Construction method for assisting transverse tunnel to enter main tunnel
Through the advance construction of auxiliary tunnels and the cross-hole connection technology, the surrounding rock stability problem during parallel construction of main tunnels and auxiliary tunnels is solved, the construction speed and quality are improved, the construction safety and economy are ensured, and it is successfully applied to Kyrgyzstan Stann North Road Cross-ridge Tunnel Project.
Patent Information
- Application Number
- CN202410764322.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-14
- Publication Date
- 2024-11-08
Smart Images

Figure CN118911688A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel construction, and in particular to a construction method for an auxiliary tunnel cross tunnel to enter a main tunnel. Background Art
[0002] Tunnels have been developed rapidly as important transportation infrastructure. During the construction and operation of tunnels, some longer highway tunnels often design auxiliary tunnels next to the main tunnel to achieve multiple purposes such as providing geological forecasts, slag discharge channels, material transportation, ventilation and maintenance for the main tunnel. However, the distance between the auxiliary tunnel and the main tunnel is small, and the parallel construction of the main tunnel and the auxiliary tunnel may affect each other. At the same time, the construction process of the connecting cross tunnel between the main and auxiliary tunnels is complex and the accuracy is difficult to control. By connecting the cross tunnel, a new working surface is added to the main tunnel, solving the problem of the mutual influence of the surrounding rock of the cross tunnel entering the main tunnel and the complex construction process of the connecting cross tunnel. Summary of the invention
[0003] In order to solve the technical problems raised by the above background, the present invention provides a construction method for an auxiliary tunnel to enter the main tunnel through a transverse tunnel. In the project of setting up the main tunnel and the auxiliary tunnel, the auxiliary tunnel is constructed in advance to avoid the mutual influence of the parallel construction of the main and auxiliary tunnels; the main tunnel and the auxiliary tunnel are connected by a connecting transverse tunnel, and the auxiliary tunnel and the connecting transverse tunnel are used as tunnels for machinery, personnel, ventilation and other passages to increase the working surface of the main tunnel and realize the simultaneous construction of multiple working surfaces of the main tunnel. The main tunnel and the auxiliary tunnel are constructed based on the New Austrian Tunneling Method construction concept and are constructed by drilling and blasting. First, the auxiliary tunnel is excavated first. When the auxiliary tunnel is excavated for 30m, so that the heading face of the auxiliary tunnel is beyond the influence range of the surrounding rock of the main tunnel construction, the main tunnel of the tunnel is excavated to avoid the mutual influence of the main and auxiliary tunnels during the parallel excavation construction, which leads to the reduction of the stability of the surrounding rock. When the pilot tunnel is constructed to a longer distance, in order to increase the working surface and speed up the construction progress, a connecting tunnel is constructed from the pilot tunnel horizontally to the main tunnel 30m behind the auxiliary tunnel heading. The connecting cross tunnel and the auxiliary tunnel serve as a new working surface communication channel. The main tunnel starts from the new working surface and is constructed along the tunnel axis parallel to the auxiliary tunnel, forming a construction method in which the auxiliary tunnel cross tunnel enters the main tunnel.
[0004] Based on the above technical ideas, the technical solution adopted by the present invention is: A construction method for an auxiliary tunnel cross tunnel into a main tunnel, the construction method comprising the following steps: Step 1: When the auxiliary tunnel is more than 1000m ahead of the main tunnel, a cross tunnel connecting the main tunnel and the auxiliary tunnel is constructed 30m behind the auxiliary tunnel face. The cross tunnel is excavated using a five-step method, with each excavation progressing 1m, and initial support is applied in a timely manner. Step 2: When the cross tunnel is excavated to 8m on the right line of the main tunnel, reserve the core soil for the step, excavate forward 1m on the step and construct a reinforcement ring; Step 3: The cross tunnel is constructed to the junction with the main tunnel, reinforced with a portal frame and supported by joists; Step 4: Excavate the pilot tunnel and construct along the main tunnel contour excavation line with a slope of 30% to the tunnel centerline, then construct parallel to the left side contour line of the main tunnel and provide temporary support; Step 5: Main tunnel construction, excavate forward along the lower steps of the horizontal tunnel, and complete the excavation in one go; Step 6: After the main tunnel excavation is completed, partial excavation is carried out along the positive direction of the main tunnel to form a new working face. From the new working face, construction begins along the longitudinal direction of the main tunnel to both sides to speed up the construction progress of the main tunnel.
[0005] Furthermore, during the construction phase of the auxiliary tunnel and the main tunnel, TGP technology was used to predict tunnel geology in advance, and advance support construction was carried out according to the surrounding rock conditions, followed by blasting excavation using the drilling and blasting method. The cross tunnel was excavated using the five-step excavation method, with the bottom of the cross tunnel being constructed forward at a slope of 10%, and the top of the cross tunnel being constructed upward at 25°, excavating forward in a trumpet shape.
[0006] Furthermore, the horizontal tunnel excavation methods include: The position of the cross tunnel was determined 30m away from the auxiliary tunnel heading, and excavation was carried out using the five-step method, with each step advancing 1m.
[0007] (1) Excavate the first part, reserve the core soil, and immediately spray concrete. Spray C25 concrete with a thickness of 20 cm. After the concrete solidifies, excavate the second part.
[0008] (2) Excavate the second part, so that the subsequent excavation is a square excavation surface, reserve the core soil, use φ25 hollow grouting anchor rods for the arch after excavation, and then install the steel arch frame. Use I20 steel frame, the steel arch frame spacing is 1.0m, and the steel arch frames are longitudinally welded together with φ22 threaded steel bars. The circumferential spacing of the connecting bars is 1m. Use φ42 locking foot anchor pipes at the arch foot position. The anchor pipe is 3m long and 42mm in diameter. Grouting is performed immediately after installation.
[0009] (3) Excavate the third part, reserve the core soil, and immediately use C25 shotcrete for the initial spraying, with a thickness of 20 cm, and wait for it to solidify.
[0010] (4) Excavate the fourth section, reserve the core soil, and immediately use C25 shotcrete for the initial spraying, with a thickness of 20 cm, and wait for it to solidify.
[0011] (5) Excavate the fifth section, reserve the core soil, install the bottom plate steel frame, install the side wall anchor rods, set φ22 mortar anchor rods, the anchor rod length is 3m, the spacing is 1.0m×1.0m, arranged in a plum blossom shape, and the side wall is hung with φ6 steel mesh, the spacing is 20cm×20cm, 1-2 grids are overlapped, and welded point by point. At the arch foot position, a φ42 lock-foot anchor pipe is used for positioning, the anchor pipe is 3m long and 42mm in diameter.
[0012] The bottom of the horizontal tunnel is excavated forward with a slope of 10%, and the top of the horizontal tunnel is excavated upward at 25 degrees, and excavated forward in a trumpet shape. When excavated to 8m on the right line of the main tunnel, the core soil of the step is reserved, and the step is excavated forward 1m and a reinforcement ring is applied. The reinforcement ring is composed of 2 horizontal tunnel standard section steel frames in parallel, and the middle is welded with steel bars to form a triangular reinforcement area. A total of 4 groups of reinforcement rings are set up, and the spacing between each group is 1m. The arch feet on the left and right sides of each group of reinforcement rings are padded with 50cm×26cm, 14mm thick steel plates, and the thickness of the protective layer is 3cm.
[0013] After excavation is completed, the safety of the surrounding rock of the cross tunnel is assessed to determine whether secondary support is required.
[0014] Furthermore, during the horizontal tunnel construction phase, the initial support construction of the horizontal tunnel includes: (1) I20 steel frames are used within the cross tunnel, with a spacing of 1.0 m between steel arch frames. φ22 threaded steel bars are longitudinally welded together between the steel arch frames, with a circumferential spacing of 1 m between the connecting bars, and φ42 locking foot anchor pipes are used for positioning; (2) The horizontal arch wall is sprayed with C25 concrete with a thickness of 20 cm. The arch part is equipped with φ25 hollow grouting anchor rods. The side walls are equipped with φ22 mortar anchor rods. The anchor rods are 3 m long and spaced 1.0 m × 1.0 m apart. They are arranged in a plum blossom shape. The arch wall is hung with φ6 steel mesh with a spacing of 20 cm × 20 cm. They are overlapped by 1-2 meshes and welded point by point.
[0015] Furthermore, when the cross tunnel is excavated to the main tunnel excavation contour line, the portal steel frame is welded with I20 steel and connected to the reinforcement ring with bolts. A longitudinal horizontal joist is set on the steel frame arch of the reinforcement ring along the main tunnel direction, and I20 steel support columns are welded between the longitudinal horizontal joist and the portal frame, and I20 steel columns are connected at both ends of the longitudinal horizontal joist to support the bottom of the main tunnel wall; and C25 concrete is used to cover the reinforcement ring and steel support columns.
[0016] Furthermore, the pilot tunnel is constructed along the excavation line of the main tunnel contour, with a slope of 30% to the center line of the tunnel, and then constructed parallel to the left contour line of the main tunnel. An I20 temporary scaffolding is used to support the top, with a scaffolding spacing of 0.8m. The scaffolding is welded as a whole with φ22 steel bars, combined with 5cm of initial sprayed concrete, and a 20cm mesh sprayed crossbeam for the temporary scaffolding with a mesh size of 15×15cm, forming a temporary support system.
[0017] Furthermore, the main tunnel construction was completed by excavating the core soil reserved along the cross tunnel and the lower step of the main tunnel at one time.
[0018] Compared with the prior art, the present invention has the following advantages: 1. The present invention adopts the advanced construction of auxiliary tunnels, the small guide tunnel scaffolding climbing method is used to excavate the connecting cross tunnels, and a new working surface of the main tunnel is added through the cross tunnel construction. The new working surface is used to construct the main tunnel along the longitudinal direction to both sides, thereby speeding up the construction speed while ensuring the construction quality.
[0019] 2. When the cross tunnel is close to the main tunnel construction section, the core soil is reserved, and the cross tunnel is excavated together with the main tunnel after the initial support. Compared with the method of excavating the cross tunnel once and then backfilling the slag to form the working surface, it greatly reduces the disturbance of the surrounding rock and ensures the safety of construction. 3. The highway parallel main and auxiliary tunnel joint construction method designed by the present invention meets the Gost standard and Chinese standard in terms of quality control; and has achieved significant benefits in terms of safety and economy. Moreover, this method has been successfully applied in the cross-mountain tunnel project of the North-South Road in Kyrgyzstan, and has a high value of promotion and application. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 Schematic diagram of the plan layout of auxiliary tunnels, main tunnels and cross tunnels.
[0021] Figure 2 for Figure 1 Schematic diagram of the connection between the main tunnel and the cross tunnel portal frame in section 1-1.
[0022] Figure 3 for Figure 1 Layout diagram of the connection between the 2-2 section joist and the main tunnel steel arch and steel support.
[0023] Figure 4 This is the connection layout diagram between the support beam and the main tunnel steel frame.
[0024] Figure 5 This is a schematic diagram of the longitudinal construction of the main tunnel at the cross tunnel.
[0025] Figure 6 This is a schematic diagram of the five-part method of excavation of a horizontal tunnel.
[0026] Figure 7 Construction photos of reinforcing rings being installed for horizontal tunnels.
[0027] Figure 8 These are construction photos of the door frame and joists.
[0028] Fig. 9 Construction photos showing the excavation of the cross tunnel to the main tunnel and the new working surface.
[0029] Fig.10 Construction photos of simple scaffolding for the horizontal tunnel.
[0030] Fig.11 Construction photo of the arch erection (close-up).
[0031] Fig.12 Construction photo of the arch erection (distant view).
[0032] Fig.13 Construction photos showing the completion of the initial support construction of the horizontal tunnel.
[0033] Fig.14 Construction photos of laying waterproof panels for horizontal tunnels. DETAILED DESCRIPTION
[0034] The present invention will be further described below in conjunction with specific embodiments. It should be understood that these embodiments are only used to illustrate the present invention and are not intended to limit the scope of the present invention. In addition, it should be understood that after reading the content taught by the present invention, those skilled in the art can make various changes or modifications to the present invention, and these equivalent forms fall within the scope limited by the appended claims of the application equally.
[0035] This embodiment specifically provides a construction method for an auxiliary tunnel cross tunnel to a main tunnel, and the construction method comprises the following steps: Step 1: When the auxiliary tunnel is more than 1000m ahead of the main tunnel, a cross tunnel connecting the main tunnel and the auxiliary tunnel is constructed 30m behind the auxiliary tunnel face. The cross tunnel is excavated using a five-step method, with each excavation progressing 1m, and initial support is applied in a timely manner. Step 2: When the cross tunnel is excavated to 8m on the right line of the main tunnel, reserve the core soil for the step, excavate forward 1m on the step and construct a reinforcement ring; Step 3: The cross tunnel is constructed to the junction of the main tunnel, reinforced with a portal frame, and joists are installed; Step 4: Excavate the pilot tunnel and construct along the main tunnel contour excavation line with a slope of 30% to the tunnel centerline, then construct parallel to the left side contour line of the main tunnel and provide temporary support; Step 5: Main tunnel construction, excavate forward along the lower steps of the horizontal tunnel, and complete the excavation in one go; Step 6: After the main tunnel excavation is completed, partial excavation is carried out along the positive direction of the main tunnel to form a new working face. From the new working face, construction begins along the longitudinal direction of the main tunnel to both sides to speed up the construction progress of the main tunnel.
[0036] During the auxiliary tunnel construction phase, TGP technology was used to predict tunnel geology in advance, and advance support construction was carried out according to the surrounding rock conditions, followed by blasting excavation using the drilling and blasting method. The cross tunnel was excavated using the five-step excavation method, with the bottom of the cross tunnel being constructed forward at a slope of 10%, and the top of the cross tunnel being constructed upward at 25°, excavating forward in a trumpet shape.
[0037] After the cross tunnel is constructed to the junction with the main tunnel, it enters the main tunnel in the form of an orthogonal trumpet, and at the same time excavates uphill to the elevation of the main tunnel vault, and continues to excavate in the same direction for a certain distance; after the working space is formed, it turns to the opposite direction for construction, and expands the temporary support to reach the standard section of the main tunnel.
[0038] The present invention provides a horizontal tunnel excavation method, which is as follows: The position of the cross tunnel was determined 30m away from the auxiliary tunnel heading, and excavation was carried out using the five-step method, with each step advancing 1m.
[0039] (1) Excavate the first part, reserve the core soil, and immediately spray concrete. Spray C25 concrete with a thickness of 20 cm. After the concrete solidifies, excavate the second part.
[0040] (2) Excavate the second part, so that the subsequent excavation is a square excavation surface, reserve the core soil, use φ25 hollow grouting anchor rods for the arch after excavation, and then install the steel arch frame. Use I20 steel frame, the steel arch frame spacing is 1.0m, and the steel arch frames are longitudinally welded together with φ22 threaded steel bars. The circumferential spacing of the connecting bars is 1m. Use φ42 locking foot anchor pipes at the arch foot position. The anchor pipe is 3m long and 42mm in diameter. Grouting is performed immediately after installation.
[0041] (3) Excavate the third part, reserve the core soil, and immediately use C25 shotcrete for the initial spraying, with a thickness of 20 cm, and wait for it to solidify.
[0042] (4) Excavate the fourth section, reserve the core soil, and immediately use C25 shotcrete for the initial spraying, with a thickness of 20 cm, and wait for it to solidify.
[0043] (5) Excavate the fifth section, reserve the core soil, install the bottom plate steel frame, install the side wall anchor rods, set φ22 mortar anchor rods, the anchor rod length is 3m, the spacing is 1.0m×1.0m, arranged in a plum blossom shape, and the side wall is hung with φ6 steel mesh, the spacing is 20cm×20cm, 1-2 grids are overlapped, and welded point by point. At the arch foot position, a φ42 lock-foot anchor pipe is used for positioning, the anchor pipe is 3m long and 42mm in diameter.
[0044] The bottom of the horizontal tunnel is excavated forward with a slope of 10%, and the top of the horizontal tunnel is excavated upward at 25 degrees, and excavated forward in a trumpet shape. When excavated to 8m on the right line of the main tunnel, the core soil of the step is reserved, and the step is excavated forward 1m and a reinforcement ring is applied. The reinforcement ring is composed of 2 horizontal tunnel standard section steel frames in parallel, and the middle is welded with steel bars to form a triangular reinforcement area. A total of 4 groups of reinforcement rings are set up, and the spacing between each group is 1m. The arch feet on the left and right sides of each group of reinforcement rings are padded with 50cm×26cm, 14mm thick steel plates, and the thickness of the protective layer is 3cm.
[0045] The following is the initial support construction of the cross tunnel when the cross tunnel is excavated to the stage close to the main tunnel construction: (1) I20 steel frames are used within the cross tunnel, with a spacing of 1.0 m between steel arch frames. φ22 threaded steel bars are longitudinally welded together between the steel arch frames, with a circumferential spacing of 1 m between the connecting bars, and φ42 locking foot anchor pipes are used for positioning; (2) The horizontal arch wall is sprayed with C25 concrete with a thickness of 20 cm. The arch part is equipped with φ25 hollow grouting anchor rods. The side walls are equipped with φ22 mortar anchor rods. The anchor rods are 3 m long and spaced 1.0 m × 1.0 m apart. They are arranged in a plum blossom shape. The arch wall is hung with φ6 steel mesh with a spacing of 20 cm × 20 cm. They are overlapped by 1-2 meshes and welded point by point.
[0046] When the cross tunnel is excavated to the main tunnel excavation contour line, the portal steel frame is welded with I20 steel and connected to the reinforcement ring with bolts. A longitudinal horizontal joist is set on the steel frame arch of the reinforcement ring along the direction of the main tunnel. The longitudinal horizontal joist and the portal frame are welded with I20 steel support columns, and I20 steel columns are connected at both ends of the longitudinal horizontal joist to support the bottom of the main tunnel wall; and the reinforcement ring and steel support columns are covered with C25 concrete.
[0047] Then the pilot tunnel was constructed along the excavation line of the main tunnel contour, with a slope of 30% to the center line of the tunnel, and then parallel to the left contour line of the main tunnel. An I20 temporary scaffolding was used to support the top, with a scaffolding spacing of 0.8m. The scaffolding was welded as a whole with φ22 steel bars, combined with 5cm of initial sprayed concrete, and a 20cm mesh sprayed crossbeam for the temporary scaffolding with a mesh size of 15×15cm to form a temporary support system.
[0048] Then the main tunnel construction started, and the core soil reserved along the cross tunnel and the lower step part of the main tunnel were excavated at one time.
[0049] Case: Construction of a mountain-crossing tunnel on the Kyrgyz North-South Road The construction area is located in Jalal-Abad Province, Kyrgyz Republic. The tunnel area from the cross tunnel to the main tunnel is excavated using the above-mentioned construction method of the auxiliary tunnel cross tunnel into the main tunnel.
[0050] The specific steps are as follows: Step 1: When the auxiliary tunnel is ahead of the main tunnel by more than 1000m, a cross tunnel connecting the main tunnel and the auxiliary tunnel is constructed 30m behind the auxiliary tunnel face. The cross tunnel is excavated using a 5-step excavation method, with 1m excavated each time, and initial support is applied in a timely manner.
[0051] The initial support construction of the horizontal tunnel includes: (1) I20 steel frames are used within the cross tunnel, with a spacing of 1.0 m between steel arch frames. φ22 threaded steel bars are longitudinally welded together between the steel arch frames, with a circumferential spacing of 1 m between the connecting bars, and φ42 locking foot anchor pipes are used for positioning; (2) The C25 concrete spraying thickness of the horizontal tunnel arch wall is 20cm. The arch part is equipped with φ25 hollow grouting anchor rods. The side walls are equipped with φ22 mortar anchor rods. The anchor rods are 3m long and 1.0m×1.0m apart. They are arranged in a plum blossom shape. The arch wall is hung with φ6 steel mesh with a spacing of 20cm×20cm. 1-2 meshes are overlapped and welded point by point. Fig.13After the initial support is completed, waterproof treatment is carried out and waterproof boards are laid, such as Fig.14 shown.
[0052] Step 2: When the cross tunnel is excavated to 8m on the right line of the main tunnel, reserve the core soil of the step, excavate forward 1m on the step and apply the reinforcement ring, such as Figure 7 shown.
[0053] like Fig.10 As shown in the figure, a simple scaffolding is set up in the horizontal hole to facilitate the construction of the horizontal hole arch frame and reinforcement ring. The reinforcement ring is composed of two horizontal hole standard section steel frames side by side, and the middle is welded with steel bars to form a triangular reinforcement area. A total of 4 groups of reinforcement rings are set, and the spacing between each group is 1m. Fig.11 and 12 As shown, the arch frame has been erected.
[0054] Step 3: The cross tunnel is constructed to the junction of the main tunnel, reinforced with a portal frame and supported by joists, such as Figure 8 The portal steel frame is welded with I20 steel and connected with the reinforcement ring with bolts. A longitudinal horizontal joist is set on the steel frame arch of the reinforcement ring along the main tunnel direction. The longitudinal horizontal joist is welded with steel support columns to the portal frame, and steel columns are connected at both ends of the longitudinal horizontal joist to support the bottom of the main tunnel wall. The reinforcement ring and the steel support column are covered with C25 concrete.
[0055] Step 4: Excavate the pilot tunnel and construct along the main tunnel contour excavation line with a slope of 30% to the tunnel centerline, then construct parallel to the left side contour line of the main tunnel and provide temporary support; Step 5: Main tunnel construction, excavate forward along the lower steps of the horizontal tunnel, and complete the excavation in one go; Step 6: After the main tunnel excavation is completed, the new working face is formed by partial excavation along the positive direction of the main tunnel. The new working face is used to start construction along the longitudinal direction of the main tunnel to both sides to speed up the construction progress of the main tunnel. Fig. 9 shown.
[0056] The above contents are further detailed descriptions of the present invention in combination with specific preferred embodiments, so that those skilled in the art can understand and apply the present invention. It cannot be determined that the specific implementation of the present invention is limited to these descriptions. For those skilled in the art of the present invention, some simple deductions or substitutions can be made without departing from the concept of the present invention, without creative work. Therefore, simple improvements made to the present invention by those skilled in the art based on the disclosure of the present invention should be within the scope of protection of the present invention.
Claims
1. A construction method for an auxiliary tunnel cross tunnel into a main tunnel, characterized in that: The construction method comprises the following steps: Step 1: When the auxiliary tunnel is ahead of the main tunnel by more than 1000m, a cross tunnel connecting the main tunnel and the auxiliary tunnel is constructed 30m behind the auxiliary tunnel face. The cross tunnel is excavated using a five-step method, with each excavation progressing 1m, and initial support is applied in a timely manner. Step 2: When the cross tunnel is excavated to 8m on the right line of the main tunnel, reserve the core soil for the step, excavate forward 1m on the step and construct a reinforcement ring; Step 3: The cross tunnel is constructed to the junction with the main tunnel, reinforced with a portal frame and supported by joists; Step 4: Excavate the pilot tunnel and construct along the main tunnel contour excavation line with a slope of 30% to the tunnel centerline, then construct parallel to the left side contour line of the main tunnel and provide temporary support; Step 5: Main tunnel construction, excavate forward along the lower steps of the horizontal tunnel, and complete the excavation in one go; Step 6: After the main tunnel excavation is completed, partial excavation is carried out along the positive direction of the main tunnel to form a new working face. From the new working face, construction begins along the main tunnel in the longitudinal direction to both sides to speed up the construction progress of the main tunnel.
2. The construction method of an auxiliary tunnel cross tunnel into a main tunnel according to claim 1, characterized in that: In step 1, during the construction phase of the auxiliary tunnel and the main tunnel, TGP technology is used to predict the tunnel geology in advance, and advance support construction is carried out according to the surrounding rock conditions. Then, the drilling and blasting method is used for blasting excavation. The cross tunnel adopts the 5-step excavation method. The bottom of the cross tunnel is constructed forward at a slope of 10%, and the top of the cross tunnel is constructed upward at 25°, and it is excavated forward in a trumpet shape.
3. The construction method of an auxiliary tunnel cross tunnel into a main tunnel according to claim 2, characterized in that: The initial support construction of the horizontal tunnel in step 1 includes: (1) I20 steel frames are used within the cross-hole arch range, with a spacing of 1.0 m between the steel arch frames. The steel arch frames are longitudinally welded together with φ22 threaded steel bars, and the circumferential spacing of the connecting bars is 1 m. φ42 locking foot anchor pipes are used for positioning; φ6 steel mesh is hung on the side wall, with a spacing of 20 cm × 20 cm, 1-2 meshes are overlapped, and welded point by point; (2) For the vault of the horizontal tunnel, the side walls are sprayed with C25 concrete with a thickness of 20 cm. The arch is equipped with φ25 hollow grouting anchor rods, and the side walls are equipped with φ22 mortar anchor rods. The anchor rods are 3 m long, with a spacing of 1.0 m × 1.0 m, and are arranged in a plum blossom shape.
4. The construction method of the auxiliary tunnel cross tunnel into the main tunnel according to claim 3 is characterized in that: In step 2, when the cross tunnel excavation construction reaches 8m on the right line of the main tunnel, reserve the core soil of the step, excavate forward 1m on the upper step and apply the reinforcement ring. The reinforcement ring is composed of 2 cross tunnel standard section steel frames arranged side by side, and steel bars are welded in the middle to form a triangular reinforcement area. There are 4 groups of reinforcement rings in total, and the spacing between each group is 1m.
5. The construction method of the auxiliary tunnel cross tunnel into the main tunnel according to claim 4 is characterized in that: In step 3, the portal steel frame is welded with I20 steel and connected to the reinforcement ring with bolts. A longitudinal horizontal support beam is set on the steel frame arch of the reinforcement ring along the direction of the main tunnel. Steel support columns are welded between the longitudinal horizontal support beam and the portal frame, and steel columns are connected at both ends of the longitudinal horizontal support beam to support the bottom of the main tunnel wall. C25 concrete covers the reinforcement ring and the steel support column.
6. A construction method for an auxiliary tunnel transverse tunnel to a main tunnel according to claim 5, characterized in that: In step 4, the excavation of the pilot tunnel is carried out along the excavation line of the main tunnel contour, with a slope of 30% to the center line of the tunnel, and then parallel to the left contour line of the main tunnel, with temporary support.
7. A construction method for an auxiliary tunnel transverse tunnel to a main tunnel according to claim 6, characterized in that: In step 5, the main tunnel construction is completed by excavating the core soil reserved along the cross tunnel and the lower step of the main tunnel at one time.
8. The construction method of the auxiliary tunnel cross tunnel into the main tunnel according to claim 7 is characterized in that: After the pilot tunnel climbs obliquely upward to the center line of the tunnel, it is excavated forward on a flat slope to the left contour line of the main tunnel. The top of the main tunnel is supported by an I20 temporary scaffolding with a scaffolding spacing of 0.8m. The scaffolding is welded as a whole with φ22 steel bars, combined with 5cm initial sprayed concrete. The temporary scaffolding beams are sprayed with 20cm mesh with a mesh size of 15×15cm to form a temporary support system.