mining excavator is working. According to the indication of the inclination sensor 6, the length of the lifting wire rope is adjusted to make the pushing bucket arm 3 in a horizontal state. At this time, the lifting wire rope only provides a vertical upward lifting force F to the bucket. The distance between the combined force G of the pushing bucket arm and the gravity of the bucket and the rotation center of the saddle is recorded as distance L3, and the distance between the lifting force F provided by the lifting wire rope to the bucket and the rotation center of the saddle is recorded as distance L4.
[0135] S103: According to the moment balance condition, the lifting force F can be calculated by formula (1):
[0136]
[0137] S104: Calibrate the angle reading of the rotary encoder 8 to α1 according to equation (2).
[0138]
[0139] Where k is the elastic coefficient of the lifting wire rope and R is the radius of the lifting drum.
[0140] Figure 3Schematic diagram of the effective length measurement method of the lifting wire rope. In the figure, the effective length of the lifting wire rope consists of three sections: the lifting wire rope drum to the sheave section AB, the sheave arc section BC, and the sheave to the bucket section CE. The deadweight of the lifting wire rope can be ignored relative to the lifting force it bears. After calibration, step S200 of the lifting wire rope lifting force measurement method is:
[0141] S201, obtain the readings of the inclination sensor, the push stroke sensor, and the rotary encoder at time t1, which are L1, α1; time t1 is the time corresponding to the rotation angle α1 of the rotary encoder calibrated in step S104.
[0142] S202: The reading of the inclination sensor obtained in step S201 The reading of the push stroke sensor L1 is used to calculate the length of the arc segment BC of the hoisting wire rope at time t1 by the following formula: The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t1
[0143] HF1=L1+C
[0144]
[0145] ∠EOD1=∠DOX+θ1-∠EHF1-∠HEO1
[0146]
[0147] ∠BDC1=2π-∠ODB-∠EDO1-∠EDC1
[0148]
[0149] In the above formula: O is the rotation center of the saddle, A is the tangent point between the lifting wire rope and the lifting wire rope drum; B and C are the two tangent points between the lifting wire rope and the sheave respectively; D is the rotation center of the sheave; E is the hinge point between the lifting wire rope and the bucket; line segment OH is the vertical line of the upper surface of the push bucket rod, and line segment EF is parallel to line segment OH;
[0150] S203, obtaining the readings of the inclination sensor, the push stroke sensor, and the rotary encoder at time t, which are respectively L t , α t ;
[0151] S204: The reading of the inclination sensor obtained in step S203 Reading of the push stroke sensor L t , calculate the length of the arc segment BC of the hoisting wire rope at time t by the following formula: The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t
[0152] HF t =L t +C
[0153]
[0154] ∠EOD t =∠DOX+θ t -∠EHF t -∠HEO t
[0155]
[0156] ∠BDC t =2π-∠ODB-∠EDO t -∠EDC t
[0157]
[0158] S204: the reading α1 of the rotary encoder obtained in step S201 and the reading α of the rotary encoder obtained in step S203 t , combined with the length of the arc segment BC of the hoisting wire rope calculated in step S202 The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t1 and the length of the arc segment BC of the hoisting wire rope at time t calculated in step S203 The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t The change ΔS of the effective length of the lifting wire rope at time t relative to the effective length of the lifting wire rope at time t1 is calculated by the following formula: t :
[0159]
[0160] S205. Calculate the lifting force of the lifting wire rope at time t by the following formula:
[0161] F t =k×ΔS t
[0162] Where: k represents the elastic parameter of the lifting wire rope itself.
[0163] It can be seen that the present invention utilizes the inclination sensor, the push stroke sensor, the rotary encoder and the inherent structural parameters of the mining excavator itself, and can complete the calibration of the lifting wire rope and the lifting force measurement through strict formula derivation, without relying on any empirical parameters. Compared with the existing direct measurement method by installing a tension sensor between the lifting wire rope and the bucket, the present invention avoids the difficulty of installing a real-time, long-time working sensor near a large-scale moving bucket, and at the same time avoids the impact damage of the ore rock on the sensor during the bucket shoveling operation, and has higher reliability.
Claims
1. A lifting force measuring device for lifting wire rope of mining excavator, used for measuring the lifting force of lifting wire rope of mining excavator, the mining excavator comprises a body, a pushing mechanism, a lifting mechanism and a bucket; the lifting mechanism comprises a lifting motor, a sheave, a lifting wire rope drum and a lifting wire rope; the pushing mechanism comprises a pushing motor, a pushing bucket rod and a saddle; characterized in that, The lifting wire rope lifting force measuring device comprises a sensor system and a data processing device; in: The sensor system includes an inclination sensor, a push stroke sensor and a rotary encoder; The inclination sensor is installed on the saddle and is used to detect the inclination value of the push rod and can convert the inclination value θ detected at any data detection time t into t transmitted to a data processing device; The pushing stroke sensor is installed on the saddle and is used to detect the pushing stroke value of the pushing bucket rod and can detect the pushing stroke value L at any data detection time t. t transmitted to a data processing device; The rotary encoder is installed on the hoisting wire rope drum to detect the rotation angle of the hoisting wire rope drum and can convert the rotation angle α detected at any data detection time t into t transmitted to a data processing device; The data processing device calculates the lifting force of the lifting wire rope at the current moment based on the inclination angle value, the pushing stroke value and the rotation angle fed back at the same data detection moment received.
2. The device for measuring the lifting force of a lifting wire rope of a mining excavator according to claim 1, characterized in that: The data processing device includes a wire rope effective length elongation calculation module and a lifting force calculation module; The wire rope effective length elongation calculation module is used to calculate the change in the effective length of the lifting wire rope at time t relative to the effective length of the lifting wire rope at time t1, and output it to the lifting force calculation module; The wire rope effective length extension calculation module calculates the effective length extension of the lifting wire rope at time t by the following formula: The lifting force calculation module is used to calculate the lifting force of the lifting wire rope at time t; the lifting force calculation module calculates the lifting force of the lifting wire rope at time t by the following formula: F t =k×ΔS t Where: k represents the elastic parameter of the lifting wire rope itself; It represents the length of the arc segment BC of the hoisting wire rope at time t, which is calculated by the inclination angle value and the pushing stroke value fed back at time t; It represents the length of the straight line segment CE of the hoisting wire rope from the crown sheave to the bucket at time t, which is calculated by the inclination angle value and the pushing stroke value fed back at time t; It represents the length of the arc segment BC of the hoisting wire rope at time t1, which is calculated by the inclination angle value and the pushing stroke value fed back at time t1; It represents the length of the straight line segment CE from the crown sheave to the bucket at time t1, which is calculated by the inclination angle value and the pushing stroke value fed back at time t1; R represents the radius of the hoisting wire rope drum; α1 represents the rotation angle detected by the rotary encoder at time t1; α t Represents the rotation angle detected by the rotary encoder at time t; In the wire rope effective length elongation calculation module, time t1 is the time corresponding to when the bucket is unloaded, the pushing bucket arm is in a horizontal state, and the straight line segment CE from the lifting wire rope sheave to the bucket is in a vertical state.
3. The device for measuring the lifting force of a lifting wire rope of a mining excavator according to claim 2, characterized in that: The steel wire rope effective length elongation calculation module includes a first calculation module and a second calculation module; The first calculation module is used to calculate the length of the arc segment BC of the hoisting wire rope at time t1. The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t1 The input of the first calculation module is the inclination value fed back by the inclination sensor at time t1 and the pushing stroke value fed back by the pushing stroke sensor, and the output is the length of the arc segment BC of the hoisting wire rope at time t1. The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t1 The second calculation module is used to calculate the length of the arc segment BC of the hoisting wire rope at time t. The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t The input of the second calculation module is the inclination value fed back by the inclination sensor at time t and the pushing stroke value fed back by the pushing stroke sensor, and the output is the length of the arc segment BC of the hoisting wire rope at time t. The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t The first calculation module and the second calculation module are both constructed by the same calculation model M, and the calculation model M includes three submodules, corresponding to the first to third calculation submodules; wherein: The first calculation submodule is used to sequentially calculate the length of the line segment OE, the angle of ∠EOD, and the length of the line segment DE, and can transmit the calculated length of the line segment OE and the angle of ∠EOD to the third calculation submodule, and transmit the calculated length of the line segment DE to the second and third calculation submodules respectively; The first calculation submodule calculates the length of the line segment OE, the angle of ∠EOD, and the length of the line segment DE in sequence according to the pushing stroke L of the pushing bucket arm detected by the pushing stroke sensor and the inclination angle θ of the pushing bucket arm detected by the inclination sensor through the following formulas: The second calculation submodule is used to calculate the length S of the straight line segment CE. CE , and can calculate the length S of the straight line segment CE CE The second calculation submodule calculates the length S of the straight line segment CE according to the length of the line segment DE transmitted from the first calculation submodule by the following formula: CE : The third calculation submodule is used to calculate the length S of the arc segment BC. BC , and the calculated length S of the arc segment BC can be BC The third calculation submodule calculates the length of the straight line segment CE transmitted from the first calculation submodule according to the angle of ∠EOD, the length of the line segment OE, the length of the line segment DE, and the length S of the straight line segment CE transmitted from the second calculation submodule. CE , calculate the length S of the arc segment BC by the following formula BC : The coordinate system XOY is constructed with the rotation center O of the saddle as the origin; In the above formula: A is the tangent point between the lifting wire rope and the lifting wire rope drum; B and C are the two tangent points between the lifting wire rope and the sheave respectively; D is the rotation center of the sheave; E is the hinge point between the lifting wire rope and the bucket; The line segment OH is a perpendicular line to the upper surface of the push arm, the line segment EF is parallel to the line segment OH; the lengths of the line segment OH and the line segment EF are both constants; and DC is the radius of the crown wheel. θ is the inclination angle of the push arm, which is detected by the inclination sensor; L is the pushing stroke of the pushing bucket arm, which is detected by the pushing stroke sensor; C is a constant.
4. The device for measuring the lifting force of a lifting wire rope of a mining excavator according to claim 3, characterized in that: At time t1, the rotation angle α1 detected by the rotary encoder satisfies: In the formula: k is the elastic coefficient of the lifting wire rope, R is the radius of the lifting wire rope drum; G represents the resultant force of the push bucket arm-bucket gravity; L3 represents the distance between the resultant force G and the saddle rotation center when the push bucket arm is in a horizontal state and the straight line segment CE from the lifting wire rope sheave to the bucket is in a vertical state; L4 represents the distance of the lifting force relative to the saddle rotation center when the push bucket arm is in a horizontal state and the straight line segment CE from the lifting wire rope sheave to the bucket is in a vertical state.
5. A method for measuring the lifting force of a lifting wire rope of a mining excavator, which is implemented based on the lifting force measuring device of a lifting wire rope of a mining excavator according to claim 1, characterized in that: The lifting force measurement of the lifting wire rope specifically includes the following steps: S201, obtaining the readings of the inclination sensor, the push stroke sensor, and the rotary encoder at time t1, which are θ1, L1, and α1 respectively; S202, according to the reading θ1 of the inclination sensor and the reading L1 of the push stroke sensor obtained in step S201, the length of the arc segment BC of the hoisting wire rope at time t1 is calculated by the following formula: The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t1 HF1=L1+C ∠EOD1=∠DOX+θ1-∠EHF1-∠HEO1 ∠BDC1=2π-∠ODB-∠EDO1-∠EDC1 In the above formula: O is the rotation center of the saddle, A is the tangent point between the lifting wire rope and the lifting wire rope drum; B and C are the two tangent points between the lifting wire rope and the sheave respectively; D is the rotation center of the sheave; E is the hinge point between the lifting wire rope and the bucket; Line segment OH is a perpendicular line to the upper surface of the push arm, and line segment EF is parallel to line segment OH; S203, obtaining the readings of the inclination sensor, the push stroke sensor, and the rotary encoder at time t, which are θ t , L t , α t ; S204: The reading θ of the inclination sensor obtained in step S203 t , Reading of the push stroke sensor L t , calculate the length of the arc segment BC of the hoisting wire rope at time t by the following formula: The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t HF t =L t +C ∠EOD t =∠DOX+θ t -∠EHF t -∠HEO t ∠BDC t =2π-∠ODB-∠EDO t -∠EDC t S204: the reading α1 of the rotary encoder obtained in step S201 and the reading α of the rotary encoder obtained in step S203 t , combined with the length of the arc segment BC of the hoisting wire rope calculated in step S202 The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t1 and the length of the arc segment BC of the hoisting wire rope at time t calculated in step S203 The length of the straight line CE of the lifting wire rope from the crown sheave to the bucket at time t The change ΔS of the effective length of the lifting wire rope at time t relative to the effective length of the lifting wire rope at time t1 is calculated by the following formula: t : S205. Calculate the lifting force of the lifting wire rope at time t by the following formula: F t =k×ΔS t Where: k represents the elastic parameter of the lifting wire rope itself.
6. The method for measuring the lifting force of a lifting wire rope of a mining excavator according to claim 5, characterized in that: Before measuring the lifting force of the lifting wire rope, it is necessary to calibrate the rotary encoder to calibrate the effective length of the lifting wire rope when the mining excavator is in an unloaded state. The specific steps include the following: S101: starting the pushing motor until the pushing stroke of the pushing bucket arm reaches the preset pushing stroke L2; S102: Start the lifting motor and adjust the length of the lifting wire rope according to the reading of the inclination sensor until the reading of the inclination sensor indicates that the push bucket arm is in a horizontal state. At this time, the lifting wire rope only provides a vertical upward lifting force F to the bucket. The distance between the combined force G of the push bucket arm and the bucket gravity and the rotation center of the saddle is recorded as distance L3, and the distance between the lifting force F provided by the lifting wire rope to the bucket and the rotation center of the saddle is recorded as L4; S103: Calculate the lifting force F by the following formula: Where: G represents the resultant force of the push arm and the bucket gravity; L3 represents the distance between the resultant force G and the saddle rotation center when the push arm is in a horizontal state and the straight line segment CE from the lifting wire rope sheave to the bucket is in a vertical state; L4 represents the distance relative to the saddle rotation center when the push arm is in a horizontal state and the straight line segment CE from the lifting wire rope sheave to the bucket is in a vertical state; S104: Calibrate the rotation angle α1 of the rotary encoder so that the rotation angle α1 satisfies: Where: k is the elastic coefficient of the lifting wire rope, R is the radius of the lifting wire rope drum; The time t1 of step S201 is the time corresponding to the rotation angle α1 of the rotary encoder calibrated in step S104.
Citation Information
Cited By
Excavator lifting force automatic test system and method
CN120846547A
An automatic test system and method for lifting force of a shovel
CN120846547B