Construction method of large-angle Y-shaped pier continuous conversion system

Through the combination of layered casting and cable-stayed support systems, the problems of large concrete volume and difficulty in controlling the eccentricity of steel bars in construction are solved, and the structure and construction safety are guaranteed, and the material use and formwork are reduced. Turnover efficiency.

CN118911033APending Publication Date: 2024-11-08THE FIRST COMPARY OF CHINA EIGHTH ENG BUREAU LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411298528.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-18
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

During the construction process, the large-angle Y-shaped pier has problems such as large concrete volume of the structure itself, high difficulty in setting up construction platforms and binding of steel bars, difficulty in controlling the eccentricity of steel bars, and difficult to control the appearance of concrete casting, which makes it difficult to ensure construction safety and structural safety.

Method used

Using the layered casting method, the Y-shaped piers are divided into straight sections, coupling sections, inclined leg sections and cover beams according to the cross-sectional shape from bottom to top, and divided into straight sections, inclined support system. For layer construction, use the rigid frame and triangular truss platform for precise positioning and support, and pour concrete layer by layer to ensure that the support method and concrete amount of each section are reasonable.

Benefits of technology

Effectively control the concrete tensile stress of the coupling part of the "V" two-inclined limb leg within the design allowable range, ensuring structural and construction safety, reducing the amount of steel and consumables used in the skeleton, shortening the turnover speed of the cover beam formwork, and reducing steel waste. , and improve the integrity and safety of the construction platform.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911033A_ABST
    Figure CN118911033A_ABST
Patent Text Reader

Abstract

The invention provides a construction method of a large-angle Y-shaped pier continuous conversion system, and belongs to the technical field of bridge construction. According to the technical scheme, the Y-shaped pier is sequentially divided into a straight line section, a coupling section, an inclined limb leg section and a cover beam from bottom to top according to the section shape, the straight line section is transited to the inclined limb leg section through the coupling section, and layered pouring is conducted on the Y-shaped pier column according to arrangement and construction convenience of a cable-stayed supporting system, and the Y-shaped pier column is sequentially divided into the first layer, the second layer, the third layer and the sixth layer. The construction method has the beneficial effects that in the construction process, it is guaranteed that the concrete tensile stress of the coupling part of the two V-shaped inclined legs does not exceed the design allowable range all the time, structural safety and construction safety are guaranteed, the steel consumption of the framework is small, the material consumption is low, and by designing the whole bent cap bracket construction platform, the bent cap formwork turnover speed is shortened, and the construction efficiency is improved. And steel waste in the template turnover process is reduced. The integrity of the bent cap bracket can be improved through split bolts arranged on the Y-shaped branch upper trusses of the inner and outer triangular trusses and transverse reinforcing channel steel arranged on the lower trusses.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a construction method of a large-angle Y-shaped pier continuous conversion system. Background Art

[0002] In the past decade, some prestressed concrete Y-type support bridges have appeared at home and abroad, including Y-type support continuous beam bridges and continuous rigid frame bridges. Compared with straight-leg rigid frame bridges, under the action of the V-pier of the prestressed concrete Y-type pier continuous rigid frame bridge, the span of the main beam can be significantly shortened, and the peak value of the negative bending moment of the support shoulder is also reduced, making the structure light and slender, which is conducive to the selection of variable-section box beams, and the appearance is more beautiful. This structure has high requirements for construction technology, mainly reflected in:

[0003] ① The structure itself has a large concrete volume. Before the prestressing of the upper tie beam is tensioned, the structure cannot form a self-contained system and requires strong support;

[0004] ② The oblique legs of the large-angle Y-shaped pier make it more difficult to set up the construction platform, tie and fix the steel bars, install the formwork and fix the position;

[0005] ③ It is difficult to control the eccentricity of steel bars such as embedded steel bars and oblique legs of large-angle Y-shaped piers;

[0006] ④ The steel bar density of the variable-section section of the large-angle Y-shaped pier is high, and the appearance of the concrete pouring is difficult to control. Summary of the invention

[0007] The purpose of the present invention is to provide a construction method for a large-angle Y-shaped pier column, which can ensure that the concrete tensile stress of the "V"-shaped two oblique leg coupling part does not exceed the design allowable range, and ensure structural safety and construction safety.

[0008] The present invention is achieved by the following measures:

[0009] A construction method for a large-angle Y-shaped pier continuous conversion system, characterized in that the Y-shaped pier is divided into a straight section, a coupling section for transitioning from the straight section to the oblique leg section, an oblique leg section and a cap beam from bottom to top according to the cross-sectional shape, and the Y-shaped pier column is cast in layers according to the setting of the oblique support system and the convenience of construction. The specific construction method comprises the following steps:

[0010] S1, pouring the first layer, wherein the first layer is a coupling section where the straight section transitions to the oblique leg section, and the height of the first layer is limited by the size of the cap 11;

[0011] S2, pouring the second layer, wherein the second layer is the oblique leg section 2 / 3 of the vertical height above the first layer;

[0012] S3, pouring the third layer, the third layer is the diagonal leg section with 1 / 3 vertical height above the second layer, and the division between the second layer and the third layer is based on minimizing the concrete volume of the large cantilever length section of the diagonal leg section, that is, reducing the moment size in the bending moment, while considering the stress condition of the diagonal support structure and the convenience of construction;

[0013] S4, pouring the VI layer, wherein the VI layer is a cap beam, and the concrete weight of the VI layer is borne by the diagonal bracing truss system;

[0014] Different sections have different support methods during the construction process, and the basis for their division is mainly the reasonable concrete volume that the tension support system can withstand and the coordination with the construction steps.

[0015] The specific features of the present invention also include:

[0016] The specific steps of S1 are as follows:

[0017] S11, after the straight line segment is cast, the corresponding rigid frame 1 is hoisted, and welding is performed after positioning. To ensure the connection strength, the welding point is reinforced with a code plate;

[0018] S12, tie the steel bars and install the pads, then install the corresponding templates and install the tension steel strands on the inner side of the two-leg steel bar skeleton;

[0019] S13. Pour the first layer of concrete. After the first layer of concrete has formed strength, remove the corresponding formwork.

[0020] The specific steps of S2 are as follows:

[0021] S21, hoist two corresponding rigid frames, and weld them after positioning;

[0022] S22, tie the steel bars and install the pads, then install the corresponding templates and install the tension truss rods at the bracket supports of the two-leg steel frame;

[0023] S23, pouring the second layer of concrete, and removing the corresponding formwork after the second layer of concrete has formed strength;

[0024] After the second layer of concrete is poured, a temporary stability system is formed through the middle tension truss rod of the second layer.

[0025] The specific steps of S3 are as follows:

[0026] S31, hoist two corresponding rigid frames 3, and weld them after positioning;

[0027] S32, tying the steel bars and installing the pads, then installing the corresponding templates and installing the two tension truss rods at the bracket supports of the two limb steel bar skeletons;

[0028] S33, pouring the third layer of concrete, and removing the corresponding formwork after the third layer of concrete has formed strength;

[0029] After the pouring of the third layer of concrete is completed, the third layer of concrete and the two truss rods form a new temporary stability system.

[0030] The specific steps of S4 are as follows:

[0031] S41, install cap beam formwork;

[0032] S42, tying steel bars;

[0033] S43, pouring cap beam concrete;

[0034] After the cap beam construction is completed, the entire Y-shaped pier forms a permanent stable system.

[0035] The rigid frame 1, the rigid frame 2 and the rigid frame 3 are collectively referred to as the rigid frame. Since the rigid frame is the key to the positioning of the pier body reinforcement and the formwork, the precise positioning of the rigid frame is very important. The installation steps of the rigid frame 1, the rigid frame 2 and the rigid frame 3 are as follows:

[0036] A1. Calculate the plane position deviation according to the inclination and height of the rigid frame 1, the rigid frame 2 or the rigid frame 3, and then use a plumb bob to preliminarily position the rigid frame 1, the rigid frame 2 or the rigid frame 3;

[0037] A2. After the rigid frame 1, the rigid frame 2 or the rigid frame 3 are initially positioned, they are temporarily fixed, and then a total station is used to measure and verify the precise position of the rigid frame 1, the rigid frame 2 or the rigid frame 3. The precise positioning should be performed at an appropriate time to avoid deviations caused by factors such as temperature difference and load;

[0038] A3. After the rigid frame 1, the rigid frame 2 or the rigid frame 3 are accurately positioned, spot welding is first performed around the rigid frame 1, the rigid frame 2 or the rigid frame triangular steel column, and then welding is performed in sections. During the welding process, care is taken to avoid position deviation of the rigid frame 1, the rigid frame 2 or the rigid frame 3 due to temperature deformation.

[0039] The cap beam construction is completed with the assistance of a corresponding working platform, which is a triangular truss platform, and the triangular truss platform includes an outer triangular truss and an inner triangular truss; during the construction of the Y-shaped pier, embedded bolts, embedded bracket anchor boxes and reserved holes for tension screws for the installation of the triangular truss platform are embedded in advance;

[0040] The triangular truss platform is made of L63mm×63mm×4mm angle steel, and is welded into a steel mesh with φ20 steel bars. A connection hole is set at the upper and lower parts of the triangular truss platform bracket close to the column side. During the construction of the Y-shaped pier, a φ20 L-shaped sleeve is embedded, and connected with the embedded φ20 L-shaped bolts through 2 M22 bolts;

[0041] The embedded corbel anchor box (8) is made of 3mm thick steel plate, and the seam welding is tight and does not leak; the embedded corbel anchor box (8) should be installed close to the template to prevent leakage, and the embedded position is strictly controlled, and the deviation shall not be greater than 5mm; after the embedded corbel anchor box is positioned, two φ16 steel bars are used to weld it firmly to the main reinforcement at the top and bottom to ensure that it does not shift during the concrete pouring process;

[0042] In order to prevent the concrete from being broken due to excessive stress at the corbel, D12 reinforcing steel mesh is added at the upper and lower positions of the embedded corbel anchor box, with a spacing of 10 cm;

[0043] The reserved hole for the tension screw rod adopts a steel pipe with a wall thickness of 3.6mm and a diameter of φ48mm. The end is processed into a groove according to the slope of the template so that the end of the steel pipe is close to the template; at the same time, the position of the stirrup under the steel pipe is adjusted so that the stirrup can support the steel pipe, and the steel pipe is fixed on the stirrup with a U-shaped steel bar, and the two ends of the stirrup are welded to the main reinforcement;

[0044] The triangular truss platform is customized by the template manufacturer, and each cap beam uses 4 pieces of the outer triangular trusses and 4 pieces of the inner triangular trusses;

[0045] The outer triangular truss and the inner triangular truss are both composed of an upper chord, a lower chord and a web. The upper chord is formed by butt welding of two 22#a channel steels, and a 20mm thick steel plate is welded at the end close to the Y-shaped pier column; the lower chord is formed by butt welding of two 20#a channel steels, and the web connecting the upper chord and the lower chord is formed by butt welding of 14#a channel steels;

[0046] After the Y-shaped pier is completed, the triangular truss platform is installed with the help of the working platform outside the template when the template is removed; before installation, the pre-buried L-shaped sleeve and L-shaped bolts are cleaned before installation; the installation of the triangular truss platform is carried out by two people, one person stabilizes the triangular truss platform and the other tightens the bolts; after the installation of the triangular truss platform is completed, check whether the triangular truss platform is in close contact with the Y-shaped pier surface and whether the bolts are tightened in place. After checking, weld the connecting steel bars on the upper part of the triangular truss platform;

[0047] The corbel is made of 700mm×200mm×30mm steel plate. Before installation, clean the embedded corbel anchor box and insert the corbel into the embedded corbel anchor box. Use small steel plates to wed the gaps on both sides to prevent the corbel steel plate from shifting after being stressed.

[0048] Before installing the triangular truss platform, check whether the processing size of the triangular truss platform is correct, and clean the tension holes of the inner triangular truss and the outer triangular truss. The tension holes are the aforementioned connection holes.

[0049] When installing the triangular truss platform, a tower crane is required. The inner triangular truss is installed first. During installation, the tower crane will lift the inner triangular truss to the tension hole according to the installation angle, insert φ32 fine-rolled threaded steel into the reserved hole of the tension screw for temporary fixation, and fill the inner triangular truss and the bracket with adjustable steel plates of different thicknesses; after the two inner triangular trusses are installed, 6 M24 bolts and anchor pads are used to connect the two inner triangular trusses opposite to each other; after the inner triangular trusses are installed, 10# channel steel is used as a transverse reinforcement device for transverse connection; after the inner triangular truss is installed, the tower crane is used to lift the outer triangular truss to the outer tension hole according to the installation angle, insert φ32 fine-rolled threaded steel into the reserved hole of the tension screw for fixation, and fill the outer triangular truss and the bracket with adjustable steel plates of different thicknesses; after the outer triangular truss is installed, 10# channel steel is used as a transverse reinforcement device for transverse connection.

[0050] The outer transverse distribution beam on the outer triangular truss is made of I20 I-steel, and the inner transverse distribution beam on the inner triangular truss is made of I28a I-steel. The spacing between the distribution beams is 80cm, and each side of the distribution beam exceeds the outer edge of the cap beam by no less than 1m as a working platform. The outside of the platform is protected by standard fencing, and the fencing uprights are made of steel pipes and firmly welded to the transverse distribution beams to increase protection stability.

[0051] The bottom formwork of the cap beam adopts a steel-wood composite formwork, the bottom plate adopts bamboo plywood (15mm thick), the back ribs adopt wooden squares (10cm×10cm), and the layout spacing is 30cm. The arc chamfers on both sides of the cap beam adopt a standard steel formwork. The structure of the bottom formwork of the cap beam is shown in the attached figure. When laying the bottom formwork, double-sided tape is pasted between the formworks to prevent leakage.

[0052] During the disassembly process, you only need to dismantle the welding between the bracket fixture and the pier body, and cut off the welding between the bracket and the pier body. The tension bolts between the dismantled nodes can become stackable and reusable materials. When changing platforms, you only need to cut the welding part of the base and hoist it to the ground as a whole by a car crane or tower crane, and it can be used for the next cap beam construction platform, which is convenient for reuse.

[0053] In the specific implementation process, firstly, according to the specific size of the cap beam, the required size of the platform outside the cap beam is calculated. By welding and assembling the cap beam bracket construction platform, a reusable assembled hoisting platform is formed. After the cap beam is poured, it is disassembled for structural inspection. After the inspection is correct, it can be used next time.

[0054] Furthermore, two-stage control is performed during the installation of steel bars:

[0055] In the first stage, the main reinforcement joints, main reinforcement spacing, and stirrup spacing are controlled within the specified range of the specification, and the number of steel bars is controlled to avoid the phenomenon of insufficient reinforcement;

[0056] In the second stage, after the template is installed and positioned, the spacing between the inner and outer layers of steel bars and the thickness of the protective layer are checked and adjusted again. After the steel bars are processed on site, they are transported to the pier by crane and manual labor before being tied.

[0057] While pre-embedding the Y-type pier body reinforcement, 8 anchoring steel bars are pre-embedded outside the pier body range on the cap to facilitate the adjustment of the Y-type pier body formwork. The vertical main reinforcement connection of the Y-type pier body adopts mechanical connection, the main reinforcement joints are staggered, the joints of the same section do not exceed 50% of the total number of reinforcements of the section, and the distance between the joint sections is not less than 1m. When cutting the reinforcement, the cut end face should be perpendicular to the reinforcement axis, and there should be no horseshoe shape or deflection. The Y-type pier body includes the aforementioned straight section, the coupling section where the straight section transitions to the oblique leg section, the oblique leg section and the cap beam.

[0058] Furthermore, the upper limb formwork is divided into 4 sections, 1 upper and lower adjustment section, 1 3m standard section, and 1 2m standard section. The formwork installation is carried out in two times, the first time is to install the lower 3m, and after the first layer of concrete pouring is completed, the formwork of the upper 3m section is installed.

[0059] The upper limb construction platform uses 10[channel steel to make a triangular bracket, which is customized by the template manufacturer. The triangular bracket is connected to the main rib of the lower template. The outer platform width is 2.5 meters, the inner width is 1.5 meters, standard square steel railings, 2.5mm thick anti-slip steel plates, and it is strictly forbidden to place steel bars on the template platform.

[0060] Before installing the formwork, clean up the concrete that has spilled on the top surface of the formwork after the pouring of the previous section to ensure that the upper formwork is reliably connected without misalignment or gaps. When installing the formwork, a crane will hold the 1 / 2 formwork section and slowly drop the steel cage along the Y-shaped pier body. During the falling process, pay attention to whether there is any conflict between the formwork and the surrounding scaffolding. After the formwork is hoisted to the installation position, it is manually assisted to align with the previous section of the formwork, and temporarily fixed to the previous section of the formwork with bolts. It is forbidden to remove the hook before it is fixed or not firmly fixed to prevent the formwork from overturning. After the entire stage of formwork installation and assembly is completed, the position of the formwork needs to be calibrated, and the formwork is adjusted by support pads and inclined pull methods. After the adjustment is completed, it is finally fixed.

[0061] The stability of the Y-type bifurcated pier column template for segmented pouring mainly depends on the connecting nuts of the upper and lower sections of the template. In order to ensure that the template is installed reliably and does not tilt during the pouring of the Y-type bifurcated pier, double nuts are used to connect the pier columns, and checks are carried out between concrete pouring to ensure that there are no omissions. For safety reasons, two φ20 steel bars are used to temporarily pull the templates for the two pier columns tilted in opposite directions before pouring. At the same time, the left and right pier columns are poured alternately during the pouring process.

[0062] Both the first and second tension truss rods are made of D20 high-strength tension rods made of 45# steel. The maximum horizontal arrangement spacing is not more than 1200mm. The positive corners are all chamfered with arcs. Steel angle molds are designed separately and then connected to the adjacent lifting molds to ensure no leakage.

[0063] The beneficial effects of the present invention are: during the construction process, the concrete tensile stress of the "V"-shaped two oblique leg coupling parts is guaranteed not to exceed the design allowable range, and the structural safety and construction safety are guaranteed. The skeleton uses less steel and has low consumables. By designing an integral cap beam bracket construction platform, the turnover speed of the cap beam template is shortened, and the waste of steel in the template turnover process is reduced. The tension bolts set on the upper truss of the Y-shaped branch of the inner and outer triangular trusses and the transverse reinforcement channel steel set on the lower truss can improve the integrity of the cap beam bracket, and the inner and outer transverse distribution beams on the triangular truss extend beyond the outer edge of the cap beam by no less than 1m on each side as a working platform for steel bar binding and supporting the template. The outside of the platform is protected by a standard fence, and the fence uprights are made of steel pipes and welded firmly to the transverse distribution beams to increase the protection stability and ensure safe and reliable construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0064] Figure 1 This is a schematic diagram of the construction structure of the second layer of an embodiment of the present invention.

[0065] Figure 2 This is a schematic diagram of the construction structure of the third floor of an embodiment of the present invention.

[0066] Figure 3 It is a schematic diagram of the structure of a triangular truss working platform according to an embodiment of the present invention.

[0067] Figure 4 It is a front view of the corresponding working platform for cap beam construction in an embodiment of the present invention.

[0068] Figure 5 It is a side view of the corresponding working platform for cap beam construction in an embodiment of the present invention.

[0069] Figure 6 Schematic diagram of the structure of the outer triangular truss in an embodiment of the present invention.

[0070] Figure 7 Schematic diagram of the structure of the inner triangular truss in an embodiment of the present invention.

[0071] Figure 8 It is a schematic diagram of the bottom mold structure of the cap beam in an embodiment of the present invention.

[0072] Among them, the figure markings are: 1. Rigid frame two; 2. Corbel; 3. M22 bolt; 4. L-shaped sleeve; 5. Reserved hole for tension screw; 6. M24 bolt; 7. Tension bolt; 8. Embedded corbel anchor box; 9. Upper chord; 10. Lower chord; 11. Web bar; 13. Steel-wood composite formwork; 14. Bamboo plywood; 15. Shaped steel formwork; 16. Wooden square; 17. Rigid frame three. DETAILED DESCRIPTION

[0073] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features in the embodiments may be combined with each other.

[0074] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and the like are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, features defined as "first", "second", and the like may explicitly or implicitly include one or more of the features. In the description of the present invention, unless otherwise specified, "multiple" means two or more.

[0075] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood by specific circumstances.

[0076] In order to clearly illustrate the technical features of this solution, this solution is described below through a specific implementation method.

[0077] See also Figure 1-8A construction method for a large-angle Y-shaped pier continuous conversion system, wherein the Y-shaped pier is divided into a straight section, a coupling section for transitioning from the straight section to the oblique leg section, an oblique leg section and a cap beam from bottom to top according to the cross-sectional shape, and the Y-shaped pier column is cast in layers according to the setting of the oblique support system and the convenience of construction. The specific construction method includes the following steps:

[0078] S1, pouring the first layer, wherein the first layer is a coupling section where the straight section transitions to the oblique leg section, and the height of the first layer is limited by the size of the cap 11;

[0079] S2, pouring the second layer, wherein the second layer is the oblique leg section 2 / 3 of the vertical height above the first layer;

[0080] S3, pouring the third layer, the third layer is the diagonal leg section with 1 / 3 vertical height above the second layer, and the division between the second layer and the third layer is based on minimizing the concrete volume of the large cantilever length section of the diagonal leg section, that is, reducing the moment size in the bending moment, while considering the stress condition of the diagonal support structure and the convenience of construction;

[0081] S4, pouring the VI layer, wherein the VI layer is a cap beam, and the concrete weight of the VI layer is borne by the diagonal bracing truss system;

[0082] Different sections have different support methods during the construction process, and the basis for their division is mainly the reasonable concrete volume that the tension support system can withstand and the coordination with the construction steps.

[0083] The specific steps of S1 are as follows:

[0084] S11, after the straight line segment is cast, the corresponding rigid frame 1 is hoisted, and welding is performed after positioning. To ensure the connection strength, the welding point is reinforced with a code plate;

[0085] S12, tie the steel bars and install the pads, then install the corresponding templates and install the tension steel strands on the inner side of the two-leg steel bar skeleton;

[0086] S13. Pour the first layer of concrete. After the first layer of concrete has formed strength, remove the corresponding formwork.

[0087] The specific steps of S2 are as follows:

[0088] S21, hoist two corresponding rigid frames 21, and weld them after positioning;

[0089] S22, tie the steel bars and install the pads, then install the corresponding templates and install the tension truss rods at the bracket supports of the two-leg steel frame;

[0090] S23, pouring the second layer of concrete, and removing the corresponding formwork after the second layer of concrete has formed strength;

[0091] After the second layer of concrete is poured, a temporary stability system is formed through the middle tension truss rod of the second layer.

[0092] The specific steps of S3 are as follows:

[0093] S31, hoist two corresponding rigid frames 17, and weld them after positioning;

[0094] S32, tying the steel bars and installing the pads, then installing the corresponding templates and installing the two tension truss rods at the bracket supports of the two limb steel bar skeletons;

[0095] S33, pouring the third layer of concrete, and removing the corresponding formwork after the third layer of concrete has formed strength;

[0096] After the pouring of the third layer of concrete is completed, the third layer of concrete and the two truss rods form a new temporary stability system.

[0097] The specific steps of S4 are as follows:

[0098] S41, install cap beam formwork;

[0099] S42, tying steel bars;

[0100] S43, pouring cap beam concrete;

[0101] After the cap beam construction is completed, the entire Y-shaped pier forms a permanent stable system.

[0102] The rigid frame 1, the rigid frame 2 1 and the rigid frame 3 17 are collectively referred to as the rigid frame. Since the rigid frame is the key to the positioning of the pier body reinforcement and the formwork, the precise positioning of the rigid frame is very important. The installation steps of the rigid frame 1, the rigid frame 2 1 and the rigid frame 3 17 are as follows:

[0103] A1. Calculate the plane position deviation according to the inclination and height of the rigid frame 1, the rigid frame 2 1 or the rigid frame 3 17, and then use a plumb line to preliminarily position the rigid frame 1, the rigid frame 2 1 or the rigid frame 3 17;

[0104] A2. After the rigid frame 1, the rigid frame 2 1 or the rigid frame 3 17 is initially positioned, it is temporarily fixed, and then a total station is used to measure and verify the precise position of the rigid frame 1, the rigid frame 2 1 or the rigid frame 3 17. The precise positioning should be carried out at a suitable time to avoid deviations caused by factors such as temperature difference and load;

[0105] A3. After the rigid frame 1, rigid frame 2 1 or rigid frame 3 17 are accurately positioned, spot welding is first performed around the angle steel columns of the rigid frame 1, rigid frame 2 1 or rigid frame 3 17, and then welding is performed in sections. During the welding process, care is taken to avoid position deviation of the rigid frame 1, rigid frame 2 1 or rigid frame 3 17 caused by temperature deformation.

[0106] The cap beam construction is completed with the assistance of a corresponding working platform, which is a triangular truss platform, and the triangular truss platform includes an outer triangular truss and an inner triangular truss; when constructing the Y-shaped pier, embedded bolts, embedded bracket anchor boxes 8 and reserved holes 5 for tension screws are embedded in advance for the installation of the triangular truss platform;

[0107] The triangular truss platform is made of L63mm×63mm×4mm angle steel, and is welded into a steel mesh with φ20 steel bars. A connection hole is provided at the upper and lower parts of the triangular truss platform bracket close to the column side. During the construction of the Y-shaped pier, a φ20 L-shaped sleeve 4 is embedded, and connected with the embedded φ20 L-shaped bolts through two M22 bolts 3;

[0108] The embedded corbel anchor box 8 is made of 3mm thick steel plate, and the seam welding is tight and does not leak; the embedded corbel anchor box 8 should be installed close to the template to prevent leakage, and the embedded position should be strictly controlled, and the deviation should not be greater than 5mm; after the embedded corbel anchor box 8 is positioned, two φ16 steel bars are used to weld it firmly on the main reinforcement to ensure that it does not shift during the concrete pouring process;

[0109] In order to prevent the concrete from being broken due to excessive stress at the corbel 2, D12 reinforcing steel mesh is added at the upper and lower positions of the embedded corbel anchor box 8, with a spacing of 10 cm;

[0110] The reserved hole 5 for the tension screw rod is made of a steel pipe with a wall thickness of 3.6 mm and a diameter of φ48 mm. The end is processed into a groove according to the slope of the template so that the end of the steel pipe is close to the template; at the same time, the position of the stirrup under the steel pipe is adjusted so that the stirrup can support the steel pipe, and the steel pipe is fixed on the stirrup with a U-shaped steel bar, and the two ends of the stirrup are welded to the main reinforcement;

[0111] The triangular truss platform is customized by the template manufacturer, and each cap beam uses 4 pieces of the outer triangular trusses and 4 pieces of the inner triangular trusses;

[0112] The outer triangular truss and the inner triangular truss are both composed of an upper chord 9, a lower chord 10 and a web 11. The upper chord 9 is formed by butt welding of two 22#a channel steels, and a 20mm thick steel plate is welded at the end close to the Y-shaped pier column; the lower chord 10 is formed by butt welding of two 20#a channel steels, and the web 11 connecting the upper chord 9 and the lower chord 10 is formed by butt welding of 14#a channel steels;

[0113] After the Y-shaped pier is completed, the triangular truss platform is installed with the help of the working platform outside the template when the template is removed; before installation, the pre-buried L-shaped sleeve 4 and the L-shaped bolt are cleaned and then the triangular truss platform is installed; the triangular truss platform is installed by 2 people, one person stabilizes the triangular truss platform and the other person tightens the bolts; after the triangular truss platform is installed, it should be checked whether the triangular truss platform is closely attached to the surface of the Y-shaped pier and whether the bolts are tightened in place. After checking, the connecting steel bars on the upper part of the triangular truss platform are welded;

[0114] The corbel 2 is made of 700mm×200mm×30mm steel plate. Before installation, clean the pre-buried corbel anchor box 8, insert the corbel 2 into the pre-buried corbel anchor box 8, and use small steel plates to wed the gaps on both sides to prevent the corbel steel plate from shifting after being stressed.

[0115] Before installing the triangular truss platform, check whether the processing size of the triangular truss platform is correct, and clean the tension holes of the inner triangular truss and the outer triangular truss. The tension holes are the aforementioned connection holes.

[0116] When installing the triangular truss platform, a tower crane is required to cooperate with the installation of the inner triangular truss first. During installation, the tower crane will lift the inner triangular truss to the tension hole according to the installation angle, insert φ32 fine-rolled threaded steel into the reserved hole 5 for tension screw for temporary fixation, and use different thickness adjustment steel plates to fill the inner triangular truss and the corbel 2 tightly; after the two inner triangular trusses are installed, 6 M24 bolts 6 and anchor pads are used to connect the two inner triangular trusses opposite to each other; after the installation of the inner triangular truss, 10# channel steel is used as a transverse reinforcement device for transverse connection; after the installation of the inner triangular truss, the tower crane is used to lift the outer triangular truss to the outer tension hole according to the installation angle, insert φ32 fine-rolled threaded steel into the reserved hole 5 for tension screw for fixation, and use different thickness adjustment steel plates to fill the outer triangular truss and the corbel 2 tightly; after the installation of the outer triangular truss, 10# channel steel is used as a transverse reinforcement device for transverse connection.

[0117] The outer transverse distribution beam on the outer triangular truss is made of I20 I-steel, and the inner transverse distribution beam on the inner triangular truss is made of I28a I-steel. The spacing between the distribution beams is 80cm, and each side of the distribution beam exceeds the outer edge of the cap beam by no less than 1m as a working platform. The outside of the platform is protected by standard fencing, and the fencing uprights are made of steel pipes and firmly welded to the transverse distribution beams to increase protection stability.

[0118] The bottom formwork of the cap beam adopts a steel-wood composite formwork 13, the bottom plate adopts a bamboo plywood 14 (15 mm thick), the back ribs adopt a wooden square 16 (10 cm × 10 cm), and the layout spacing is 30 cm. The arc chamfers on both sides of the cap beam adopt a shaped steel formwork 15. The structure of the bottom formwork of the cap beam is shown in the attached figure. When laying the bottom formwork, double-sided tape is pasted between the formworks to prevent leakage of slurry;

[0119] During the disassembly process, it is only necessary to disassemble the welding between the bracket fixing device and the pier body, and cut off the welding between the bracket and the pier body, and the tension bolts 7 between the disassembly nodes can become stackable and reusable materials. When changing platforms, it is only necessary to cut the welding part of the base and hoist it to the ground as a whole by a car crane or a tower crane, and it can be used for the next cap beam construction platform, which is convenient for reuse.

[0120] In the specific implementation process, firstly, according to the specific size of the cap beam, the required size of the platform outside the cap beam is calculated. By welding and assembling the cap beam bracket construction platform, a reusable assembled hoisting platform is formed. After the cap beam is poured, it is disassembled for structural inspection. After the inspection is correct, it can be used next time.

[0121] Furthermore, two-stage control is performed during the installation of steel bars:

[0122] In the first stage, the main reinforcement joints, main reinforcement spacing, and stirrup spacing are controlled within the specified range of the specification, and the number of steel bars is controlled to avoid the phenomenon of insufficient reinforcement;

[0123] In the second stage, after the template is installed and positioned, the spacing between the inner and outer layers of steel bars and the thickness of the protective layer are checked and adjusted again. After the steel bars are processed on site, they are transported to the pier by crane and manual labor before being tied.

[0124] While pre-embedding the Y-type pier body reinforcement, 8 anchoring steel bars are pre-embedded outside the pier body range on the cap to facilitate the adjustment of the Y-type pier body formwork. The vertical main reinforcement connection of the Y-type pier body adopts mechanical connection, the main reinforcement joints are staggered, the joints of the same section do not exceed 50% of the total number of reinforcements of the section, and the distance between the joint sections is not less than 1m. When cutting the reinforcement, the cut end face should be perpendicular to the reinforcement axis, and there should be no horseshoe shape or deflection. The Y-type pier body includes the aforementioned straight section, the coupling section where the straight section transitions to the oblique leg section, the oblique leg section and the cap beam.

[0125] Furthermore, the upper limb formwork is divided into 4 sections, 1 upper and lower adjustment section, 1 3m standard section, and 1 2m standard section. The formwork installation is carried out in two times, the first time is to install the lower 3m, and after the first layer of concrete pouring is completed, the formwork of the upper 3m section is installed.

[0126] The upper limb construction platform uses 10[channel steel to make a triangular bracket, which is customized by the template manufacturer. The triangular bracket is connected to the main rib of the lower template. The outer platform width is 2.5 meters, the inner width is 1.5 meters, standard square steel railings, 2.5mm thick anti-slip steel plates, and it is strictly forbidden to place steel bars on the template platform.

[0127] Before installing the formwork, clean up the concrete that has spilled on the top surface of the formwork after the pouring of the previous section to ensure that the upper formwork is reliably connected without misalignment or gaps. When installing the formwork, a crane will hold the 1 / 2 formwork section and slowly drop the steel cage along the Y-shaped pier body. During the falling process, pay attention to whether there is any conflict between the formwork and the surrounding scaffolding. After the formwork is hoisted to the installation position, it is manually assisted to align with the previous section of the formwork, and temporarily fixed to the previous section of the formwork with bolts. It is forbidden to remove the hook before it is fixed or not firmly fixed to prevent the formwork from overturning. After the entire stage of formwork installation and assembly is completed, the position of the formwork needs to be calibrated, and the formwork is adjusted by support pads and inclined pull methods. After the adjustment is completed, it is finally fixed.

[0128] The stability of the Y-type bifurcated pier column template for segmented pouring mainly depends on the connecting nuts of the upper and lower sections of the template. In order to ensure that the template is installed reliably and does not tilt during the pouring of the Y-type bifurcated pier, double nuts are used to connect the pier columns, and checks are carried out between concrete pouring to ensure that there are no omissions. For safety reasons, two φ20 steel bars are used to temporarily pull the templates for the two pier columns tilted in opposite directions before pouring. At the same time, the left and right pier columns are poured alternately during the pouring process.

[0129] Both the first and second tension truss rods are made of D20 high-strength tension rods made of 45# steel. The maximum horizontal arrangement spacing is not more than 1200mm. The positive corners are all chamfered with arcs. Steel angle molds are designed separately and then connected to the adjacent lifting molds to ensure no leakage.

[0130] Technical features not described in the present invention can be achieved through or by adopting existing technologies and will not be described in detail here. Of course, the above description is not a limitation of the present invention, and the present invention is not limited to the above examples. Changes, modifications, additions or substitutions made by ordinary technicians in this technical field within the essential scope of the present invention should also fall within the scope of protection of the present invention.

Claims

1. A construction method for a large-angle Y-shaped pier continuous conversion system, characterized in that: The Y-shaped pier is divided into a straight section, a coupling section transitioning from the straight section to the oblique leg section, an oblique leg section and a cap beam from bottom to top according to the cross-sectional shape. The Y-shaped pier column is cast in layers according to the setting of the oblique support system and the convenience of construction. The specific construction method includes the following steps: S1, pouring the first layer, wherein the first layer is a coupling section where the straight section transitions to the oblique leg section; S2, pouring the second layer, wherein the second layer is the oblique leg section 2 / 3 of the vertical height above the first layer; S3, pouring the third layer, wherein the third layer is the oblique leg section which is 1 / 3 of the vertical height above the second layer; S4, pouring the VI layer, wherein the VI layer is a cap beam.

2. The construction method of the large-angle Y-shaped pier continuous conversion system according to claim 1 is characterized in that: The specific steps of S1 are as follows: S11, after the straight line segment is cast, the corresponding rigid frame 1 is hoisted, positioned and then welded; S12, tie the steel bars and install the pads, then install the corresponding templates and install the tension steel strands on the inner side of the two-leg steel bar skeleton; S13. Pour the first layer of concrete. After the first layer of concrete has formed strength, remove the corresponding formwork.

3. The construction method of the large-angle Y-shaped pier continuous conversion system according to claim 1 is characterized in that: The specific steps of S2 are as follows: S21, hoist two corresponding rigid frames (1), position them and then weld them; S22, tie the steel bars and install the pads, then install the corresponding templates and install the tension truss rods at the bracket supports of the two-leg steel frame; S23. Pour the second layer of concrete. After the second layer of concrete has formed strength, remove the corresponding formwork.

4. The construction method of the large-angle Y-shaped pier continuous conversion system according to claim 1 is characterized in that: The specific steps of S3 are as follows: S31, hoist two corresponding rigid frames (17), position them and weld them; S32, tying the steel bars and installing the pads, then installing the corresponding templates and installing the two tension truss rods at the bracket supports of the two limb steel bar skeletons; S33. Pour the third layer of concrete. After the third layer of concrete has formed strength, remove the corresponding formwork.

5. The construction method of the large-angle Y-shaped pier continuous conversion system according to claim 1 is characterized in that: The specific steps of S4 are as follows: S41, install the cap beam formwork; S42, tying steel bars; S43. Pour cap beam concrete.

6. The construction method of the large-angle Y-shaped pier continuous conversion system according to any one of claims 2 to 5, characterized in that: The steps for installing the rigid frame 1, the rigid frame 2 (1) and the rigid frame 3 (17) are as follows: A1. Calculate the plane position deviation according to the inclination and height of the rigid frame 1, the rigid frame 2 (1) or the rigid frame 3 (17), and then use a plumb line to preliminarily locate the rigid frame 1, the rigid frame 2 (1) or the rigid frame 3 (17); A2. After the rigid frame 1, the rigid frame 2 (1) or the rigid frame 3 (17) is initially positioned, it is temporarily fixed, and then a total station is used to measure and verify the precise position of the rigid frame 1, the rigid frame 2 (1) or the rigid frame 3 (17); A3. After the rigid frame 1, the rigid frame 2 (1) or the rigid frame 3 (17) are accurately positioned, spot welding is first performed around the angle steel columns of the rigid frame 1, the rigid frame 2 (1) or the rigid frame 3 (17), and then welding is performed in sections.

7. The construction method of the large-angle Y-shaped pier continuous conversion system according to claim 5 is characterized in that: The cap beam construction is completed with the assistance of a corresponding working platform, wherein the working platform is a triangular truss platform, and the triangular truss platform includes an outer triangular truss and an inner triangular truss; the Y-shaped pier is provided with embedded bolts, embedded bracket anchor boxes (8) and reserved holes (5) for tension screws for installing the triangular truss platform; The outer triangular truss and the inner triangular truss are both composed of an upper chord (9), a lower chord (10) and a web (11).