Highway tunnel disease inverted arch treatment construction method
By using prefabricated arch transfer yard and support leveling device in the treatment of highway tunnel disease arches, the continuous laying and early opening of prefabricated arches are achieved, the problems of low construction efficiency and poor quality are solved, and the construction efficiency and Security.
Patent Information
- Application Number
- CN202410997833.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-24
- Publication Date
- 2024-11-05
AI Technical Summary
The construction process in the highway tunnel disease arch control project is complicated, resulting in low construction efficiency and poor quality, and difficult adjustment after prefabricated arch laying, resulting in traffic jams and affecting traffic safety.
The prefabricated arch transfer field and support leveling device are adopted. Through the hoisting and continuous cross-parallel operation of the prefabricated arch paving platform, combined with the leveling function of the support leveling device, the continuous laying of the prefabricated arch and the early opening of traffic is achieved.
The construction efficiency and quality of disease arch control has been improved, the construction cycle has been shortened, the jams have been reduced, and the early opening of traffic has been achieved, which has improved construction safety and efficiency.
Smart Images

Figure CN118895980A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of highway tunnel invert construction, in particular to a highway tunnel diseased invert treatment construction method. Background Art
[0002] As a hidden project in the mountain, highway tunnels are subject to complex geological structure of the roadbed, design and construction quality of the invert structure, etc., which may cause tunnel structure instability, road surface settlement and cracking, and mud and slurry. These problems pose a huge safety hazard to traffic safety.
[0003] In the treatment of damaged inverts in highway tunnels, the construction process and method of excavating the invert layer in the diseased area, tying steel bars on site and pouring concrete is usually adopted. This traditional method has problems such as long concrete curing period, unstable construction quality affected by external factors such as the environment, low efficiency due to the inability to cross-operate, and affecting traffic time. The construction of prefabricated inverts adopts the method of prefabricating the inverts first and then transporting the prefabricated inverts to the site for paving. This construction method has the advantages of reliable quality of prefabricated inverts, fast construction of prefabricated inverts, cross-construction of multiple construction operations, little impact on the tunnel environment, short maintenance period, and controllable costs. At present, the construction of prefabricated inverts has become an important development direction.
[0004] In the treatment of defective inverts in highway tunnels, the following problems and challenges still exist: In the treatment of defective inverts in highway tunnels, due to the complicated construction process, a process-based operation mode is usually adopted. There are time bottlenecks in single construction links such as the excavation of the pavement and the invert layer, which results in a long process-based construction operation time. In addition, after the prefabricated invert is paved, the supporting stratum of the invert needs to be grouting treated, which requires a certain amount of curing time after grouting and is not able to bear loads immediately, resulting in low construction efficiency. The prefabricated invert is difficult to adjust after laying, and the construction quality is poor. Summary of the invention
[0005] In order to solve the above problems, the present invention provides a construction method for treating diseased inverts in highway tunnels, thereby improving the construction efficiency and quality of treating diseased inverts and reducing traffic congestion points.
[0006] In order to achieve the above object, the technical solution adopted by the present invention is:
[0007] The invention discloses a construction method for treating a damaged invert in a highway tunnel, comprising the following steps:
[0008] S1. Setting a prefabricated invert transfer yard near the tunnel entrance, and designing and manufacturing prefabricated inverts at the prefabricated invert transfer yard;
[0009] S2. Cut and clean the diseased invert area;
[0010] S3, installing a support and leveling device on the cleared invert foundation layer;
[0011] S4, assembling and debugging the prefabricated inverted arch track laying platform, sending the debugged prefabricated inverted arch track laying platform into the tunnel, and moving the prefabricated inverted arch track laying platform to a designated track laying station close to the inverted arch foundation layer;
[0012] S5. The special flat car for transporting the inverted arch transports the prefabricated inverted arch to the bottom of the prefabricated inverted arch laying platform;
[0013] S6. The prefabricated invert laying platform hoists the prefabricated invert on the invert foundation layer, and the invert transport special flat car exits the tunnel to transport the next prefabricated invert;
[0014] S7, repeat steps S5 and S6 to complete the installation of the next prefabricated invert;
[0015] S8, adjacent prefabricated inverts are connected and the bottom gap is grouting;
[0016] S9, road surface leveling.
[0017] Furthermore, operations such as cutting of diseased pavement, excavation of pavement concrete layer, excavation of invert layer, removal of debris, shaping of invert foundation layer and passage of vehicles are arranged on the tunnel exit side, and operations such as invert transportation, invert transfer, invert paving, invert connection, grouting and post-processing and passage of vehicles are arranged on the tunnel entrance side.
[0018] Furthermore, the prefabricated arch laying platform includes a platform frame, the platform frame is provided with a lifting mechanism and a supporting mechanism, the supporting mechanism includes a front leg telescopic support, a middle leg wheel and a rear leg wheel telescopic support, the two rear leg wheel telescopic supports are relatively fixedly arranged at the rear end of the platform frame, the two front leg telescopic supports are relatively fixedly arranged at the front end of the platform frame, the middle leg wheel is movably arranged between the front leg telescopic support and the rear leg wheel telescopic support, and the platform frame is provided with a middle leg wheel locking mechanism for locking the middle leg wheel.
[0019] Furthermore, the platform frame includes a rear crossbeam, a front crossbeam and a guide beam, the rear crossbeam and the front crossbeam are arranged opposite to each other, the four guide beams are fixedly arranged between the rear crossbeam and the front crossbeam at intervals, the two rear leg wheel telescopic supports are relatively fixedly arranged at the two ends of the rear crossbeam, the two front leg telescopic supports are relatively fixedly arranged at the two ends of the front crossbeam, and the middle leg wheel is movably arranged on the guide beam.
[0020] Furthermore, the lifting mechanism includes a moving trolley, a driving motor for driving the moving trolley to move, and a chain hoist hook, the driving motor is arranged on the moving trolley, the driving motor is drivingly connected to the wheels of the moving trolley, the chain hoist hook is arranged below the moving trolley, a moving trolley guide rail is arranged at the top of the guide beam along its length direction, the wheels of the moving trolley move along the length direction of the moving trolley guide rail, and a moving trolley locking mechanism for locking the moving trolley is arranged at a position of the guide beam close to the rear cross beam.
[0021] Furthermore, the rear leg wheel telescopic support includes a rear supporting leg, a rear leg supporting platform, a rear leg cylinder, a rear leg supporting base, a rear leg driving wheel group and a rear leg driven wheel group. The rear supporting leg is fixedly arranged below the rear cross beam, the rear leg supporting platform is fixedly arranged below the rear supporting leg, the base of the rear leg cylinder is fixedly arranged below the rear leg supporting platform, the rear leg supporting base is fixedly arranged on the piston rod of the rear leg cylinder, the rear leg driving wheel group and the rear leg driven wheel group are arranged below the rear leg supporting platform, and the rear leg driving wheel group is provided with a hydraulic motor.
[0022] Furthermore, the middle leg wheel includes a middle support leg, a middle leg support platform, a middle leg driving wheel group and a middle leg driven wheel group, the middle support leg is movably arranged on the side wall of the guide beam, the middle leg support platform is fixedly arranged below the middle support leg, the middle leg driving wheel group and the middle leg driven wheel group are fixedly arranged below the middle leg support platform, the middle leg driving wheel group is provided with the hydraulic motor, the two side walls at the lower end of the guide beam are provided with relative wing plates along the length direction of the guide beam, the wing plates are arranged perpendicular to the side walls of the guide beam, the lower end of the guide beam is provided with a concave middle leg moving driving wheel mounting frame, the middle leg wheel is arranged at the lower end of the middle leg moving driving wheel mounting frame, the middle leg moving driving wheel mounting frame is clamped at the lower end of the guide beam, the inner side wall of the middle leg moving driving wheel mounting frame is relatively provided with a middle leg moving driving wheel, the middle leg moving driving wheel moves along the corresponding wing plate, and the outer side wall of the middle leg moving driving wheel mounting frame is provided with a middle leg moving motor for driving the middle leg moving driving wheel to move.
[0023] Furthermore, the front leg telescopic support includes a front supporting leg, a front leg cylinder, and a front leg supporting base. The front supporting leg is fixedly arranged below the front cross beam, the base of the front leg cylinder is fixedly arranged below the front supporting leg, and the front leg supporting base is fixedly arranged on the piston rod of the front leg cylinder.
[0024] Furthermore, the support and leveling device includes a support pad and a fixed anchor, the upper end of the support pad cooperates with the lower end surface of the prefabricated invert arch, the support pad is provided with a fixed anchor hole that cooperates with the fixed anchor, the fixed anchor is passed through the fixed anchor hole, and the upper end of the support pad is provided with a leveling reference platform, and the leveling reference platform is provided with a spirit level and a laser rangefinder.
[0025] Furthermore, jacks are arranged at intervals on both side ends of the prefabricated inverted arch, channel steels are arranged along the arch feet of the upper lining, the prefabricated inverted arch is hoisted on the supporting and leveling device, and the piston rod of the jack is arranged opposite to the channel steel.
[0026] The beneficial effects of the present invention are as follows: a construction method for treating a defective inverted arch in a highway tunnel of the present invention is used for treating a defective inverted arch in a tunnel, and the processes of prefabricated inverted arch transportation, prefabricated inverted arch laying platform hoisting the prefabricated inverted arch, support leveling device leveling, defective inverted arch area cutting and cleaning, prefabricated inverted arch connection, and bottom layer gap grouting are coordinated and continuously cross-operated in parallel, thereby reducing time bottlenecks, shortening the construction period, and improving the construction efficiency of treating a defective inverted arch; after each support leveling device is leveled, the support leveling device keeps the prefabricated inverted arch hoisted thereon at the same horizontal height, thereby improving Improve construction quality; hoist the prefabricated invert on the supporting pad, which effectively supports the prefabricated invert, and continue to lay the next prefabricated invert, so as to realize the continuous laying operation of the prefabricated invert. At the same time, the prefabricated invert keeps the same horizontal height, and there is no need to adjust the level and height of the prefabricated invert, thereby improving the installation construction efficiency of the prefabricated invert, and then improving the construction efficiency of the diseased invert treatment; hoist the prefabricated invert on the supporting pad, which effectively supports the prefabricated invert, and can bear the load after grouting, thereby reducing traffic congestion and realizing early opening to traffic. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0028] Figure 1 It is a flow chart of a construction method for treating a damaged invert in a highway tunnel provided by an embodiment of the present invention;
[0029] Figure 2 It is a structural schematic diagram of a prefabricated invert laying platform for a highway tunnel provided by an embodiment of the present invention;
[0030] Figure 3 It is a front view of a prefabricated inverted arch laying platform for a highway tunnel provided by an embodiment of the present invention;
[0031] Figure 4 It is a front view of a special flat car for transporting an inverted arch provided by an embodiment of the present invention, which transports the inverted arch to a loading and unloading lifting station below a prefabricated inverted arch laying platform;
[0032] Figure 5 is a front view of a prefabricated invert provided by an embodiment of the present invention after rotation;
[0033] Figure 6 It is a front view of the prefabricated invert provided by the embodiment of the present invention being hoisted to the top of the installation station;
[0034] Figure 7 It is a side view of a prefabricated invert provided by an embodiment of the present invention being hoisted to a position directly above the installation station;
[0035] Figure 8 is a front view of a prefabricated invert provided by an embodiment of the present invention being installed at an installation station;
[0036] Fig. 9 is a side view of a prefabricated invert provided by an embodiment of the present invention being installed at an installation station;
[0037] Fig.10 It is a structural schematic diagram of a highway tunnel prefabricated invert laying platform with a track clamp provided by an embodiment of the present invention;
[0038] Fig.11 is an enlarged view of a middle leg mobile driving wheel mounting frame provided by an embodiment of the present invention;
[0039] Fig.12 It is a flow chart of a method for constructing a prefabricated invert in a highway tunnel provided by an embodiment of the present invention;
[0040] Fig.13 is a front view of a prefabricated invert provided by an embodiment of the present invention being hoisted on a supporting pad;
[0041] Fig.14 is a front view of a support pad provided by an embodiment of the present invention;
[0042] Fig.15 is a cross-sectional view of a support pad provided by an embodiment of the present invention;
[0043] Fig.16 is a top view of a support pad provided by an embodiment of the present invention;
[0044] Fig.17 is a front view of the connection between the prefabricated invert and the upper lining provided by an embodiment of the present invention;
[0045] Fig.18 It is a schematic diagram of the connection of a prefabricated invert, a jack, a channel steel and an upper lining provided in an embodiment of the present invention.
[0046] Figure numerals: rear cross beam 1, locking pin hole 101, mobile trolley 2, guide beam 3, mobile trolley guide rail 4, front cross beam 5, front leg telescopic support 6, front support leg 601, front leg cylinder 602, front leg support base 603, middle leg wheel locking mechanism 7, middle leg mobile driving wheel mounting frame 8, middle leg mobile driving wheel 9, middle leg mobile motor 10, middle leg wheel 11, middle support leg 1101, middle leg support platform 1102, middle leg driving wheel group 1103, middle leg hydraulic station 1104, middle leg driven wheel group 1105, wing plate 12, rear leg wheel telescopic support 13, rear support leg 1301, rear Leg support platform 1302, rear leg driving wheel group 1303, rear leg cylinder 1304, rear leg support base 1305, rear leg driven wheel group 1306, control cabinet 14, driver's cab 15, electrical cabinet 16, hydraulic station 17, chain hoist hook 18, special flat car for arch transportation 19, prefabricated arch 20, rail clamp 21, locking pin telescopic cylinder 22, locking pin 23, middle leg moving guide wheel installation distance adjustment part 24, middle leg moving guide wheel 25, chain 26, upper lining 27, channel steel 28, jack 29, support pad 30, fixed anchor 31, leveling reference platform 32. DETAILED DESCRIPTION
[0047] To make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be described in detail below. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other implementation methods obtained by ordinary technicians in this field without creative work belong to the scope of protection of the present invention.
[0048] The present invention is further described below in conjunction with the accompanying drawings and embodiments.
[0049] like Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 , Figure 6 , Figure 7 , Figure 8 , Fig. 9 , Fig.10 , Fig.11 , Fig.12 , Fig.13 , Fig.14 , Fig.15 , Fig.16 , Fig.17 , Fig.18 As shown, this embodiment provides a construction method for treating a damaged invert in a highway tunnel, comprising the following steps:
[0050] S1, setting up a prefabricated inverted arch transfer yard near the tunnel entrance, designing and manufacturing the prefabricated inverted arch 20 at the prefabricated inverted arch transfer yard, or transferring the prefabricated inverted arch produced at other inverted arch prefabrication yards to the prefabricated inverted arch transfer yard for transit storage;
[0051] S2. Cut and clean the diseased invert area;
[0052] S3, installing a support and leveling device on the cleared invert foundation layer;
[0053] S4, assembling and debugging the prefabricated inverted arch track laying platform, sending the debugged prefabricated inverted arch track laying platform into the tunnel, and moving the prefabricated inverted arch track laying platform to a designated track laying station close to the inverted arch foundation layer;
[0054] S5, transporting the prefabricated inverted arch 20 to the bottom of the prefabricated inverted arch laying platform by using the special flat car 19 for inverted arch transportation;
[0055] S6, controlling the prefabricated inverted arch laying platform to hoist the prefabricated inverted arch 20 on the inverted arch foundation layer, and withdrawing the inverted arch transportation special flat car 19 from the tunnel to transport the next prefabricated inverted arch 20;
[0056] S7, repeat steps S5 and S6 to complete the hoisting of the next prefabricated invert 20;
[0057] S8, connecting adjacent prefabricated inverts 20 and grouting the bottom gap;
[0058] S9, road surface leveling.
[0059] The above-mentioned highway tunnel diseased inverted arch treatment construction method is adopted for tunnel diseased inverted arch treatment, and the measurement before construction and the organization and preparation of construction equipment are completed. The treatment of highway tunnel diseased inverted arch is completed through the steps of S1 setting a prefabricated inverted arch transfer yard - S2 cutting and cleaning the diseased inverted arch area - S3 installing a support and leveling device - S4 assembling and debugging a prefabricated inverted arch laying platform - S5 transporting a prefabricated inverted arch 20 by a special flat car 19 for inverted arch transportation - S6 hoisting the prefabricated inverted arch 20 by the prefabricated inverted arch laying platform, and transporting the next prefabricated inverted arch by the special flat car 19 for inverted arch transportation - S7 repeating steps S5 and S6-S8 connecting the prefabricated inverted arch bottom layer grouting - S9-road surface leveling treatment, and the treatment of highway tunnel diseased inverted arch is completed. The treatment of tunnel diseased inverted arch includes the transportation of prefabricated inverted arch 20, hoisting of the prefabricated inverted arch 20 by the prefabricated inverted arch laying platform, leveling of the support and leveling device, cutting and cleaning of the diseased inverted arch area, connection of the prefabricated inverted arch 20, grouting of the bottom layer gap The grouting processes are coordinated and operated in parallel, which reduces time bottlenecks, shortens the construction period, and improves the construction efficiency of the diseased inverted arch treatment. After each support leveling device is leveled, the support leveling device keeps the prefabricated inverted arch 20 hoisted thereon at the same horizontal height, thereby improving the construction quality. The prefabricated inverted arch 20 is hoisted on the support pad 30, and the support pad 30 forms an effective support for the prefabricated inverted arch 20. The next prefabricated inverted arch 20 is continued to be laid, which can realize the continuous laying operation of the prefabricated inverted arch 20. At the same time, the prefabricated inverted arch 20 maintains the same horizontal height, and there is no need to adjust the level and height of the prefabricated inverted arch 20, thereby improving the installation construction efficiency of the prefabricated inverted arch 20, and then improving the construction efficiency of the diseased inverted arch treatment. The prefabricated inverted arch 20 is hoisted on the support pad 30, and the support pad 30 forms an effective support for the prefabricated inverted arch 20. After grouting, it can bear the load, which reduces traffic bottlenecks and realizes early opening to traffic. During the construction process of the treatment of the diseased inverted arch of a highway tunnel, the treatment of the diseased inverted arch of a highway tunnel can be divided into five main construction operation modules, namely, the design, manufacture and transportation of the prefabricated inverted arch 20, the transportation of the prefabricated inverted arch 20, the laying of the prefabricated inverted arch 20, the excavation and shaping of the pavement and inverted arch foundation layer, and the connection grouting and post-processing of the prefabricated inverted arch 20. Each construction operation module performs cyclic parallel operations respectively, which improves the construction efficiency of the treatment of the diseased inverted arch, shortens the construction time and reduces the construction cost. The cutting of the diseased pavement, the excavation and removal of the pavement and concrete layer are separated and operated first, and the subsequent excavation of the inverted arch foundation layer and the removal of slag, and the shaping and laying of the inverted arch foundation layer are carried out in parallel, which can greatly reduce the time required for the excavation operation, thereby effectively solving the problem of the blockage point where the excavation operation takes a long time.The transfer and rotation operations of the prefabricated inverted arch 20 are realized by the special flat car 19 for transferring the inverted arch. After the prefabricated inverted arch transfer yard is set up, the transportation distance from the prefabricated inverted arch transfer yard to the hoisting and unloading position of the prefabricated inverted arch 20 is relatively short, and the transfer time is short and controllable. By driving the turntable of the special flat car 19 for transferring the inverted arch, the rotation of the prefabricated inverted arch 20 in the tunnel can be realized. The rotation of the prefabricated inverted arch 20 and the motion control action of the moving trolley above the prefabricated inverted arch laying platform can be carried out alternately, which solves the risk that the rotation operation and the laying operation of the prefabricated inverted arch laying platform are time-consuming and restricted by the tunnel limit conditions.
[0060] Among them, the cutting of diseased pavement, excavation of pavement concrete layer, excavation of invert layer, removal of slag, repair of invert foundation layer and vehicle passage are arranged on the exit side of the tunnel portal, and the prefabricated invert transfer yard, prefabricated invert laying platform and prefabricated invert 20 connection, grouting and subsequent pavement leveling treatment operations and vehicle passage are arranged on the entrance side of the tunnel portal.
[0061] Using a one-way operation mode, different construction processes are distributed in the entrance and exit areas along the tunnel construction line with the invert laying construction point as the boundary. This not only solves the problem of mutual interference between different operating equipment or vehicles under limited space conditions in the tunnel, but also ensures construction safety and quality.
[0062] A clustered operation mode of construction machinery is adopted, and construction machinery is used for pavement cutting, excavation of pavement concrete layer, excavation of invert layer, removal of debris, shaping of invert foundation layer, transportation and loading and unloading of invert, and paving of invert, etc., which not only greatly shortens the time of each construction operation, but also the effective construction organization management and reasonable use of special construction machinery after the separation of construction processes also effectively ensure construction safety and quality.
[0063] As an implementation method, Figure 2 As shown, the prefabricated arch laying platform includes a platform frame, and the platform frame is provided with a lifting mechanism and a supporting mechanism. The supporting mechanism includes a front leg telescopic support 6, a middle leg wheel 11 and a rear leg wheel telescopic support 13. The two rear leg wheel telescopic supports 13 are relatively fixedly arranged at the rear end of the platform frame, and the two front leg telescopic supports 6 are relatively fixedly arranged at the front end of the platform frame. The middle leg wheel 11 is movably arranged between the front leg telescopic support 6 and the rear leg wheel telescopic support 13. The platform frame is provided with a middle leg wheel locking mechanism 7 for locking the middle leg wheel 11.
[0064] A movable middle leg structure is adopted. During the movement of the prefabricated inverted arch laying platform, the middle leg wheel locking mechanism 7 is locked, the front leg telescopic support 6 is retracted and suspended in the air, and the wheels of the middle leg wheel 11 and the rear leg wheel telescopic support 13 are supported on the tunnel pavement, driving the prefabricated inverted arch laying platform to move forward; after the prefabricated inverted arch laying platform arrives at the designated laying station, the supporting bases of the front leg telescopic support 6 and the rear leg wheel telescopic support 13 are extended and supported on the tunnel pavement, the lower parts of the wheels of the middle leg wheel 11 and the rear leg wheel telescopic support 13 are suspended in the air, and the middle leg wheel locking mechanism 7 is unlocked, so that the middle leg wheel 11 moves along the platform frame toward the rear leg wheel telescopic support 13, and the middle leg wheel 11 moves along the platform frame to a position near the rear leg wheel telescopic support 13, making room for the rotation and lifting of the prefabricated inverted arch 20, ensuring that the prefabricated inverted arch 20 with large size and large tonnage can be rotated and hoisted in a limited space tunnel, so as to facilitate the fast and convenient installation of the prefabricated inverted arch 20 with large size and large tonnage in the tunnel. After the installation of the prefabricated inverted arch 20 at the track laying station is completed, the prefabricated inverted arch 20 entering the next track laying station is hoisted and installed, so that the middle leg wheel 11 moves along the platform frame toward the front leg telescopic support 6, and is locked at the middle leg wheel locking mechanism 7. The supporting bases of the front leg telescopic support 6 and the rear leg wheel telescopic support 13 are retracted and suspended in the air, and the wheel supports of the middle leg wheel 11 and the rear leg wheel telescopic support 13 are on the tunnel pavement, driving the prefabricated inverted arch track laying platform to move to the next track laying station, which is very convenient.
[0065] As an implementation method, Figure 2 As shown, the platform frame includes a rear cross beam 1, a front cross beam 5 and a guide beam 3. The rear cross beam 1 and the front cross beam 5 are arranged opposite to each other. The four guide beams 3 are fixedly arranged between the rear cross beam 1 and the front cross beam 5 at intervals. The two rear leg wheel telescopic supports 13 are relatively fixedly arranged at the two ends of the rear cross beam 1. The two front leg telescopic supports 6 are relatively fixedly arranged at the two ends of the front cross beam 5. The middle leg wheel 11 is movably arranged on the guide beam 3.
[0066] Four guide beams 3 are fixed at intervals between the rear cross beam 1 and the front cross beam 5 to form a rectangular prefabricated inverted arch laying platform, which is adapted to the highway tunnel and is easy to move in the highway tunnel. The four guide beams 3 are divided into two groups of two, and the spacing between the two guide beams 3 in each group is adapted to the width of the mobile trolley 2, so as to ensure that the wheels on both sides of the mobile trolley 2 move on the two guide beams 3. The rear cross beam 1, the front cross beam 5 and the guide beam 3 can be made of welded steel, and the rear cross beam 1, the front cross beam 5 and the guide beam 3 can be connected by high-strength bolts, and reinforcing ribs are welded at the connection.
[0067] As an implementation method, Figure 2 , Figure 3 , Fig.10As shown, the lifting mechanism includes a moving trolley 2, a driving motor for driving the moving trolley 2 to move, and a chain hoist hook 18, the driving motor is arranged on the moving trolley 2, the driving motor is drivingly connected to the wheels of the moving trolley 2, the chain hoist hook 18 is arranged below the moving trolley 2, a moving trolley guide rail 4 is arranged at the top of the guide beam 3 along its length direction, the wheels of the moving trolley 2 move along the length direction of the moving trolley guide rail 4, and a moving trolley locking mechanism for locking the moving trolley 2 is arranged at a position of the guide beam 3 close to the rear cross beam 1.
[0068] The mobile trolley 2 moves back and forth along the mobile trolley guide rail 4 on the guide beam 3 under the drive of the driving motor, and cooperates with the chain hoist hook 18 below the mobile trolley 2 to move, hoist and transport the prefabricated inverted arch 20. The number of mobile trolleys 2 is two or four. If the number of mobile trolleys 2 is four, the four mobile trolleys 2 are divided into two groups of two. One group of mobile trolleys 2 corresponds to one group of guide beams 3 respectively, and the two mobile trolleys 2 in the same group are arranged front and back and rigidly connected by connecting rods. When the mobile trolley 2 is not hoisting the prefabricated inverted arch 20, it moves to the mobile trolley locking mechanism to be locked, and the mobile trolley locking mechanism can be an electromagnetic lock. A track clamp 21 is provided at one end of the mobile trolley 2 that moves along the guide beam 3. If the track clamp 21 is provided at the rear end of the mobile trolley 2, the mobile trolley 2 moves along the guide beam 3. After arriving at the lifting station, the track clamp 21 is controlled to clamp on the mobile trolley guide rail 4 to prevent the mobile trolley 2 from moving during the process of the chain hoist hook 18 lifting the prefabricated inverted arch 20, thereby ensuring the accurate lifting of the prefabricated inverted arch 20 and improving the installation efficiency of the prefabricated inverted arch 20. After the lifting is completed and before the mobile trolley 2 moves, the track clamp 21 is controlled to be loosened, and the mobile trolley 2 can move on the mobile trolley guide rail 4.
[0069] As an implementation method, Figure 2 As shown, the rear leg wheel telescopic support 13 includes a rear support leg 1301, a rear leg support platform 1302, a rear leg cylinder 1304, a rear leg support base 1305, a rear leg driving wheel group 1303 and a rear leg driven wheel group 1306, the rear support leg 1301 is fixedly arranged below the rear cross beam 1, the rear leg support platform 1302 is fixedly arranged below the rear support leg 1301, the base of the rear leg cylinder 1304 is fixedly arranged below the rear leg support platform 1302, the rear leg support base 1305 is fixedly arranged on the piston rod of the rear leg cylinder 1304, the rear leg driving wheel group 1303 and the rear leg driven wheel group 1306 are arranged below the rear leg support platform 1302, and the rear leg driving wheel group 1303 is provided with a hydraulic motor.
[0070] During the movement of the inverted arch track laying platform, the piston rod of the rear leg cylinder 1304 is in a retracted state, the rear leg support base 1305 is lifted up and suspended, the rear leg driving wheel group 1303 and the rear leg driven wheel group 1306 are supported on the tunnel pavement, and when the hydraulic motor is working, the rear leg driving wheel group 1303 is driven to rotate, which drives the rear leg driven wheel group 1306 to rotate, and cooperates with the middle leg wheel 11 to move on the tunnel pavement. After arriving at the track laying station, the hydraulic motor stops working, the piston rod of the rear leg cylinder 1304 is extended, the rear leg support base 1305 is supported on the tunnel pavement, and the rear leg driving wheel group 1303 and the rear leg driven wheel group 1306 are lifted up and suspended.
[0071] As an implementation method, Figure 2 , Figure 3 , Fig.10 , Fig.11 As shown, the middle leg wheel 11 includes a middle support leg 1101, a middle leg support platform 1102, a middle leg driving wheel group 1103 and a middle leg driven wheel group 1105, the middle support leg 1101 is movably arranged on the side wall of the guide beam 3, the middle leg support platform 1102 is fixedly arranged below the middle support leg 1101, the middle leg driving wheel group 1103 and the middle leg driven wheel group 1105 are fixedly arranged below the middle leg support platform 1102, the middle leg driving wheel group 1103 is provided with the hydraulic motor, and the lower end side walls of the guide beam 3 are arranged along the length direction of the guide beam 3. There are relative wing plates 12, and the wing plates 12 are arranged perpendicular to the side walls of the guide beam 3. The lower end of the guide beam 3 is provided with a concave middle leg movable driving wheel mounting frame 8, and the middle leg wheel 11 is arranged at the lower end of the middle leg movable driving wheel mounting frame 8. The middle leg movable driving wheel mounting frame 8 is clamped at the lower end of the guide beam 3, and the inner side wall of the middle leg movable driving wheel mounting frame 8 is relatively provided with a middle leg movable driving wheel 9, and the middle leg movable driving wheel 9 moves along the corresponding wing plates 12, and the outer side wall of the middle leg movable driving wheel mounting frame 8 is provided with a middle leg movable motor 10 for driving the middle leg movable driving wheel 9 to move.
[0072] The middle leg driving wheel group 1103 and the middle leg driven wheel group 1105 cooperate with the rear leg driving wheel group 1303 and the rear leg driven wheel group 1306 to drive the prefabricated inverted arch laying platform to advance. To improve the stability of the prefabricated inverted arch laying platform, the number of the middle leg driving wheel group 1103, the middle leg driven wheel group 1105, the rear leg driving wheel group 1303 and the rear leg driven wheel group 1306 is set to two groups, each with two. The middle leg driving wheel group 1103, the middle leg driven wheel group 1105, the rear leg driving wheel group 1303 and the rear leg driven wheel group 1306 are rubber wheel groups to prevent damage to the tunnel pavement. A middle leg hydraulic station 1104 is provided on the middle leg support platform 1102, and the middle leg hydraulic station 1104 provides power for the hydraulic motor of the middle leg driving wheel group 1103. The middle leg driving wheel group 1103, the middle leg driven wheel group 1105, the rear leg driving wheel group 1303 and the rear leg driven wheel group 1306 are provided with a suspension and a slewing device. The suspension makes the prefabricated inverted arch laying platform move more steadily, and the slewing device controls the travel direction of the prefabricated inverted arch laying platform. A synchronous slewing mechanism driven by a hydraulic cylinder is designed at the slewing device to achieve consistent steering of the four wheels below a single leg, and the steering of the same group of legs is achieved by controlling the stroke of the hydraulic cylinders on the left and right sides. The above-mentioned hydraulic cylinder is connected to the middle leg hydraulic station 1104 to supply oil to the hydraulic cylinder. The concave middle leg mobile driving wheel mounting frame 8 is clamped and clamped at the lower end of the guide beam 3, and the relatively arranged middle leg mobile driving wheels 9 are respectively located on the two wing plates 12 of the guide beam 3 and move along the wing plates 12. The number of the middle leg moving driving wheels 9 is two or four. For example, if the number of the middle leg moving driving wheels 9 is four, two of them are relatively arranged on the two inner side walls of the concave middle leg moving driving wheel mounting frame 8, so as to improve the stability of the middle leg wheel 11 moving along the wing plate 12. A gear is fixedly arranged on the mounting shaft of the two middle leg moving driving wheels 9 of the same group, close to one end of the middle leg moving driving wheel mounting frame 8. The two middle leg moving driving wheels 9 are connected by a gear chain 26 or a gear belt transmission, so as to ensure that the two middle leg moving driving wheels 9 of the same group rotate synchronously. The inner side wall of the middle leg moving driving wheel mounting frame 8 is relatively arranged with a middle leg moving guide wheel 25, and the middle leg moving guide wheel 25 is arranged above the middle leg moving driving wheel 9. The concave middle leg moving driving wheel mounting frame 8 is clamped and clamped at the lower end of the guide beam 3. The relatively arranged middle leg moving guide wheels 25 are respectively in contact with the two side walls of the guide beam 3, and move along the length direction of the guide beam 3 on the side wall of the guide beam 3, so as to play a guiding and supporting role, and at the same time improve the stability of the middle leg wheel 11 moving along the wing plate 12.The number of the middle leg moving guide wheels 25 is two or four. For example, if the number of the middle leg moving guide wheels 25 is four, two of them are relatively arranged on the two inner side walls of the concave middle leg moving drive wheel mounting frame 8, so as to further improve the stability of the middle leg wheel 11 moving along the wing plate 12. The middle leg moving drive wheel mounting frame 8 is provided with a middle leg moving guide wheel installation distance adjustment member 24, which can conveniently adjust the installation distance between the middle leg moving guide wheel 25 and the side wall contact surface of the guide beam 3 according to actual needs and the wear of the middle leg moving guide wheel 25, such as adjusting the distance between the middle leg moving guide wheel 25 and the side wall of the guide beam 3 by adjusting the bolt. Alternatively, a middle leg moving guide rail is arranged on the side wall of the guide beam 3 along its length direction, and the middle leg moving motor 10 drives the middle leg moving drive wheel 9 to slide in the middle leg moving guide rail, driving the middle leg wheel 11 to move along the guide beam 3.
[0073] like Figure 2 As shown, the front leg telescopic support 6 includes a front supporting leg 601, a front leg cylinder 602, and a front leg supporting base 603. The front supporting leg 601 is fixedly arranged below the front cross beam 5, the base of the front leg cylinder 602 is fixedly arranged below the front supporting leg 601, and the front leg supporting base 603 is fixedly arranged on the piston rod of the front leg cylinder 602.
[0074] During the movement of the prefabricated inverted track laying platform, the piston rod of the front leg cylinder 602 is in a retracted state, the front leg support base 603 is lifted up and suspended in the air, and reaches the track laying station, the piston rod of the front leg cylinder 602 is extended, the front leg support base 603 is supported on the tunnel pavement, and cooperates with the rear leg support base 1305 to support the tunnel pavement, thereby supporting the prefabricated inverted track laying platform. At this time, the middle leg driving wheel group 1103, the middle leg driven wheel group 1105, the rear leg driving wheel group 1303 and the rear leg driven wheel group 1306 are suspended in the air.
[0075] As an implementation method, Figure 2 As shown, a driver's cab 15 and a control cabinet 14 are provided on the rear leg support platform 1302 on one side, an electrical cabinet 16 is provided on the rear leg support platform 1302 on the other side, a hydraulic station 17 is provided on the rear cross beam 1, and the hydraulic station 17 is connected to the hydraulic motor of the front leg cylinder 602, the rear leg cylinder 1304 and the rear leg driving wheel group 1303 for oil supply, the control cabinet 14, the driving motor and the chain hoist hook 18 are electrically connected to the electrical cabinet 16, and the control cabinet 14 is electrically connected to the driving motor and the chain hoist hook 18.
[0076] The driver's cab 15, control cabinet 14 and electrical cabinet 16 are respectively arranged on the rear leg support platforms 1302 on both sides, and the hydraulic station 17 is arranged on the rear cross beam 1, and the counterweight is balanced to improve the operational safety, stability and convenience of the prefabricated inverted arch laying platform. The electricity required in the electrical cabinet 16, control cabinet 14 and driver's cab 14 can be powered by batteries, and the batteries can be installed close to the electrical cabinet 16.
[0077] Preferably, Figure 2 , Figure 3 , Fig.10 , Fig.11 As shown, position sensors and middle leg wheel locking mechanisms 7 are provided at positions of the guide beam close to the rear cross beam 1 and the front leg telescopic supports 6 , and the position sensors are electrically connected to the control cabinet 14 and the electrical cabinet 16 .
[0078] The middle leg wheel locking mechanism 7 near the rear cross beam 1 is used to move the middle leg wheel 10 to the rear and lock it when it is not working, so as to make room for the prefabricated inverted arch 20 to rotate. When the middle leg wheel 10 is working, the middle leg wheel locking mechanism 7 near the front leg telescopic support 6 is locked to prevent the middle leg wheel 10 from moving. The guide beam 3 is provided with a distance sensor, an inclination sensor, a video auxiliary system, etc., which are electrically connected to the control cabinet 13 and the electrical cabinet 15, so as to realize the detection of various items such as position, distance, inclination, etc. A locking pin hole 101 is provided at the position of the middle leg wheel locking mechanism 7 near the front leg telescopic support 6 of the guide beam 3, and a through hole opposite to the locking pin hole 101 is provided on the middle leg moving driving wheel mounting frame 8, and a locking pin 23 is provided in the through hole. During the movement of the prefabricated inverted arch laying platform, the plug-in end of the locking pin 23 is plugged into the locking pin hole 101, further locking the middle leg wheel 10 to prevent it from moving along the guide beam 3. The prefabricated inverted arch laying platform is moved to the designated laying station, and the locking pin 23 is pulled out from the locking pin hole 101 to adjust the height of the middle leg wheel 10. The middle leg moving driving wheel mounting frame 8 is provided with a locking pin telescopic cylinder 22, and the piston rod of the locking pin telescopic cylinder 22 is fixedly connected to the other end of the opposite plug-in end of the locking pin 23. By controlling the extension and retraction of the locking pin telescopic cylinder 22, the locking pin 23 is controlled to be inserted into the locking pin hole 101 or pulled out from the locking pin hole 101, which is very convenient. The locking pin telescopic cylinder 22 can be connected to the middle leg hydraulic station 1104 to supply oil to the hydraulic cylinder.
[0079] like Figure 2 , Figure 3 , Figure 4 , Figure 5 , Figure 6 , Figure 7 , Figure 8 , Fig. 9 , Fig.10 , Fig.11 , Fig.12 As shown in the figure, the construction steps of hoisting the prefabricated invert using the prefabricated invert laying platform are as follows:
[0080] S1. Complete the assembly and commissioning of the prefabricated invert laying platform outside the tunnel;
[0081] S2. After the prefabricated inverted arch laying platform is debugged, the prefabricated inverted arch laying platform is sent into the tunnel;
[0082] S3, the driver of the prefabricated inverted arch track laying platform controls and drives the prefabricated inverted arch track laying platform to move to the designated track laying station;
[0083] S4, after the prefabricated inverted arch track laying platform arrives at the designated track laying station, the driver of the prefabricated inverted arch track laying platform controls the piston rods of the front leg oil cylinder 602 and the rear leg oil cylinder 1304 of the prefabricated inverted arch track laying platform to extend, and the front leg support base 603 and the rear leg wheel telescopic support 13 are extended to the designated support position. After the middle leg wheel 11 leaves the ground, the middle leg moving motor 10 is controlled to drive the middle leg wheel 11 to move to the rear end of the rear middle leg moving guide rail and lock it;
[0084] S5, the prefabricated inverted arch 20 is longitudinally placed on the special flat car 19 for inverted arch transportation, and transported to the loading and unloading lifting station below the prefabricated inverted arch 20 to the track laying platform. The driver of the special flat car 19 for inverted arch transportation controls the lower center turntable of the special flat car 19 for inverted arch transportation to rotate the prefabricated inverted arch 20 90°;
[0085] S6, the driver of the prefabricated inverted arch laying platform controls the mobile trolley 2 on the guide beam 3 of the prefabricated inverted arch laying platform to move to the loading and unloading lifting operation position, the operator locks the four lifting points set with the sling and the prefabricated inverted arch 20, controls the motor of the chain hoist hook 18 to drive the lifting chain to rise, lifts the prefabricated inverted arch 20 from the special flat car 19 for inverted arch transportation, controls the motor of the chain hoist hook 18 to drive the lifting chain to descend, makes the height of the prefabricated inverted arch 20 drop to the position 50cm from the ground, and the special flat car 19 for inverted arch transportation withdraws from the bottom of the prefabricated inverted arch laying platform and returns to the transfer yard outside the tunnel entrance to transport new inverted arches;
[0086] S7, the driver of the prefabricated inverted arch laying platform drives the moving trolley 2 on the laying platform guide beam 3 to move to the laying station, so that the prefabricated inverted arch 20 is directly above the lifting position, and then controls the motor of the chain hoist hook 18 to place the prefabricated inverted arch 20 in the designated position;
[0087] S8, the operator adjusts and connects the adjacent prefabricated inverts 20, loosens the sling after installation, controls the motor of the chain hoist hook 18 to raise the hook, and cross-carries grouting operations on the bottom and side gaps;
[0088] S9, the driver of the prefabricated inverted arch track laying platform controls the moving trolley 2 to move to the position of the guide beam 3 close to the rear cross beam 1 and locks it, controls the middle leg wheel 11 to move to the front end position of the middle leg moving guide rail and locks it, controls the front leg oil cylinder 602 and the rear leg oil cylinder 1304 to retract, and makes the rear leg driving wheel group 1303, the rear leg driven wheel group 1306, the middle leg driving wheel group 1103 and the middle leg driven wheel group 1105 of the prefabricated inverted arch track laying platform be in the supporting position and move to the next designated track laying station;
[0089] S10, repeating steps S3-S9 to complete the laying operation of the prefabricated invert 20.
[0090] The prefabricated invert 20 is hoisted and installed through the steps S1-S10 of the above-mentioned method for constructing a prefabricated invert for a highway tunnel, ensuring that the prefabricated invert 20 of large size and large tonnage is convenient for rotation and hoisting in the limited space of the tunnel, and convenient for the prefabricated invert 20 of large size and large tonnage to be installed quickly and conveniently in the tunnel. The mobile trolley 2 and the guide rails 4 of the mobile trolley cooperate with the chain hoist hook 18 to facilitate the adjustment of the prefabricated invert 20, which is hoisted and installed from directly above the hoisting position to ensure the installation quality of the prefabricated invert. The special flat car 19 for transporting the prefabricated invert and the prefabricated invert laying platform cooperate with continuous cross operation to improve the installation efficiency of the prefabricated invert.
[0091] As an implementation method, Fig.13 , Fig.14 , Fig.15 , Fig.16 As shown, the support and leveling device includes a support pad 30 and a fixed anchor 31. The upper end of the support pad 30 cooperates with the lower end surface of the prefabricated invert 20. The support pad 30 is provided with a fixed anchor hole that cooperates with the fixed anchor 31. The fixed anchor 31 is passed through the fixed anchor hole. The upper end of the support pad 30 is provided with a leveling reference platform 32. The leveling reference platform 32 is provided with a spirit level and a laser rangefinder.
[0092] The position and attitude measurement of the support pad 30 is realized by placing a laser rangefinder and a two-way level on the leveling reference platform 32 to adjust the horizontal position and height position of each support pad 30. After the position of the support pad 30 is adjusted, the support pad 30 is fixed with a fixing anchor 31. The prefabricated inverted arch 20 is hoisted on the support pad 30, and the prefabricated inverted arch 20 maintains the same horizontal height, and there is no need to adjust the horizontal and height position of the prefabricated inverted arch 20. The support pad 30 is prefabricated with concrete. After the prefabricated inverted arch 20 is laid on the support pad 30, the support pad 30 can form an effective support for the prefabricated inverted arch 20, and the next prefabricated inverted arch 20 is continued to be laid, so that the continuous laying operation of the prefabricated inverted arch 20 can be realized.
[0093] As an implementation method, Fig.17 , Fig.18 As shown, jacks 29 are arranged at intervals on both sides of the prefabricated inverted arch 20, channel steels 28 are arranged along the arch foot of the upper lining 27, and the prefabricated inverted arch 20 is hoisted on the supporting and leveling device, and the piston rod of the jack 29 is arranged opposite to the corresponding channel steel 28. The jack 29 can be a bolt jack or a hydraulic jack.
[0094] If the jack 29 is a bolt jack, the use of a screw jack and a longitudinal channel steel can quickly and effectively connect the prefabricated invert 20 and the upper lining 27, ensure the safety and stability of the prefabricated invert 20 and the upper lining 27, and directly cast the screw jack inside the concrete structure. The supporting force of the screw jack is used to realize rapid traffic operation after the tunnel bottom is poured with concrete, thereby reducing traffic congestion.
[0095] The above description is only a specific implementation mode of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A construction method for treating damaged inverts in highway tunnels. Its characteristics are: The following steps are involved: S1, setting up a prefabricated invert transfer yard near the tunnel entrance, and designing and manufacturing prefabricated inverts (20) at the prefabricated invert transfer yard; S2. Cut and clean the diseased invert area; S3, installing a support and leveling device on the cleared invert foundation layer; S4, assembling and debugging the prefabricated inverted arch track laying platform, sending the debugged prefabricated inverted arch track laying platform into the tunnel, and moving the prefabricated inverted arch track laying platform to a designated track laying station close to the inverted arch foundation layer; S5, the special flat car (19) for transporting the prefabricated inverted arch (20) is transported to the bottom of the prefabricated inverted arch laying platform; S6, the prefabricated inverted arch laying platform hoists the prefabricated inverted arch (20) on the inverted arch foundation layer, and the inverted arch transportation special flat car (19) exits the tunnel to transport the next prefabricated inverted arch (20); S7, repeating steps S5 and S6 to complete the installation of the next prefabricated invert (20); S8, connecting adjacent prefabricated inverts (20) and grouting the gaps in the bottom layer; S9, road surface leveling.
2. A construction method for treating a damaged invert in a highway tunnel according to claim 1, Its characteristics are: The operations of cutting the damaged road surface, excavating the road surface concrete layer, excavating the inverted arch layer, removing the slag, repairing the inverted arch foundation layer and the passage of vehicles are arranged on the exit side of the tunnel portal, and the operations of the prefabricated inverted arch transfer yard, the prefabricated inverted arch laying platform and the prefabricated inverted arch (20) connection, grouting and later road surface leveling treatment and the passage of vehicles are arranged on the entrance side of the tunnel portal.
3. A construction method for treating a damaged invert in a highway tunnel according to claim 1, Its characteristics are: The prefabricated inverted arch laying platform comprises a platform frame, the platform frame is provided with a lifting mechanism and a supporting mechanism, the supporting mechanism comprises a front leg telescopic support (6), a middle leg wheel (11) and a rear leg wheel telescopic support (13), the two rear leg wheel telescopic supports (13) are relatively fixedly arranged at the rear end of the platform frame, the two front leg telescopic supports (6) are relatively fixedly arranged at the front end of the platform frame, the middle leg wheel (11) is movably arranged between the front leg telescopic support (6) and the rear leg wheel telescopic support (13), and the platform frame is provided with a middle leg wheel locking mechanism (7) for locking the middle leg wheel (11).
4. A construction method for treating a damaged invert in a highway tunnel according to claim 3, Its characteristics are: The platform frame comprises a rear cross beam (1), a front cross beam (5) and a guide beam (3); the rear cross beam (1) and the front cross beam (5) are arranged opposite to each other; four guide beams (3) are fixedly arranged between the rear cross beam (1) and the front cross beam (5) at intervals; two rear leg wheel telescopic supports (13) are relatively fixedly arranged at the two ends of the rear cross beam (1); two front leg telescopic supports (6) are relatively fixedly arranged at the two ends of the front cross beam (5); and the middle leg wheel (11) is movably arranged on the guide beam (3).
5. A construction method for treating a damaged invert in a highway tunnel according to claim 4, Its characteristics are: The lifting mechanism comprises a moving trolley (2), a driving motor for driving the moving trolley (2) to move, and a chain hoist hook (18); the driving motor is arranged on the moving trolley (2), the driving motor is connected to the wheels of the moving trolley (2) by transmission, the chain hoist hook (18) is arranged below the moving trolley (2), a moving trolley guide rail (4) is arranged at the top of the guide beam (3) along its length direction, the wheels of the moving trolley (2) move along the length direction of the moving trolley guide rail (4), and a moving trolley locking mechanism for locking the moving trolley (2) is arranged at a position of the guide beam (3) close to the rear cross beam (1).
6. A construction method for treating a damaged invert in a highway tunnel according to claim 5, Its characteristics are: The rear leg wheel telescopic support (13) comprises a rear supporting leg (1301), a rear leg supporting platform (1302), a rear leg oil cylinder (1304), a rear leg supporting base (1305), a rear leg driving wheel group (1303) and a rear leg driven wheel group (1306); the rear supporting leg (1301) is fixedly arranged below the rear cross beam (1); the rear leg supporting platform (1302) is fixedly arranged below the rear supporting leg (1301); the base of the rear leg oil cylinder (1304) is fixedly arranged below the rear leg supporting platform (1302); the rear leg supporting base (1305) is fixedly arranged on the piston rod of the rear leg oil cylinder (1304); the rear leg driving wheel group (1303) and the rear leg driven wheel group (1306) are arranged below the rear leg supporting platform (1302); and the rear leg driving wheel group (1303) is provided with a hydraulic motor.
7. A construction method for treating a damaged invert in a highway tunnel according to claim 6, Its characteristics are: The middle leg wheel (11) comprises a middle support leg (1101), a middle leg support platform (1102), a middle leg driving wheel group (1103) and a middle leg driven wheel group (1105); the middle support leg (1101) is movably arranged on the side wall of the guide beam (3); the middle leg support platform (1102) is fixedly arranged below the middle support leg (1101); the middle leg driving wheel group (1103) and the middle leg driven wheel group (1105) are fixedly arranged below the middle leg support platform (1102); the middle leg driving wheel group (1103) is provided with the hydraulic motor; and the two side walls at the lower end of the guide beam (3) are provided with corresponding A pair of wing plates (12), the wing plates (12) are arranged perpendicular to the side walls of the guide beam (3), the lower end of the guide beam (3) is provided with a concave middle leg movable driving wheel mounting frame (8), the middle leg wheel (11) is arranged at the lower end of the middle leg movable driving wheel mounting frame (8), the middle leg movable driving wheel mounting frame (8) is clamped at the lower end of the guide beam (3), the inner side wall of the middle leg movable driving wheel mounting frame (8) is relatively provided with a middle leg movable driving wheel (9), the middle leg movable driving wheel (9) moves along the corresponding wing plates (12), and the outer side wall of the middle leg movable driving wheel mounting frame (8) is provided with a middle leg movable motor (10) for driving the middle leg movable driving wheel (9) to move.
8. A construction method for treating a damaged invert in a highway tunnel according to claim 7, Its characteristics are: The front leg telescopic support (6) comprises a front supporting leg (601), a front leg oil cylinder (602), and a front leg supporting base (603); the front supporting leg (601) is fixedly arranged below the front cross beam (5); the base of the front leg oil cylinder (602) is fixedly arranged below the front supporting leg (601); and the front leg supporting base (603) is fixedly arranged on the piston rod of the front leg oil cylinder (602).
9. A construction method for treating a damaged invert in a highway tunnel according to claim 1, Its characteristics are: The support and leveling device comprises a support pad (30) and a fixing anchor (31), the upper end of the support pad (30) matches with the lower end surface of the prefabricated invert (20), the support pad (30) is provided with a fixing anchor hole matched with the fixing anchor (31), the fixing anchor (31) is penetrated through the fixing anchor hole, and the upper end of the support pad (30) is provided with a leveling reference platform (32), and the leveling reference platform (32) is provided with a level and a laser rangefinder.
10. A construction method for treating a damaged invert in a highway tunnel according to claim 1, Its characteristics are: Jacks (29) are arranged at intervals on both side ends of the prefabricated inverted arch (20), channel steels (28) are arranged along the arch foot of the upper lining (27), the prefabricated inverted arch (20) is hoisted on the supporting and leveling device, and the piston rod of the jack (29) is arranged opposite to the channel steel (28).
Citation Information
Cited By
Tunnel local assembly type reinforcing structure mounting system and monitoring and construction method
CN119981995A