Construction method for tunnel reverse slope drainage
By setting up water collection pits and multi-stage sedimentation tanks in tunnel construction in high-altitude areas, sewage and clean water are diverted, which solves the problem of groundwater discharge in tunnels, reduces the impact of construction on the water environment, and achieves efficient and low-cost drainage Solution.
Patent Information
- Application Number
- CN202410968288.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-18
- Publication Date
- 2024-11-08
AI Technical Summary
During tunnel construction in high-altitude areas, groundwater drainage problems and high environmental protection requirements have led to limited construction safety and progress, and the drainage system is complex, making it difficult to effectively treat sewage and clean water in water-rich areas.
A tunnel back slope drainage construction method is adopted, by setting up a water collection hole, a multi-stage sedimentation tank and a central ditch, and using a pump station and a sedimentation tank to divert sewage and clean water, to achieve step by step Sedimentation and discharge to ensure that sewage meets the standards and discharges.
It has achieved effective sewage control and drainage in long-distance tunnels, reduced the impact of construction on the water environment, significant water saving effect and low cost, and is suitable for tunnel construction under high buried depth and complex geological conditions.
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel construction, and in particular to a construction method for tunnel slope drainage. Background Art
[0002] At present, with the implementation of the national policy of vigorously developing infrastructure, tunnel construction technology has been vigorously developed, and tunnel construction in high-altitude areas has become more and more common. Tunnels in high-altitude areas are often located in mountain gullies, with variable terrain and large ups and downs, mainly woodland and grassland, high altitude, low air pressure, low oxygen content, high cold and strong winds in plateau areas. Due to low oxygen content, the labor efficiency of personnel and machinery is reduced.
[0003] In addition, the ecological environment of tunnels in high-altitude areas is relatively fragile, and the requirements for environmental protection during construction are extremely high, especially in the construction of water-rich karst tunnels in complex environments with high burial depths and long distances. Whether the groundwater drainage is unobstructed and whether the groundwater drainage can be guaranteed and the impact on the water environment can be reduced are related to the safety and progress of the entire tunnel construction.
[0004] Due to the long tunnel, steep slope and great interference between various working surfaces, not only are high requirements placed on transportation and ventilation in the tunnel, but drainage in water-rich areas will also become more difficult. How to deal with these problems and ensure construction safety and progress quality is a difficult point in tunnel drainage construction. Summary of the invention
[0005] In order to solve the defects in the prior art, the present invention provides a construction method for tunnel slope drainage. The present invention is suitable for long-distance tunnel pollution control and drainage, and can solve the problem of tunnel groundwater discharge; the structure is simple, the investment is small, the operation and maintenance are convenient, the space occupied is small, and the dynamic transportation of tunnel slag is not affected, and the water-saving effect is significant, and the pollution control cost is low.
[0006] To achieve the above object, the present invention provides a construction method for tunnel slope drainage, comprising the following construction steps:
[0007] 1) Set up a sump on the face and arrange the first-level pumping station there;
[0008] 2) Set up a sump at the end of the invert and arrange the second-stage pumping station there;
[0009] 3) Set up a four-stage sedimentation tank for sewage sedimentation and discharge; set up a third-stage pump station in the four-stage sedimentation tank;
[0010] 4) Set up a central ditch and its sump for clear water discharge; a third-level pumping station is also set up on the central ditch;
[0011] 5) The water in the water collection pit at the face is pumped to the first-stage sedimentation tank in the four-stage sedimentation tank by the first-stage pump station;
[0012] 6) The clean water in the sump at the end of the invert is discharged through the second-stage pump station, and the clean water in the central ditch is discharged through the third-stage pump station;
[0013] 7) The sewage in the sump at the end of the invert is pumped to the first sedimentation tank in the four-stage sedimentation tank through the second-stage pumping station.
[0014] 8) The sewage pumped into the first-stage sedimentation tank is continuously precipitated step by step in the four-stage sedimentation tank and discharged after reaching the standards.
[0015] Preferably, the tunnel is excavated in both directions, a longitudinal slope of 2.83% is set from the entrance to the exit of the tunnel, and reverse slope drainage is adopted for the tunnel exit construction, that is, the construction direction in the tunnel is downhill.
[0016] In any of the above schemes, it is preferred that the first-stage pumping station includes two 30kw mobile submersible pumps to pump the sewage to the first-stage sedimentation tank among the four-stage sedimentation tanks; the second-stage pumping station includes two 30kw submersible pumps, in the step 6), one of the 30kw submersible pumps delivers the clean water in the sump at the end of the invert arch to the mobile clean water tank for discharge, and in the step 7), the other 30kw submersible pump pumps the sewage remaining after sedimentation in the sump at the end of the invert arch to the first-stage sedimentation tank among the four-stage sedimentation tanks for further sedimentation.
[0017] In any of the above schemes, it is preferred that in step 3), a four-stage sedimentation tank is provided in the widened section to carry out sewage sedimentation treatment.
[0018] In any of the above schemes, preferably, in the step 3), the first-stage sedimentation tank is set to a size of 6m×12m×2.39m×1.47m, the second-stage sedimentation tank is set to a size of 6m×12m×2.39m×1.47m, the third-stage sedimentation tank is set to a size of 6m×9m×2.39m×1.47m, and the fourth-stage sedimentation tank is set to a size of 6m×12m×2.39m×1.47m; the wall thickness of each stage of the sedimentation tank is 30cm and is cast with C20 concrete.
[0019] In any of the above schemes, it is preferred that in step 4), a concrete fixed plug is set every 400m in the central ditch, and the third-level pumping station installed on the central ditch includes a 30kw mobile submersible pump, which pumps the clean water returning from the central ditch into a mobile clean water tank, and then sends the clean water to the outside of the cave for unified discharge through the booster pumping station.
[0020] Among any of the above schemes, it is preferred that, in order to reduce interference with construction in the tunnel, the excavation width of the water collection pit at the heading face should be reduced, and its setting dimensions are 3m×2m×1m; the setting dimensions of the water collection pit at the end of the invert arch are 5m×3m×2m; the setting dimensions of the mobile clean water tank are 3m×2m×1.5m; in order to reduce the damage to the water pump and drainage pipeline caused by mud and impurities in the tunnel, the mobile clean water tank is arranged in two compartments, and a filter baffle is arranged in the middle, which can also play a role in enhancing the rigidity of the water tank.
[0021] In any of the above schemes, it is preferred that a third-stage pumping station including two 30kw submersible pumps is set in the four-stage sedimentation tank. In the step 8), the sewage treated by continuous step-by-step sedimentation is pumped into a mobile sewage tank. A 55kw submersible pump is set in the mobile sewage tank to send the sewage to the sewage treatment equipment outside the cave for final treatment, and then discharged after the sewage meets the standards.
[0022] In any of the above schemes, it is preferred that the sewage treatment equipment includes: 10 integrated high-efficiency sedimentation tanks, 6.5m high and 3.0m in diameter; 2 sedimentation tanks, with dimensions of 10m×3m×3m; a dosing room, with dimensions of 8m×3m×2mm; a clear water tank and a sludge tank, with dimensions of 6m×3m×3m.
[0023] In any of the above schemes, it is preferred that the tunnel face is connected to the mobile sewage tank through a hose, and the mobile clean water tank or the mobile sewage tank is connected to the outside of the tunnel through an iron pipe.
[0024] Beneficial effects of the present invention:
[0025] 1. The present invention is suitable for pollution control and drainage in long-distance tunnels and can solve the problem of groundwater discharge in tunnels; it has a simple structure, low investment, convenient operation and maintenance, occupies a small space, does not affect the dynamic transportation of tunnel debris, and has a significant water-saving effect and low pollution control cost.
[0026] 2. In order to prevent the mixing of clean and dirty water in tunnel drainage, which would increase the pressure on sewage treatment, the present invention separates clean and dirty water for drainage, thereby reducing the generation of tunnel construction wastewater from the construction source and reducing the impact on the water environment around the construction.
[0027] 3. The present invention can be applied to sewage treatment and drainage in deep and long-distance tunnels; the sewage drainage capacity of tunnels should reach 9500m 3 / d, that is, the drainage capacity per hour is 395m 3 ; The clean water drainage capacity of the central ditch should reach 4000m 3 / d, that is, the drainage capacity per hour is 166.7m 3 The construction progress of the tunnel reverse slope drainage closely follows the tunnel face, which can solve the drainage problem of long-distance tunnels.
[0028] 4. The present invention sets sump at the face and the end of the invert to ensure that sewage at the face and the invert does not overflow, thereby ensuring smooth continuation of the construction process; the present invention has the advantages of less manpower, high environmental protection, good soil and water conservation effect, low construction cost, high construction efficiency, low construction risk and strong popularization and applicability in tunnel construction. DETAILED DESCRIPTION
[0029] The technical solution of the present application will be described in detail below in conjunction with the specific implementation methods of the present application, but the following examples are only for understanding the present invention. The embodiments in the present application and the features in the embodiments can be combined with each other, and the present application can be implemented in a variety of different ways as defined and covered by the claims.
[0030] Example 1
[0031] A construction method for tunnel slope drainage, comprising the following construction steps:
[0032] 1) Set up a sump on the face and arrange the first-level pumping station there;
[0033] 2) Set up a sump at the end of the invert and arrange the second-stage pumping station there;
[0034] 3) Set up a four-stage sedimentation tank for sewage sedimentation and discharge; set up a third-stage pump station in the four-stage sedimentation tank;
[0035] 4) Set up a central ditch and its sump for clear water discharge; a third-level pumping station is also set up on the central ditch;
[0036] 5) The water in the water collection pit at the face is pumped to the first-stage sedimentation tank in the four-stage sedimentation tank by the first-stage pump station;
[0037] 6) The clean water in the sump at the end of the invert is discharged through the second-stage pump station, and the clean water in the central ditch is discharged through the third-stage pump station;
[0038] 7) The sewage in the sump at the end of the invert is pumped to the first sedimentation tank in the four-stage sedimentation tank through the second-stage pumping station.
[0039] 8) The sewage pumped into the first-stage sedimentation tank is continuously precipitated step by step in the four-stage sedimentation tank and discharged after reaching the standards.
[0040] The tunnel adopts bidirectional excavation, and a longitudinal slope of 2.83% is set from the entrance to the exit of the tunnel. The tunnel exit construction adopts reverse slope drainage, that is, the construction direction in the tunnel is downhill.
[0041] The first-stage pumping station includes two 30kw mobile submersible pumps, which pump sewage to the first-stage sedimentation tank among the four-stage sedimentation tanks; the second-stage pumping station includes two 30kw submersible pumps, in the step 6), one of the 30kw submersible pumps delivers the clean water in the sump at the end of the invert to the mobile clean water tank for discharge, and in the step 7), the other 30kw submersible pump pumps the remaining sewage after sedimentation in the sump at the end of the invert to the first-stage sedimentation tank among the four-stage sedimentation tanks for further sedimentation.
[0042] In the step 3), four-stage sedimentation tanks are set up in the widened section to treat the sewage.
[0043] In the step 3), the first-stage sedimentation tank is set to a size of 6m×12m×2.39m×1.47m, the second-stage sedimentation tank is set to a size of 6m×12m×2.39m×1.47m, the third-stage sedimentation tank is set to a size of 6m×9m×2.39m×1.47m, and the fourth-stage sedimentation tank is set to a size of 6m×12m×2.39m×1.47m; the wall thickness of each level of sedimentation tank is 30cm and is poured with C20 concrete.
[0044] In the step 4), a concrete fixed plug is set every 400m in the central ditch, and the third-level pump station set on the central ditch includes a 30kw mobile submersible pump, which pumps the clean water returned from the central ditch into a mobile clean water tank, and then sends the clean water to the outside of the cave for unified discharge through the booster pump station.
[0045] In order to reduce the interference to the construction in the tunnel, the excavation width of the water collection pit on the heading face should be reduced, and its setting dimensions are 3m×2m×1m; the setting dimensions of the water collection pit at the end of the invert arch are 5m×3m×2m; the setting dimensions of the mobile clean water tank are 3m×2m×1.5m; in order to reduce the damage of mud and impurities in the tunnel to the water pump and drainage pipeline, the mobile clean water tank is set into two compartments, and a filter baffle is set in the middle, which can also play a role in enhancing the rigidity of the water tank.
[0046] The third-level pumping station is set in the four-level sedimentation tank, including two 30kw submersible pumps. In the step 8), the sewage treated by continuous step-by-step sedimentation is pumped into a mobile sewage tank. A 55kw submersible pump is set in the mobile sewage tank to send the sewage to the sewage treatment equipment outside the cave for final treatment, and then discharged after the sewage meets the standards.
[0047] The sewage treatment equipment includes: 10 integrated high-efficiency sedimentation tanks, 6.5m high and 3.0m in diameter; 2 sedimentation tanks, with dimensions of 10m×3m×3m; a dosing room, with dimensions of 8m×3m×2mm; a clear water tank and a sludge tank, both with dimensions of 6m×3m×3m.
[0048] The face is connected to the mobile sewage tank via a hose, and the mobile clean water tank or mobile sewage tank is connected to the outside of the tunnel via an iron pipe.
[0049] Example 2
[0050] A construction method for tunnel slope drainage, comprising the following construction steps:
[0051] 1) Set up a sump on the face and arrange the first-level pumping station there;
[0052] 2) Set up a sump at the end of the invert and arrange the second-stage pumping station there;
[0053] 3) Set up a four-stage sedimentation tank for sewage sedimentation and discharge; set up a third-stage pump station in the four-stage sedimentation tank;
[0054] 4) Set up a central ditch and its sump for clear water discharge; a third-level pumping station is also set up on the central ditch;
[0055] 5) The water in the water collection pit at the face is pumped to the first-stage sedimentation tank in the four-stage sedimentation tank by the first-stage pump station;
[0056] 6) The clean water in the sump at the end of the invert is discharged through the second-stage pump station, and the clean water in the central ditch is discharged through the third-stage pump station;
[0057] 7) The sewage in the sump at the end of the invert is pumped to the first sedimentation tank in the four-stage sedimentation tank through the second-stage pumping station.
[0058] 8) The sewage pumped into the first-stage sedimentation tank is continuously precipitated step by step in the four-stage sedimentation tank and discharged after reaching the standards.
[0059] The tunnel adopts bidirectional excavation, and a longitudinal slope of 2.83% is set from the entrance to the exit of the tunnel. The tunnel exit construction adopts reverse slope drainage, that is, the construction direction in the tunnel is downhill.
[0060] The first-stage pumping station includes two 30kw mobile submersible pumps, which pump sewage to the first-stage sedimentation tank among the four-stage sedimentation tanks; the second-stage pumping station includes two 30kw submersible pumps, in the step 6), one of the 30kw submersible pumps delivers the clean water in the sump at the end of the invert to the mobile clean water tank for discharge, and in the step 7), the other 30kw submersible pump pumps the remaining sewage after sedimentation in the sump at the end of the invert to the first-stage sedimentation tank among the four-stage sedimentation tanks for further sedimentation.
[0061] In the step 3), four-stage sedimentation tanks are set up in the widened section to treat the sewage.
[0062] In the step 3), the first-stage sedimentation tank is set to a size of 6m×12m×2.39m×1.47m, the second-stage sedimentation tank is set to a size of 6m×12m×2.39m×1.47m, the third-stage sedimentation tank is set to a size of 6m×9m×2.39m×1.47m, and the fourth-stage sedimentation tank is set to a size of 6m×12m×2.39m×1.47m; the wall thickness of each level of sedimentation tank is 30cm and is poured with C20 concrete.
[0063] In the step 4), a concrete fixed plug is set every 400m in the central ditch, and the third-level pump station set on the central ditch includes a 30kw mobile submersible pump, which pumps the clean water returned from the central ditch into a mobile clean water tank, and then sends the clean water to the outside of the cave for unified discharge through the booster pump station.
[0064] In order to reduce the interference to the construction in the tunnel, the excavation width of the water collection pit on the heading face should be reduced, and its setting dimensions are 3m×2m×1m; the setting dimensions of the water collection pit at the end of the invert arch are 5m×3m×2m; the setting dimensions of the mobile clean water tank are 3m×2m×1.5m; in order to reduce the damage of mud and impurities in the tunnel to the water pump and drainage pipeline, the mobile clean water tank is set into two compartments, and a filter baffle is set in the middle, which can also play a role in enhancing the rigidity of the water tank.
[0065] The third-level pumping station is set in the four-level sedimentation tank, including two 30kw submersible pumps. In the step 8), the sewage treated by continuous step-by-step sedimentation is pumped into a mobile sewage tank. A 55kw submersible pump is set in the mobile sewage tank to send the sewage to the sewage treatment equipment outside the cave for final treatment, and then discharged after the sewage meets the standards.
[0066] The sewage treatment equipment includes: 10 integrated high-efficiency sedimentation tanks, 6.5m high and 3.0m in diameter; 2 sedimentation tanks, with dimensions of 10m×3m×3m; a dosing room, with dimensions of 8m×3m×2mm; a clear water tank and a sludge tank, both with dimensions of 6m×3m×3m.
[0067] The face is connected to the mobile sewage tank via a hose, and the mobile clean water tank or mobile sewage tank is connected to the outside of the tunnel via an iron pipe.
[0068] In addition, in order to further improve the technical effect of the present invention, in this embodiment, in the step 3), the construction method of setting a four-stage sedimentation tank includes:
[0069] A. Measurement and Stakeout
[0070] According to the design drawings, use a total station to measure and lay out the walls of the sedimentation tank, paying attention to the height and thickness of the wall. After the measurement and layout is completed, re-measurement is carried out, and only after passing it can the next process of construction be started.
[0071] B. Pre-embedded steel bars in the pool wall
[0072] Vertically embedded Φ25 steel bars are welded to the inverted arch steel bars. The front, back, left and right spacing of the steel bars is 25cm and the length of the steel bars is 50cm.
[0073] C. Invert construction
[0074] After the pre-embedded steel bars of the pool wall are completed, the inverted arch concrete C30 is poured. After the continuous pouring of the inverted arch concrete is completed, the concrete is vibrated with an inserted vibrator to make it dense, the surface is compacted and smoothed, and the construction joints are set and processed according to the design and specification requirements.
[0075] D. Formwork support
[0076] After the inverted arch concrete reaches the required strength, a steel pipe support is erected on the outside of the pool wall, and the formwork is installed. The inner and outer forms are connected together by through bolts, and the steel pipe support is used to adjust the formwork into place and reinforce it. The contact surface between the formwork and the concrete is coated with a release agent as an isolation agent. After the formwork is installed, the axis position and elevation are re-measured to meet the design requirements. When removing the formwork, first loosen the bolts, remove part of the upper support iron pipe, and then remove the form card, and remove the formwork in blocks to prevent the concrete surface or corners from being damaged. Finally, remove the lower support, and remove the steel pipe in batches to ensure safety. The pool wall uses wooden formwork, and tie rods are used as horizontal and vertical rods. The formwork support has sufficient strength, rigidity and stability. The joint of the formwork is no more than 2mm.
[0077] E. Pouring of pool wall concrete
[0078] The pool wall concrete pouring adopts C20 concrete, with a water-to-cement grade of P8. Ordinary Portland cement is used for concrete cement, with a water-cement ratio of no more than 0.5; the particle size of coarse aggregate is no more than 40mm, and no more than 1 / 4 of the minimum section thickness; the mud content is no more than 1% by weight; the mud content and mica content of sand are no more than 3% by weight; the maximum alkali content in concrete meets the requirements of the "Standard for Limits of Alkali Content in Concrete"; the concrete is divided into sections and layers according to the horizontal plane, and poured evenly and continuously, and the pool wall should be layered and circled. Each layer is 30-50cm thick. Concrete is vibrated and compacted. The concrete is vibrated carefully and fully compacted with a vibrator, the vibration time is 8-15s, and the spacing is about 50cm. Avoid missing vibration, insufficient vibration, excessive vibration and collision with steel bars. It is strictly forbidden to use a vibrator to push and distribute concrete to avoid segregation or local formation of slurry pools. The time from the discharge of concrete from the mixer to the pouring of the second layer of concrete is no more than 3h when the temperature is less than 25℃; no more than 2.5h when the temperature is greater than or equal to 25℃.
[0079] F. Pool wall concrete maintenance
[0080] After the waterproof concrete is poured, it should be covered and maintained in time according to the on-site temperature conditions, and a heater should be used for 24-hour heat preservation maintenance, and the maintenance time should be no less than 14 days. The maintenance can be removed when the outer wall of the pool is backfilled. Under the premise of meeting the critical antifreeze strength before cooling, lowering the concrete mold temperature can reduce the setting temperature, reduce the temperature difference, and reduce the temperature difference stress, thereby preventing the occurrence of temperature difference cracks.
[0081] Formwork removal: The pool wall formwork should be removed when the temperature difference between the concrete surface temperature and the ambient air temperature is small, and the temperature difference should be ≤15℃. After the formwork is removed, cover it with insulating water immediately to prevent shrinkage cracks during the formwork removal process.
[0082] G. Test the waters
[0083] After the maintenance is completed, the sedimentation tank is tested. Fill each sedimentation tank with water in the designed process sequence; fill the water three times, i.e. 1 / 3, 1 / 3, and 1 / 3. After each 1 / 3 of water is filled, pause for 3-8 hours to check the liquid level changes and the leakage and pressure resistance of the sedimentation tank. Design a double-sided water-level partition wall that is not subjected to force, and fill the water on both sides at the same time. The sedimentation tank that has been tested for water filling can be filled to full load at one time. And according to the design water level elevation requirements, check whether the waterway is unobstructed to ensure the self-flow and safety surpassing function of the full water volume after normal operation to prevent water bubbling and water leakage.
[0084] H. Sedimentation tank desilting
[0085] Every other day, the silt in the sedimentation tank is removed by an excavator, and the excavated silt is loaded into a slag truck and transported to the slag dump for disposal.
[0086] The present invention has good sedimentation and filtration effects, and a multi-stage filtration and sedimentation system is set up to meet the requirements of reuse, with significant water-saving effects and low pollution control costs. By setting up a four-stage sedimentation tank for sewage treatment at the entrance of the cave, the turbidity and amount of sewage outside the cave are reduced, thereby reducing the operating costs of the sewage treatment station.
[0087] Temporary drainage ditches are set up for construction drainage, and the central ditch is not used as the construction drainage channel to prevent silt accumulation from reducing the effective drainage section of the central drainage ditch and affecting the normal use of the central drainage ditch during operation.
[0088] Example 3
[0089] A construction method for tunnel slope drainage, comprising the following construction steps:
[0090] 1) Set up a sump on the face and arrange the first-level pumping station there;
[0091] 2) Set up a sump at the end of the invert and arrange the second-stage pumping station there;
[0092] 3) Set up a four-stage sedimentation tank for sewage sedimentation and discharge; set up a third-stage pump station in the four-stage sedimentation tank;
[0093] 4) Set up a central ditch and its sump for clear water discharge; a third-level pumping station is also set up on the central ditch;
[0094] 5) The water in the water collection pit at the face is pumped to the first-stage sedimentation tank in the four-stage sedimentation tank by the first-stage pump station;
[0095] 6) The clean water in the sump at the end of the invert is discharged through the second-stage pump station, and the clean water in the central ditch is discharged through the third-stage pump station;
[0096] 7) The sewage in the sump at the end of the invert is pumped to the first sedimentation tank in the four-stage sedimentation tank through the second-stage pumping station.
[0097] 8) The sewage pumped into the first-stage sedimentation tank is continuously precipitated step by step in the four-stage sedimentation tank and discharged after reaching the standards.
[0098] The tunnel adopts bidirectional excavation, and a longitudinal slope of 2.83% is set from the entrance to the exit of the tunnel. The tunnel exit construction adopts reverse slope drainage, that is, the construction direction in the tunnel is downhill.
[0099] The first-stage pumping station includes two 30kw mobile submersible pumps, which pump sewage to the first-stage sedimentation tank among the four-stage sedimentation tanks; the second-stage pumping station includes two 30kw submersible pumps, in the step 6), one of the 30kw submersible pumps delivers the clean water in the sump at the end of the invert to the mobile clean water tank for discharge, and in the step 7), the other 30kw submersible pump pumps the remaining sewage after sedimentation in the sump at the end of the invert to the first-stage sedimentation tank among the four-stage sedimentation tanks for further sedimentation.
[0100] In the step 3), four-stage sedimentation tanks are set up in the widened section to treat the sewage.
[0101] In the step 3), the first-stage sedimentation tank is set to a size of 6m×12m×2.39m×1.47m, the second-stage sedimentation tank is set to a size of 6m×12m×2.39m×1.47m, the third-stage sedimentation tank is set to a size of 6m×9m×2.39m×1.47m, and the fourth-stage sedimentation tank is set to a size of 6m×12m×2.39m×1.47m; the wall thickness of each level of sedimentation tank is 30cm and is poured with C20 concrete.
[0102] In the step 4), a concrete fixed plug is set every 400m in the central ditch, and the third-level pump station set on the central ditch includes a 30kw mobile submersible pump, which pumps the clean water returned from the central ditch into a mobile clean water tank, and then sends the clean water to the outside of the cave for unified discharge through the booster pump station.
[0103] In order to reduce the interference to the construction in the tunnel, the excavation width of the water collection pit on the heading face should be reduced, and its setting dimensions are 3m×2m×1m; the setting dimensions of the water collection pit at the end of the invert arch are 5m×3m×2m; the setting dimensions of the mobile clean water tank are 3m×2m×1.5m; in order to reduce the damage of mud and impurities in the tunnel to the water pump and drainage pipeline, the mobile clean water tank is set into two compartments, and a filter baffle is set in the middle, which can also play a role in enhancing the rigidity of the water tank.
[0104] The third-level pumping station is set in the four-level sedimentation tank, including two 30kw submersible pumps. In the step 8), the sewage treated by continuous step-by-step sedimentation is pumped into a mobile sewage tank. A 55kw submersible pump is set in the mobile sewage tank to send the sewage to the sewage treatment equipment outside the cave for final treatment, and then discharged after the sewage meets the standards.
[0105] The sewage treatment equipment includes: 10 integrated high-efficiency sedimentation tanks, 6.5m high and 3.0m in diameter; 2 sedimentation tanks, with dimensions of 10m×3m×3m; a dosing room, with dimensions of 8m×3m×2mm; a clear water tank and a sludge tank, both with dimensions of 6m×3m×3m.
[0106] The face is connected to the mobile sewage tank via a hose, and the mobile clean water tank or mobile sewage tank is connected to the outside of the tunnel via an iron pipe.
[0107] In addition, in order to further improve the technical effect of the present invention, in this embodiment, in order to prevent the risk of sudden water and mud in the tunnel during the tunnel backslope drainage construction process, the following construction method is also adopted:
[0108] 1. Carry out advanced geological prediction and forecast and surrounding rock monitoring and measurement to keep abreast of the geological conditions of the face and ensure standardized operations according to operating procedures.
[0109] 2. Before the designed mud and water burst section is constructed, a pneumatic drill is used to drill a deeper blast hole on the face of the tunnel, which is 2-3 meters longer than the general blast hole, to detect whether there is water bursting out in front. If there is no water bursting out, the normal construction method is used.
[0110] 3. If sudden mud and water gushing is detected ahead, grouting or curtain grouting shall be carried out on the face of the heading.
[0111] 4. After the grouting or curtain grouting is completed, carry out short excavation with weak blasting, excavate a distance of steel frame and promptly erect steel frame anchor spraying support.
[0112] 5. After the excavation and support reaches 12 meters, the invert concrete should be applied in time.
[0113] 6. After the excavation and support reaches 24 meters, and the invert concrete is applied for 12 meters, the second lining of the arch wall should be applied in time.
[0114] 7. Repeat the construction process in this way until you have passed the mud and water surge section.
[0115] It can be seen from the above embodiments that the present invention is suitable for pollution control and drainage in long-distance tunnels, and can solve the problem of groundwater discharge in tunnels; it has a simple structure, low investment, convenient operation and maintenance, occupies a small space, does not affect the dynamic transportation of tunnel debris, and has a significant water-saving effect and low pollution control cost.
[0116] In order to prevent the mixing of clean and dirty water in tunnel drainage, which leads to increased pressure on sewage treatment, the present invention separates clean and dirty water for drainage, reduces the generation of tunnel construction wastewater from the construction source, and reduces the impact on the water environment around the construction.
[0117] The invention can be applied to sewage treatment and drainage in tunnels with high burial depth and long distance; the sewage drainage capacity of the tunnel should reach 9500m 3 / d, that is, the drainage capacity per hour is 395m 3 ; The clean water drainage capacity of the central ditch should reach 4000m 3 / d, that is, the drainage capacity per hour is 166.7m 3 The construction progress of the tunnel reverse slope drainage closely follows the tunnel face, which can solve the drainage problem of long-distance tunnels.
[0118] The present invention sets sump at the tunnel face and the end of the invert to ensure that sewage at the tunnel face and the invert does not overflow, thereby ensuring that the construction process proceeds smoothly. The present invention has the advantages of less manpower, high environmental protection, good soil and water conservation effect, low construction cost, high construction efficiency, low construction risk and strong popularization and applicability in tunnel construction.
[0119] The above is only a preferred embodiment of the present invention, and does not limit the present invention in other forms. Any technician familiar with the profession may use the above disclosed technical content to change or modify it into an equivalent embodiment with equivalent changes. However, any simple modification, equivalent change and modification made to the above embodiment according to the technical essence of the present invention without departing from the technical solution of the present invention still belongs to the protection scope of the technical solution of the present invention.
Claims
1. A construction method for tunnel slope drainage, characterized in that: The construction steps include: 1) Set up a sump on the face and arrange the first-level pumping station there; 2) Set up a sump at the end of the invert and arrange the second-stage pumping station there; 3) Set up a four-stage sedimentation tank for sewage sedimentation and discharge; set up a third-stage pump station in the four-stage sedimentation tank; 4) Set up a central ditch and its sump for clear water discharge; a third-level pumping station is also set up on the central ditch; 5) The water in the water collection pit at the face is pumped to the first-stage sedimentation tank in the four-stage sedimentation tank by the first-stage pump station; 6) The clean water in the sump at the end of the invert is discharged through the second-stage pump station, and the clean water in the central ditch is discharged through the third-stage pump station; 7) The sewage in the sump at the end of the invert is pumped to the first sedimentation tank in the four-stage sedimentation tank through the second-stage pump station; 8) The sewage pumped into the first-stage sedimentation tank is continuously precipitated step by step in the four-stage sedimentation tank and discharged after reaching the standards.
2. The construction method for tunnel slope drainage according to claim 1, characterized in that: The tunnel adopts bidirectional excavation, and a longitudinal slope of 2.83% is set from the entrance to the exit of the tunnel. The tunnel exit construction adopts reverse slope drainage, that is, the construction direction in the tunnel is downhill.
3. The construction method for tunnel slope drainage according to claim 1 or 2, characterized in that: The first-stage pumping station includes two 30kw mobile submersible pumps, which pump sewage to the first-stage sedimentation tank among the four-stage sedimentation tanks; the second-stage pumping station includes two 30kw submersible pumps, in the step 6), one of the 30kw submersible pumps delivers the clean water in the sump at the end of the invert to the mobile clean water tank for discharge, and in the step 7), the other 30kw submersible pump pumps the remaining sewage after sedimentation in the sump at the end of the invert to the first-stage sedimentation tank among the four-stage sedimentation tanks for further sedimentation.
4. The construction method for tunnel slope drainage according to claim 3, characterized in that: In the step 3), four-stage sedimentation tanks are set up in the widened section to treat the sewage.
5. The construction method for tunnel slope drainage according to claim 4, characterized in that: In the step 3), the first-stage sedimentation tank is set to a size of 6m×12m×2.39m×1.47m, the second-stage sedimentation tank is set to a size of 6m×12m×2.39m×1.47m, the third-stage sedimentation tank is set to a size of 6m×9m×2.39m×1.47m, and the fourth-stage sedimentation tank is set to a size of 6m×12m×2.39m×1.47m; the wall thickness of each level of sedimentation tank is 30cm and is poured with C20 concrete.
6. The construction method for tunnel slope drainage according to claim 4 or 5, characterized in that: In the step 4), a concrete fixed plug is set every 400m in the central ditch, and the third-level pump station set on the central ditch includes a 30kw mobile submersible pump, which pumps the clean water returned from the central ditch into a mobile clean water tank, and then sends the clean water to the outside of the cave for unified discharge through the booster pump station.
7. The construction method for tunnel slope drainage according to claim 6, characterized in that: The dimensions of the sump at the face are 3m×2m×1m; the dimensions of the sump at the end of the invert are 5m×3m×2m; the dimensions of the mobile clean water tank are 3m×2m×1.5m; the mobile clean water tank is divided into two compartments, with a filter baffle in the middle.
8. The construction method for tunnel slope drainage according to claim 7, characterized in that: The third-level pumping station is set in the four-level sedimentation tank, including two 30kw submersible pumps. In the step 8), the sewage treated by continuous step-by-step sedimentation is pumped into a mobile sewage tank. A 55kw submersible pump is set in the mobile sewage tank to send the sewage to the sewage treatment equipment outside the cave for final treatment, and then discharged after the sewage meets the standards.
9. The construction method for tunnel slope drainage according to claim 8, characterized in that: The sewage treatment equipment includes: 10 integrated high-efficiency sedimentation tanks, 6.5m high and 3.0m in diameter; 2 sedimentation tanks, with dimensions of 10m×3m×3m; a dosing room, with dimensions of 8m×3m×2mm; a clear water tank and a sludge tank, both with dimensions of 6m×3m×3m.
10. The construction method for tunnel slope drainage according to claim 8 or 9, characterized in that: The face is connected to the mobile sewage tank via a hose, and the mobile clean water tank or mobile sewage tank is connected to the outside of the tunnel via an iron pipe.
Citation Information
Cited By
Ecological recycling system and method for tunnel gushing wastewater
CN121342240A
Submarine tunnel long-distance reverse slope drainage method
CN121452018A
Long-distance reverse slope drainage method for undersea tunnels
CN121452018B
Three-dimensional detection method for hidden defects of tunnel surrounding rock based on double-section deep neural network
CN122798801A