Intelligent monitoring system for ballastless track-bridge structure system

Through the intelligent monitoring system, a variety of sensing equipment and database technologies are used to achieve all-round real-time monitoring of ballastless track-bridge structures, solving the problems of slow inspection speed and untimely monitoring, and improving monitoring accuracy and cost-effectiveness , ensuring the safe operation of the structure.

CN118913346AInactive Publication Date: 2024-11-08CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD +1

Patent Information

Application Number
CN202410846520.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-27
Publication Date
2024-11-08
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Traditional manual inspections are difficult to detect damage to the ballless track-bridge structure in a timely manner, resulting in untimely repair and high cost, and the single sensor monitoring is not comprehensive enough, resulting in untimely detection of damage.

Method used

An intelligent monitoring system for ballless track-bridge structure system was designed, including monitoring equipment layout module, monitoring data acquisition module and bridge monitoring module, using sensor monitoring equipment, internal hidden danger monitoring equipment and vehicle-rail-bridge system spatial positioning test Equipment, collects data from multiple aspects in real time, and establishes monitoring databases for early warning and maintenance.

Benefits of technology

It improves the accuracy of data acquisition and monitoring accuracy, saves labor costs, and realizes intelligent monitoring of ballastless track-bridge structures throughout the whole period and region, ensuring the normal operation and service life of the structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118913346A_ABST
    Figure CN118913346A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of ballastless track-bridge safety operation monitoring, in particular to an intelligent monitoring system for a ballastless track-bridge structure system. The system comprises a monitoring equipment arrangement module, a monitoring data acquisition module and a bridge monitoring module, the monitoring equipment arrangement module is used for arranging monitoring equipment on the ballastless track-bridge, and the monitoring equipment comprises sensor monitoring equipment, internal hidden danger monitoring equipment and vehicle-track-bridge system space configuration testing equipment; the monitoring data acquisition module is used for acquiring monitoring data by using monitoring equipment and establishing a monitoring database; and the bridge monitoring module is used for monitoring the ballastless track-bridge structure system according to the monitoring database and carrying out early warning and maintenance. According to the invention, the ballastless track-bridge structure system can be monitored comprehensively, so that the operation safety is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of ballastless track-bridge safe operation monitoring, and in particular to an intelligent monitoring system for a ballastless track-bridge structure system. Background Art

[0002] Rail transit projects are developing rapidly, especially in the fields of high-speed railways, heavy-load railways, urban subways and light rails. The track-bridge structure is an important part of the healthy operation of the track. The track-bridge structure is subjected to high-frequency and repeated train loads and external environmental alternations during service. The track-bridge structure system will have different degrees of diseases, including track plate cracking, concrete bridge cracking, etc. These diseases will not only damage the track-bridge structure system, but more seriously affect its operational safety. Therefore, it is necessary to conduct full-time and full-area intelligent monitoring of the damage behavior of the ballastless track-bridge structure system throughout its life cycle to avoid missing the best time for maintenance and repair of the structure system, or even causing serious consequences such as the collapse of the structure system.

[0003] Traditionally, the monitoring of ballastless track-bridge structure systems is carried out through regular manual inspections. However, the monitoring and diagnosis of track-bridge structure system defects through manual inspections has the problems of slow diagnosis and treatment speed and serious deterioration of defects. In addition, periodic inspections cannot detect damage to ballastless track-bridges in time, which will lead to untimely repairs, high labor costs and strong subjectivity. With the development of the Internet of Things, a single sensor is used for monitoring, and the monitoring indicators are single and not comprehensive, resulting in inadequate monitoring, which leads to some damage not being discovered or being discovered untimely. Summary of the invention

[0004] In order to solve the above technical problems, the purpose of the present invention is to provide an intelligent monitoring system for ballastless track-bridge structure system, and the technical solutions adopted are as follows:

[0005] An embodiment of the present invention provides an intelligent monitoring system for a ballastless track-bridge structure system, the system comprising: a monitoring equipment arrangement module, a monitoring data acquisition module and a bridge monitoring module;

[0006] A monitoring equipment arrangement module, used to arrange monitoring equipment on the ballastless track-bridge, wherein the monitoring equipment includes sensor monitoring equipment, internal hidden danger monitoring equipment and vehicle-track-bridge system spatial configuration testing equipment;

[0007] A monitoring data collection module is used to collect monitoring data using monitoring equipment and establish a monitoring database;

[0008] The bridge monitoring module is used to monitor the ballastless track-bridge structure system according to the monitoring database and to carry out early warning and maintenance.

[0009] Preferably, the sensor monitoring equipment is used for bridge vibration response monitoring, beam dynamic deflection monitoring, support displacement monitoring, track structure vibration monitoring, track structure displacement monitoring, beam strain monitoring, beam joint displacement monitoring, beam end inclination monitoring, wheel-rail force monitoring, wind speed and direction monitoring, temperature and humidity monitoring, and train running speed monitoring.

[0010] Preferably, the internal hidden danger monitoring equipment is an ultrasonic continuous detection equipment for hidden diseases under the track slab, which uses ultrasonic waves for continuous detection to obtain data on hidden diseases inside the ballastless track structure; when monitoring, measuring lines are laid out on the track slab along the line direction, located in the center and on both sides of the track support platform respectively, the main machine and the programmable motor are placed at the tail of the track slab, and the receiving transducer is placed at the head of the track slab.

[0011] Preferably, the vehicle-track-bridge system spatial configuration test device comprises a parallel light visual measurement unit, a light source unit, a device fixing unit, an industrial control unit and a target unit;

[0012] The parallel light vision measurement unit is used to measure the vertical vibration displacement of the high-speed railway box girder, the vertical high-frequency vibration displacement of the track and the vertical relative displacement between the multi-layer structures of the track; the light source unit adopts a near-infrared light source, which is invisible light; the fixing unit adopts a snap-on fixing structure to fix the parallel light vision measurement unit; the industrial control unit is used for camera control and data acquisition and transmission, and has a built-in network communication module; the target unit is used to set and fix the track plate target and track target.

[0013] Preferably, the collecting monitoring data using monitoring equipment includes:

[0014] Real-time data collection is carried out for the arranged monitoring equipment according to the corresponding collection system and sampling frequency, and the time series data of different monitoring items are kept synchronized. The continuously recorded monitoring data are saved in hours and saved in binary compressed file format.

[0015] Preferably, the establishing of a monitoring database comprises:

[0016] The monitoring database includes the original database, pre-processing database, analysis database, real-time query database and error information database;

[0017] The data in the original database are the original monitoring data collected; the data in the preprocessing database are the data after preprocessing the original data collected, and the preprocessing operation is to reduce the noise of the data and eliminate abnormal monitoring data; the data in the analysis database are obtained by analyzing the data in the preprocessing database; the data in the real-time query database are used for real-time query by the staff; the data in the error information database are the error information data in the process of monitoring equipment collecting monitoring data and the original monitoring data with errors.

[0018] Preferably, the monitoring data acquisition module is also used to collect offline monitoring data. The acquisition of offline monitoring data includes: establishing an on-site corrosion environment exposure test site at the monitored ballastless track-bridge, taking samples every six months to conduct structural system durability degradation tests, and acquiring offline monitoring data; the offline monitoring data is also included in the monitoring database.

[0019] Preferably, the bridge monitoring module includes an early warning submodule; the early warning submodule includes a single monitoring device early warning and a multi-monitoring device fusion early warning; the single monitoring device early warning is to set an early warning threshold for a single monitoring device, and to issue an early warning based on the comparison of the monitoring data collected by the monitoring device with the early warning threshold; the multi-monitoring device early warning weight setting includes setting the weight of each monitoring device for fusion early warning.

[0020] Preferably, the bridge monitoring module includes a maintenance submodule; the maintenance submodule includes formulating daily inspection tasks and formulating early warning inspection tasks; daily inspection tasks are periodic line inspection tasks, which set inspection cycles and inspection routes, form daily inspection task packages, and send them to inspection personnel, who conduct inspections along the inspection routes;

[0021] Formulate early warning inspection tasks. When an early warning occurs, locate the location where the early warning occurs, form an early warning inspection task package, and send it to the inspection personnel, who will conduct the inspection.

[0022] The embodiments of the present invention have at least the following beneficial effects: the present invention arranges monitoring equipment, wherein the arranged monitoring equipment includes sensor monitoring equipment, internal hidden danger monitoring equipment and vehicle-track-bridge system space configuration test equipment, monitors the ballastless track-bridge structure system from various aspects, can not only monitor its internal hidden dangers, but also use the vehicle-track-bridge system space configuration test equipment to monitor and collect data on the vehicle-track-bridge system space configuration, can improve the accuracy of data collection and the accuracy of monitoring, can save manpower, and improve the objectivity of monitoring; a monitoring data acquisition module is used to use the monitoring equipment to collect monitoring data and establish a monitoring database to facilitate the storage of monitoring data and subsequent monitoring of the ballastless track-bridge structure system; the ballastless track-bridge structure system is monitored according to the monitoring database, and early warning and maintenance are carried out, and the monitoring data is used to replace the traditional manual inspection method, save labor costs, and improve the accuracy of monitoring. At the same time, maintenance is carried out according to the monitoring results, which can ensure the normal operation of the ballastless track-bridge structure system and increase its service life. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the technical solutions and advantages in the embodiments of the present invention or the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0024] Figure 1 A system block diagram of an intelligent monitoring system for a ballastless track-bridge structure system provided by an embodiment of the present invention;

[0025] Figure 2 A schematic diagram of the operation principle of an internal hidden danger monitoring device of a ballastless track-bridge structure system intelligent monitoring system provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0026] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined invention purpose, the specific implementation method, structure, features and effects of the intelligent monitoring system for ballastless track-bridge structure system proposed by the present invention are described in detail below in combination with the accompanying drawings and preferred embodiments. In the following description, different "one embodiment" or "another embodiment" does not necessarily refer to the same embodiment. In addition, specific features, structures, or characteristics in one or more embodiments may be combined in any suitable form.

[0027] Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs.

[0028] The specific scheme of the intelligent monitoring system for ballastless track-bridge structure system provided by the present invention is described in detail below with reference to the accompanying drawings.

[0029] Example:

[0030] The main application scenarios of the present invention are: the present invention sets sensors to collect data from each sensor, analyzes and combines the collected data, monitors the ballastless track-bridge structure system according to the measured data and the analyzed and combined data, performs timely maintenance and care for damage to the ballastless track-bridge structure, and ensures the operational safety of the ballastless track-bridge structure system.

[0031] See also Figure 1 , which shows a system block diagram of an intelligent monitoring system for a ballastless track-bridge structure system provided by an embodiment of the present invention, the system includes a monitoring equipment layout module, a monitoring data acquisition module and a bridge monitoring module.

[0032] Specifically,

[0033] The monitoring equipment arrangement module is used to arrange monitoring equipment on the ballastless track-bridge, wherein the monitoring equipment includes sensor monitoring equipment, internal hidden danger monitoring equipment and vehicle-track-bridge system spatial configuration testing equipment.

[0034] When conducting ballastless track-bridge monitoring, it is necessary to collect data from multiple aspects to make the collected data more comprehensive. The main contents of monitoring include structural response monitoring, long-term monitoring, special part monitoring, and environment and load monitoring.

[0035] Among them, structural response monitoring mainly includes track structure vibration, track structure displacement, vertical dynamic deflection and impact coefficient of bridge span, vertical / lateral amplitude (mid-span and support), vertical / lateral acceleration, lateral amplitude of pier top and abutment top, lateral and longitudinal displacement of bearing, vertical compression of bearing, etc. Long-term monitoring mainly includes designer fatigue performance and long-term deformation performance. The main performance involved includes material strength of structural components, apparent quality of structural system, surface looseness and peeling, corner and block falling phenomenon; crack distribution and direction, crack width and depth, separation distribution and direction and separation width and depth; bearing damage and rust status. Special parts monitoring includes wheel-rail force, beam joint displacement, beam end rotation angle. Environmental and load monitoring, including temperature, humidity, wind direction, wind speed and train speed.

[0036] Among them, the monitoring equipment during the monitoring process is mainly divided into sensor monitoring equipment, internal hidden danger monitoring equipment, vehicle-track-bridge system spatial configuration testing equipment and video monitoring equipment.

[0037] Sensor monitoring equipment is mainly used for bridge vibration response monitoring, beam dynamic deflection monitoring, support displacement monitoring, track structure vibration monitoring, track structure displacement monitoring, beam strain monitoring, beam joint displacement monitoring, beam end inclination monitoring, wheel-rail force monitoring, wind speed and direction monitoring, temperature and humidity monitoring, and train speed monitoring.

[0038] The bridge vibration response monitoring uses two acceleration sensors and three amplitude sensors to measure the vertical and lateral vibration acceleration of the bridge beam, the vertical and lateral amplitude of the bridge beam, and the lateral amplitude of the pier top. The amplitude test of the bridge structure uses a velocity sensor to integrate the displacement, and the acceleration test uses an acceleration sensor, and the vibration value triggers the collection of vibration response data when the train passes by; the acceleration sensor corresponding to the vertical and lateral vibration acceleration of the beam is installed and arranged in the middle of the span, and the amplitude sensor corresponding to the vertical and lateral amplitude of the beam is arranged in the middle of the span; the amplitude sensor corresponding to the lateral amplitude of the pier top is arranged at the center of the cross section of the pier top. The sensor used for the dynamic deflection monitoring of the beam is a displacement meter, which is arranged in the middle of the span of the beam.

[0039] The sensor used for bearing displacement monitoring is a displacement meter, which can monitor multi-directional displacement according to the type of movable bearing. Preferably, in an embodiment of the present invention, the lateral, longitudinal and vertical displacements of the bearing are monitored, that is, the relative displacement between the upper and lower swings of the bearing is monitored, and the displacement meter is arranged at the center line of the bearing.

[0040] Track structure vibration monitoring is carried out with two transition section track plate vibration acceleration sensors and one track plate three-dimensional acceleration sensor. The transition section track plate vibration acceleration sensor is arranged on the side of the disconnection point between the two track plates in the transition section, and the track plate vibration acceleration sensor is arranged on the side of the track plate; in the study of vehicle-bridge coupling relationship, track plate vibration and bridge transition section vibration are important evaluation indicators.

[0041] Track structure displacement monitoring requires the deployment of transverse and vertical displacement sensors on the side of the track plate in the middle of the simply supported beam section, and the deployment of vertical displacement sensors on the two track plates disconnected between the abutment and the roadbed in the transition section to monitor the vertical and transverse displacement of the track installed in the simply supported beam section, and to perform displacement monitoring on the vibration between the two track plates in the roadbed transition section.

[0042] For beam strain monitoring, the bridge method is used for testing, and a total of two arched surface strain sensors are used. When the concrete on the top surface of the box beam bottom plate is uneven or there is a large amount of slurry, which has a great influence on the strain test results, the installation surface should be polished before installation. In the test section of the box beam, the sensor is arranged on the bottom surface of the bottom plate of the center line of the box beam cross section.

[0043] Monitoring of special parts, namely beam joint displacement monitoring, beam end inclination monitoring and wheel-rail force monitoring; for beam joint displacement monitoring, a total of 2 sensors are arranged, usually contact displacement sensors, and the sensor beam ends are arranged at the ends of the two beams respectively; for beam end inclination monitoring, a total of 2 sensors are arranged, the monitoring beam ends are perpendicular to the bridge axis direction, and are arranged on the top surface of the box girder bottom plate at the center of the test cross section; the sensor used for wheel-rail force monitoring is a special collector for wheel-rail force monitoring, which is arranged on two rails at the same time, and the vertical force strain gauge is pasted on the neutral axis on both sides of the rail in the left-right symmetrical section of the center line between adjacent rail supports, with a spacing b of 160-240mm, and the direction of the strain gauge is at a 45° angle to the longitudinal direction of the rail, and the transverse force strain gauge is pasted on the upper surface of the rail bottom 20mm away from the rail bottom edge in the left-right symmetrical section of the center line between adjacent rail supports, with a spacing b of 160-240mm, and the direction of the strain gauge is at a 45° angle to the longitudinal direction of the rail, and the derailment coefficient needs to be analyzed, so the transverse force and vertical force strain gauges are arranged on the same section.

[0044] Wind speed and direction monitoring uses ultrasonic wind speed and direction sensors, which are arranged on the main span bridge deck, in an unobstructed position in all directions, with a total of 1 measuring point, to monitor wind speed and direction. The temperature and humidity monitoring sensor uses a temperature and humidity transmitter, which is arranged on the side of the bridge deck beam in the middle of the span. The train speed monitoring sensor uses an ultrasonic speed radar, which is arranged on the pole of the road-bridge transition section.

[0045] Internal hidden danger monitoring equipment is an ultrasonic continuous detection device for hidden defects under the track slab. It uses ultrasonic waves for continuous detection to obtain data on hidden defects inside the ballastless track structure. It mainly uses non-destructive monitoring methods to find out the hidden defects inside the ballastless track structure. It can promptly identify the causes of defects and damage and eliminate the safety hazards of the ballastless track structure. The equipment is equipped with a programmable motor to realize mechanized continuous automatic collection. The equipment is designed for two-channel collection. In actual detection, both the ultrasonic transmitting and receiving transducers are placed on the track slab surface and the effective offset distance is maintained. The detection work is carried out by adding water coupling. The working principle diagram is as follows: Figure 2 As shown in the figure, 1 represents the emission of ultrasonic signals, and 2 represents the reception of reflected signals. The motor moves with the ultrasonic transmitting and receiving transducers to continuously monitor the hidden diseases under the track slab. It should be noted that when monitoring, 4 measuring lines are arranged on the track slab along the line direction, which are located in the center and both sides of the track support platform respectively. The main machine and the programmable motor are placed at the tail of the track slab, and the transducer is placed at the head of the track slab. The maximum efficiency of the equipment is 1-2 linear meters per minute, and it requires 2 manual workers to cooperate.

[0046] The vehicle-track-bridge system spatial configuration test equipment is used to monitor the vertical vibration displacement of the high-speed railway box girder, the vertical high-frequency vibration displacement of the track, and the vertical relative displacement between the multi-layer structures of the track. It includes a parallel light visual measurement unit, a light source unit, an equipment fixing unit, an industrial control unit, and a target unit. Among them, the parallel light visual measurement unit on the bridge is fixedly installed on the protective wall next to the track structure by drilling holes in the base. The parallel light visual measurement unit under the bridge is fixed to the top of the pier and the bottom of the box girder together with the industrial control computer and related instruments. The visual measurement unit is 1 meter away from the track plate target and the track target in the target unit.

[0047] The parallel light vision measurement unit is used to measure the vertical vibration displacement of the high-speed railway box girder, the vertical high-frequency vibration displacement of the track, and the vertical relative displacement between the multi-layer structures of the track; the light source unit adopts a near-infrared light source, which is invisible light; the fixing unit adopts a snap-on fixing structure to fix the parallel light vision measurement unit; the industrial control unit is used for camera control and data acquisition and transmission, and has a built-in 4G network communication module; the target unit is used to set and fix the track plate target and track target.

[0048] At this point, sensor monitoring equipment, internal hidden danger monitoring equipment and vehicle-track-bridge system spatial configuration testing equipment have been arranged to monitor the ballastless track-bridge structure system.

[0049] The monitoring data collection module is used to collect monitoring data using monitoring equipment and establish a monitoring database.

[0050] In the monitoring equipment layout module, sensor monitoring equipment, internal hidden danger monitoring equipment and vehicle-track-bridge system spatial configuration test equipment are arranged to collect data; the monitoring data acquisition module is compatible with various automated monitoring equipment protocols and communication methods, and can quickly access monitoring data through front-end configuration; it realizes unified management of sensors and acquisition equipment installed on all project sites, centralized data collection and control.

[0051] Specifically, real-time data collection is carried out on the arranged monitoring equipment according to the corresponding collection system and sampling frequency, and the time series data of different monitoring items are kept synchronized. The continuously recorded monitoring data are saved in hours in binary compressed file format.

[0052] A monitoring database is constructed based on the monitoring data collected by sensor monitoring equipment, internal hidden danger monitoring equipment and vehicle-track-bridge system spatial configuration test equipment, wherein the monitoring database includes an original database, a preprocessing database, an analysis database, a real-time query database and an error information database; the data in the original database are the original monitoring data collected; the data in the preprocessing database are the data after preprocessing the collected original data, and the preprocessing operation is to perform noise reduction on the data and eliminate abnormal monitoring data; the data in the analysis database are the data obtained by analyzing the data in the preprocessing database; the data in the real-time query database are used for real-time queries by staff; the data in the error information database are the error information data in the process of monitoring equipment collecting monitoring data and the original monitoring data with errors.

[0053] The monitoring data acquisition module is also used to collect offline monitoring data, which is indirectly acquired monitoring data. The acquisition of offline monitoring data includes establishing an on-site corrosion environment exposure test site at the monitored ballastless track-bridge, taking samples every six months to conduct structural system durability degradation tests, and acquiring offline monitoring data. Offline monitoring data is also included in the monitoring database.

[0054] The bridge monitoring module is used to monitor the ballastless track-bridge structure system according to the monitoring database and to carry out early warning and maintenance.

[0055] After collecting the monitoring data, a monitoring database was established, and the data in the monitoring database was used for further feature analysis. The main characteristic values ​​include the maximum, minimum, average, median, root mean square, frequency, etc. of each data; when monitoring, the monitoring data collected by various sensor monitoring equipment, internal hidden danger monitoring equipment and vehicle-track-bridge system spatial configuration test equipment are available for staff to query, and the data can be queried in units of 1 minute, 10 minutes, hours, and days.

[0056] The bridge monitoring module also includes an early warning submodule and a maintenance submodule. The early warning submodule is used for early warning, and the maintenance submodule is used for the maintenance of the ballastless track-bridge structure system; the early warning submodule includes a single monitoring device early warning and a multi-monitoring device fusion early warning, where the single monitoring device early warning and the multi-monitoring device fusion early warning are also single indicator early warning and multi-indicator fusion early warning. The multi-monitoring device fusion early warning requires the setting of the warning weight of multiple monitoring devices. The monitoring data is analyzed in real time to obtain the key characteristic information (various indicators) of the infrastructure of each part of the ballastless track-bridge, and compared with the threshold. The single monitoring device early warning is the basis and key to the fusion alarm analysis of multiple monitoring devices.

[0057] Among them, the single monitoring device warning is to set the warning threshold of a single monitoring device, and to issue a warning based on the comparison of the monitoring data collected by the monitoring device with the warning threshold. The warning weight setting of multiple monitoring devices includes setting the weight of each monitoring device and performing fusion warning. The weight setting needs to be set according to the actual situation. When the fusion alarm is issued, it is necessary to perform a fusion alarm based on the correlation between the content monitored by each monitoring device. The number of monitoring devices for fusion alarm is set to a preset number. It can be fused by two monitoring devices, or three or four monitoring devices. The value of the preset number is determined by the staff based on the correlation between the monitoring devices, and the combination scheme of the fusion alarm needs to be set manually. At the same time, the threshold of the fusion alarm of multiple monitoring devices is set.

[0058] The maintenance submodule includes formulating daily inspection tasks and formulating early warning inspection tasks; daily inspection tasks are periodic line inspection tasks, which set inspection cycles and inspection routes to form daily inspection task packages, which are sent to inspection personnel. Inspection personnel conduct inspections along the inspection routes, record the disease data that occurs and upload them. Technical personnel analyze the disease data and give maintenance opinions or suggestions. Maintenance orders are generated for diseases that need to be repaired and sent to maintenance personnel, who simultaneously record and upload the repair progress.

[0059] Formulate early warning inspection tasks. When an early warning occurs, locate the location where the early warning occurs, form an early warning inspection task package, and send it to the inspection personnel. The inspection personnel will conduct inspections, record and upload the disease data in real time, and the technical personnel will analyze the disease data and give repair opinions or suggestions. For diseases that need to be repaired, maintenance orders will be generated and sent to the maintenance personnel, who will also record and upload the repair progress simultaneously.

[0060] It should be noted that the sequence of the above embodiments of the present invention is only for description and does not represent the advantages and disadvantages of the embodiments. The above is a description of a specific embodiment of this specification. In addition, the processes depicted in the accompanying drawings do not necessarily require the specific order or continuous order shown to achieve the desired results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.

[0061] The various embodiments in this specification are described in a progressive manner, and the same or similar parts between the various embodiments can be referenced to each other, and each embodiment focuses on the differences from other embodiments.

[0062] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. An intelligent monitoring system for ballastless track-bridge structure system, characterized in that: The system includes: a monitoring equipment arrangement module, a monitoring data acquisition module and a bridge monitoring module; A monitoring equipment arrangement module, used to arrange monitoring equipment on the ballastless track-bridge, wherein the monitoring equipment includes sensor monitoring equipment, internal hidden danger monitoring equipment and vehicle-track-bridge system spatial configuration testing equipment; A monitoring data collection module is used to collect monitoring data using monitoring equipment and establish a monitoring database; The bridge monitoring module is used to monitor the ballastless track-bridge structure system according to the monitoring database and to carry out early warning and maintenance.

2. The intelligent monitoring system for ballastless track-bridge structure system according to claim 1 is characterized in that: The sensor monitoring equipment is used for bridge vibration response monitoring, beam dynamic deflection monitoring, support displacement monitoring, track structure vibration monitoring, track structure displacement monitoring, beam strain monitoring, beam joint displacement monitoring, beam end inclination monitoring, wheel-rail force monitoring, wind speed and direction monitoring, temperature and humidity monitoring, and train running speed monitoring.

3. The intelligent monitoring system for ballastless track-bridge structure system according to claim 1 is characterized in that: The internal hidden danger monitoring equipment is an ultrasonic continuous detection equipment for hidden diseases under the track slab, which uses ultrasonic waves for continuous detection to obtain data on hidden diseases inside the ballastless track structure. When monitoring, measuring lines are laid out on the track slab along the line direction, located in the center and both sides of the track support platform respectively, the main machine and the programmable motor are placed at the tail of the track slab, and the receiving transducer is placed at the head of the track slab.

4. The intelligent monitoring system for ballastless track-bridge structure system according to claim 1 is characterized in that: The vehicle-track-bridge system spatial configuration test equipment comprises a parallel light visual measurement unit, a light source unit, an equipment fixing unit, an industrial control unit and a target unit; The parallel light vision measurement unit is used to measure the vertical vibration displacement of the high-speed railway box girder, the vertical high-frequency vibration displacement of the track, and the vertical relative displacement between the multi-layer structures of the track; the light source unit adopts a near-infrared light source, which is invisible light; the fixing unit adopts a snap-on fixing structure to fix the parallel light vision measurement unit; the industrial control unit is used for camera control and data acquisition and transmission, and has a built-in 4G network communication module; the target unit is used to set and fix the track plate target and track target.

5. The intelligent monitoring system for ballastless track-bridge structure system according to claim 1 is characterized in that: The method of collecting monitoring data using monitoring equipment includes: Real-time data collection is carried out for the arranged monitoring equipment according to the corresponding collection system and sampling frequency, and the time series data of different monitoring items are kept synchronized. The continuously recorded monitoring data are saved in hours and saved in binary compressed file format.

6. The intelligent monitoring system for ballastless track-bridge structure system according to claim 1 is characterized in that: The establishment of a monitoring database comprises: The monitoring database includes the original database, pre-processing database, analysis database, real-time query database and error information database; The data in the original database are the original monitoring data collected; the data in the preprocessing database are the data after preprocessing the original data collected, and the preprocessing operation is to reduce the noise of the data and eliminate abnormal monitoring data; the data in the analysis database are obtained by analyzing the data in the preprocessing database; the data in the real-time query database are used for real-time query by the staff; the data in the error information database are the error information data in the process of monitoring equipment collecting monitoring data and the original monitoring data with errors.

7. The intelligent monitoring system for ballastless track-bridge structure system according to claim 1 is characterized in that: The monitoring data acquisition module is also used to collect offline monitoring data. The acquisition of offline monitoring data includes: establishing an on-site corrosion environment exposure test site at the monitored ballastless track-bridge, taking samples every six months to conduct structural system durability degradation tests, and obtaining offline monitoring data; the offline monitoring data is also included in the monitoring database.

8. The intelligent monitoring system for ballastless track-bridge structure system according to claim 1 is characterized in that: The bridge monitoring module includes an early warning submodule; The early warning submodule is used for early warning, including single monitoring device early warning and multi-monitoring device fusion early warning; Single monitoring device warning is to set the warning threshold of a single monitoring device, and issue a warning based on the comparison between the monitoring data collected by the monitoring device and the warning threshold; The multi-monitoring device warning weight setting includes setting the weight of each monitoring device and performing integrated warning.

9. The intelligent monitoring system for ballastless track-bridge structure system according to claim 1, characterized in that: The bridge monitoring module includes a maintenance submodule; the maintenance submodule is used for the maintenance of the ballastless track-bridge structure system, including formulating daily inspection tasks and formulating early warning inspection tasks; Daily inspection tasks are periodic line inspection tasks. Inspection cycles and inspection routes are set to form daily inspection task packages, which are sent to inspection personnel. Inspection personnel conduct inspections according to the inspection routes. Formulate early warning inspection tasks. When an early warning occurs, locate the location where the early warning occurs, form an early warning inspection task package, and send it to the inspection personnel, who will conduct the inspection.

Citation Information

Patent Citations

  • Fault diagnosis prediction system and method of large-span railroad bridge based on PHM

    CN107609304A

  • Comprehensive monitoring and intelligent analysis method of safe state of rail system

    CN107858883A

  • Automatic monitoring device for ballastless track structure

    CN110542380A

  • Bridge safety and health monitoring system and method

    CN113984110A

  • Bridge track deformation displacement monitoring device and monitoring method

    CN115307565A

Cited By

  • Intelligent control system for fine adjustment operation of track bent frame

    CN122571426A