Prefabricated inverted arch structure convenient to level and construction method
By using jacks to level the prefabricated arch block in tunnel construction, the surface leveling problem during prefabricated arch block installation is solved, the construction efficiency and structural stability are improved, and rapid and effective tunnel construction is achieved.
Patent Information
- Application Number
- CN202410997396.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-24
- Publication Date
- 2024-11-05
AI Technical Summary
During the tunnel construction process, the surface leveling was not performed when the prefabricated arch block was installed, resulting in uneven thickness of the concrete leveling layer, affecting the stability of the overall structure.
A prefabricated arch structure that is convenient to level is designed, using a jack to level the upper surface of the prefabricated arch. By installing a jack in the reserved hole and entering the working cavity through the inspection hole, the jack height is adjusted, and the cast-in-place arch foot is used to adjust the jack height. and pour the asphalt pavement layer to ensure the surface is flat.
The rapid leveling of prefabricated arches is achieved, the construction efficiency is improved, the construction period is shortened, and the problem of narrow construction space is solved, ensuring the stability of the structure.
Smart Images

Figure CN118895986A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel construction, in particular to a prefabricated invert structure which is convenient for leveling and a construction method. Background Art
[0002] Mountain tunnels are usually constructed using the mining method. Their support system includes primary support and secondary support, of which the secondary support includes the bottom invert structure and the secondary lining structure. The invert is a reverse arch structure set at the bottom of the tunnel to improve the stress conditions of the upper secondary lining. It is one of the main components of the tunnel lining structure. On the one hand, the invert can effectively transfer the stratum pressure and road load on the upper part of the tunnel to the underground through the tunnel side wall structure, and at the same time it can effectively resist the reaction force from the lower stratum of the tunnel. The invert and the secondary lining are closed into a ring to form the whole tunnel lining, increasing the structural stability.
[0003] Chinese utility model patent CN217380573U discloses a semi-prefabricated tunnel composite lining structure, including initial support, and a composite secondary lining on the inside; the top center of the composite secondary lining is a prefabricated vault block, the bottom center is a prefabricated invert block, and the two sides from top to bottom are prefabricated arch wall blocks and cast-in-place side walls. In the structure of the utility model, the vault, arch wall and invert are all prefabricated splicing structures, and the side wall is a cast-in-place structure, which effectively reduces the height of the cast-in-place side wall and reduces the risk of cantilevering after the side wall is cast-in-place; the prefabricated arch wall block is compacted with the cast-in-place side wall by its own gravity, reducing the contact gap and the overall structure is stable.
[0004] The above patent has some problems during use: when installing the prefabricated inverted arch block, the upper surface of the prefabricated inverted arch block is not leveled, which may cause uneven thickness of the concrete leveling layer during the subsequent construction of the concrete leveling layer, thereby causing overall structural instability. Summary of the invention
[0005] The technical problem to be solved by the present invention is to provide a prefabricated inverted arch structure and a construction method which are convenient for leveling, and are used for leveling the upper surface of the prefabricated inverted arch during the construction process to ensure the construction quality.
[0006] The technical solution adopted by the present invention to solve its technical problems is a prefabricated inverted arch structure that is convenient for leveling, comprising a tunnel body, an inner circumferential surface of the tunnel body is provided with a tunnel primary support, the inner side of the tunnel primary support is provided with a secondary lining, a prefabricated inverted arch and a cast-in-place arch foot connecting the secondary lining and the prefabricated inverted arch, the secondary lining, the cast-in-place arch foot and the prefabricated inverted arch form an annular structure, a group of mounting holes are respectively provided on both sides of the center line of the lower surface of the prefabricated inverted arch, each group of mounting holes includes at least two reserved holes arranged at intervals along the length direction of the tunnel body, a jack is provided in each of the reserved holes, one end of the jack is abutted against the tunnel primary support, and the other end is abutted against the bottom of the mounting hole, a working cavity connected to the mounting hole is provided inside the prefabricated inverted arch, an inspection hole connected to the working cavity is provided on the upper surface of the prefabricated inverted arch, and a cover plate for opening or closing the inspection hole is provided on the inspection hole.
[0007] Furthermore, protrusions are provided on both sides of the prefabricated inverted arch, and pressure blocks used in conjunction with the protrusions are provided on the cast-in-place arch feet.
[0008] Furthermore, the number of the working chambers is two, and each working chamber is communicated with a group of mounting holes.
[0009] Furthermore, pressure relief chambers are provided on both sides of each working chamber.
[0010] Furthermore, a countersunk hole is coaxially arranged above the inspection hole, the cover plate is arranged in the countersunk hole, and the cover plate is hinged to the upper surface of the prefabricated invert arch.
[0011] Furthermore, a cable well is provided on the cast-in-place arch foot.
[0012] A construction method of a prefabricated inverted arch structure that is convenient for leveling, using a prefabricated inverted arch structure that is convenient for leveling, comprising the following steps:
[0013] S1: A primary tunnel support is provided on the inner circumference of the tunnel body, and a secondary lining is provided on the top of the inner side of the primary tunnel support;
[0014] S2: Install a jack in the reserved hole of the prefabricated invert, and hoist the prefabricated invert to the bottom of the inner side of the primary support of the tunnel;
[0015] S3: The operator opens the cover plate and enters the working chamber from the inspection hole, adjusts the lifting height of the jack, and performs leveling on the upper surface of the prefabricated invert. After the leveling is completed, the operator exits the working chamber and closes the cover plate;
[0016] S4: Pour mortar into the gap between the precast invert and the primary support of the tunnel, and use concrete to cast the cast-in-place arch foot between the secondary lining and the precast invert, and pour the asphalt pavement layer on the upper surface of the precast invert.
[0017] The beneficial effects of the present invention are:
[0018] 1. The jack is used to quickly level the upper surface of the prefabricated invert, eliminating the need for large-scale lifting equipment to repeatedly lift the prefabricated invert, thereby improving construction efficiency.
[0019] 2. Use the supporting capacity of the jack to achieve rapid vehicle passage conditions, avoid the limitation of concrete curing age, and effectively shorten the construction period.
[0020] 3. Enter the working cavity of the prefabricated invert through the inspection hole on the upper surface of the prefabricated invert, and adjust the height of the prefabricated invert in the working cavity, which solves the problem of narrow construction space at both ends of tunnel maintenance. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a schematic diagram of the structure of the present invention;
[0022] Figure 2 It is a schematic diagram of a prefabricated invert;
[0023] Figure 3 yes Figure 2 Sectional view along line AA.
[0024] Figure numerals: 1-tunnel body; 2-primary support of tunnel; 3-secondary lining; 4-prefabricated invert; 5-cast-in-place arch foot; 6-installation hole; 601-reserved hole; 7-jack; 8-working chamber; 9-inspection hole; 10-cover plate; 11-bump; 12-pressure block; 13-pressure relief chamber; 14-sinking hole; 15-cable well; 16-asphalt pavement layer. DETAILED DESCRIPTION
[0025] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.
[0026] like Figure 1-Figure 3As shown, the present invention provides a prefabricated inverted arch structure that is convenient for leveling, a tunnel body 1, an inner circumferential surface of the tunnel body 1 is provided with a tunnel primary support 2, the inner side of the tunnel primary support 2 is provided with a secondary lining 3, a prefabricated inverted arch 4 and a cast-in-place arch foot 5 connecting the secondary lining 3 and the prefabricated inverted arch 4, the secondary lining 3, the cast-in-place arch foot 5 and the prefabricated inverted arch 4 form an annular structure, a group of mounting holes 6 are respectively provided on both sides of the midline of the lower surface of the prefabricated inverted arch 4, each group of mounting holes 6 includes at least two reserved holes 601 arranged at intervals along the length direction of the tunnel body 1, each of the reserved holes 601 is provided with a jack 7, one end of the jack 7 is abutted against the tunnel primary support 2, and the other end is abutted against the bottom of the mounting hole 6, a working cavity 8 connected to the mounting hole 6 is provided inside the prefabricated inverted arch 4, an inspection hole 9 connected to the working cavity 8 is provided on the upper surface of the prefabricated inverted arch 4, and a cover plate 10 for opening or closing the inspection hole 9 is provided on the inspection hole 9.
[0027] Among them, the secondary lining 3 is a cast concrete or reinforced concrete lining applied inside the tunnel primary support 2, and together with the tunnel primary support 2, it forms a composite lining; the precast invert 4 is precast from reinforced concrete and hoisted into the tunnel when in use; the cast-in-place arch foot 5 is a concrete structure cast between the precast invert 4 and the secondary lining 3 after the precast invert 4 and the secondary lining 3 are installed, and is used to connect the precast invert 4 and the secondary lining 3. After the construction is completed, the secondary lining 3, the cast-in-place arch foot 5 and the precast invert 4 form a ring structure. A group of mounting holes 6 are respectively provided on both sides of the center line of the lower surface of the precast invert 4, and the two groups of mounting holes 6 are symmetrically arranged about the vertical plane where the center line of the lower surface of the precast invert 4 is located, that is, the distance between each group of mounting holes 6 and the center line of the lower surface of the precast invert 4 is consistent. Each group of mounting holes 6 includes at least two reserved holes 601 arranged at intervals along the length direction of the tunnel body 1, and the axes of the reserved holes 601 are vertical. Each group of mounting holes 6 includes at least two reserved holes 601, and jacks 7 are arranged in the reserved holes 601, so that the prefabricated inverted arch 4 can be stably placed on the tunnel primary support 2; the jack 7 can be a screw jack 7 or a hydraulic jack 7, one end of the jack 7 is abutted against the tunnel primary support 2, and the other end is abutted against the bottom of the mounting hole 6, which is used to adjust the height of the prefabricated inverted arch 4; a working cavity 8 connected with the mounting hole 6 is arranged inside the prefabricated inverted arch 4, and an inspection hole 9 connected with the working cavity 8 is arranged on the upper surface of the prefabricated inverted arch 4, and workers can enter the working cavity 8 through the inspection hole 9, adjust the lifting height of the jack 7, and level the upper surface of the prefabricated inverted arch 4, and a cover plate 10 for opening or closing the inspection hole 9 is arranged on the inspection hole 9.
[0028] In order to realize the vertical limit of the prefabricated invert 4, further, see Figure 1 The prefabricated inverted arch 4 is provided with protrusions 11 on both sides, and the cast-in-place arch foot 5 is provided with a pressing block 12 used in conjunction with the protrusions 11.
[0029] If one working chamber 8 is used to adjust the two sets of jacks 7 in the installation chamber, the span of the hollow part of the prefabricated invert 4 will be too large, and there will be no support in the working chamber 8, which will affect the overall strength. Figure 1 The number of working chambers 8 is two, and each working chamber 8 is connected to a group of mounting holes 6 respectively.
[0030] In order to reduce the overall weight of the prefabricated inverted arch 4 and simultaneously realize the pressure relief on the upper surface of the prefabricated inverted arch 4, further, see Figure 1 , pressure relief chambers 13 are arranged on both sides of each working chamber 8. A web is provided between the pressure relief chamber 13 and the working chamber 8, thus forming a pressure relief structure.
[0031] For further information, see Figure 1 A countersunk hole 14 is coaxially arranged above the inspection hole 9 , and the cover plate 10 is arranged in the countersunk hole 14 . The cover plate 10 is hinged to the upper surface of the prefabricated invert 4 .
[0032] Furthermore, a cable well 15 is provided on the cast-in-place arch foot 5 .
[0033] A construction method of a prefabricated inverted arch 4 structure that is convenient for leveling, using a prefabricated inverted arch 4 structure that is convenient for leveling, comprising the following steps:
[0034] S1: A tunnel primary branch 2 is provided on the inner circumference of the tunnel body 1, and a secondary lining 3 is provided on the top of the inner side of the tunnel primary branch 2;
[0035] S2: Install the jack 7 in the reserved hole 601 of the prefabricated invert 4, and hoist the prefabricated invert 4 to the bottom of the inner side of the tunnel primary support 2;
[0036] S3: The operator opens the cover plate 10 and enters the working chamber 8 from the inspection hole 9, adjusts the lifting height of the jack 7, and performs leveling on the upper surface of the prefabricated invert 4. After the leveling is completed, the operator exits the working chamber 8 and closes the cover plate 10;
[0037] S4: pour mortar into the gap between the precast invert 4 and the primary support 2 of the tunnel, and use concrete to cast the cast-in-place arch foot 5 at the position between the secondary lining 3 and the precast invert 4, and pour the asphalt pavement layer 16 on the upper surface of the precast invert 4.
[0038] The embodiments of this specific implementation method are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A prefabricated inverted arch structure convenient for leveling, a tunnel body (1), wherein the inner circumference of the tunnel body (1) is provided with a tunnel primary support (2), characterized in that: The inner side of the tunnel primary support (2) is provided with a secondary lining (3), a prefabricated inverted arch (4) and a cast-in-place arch foot (5) connecting the secondary lining (3) and the prefabricated inverted arch (4); the secondary lining (3), the cast-in-place arch foot (5) and the prefabricated inverted arch (4) form an annular structure; a group of mounting holes (6) are respectively provided on both sides of the midline of the lower surface of the prefabricated inverted arch (4); each group of mounting holes (6) includes at least two reserved holes (60) arranged at intervals along the length direction of the tunnel body (1) 1), a jack (7) is arranged in each of the reserved holes (601), one end of the jack (7) is in contact with the tunnel primary support (2), and the other end is in contact with the bottom of the installation hole (6), a working cavity (8) connected to the installation hole (6) is arranged inside the prefabricated inverted arch (4), an inspection hole (9) in contact with the working cavity (8) is arranged on the upper surface of the prefabricated inverted arch (4), and a cover plate (10) for opening or closing the inspection hole (9) is arranged on the inspection hole (9).
2. A prefabricated inverted arch structure convenient for leveling as claimed in claim 1, characterized in that: The prefabricated inverted arch (4) is provided with protrusions (11) on both sides, and the cast-in-place arch foot (5) is provided with a pressing block (12) used in conjunction with the protrusions (11).
3. The prefabricated inverted arch structure convenient for leveling according to claim 1, characterized in that: The working chambers (8) are provided in two numbers, and each working chamber (8) is communicated with a group of mounting holes (6) respectively.
4. A prefabricated inverted arch structure convenient for leveling as claimed in claim 3, characterized in that: Pressure relief chambers (13) are provided on both sides of each working chamber (8).
5. The prefabricated inverted arch structure convenient for leveling according to claim 1, characterized in that: A countersunk hole (14) is coaxially arranged above the inspection hole (9), the cover plate (10) is arranged in the countersunk hole (14), and the cover plate (10) is hinged to the upper surface of the prefabricated invert (4).
6. The prefabricated inverted arch structure convenient for leveling according to claim 1, characterized in that: A cable well (15) is provided on the cast-in-place arch foot (5).
7. A construction method for a prefabricated inverted arch structure that is convenient for leveling, using the prefabricated inverted arch structure that is convenient for leveling as claimed in any one of claims 1 to 6, characterized in that: The following steps are included: S1: A tunnel primary branch (2) is arranged on the inner circumference of the tunnel body (1), and a secondary lining (3) is arranged on the top of the inner side of the tunnel primary branch (2); S2: Install a jack (7) in the reserved hole (601) of the prefabricated inverted arch (4), and hoist the prefabricated inverted arch (4) to the bottom of the inner side of the tunnel primary support (2); S3: The operator opens the cover plate (10) and enters the working chamber (8) through the inspection hole (9), adjusts the lifting height of the jack (7), and performs leveling on the upper surface of the prefabricated invert (4). After the leveling is completed, the operator exits the working chamber (8) and closes the cover plate (10); S4: Mortar is poured into the gap between the precast invert (4) and the primary support (2) of the tunnel, and a cast-in-place arch foot (5) is cast with concrete at a position between the secondary lining (3) and the precast invert (4), and an asphalt pavement layer (16) is cast on the upper surface of the precast invert (4).