Stone cutting excavation construction method for deep foundation pit close to existing line

By using a combination construction method of double-knife mine cutting machine and diamond rope saw in close proximity to the railway line and the complex surrounding environment, the vibration and safety risks in traditional stone blasting and excavation construction are solved, and a fast and safe deep foundation pit is achieved. Stone cutting improves construction efficiency and stone utilization.

CN118906249APending Publication Date: 2024-11-08CHINA RAILWAY NO 5 ENGINEERING GROUP CO LTD +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410802186.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-20
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

In close proximity to existing railway lines and the complex surrounding environment, traditional stone blasting and excavation construction leads to great vibration and interference, high safety risks, and it is difficult to ensure the safety of deep foundation pit construction.

Method used

Using a double-knife mine cutting machine for vertical cutting and diamond rope saw horizontal rock breaking construction. Cut into blocks first and then horizontally, reducing the perforation process, reducing labor intensity and corner impact, and using track laying and auxiliary support sleeves to improve cutting efficiency and safety sex.

Benefits of technology

It realizes rapid and safe cutting of deep foundation pit stones in complex environments, reduces construction vibration and interference, improves cutting efficiency and safety, ensures the safety of existing railways and surrounding buildings, and has a high stone utilization rate.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118906249A_ABST
    Figure CN118906249A_ABST
Patent Text Reader

Abstract

The invention discloses a deep foundation pit stonework cutting excavation construction method adjacent to an existing line, and belongs to the technical field of deep foundation pit stonework cutting excavation. Measuring and positioning the foundation pit earthwork after the base surface is leveled, and lofting the cutting height; laying a track on the earthwork base surface of the foundation pit; rock stratum vertical cutting is conducted, specifically, a double-blade mine cutting machine is adopted to conduct longitudinal and transverse interval cutting on the foundation pit earthwork into set square stones; a diamond wire saw device is adopted for conducting horizontal cutting and rock breaking on the square stones formed through longitudinal and transverse cutting; and hoisting and transferring. According to the method, cutting into blocks is conducted firstly, then rope saw sleeving horizontal cutting is conducted, punching is avoided, the rope saw chain of the rope saw cutting equipment can be conveniently arranged to the cutting starting position, the arrangement labor intensity is greatly reduced, placement is not affected by corners, the arrangement difficulty is greatly reduced, the rope saw chain can be arranged without opening, the installation efficiency is greatly improved, and the cost is reduced. And the cutting efficiency is higher.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of deep foundation pit stone cutting, and relates to a deep foundation pit stone cutting excavation construction method close to an existing line. Background Art

[0002] In the deep foundation pit excavation in the vicinity of the existing railway operation line and the surrounding complex environment, the shortcomings of traditional stone blasting excavation are: the construction process brings great vibration and interference, the deep foundation pit excavation safety risk is high, and it is impossible to ensure the safety of deep foundation pit construction, the existing railway operation line and the surrounding buildings. The Chinese patent application (publication number is CN116277516 A) discloses a construction method for mechanical excavation of stone in urban deep foundation pits. During the cutting process, only the stone cutting and excavation of the deep pit bedrock is carried out. The cutting process is: cutting the vertical surface of the foundation stone - cutting the horizontal surface of the foundation stone - cutting into blocks in another direction perpendicular to the vertical surface cutting direction of the foundation stone. When cutting the horizontal surface of the foundation stone, a drilling process is required to arrange the rope saw chain of the rope saw cutting equipment to penetrate. The penetration method is labor-intensive, there are corners, and it is not easy to penetrate. Moreover, when lattice columns are arranged in the foundation pit, it is difficult to use this method for cutting. In addition, the deep foundation pit excavation in the city is faced with stone excavation. In this application, the deep foundation pit excavation in the existing railway operation line and the surrounding complex environment, the working conditions are more complicated. Summary of the invention

[0003] The technical problem to be solved by the present invention is to provide a construction method for cutting and excavating stone in a deep foundation pit close to an existing line, which can quickly achieve horizontal cutting, is easy to insert a rope saw chain, has low labor intensity, does not require pulling, and does not need to consider the impact of corners.

[0004] The technical solution adopted by the present invention is: a construction method for cutting and excavating stone in a deep foundation pit close to an existing line, the method comprising the following steps: Step 1: Leveling the base surface: Use a rope saw to cut the foundation pit soil to level the base surface; Step 2: Positioning and staking out: measure and locate the foundation pit earthwork after the base surface is leveled, and stake out the cutting height; Step 3: Track laying: track laying on the foundation pit soil base; Step 4, cutting machine in place: install the double-blade mining cutting machine at the starting position on the track; Step 5, vertical cutting of rock strata: a double-blade mining cutter is used to cut the foundation pit soil into set blocks of stone at intervals in the vertical and horizontal directions; wherein, for the position of the lattice column, four vertical cutting seams are cut around the lattice column to form small blocks of cut rock; Step 6: Cutting and breaking rocks with a wire saw: Using a diamond wire saw to horizontally cut the blocks of stone cut vertically and horizontally; Step 7: Transfer within the pit and hoist for transportation outside: The cut stone blocks are transferred and hoisted outside the foundation pit.

[0005] Furthermore, the specific method and steps for leveling the base surface in the above step 1 are as follows: 1.1. Excavate the foundation pit to the rock layer, and clean the rock surface with manual and mechanical methods. After cleaning, diamond wire saw equipment is used to cut the base surface according to the undulating state of the rock layer; 1.2. First determine the leveling elevation, use a pneumatic drill to drill holes along the raised parts of the rock surface to allow the rope saw chain to pass through, and cut the raised rock layer. After cutting, use mechanical crushing and excavation for transportation.

[0006] Furthermore, the specific steps of positioning and setting out in the above step 2 are as follows: 2.1 After the base surface is leveled, use a total station to measure and locate according to the cutting size. When the distance from the retaining structure is less than 1.5m (less than the width of a single block), reserve 20cm of working space; when excavating the slope, the staggered surface produced by cutting each layer is used as the slope space; 2.2 When laying out, first determine the elevation of the cutting point, calculate the height difference between the cutting surface and the design support and base elevation, and determine the required cutting depth, that is, the depth is calculated based on the relative height difference. Assuming that the maximum cutting depth of a single layer is 1.5 m, if the distance between the cutting surface and the bottom of the concrete support is H, in m, round H / 1.5. If there is no remainder, cut according to H / 1.5 layers, otherwise cut according to H / 1.5+1 layers; 2.3 For small foundation pits with an excavation depth of less than 1.5m, cutting shall be carried out according to the designed size; when the depth exceeds 1.5m, a 20cm working platform shall be added on each side for every additional 1.5m.

[0007] Furthermore, the specific method and steps for track laying in step 3 above are as follows: 3.1 After the base surface is cleaned and the ground is relatively flat, track laying should be carried out. First, the loose slag on the surface of the track support and reinforcement should be cleaned to ensure that the foundation of the track support is firm and reliable and the ground is relatively flat; 3.2 The track adopts a 4-meter standard track, that is, a short track. Each section of the track is fixedly connected with an auxiliary support sleeve and bolts or a connecting plate with bolts. The level meter is used to level the two track surfaces so that they are parallel to the same horizontal plane. The two tracks must be parallel and the two track surfaces should be on the same level. The horizontal error should be less than 1 / 1000; 3.3 According to the cutting depth of each layer, first install the first track, and then reinforce it after checking the straightness and flatness of the cutting edge. Based on the first track, use a level ruler and caliper to install the second track with a spacing of 2.6mm. The width of each track should be consistent and the installation should be horizontal, firm and reliable. 3.4 When the track is laid directly on the ground, two adjacent short tracks are butt-jointed and fixedly connected to the ground with auxiliary support sleeves, or laid using the following methods: use guide holes to drive steel fibers to fix and clamp them to the bedrock; when the rock surface is relatively flat and the track is less than 100mm from the ground, use holes drilled on both sides of the track to insert steel pins for fixation; when the distance from the rock surface is greater than 100mm but less than 200mm, use holes drilled in the rock between the two tracks to insert steel pins and use two φ22 round steels to cross weld and fix them, and use sleepers and wooden wedges for leveling; for bedrock with a height difference greater than 200mm, rock square materials can be used for padding or jacks can be used for automatic fine-tuning; 3.5 After the track is installed, the verticality and horizontality of the track should be checked again. A laser level is installed at the end of the track to automatically level and straighten the track. Multiple cutting tracks can be installed at one time. The starting end of each track is reserved for installing a transition track. The transition track is used to connect adjacent track groups to transfer the double-blade mining cutter and perform continuous cutting on the same track line. The detachable transition track can easily and quickly realize the shifting of the double-blade mining cutter to the adjacent track group to avoid the large crane being unable to shift due to the obstruction of the top beam.

[0008] Furthermore, the above-mentioned double-blade mining cutting machine is equipped with a protective baffle at one end where the walking on each track ends. The protective baffle is rotatably connected to two supports on both sides in the width direction. The two supports are fixedly connected to the base plate. A plurality of compression springs are connected to the back of the protective baffle. The plurality of compression springs are fixedly connected to the support rod. The lower end of the support rod is fixedly connected to the base plate. The base plate is fixedly connected to the track. The base plate is connected to the two tracks through two quick clamping mechanisms. The quick clamping mechanisms include a pressure plate, a push plate, a push rod, a connecting rod one, a connecting rod two and a connecting rod three. The pressure plate is a T-shaped plate. Two connecting rods one are hinged on both sides of one end of the big head. The other ends of the two connecting rods one are hinged to one end of the push plate. The other end of the push plate is hinged to two The two cams are connected by a screw bolt to the top of the push plate, and the two cams are connected by a screw bolt to the top of the push plate, and the two cams are connected by a screw bolt to the bottom of the push plate.

[0009] Furthermore, the specific steps for installing the cutting machine in step 4 are as follows: 4.1 Use a car crane to hoist the double-blade mining cutter onto the track, use the wheels and adjustable bolts at the bottom of the double-blade mining cutter to fine-tune it to the exact position of the track, and then lower the bolts to drop the wheels onto the track; 4.2 Determine the position of the two spindle boxes according to the width of the stone block to adjust the distance between the two saw blades; 4.3 Clear all obstacles around the machine and check the height of the saw blade. The distance between its lowest edge and the highest point of the cutting surface should be 10mm to 20mm.

[0010] Furthermore, the specific method and steps of the vertical cutting by the cutting machine in the above step 5 are as follows: 5.1 The maximum cutting length of deep foundation pit stone cutting is 3m, height 1.5m and cutting width 1.5m according to the site and rock integrity. When encountering lattice columns, leave 20cm margin on the four sides of the lattice columns for cutting. Strictly control the cutting depth of the rock stratum. Accurately calculate the cutting depth according to the distance between the track elevation and the outer edge of the saw blade, so that the broken rock surface is level and consistent, avoiding over-excavation and under-excavation during the cutting process; 5.2 When the double-blade mining cutting machine is used for initial cutting, a φ2200mm saw blade is used. When the cutting depth reaches 800mm, a φ3000mm saw blade is replaced for cutting (if a φ3000mm saw blade is used for initial cutting, it is very easy to cause shaking); when installing the saw blade, the runout of the saw blade end face and the radial face shall not exceed 0.5mm, and at the same time, check whether the cutter disc and the bolts of each fastening part are loose; 5.3 When cutting each layer, the distance should be set at a convenient place for stone lifting or at a distance from the temporary construction road (determined according to the working radius of the lifting equipment to meet the lifting requirements; if an 80T truck crane with a working radius of 8m and a boom length of less than 36m is used, the maximum lifting weight requirement of 17.55t for this project can be met). The distance should be set according to the working radius of the lifting equipment. The longitudinal cutting line should be cut at a spacing of 0.75m within the range of 4.5m, and the horizontal length should be controlled at about 2m. After the rock formation in this range is cut, it should be squeezed and fractured or mechanically broken to serve as the rock formation breaking working surface and transfer channel. After the breaking working surface is completed, the cutting width of other areas should avoid the lattice columns according to the arrangement of the lattice columns on site, and the cutting should be carried out according to the requirement that the cutting width should not exceed 1.5m. When cutting the horizontal and vertical cutting lines, the on-site positioning requirements should be followed; 5.4 For small foundation pits such as water collection wells at the bottom of foundation pits and downward beams, on-site setting out and determination of cutting depth shall be carried out according to the designed dimensions before cutting. Cutting and separation shall be carried out along the scope of the foundation pit to avoid over-excavation and under-excavation, and mechanical crushing and transportation shall be adopted; During the cutting process, if there is internal gravel, the current of the motor driving the circular saw will be monitored to change suddenly. When the sudden change reaches the set value, the cutting speed will be reduced. Each time the speed is reduced according to the set speed, after one or more speed reductions, the current drops below the set threshold, and the cutting is performed at a uniform speed after the speed reduction. When the current stabilizes to the set range, the gravel area is avoided and the speed is gradually adjusted to the speed before the speed reduction. 5.5 Equipment operation requirements: 1. When cutting, the blade is against the stone and it is forbidden to start the machine. The circular saw blade can only be lowered for cutting after it runs smoothly. The lowering speed is adjusted according to the hardness of the base rock to achieve the best lowering requirement. The maximum cutting depth per time should not exceed 10cm. There must be sufficient cooling water during cutting. Cutting without water or with little water is strictly prohibited. 2. When cutting to the end, the blade should be stopped first. To continue cutting, the blade should be lowered again. When lowering the blade, make sure that the main machine is not lifted. When stopping cutting, the saw blade should be raised above the ground level before the motor can be stopped. 3. After the stone is cut, the cutter must be moved away from the end before the cutter can be lifted out; 4. Set up a sump on each cutting work surface to pump the cutting cooling water to the sedimentation tank on site and recycle it after sedimentation treatment.

[0011] Furthermore, the specific method steps of cutting the rock with a rope saw in step 6 are as follows: 6.1 For each layer of rock fracture working face, the rock with a cutting width of 0.75m is cut by hammering the cutting seam with a Φ22 round steel tip chisel (arranged according to the hardness of the rock) and a sledgehammer to squeeze holes, thereby generating horizontal squeezing stress, so that the rock is horizontally broken at the bottom of the cut and hoisted for transportation or mechanical equipment is used to break it for transportation; 6.2 After the rock-breaking working surface is equipped with wire saw cutting, the wire saw chain is installed to the bottom of the cutting seam using diamond wire saw equipment to perform horizontal cutting of the rock. The wire saw chain should be installed away from the lattice column. It is forbidden to include the lattice column in the wire saw rock-breaking range to avoid damaging the lattice column and causing the support to become unstable. 6.3 After the chain is installed, adjust the tension of the driving wheel through the control panel to ensure that the diamond rope is properly tightened, and supply circulating cooling water to drive the driving wheel to drive the rope saw chain to rotate and cut. During the cutting process, the stability of the machine base must be closely observed, and the offset of the guide wheel must be adjusted at any time to ensure that the cutting rope is in the same plane; 6.4 Adjust the cutting parameters by operating the control panel to ensure that the linear speed of the wire saw chain is about 20m / s. Sufficient flushing fluid should be provided during the cutting process to ensure the cooling of the diamond wire and take away the grinding chips. The cutting operation should be stable in speed, parameters and equipment.

[0012] Furthermore, the specific method steps for the pit transfer and hoisting transportation in the above step 7 are as follows: 7.1 After each layer of rock is cut to a point where a forklift can pass through, it shall be transported to a fixed lifting point by a forklift; no one is allowed to walk or stay within the working radius of the boom of the lifting equipment at the fixed lifting point; for lifting at night, there must be sufficient lighting above and below, and there must be an experienced crane operator to direct; 7.2 Mobile hoisting equipment shall be equipped according to the size of the project stone blocks. Each rock block shall be hoisted as a whole. During the hoisting, a dedicated person shall observe and direct from a distance, directing the crane driver to hoist slowly. During the process of lowering the rock blocks out of the foundation pit, a dedicated person shall use a traction rope to hold the rock blocks and adjust the direction appropriately. It is strictly forbidden to collide with the upper beams, side lattice columns and side walls of the foundation pit; 7.3 Before lifting the rock, the integrity of the cut rock should be checked. If there are obvious cracks or fissures, lifting is prohibited to avoid brittle fracture during lifting, which may affect the safety of workers and foundation pit support. 7.4 The rock block is hoisted by two 6*37 wire φ32mm wire ropes. The wire ropes are laid at the 1 / 4~1 / 5 position at both ends of the rock block. The wire ropes and the corners of the rock block are isolated and protected by rubber. The wire ropes need to be maintained regularly and replaced immediately if they are worn and broken. 7.5 After the rock blocks are hoisted out of the foundation pit, they are transported out using a flatbed truck and placed stably in the car to ensure that they are stable in the car to prevent them from falling during transportation. If the rock blocks are not transported out in time, a forklift can be used to transfer the square materials to a temporary transfer site, where they can be stacked neatly, stably and reliably.

[0013] Furthermore, the track in the above step 3 adopts a multi-segment short track splicing structure, and the two adjacent short tracks are connected with auxiliary support sleeves. The auxiliary support sleeve is provided with a through groove with an upper opening, and the through groove is consistent with the track bottom structure. Raised pressing plates are provided on both sides of the bottom of the auxiliary support sleeve, and an auxiliary support sleeve is also sleeved near the middle of the short track. Each auxiliary support sleeve is locked on the foundation pit surface by a pressing plate and an expansion screw. A transition track group is installed between two adjacent groups of tracks. The transition track group can be obliquely spliced ​​to the two adjacent groups of tracks near the ends. The track of the transition track group is connected to the main line track with a detachable elbow sleeve. Multiple auxiliary support sleeves are installed on the transition track group, and the bottom surface of the auxiliary support sleeve is provided with a hard rubber shock-absorbing pad.

[0014] Beneficial effects of the present invention: Compared with the prior art, the effects of the present invention are as follows: (1) In the case of deep foundation pit excavation in the vicinity of existing lines and in complex surrounding environments, a combination of double-blade mine vertical cutting and diamond wire saw horizontal rock breaking is used for construction. First, a mine cutter is used in the vertical direction to cut in sections and layers to a certain depth. Then, a diamond wire saw is used in the horizontal direction to cut the rock into blocks. The foundation pit rock layer is cut, broken, and hoisted for transportation. That is, the blocks are cut first, and then the rope saw is used for horizontal cutting. There is no perforation process, which makes it easy to arrange the rope saw chain of the rope saw cutting equipment to the starting position of the cutting. The labor intensity of the arrangement is greatly reduced, the corner does not affect the placement, the difficulty of the arrangement is greatly reduced, and the rope saw chain can be arranged without opening, which is efficient in installation. The efficiency is greatly improved, and the cutting efficiency is higher; it also solves the shortcomings of traditional stone blasting excavation, reduces the vibration and interference caused by construction, reduces the safety risk of deep foundation pit excavation, and ensures the safety of deep foundation pit construction, existing railway operating lines and surrounding buildings. The construction method of the present invention is simple and fast to operate, can be constructed on multiple working surfaces at the same time and can operate 24 hours a day, and has high construction efficiency; the foundation pit is formed regularly, the size is accurately controlled, there is no over-excavation, and the consumption of backfill materials is reduced; at the same time, it does not destroy the integrity of the foundation rock, which is conducive to the sealing of water leakage at the bottom of the pit, and the construction quality is reliable; the square rock formed by cutting is regular in shape, has a high reusability rate, and effectively utilizes stone resources. The construction safety, quality and construction period are ensured. Compared with the previous construction technologies at home and abroad, the technology is original, advanced, applicable and safe. The technology is mature and reliable. When the deep foundation pit is excavated close to the existing line and in the surrounding complex environment, it is necessary to arrange the retaining piles and the transverse support beams and longitudinal support beams connected with the retaining piles at the top of the deep foundation pit. The existence of this structure greatly affects the efficiency and convenience of hoisting. Therefore, the present invention adopts block cutting and transportation to the centralized hoisting point to facilitate hoisting. (2) For the location of the lattice column, four vertical cutting seams are cut around the lattice column to form small cutting rock blocks, which can effectively avoid the cutting of the lattice column and affect the support of the lattice column; (3) Setting up a working surface to facilitate the arrangement of diamond wire saw equipment for horizontal surface cutting; (4) The use of auxiliary support sleeves for track splicing and auxiliary support can greatly improve the track installation efficiency. The auxiliary support sleeves are fixed by pressing plates, and the pressing space is wide, which is convenient for track locking. After the auxiliary support is inserted into the track, the side is locked with locking screws, which makes installation quick and convenient. The transition track and elbow sleeve are arranged to enable the double-blade mining cutter to move quickly to the adjacent track group, which can prevent the lifting equipment from being affected by the beam above the foundation pit or the lifting position from being limited. The detachable structure is easy to assemble and disassemble, and can be reused to improve equipment utilization. The hard rubber shock-absorbing pad is set to improve the shock-absorbing effect of the track, and prevent the vibration of the cutting motor from being transmitted to the ground through the track and then interfering with the cutting tool, affecting the tool cutting. (5) A protective baffle is provided. For a high-speed cutting circular saw, when broken stones or blade damage occur, the broken stones or damaged blades hit the protective baffle, which plays an effective protective role. A compression spring is provided to play an elastic buffering role for the hitting stones, so as to prevent the protective baffle from being damaged rapidly due to excessive force instantaneously. When the push rod moves downward, the pressure plate can be gradually extended to the rubber block at the bottom of the rail top and reach a certain position. The pressure plate is pressed against the rubber block by the push rod, and the pressure plate is pulled out conveniently through various connecting rod structures. It is far away from the track and extends to the top of the track for tightening, which is convenient for quick disassembly. When in use, the assembly and disassembly nut is gradually rotated, and the push rod is pulled upward. The free end of the pressure plate is away from the track. A groove is set at the bottom of the base plate. The groove is against the track to achieve rapid limit. Loosen the assembly and disassembly nut. Under the elastic force of the compression spring, the push rod moves downward, and then drives the pressure plate to move toward the bottom of the track top. When the rubber block contact height reaches 0.5cm, the rubber block is pressed against the bottom of the track top, and then the assembly and disassembly nut is gradually rotated. Finally, the pressure plate relies on the elastic force to press against the track. The second compression spring and the rubber block can also play an elastic buffering and protective role for the entire protective baffle. When encountering a large stone impact, the force is enough to directly overcome the elastic force of the second compression spring and then separate the pressure plate from the bottom of the track top to achieve maximum protection, double buffering, and better effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a schematic diagram of the construction method flow chart; Figure 2 It is a schematic diagram of the vertical cutting line arrangement structure; Figure 3 It is a schematic diagram of the horizontal cutting line arrangement structure; Figure 4 It is a schematic diagram of the rock segmentation structure; Figure 5 It is a front view structural diagram of a double-blade mining cutting machine; Figure 6 It is a schematic diagram of the side structure of a double-blade mining cutting machine; Figure 5-6 Among them, 1-saw blade hoisting mechanism; 2-spare saw blade hanger; 3-cylinder lifting mechanism; 4-travel track; 5-appearance sheet metal mechanism; 6-travel mechanism; Figure 7 This is a schematic diagram of the structure of the protective plate installed on the track; Figure 8 This is a schematic diagram of the installation structure of the protective baffle from the rear view; Fig. 9 It is a schematic diagram of the structure viewed from above the cutting line; Fig.10 This is a schematic diagram of the track installation structure; Fig.11 This is a schematic diagram of the cross-sectional structure of the auxiliary support sleeve installation; Fig.12 It is a schematic diagram of the structure of the corner auxiliary support sleeve; Fig.13 A top view of the corner auxiliary support sleeve structure; Fig.14 It is a schematic diagram of the anti-vibration mechanism structure. DETAILED DESCRIPTION

[0016] The present invention is further described below in conjunction with the accompanying drawings and specific embodiments.

[0017] Example 1: Figure 1 to Figure 14 As shown, a construction method for cutting and excavating a deep foundation pit adjacent to an existing line includes the following steps: Construction method Construction preparation: Before formal construction, technical management personnel should be familiar with the drawings, understand the geological conditions, the outer dimensions of the foundation pit or the dimensions of the pit in the pit, the base elevation and other relevant parameters, and conduct technical and safety briefings for the operators to meet the conditions for starting construction. Carefully check the geological survey data, find out the lithology, geological structure, thickness of the bedrock weathering layer, degree of fragmentation, weak interlayer conditions and groundwater conditions, investigate and determine the lithology of the rock, analyze the value of renewable utilization, and formulate corresponding solutions and emergency measures for common problems encountered in construction. Connect the power supply and water source, and transport the materials and machinery used for construction to the site. The cables in the pit need to be protected by insulating tubes and fixed to temporary columns with triangular supports or insulating hangers. Cables are prohibited from dragging on the ground.

[0018] Step 1: Leveling the base surface: Use a rope saw to cut the foundation pit soil to level the base surface; The specific steps are as follows: 1.1. Excavate the foundation pit to the rock layer, and clean the rock surface with manual and mechanical methods. After cleaning, diamond wire saw equipment is used to cut the base surface according to the undulating state of the rock layer; 1.2. First, determine the leveling elevation, use a pneumatic drill to drill holes along the raised parts of the rock surface to allow the rope saw chain to pass through, and cut the raised rock layers. After cutting, use mechanical crushing and excavation for transportation; Step 2: Positioning and staking out: measure and position the foundation pit earthwork after the base surface is leveled, and stake out the cutting height; the specific steps are as follows: 2.1 After the base surface is leveled, use a total station to measure and locate according to the cutting size. When the distance from the retaining structure is less than 1.5m, reserve 20cm of working space; when excavating the slope, the staggered surface produced by cutting each layer is used as the slope space.

[0019] 2.2 When laying out, first determine the elevation of the cutting point, calculate the height difference between the cutting surface and the design support and base elevation, and determine the required cutting depth, that is, the depth is calculated based on the relative height difference. Assume that the maximum cutting depth of a single layer is 1.5 m. If the distance between the cutting surface and the bottom of the concrete support is H, in m, round H / 1.5. If there is no remainder, cut according to H / 1.5 layers, otherwise cut according to H / 1.5+1 layers.

[0020] 2.3 For small foundation pits (water collection wells, downturned beams) with an excavation depth of less than 1.5m, cutting can be carried out according to the designed size; when the depth exceeds 1.5m, a 20cm working platform needs to be added on each side for every additional 1.5m; Step 3: Track laying: track laying is carried out on the foundation pit soil base surface; the specific method and steps are as follows: 3.1 After the base surface is cleaned, the ground is relatively flat. When laying the track, first clean the loose slag on the surface of the track support and reinforcement to ensure that the foundation of the track support is firm and reliable and the ground is relatively flat.

[0021] 3.2 The track adopts a 4-meter standard track, that is, a short track. Each section of the track is fixedly connected with an auxiliary support sleeve and bolts or a connecting plate with bolts. The level meter is used to level the two track surfaces so that they are parallel to the same horizontal plane. The two tracks must be parallel and the two track surfaces should be on the same level. The error should be less than 1 / 1000; 3.3 According to the cutting depth of each layer, first install the first track, and then reinforce it after checking the straightness and flatness of the cutting edge. Based on the first track, use a level ruler and caliper to install the second steel track with a spacing of 2.6mm. The width of each track should be consistent and the installation should be horizontal, firm and reliable. 3.4 When the track is laid directly on the ground, two adjacent short tracks are butt-jointed and fixedly connected to the ground with auxiliary support sleeves, or laid using the following methods: use guide holes to drive steel fibers to fix and clamp them to the bedrock; when the rock surface is relatively flat and the track is less than 100mm from the ground, use holes drilled on both sides of the track to insert steel pins for fixation; when the distance from the rock surface is greater than 100mm but less than 200mm, use holes drilled in the rock between the two tracks to insert steel pins and use two φ22 round steels to cross weld and fix them, and use sleepers and wooden wedges for leveling; for bedrock with a height difference greater than 200mm, rock square materials can be used for padding or jacks can be used for automatic fine-tuning; 3.5 After the track is installed, the verticality and horizontality of the track should be checked again. A laser level is installed at the end of the track to automatically level and straighten the track. Multiple cutting tracks can be installed at one time. The starting end of each set of tracks is reserved for installing transition tracks. The transition tracks are used to splice adjacent track groups to transfer the double-blade mining cutting machine and perform continuous cutting on the same track line. Step 4: Put the cutting machine in place: Install the double-blade mining cutting machine at the starting position on the track; the specific steps are as follows: 4.1 Use a car crane to hoist the double-blade mining cutter onto the track, use the wheels and adjustable bolts at the bottom of the double-blade mining cutter to fine-tune it to the exact position of the track, and then lower the bolts to drop the wheels onto the track; 4.2 Determine the position of the two spindle boxes according to the width of the stone block to adjust the distance between the two saw blades; 4.3 Clear all obstacles around the machine and check the height of the saw blade. The distance between its lowest edge and the highest point of the cutting surface should be 10mm to 20mm; Step 5: Vertical cutting of rock strata: Use a double-blade mining cutter to cut the foundation pit soil into set blocks of stone at intervals in the vertical and horizontal directions. The specific method and steps are as follows: 5.1 The maximum cutting length, height and width of deep foundation pit stone cutting shall be 3m, 1.5m and 1.5m respectively (which can be adjusted according to the actual situation) according to the site and the integrity of the rock formation. When encountering lattice columns, a margin of 20cm shall be left on the four sides of the lattice columns for cutting. The cutting depth of the rock formation shall be strictly controlled. The cutting depth shall be accurately calculated according to the distance between the track elevation and the outer edge of the saw blade, so that the rock surface is level and consistent, avoiding over-excavation and under-excavation during the cutting process. 5.2 Use a φ2200mm saw blade for the initial cut, and replace it with a φ3000mm saw blade when the cut reaches a depth of 800mm (if a φ3000mm saw blade is used for the initial cut, it is very easy to cause shaking); when installing the saw blade, the runout of the end face and the radial face of the saw blade shall not exceed 0.5mm, and at the same time check whether the cutter disc and the bolts of each fastening part are loose; 5.3 When cutting each layer, the cutting shall be done at a location convenient for stone lifting or at a set distance from the temporary construction road. The set distance shall be determined according to the working radius of the lifting equipment. The longitudinal cutting line shall be cut at a spacing of 0.75m within the range of 4.5m, and the horizontal length shall be controlled at about 2m. The rock formation in this range shall be cut by extrusion fracture or mechanical breaking to serve as the rock fracture working surface and transfer channel. After the rock fracture working surface is cut, the cutting width of other areas shall avoid the lattice columns according to the arrangement of the lattice columns on site, and the cutting shall be carried out according to the requirement that the cutting width shall not exceed 1.5m. The horizontal and longitudinal cutting lines shall be cut according to the on-site positioning requirements; 5.4 For small foundation pits such as water collection wells at the bottom of foundation pits and downward beams, on-site setting out and determination of cutting depth shall be carried out according to the designed dimensions before cutting. Cutting and separation shall be carried out along the scope of the foundation pit to avoid over-excavation and under-excavation, and mechanical crushing and transportation shall be adopted; During the cutting process, if there is internal gravel, due to the change in the force of the disc cutter, the current of the motor driving the circular saw will be monitored and suddenly changed. When the sudden change reaches the set value, the cutting speed will be reduced. Each time the speed is reduced according to the set speed, after one or more speed reductions, the current drops below the set threshold, and the cutting is performed at a uniform speed after the speed reduction. When the current stabilizes to the set range, the gravel area is avoided and the speed is gradually adjusted to the speed before the speed reduction. Through this control method, the cutter can be effectively protected, the damage of the cutter can be avoided, the service life of the cutter can be increased, the cost can be reduced, and the downtime can be reduced. 5.5 Equipment operation requirements: 1. When cutting, the blade is against the stone and it is forbidden to start the machine. The circular saw blade can only be lowered for cutting after it runs smoothly. The lowering speed is adjusted according to the hardness of the base rock to achieve the best lowering requirement. The maximum cutting depth per time should not exceed 10cm. There must be sufficient cooling water during cutting. Cutting without water or with little water is strictly prohibited. 2. When cutting to the end, the blade should be stopped first. To continue cutting, the blade should be lowered again. When lowering the blade, make sure that the main machine is not lifted. When stopping cutting, the saw blade should be raised above the ground level before the motor can be stopped. 3. After the stone is cut, the cutter must be moved away from the end before the cutter can be lifted out; 4. Set up a water collection pit on each cutting operation surface to centrally pump the cutting cooling water to the sedimentation tank on site for recycling after sedimentation treatment; Step 6: Cutting and breaking rocks with a wire saw: Use diamond wire saw equipment to horizontally cut and break rocks into cubes cut vertically and horizontally. The specific method and steps are as follows: 6.1 For each layer of rock fracture working face, the rock with a cutting width of 0.75m is cut by hammering the cutting seam with a Φ22 round steel tip chisel (arranged according to the hardness of the rock) and a sledgehammer to squeeze holes, thereby generating horizontal squeezing stress, so that the rock is horizontally broken at the bottom of the cut and hoisted for transportation or mechanical equipment is used to break it for transportation; 6.2 After the working surface for wire saw cutting and breaking rock is available, the wire saw chain shall be installed to the bottom of the cutting seam using diamond wire saw equipment to cut and break rock horizontally. The wire saw chain shall be installed away from the lattice column, and it is forbidden to include the lattice column in the wire saw cutting and breaking rock range, so as to avoid damaging the lattice column and causing the support to become unstable; 6.3 After the chain is installed, adjust the tension of the driving wheel through the control panel to ensure that the diamond rope is properly tightened, supply circulating cooling water, and drive the driving wheel to drive the diamond rope to rotate and cut. During the cutting process, the stability of the machine base must be closely observed, and the offset of the guide wheel must be adjusted at any time to ensure that the cutting rope is in the same plane; 6.4 Adjust the cutting parameters by operating the control panel to ensure that the linear speed of the diamond wire is about 20m / s. Sufficient flushing fluid should be provided during the cutting process to ensure the cooling of the diamond wire and take away the grinding chips. The cutting operation should be stable in speed, parameters and equipment. Step 7: Transport within the pit and lift it outside the pit: transport and lift the cut stone blocks outside the pit. The specific steps are as follows: 7.1 Each layer of rock blocks shall be cut to a point where a forklift can pass through, and then be transported to a fixed lifting point by forklift; no one is allowed to walk or stay within the working radius of the crane arm; when lifting the steel cage at night, there must be sufficient lighting above and below, and an experienced crane operator must be in charge.

[0022] 7.2 Equip mobile lifting equipment according to the size of the project stone blocks. Each rock block shall be hoisted as a whole. During the lifting and hoisting, a dedicated person shall observe and direct from a distance, instructing the crane driver to lift slowly. During the process of lowering the rock blocks out of the foundation pit, a dedicated person shall use a traction rope to hold the rock blocks and adjust the direction appropriately. Collision is strictly prohibited.

[0023] 7.3 Before lifting the rock block, the integrity of the cut rock block should be checked. If there are obvious cracks or fissures, lifting is prohibited to avoid brittle fracture during lifting, which may affect the safety of workers and foundation pit support. 7.4 The rock block is hoisted with two 6*37 wire φ32mm steel wire ropes (adjusted according to the size of the hoisted rock block). The steel wire ropes are laid at the 1 / 4~1 / 5 position at both ends of the rock block. The steel wire ropes and the corners of the rock block are isolated and protected by rubber. The steel wire ropes need to be maintained regularly and replaced immediately if they are worn and broken. 7.5 After the rock blocks are hoisted out of the foundation pit, they are transported out using a flatbed truck and placed stably in the car to ensure that they are stable in the car to prevent them from falling during transportation. If the rock blocks are not transported out in time, a forklift can be used to transfer the square materials to a temporary transfer site, where they can be stacked neatly, stably and reliably.

[0024] Furthermore, a protective baffle 101 is installed on the track 301 of the above-mentioned double-blade mining cutter 102. The protective baffle is set. For a high-speed cutting circular saw, when crushed stones or blade damage occur, the crushed stones or damaged blades hit the protective baffle, which plays an effective protective role. The protective baffle 101 is rotatably connected to two supports 103 on both sides in the width direction, and the two supports 103 are fixedly connected to the base plate 104. A plurality of compression springs 105 are connected to the back of the protective baffle 101, and the plurality of compression springs 105 are fixedly connected to the support rod 106. The lower end of the support rod 106 is fixedly connected to the base plate 104, and the base plate 104 is fixedly connected to the track 301. The compression spring is set, which can play an elastic buffering role for the struck stones. To avoid the protective baffle being damaged quickly due to excessive instantaneous force, the base plate 104 is connected to the two rails 301 through two quick clamping mechanisms. The quick clamping mechanisms include a pressure plate 107, a push plate 108, a push rod 109, a connecting rod 110, a connecting rod 2 111 and a connecting rod 3 112. The pressure plate 107 is a T-shaped plate. Two connecting rods 110 are hinged on both sides of one end of the big head. The other ends of the two connecting rods 110 are hinged to one end of the push plate 108. Two connecting rods 2 111 are hinged on both sides of the other end of the push plate 108. The other ends of the two connecting rods 2 111 are hinged to the two connecting rods 3 112 near the middle. The upper ends of the two connecting rods 3 112 are hinged on the hinge seat 113, and the hinge seat 113 is fixedly connected to the base plate 104. The lower ends of the two connecting rods 3 112 are hinged It is connected to both sides of the pressure plate 107 near the middle, and a push rod 109 is fixedly connected to the top of the push plate 108 and is close to the hinge of the two connecting rods 111 and the push plate 108. A push rod 114 is arranged below the push plate 108. The top of the push rod 114 is a ball head structure, and the bottom of the contacting pressure plate is provided with an abutting arc surface, which can achieve stable abutment. The push rod 114 and the push rod 109 remain coaxial, and the push rod 109 is connected with a mounting and disassembly nut 115 (a threaded portion is arranged on the upper end of the push rod) after passing through the base plate 104. A thrust bearing 118 is installed between the mounting and disassembly nut 115 and the base plate 104, and the thrust bearing 118 is sleeved on the push rod. A compression spring 116 is also sleeved on the push rod 109, and both ends of the compression spring 116 abut against the upper end surface of the push plate 108 and the base plate 104. The bottom, the bottom of the rail top of the track 301 is abutted with a rubber block 117, and the top left of the rubber block 117 is provided with a side baffle that abuts against the side of the rail top. The bottom is provided with an abutting step, which is used for the end of the pressure plate 107 to abut. The push rod moves downward, and the pressure plate can be gradually extended to the rubber block at the bottom of the rail top and reach a certain position. The pressure plate is pressed against the rubber block by the push rod. Through various connecting rod structures, it is convenient to pull the pressure plate away from the rail and extend it to the rail top for compression, which is convenient for quick disassembly. When in use, the assembly and disassembly nut is gradually rotated, and the push rod is pulled upward. The free end of the pressure plate is away from the rail. A groove is provided at the bottom of the base plate. After the groove abuts on the rail, rapid limiting is achieved. The assembly and disassembly nut is loosened, and the push rod moves downward under the elastic force of the compression spring.Then the pressure plate is driven to move toward the bottom of the rail top. When the rubber block contact height reaches 0.5cm, the rubber block is pressed against the bottom of the rail top, and then the nut is gradually rotated and disassembled. Finally, the pressure plate is pressed against the rail by elastic force. The second compression spring and the rubber block can also play an elastic buffering and protective role for the entire protective baffle. When encountering a large stone impact, the force is enough to directly overcome the elastic force of the second compression spring and then separate the pressure plate from the bottom of the rail top, achieving maximum protection, double buffering, and better effect. Both sides of the protective baffle are bent toward one side of the equipment.

[0025] The construction method after cutting and transporting the stone at the lattice column position is: after the rope saw has cut the stone around the lattice column, the stone around the lattice column is crushed and cleaned with a crusher.

[0026] The cutting saw blade 201 of the double-blade mining cutter 102 is rotatably connected to the lifting frame 202, and a saw blade anti-vibration mechanism is installed on the lifting frame 202. The saw blade anti-vibration mechanism includes an anti-vibration frame 203, and one side of the anti-vibration frame 203 is fixedly connected to the lifting frame 202. The anti-vibration frame 203 is an arc-shaped structure, and two rows of rollers 204 are symmetrically arranged on both sides. The two rows of rollers 204 elastically rest on both sides above the rotating shaft of the cutting saw blade 201 and are located at two-thirds of the radius of the cutting saw blade 201. The rolling direction of the roller 204 is tangent to the rotation direction of the cutting saw blade 201. By setting an elastic roller, the vibration generated by the cutting saw blade can be absorbed, the vibration of the cutting saw blade can be reduced, and the cutting stability can be improved. In order to further improve the shock absorption effect, multiple rows are arranged on one side, and each roller 204 is rotatably connected to the hollow 205. The two ends of the axle of the roller 204 are rotatably connected to two bearing seats 206 respectively. The bearing seat 206 is fixedly connected with a square guide rod 207. The end of the square guide rod 207 is provided with a screw rod 208. The screw rod 208 passes through the square hole 209 provided on the wall plate of the anti-vibration frame 203 and is connected with a limited position adjustment nut 210. A concave step 212 is provided on the inner side of the hollow 205 of the wall plate of the anti-vibration frame 203 to ensure that the direction guide rod 207 is partially embedded in the square hole 209. The square guide rod 2 07 is sleeved with a compression spring 211, and the two ends of the compression spring 211 are respectively against the bearing seat 206 and the concave step 212. The elastic telescopic structure composed of the compression spring and the square guide rod is convenient for adjusting the extension amount to ensure that the blade is symmetrically stressed and can have a better shock-absorbing effect on the cutting saw blade, which is more conducive to the stability of the cutting effect. The concave step is set to make the structure more compact. A connecting plate 213 is set on the inner side of the anti-tremor frame 203. The connecting plate 213 is fixedly connected to the lifting frame 202 by screws. A reinforcing rib 214 is set on the connecting plate 213. The structure has stable support and is easy to assemble and disassemble.

[0027] The track 301 in step 3 adopts a structure of splicing multiple short tracks 302. The two adjacent short tracks 302 are connected by auxiliary support sleeves 303. The auxiliary support sleeves 303 are provided with a through groove 304 with an upper opening. The through groove 304 is consistent with the structure of the track bottom 305. Both sides of the bottom of the auxiliary support sleeves 303 are provided with raised pressing plates 306. An auxiliary support sleeve 303 is also sleeved near the middle of the short track 302, which can achieve multiple supports and better support stability. The auxiliary support sleeve 303 in the middle where the short track 302 is connected is fixed to the ground, and the auxiliary support sleeves 303 between the middle and the two ends do not need to be fixed to the ground and the short track 301. They only need to be leveled and stressed. Each auxiliary support sleeve 303 is fixed to the ground and the short track 301. It only needs to be leveled and stressed. The expansion screws 307 are locked on the surface of the foundation pit, and a transition track group 308 is installed between two adjacent groups of tracks 301. The transition track group 308 can be obliquely spliced ​​to the adjacent groups of tracks 301 near the ends. The tracks of the transition track group 308 are connected to the tracks 301 of the main line by a detachable elbow sleeve 309. Two sections of connected track heads 310 are arranged at the corners of the elbow sleeve 309, which can quickly connect two straight short tracks 302 to achieve a smooth transition without additional processing. A plurality of auxiliary support sleeves 303 are installed on the transition track group 309, and a hard rubber shock-absorbing pad 311 is arranged on the bottom surface of the auxiliary support sleeve 303. The installation of hard rubber shock-absorbing pads can not only provide a certain degree of rigid support, but also play a shock-absorbing role.

[0028] The above-mentioned use of auxiliary support sleeves for track splicing and auxiliary support can greatly improve the track installation efficiency and is fixed by the pressing plate of the auxiliary support sleeve. The pressing space is wide, which is convenient for track locking. After the auxiliary support is inserted into the track, the side is locked with a locking screw, and the installation is quick and convenient; the arrangement of transition tracks and elbow sleeves can quickly move the double-blade mining cutter to the adjacent track group, which can prevent the lifting equipment from being affected by the beams above the foundation pit or the limitation of the lifting position; the detachable structure is easy to assemble and disassemble, and can be reused to improve equipment utilization; the provision of hard rubber shock-absorbing pads can improve the shock-absorbing effect of the track, and prevent the vibration of the cutting motor from being transmitted to the ground through the track and then interfering with the cutting tool, affecting the tool cutting.

[0029] By mechanically cutting the deep foundation pit stone into blocks and hoisting and transporting them out, the interference caused by stone excavation construction is eliminated, and the problem of deep foundation pit stone excavation close to the existing line is solved. The cutting method is used for deep foundation pit stone excavation, which is simple and fast to operate. It can be constructed on multiple working faces at the same time and operate 24 hours a day. The stone excavation efficiency reaches 600m³ / d, and each working face can excavate 200m³ / day on average, with excellent performance indicators.

[0030] All construction sites have been hardened, a water sprinkling system for dust reduction has been established, construction fences have been installed with a sprinkler system, special watering equipment has been equipped and specific personnel have been designated to be responsible. In seasons prone to dust generation, water sprinkling is used to reduce dust at the construction site.

[0031] The cutting cooling water shall be precipitated and recycled; the waste mud generated during construction must be precipitated to meet the discharge standards before it can be discharged into the municipal sewage pipe. It is strictly prohibited to discharge it directly into the municipal sewage pipe.

[0032] The stone cutting and excavation method solves the problem of interference of deep foundation pit stone excavation construction on adjacent existing lines and surrounding environment. Stone cutting construction is not affected by external factors, and multiple working surfaces can be constructed simultaneously and operate 24 hours a day, which greatly improves construction efficiency, reduces construction costs, improves foundation integrity, reduces the risk of base leakage and water inrush, and ensures construction safety, quality, and construction period. The implementation of this technology has achieved good results.

[0033] In view of the complex environmental conditions, the present invention adopts a double-blade mining cutter to cut rock layers, and uses a diamond rope saw to cut rocks, thereby reducing surrounding disturbances, reducing the impact of deep foundation pit excavation construction on existing lines and surrounding buildings, and ensuring construction safety.

[0034] The cutting method is used to excavate the rock foundation in regular shapes and with precise geometrical dimension control, which does not damage the integrity of the foundation rock and reduces water leakage from the basement karst fissures. This is beneficial for sealing water leakage at the bottom of the pit and ensures reliable construction quality.

[0035] Stone is a limited and non-renewable natural resource. The square rocks cut by this technology are neatly shaped, have a high recycling rate, and do not cause environmental pollution during the operation.

[0036] The economic benefits generated by the implementation of the method of the present invention are as follows: the unit price of rock stratum cutting is about 80 yuan / m³, and the unit price of cutting stone for transportation is 35 yuan / m³; if digital detonator micro-difference controlled blasting is used, the unit price of blasting excavation is about 120 yuan / m³, and the unit price of blasting stone for transportation is 55 yuan / m³. The construction method can save the excavation and transportation cost by 60 yuan / m³. A total of direct economic benefits (saving construction costs) are generated: 120,000×60=7.2 million yuan. At the same time, the stone excavated by blasting is relatively scattered and can only be used as building materials such as crushed stone and stone powder, with a utilization value of about 40 yuan / m³; the stone excavated by mechanical cutting is relatively complete and regular in size, and can be used as raw materials for floor tiles and sculptures, with a stone utilization value of about 80 yuan / m³; the amount of complete cut stone is calculated as 50% of the total amount, and the reuse value of stone is increased by 120,000×0.5×40=2.4 million yuan.

[0037] In addition, there are many cases of over-excavation and under-excavation when using blasting construction, and the over-consumption of cushion casting is more than 40%. The error of the base by cutting excavation is basically controlled within 5cm. Compared with blasting excavation, 0.11m³ of concrete can be saved per square meter, and the construction cost can be saved by about 79 yuan / ㎡, generating a total direct economic benefit (saving construction cost): 7200×79=568,800 yuan.

[0038] The above description is only a specific implementation mode of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. Construction method of cutting and excavating deep foundation pits close to existing lines. Features: The method comprises the following steps: Step 1: Leveling the base surface: Use a rope saw to cut the foundation pit soil to level the base surface; Step 2: Positioning and staking out: measure and locate the foundation pit earthwork after the base surface is leveled, and stake out the cutting height; Step 3: Track laying: track laying on the foundation pit soil base; Step 4, cutting machine in place: install the double-blade mining cutting machine at the starting position on the track; Step 5, vertical cutting of rock strata: a double-blade mining cutter is used to cut the foundation pit soil into set blocks of stone at intervals in the vertical and horizontal directions; wherein, for the position of the lattice column, four vertical cutting seams are cut around the lattice column to form small blocks of cut rock; Step 6: Cutting and breaking rocks with a wire saw: Using a diamond wire saw to horizontally cut the blocks of stone cut vertically and horizontally; Step 7: Transfer within the pit and hoist for transportation outside: The cut stone blocks are transferred and hoisted outside the foundation pit.

2. The method for cutting and excavating a deep foundation pit adjacent to an existing line according to claim 1, Features: The specific steps for leveling the base surface in step 1 are as follows: 1.

1. Excavate the foundation pit to the rock layer, and clean the rock surface with manual and mechanical methods. After cleaning, diamond wire saw equipment is used to cut the base surface according to the undulating state of the rock layer; 1.

2. First determine the leveling elevation, use a pneumatic drill to drill holes along the raised parts of the rock surface to allow the rope saw chain to pass through, and cut the raised rock layer. After cutting, use mechanical crushing and excavation for transportation.

3. The method for cutting and excavating a deep foundation pit adjacent to an existing line according to claim 2, Features: The specific steps for positioning and setting out in step 2 are as follows: 2.1 After the base surface is leveled, use the total station to measure and locate according to the set cutting size. When the distance from the retaining structure is less than 1.5m, reserve 20cm of working space; the staggered surface produced by cutting each layer during slope excavation is used as slope space; 2.2 When laying out, first determine the elevation of the cutting point, calculate the height difference between the cutting surface and the design support and base elevation, and determine the required cutting depth, that is, the depth is calculated based on the relative height difference. Assuming that the maximum cutting depth of a single layer is 1.5 m, if the distance between the cutting surface and the bottom of the concrete support is H, in m, round H / 1.

5. If there is no remainder, cut according to H / 1.5 layers, otherwise cut according to H / 1.5+1 layers; 2.3 For small foundation pits with an excavation depth of less than 1.5m, cutting shall be carried out according to the designed size; when the depth exceeds 1.5m, a 20cm working platform shall be added on each side for every additional 1.5m.

4. The method for cutting and excavating a deep foundation pit adjacent to an existing line according to claim 3, Features: The specific steps for track laying in step 3 are as follows: 3.1 First clean the loose slag on the surface of the track support and reinforcement; 3.2 The track adopts a 4-meter standard track, that is, a short track. Each section of the track is fixedly connected with an auxiliary support sleeve and bolts or a connecting plate with bolts. The level meter is used to level the two track surfaces so that they are parallel to the same horizontal plane. The two tracks must be parallel and the two track surfaces should be on the same level. The horizontal error should be less than 1 / 1000; 3.3 According to the cutting depth of each layer, first install the first track, and then reinforce it after checking the straightness and flatness of the cutting edge. Based on the first track, use a level ruler and caliper to install the second track with a spacing of 2.6mm. The width of each track should be consistent and the installation should be horizontal, firm and reliable. 3.4 When the track is laid directly on the ground, two adjacent short tracks are butt-jointed and fixedly connected to the ground with auxiliary support sleeves, or laid using the following methods: use guide holes to drive steel fibers to fix and clamp them to the bedrock; when the rock surface is relatively flat and the track is less than 100mm from the ground, use holes drilled on both sides of the track to insert steel pins for fixation; when the distance from the rock surface is greater than 100mm but less than 200mm, use holes drilled in the rock between the two tracks to insert steel pins and use two φ22 round steels to cross weld and fix them, and use sleepers and wooden wedges for leveling; for bedrock with a height difference greater than 200mm, rock square materials can be used for padding or jacks can be used for automatic fine-tuning; 3.5 After the track installation is completed, the verticality and horizontality of the track should be checked again. A laser level should be installed at the end of the track to automatically level and straighten the steel track. Tracks for multiple cutting should be installed at one time. The starting end of each set of tracks should be left open to install transition tracks. The transition tracks are used to connect adjacent track groups and transfer double-blade mining cutting machines for continuous cutting on the same track line.

5. The method for cutting and excavating a deep foundation pit adjacent to an existing line according to claim 4, Features: A protective baffle is installed at one end of each track where the double-blade mining cutter stops walking. Both sides of the protective baffle are rotatably connected to two supports in the width direction. The two supports are fixedly connected to the base plate. Multiple compression springs are connected to the back of the protective baffle. Multiple compression springs are fixedly connected to the support rod. The lower end of the support rod is fixedly connected to the base plate. The base plate is fixedly connected to the track. The base plate is connected to the two tracks through two quick clamping mechanisms. The quick clamping mechanisms include a pressure plate, a push plate, a push rod, a connecting rod one, a connecting rod two and a connecting rod three. The pressure plate is a T-shaped plate. Two connecting rods one are hinged on both sides of one end of the big head. The other end of the two connecting rods one is hinged to one end of the push plate. Two connecting rods two are hinged on both sides of the other end of the push plate. The other ends of the two connecting rods are hinged to the two connecting rods three near the middle, and the upper ends of the two connecting rods three are hinged on the hinge seats, and the hinge seats are fixedly connected to the base plate. The lower ends of the two connecting rods three are hinged on both sides of the pressure plate near the middle. A push rod is fixedly connected to the top of the push plate and is close to the hinge of the two connecting rods two and the push plate. A push rod is arranged under the push plate, and the push rod and the push rod are kept coaxial. After the push rod passes through the base plate, it is connected with an assembly and disassembly nut. A compression spring two is also sleeved on the push rod, and the two ends of the compression spring two abut on the upper end surface of the push plate and the bottom of the base plate. A rubber block is abutted on the bottom of the top of the track, and a side baffle abutting against the side of the top of the track is arranged on the top left side of the rubber block, and an abutting step is arranged at the bottom, which is used for the end of the pressure plate to abut.

6. The method for cutting and excavating a deep foundation pit adjacent to an existing line according to claim 4, Features: The specific steps for installing the cutting machine in step 4 are as follows: 4.1 Use a car crane to hoist the double-blade mining cutter onto the track, use the wheels and adjustable bolts at the bottom of the double-blade mining cutter to fine-tune it to the exact position of the track, and then lower the bolts to drop the wheels onto the track; 4.2 According to the width of the earthwork and stone materials in the foundation pit, determine the position of the two spindle boxes of the double-blade mining cutting machine to adjust the distance between the two saw blades of the double-blade mining cutting machine; 4.3 Clear all obstacles around the machine platform of the double-blade mining cutter and check the height of the saw blade. The distance between its lowest edge and the highest point of the cutting surface should be 10mm to 20mm.

7. The method for cutting and excavating a deep foundation pit adjacent to an existing line according to claim 5, Features: The specific steps for vertical cutting by the cutting machine in step 5 are as follows: 5.1 The maximum cutting length, depth and width of the foundation pit earthwork are 3m, 1.5m and 1.5m respectively according to the site and rock integrity. When encountering lattice columns, a 20cm margin is left on the four sides of the lattice columns for cutting. The cutting depth of the rock stratum is strictly controlled. The cutting depth is accurately calculated according to the distance between the track elevation and the outer edge of the saw blade to make the rock surface level. 5.2 When the double-blade mining cutting machine is used for initial cutting, a φ2200mm saw blade is used. When the cutting depth reaches 800mm, a φ3000mm saw blade is replaced for cutting. When installing the saw blade, the runout of the saw blade end face and the radial face shall not exceed 0.5mm. At the same time, check whether the cutter disc and the bolts of each fastening part are loose. Auxiliary 5.3 When cutting each layer, the cutting shall be carried out at a location convenient for stone lifting or at a set distance from the temporary construction road. The set distance shall be determined according to the working radius of the lifting equipment. The longitudinal cutting line shall be cut at a spacing of 0.75m within the range of 4.5m, and the horizontal length shall be controlled at 2m. The rock formation in this range shall be cut and then extruded and fractured or mechanically broken to serve as the rock-breaking working surface and transfer channel of the rock formation. After the rock-breaking working surface is cut, the cutting width of other areas shall avoid the lattice columns according to the arrangement of the lattice columns on site, and the cutting shall be carried out according to the requirement that the cutting width shall not exceed 1.5m. The horizontal and longitudinal cutting lines shall be cut according to the on-site positioning requirements; During the cutting process, if there is internal gravel, the current of the motor driving the circular saw will be monitored to change suddenly. When the sudden change reaches the set value, the cutting speed will be reduced. Each time the speed is reduced according to the set speed, after one or more speed reductions, the current drops below the set threshold, and the cutting is performed at a uniform speed after the speed reduction. When the current stabilizes to the set range, the gravel area is avoided and the speed is gradually adjusted to the speed before the speed reduction. 5.4 For small foundation pits at the bottom of excavated foundation pits, on-site layout must be carried out according to the design dimensions and the cutting depth must be measured before cutting. Cutting and separation must be carried out along the range of the small foundation pit and mechanical crushing and transportation must be used.

8. The method for cutting and excavating a deep foundation pit adjacent to an existing line according to claim 6, Features: The specific steps for cutting the rock with a rope saw in step 6 are as follows: 6.1 For each layer of rock fracture working face, the rock with a cutting width of 0.75m is cut by hammering the cutting seam with a Φ22 round steel tip chisel and a sledgehammer to squeeze holes. The horizontal squeezing stress generated causes the rock to break horizontally at the bottom of the cut and be hoisted for transportation or mechanical equipment is used to break it for transportation; 6.2 After the rock-breaking working face is equipped with wire saw cutting, the wire saw chain is installed to the bottom of the cutting seam using the diamond wire saw equipment, and a guide wheel for the wire saw chain to pass through is arranged between the stone to be cut and the diamond wire saw equipment to perform horizontal cutting of the rock. The wire saw chain is installed to avoid the lattice column; 6.3 After the wire saw chain is installed, adjust the tension of the driving wheel through the control panel of the diamond wire saw equipment to ensure that the diamond wire is tight, and supply circulating cooling water to drive the driving wheel to drive the wire saw chain to rotate and cut. During the cutting process, observe the stability of the machine base and adjust the offset of the guide wheel at any time to ensure that the wire saw chain is in the same plane; 6.4 Adjust the cutting parameters by operating the control panel to ensure that the linear speed of the rope saw chain is 20m / s, and the flushing fluid should be ensured during the cutting process.

9. The method for cutting and excavating a deep foundation pit adjacent to an existing line according to claim 7, Features: The specific steps for in-pit transfer and hoisting transportation in step 7 are as follows: 7.1 After each layer of rock is cut to a point where a forklift can pass, the rock should be transported to a fixed lifting point by a forklift; no one is allowed to walk or stay within the working radius of the boom of the lifting equipment at the fixed lifting point; for lifting at night, there must be lighting from above and below, and there must be an experienced crane operator to direct; 7.2 Mobile hoisting equipment shall be equipped according to the size of the project stone blocks. Each rock block shall be hoisted as a whole. During the hoisting, a dedicated person shall observe and direct from a distance, directing the crane driver to hoist slowly. During the process of lowering the rock blocks out of the foundation pit, a dedicated person shall use a traction rope to hold the rock blocks and adjust the direction. It is strictly forbidden to collide with the upper beams, side lattice columns and side walls of the foundation pit; 7.3 Before lifting the rock, the integrity of the cut rock should be checked. If there are obvious cracks and fissures, lifting is prohibited; 7.4 The rock block is hoisted by two 6*37 wire φ32mm steel wire ropes, which are laid at the 1 / 4~1 / 5 position at both ends of the rock block. The steel wire ropes and the corners of the rock block are isolated by rubber. The steel wire ropes need to be maintained regularly and replaced immediately if they are worn and broken. 7.5 After the rock blocks are hoisted out of the foundation pit, they are transported out using a flatbed truck and placed stably in the truck compartment. If the rock blocks cannot be transported out in time, a forklift will be used to transfer the square materials to a temporary transfer site and stacked neatly.

10. The method for cutting and excavating a deep foundation pit adjacent to an existing line according to claim 1, Features: The track in step 3 adopts a multi-segment short track splicing structure, and the two adjacent short tracks are connected with auxiliary support sleeves. The auxiliary support sleeves are provided with a through groove with an upper opening, and the through groove is consistent with the track bottom structure. Raised pressing plates are provided on both sides of the bottom of the auxiliary support sleeves, and an auxiliary support sleeve is also sleeved near the middle of the short track. Each auxiliary support sleeve is locked on the foundation pit surface by a pressing plate and an expansion screw. A transition track group is installed between two adjacent groups of tracks. The transition track group can be obliquely spliced ​​to the two adjacent groups of tracks near the ends. The tracks of the transition track group and the main line track are connected with a detachable elbow sleeve. Multiple auxiliary support sleeves are installed on the transition track group, and hard rubber shock-absorbing pads are provided on the bottom of the auxiliary support sleeves.