Furnace lining ramming repair and blow-in process for manganese-silicon submerged arc furnace

By optimizing the furnace lining repair and start-up process of manganese silicon submerged arc furnace, the furnace lining repair process was improved, solving the problems of long time consumption and high cost in the existing technology, and realizing rapid resumption of production and efficient production.

CN118896490APending Publication Date: 2024-11-05JIAYUGUAN HONG DIAN IRON ALLOY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411251636.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-08
Publication Date
2024-11-05

AI Technical Summary

Technical Problem

Existing lining repair processes for manganese silicon submerged arc furnaces are time-consuming, costly, and unsuitable for the rapid resumption of production in some submerged arc furnaces.

Method used

The process of ramming and repairing the furnace lining of a manganese silicon submerged arc furnace and starting the furnace is adopted. This includes steps such as electrode control, cleaning of residual materials in the furnace, ramming and leveling of the furnace bottom, preparation for furnace drying and power supply for furnace drying. The furnace lining repair process is optimized by using cold ramming paste and dry manganese silicon slag with material for furnace drying.

Benefits of technology

It shortens repair time, reduces costs, increases furnace lining life and production efficiency, is suitable for short-term resumption of production in submerged arc furnaces, and improves cost-effectiveness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure FT_1
    Figure FT_1
Patent Text Reader

Abstract

The invention discloses a manganese-silicon submerged arc furnace lining ramming repair and blow-in process. The process comprises the steps of preparation before blow-out, cleaning of residual furnace charge and slag iron in a furnace, ramming leveling and overall repair of a furnace bottom, preparation before baking, ignition baking, power transmission baking, silicon-manganese dry slag baking and normal material input, and gradual strengthening to be normal. According to the characteristics of furnace lining repair, a new method of firewood baking and silicomanganese dry slag strip furnace baking is adopted, the furnace baking effect of the whole ramming furnace lining is improved, the furnace lining is sintered into a whole, and the service life is prolonged; meanwhile, the silicon-manganese dry slag is used for baking the furnace, so that the cost input for feeding and baking the furnace by using manganese ore is reduced; and secondly, by utilizing the property after the silicon-manganese dry slag is molten into slag, the furnace baking effect is improved by balanced temperature rise, and meanwhile, the furnace protection effect is also achieved after the slag is adhered to the furnace lining.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of ferroalloy production, and in particular relates to a ramming and repairing process for a lining of a manganese silicon ore arc furnace and a furnace opening process. Background Art

[0002] Manganese silicon alloy is an alloy composed of manganese, silicon, iron, a small amount of carbon and other elements. It is a ferroalloy with a wide range of uses and a large output. Manganese silicon alloy is a commonly used composite deoxidizer in steelmaking, and a reducing agent in the production of medium and low carbon ferromanganese and the production of metallic manganese by electrosilicon thermal method.

[0003] The lining of the manganese silicon ore thermal furnace consists of three parts: furnace bottom, furnace wall and furnace eye. The furnace bottom includes furnace bottom steel plate, asbestos board, clay refractory grain elastic layer, furnace bottom low-temperature rough joint paste leveling protective layer, furnace bottom refractory bricks and furnace bottom carbon bricks (furnace bottom carbon bricks are divided into three layers, each layer is 400mm thick, totaling 1200mm); the furnace wall is composed of furnace skin, asbestos board, furnace wall refractory clay lightweight brick layer and ring carbon (ring carbon thickness 400mm); the furnace eye is built with furnace eye carbon bricks.

[0004] The normal repair furnace lining construction process is: clean up the accumulated materials and slag iron in the furnace, remove the original furnace wall carbon ring and furnace bottom carbon bricks, re-level the furnace bottom and build three layers of carbon bricks and furnace wall carbon rings. This method is suitable for submerged arc furnaces that need to be produced for a long time after repair and the supporting systems are updated synchronously, creating benefits through long-term production. However, this method is not suitable for some submerged arc furnaces. Summary of the invention

[0005] The purpose of the present invention is to provide a ramming and repairing process for the lining of a manganese silicon ore arc furnace and a furnace opening process, which can reduce the repair cost of the ore arc furnace, save time, quickly achieve results, improve the furnace drying effect and reduce the furnace opening cost, thereby solving the problems existing in the original technology.

[0006] In order to achieve the above object, the technical solution adopted by the present invention is: A ramming and repairing process for a manganese silicon ore furnace lining and a furnace opening process comprises the following steps: S1. Preparation before shutdown: Preparation before shutdown includes electrode control, batching adjustment and iron tapping management; Electrode control: 2-3 days before the furnace is shut down, the electrode is placed in the furnace, and the electrode is displaced downward to reduce the electrode pressure. The electrode displacement is inserted downward to 500-650mm. Ingredient adjustment: Increase the amount of self-produced slag by 50-80kg / batch the day before the shutdown; Iron tapping management: stop feeding the last batch of iron and let the material level drop naturally. When tapping, open both furnace holes at the same time and block the holes when slag and iron stop flowing out. S2. Cleaning of residual charge and slag in the furnace: First clean the loose materials on the upper part, then clean the residual slag iron on the lower part. During the cleaning process, the burned and broken carbon bricks are cleaned together until the carbon bricks are regular. S3, ramming and leveling of furnace bottom and overall repair: On the basis of the cleaned regular carbon bricks, a layer of 200-500mm cold rammed paste is first knotted on the furnace bottom, and then the cold rammed paste is used to knot and compact the carbon ring and the furnace bottom support formwork to connect the carbon ring and the furnace bottom into a whole; S4. Preparation before baking: Preparation before furnace baking includes furnace eye preparation, furnace bottom preparation, soot blowing preparation and electrode displacement control; Preparation of furnace eye: Use anhydrous taphole mud to plug the furnace mouth, the depth of anhydrous taphole mud is 400mm, so that a 300mm taphole mud bag is formed at the furnace mouth; use coke powder to fill and tamp from the furnace mouth, the depth is 500mm; then use eye-plugging mud balls to plug the outer furnace mouth, the depth is 200mm; Preparation of furnace bottom: a layer of clay bricks is laid around the furnace bottom and the ring carbon to form a protective layer to prevent oxidation or damage to the ring carbon or the carbonaceous materials at the furnace bottom during the furnace opening process; Soot blowing preparation: When the fire is weak, connect compressed air to send air into the furnace bottom; use oxygen blowing pipe to guide the air pipe. During the furnace drying period, there is a lot of ash at the bottom of the furnace. Sending air into the bottom of the furnace will help to increase the flame, increase the temperature of the furnace bottom, and quickly dry the furnace lining; Electrode displacement control: The electrode displacement is controlled at the upper limit, and the electrode is not pressed before power is supplied; this prevents the electrode paste from being repeatedly baked at high temperature during furnace baking; S5, Ignition oven: The furnace lining is mainly baked after ramming and repair, following the principle of heating speed from slow to fast, flame from small to large, and current from small to large, including low-fire furnace baking and high-fire furnace baking; focus on the temperature of the furnace lining, and the furnace baking process control refers to the furnace heating rate. Figure 1 During the drying process, the temperature of the furnace is controlled by referring to the heating curve of the furnace. The temperature is measured in the area 600mm below the ring carbon. A total of 6 points are measured and recorded in the large and small areas. The measurement and recording are done every 2 hours. While drying the furnace lining, the furnace body accumulates enough heat to ensure that the entire furnace body has good thermal stability. At the same time, in order to ensure the burning intensity and temperature of the firewood in the furnace, the air duct can be used to blow air into the furnace to assist combustion. Baking the furnace with a small fire: Before ignition, lay 300-500mm chopped firewood at the bottom of the furnace, and sprinkle diesel on the chopped firewood for easy ignition. The flame height should not exceed 1 / 2 of the furnace depth. Baking the furnace lining with a small fire in the early stage. The time for baking the furnace with a small fire is organized according to the 48h of the whole firewood baking time. During the baking process, gradually add firewood to the furnace according to the fire and temperature in the furnace. High-fire furnace baking: After low-fire furnace baking, high-fire furnace baking is carried out. The fire and temperature are increased by increasing the amount of firewood. When adding firewood, try to make the firewood burn evenly and violently. The flame height cannot exceed the position of the furnace door. The furnace baking time is organized according to 30-36 hours; S6, power supply oven: After the wood-fired baking is completed, the dead ash in the furnace is blown out using a compressed air pipe, and the coke prepared in the top bunker is lowered into the furnace to a height of more than 1m. The material tip is flattened using a rake, and the coke in the furnace is pushed to the same level; the electrode is pressed and released, and the three-phase electrode displacement is controlled to 500mm-550mm before the electrode is pressed and released. The electrode is pressed and released above the material surface, and the electrode is compacted in the coke by means of downward displacement. After the displacement is lifted, the coke is filled under the electrode, and the coke is compacted repeatedly; The furnace is dried by indirect power supply. When the electrode temperature or the furnace lining temperature rises too fast, the power supply is stopped as needed to control the heating speed. After the electric drying is carried out for 3 days or the electrode temperature reaches 600℃, silicon manganese dry slag is added to the furnace for drying. S7, silicon-manganese dry slag drying furnace; After the electric drying is completed, the silicon-manganese dry slag material is put into the belt drying furnace. During the dry slag drying process, the power factor is controlled above 0.85 to ensure the electrode work. When there is slag spraying at the root of the electrode in the furnace, coke is added according to the actual situation. After consuming 300,000 kWh of electricity, slag discharge is organized; Feeding method: Use a feeding pipe to feed materials evenly. The speed of the material surface is mainly to cover the arc light. The area with arc light is controlled by a furnace tamping machine. The material surface is controlled at 2 / 3 of the highest material surface, and the material surface is gradually increased. It takes 2-4 furnaces to add the material surface to the same height as the furnace mouth. There should be materials in the material bin on the top of the furnace at all times. S8. Invest in normal material ratio and gradually strengthen to normal: After 2-3 days of dry slag drying, normal material ratio is started. According to the power supply system, the load is gradually increased to strengthen the furnace condition. When the load is increased to 80% of the normal load, compensation is organized after 1-2 days of stable furnace discharge, and the load is increased to normal smelting.

[0007] In order to further realize the present invention, before cleaning the loose materials on the upper part as described in S2, the electrodes are first locked, and after stopping the furnace, all electrodes below 100 mm of the copper tile are broken, and the electrode displacement is raised to the upper limit and fixed.

[0008] In order to further realize the present invention, before a layer of 200-500mm cold ramming paste is tied on the furnace bottom in S3, CCS paste is first used for leveling.

[0009] In order to further realize the present invention, the cold pounding paste in S3 is K paste.

[0010] In order to further realize the present invention, the furnace bottom formwork described in S3 adopts 4-5mm steel plate.

[0011] In order to further realize the present invention, the thickness of the cold ramming paste used to connect the ring carbon and the furnace bottom into a whole in S3 is 80-100 mm.

[0012] In order to further realize the present invention, in the process of allowing the material surface to drop naturally in the preparation before shutdown described in S1, the material level in the furnace top silo shall not exceed 2 batches; before shutdown, all materials in all furnace top material pipes shall be added to the furnace, and no stockpiled materials are allowed; three days before shutdown, the height of the paste column shall be controlled, and the height of the paste column shall be reduced by 200mm for each team, and finally the height of the paste column shall be controlled at 2.5-3.0m, and no further paste shall be added.

[0013] In order to further realize the present invention, the dry slag produced in the silicon-manganese production process is used in the silicon-manganese dry slag drying furnace described in S7, and the manganese content of the dry slag is less than 10%. The use of dry slag with material drying furnace can make full use of the dry slag melting to evenly heat the furnace lining of the furnace bottom ramming, and prevent the material from melting and reducing to produce alloys directly after normal materials are added, which will cause the alloy to erode the furnace bottom due to the high specific gravity of silicon-manganese alloy. At the same time, the use of silicon-manganese dry slag drying furnace can effectively reduce the waste and loss of manganese ore caused by insufficient temperature and insufficient alloy reduction during the drying furnace temperature increase period, and reduce the cost of furnace opening.

[0014] Compared with the prior art, the present invention has the following beneficial effects: Under normal masonry technology, all materials in the furnace, including furnace bottom carbon bricks and ring carbon, need to be cleaned, which is labor-intensive and time-consuming, generally taking about 10-15 days. After optimizing the furnace lining repair process, the cleaning work can be completed in 5-8 days, effectively shortening the cleaning time and reducing the cleaning cost. From shutdown to resumption of production, the present invention saves 10-15 days compared with the normal masonry process. In addition to reducing labor costs in the process, it also enables the ore-fired furnace to resume production ahead of schedule, increasing production capacity and improving overall benefits.

[0015] The present invention focuses on the requirements of on-demand repair and new furnace opening technology, and is suitable for short-term resumption of production of submerged arc furnaces with long furnace life, which greatly improves the cost-effectiveness of submerged arc furnace repair. At the same time, a new furnace opening method is adopted specifically for the furnace lining repair process, which complements the furnace lining repair process and fits perfectly.

[0016] After the implementation of the present invention, the furnace lining can be quickly repaired, which greatly reduces the repair time of the furnace lining. At the same time, during the furnace baking process, as the temperature rises, the overall rammed and repaired furnace lining is baked into shape, effectively preventing various accidents caused by gaps in the newly repaired furnace lining.

[0017] The present invention adopts cold ramming paste knotting and forming, and its price is between 50% and 70% of carbon bricks, which greatly reduces the cost of furnace lining repair.

[0018] According to the characteristics of furnace lining repair, the present invention adopts a new method of wood baking + silicon-manganese dry slag baking, which improves the baking effect of the overall ramming furnace lining, sintering the furnace lining into a whole, and improving the service life; at the same time, the silicon-manganese dry slag is used to bake the furnace, firstly, the cost investment of using manganese ore to feed the furnace is reduced; secondly, the properties of the silicon-manganese dry slag after melting into slag are utilized to evenly increase the temperature to improve the baking effect, and at the same time, the furnace lining also plays a role in protecting the furnace after hanging slag. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 This is the oven temperature rise curve of S5 in the present invention. DETAILED DESCRIPTION

[0020] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

[0021] A ramming and repairing process for a manganese silicon ore furnace lining and a furnace opening process comprises the following steps: S1. Preparation before shutdown: Preparation before shutdown includes electrode control, batching adjustment and iron tapping management; Electrode control: 2-3 days before the furnace is shut down, the electrode is placed in the furnace, and the electrode is displaced downward to reduce the electrode pressure. The electrode displacement is inserted downward to 500-650mm. Ingredient adjustment: Increase the amount of self-produced slag by 50-80kg / batch the day before the shutdown; Iron tapping management: Stop unloading the last batch of iron and let the material level drop naturally. The material level in the furnace top silo should not exceed 2 batches. Before stopping the furnace, all materials in the furnace top material pipes should be added into the furnace. No stock is allowed. The height of the paste column should be controlled three days before stopping the furnace. The height of the paste column should be reduced by 200mm for each team. Finally, the height of the paste column should be controlled at 2.5-3.0m. No more paste should be added. When tapping iron, the two furnace eyes should be opened at the same time. When the slag iron stops flowing out, the eyes should be blocked. S2. Cleaning of residual charge and slag in the furnace: First lock the electrode, after stopping the furnace, break all the electrodes below 100mm of the copper tile, raise the electrode displacement to the upper limit and fix it, clean up the loose materials on the upper part, and then clean up the residual slag and iron on the lower part. During the cleaning process, clean up the burned and broken carbon bricks together until the carbon bricks are regular; S3, ramming and leveling of furnace bottom and overall repair: On the basis of the cleaned regular carbon bricks, first use CCS paste for leveling, then tie a layer of 200-500mm K paste on the furnace bottom as cold ramming paste, and then use cold ramming paste to tie and tamp around the ring carbon and the furnace bottom support formwork. The furnace bottom support formwork uses 4-5mm steel plates to connect the ring carbon and the furnace bottom into a whole. The thickness of the cold ramming paste is 80-100mm; S4. Preparation before baking: Preparation before furnace baking includes furnace eye preparation, furnace bottom preparation, soot blowing preparation and electrode displacement control; Preparation of furnace eye: Use anhydrous taphole mud to plug the furnace mouth, so that the furnace mouth forms a 300mm taphole mud bag; use coke powder to fill and tamp from the furnace mouth to a depth of 500mm; then use eye-plugging mud balls to plug the outer furnace mouth to a depth of 200mm; Preparation of furnace bottom: A layer of clay bricks is laid around the furnace bottom and carbon ring to form a protective layer; Preparation for soot blowing: When the fire is weak, connect compressed air to send air into the bottom of the furnace; Electrode displacement control: The electrode displacement is controlled at the upper limit, and the electrode is not pressed before power is supplied; S5, Ignition oven: The furnace after ramming repair is mainly used for baking furnace lining, following the principle of heating speed from slow to fast, flame from small to large, and current from small to large, including low-fire furnace and high-fire furnace; Baking the furnace with a small fire: Before ignition, lay 300-500mm chopped firewood at the bottom of the furnace, and sprinkle diesel on the chopped firewood for easy ignition. The flame height should not exceed 1 / 2 of the furnace depth. Baking the furnace lining with a small fire in the early stage. The time for baking the furnace with a small fire is organized according to the 48h of the whole firewood baking time. During the baking process, gradually add firewood to the furnace according to the fire and temperature in the furnace. High-fire furnace baking: After low-fire furnace baking, high-fire furnace baking is carried out. The fire and temperature are increased by increasing the amount of firewood. When adding firewood, try to make the firewood burn evenly and violently. The flame height cannot exceed the position of the furnace door. The furnace baking time is organized according to 30-36 hours; S6, power supply oven: After the wood-fired baking is completed, the dead ash in the furnace is blown out using a compressed air pipe, and the coke prepared in the top bunker is lowered into the furnace to a height of more than 1m. The material tip is flattened using a rake, and the coke in the furnace is pushed to the same level; the electrode is pressed and released, and the three-phase electrode displacement is controlled to 500mm-550mm before the electrode is pressed and released. The electrode is pressed and released above the material surface, and the electrode is compacted in the coke by means of downward displacement. After the displacement is lifted, the coke is filled under the electrode, and the coke is compacted repeatedly; The furnace is dried by indirect power supply. When the electrode temperature or the furnace lining temperature rises too fast, the power supply is stopped as needed to control the heating speed. After the electric drying is carried out for 3 days or the electrode temperature reaches 600℃, silicon manganese dry slag is added to the furnace for drying. S7, silicon-manganese dry slag drying furnace; After the electric drying is completed, the silicon-manganese dry slag material is put into the belt drying furnace. The silicon-manganese dry slag drying furnace uses all the dry slag produced in the silicon-manganese production process. The manganese content of the dry slag is less than 10%. During the dry slag drying process, the power factor is controlled above 0.85 to ensure that the electrode can do work. When there is slag spraying at the root of the electrode in the furnace, coke is added according to the actual situation. After consuming 300,000 kWh of electricity, slag discharge is organized; Feeding method: Use a feeding pipe to feed materials evenly. The speed of the material surface is mainly to cover the arc light. The area with arc light is controlled by a furnace tamping machine. The material surface is controlled at 2 / 3 of the highest material surface, and the material surface is gradually increased. It takes 2-4 furnaces to add the material surface to the same height as the furnace mouth. There should be materials in the material bin on the top of the furnace at all times. S8. Invest in normal material ratio and gradually strengthen to normal: After 2-3 days of dry slag drying, normal material ratio is started. According to the power supply system, the load is gradually increased to strengthen the furnace condition. When the load is increased to 80% of the normal load, compensation is organized after 1-2 days of stable furnace discharge, and the load is increased to normal smelting.

[0022] Embodiment 1: The new process of ramming and repairing the lining of manganese silicon ore furnace and opening the furnace includes the following steps: Preparation before shutdown: 3 days before shutdown, start reducing the electrode pressure in the furnace, reducing it by 50mm / shift from the normal 280-310mm / shift. At the same time, monitor the temperature of the furnace bottom and furnace body to prevent the local temperature of the furnace body from rising due to the electrode being too short. While reducing the electrode pressure, insert the electrode displacement down to 590mm. One day before shutdown, increase the amount of self-produced slag by 55kg / batch to ensure that the slag and iron in the furnace can be discharged smoothly and completely.

[0023] After the furnace is shut down, the three-phase electrodes are lifted up to the upper limit of 200mm, and the three-phase electrode ends are locked together with the large sleeve with steel wire ropes to prevent the electrodes from falling.

[0024] Organize the cleaning of the charge and slag in the furnace. In the process, the carbon bricks that are broken or lost by more than half will be removed together until complete or regular carbon bricks are seen. At the same time, the powder in the gap of the carbon ring will be cleaned up.

[0025] After cleaning, use CCS paste to level the cleaned gaps or pits, and then use K paste to ram the entire area to a thickness of 350mm; use 4mm steel plates for formwork, with the steel plates 80mm away from the ring carbon, and then use cold ramming paste to knot and shape. The thickness of the furnace bottom is controlled at 2000mm and the depth of the furnace is 2800mm.

[0026] After tying the knots, lay a layer of refractory bricks on the bottom of the furnace, lay 280mm thick large-grain coke on the bottom of the furnace, put in an appropriate amount of wood and ignite the furnace.

[0027] After the wood-fired baking is completed, 1.1 meters thick coke is added to the furnace, and then the electrode is lowered onto the coke to make it firm, and then the electric baking furnace is sent.

[0028] After the electric drying is completed, the furnace is dried with material, and silicon-manganese dry slag is added into the furnace to 2 / 3 of the normal material level. When the power consumption reaches 310,000 kWh, the eye is opened. One day after the furnace is taken out of the furnace, the normal material ratio is put into the corner.

[0029] In this embodiment, the overall repair period is shortened by 10 days compared with the normal period, various expenses are saved by 1.38 million yuan, the manganese ore consumption is reduced by 450 tons, the submerged arc furnace resumes production 10 days ahead of schedule, the output is increased by 613 tons, and the overall repair of the furnace lining adopts the new process and operates safely for three years after the furnace is opened.

[0030] Embodiment 2: The new process of ramming and repairing the lining of manganese silicon ore furnace and opening the furnace includes the following steps: Preparation before shutdown: Start reducing the electrode pressure in the furnace 3 days before shutdown, reducing it by 80mm / shift from the normal 280-310mm / shift. At the same time, monitor the temperature of the furnace bottom and furnace body to prevent the local temperature of the furnace body from rising due to the electrode being too short. While reducing the electrode pressure, insert the electrode displacement down to 680mm. Increase the amount of self-produced slag by 50kg / batch one day before shutdown to ensure that the slag and iron in the furnace can be discharged smoothly and completely.

[0031] After the furnace is shut down, the three-phase electrode displacements are lifted up to the upper limit of 220mm, and the three-phase electrode ends are locked together with the large sleeve with steel wire ropes to prevent the electrodes from falling.

[0032] Organize the cleaning of the charge and slag in the furnace. In the process, the carbon bricks that are broken or lost by more than half will be removed together until complete or regular carbon bricks are seen. At the same time, the powder in the gap of the carbon ring will be cleaned up.

[0033] After cleaning, use CCS paste to level the cleaned gaps or pits, and then use K paste to ram the entire area to a thickness of 400mm; use 4mm steel plates for formwork, with the steel plates 80mm away from the ring carbon, and then use cold ramming paste to knot and shape. The thickness of the furnace bottom is controlled at 2000mm and the furnace depth is 3200mm.

[0034] After tying the knots, lay a layer of refractory bricks on the bottom of the furnace, lay 300mm thick large-grain coke on the bottom of the furnace, put in an appropriate amount of wood and ignite the furnace.

[0035] After the wood-fired baking is completed, 1.2 meters thick coke is added to the furnace, and then the electrode is lowered onto the coke to make it firm, and then the electric baking furnace is sent.

[0036] After the electric drying is completed, the furnace is dried with material, and silicon-manganese dry slag is added into the furnace to 2 / 3 of the normal material level. When the power consumption reaches 340,000 kWh, the eye is opened. Two days after the furnace is taken out of the furnace, the normal material ratio is put into the corner.

[0037] In this embodiment, the overall repair period is shortened by 15 days compared with the normal period, saving various expenses of 1.8 million yuan, reducing the use of manganese ore by 560 tons, and the submerged arc furnace resumes production 15 days ahead of schedule, increasing output by 760 tons. The overall repaired furnace lining adopts the new process and operates safely for three years after the furnace is opened.

Claims

1. A ramming and repairing process for a manganese silicon ore furnace lining and a furnace opening process, characterized in that The steps include: S1. Preparation before shutdown: Preparation before shutdown includes electrode control, batching adjustment and iron tapping management; Electrode control: 2-3 days before the furnace is shut down, the electrode is placed in the furnace, and the electrode is displaced downward to reduce the electrode pressure. The electrode displacement is inserted downward to 500-650mm. Ingredient adjustment: Increase the amount of self-produced slag by 50-80kg / batch the day before the shutdown; Iron tapping management: stop feeding the last batch of iron and let the material level drop naturally. When tapping, open both furnace holes at the same time and block the holes when slag and iron stop flowing out. S2. Cleaning of residual charge and slag in the furnace: First clean the loose materials on the upper part, then clean the residual slag iron on the lower part. During the cleaning process, the burned and broken carbon bricks are cleaned together until the carbon bricks are regular. S3, ramming and leveling of furnace bottom and overall repair: On the basis of the cleaned regular carbon bricks, a layer of 200-500mm cold rammed paste is first knotted on the furnace bottom, and then the cold rammed paste is used to knot and compact the carbon ring and the furnace bottom support formwork to connect the carbon ring and the furnace bottom into a whole; S4. Preparation before baking: Preparation before furnace baking includes furnace eye preparation, furnace bottom preparation, soot blowing preparation and electrode displacement control; Preparation of furnace eye: Use anhydrous taphole mud to plug the furnace mouth, so that the furnace mouth forms a 300mm taphole mud bag; use coke powder to fill and tamp from the furnace mouth to a depth of 500mm; then use eye-plugging mud balls to plug the outer furnace mouth to a depth of 200mm; Preparation of furnace bottom: A layer of clay bricks is laid around the furnace bottom and carbon ring to form a protective layer; Preparation for soot blowing: When the fire is weak, connect compressed air to send air into the bottom of the furnace; Electrode displacement control: The electrode displacement is controlled at the upper limit, and the electrode is not pressed before power is supplied; S5, Ignition oven: The furnace after ramming repair is mainly used for baking furnace lining, following the principle of heating speed from slow to fast, flame from small to large, and current from small to large, including low-fire furnace and high-fire furnace; Baking the furnace with a small fire: Before ignition, lay 300-500mm chopped firewood at the bottom of the furnace, and sprinkle diesel on the chopped firewood for easy ignition. The flame height should not exceed 1 / 2 of the furnace depth. Baking the furnace lining with a small fire in the early stage. The time for baking the furnace with a small fire is organized according to the 48h of the whole firewood baking time. During the baking process, gradually add firewood to the furnace according to the fire and temperature in the furnace. High-fire furnace baking: After low-fire furnace baking, high-fire furnace baking is carried out. The fire and temperature are increased by increasing the amount of firewood. When adding firewood, try to make the firewood burn evenly and violently. The flame height cannot exceed the position of the furnace door. The furnace baking time is organized according to 30-36 hours; S6, power supply oven: After the wood-fired baking is completed, the dead ash in the furnace is blown out using a compressed air pipe, and the coke prepared in the top bunker is lowered into the furnace to a height of more than 1m. The material tip is flattened using a rake, and the coke in the furnace is pushed to the same level; the electrode is pressed and released, and the three-phase electrode displacement is controlled to 500mm-550mm before the electrode is pressed and released. The electrode is pressed and released above the material surface, and the electrode is compacted in the coke by means of downward displacement. After the displacement is lifted, the coke is filled under the electrode, and the coke is compacted repeatedly; The furnace is dried by indirect power supply. When the electrode temperature or the furnace lining temperature rises too fast, the power supply is stopped as needed to control the heating speed. After the electric drying is carried out for 3 days or the electrode temperature reaches 600℃, silicon manganese dry slag is added to the furnace for drying. S7, silicon-manganese dry slag drying furnace; After the electric drying is completed, the silicon-manganese dry slag material is put into the belt drying furnace. During the dry slag drying process, the power factor is controlled above 0.85 to ensure the electrode work. When there is slag spraying at the root of the electrode in the furnace, coke is added according to the actual situation. After consuming 300,000 kWh of electricity, slag discharge is organized; Feeding method: Use a feeding pipe to feed materials evenly. The speed of the material surface is mainly to cover the arc light. The area with arc light is controlled by a furnace tamping machine. The material surface is controlled at 2 / 3 of the highest material surface, and the material surface is gradually increased. It takes 2-4 furnaces to add the material surface to the same height as the furnace mouth. There should be materials in the material bin on the top of the furnace at all times. S8. Invest in normal material ratio and gradually strengthen to normal: After 2-3 days of dry slag drying, normal material ratio is started. According to the power supply system, the load is gradually increased to strengthen the furnace condition. When the load is increased to 80% of the normal load, compensation is organized after 1-2 days of stable furnace discharge, and the load is increased to normal smelting.

2. The ramming repair and furnace opening process of the manganese silicon ore furnace lining as claimed in claim 1 is characterized in that: Before cleaning the loose materials on the upper part as described in S2, lock the electrodes first, and after stopping the furnace, break all the electrodes below 100mm of the copper tile, raise the electrode displacement to the upper limit and fix it.

3. The ramming repair and furnace opening process of the manganese silicon ore furnace lining as claimed in claim 2 is characterized in that: Before tying a layer of 200-500mm cold rammed paste on the furnace bottom as described in S3, CCS paste is used for leveling.

4. The ramming repair and furnace opening process of the manganese silicon ore furnace lining as claimed in claim 3 is characterized by: The cold pounding paste in S3 is K paste.

5. The ramming repair and furnace opening process of the manganese silicon ore furnace lining as claimed in claim 4 is characterized in that: The furnace bottom formwork described in S3 uses a 4-5 mm steel plate.

6. The ramming repair and furnace opening process of the manganese silicon ore furnace lining as claimed in claim 5, characterized in that: The thickness of the cold ramming paste used to connect the ring carbon and the furnace bottom into a whole in S3 is 80-100 mm.

7. The ramming repair and furnace opening process of the manganese silicon ore furnace lining as claimed in claim 6, characterized in that: During the process of allowing the material surface to drop naturally in the preparation before shutdown as described in S1, the material level in the furnace top silo shall not exceed 2 batches; before shutdown, all materials in all furnace top material pipes shall be added to the furnace, and no stockpiled materials are allowed; three days before shutdown, the height of the paste column shall be controlled, and the height of the paste column shall be reduced by 200mm for each team, and finally the height of the paste column shall be controlled at 2.5-3.0m, and no further paste shall be added.

8. The ramming repair and furnace opening process of the manganese silicon ore furnace lining as claimed in claim 7, characterized in that: The dry slag drying furnace described in S7 uses all the dry slag produced in the silicon manganese production process, and the manganese content of the dry slag is less than 10%.