Construction method for blocking tailing pond flood drainage system
Through the method of segmented grouting and replenishing, the problem of insufficient structural strength of the drainage pipe when the tailings pond drainage system is heightened and expanded is solved, a stable blocking effect is achieved, the risk of collapse and construction difficulty are reduced, and the construction efficiency is improved. Security.
Patent Information
- Application Number
- CN202411093124.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-10-22
AI Technical Summary
When the existing tailings pond drainage system was heightened and expanded, the original drainage pipe structure was not strong enough, resulting in poor sealing quality, risk of collapse, difficult construction, and high safety hazards.
The method of segmented grouting and grouting is used to calculate the safe distance of air supply and grouting equipment by obtaining environmental parameters, and the elastic capsule is filled with cement slurry for pre-blocking and grouting to ensure that the cement slurry in each section is solidified. The pressure is greater than the pressure during grouting, which enhances the structural strength of the flood drainage pipe.
It achieves stable blocking of flood drainage pipelines, reduces the risk of collapse and construction difficulty, and improves the quality and safety of blocking.
Smart Images

Figure CN118814728A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of tailings pond flood discharge systems, and in particular relates to a construction method for plugging a tailings pond flood discharge system. Background Art
[0002] For tailings ponds that use drainage wells, drainage pipes, drainage chutes, and drainage pipes for drainage, when the tailings dam is raised and expanded, the structural strength of the original drainage pipes often cannot meet the bearing capacity requirements after the dam is raised. Therefore, when dry storage yards (such as ash yards, tailings ponds, red mud yards, phosphogypsum yards, etc.) reach the designed storage elevation or storage capacity, the flood discharge system needs to be blocked. At present, the flood discharge system is generally blocked by stone blocking and top plate blocking. These technologies have the following main disadvantages:
[0003] In order to save investment during the construction of the current storage yard, the diameter of the flood discharge pipes of most storage yard flood discharge systems is between 1.2m and 1.5m. These flood discharge pipes have small diameters and thin structures, which make it difficult for personnel to enter, and it is even more difficult to transport the plugging materials. Therefore, when using stone blocks to block such flood discharge pipes, it is often only possible to block a small section, and the blocking quality cannot be guaranteed. In addition, there are large gaps between the stone blocks, and after blocking, slurry will still flow out of the flood discharge pipe, polluting the external environment. After blocking, the flood discharge pipe structure is not effectively supported, and there is still a risk of collapse and failure.
[0004] The top plate plugging is generally to set a reinforced concrete top plate plugging at the connection between the drainage shaft (drainage chute) and the drainage pipe. This plugging method only blocks the water inlet, and the plugging process is short, but there is a risk of the plugging top plate breaking in the later stage. Once broken, it will cause more slurry to leak. At present, most of the domestic drainage shafts or chutes were built early, with small structural dimensions and high shaft heights. The reinforced concrete top plate is still being constructed underground, which makes construction difficult and material transportation difficult, and it is easy to cause serious safety accidents during the construction process. Summary of the invention
[0005] In order to solve the problems existing in the existing plugging technology flood discharge system method described in the background technology, the present invention proposes the following technical solutions:
[0006] A construction method for plugging a tailings pond flood discharge system, comprising:
[0007] Pulling the grouting pipe and the drainage pipe from the inlet of the flood discharge pipe to the outlet of the flood discharge pipe;
[0008] Acquiring environmental parameters and dividing the flood discharge pipe into sections;
[0009] Pre-blocking the outlet of the flood discharge pipe and performing grouting operations on the flood discharge pipe in sections;
[0010] After each grouting operation, grouting operation is performed on the flood discharge pipe of the current section.
[0011] When the grouting operation is performed, a plurality of filling pipes having the same length as the flood discharge pipe of the current section need to be installed on the construction surface of the flood discharge pipe of the current section, and a plurality of filling holes are provided on the outer peripheral surface of each filling pipe.
[0012] Furthermore, before pre-sealing the flood discharge pipe, it is necessary to calculate the safe distance between the air supply equipment and the grouting equipment during operation based on the environmental parameters, and install the air supply equipment and the grouting equipment according to the safe distance before each grouting operation.
[0013] Furthermore, the environmental parameters include: air humidity coefficient K, height H from the air outlet to the ground, air outlet width L, outlet pumping pressure P, and pipeline wind speed V.
[0014] Furthermore, the safety distance D1 of the air supply device is obtained by D1=(V2*K*0.16) / (H*L).
[0015] Furthermore, the safety distance D2 of the grouting equipment is obtained by D2={(P-2) / 0.0135}-91.
[0016] Furthermore, after the drainage pipe and the grouting pipe are pulled to the outlet of the flood discharge pipe, the flood discharge pipe is pre-sealed by filling cement slurry in the elastic capsule.
[0017] Furthermore, each time the grouting operation is performed, the pressure of the cement slurry input into the filling pipe is greater than the pressure of the cement slurry input into the construction surface of the corresponding section during the grouting operation.
[0018] Furthermore, before pulling the drainage pipe and the grouting pipe, the flood discharge pipe needs to be desilted.
[0019] Furthermore, the friction force of the elastic capsule is greater than 1.1 times the hydrostatic pressure.
[0020] Beneficial effects: The present invention performs grouting operations on the flood drainage pipe in sections after laying the drainage pipe and performs grouting operations after each grouting is completed, so that the entire flood drainage pipe forms a structure with stable strength after grouting is completed. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 The present invention is a flowchart of a construction method for plugging a tailings pond flood discharge system according to an embodiment of the present invention. DETAILED DESCRIPTION
[0022] In order to make the purpose, technical solution and advantages of the present application clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0023] It should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing this patent and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on this patent.
[0024] Figure 1 The present invention is a flowchart of a construction method for plugging a tailings pond flood discharge system according to an embodiment of the present invention.
[0025] Reference Figure 1 According to an embodiment of the present invention, a construction method for plugging a tailings pond flood discharge system includes:
[0026] S000. Pull the grouting pipe and the drainage pipe from the inlet of the flood discharge pipe to the outlet of the flood discharge pipe.
[0027] Specifically, in this step, the entire flood discharge pipeline needs to be desilted first to prevent the sludge from forming part of the supporting structure after the subsequent grouting, which may cause a gap between the structure formed by the grouting and the flood discharge pipeline after the sludge is washed away. After the desilting is completed, the grouting pipe and the drainage pipe are first pulled from the flood discharge pipeline to the outlet of the flood discharge pipeline by a transportation device (such as a mobile car, etc.). The drainage pipe is used as drainage during the construction operation. The grouting pipe is connected to the grouting equipment and is transferred with the movement of the construction personnel during each grouting operation.
[0028] S010. Acquire environmental parameters and divide the flood discharge pipe into sections.
[0029] In this step, it is necessary to survey the environment in the entire flood discharge pipeline to obtain the corresponding environmental parameters, so as to guide the subsequent construction work. The environmental parameters include but are not limited to: air humidity coefficient K, height H from the air outlet to the ground, width L of the air outlet, outlet pumping pressure P, and total length Z of the flood discharge pipeline.
[0030] In addition, before plugging the flood drainage pipe, the entire flood drainage pipe is divided into sections according to the total length Z of the flood drainage pipe and the solidification time of the cement slurry to avoid the loss of cement slurry during subsequent construction due to the excessive length of the flood drainage pipe.
[0031] S020. Pre-block the outlet of the flood discharge pipe and perform grouting operations on the flood discharge pipe in sections.
[0032] Specifically, in this step, a plug is formed at the outlet of the flood discharge pipe by filling cement slurry in elastic rubber (a cement block formed by solidification of the elastic capsule after the cement slurry is injected). In order to ensure that the plug will not be washed away by the cement slurry injected during the subsequent grouting operation after it is formed, the friction force F of the selected elastic capsule needs to be greater than the pressure T on the plug.
[0033] Among them, F = G*f, T = N*Rd*A / 2. G is the gravity of the rubber, A is the force-bearing area of the rubber, and Rd is the diameter of the flood discharge pipe. Among them, the friction force of the elastic capsule is related to the inherent physical properties of the elastic capsule itself, and can be changed by changing the material of the elastic capsule. In addition, the friction force of the elastic capsule is not only a key parameter for evaluating whether the plug can withstand the hydrostatic pressure of the flood discharge pipe section, but also the basis for adjusting the gradation of the filler in the elastic capsule based on the friction force of the elastic capsule. In this embodiment, the friction force of the elastic capsule needs to be greater than 1.1 times the hydrostatic pressure.
[0034] Since the total length of the flood discharge pipeline is generally more than one kilometer, the air supply equipment and grouting equipment need to maintain a suitable distance from the construction surface for construction. Before each grouting operation, it is necessary to install the grouting equipment and air supply equipment in the flood discharge pipeline according to the safety distance of the grouting equipment and the air supply equipment. Among them, calculated by the collected environmental parameters, the safety distance of the air supply equipment is D1 = (V*K*0.16) / (H*L). In this formula, V is the wind speed of the pipeline wind, K is the air humidity coefficient, H is the height from the air outlet to the ground, and L is the width of the air outlet. The safety distance of the grouting equipment D2 = {(P-2) / 0.0135}-91, P is the outlet pumping pressure.
[0035] In order to control the initial setting time of the cement blocks formed by the grouting operation within 6 hours after the grouting operation of each section is completed, the cement slurry in the grouting equipment is added with a corresponding accelerating setting agent. When the grouting operation is carried out in the flood discharge pipe of each section, a plurality of filling pipes need to be laid on the construction surface of the flood discharge pipe of each section. Each filling pipe is respectively arranged at the edge of the construction surface of the flood discharge pipe of each section, and a plurality of filling holes are arranged on the outer peripheral surface of each filling pipe, so that during the grouting operation, the cement slurry can quickly fill the distance between the flood discharge pipe and the solidified cement blocks.
[0036] S030. After each grouting operation, perform grouting operation on the flood discharge pipe of the current section.
[0037] Specifically, since the cement block will not only shrink in volume after solidification, but may also expand slightly, which will form a narrow gap between the cement block and the inner wall of the flood drainage pipe, further grouting operations need to be performed through a filling pipe after the grouting operation of each section of the flood drainage pipe is completed. The grouting operation uses cement slurry with a pressure greater than that used in the grouting operation. After the cement block formed by the grouting operation solidifies, the narrow gap between the cement block and the flood drainage pipe of the section is filled through the filling pipe, thereby enhancing the structural strength of the entire flood drainage pipe.
[0038] In summary, the present invention performs grouting operations on the flood drainage pipe in sections after laying the drainage pipe and performs grouting operations after each grouting is completed, so that the entire flood drainage pipe forms a structure with stable strength after grouting is completed.
[0039] The foregoing describes certain embodiments of the invention. Other embodiments are within the scope of the following claims.
[0040] The terms "exemplary," "example," and the like used throughout this specification mean "used as an example, instance, or illustration" and do not mean "preferred" or "advantageous" over other embodiments. The detailed description includes specific details for the purpose of providing an understanding of the described techniques. However, these techniques can be implemented without these specific details. In some instances, in order to avoid obscuring the concepts of the described embodiments, well-known structures and devices are shown in block diagram form.
[0041] The optional implementation modes of the embodiments of the present invention are described in detail above in conjunction with the accompanying drawings. However, the embodiments of the present invention are not limited to the specific details in the above implementation modes. Within the technical concept of the embodiments of the present invention, various simple modifications can be made to the technical solutions of the embodiments of the present invention, and these simple modifications all belong to the protection scope of the embodiments of the present invention.
[0042] The above description of the contents of this specification is provided to enable any person of ordinary skill in the art to implement or use the contents of this specification. Various modifications to the contents of this specification will be apparent to those of ordinary skill in the art, and the general principles defined herein may be applied to other variations without departing from the scope of protection of the contents of this specification. Therefore, the contents of this specification are not limited to the examples and designs described herein, but are consistent with the widest range of principles and novel features disclosed herein.
Claims
1. A construction method for plugging a tailings pond flood discharge system, characterized in that: include: Pulling the grouting pipe and the drainage pipe from the inlet of the flood discharge pipe to the outlet of the flood discharge pipe; Acquiring environmental parameters and dividing the flood discharge pipe into sections; Pre-blocking the outlet of the flood discharge pipe and performing grouting operations on the flood discharge pipe in sections; After each grouting operation, grouting operation is performed on the flood discharge pipe of the current section.
2. A construction method for plugging a tailings pond flood discharge system according to claim 1, characterized in that: When performing the grouting operation, it is necessary to install a plurality of filling pipes with the same length as the flood discharge pipe of the current section on the construction surface of the flood discharge pipe of the current section, and the outer peripheral surface of each filling pipe is provided with a plurality of filling holes.
3. A construction method for plugging a tailings pond flood discharge system according to claim 1, characterized in that: Before pre-blocking the flood discharge pipe, it is necessary to calculate the safe distance between the air supply equipment and the grouting equipment during operation according to the environmental parameters, and install the air supply equipment and the grouting equipment according to the safe distance before each grouting operation.
4. A construction method for plugging a tailings pond flood discharge system according to claim 3, characterized in that: The environmental parameters include: air humidity coefficient K, height H from air outlet to the ground, air outlet width L, outlet pumping pressure P, and pipeline wind speed V.
5. A construction method for plugging a tailings pond flood discharge system according to claim 4, characterized in that: The safety distance D1 of the air supply equipment is obtained by D1 = (V2*K*0.16) / (H*L).
6. A construction method for plugging a tailings pond flood discharge system according to claim 5, characterized in that: The safety distance D2 of the grouting equipment is obtained by D2={(P-2) / 0.0135}-91.
7. A construction method for plugging a tailings pond flood discharge system according to claim 3, characterized in that: After the drainage pipe and the grouting pipe are pulled to the outlet of the flood discharge pipe, the flood discharge pipe is pre-blocked by filling cement slurry in the elastic capsule.
8. A construction method for plugging a tailings pond flood discharge system according to claim 7, characterized in that: Each time the grouting operation is performed, the pressure of the cement slurry input into the filling pipe is greater than the pressure of the cement slurry input into the construction surface of the corresponding section during the grouting operation.
9. A construction method for plugging a tailings pond flood discharge system according to claim 8, characterized in that: Before pulling the drainage pipe and the grouting pipe, the flood discharge pipe needs to be desilted.
10. A construction method for plugging a tailings pond flood discharge system according to claim 8, characterized in that: The friction force of the elastic capsule is greater than 1.1 times the hydrostatic pressure.