Earth and stone backfilling method for vehicle base maintenance warehouse

By backfilling the cap gap in front of the vehicle base maintenance warehouse and reserving a width structure to form a backfill path, and using large machinery to backfill earth and stone, the problem of long longitudinal transportation lines and cap gap limitations has been solved, construction efficiency and backfilling speed have been improved, and the cost has been reduced. cost.

CN118814822APending Publication Date: 2024-10-22CHINA CONSTR EIGHTH BUREAU RAIL TRANSIT CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411151014.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-21
Publication Date
2024-10-22

AI Technical Summary

Technical Problem

The vehicle base maintenance warehouse has long longitudinal transportation lines, slow backfilling speed, and the gap between the platform and the platform limits the passage of small tricycles, affecting construction efficiency.

Method used

Before the construction of the maintenance pit, backfill the cap gap, reserve a width structure to form a backfill path, and use large transport vehicles and excavators to backfill earth and stone to ensure the width of the backfill path and smooth access.

Benefits of technology

The construction efficiency is improved, the construction period is shortened, the cost is reduced, and efficient earth and stone backfilling is achieved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118814822A_ABST
    Figure CN118814822A_ABST
Patent Text Reader

Abstract

The invention relates to a vehicle base maintenance warehouse earthwork backfilling method which comprises the following steps that before a maintenance pit is constructed, earthwork backfilling is conducted on a bearing platform gap near the construction position of the maintenance pit to form a first soil filling layer; when the maintenance pit is constructed, a structure with a set width is reserved in each section of construction area for post-pouring, so that a backfilling path is formed; and after construction of the maintenance pit is completed, earth and stone backfilling is conducted on the outer side of the maintenance pit through the backfilling path. According to the method, the gap of the bearing platform is backfilled before the maintenance pit is constructed, and large machines and excavators can be adopted for backfilling operation due to no limitation of the maintenance pit structure during backfilling, so that the construction efficiency can be greatly improved. And during construction of the overhaul pit, a certain width structure is reserved for each section and then is poured, so that a backfilling path is formed to backfill earth and stone of the overhaul pit, and the problem that the longitudinal backfilling path is far is solved. The backfilling method has the advantages of being high in construction efficiency, low in cost and short in construction period.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of foundation pit backfilling construction engineering, in particular to an earth and stone backfilling method for a vehicle base maintenance depot. Background Art

[0002] The vehicle base maintenance warehouse occupies a large area. After the structural construction is completed, there is a lot of earth and stone backfilling work. There are rows of maintenance pits in the vehicle base in the vertical direction, and the distance between the maintenance pits is 3 meters. If the maintenance pit structure is constructed by backfilling first and then excavating, most of the earth in the backfilled area will be excavated again, increasing the workload of backfilling and excavation, and increasing the cost. Therefore, the maintenance pit structure is constructed first and then the earth and stone are backfilled, but this method will have the following problems: 1. The distance between the maintenance pits is small, and only small tricycles can be used to enter, and the longitudinal transportation route is long, and the backfilling speed is slow. 2. There is a gap between the pedestals next to the maintenance pit, which makes it impossible for the small tricycle to pass through the gap. The gap between the pedestals needs to be backfilled before the backfill channel can be opened smoothly, affecting the construction efficiency. Summary of the invention

[0003] The purpose of the present invention is to overcome the defects of the prior art and provide a method for backfilling earth and stone in a vehicle base maintenance depot, so as to solve the problems existing in the backfilling of earth and stone in the maintenance pit, such as long longitudinal transportation line, slow backfilling speed, and the existence of pedestal gaps beside the maintenance pit, which makes it impossible for small tricycles to pass through and thus requires backfilling the pedestal gaps first to open the backfill channel, thus affecting the construction efficiency.

[0004] The technical solution to achieve the above purpose is:

[0005] The present invention provides a method for backfilling earth and stone in a vehicle base maintenance depot, comprising the following steps:

[0006] Before constructing the maintenance pit, the gap between the caps near the construction location of the maintenance pit is backfilled with earth and stone to form the first fill layer;

[0007] When constructing the inspection pit, a structure of set width is reserved in each construction area for post-casting, thus forming a backfill path;

[0008] After the construction of the maintenance pit is completed, the backfill path is used to backfill earth and stone on the outside of the maintenance pit.

[0009] A further improvement of the earth and stone backfilling method for a vehicle base maintenance depot of the present invention is that when the earth and stone backfilling is performed on the outer side of the maintenance pit using the backfilling path, the earth and stone backfilling is performed to the left and right sides through the backfilling path.

[0010] A further improvement of the earth and stone backfilling method of the vehicle base maintenance depot of the present invention is that when the earth and stone backfilling of the gap between the caps near the construction position of the maintenance pit forms the first filling layer, a large transport vehicle and an excavator are used for the backfilling operation.

[0011] A further improvement of the earth and stone backfilling method of the vehicle base maintenance depot of the present invention is that the reserved set width of the backfill path is 2.5m to 3.5m.

[0012] A further improvement of the earth and stone backfilling method of the vehicle base maintenance depot of the present invention is that the backfilling path is arranged in the width direction of the vehicle foundation pit maintenance depot.

[0013] A further improvement of the earth and stone backfilling method of the vehicle base maintenance depot of the present invention is that the first filling layer and the corresponding top surface of the foundation are used as a mechanical transportation channel.

[0014] The beneficial effects of the earth and stone backfilling method of the vehicle base maintenance depot of the present invention are:

[0015] The present invention backfills the gap between the caps before the construction of the inspection pit. During the backfilling, large machinery and excavators can be used for the backfilling operation because there is no restriction on the inspection pit structure, which can greatly improve the construction efficiency.

[0016] The present invention reserves a certain width for each section of the structure during the construction of the maintenance pit and then casts it, thereby forming a backfill path for backfilling the earth and stone of the maintenance pit, thereby solving the problem of a long vertical backfill path.

[0017] The backfilling method of the present invention has the advantages of high construction efficiency, low cost and short construction period. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 The present invention is a schematic structural diagram of a backfilling path reserved for a manhole in the earth and stone backfilling method for a vehicle base maintenance depot.

[0019] Figure 2 It is a structural schematic diagram of the earth and stone backfilling route in the earth and stone backfilling method of the vehicle base maintenance depot of the present invention. DETAILED DESCRIPTION

[0020] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

[0021] See also Figure 1The present invention provides a method for backfilling earth and stone in a vehicle base maintenance depot, which is used to solve the problem that the existing method of first constructing the maintenance pit structure and then backfilling the earth and stone is that the distance between the maintenance pits can only allow small tricycles to enter, the longitudinal transportation path is long, and the backfilling speed is slow. It is also used to solve the problem that there is a gap between the pedestals next to the maintenance pit, which makes it impossible for small tricycles to pass through the gap between the pedestals, so it is necessary to backfill the gap between the pedestals before the backfill channel can be smoothly opened, which affects the construction efficiency. The backfilling method of the present invention uses a large transport vehicle and an excavator to backfill the gap between the pedestals before the construction of the maintenance pit. Since there is no limitation of the maintenance pit at this time, large machinery can be used, which can greatly improve the efficiency. When constructing the maintenance pit, each section is reserved for about 3m of structure and then poured, which is used as the backfill path for the maintenance depot to backfill earth and stone on the left and right sides, solving the problem of the long longitudinal backfill path and improving the backfilling speed. The method for backfilling earth and stone in the vehicle base maintenance depot of the present invention is described below in conjunction with the accompanying drawings.

[0022] See also Figure 1 , showing a schematic diagram of the structure of the reserved backfill path of the manhole in the earthwork backfilling method of the vehicle base maintenance depot of the present invention. Figure 2 , showing the structural schematic diagram of the earthwork backfilling route in the earthwork backfilling method of the vehicle base maintenance depot of the present invention. Figure 1 and Figure 2 , the foundation pit combined supporting structure of the present invention is described.

[0023] like Figure 1 and Figure 2 As shown, the earth and stone backfilling method of the vehicle base maintenance depot of the present invention comprises the following steps:

[0024] Before constructing the maintenance pit 11, the gap between the caps near the construction location of the maintenance pit is backfilled with earth and stone to form a first filling layer;

[0025] When constructing the inspection pit 11, a structure of a set width is reserved in each construction area for post-casting, thereby forming a backfill path 21;

[0026] After the construction of the maintenance pit is completed, the outer side of the maintenance pit 11 is backfilled with earth and stone using the backfill path 21 .

[0027] The present invention provides a backfill path (that is, a reserved channel) to backfill the gap between the caps before the construction of the maintenance pit, thereby providing convenient conditions for backfilling earth and stone in the vehicle foundation pit maintenance depot, and being highly efficient and economical.

[0028] In a specific implementation of the present invention, when backfilling the outer side of the maintenance pit with earth and stone, backfilling the earth and stone to the left and right areas through the backfilling path.

[0029] Furthermore, the first fill layer and the corresponding top surface of the foundation are used as mechanical transportation channels.

[0030] like Figure 2 As shown, the transport vehicle can first walk along the backfill path and then turn to the mechanical transport channel on the left or right to complete the backfill operation of the corresponding backfill area.

[0031] In a specific implementation of the present invention, when backfilling the gap between the caps near the construction location of the maintenance pit to form the first fill layer, a large transport vehicle and an excavator are used to perform the backfilling operation.

[0032] In a specific implementation of the present invention, the set width reserved for the backfill path is 2.5m to 3.5m. Preferably, the set width reserved for the backfill path is 3m.

[0033] In a specific embodiment of the present invention, the backfill path is arranged in the width direction of the vehicle pit maintenance garage. The width direction can also be called the transverse direction. The maintenance pits are arranged in rows in the longitudinal direction of the vehicle base, and the distance between the maintenance pits is 3m.

[0034] In the present invention, the space before the construction of the maintenance pit is backfilled by using a large transport vehicle and an excavator to fill the gap between the caps. At this time, large machinery can be used without the limitation of the maintenance pit, which greatly improves the efficiency.

[0035] During the construction of the maintenance pit of the present invention, a 3m structure is reserved for each section for later pouring, and this is used as the earthwork path of the maintenance pit for earthwork backfilling on the left and right sides, which solves the problem of long longitudinal backfilling path and improves the backfilling speed. Figure 1 As shown, a horizontal backfill path is reserved, shortening the original backfill path of the right longitudinal transportation. Figure 2 The figure shows the route of the transport vehicle after it passes through the reserved backfill path.

[0036] The present invention is described in detail above in conjunction with the embodiments of the accompanying drawings. A person skilled in the art can make various variations of the present invention according to the above description. Therefore, certain details in the embodiments should not constitute a limitation of the present invention, and the scope of protection of the present invention shall be defined by the scope of the attached claims.

Claims

1. A method for backfilling earth and stone in a vehicle base maintenance depot. It is characterized in that The steps include: Before constructing the maintenance pit, the gap between the caps near the construction location of the maintenance pit is backfilled with earth and stone to form the first fill layer; When constructing the inspection pit, a structure of set width is reserved in each construction area for post-casting, thus forming a backfill path; After the construction of the maintenance pit is completed, the backfill path is used to backfill earth and stone on the outside of the maintenance pit.

2. The method for backfilling earth and stone in a vehicle base maintenance depot according to claim 1, It is characterized in that When the backfill path is used to backfill the outer side of the maintenance pit with earth and stone, the backfill is carried out to the left and right sides through the backfill path.

3. The method for backfilling earth and stone in a vehicle base maintenance depot according to claim 1, It is characterized in that When backfilling the foundation gap near the construction location of the maintenance pit to form the first fill layer, large transport vehicles and excavators are used for backfilling operations.

4. The method for backfilling earth and stone in a vehicle base maintenance depot according to claim 1, It is characterized in that The reserved width of the backfill path is set to 2.5m to 3.5m.

5. The method for backfilling earth and stone in a vehicle base maintenance depot according to claim 1, It is characterized in that The backfill path is arranged in the width direction of the vehicle foundation pit maintenance depot.

6. The method for backfilling earth and stone in a vehicle base maintenance depot according to claim 1, It is characterized in that The first fill layer and the corresponding top surface of the foundation are used as a mechanical transportation channel.