Cement injection floating equipment performance test system and test method

By designing a performance testing system for cement-injected floating equipment, and using components such as upper computers and programmable controllers to achieve automated control, the problem of difficult performance testing of floating equipment is solved, and automated testing and accurate data recording are realized.

CN118913748APending Publication Date: 2024-11-08SHAANXI NEWLAND INDUSTRIAL CORPORATION LIMITED
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411113763.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-14
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

In the prior art, floating equipment performance testing is difficult to implement simply and quickly, and complete performance measurement and automatic data recording cannot be carried out.

Method used

A performance testing system for cement-injected floating equipment is designed, including a computer, programmable controller, frequency converter, mud pump, electric switch valve, pressure transmitter, temperature transmitter and flow transmitter, through the serial port The connection realizes automatic control and data acquisition, and the test system can automatically adjust the valve opening and flow rate to achieve full process automation.

Benefits of technology

It realizes automatic testing of floating equipment, reduces the labor intensity of operators, has flexible testing, accurate and timely data measurement, and has automatic control, automatic measurement and automatic recording functions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118913748A_ABST
    Figure CN118913748A_ABST
Patent Text Reader

Abstract

The invention discloses a cementing floating equipment performance test system, which comprises an upper computer, a configuration control interface of the upper computer is provided with a plurality of control buttons, the upper computer is connected with a programmable controller through a serial port, the programmable controller is electrically connected with a frequency converter, and the frequency converter is electrically connected with a slurry pump. The invention further discloses a performance testing method for the cementing floating equipment. The method is specifically implemented according to the following steps: preparing before testing; performing forward testing; performing reverse testing; the test system automatically collects parameters such as pressure, temperature and flow and generates a curve. According to the performance test system and method for the cementing floating equipment, the functions of automatic control, automatic measurement and automatic recording are achieved, and automation of the whole process of testing of the floating equipment is achieved; operators do not need to adjust the opening degree of the valve on site and record data, so that the labor intensity of the operators is reduced; the test process is flexible and convenient to control, and data measurement is accurate and timely.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of petroleum cementing tool testing equipment, and relates to a cementing floating equipment performance testing system. The invention also relates to a cementing floating equipment performance testing method. Background Art

[0002] "Cementing float device" means one or more check valves embedded in the drill string that prevent the flow of drilling fluid into the casing from escaping the casing. The primary purpose of the cementing float device is to prevent cement that has entered the casing or wellbore annulus from escaping the casing or U-shaped pipe. In some cases, such as liner cementing, the float device may be the only practical way to prevent the formation of U-shaped pipe. In other cases, the float device is used to hold the cement in the annulus without increasing the pressure in the casing, thereby preventing U-shaped pipe. Generally, it is undesirable to increase the casing pressure when cement is specified because the increased pressure may cause cracks to appear in the annulus created by the cement.

[0003] Programmable Logic Controller (PLC) is an electronic system for digital computing, designed for use in industrial environments. It uses programmable memory to store instructions for performing logical operations, sequential control, timing, counting and arithmetic operations, and controls various types of machinery or production processes through digital and analog input and output. Variable-frequency Drive (VFD) is a power control device that uses frequency conversion technology and microelectronics technology to control AC motors by changing the frequency of the motor's working power supply. The inverter provides the required power supply voltage according to the actual needs of the motor, thereby achieving the purpose of energy saving and speed regulation. In addition, the inverter has many protection functions, such as overcurrent, overvoltage, overload protection, etc. With the continuous improvement of industrial automation, inverters have also been widely used. The host computer is a control computer used to manage and realize human-computer interaction functions and process control relative to the field controller of industrial field process control, which can be developed and designed through control software. Currently, there is a lack of specialized floating equipment performance testing systems, so it is impossible to conduct complete performance tests on floating equipment. The performance of floating equipment under different working conditions cannot be qualitatively and quantitatively measured, and the data cannot be automatically recorded.

[0004] In summary, the existing technology has the problem that the performance test of floating equipment is difficult to implement simply and quickly. Summary of the invention

[0005] The purpose of the present invention is to provide a cementing floating equipment performance test system, which solves the problem in the prior art that the floating equipment performance test is difficult to implement simply and quickly.

[0006] Another object of the present invention is to provide a method for testing the performance of a cementing floating device.

[0007] The technical solution adopted by the present invention is a cementing floating equipment performance test system, including a host computer with a configuration control interface provided with a plurality of control buttons, the host computer is connected to a programmable controller through a serial port, the programmable controller is electrically connected to a frequency converter, the frequency converter is electrically connected to a mud pump, and the programmable controller is electrically connected to an electric switch valve, a pressure transmitter, a temperature transmitter, an electric regulating valve, and a flow transmitter.

[0008] The present invention is also characterized in that:

[0009] The mud pump pipeline is connected to the mud pool, the mud pump is connected to a test pipeline b, a pressure transmitter a and an electric switch valve a are arranged on the test pipeline b, a test pipeline c is connected to the upper side of the test pipeline b, an electric regulating valve b and a pressure transmitter b are arranged on the test pipeline c, the test pipeline b is connected to a test pipeline e, and a pressure transmitter c, an electric regulating valve c, a temperature transmitter, a flow transmitter and an electric switch valve d are arranged in sequence in the axial direction of the test pipeline e.

[0010] A floating device is arranged between test pipeline e and test pipeline c, test pipeline c is connected to test pipeline d, electric switch valve e is arranged on test pipeline d, test pipeline d is connected to test pipeline a, test pipeline a is connected to the mud pool, and test pipeline e is connected to test pipeline a on its side.

[0011] Another technical solution adopted by the present invention is a method for testing the performance of a cementing floating device, which is specifically implemented according to the following steps:

[0012] Step 1: Preparation before the test;

[0013] Step 2: Start forward testing;

[0014] Step 3: End the forward test: Click the "End Test" button on the configuration control interface of the host computer. The test is completed and the mud pump automatically shuts down.

[0015] Step 4: Start reverse testing;

[0016] Step 5: End the reverse test: Click the "End Test" button on the configuration control interface of the host computer. The test is completed and the mud pump automatically shuts down;

[0017] Step 6: The test system automatically collects parameters such as pressure, temperature, flow, etc. and generates curves.

[0018] Another technical solution of the present invention is also characterized in that:

[0019] Step 1: Preparation before testing: Add 2.2m 3 -3.2m3 Mud, install and fix the floating device between the test pipe e and the test pipe c.

[0020] Step 2: Start the forward test: Click the "Start" button on the configuration control interface of the host computer to start the test system, click the "Forward Test" button, the programmable controller controls the electronically controlled valve to automatically switch to the forward test process, start the mud pump, and start the test.

[0021] Step 4: Start reverse test: Click "Reverse Test" on the configuration control interface of the host computer, the programmable controller controls the electronically controlled valve to automatically switch to the reverse test process, starts the mud pump, and starts the test.

[0022] In the forward test of step 2, the electric switch valve a and the electric switch valve e are closed, the electric regulating valve c and the electric switch valve d are opened, and the programmable controller controls the opening and closing degree of the electric regulating valve b to adjust the mud flow; in the reverse test of step 4, the electric regulating valve b and the electric switch valve d are closed, the electric switch valve a and the electric switch valve e are opened, and the programmable controller controls the opening and closing degree of the electric regulating valve c to adjust the mud flow.

[0023] During the test of steps 2 and 4, by modifying the set flow value on the configuration control interface of the host computer, the test system automatically adjusts the valve opening so that the actual flow reaches the set flow value; during the test of steps 2 and 4, click the "step test" button on the configuration control interface of the host computer, and the test system automatically switches the flow according to the set time and flow.

[0024] The beneficial effects of the present invention are as follows: the cementing floating equipment performance test system of the present invention has automatic control, automatic measurement, and automatic recording functions, realizing the automation of the entire process of floating equipment testing; operators do not need to adjust valve openings and record data on site, thereby reducing the labor intensity of operators; the test process control is flexible and convenient, and data measurement is accurate and timely. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a structural schematic diagram of a performance test system for cementing floating equipment of the present invention;

[0026] Figure 2 It is a schematic diagram of on-site connection of a performance test system for cementing floating equipment of the present invention.

[0027] In the figure, 1. host computer; 2. programmable controller; 3. frequency converter; 4. electric switch valve; 5. pressure transmitter; 6. temperature transmitter; 7. electric control valve; 8. flow transmitter; 9. mud pump; 10. test pipeline; 11. mud pool; 12. electric switch valve a; 13. electric switch valve d; 14. electric switch valve e; 15. electric control valve b; 16. electric control valve c; 17. pressure transmitter a; 18. pressure transmitter b; 19. pressure transmitter c; 20. floating device; 21. test pipeline a; 22. test pipeline b; 23. test pipeline c; 24. test pipeline d; 25. test pipeline e. DETAILED DESCRIPTION

[0028] The present invention is described in detail below with reference to the accompanying drawings and specific embodiments.

[0029] The performance testing system of cementing floating equipment of the present invention is as follows: Figure 1 As shown, it includes a host computer 1 with a configuration control interface provided with a plurality of control buttons, the host computer 1 is connected to a programmable controller 2 through a serial port, the programmable controller 2 is electrically connected to a frequency converter 3, the frequency converter 3 is electrically connected to a mud pump 9, and the programmable controller 2 is electrically connected to an electric switch valve 4, a pressure transmitter 5, a temperature transmitter 6, an electric regulating valve 7, and a flow transmitter 8.

[0030] like Figure 2 As shown, the mud pump 9 is connected to the mud pool 11 through a pipeline, and the mud pump is connected to a test pipeline b22, on which a pressure transmitter a17 and an electric switch valve a12 are arranged, and on the upper side of the test pipeline b22, a test pipeline c23 is connected, and on the test pipeline c23, an electric regulating valve b15 and a pressure transmitter b18 are arranged, and the test pipeline b22 is connected to a test pipeline e25, and on the axial direction of the test pipeline e25, a pressure transmitter c19, an electric regulating valve c16, a temperature transmitter 6, a flow transmitter 8, and an electric switch valve d13 are arranged in sequence. A floating device 20 is arranged between the test pipeline e25 and the test pipeline c23, and a test pipeline d24 is connected to the side of the test pipeline c23, and an electric switch valve e14 is arranged on the test pipeline d24, and the test pipeline d24 is connected to the test pipeline a21, and the test pipeline a21 is connected to the mud pool 11, and the test pipeline e25 is connected to the test pipeline a21 on the side.

[0031] The performance test method of cementing floating equipment is implemented in the following steps:

[0032] Step 1: Preparation before testing: Add 2.2m 3 -3.2m 3 Mud, install and fix the floating device 20 between the test pipe e25 and the test pipe c23;

[0033] Step 2: Start the forward test: Click the "Start" button on the configuration control interface of the host computer 1, the test system starts, click the "Forward Test" button, the programmable controller 2 controls the electronically controlled valve to automatically switch to the forward test process, start the mud pump 9, and start the test;

[0034] Step 3: End the forward test: Click the "End Test" button on the configuration control interface of the host computer 1, the test is completed, and the mud pump 9 is automatically turned off;

[0035] Step 4: Start the forward test; click "reverse test" on the configuration control interface of the host computer 1, the programmable controller 2 controls the electronically controlled valve to automatically switch to the reverse test process, starts the mud pump 9, and starts the test;

[0036] Step 5: End the reverse test: Click the "End Test" button on the configuration control interface of the host computer 1, the test is completed, and the mud pump 9 is automatically turned off;

[0037] Step 6: The test system automatically collects parameters such as pressure, temperature, flow, etc. and generates curves.

[0038] In the forward test of step 2, the electric switch valve a12 and the electric switch valve e14 are closed, the electric regulating valve c16 and the electric switch valve d13 are opened, and the programmable controller 2 controls the opening and closing degree of the electric regulating valve b15 to adjust the mud flow; in the reverse test of step 4, the electric regulating valve b15 and the electric switch valve d13 are closed, the electric switch valve a12 and the electric switch valve e14 are opened, and the programmable controller 2 controls the opening and closing degree of the electric regulating valve c16 to adjust the mud flow; during the test of steps 2 and 4, by modifying the set flow value in the configuration control interface of the host computer 1, the test system automatically adjusts the valve opening so that the actual flow reaches the set flow value; during the test of steps 2 and 4, click the "step test" button on the configuration control interface of the host computer 1, and the test system automatically switches the flow according to the set time and flow.

[0039] The cementing floating equipment performance test system uses a host computer 1 + programmable controller 2 + frequency converter 3 + electric valve + flow transmitter 8 to realize automatic monitoring of the entire test process. The process control adopts computer software and programmable controller program control, and the flow control adopts frequency converter 3 + electric valve adjustment + flow transmitter 8 to achieve closed-loop control. The test data is automatically collected and recorded by programmable controller 2 + host computer 1, and the host computer automatically generates a test report; the full digital measurement and control technology is used to accurately control and measure the entire cementing floating equipment performance test process. The entire test process is completely automatically controlled by the test system and can be unattended.

[0040] Example 1

[0041] like Figure 1-2 As shown, this embodiment proposes a cementing floating equipment performance test system, including a host computer 1 with a configuration control interface provided with a plurality of control buttons, the host computer 1 is connected to a programmable controller 2 through a serial port, the programmable controller 2 is electrically connected to a frequency converter 3, the frequency converter 3 is electrically connected to a mud pump 9, the programmable controller 2 is electrically connected to an electric switch valve 4, a pressure transmitter 5, a temperature transmitter 6, an electric regulating valve 7, and a flow transmitter 8.

[0042] Example 2

[0043] like Figure 1-2 As shown, this embodiment proposes a cementing floating equipment performance test system, including a host computer 1 with a configuration control interface provided with a plurality of control buttons, the host computer 1 is connected to a programmable controller 2 through a serial port, the programmable controller 2 is electrically connected to a frequency converter 3, the frequency converter 3 is electrically connected to a mud pump 9, the programmable controller 2 is electrically connected to an electric switch valve 4, a pressure transmitter 5, a temperature transmitter 6, an electric regulating valve 7, and a flow transmitter 8.

[0044] The mud pump 9 is connected to the mud pool 11 by pipeline, and the mud pump is connected to the test pipeline b22. The test pipeline b22 is provided with a pressure transmitter a17 and an electric switch valve a12. The upper side of the test pipeline b22 is connected to the test pipeline c23. The test pipeline c23 is provided with an electric regulating valve b15 and a pressure transmitter b18. The test pipeline b22 is connected to the test pipeline e25. The test pipeline e25 is provided with a pressure transmitter c19, an electric regulating valve c16, a temperature transmitter 6, a flow transmitter 8, and an electric switch valve d13 in sequence in the axial direction. A floating device 20 is provided between the test pipeline e25 and the test pipeline c23. The test pipeline c23 is connected to the test pipeline d24 on the side. The test pipeline d24 is provided with an electric switch valve e14. The test pipeline d24 is connected to the test pipeline a21. The test pipeline a21 is connected to the mud pool 11, and the test pipeline e25 is connected to the test pipeline a21 on the side.

[0045] Example 3

[0046] This embodiment proposes a method for testing the performance of a cementing floating device, which is specifically implemented according to the following steps:

[0047] Step 1: Preparation before the test;

[0048] Step 2: Start forward testing;

[0049] Step 3: End the forward test: Click the "End Test" button on the configuration control interface of the host computer 1, the test is completed, and the mud pump 9 is automatically turned off;

[0050] Step 4: Start reverse testing;

[0051] Step 5: End the reverse test: Click the "End Test" button on the configuration control interface of the host computer 1, the test is completed, and the mud pump 9 is automatically turned off;

[0052] Step 6: The test system automatically collects parameters such as pressure, temperature, flow, etc. and generates curves.

[0053] Example 4

[0054] This embodiment proposes a method for testing the performance of a cementing floating device, which is specifically implemented according to the following steps:

[0055] Step 1: Preparation before testing: Add 2.2m 3 -3.2m 3 Mud, install and fix the floating device 20 between the test pipe e25 and the test pipe c23;

[0056] Step 2: Start the forward test: Click the "Start" button on the configuration control interface of the host computer 1, the test system starts, click the "Forward Test" button, the programmable controller 2 controls the electronically controlled valve to automatically switch to the forward test process, start the mud pump 9, and start the test;

[0057] Step 3: End the forward test: Click the "End Test" button on the configuration control interface of the host computer 1, the test is completed, and the mud pump 9 is automatically turned off;

[0058] Step 4: Start reverse test: Click "Reverse Test" on the configuration control interface of the host computer 1, the programmable controller 2 controls the electronically controlled valve to automatically switch to the reverse test process, starts the mud pump 9, and starts the test;

[0059] Step 5: End the reverse test: Click the "End Test" button on the configuration control interface of the host computer 1, the test is completed, and the mud pump 9 is automatically turned off;

[0060] Step 6: The test system automatically collects parameters such as pressure, temperature, flow, etc. and generates curves.

[0061] In the forward test of step two, the electric switch valve a12 and the electric switch valve e14 are closed, the electric regulating valve c16 and the electric switch valve d13 are opened, and the programmable controller 2 controls the opening and closing degree of the electric regulating valve b15 to adjust the mud flow; in the reverse test of step four, the electric regulating valve b15 and the electric switch valve d13 are closed, the electric switch valve a12 and the electric switch valve e14 are opened, and the programmable controller 2 controls the opening and closing degree of the electric regulating valve c16 to adjust the mud flow.

[0062] During the test of steps 2 and 4, by modifying the set flow value on the configuration control interface of the host computer 1, the test system automatically adjusts the valve opening so that the actual flow reaches the set flow value; during the test of steps 2 and 4, click the "step test" button on the configuration control interface of the host computer 1, and the test system automatically switches the flow according to the set time and flow.

Claims

1. Cementing floating equipment performance test system, characterized in that: The invention comprises a host computer (1) having a configuration control interface provided with a plurality of control buttons, wherein the host computer (1) is connected to a programmable controller (2) via a serial port, the programmable controller (2) is electrically connected to a frequency converter (3), the frequency converter (3) is electrically connected to a mud pump (9), and the programmable controller (2) is electrically connected to an electric switch valve (4), a pressure transmitter (5), a temperature transmitter (6), an electric regulating valve (7), and a flow transmitter (8).

2. The cementing floating equipment performance testing system according to claim 1 is characterized in that: The mud pump (9) is connected to a mud pool (11) through a pipeline, and the mud pump is connected to a test pipeline b (22). The test pipeline b (22) is provided with a pressure transmitter a (17) and an electric switch valve a (12). The upper side of the test pipeline b (22) is connected to a test pipeline c (23). The test pipeline c (23) is provided with an electric regulating valve b (15) and a pressure transmitter b (18). The test pipeline b (22) is connected to a test pipeline e (25). The test pipeline e (25) is provided with a pressure transmitter c (19), an electric regulating valve c (16), a temperature transmitter (6), a flow transmitter (8), and an electric switch valve d (13) in sequence in the axial direction.

3. The cementing floating equipment performance testing system according to claim 2 is characterized in that: A floating device (20) is provided between the test pipeline e (25) and the test pipeline c (23); the test pipeline c (23) is connected to the test pipeline d (24) on the side; the test pipeline d (24) is provided with an electric switch valve e (14); the test pipeline d (24) is connected to the test pipeline a (21); the test pipeline a (21) is connected to the mud pool (11); and the test pipeline e (25) is connected to the test pipeline a (21) on the side.

4. A method for testing the performance of a cementing floating device, characterized in that: The cementing floating equipment performance test system according to claims 1-3 is implemented specifically according to the following steps: Step 1: Preparation before the test; Step 2: Start forward testing; Step 3: End the forward test: Click the "End Test" button on the configuration control interface of the host computer (1), the test is completed, and the mud pump (9) is automatically turned off; Step 4: Start reverse testing; Step 5: End the reverse test: Click the "End Test" button on the configuration control interface of the host computer (1), the test is completed, and the mud pump (9) is automatically turned off; Step 6: The test system automatically collects parameters such as pressure, temperature, flow, etc. and generates curves.

5. The performance testing method of cementing floating equipment according to claim 4 is characterized in that: Step 1: Preparation before testing: Add 2.2 m 3 -3.2m 3 Mud, the floating device (20) is installed and fixed between the test pipe e (25) and the test pipe c (23).

6. The performance testing method of cementing floating equipment according to claim 4, characterized in that: Step 2: Start the forward test: Click the "Start" button on the configuration control interface of the host computer (1) to start the test system, click the "Forward Test" button, the programmable controller (2) controls the electric control valve to automatically switch to the forward test process, start the mud pump (9), and start the test.

7. The performance testing method of cementing floating equipment according to claim 4, characterized in that: Step 4: Start reverse test: Click "reverse test" on the configuration control interface of the host computer (1), the programmable controller (2) controls the electric control valve to automatically switch to the reverse test process, starts the mud pump (9), and starts the test.

8. The performance testing method of cementing floating equipment according to claim 4, characterized in that: In the forward test of step 2, the electric switch valve a (12) and the electric switch valve e (14) are closed, the electric regulating valve c (16) and the electric switch valve d (13) are opened, and the programmable controller (2) controls the opening and closing degree of the electric regulating valve b (15) to adjust the mud flow rate; in the reverse test of step 4, the electric regulating valve b (15) and the electric switch valve d (13) are closed, the electric switch valve a (12) and the electric switch valve e (14) are opened, and the programmable controller (2) controls the opening and closing degree of the electric regulating valve c (16) to adjust the mud flow rate.

9. The performance testing method of cementing floating equipment according to claim 4, characterized in that: During the test of step 2 and step 4, by modifying the set flow value on the configuration control interface of the host computer (1), the test system automatically adjusts the valve opening so that the actual flow reaches the set flow value; during the test of step 2 and step 4, by clicking the "step test" button on the configuration control interface of the host computer (1), the test system automatically switches the flow according to the set time and flow.