Communication design method for sewage treatment plant group
By classifying and zoning China Unicom sewage treatment plants, the existing facilities and genetic algorithms are optimized to optimize the layout of China Unicom pipelines, the problems of mismatch inlet loads and overflow pollution in sewage treatment plants are solved, and efficient China Unicom sewage treatment systems and water environment protection are achieved. .
Patent Information
- Application Number
- CN202411167208.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-23
- Publication Date
- 2024-11-08
AI Technical Summary
The mismatch of water inlet loads in sewage treatment plants and overflow pollution caused by regional rainfall caused by climate change leads to water environment problems, which are difficult to effectively solve in the existing technology.
By obtaining the technical indicators of the sewage treatment plant, classifying and zoning, establishing a sewage treatment plant group system, optimizing existing pipelines and pumping station facilities, selecting the optimal plant group system construction plan, and using genetic algorithms to optimize the layout of the China Unicom pipelines to realize sewage Connection and balanced transfer between processing plants.
It realizes efficient connectivity between sewage treatment plants, reduces the cost of building or renovating pipelines, improves the efficiency and flexibility of sewage treatment systems, avoids water environment pollution, and improves the resilience of the entire sewage collection and treatment system.
Smart Images

Figure CN118917027A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of sewage treatment, and in particular to a design method for interconnecting a group of sewage treatment plants. Background Art
[0002] Sewage treatment plants are an important factor in ensuring the urban environment, but there is a mismatch in the inlet load of sewage treatment plants in each region. For example, some plants are operating beyond their scale, and some plants have not reached their design scale. At the same time, regional rainfall caused by climate change will cause overflow pollution in front of a single sewage treatment plant, causing water environment problems. Connecting several sewage treatment plants in a region to form a plant cluster can balance the sewage treatment needs in the region, effectively solve the problem of mismatch in sewage treatment loads in the region, and improve the operating efficiency of each sewage treatment plant. At the same time, it can solve the overflow problem of sewage treatment plants in emergency events, avoid water environment pollution, and thus improve the resilience of the entire sewage collection and treatment system.
[0003] Since the supporting sewage collection pipe network system (including pipelines, pumping stations, inspection wells, etc.) has been built when each sewage treatment plant was built, it is inevitable to rebuild sewage pipes and other infrastructure to meet the overall interconnection needs of several sewage treatment plants. Therefore, a technical solution is needed to make full use of existing pipelines, pumping stations and other infrastructure, and to build or relocate pipelines at a relatively low cost to maximize the interconnection benefits between sewage treatment plants. Summary of the invention
[0004] To achieve the above objectives, the present application provides a sewage treatment plant group interconnection design method, which is characterized by comprising the following steps:
[0005] Obtain technical indicators of sewage treatment plants and conduct positioning analysis of connected sewage treatment plant clusters; the technical indicators include: design scale, water inflow, receivable sewage scale WKS, and external sewage scale WKP; the positioning of the connected sewage treatment plant cluster refers to classifying sewage treatment plants according to technical indicators, and the classification includes: receiving plant WS, external discharge plant WP and transfer plant WZ;
[0006] Establishing a sewage treatment plant group zone to realize the interconnection of the sewage treatment plant group zones; including: identifying the pollution receiving zones of each sewage treatment plant, interconnecting the pollution receiving zones, allocating sewage flow paths, and realizing the transfer of sewage between different pollution receiving zones; wherein, when identifying the pollution receiving zones of each sewage treatment plant, obtaining the sewage volume Q in the pollution receiving zones of the sewage treatment plant ij ; The amount of sewage in the polluted area Q ij It is expressed as:
[0007] Among them, QP ij QS is the total amount of sewage in the jth zone of the i-th external discharge plant, ijis the total amount of sewage in the jth zone of the i-th receiving plant, QZ ij is the total amount of sewage in the jth zone of the i-th transfer plant;
[0008] Update the location of the connected sewage treatment plant group and determine the updated classification, including: receiving plant WS', external discharge plant WP' and transfer plant WZ';
[0009] Constructing a sewage treatment plant cluster system to minimize the number of external discharge plants and receiving plants in the entire interconnected area; the sewage treatment plant cluster system includes: sewage treatment plants, interconnected pipes, original sewage pipe networks, and original sewage pumping stations;
[0010] Select the optimal plant cluster system construction plan, the optimal standards including: balance between sewage treatment capacity and sewage treatment volume in the region, and achieving cost compliance constraints.
[0011] The classification of sewage treatment plants according to technical indicators includes:
[0012] If the daily frequency of the inflow of a sewage treatment plant exceeding the design scale k1 times exceeds the set threshold, the sewage treatment plant is defined as an external discharge plant;
[0013] If the frequency of the inflow of the sewage treatment plant being less than k2 times of the design scale exceeds the set threshold, the sewage treatment plant is defined as a receiving plant;
[0014] The rest are transit plants; among them, k1 and k2 are preset coefficients, which can be preset according to the actual requirements of projects in various places.
[0015] Among them, the scale of sewage that can be received by each sewage treatment plant is WKS, which is the scale of sewage that can be received by each sewage treatment plant, and the scale of sewage discharged by each sewage treatment plant is WKP, which is the scale of sewage that can be discharged by each sewage treatment plant.
[0016] Among them, the method for calculating the scale of retained sewage is: selecting the average value of the data of the water inflow of each receiving plant in the past two years that is less than the design scale as the scale of retained sewage; the method for calculating the external discharge scale is: selecting the average value of the data of the water inflow of each external discharge plant in the past two years that is greater than the design scale as the external discharge scale.
[0017] Furthermore, when connecting the polluted zones, all sewage treatment plants are traversed, and the connection operation is determined according to the location of the two adjacent sewage treatment plants, including:
[0018] If the adjacent sewage treatment plants are positioned as receiving plants and external discharge plants, the adjacent pollution receiving zones are divided into interconnected zones;
[0019] If the adjacent sewage treatment plants are positioned as receiving plants and transfer plants or external discharge plants and transfer plants, the adjacent pollution receiving areas are divided into transfer areas;
[0020] If adjacent sewage treatment plants have the same location, the adjacent pollution receiving zones are divided into co-flow zones;
[0021] The adjacent pollution-receiving zones refer to pollution-receiving zones that belong to two different sewage treatment plants and are geographically adjacent to each other.
[0022] Furthermore, the adjacent pollution-receiving areas are divided into interconnected areas, including the following steps:
[0023] Find the sewage mains in each zone according to the sewage transfer direction;
[0024] Connect and arrange interconnecting pipes on the sewage main pipe or pump station so that sewage in the sewage receiving area of the external discharge plant enters the sewage receiving area of the receiving plant through the interconnecting pipes; wherein the interconnecting pipe set is recorded as GPSL = {GPSL1, GPSL2, ... GPSLn}, and n is the number of interconnecting pipes arranged;
[0025] The step of dividing adjacent pollution receiving areas into transfer areas comprises the following steps:
[0026] Find the sewage mains in each zone according to the sewage transfer direction;
[0027] Connect and arrange interconnecting pipes on the sewage main pipe or pump station, so that sewage in the sewage receiving area of the external discharge plant enters the sewage receiving area of the transfer plant through the interconnecting pipes, and sewage in the sewage receiving area of the transfer plant enters the sewage receiving area of the receiving plant through the interconnecting pipes; the interconnecting pipe set is recorded as GZZL = {GZZL1, GZZL2, ... GZZLn}, where n is the number of interconnecting pipes arranged;
[0028] The step of dividing the adjacent pollution receiving zones into co-flow zones comprises the following steps:
[0029] Find the sewage mains in each zone according to the sewage transfer direction;
[0030] Connecting pipes are arranged on the sewage main pipe or pump station to connect the sewage in the pollution receiving areas of the two sewage treatment plants through the connecting pipes, and the sewage flows to the pollution receiving areas of the receiving plant. The connecting pipe set is recorded as GTTL = {GTTL1, GTTL2, ... GTTLn}, where n is the number of connecting pipes arranged.
[0031] Furthermore, the updated positioning of the Unicom sewage treatment plant cluster includes:
[0032] Statistics and calculation of the amount of sewage discharged or received by each sewage treatment plant after the sewage treatment plant cluster is connected;
[0033] Compare the relationship between the corresponding sewage changes of each sewage treatment plant and the corresponding water volume of WKS and WKP, and update the location of each sewage treatment plant, which is expressed as: receiving plant WS′, external discharge plant WS′, transfer plant WZ′;
[0034] The update method is:
[0035]
[0036] Among them, ∑QS ij is the total value of the sewage volume flowing into the i-th receiving plant through the interconnecting pipes of each pollution receiving zone, ∑QP ij It is the total value of the amount of sewage flowing out of the i-th discharge plant through the connecting pipe in each pollution-receiving area.
[0037] Among them, factors that need to be considered when constructing a plant cluster system include: sewage treatment plants, connecting pipes, the total amount of sewage discharged from each sewage treatment plant, and the total amount of sewage received;
[0038] The sewage treatment plant is The connecting pipe is GL′=∑GPSL′+∑GZZL′+∑GTTL′, and the total amount of sewage that needs to be discharged from the sewage treatment plant is WKP′=∑WKP i ′, the total amount of sewage that the sewage treatment plant needs to receive is WKS′=∑WKS i ′.
[0039] Furthermore, identifying the pollution receiving zones of each sewage treatment plant means: identifying the topological relationship of the sewage collection system in the sewage zone, wherein the sewage collection system includes a pump station, a pipeline, and a manhole;
[0040] The connecting the pollution-accepting partitions comprises the following steps:
[0041] Subdivide the sewage area into internal subdivisions and calculate the sewage volume Q of each internal subdivision after subdivision 转 ;
[0042] Establish a multi-objective decision-making model, expressed as: Among them, ∑Q 转 The flow rate that can be transferred by this interconnecting pipe;
[0043] The optimal connecting pipe set is obtained through the multi-objective decision model, including: taking the pump station or inspection well of the sewage outflow zone as the starting point of the connecting pipe and traversing the inspection well; taking the pump station or inspection well of the sewage inflow zone as the ending point of the connecting pipe, traversing the starting point and the ending point in turn to obtain several connecting pipe construction routes, and using a genetic algorithm to solve the connecting pipe construction multi-objective decision model to obtain the optimal connecting pipe set.
[0044] Furthermore, when selecting the optimal plant cluster system construction plan, it includes:
[0045] A multi-objective decision-making model for the sewage treatment plant interconnection scheme based on sewage transfer objectives and engineering cost objectives is established, which can be expressed as:
[0046]
[0047] Among them, c i 、c j 、c k is the construction cost of each section of the interconnecting pipe, a and b are the set thresholds,
[0048] And: 0≤WKS′≤WKS, 0≤WKP′≤WKP×60%, 0≤GPSL′, 0≤GZZL′, 0≤GTTL′, 0≤a, 0≤b;
[0049] Genetic algorithm is used to solve the multi-objective decision-making model of sewage treatment plant interconnection scheme to obtain the optimal solution.
[0050] The first aspect of the present invention provides a method for optimal layout of interconnecting pipelines of a group of sewage treatment plants, aiming to reduce the amount of engineering work for new or modified pipelines and the cost of interconnection by optimizing the existing resource allocation, while improving the efficiency and flexibility of the sewage treatment system; at the same time, it can maximize the benefits of sewage treatment plants in the region, and through the orderly flow of sewage, avoid the pollution of the water environment by sewage treatment plants in response to adverse meteorological conditions such as rainfall; the present invention also provides a method for arranging zoned pipelines of a group of interconnected sewage treatment plants, providing an optimal solution for the layout of each sewage interconnecting pipe to maximize the benefits at low cost; and proposes an optimization method for the interconnected sewage treatment plant group system, providing an optimal solution for the interconnection of regional systematic sewage treatment plant groups, and achieving maximum benefits at low cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0051] Figure 1 It is a step diagram of a sewage treatment plant group interconnection design method provided according to an embodiment of the present invention. DETAILED DESCRIPTION
[0052] The specific implementation of the present invention is described in detail below with reference to the accompanying drawings.
[0053] Figure 1 A step diagram of the design method for interconnecting a group of sewage treatment plants is provided, including the following steps:
[0054] Step S100: Obtain technical indicators of the sewage treatment plant and conduct location analysis of the connected sewage treatment plant cluster;
[0055] In the present invention, the positioning analysis of the interconnected sewage treatment plant group refers to judging and classifying the sewage treatment plants that need to be interconnected, and classifying them into receiving plants WS, external discharge plants WP, and transfer plants WZ.
[0056] Specifically, the technical indicators include: design scale, inflow volume, acceptable sewage scale WKS, and external sewage scale WKP. When analyzing the location of the connected sewage treatment plant group, the sewage treatment plant is judged based on its technical indicators in the past two years (such as daily inflow volume). The specific judgment criteria include:
[0057] If the daily frequency of the inflow of a sewage treatment plant exceeding the design scale k1 times exceeds the set threshold, the sewage treatment plant is defined as an external discharge plant;
[0058] If the frequency of the inflow of the sewage treatment plant being less than k2 times of the design scale exceeds the set threshold, the sewage treatment plant is defined as a receiving plant;
[0059] The rest are transit plants;
[0060] For example, if the threshold is set at 200 days, then within 2 years, if the number of days when the inflow water volume of a sewage treatment plant is greater than k1 times the design scale exceeds 200 days, the sewage treatment plant is defined as an external discharge plant.
[0061] Among them, k1 and k2 are preset coefficients, usually k1=1.2 and k2=0.8, which can be preset according to the actual requirements of local projects.
[0062] On the other hand, the receiving plant's receivable scale and the discharge scale of the discharge plant are determined by technical indicators, specifically:
[0063] The wastewater scale that each wastewater treatment plant can accept is obtained by subtracting the scale of reserved wastewater from the design scale of each wastewater treatment plant, which is recorded as WKS = {WKS1, WKS2, ... WKS i}, and satisfy WKS1≥WKS2≥……≥WKS i , where i is the number of receiving plants, and the scale of retained sewage can be obtained by using statistical methods from the water inflow of each receiving plant in the past two years;
[0064] The method for calculating the scale of retained sewage is: select the average value of the data of water inflow of each receiving plant in the past two years that is less than the design scale as the scale of retained sewage.
[0065] The scale of sewage discharged from each sewage treatment plant is obtained by subtracting the design scale of each sewage treatment plant from the existing discharge scale, which is recorded as WKP = {WKP1, WKP2, ... WKP i}, and satisfy WKP1≥WKP2≥……≥WKP i , where i is the number of discharge plants. The existing discharge scale can be obtained by using statistical methods from the water inflow of each discharge plant in the past two years.
[0066] The method for calculating the discharge scale is: select the average value of the data of water inflow of each discharge plant in the past two years that is greater than the design scale as the discharge scale.
[0067] Step S110: Establishing sewage treatment plant cluster zones to achieve interconnection of sewage treatment plant cluster zones.
[0068] In practice, each sewage treatment plant has a corresponding pollution zone. The sewage in the pollution zone enters the sewage treatment plant for treatment through the existing sewage collection system; and the pollution zones belonging to the same sewage treatment plant do not overlap or intersect in space and can be adjacent.
[0069] In this step, the pollution receiving zones of each sewage treatment plant are identified, the pollution receiving zones are connected, and the sewage flow paths are allocated to realize the transfer of sewage between different pollution receiving zones. The specific implementation process includes the following steps:
[0070] First, traverse the pollution receiving zones contained in all sewage treatment plants to obtain the sewage transfer direction and the total amount of sewage in the pollution receiving zones;
[0071] Among them, the sewage volume in the partition is Q ij It is expressed as:
[0072] Among them, QP ij QS is the total amount of sewage in the jth zone of the i-th external discharge plant, ij is the total amount of sewage in the jth zone of the i-th receiving plant, QZ ij is the total amount of sewage in the jth zone of the ith transfer plant.
[0073] Sewage volume Q in polluted area ij It exists objectively and can be obtained through per capita pollution coefficient method, water volume monitoring and other methods.
[0074] Second: According to the sewage treatment plant positioning result obtained in step S100, the adjacent pollution receiving zones of two adjacent sewage treatment plants are connected. Among them, the adjacent pollution receiving zones refer to the pollution receiving zones belonging to two different sewage treatment plants and bordering each other geographically:
[0075] 1) If the adjacent sewage treatment plants are positioned as receiving plants and external discharge plants, the adjacent pollution receiving areas are divided into interconnected areas;
[0076] The specific implementation includes the following steps:
[0077] Find the sewage mains in each zone according to the sewage transfer direction;
[0078] Connect and arrange interconnecting pipes on the sewage main pipe or pump station, so that the sewage in the sewage receiving area of the external discharge plant enters the sewage receiving area of the receiving plant through the interconnecting pipes; wherein the interconnecting pipe set is recorded as GPSL = {GPSL1, GPSL2, ... GPSLn}, and n is the number of interconnecting pipes arranged;
[0079] 2) If the adjacent sewage treatment plants are positioned as receiving plants and transfer plants or external discharge plants and transfer plants, the adjacent pollution receiving areas are divided into transfer areas;
[0080] The specific implementation includes the following steps:
[0081] Find the sewage mains in each zone according to the sewage transfer direction;
[0082] Connect and arrange interconnecting pipes on the sewage main pipe or pump station, so that the sewage in the sewage receiving area of the external discharge plant enters the sewage receiving area of the transfer plant through the interconnecting pipe, and the sewage in the sewage receiving area of the transfer plant enters the sewage receiving area of the receiving plant through the interconnecting pipe; the interconnecting pipe set is recorded as GZZL = {GZZL1, GZZL2, ... GZZLn}, where n is the number of interconnecting pipes arranged;
[0083] 3) If adjacent sewage treatment plants have the same location, the adjacent pollution receiving areas are divided into co-flow areas;
[0084] The specific implementation includes the following steps:
[0085] Find the sewage mains in each zone according to the sewage transfer direction;
[0086] Connecting pipes are arranged on the sewage main pipe or pump station to connect the sewage in the pollution receiving areas of the two sewage treatment plants through the connecting pipes, and the sewage flows to the pollution receiving areas of the receiving plant. The connecting pipe set is recorded as GTTL = {GTTL1, GTTL2, ... GTTLn}, where n is the number of connecting pipes arranged.
[0087] In this step, the arrangement of the connecting pipes gives priority to the transfer between sewage treatment plants with large demand, and the type of arrangement of the connecting pipes is preferably gravity flow, and the second choice is pressure boosting.
[0088] The method to achieve the design of connected pollution zoning is as follows:
[0089] 1) Identify the topological relationship of the sewage collection system within the sewage zone, wherein the sewage collection system includes a pump station, a pipeline, and a manhole;
[0090] 2) Subdivide the sewage area into internal subdivisions and calculate the sewage volume Q of each internal subdivision after subdivision 转 ;
[0091] 3) Establish a multi-objective decision-making model for interconnection pipe construction based on sewage transfer capacity and construction length, expressed as: Among them, ∑Q 转 The flow rate that can be transferred by this interconnecting pipe;
[0092] 4) The optimal connecting pipe set is obtained through a multi-objective decision-making model, including: taking the pump station or inspection well of the sewage outflow zone as the starting point of the connecting pipe and traversing the inspection well; taking the pump station or inspection well of the sewage inflow zone as the end point of the connecting pipe, traversing the starting point and the end point in turn to obtain several connecting pipe construction routes, and using a genetic algorithm to solve the connecting pipe construction multi-objective decision-making model to obtain the optimal connecting pipe set.
[0093] When solving the multi-objective decision-making model for Unicom pipeline construction, the following steps are included:
[0094] A) Using Unicom to build a multi-objective decision-making model as the objective function and decision variables to form a decision-making scheme as a chromosome, randomly generate an initial population Pn of N chromosomes;
[0095] B) Perform non-dominated sorting on the chromosomes in Pn, put all non-dominated chromosomes into the non-dominated set Z, and determine the size of the non-dominated set Z. If the size of the non-dominated set Z exceeds N, the dominated chromosomes with large crowding distance are preferentially selected to be placed in the non-dominated set Z. If the size of the non-dominated set Z is less than N, the dominated chromosomes with high fitness are preferentially selected to enter the non-dominated set Z until the size of the non-dominated set Z is equal to N. The non-dominated set is the new population Pn+1.
[0096] C) Crossover and mutation of chromosomes in Pn+1 to produce offspring population Qn+1;
[0097] D) Determine whether the termination criteria are met. If so, output the optimal solution set. If not, merge Qn+1 and Pn+1 to form a new Pn, and re-execute step B) to perform non-dominated sorting on the chromosomes in Pn and perform iterative calculations.
[0098] When the number of iterations reaches the specified number, the iterative calculation stops.
[0099] In this step, the interconnecting pipe arrangement realizes the transfer of sewage, so the influent water volume of the original sewage treatment plant will change, and the positioning also needs to change with the increase or decrease of the influent water volume. At this time, the positioning of each sewage treatment plant is updated according to the new water volume after the interconnecting pipe arrangement, see step S120 for details.
[0100] Step S120: updating the location of the connected sewage treatment plant group and determining the updated classification, including: receiving plant WS', external discharge plant WP' and transfer plant WZ';
[0101] The processing steps for updating the location of the connected sewage treatment plant cluster include:
[0102] 1) Counting and calculating the amount of sewage discharged or received by each sewage treatment plant after step S110 is implemented;
[0103] 2) Compare the relationship between the corresponding sewage changes of each connected sewage treatment plant and the corresponding water volume of WKS and WKP, and update the location of each sewage treatment plant, which is expressed as: receiving plant WS′, external discharge plant WS′, transfer plant WZ′;
[0104] The specific update method is:
[0105]
[0106] Among them, ∑QS ij is the total value of the sewage volume flowing into the i-th receiving plant through the interconnecting pipes of each pollution receiving zone, ∑QP ij It is the total value of the amount of sewage flowing out of the i-th discharge plant through the connecting pipe in each pollution-receiving area.
[0107] 3) After obtaining the location of the new sewage treatment plant, the corresponding sewage treatment plant pollution zone is updated simultaneously.
[0108] Step S130: constructing a plant cluster system to minimize the number of internal and external discharge plants and receiving plants in the entire interconnected area;
[0109] Iteratively run steps S110 and S120, and finally realize a preliminary interconnection system of sewage treatment plants with relatively balanced sewage transfer by arranging a number of interconnection pipes.
[0110] Specifically, the plant cluster system includes: sewage treatment plants, interconnecting pipes, existing sewage pipe networks, and existing sewage pumping stations; factors that need to be considered when constructing the plant cluster system include: sewage treatment plants, interconnecting pipes, the total amount of sewage discharged by each sewage treatment plant, and the total amount of sewage received; by constructing the plant cluster system, the interconnecting pipe design is realized, and the sewage treatment plants are connected;
[0111] The sewage treatment plant in the system is
[0112] The connecting pipe in the system is GL′=∑GPSL′+∑GZZL′+∑GTTL′,
[0113] The total amount of sewage that needs to be discharged from the sewage treatment plant in the system is WKP′=∑WKP i ′,
[0114] The total amount of sewage that the sewage treatment plant in the system needs to receive is WKS′=∑WKS i ′;
[0115] Among them, the amount of sewage that needs to be discharged by each sewage treatment plant in the system is WKP i ′, the amount of sewage that each sewage treatment plant in the system needs to receive is WKS i ′, the connecting pipes of the interconnecting area, transfer area and co-flow area in the system are GPSL′, GZZL′ and GTTL′ respectively:
[0116] In the actual design of the plant cluster system, there will be multiple interconnecting pipe solutions. The principle of realizing the plant cluster system structure in this step is to make full use of the existing sewage collection system infrastructure, optimize the existing resource allocation, and balance the sewage in the entire interconnected area, that is, to minimize the number of external discharge plants and receiving plants.
[0117] Step S140: Selecting the optimal plant cluster system construction plan, wherein the optimal criteria include: balancing the sewage treatment capacity and sewage treatment volume in the region, and achieving cost compliance constraints.
[0118] The system structure of the sewage treatment plant group obtained through steps S100-S130 will increase the project investment while realizing the sewage transfer in the region. Therefore, it is necessary to optimize and adjust under the constraints of project benefits and investment amount, and finally obtain the optimal layout plan of the sewage treatment plant group interconnection pipeline. Among them, the project benefit refers to the relative balance of the sewage treatment capacity and the corresponding sewage treatment volume in the region after the implementation of the interconnection pipe project; the investment amount constraint refers to the construction cost of the interconnection pipe project, operation and maintenance costs, etc. In this step, based on these two factors, the interconnection pipe layout is modified to obtain the optimal sewage treatment plant group system construction plan.
[0119] The method for selecting the optimal plant cluster system construction plan includes:
[0120] A multi-objective decision-making model for the sewage treatment plant interconnection scheme based on sewage transfer objectives and engineering cost objectives is established, which can be expressed as:
[0121]
[0122] Among them, c i 、c j 、c k is the construction cost of each section of the interconnecting pipe, a and b are the set thresholds,
[0123] And: 0≤WKS′≤WKS, 0≤WKP′≤WKP×60%, 0≤GPSL′, 0≤GZZL′, 0≤GTTL′, 0≤a, 0≤b;
[0124] Genetic algorithm is used to solve the multi-objective decision-making model of sewage treatment plant interconnection scheme to obtain the optimal solution.
[0125] The solution process includes:
[0126] The decision variables and the objective function value form a decision plan, which is used as a chromosome to randomly generate an initial population Pn of N chromosomes.
[0127] Perform non-dominated sorting on the chromosomes in Pn, put all non-dominated chromosomes into the non-dominated set Z, and determine the size of the non-dominated set Z. If the size of the non-dominated set Z exceeds N, give priority to the dominated chromosomes with large crowding distance and put them into the non-dominated set Z. If the size of the non-dominated set Z is less than N, give priority to the dominated chromosomes with high fitness to enter the non-dominated set Z until the size of the non-dominated set Z is equal to N. The non-dominated set is the new population Pn+1.
[0128] Perform crossover and mutation on the chromosomes in Pn+1 to generate the offspring population Qn+1;
[0129] Determine whether the termination criteria are met. If so, output the optimal solution set. If not, merge Qn+1 and Pn+1 to form a new Pn, re-enter the non-dominated sorting of the chromosomes in Pn, and perform iterative calculations.
[0130] If the number of iterations reaches the specified number of iterations, the iterative calculation is terminated.
[0131] In the present invention, the method for optimal layout of interconnected pipes of a sewage treatment plant group can maximize the benefits of sewage treatment plants in the region. Through the orderly flow of sewage, it is possible to avoid pollution of the water environment by sewage treatment plants in response to adverse meteorological conditions such as rainfall, and provide an optimal solution for the layout of each sewage interconnecting pipe to achieve maximum benefits at low cost. In the overall design process, by optimizing the allocation of existing resources, reducing the amount of engineering work for new or rebuilt pipelines, and reducing the cost of interconnection, an optimal solution is provided for the interconnection of regional systematic sewage treatment plant groups, achieving maximum benefits at low cost, while improving the efficiency and flexibility of the sewage treatment system.
[0132] The above disclosures are only several specific embodiments of the present invention; however, the present invention is not limited thereto, and any changes that can be conceived by those skilled in the art should fall within the protection scope of the present invention.
Claims
1. A sewage treatment plant group interconnection design method, characterized in that: The following steps are involved: Obtain technical indicators of sewage treatment plants and conduct positioning analysis of connected sewage treatment plant clusters; the technical indicators include: design scale, water inflow, receivable sewage scale WKS, and external sewage scale WKP; the positioning of the connected sewage treatment plant cluster refers to classifying sewage treatment plants according to technical indicators, and the classification includes: receiving plant WS, external discharge plant WP and transfer plant WZ; Establishing a sewage treatment plant group zone to realize the interconnection of the sewage treatment plant group zones; including: identifying the pollution receiving zones of each sewage treatment plant, interconnecting the pollution receiving zones, allocating sewage flow paths, and realizing the transfer of sewage between different pollution receiving zones; wherein, when identifying the pollution receiving zones of each sewage treatment plant, obtaining the sewage volume Q in the pollution receiving zones of the sewage treatment plant ij ; The amount of sewage in the polluted area Q ij It is expressed as: Among them, QP ij QS is the total amount of sewage in the jth zone of the i-th external discharge plant, ij is the total amount of sewage in the jth zone of the i-th receiving plant, QZ ij is the total amount of sewage in the jth zone of the i-th transfer plant; Update the location of the connected sewage treatment plant group and determine the updated classification, including: receiving plant WS', external discharge plant WP' and transfer plant WZ'; Constructing a sewage treatment plant cluster system to minimize the number of external discharge plants and receiving plants in the entire interconnected area; the sewage treatment plant cluster system includes: sewage treatment plants, interconnected pipes, original sewage pipe networks, and original sewage pumping stations; Select the optimal plant cluster system construction plan, the optimal standards including: balance between sewage treatment capacity and sewage treatment volume in the region, and achieving cost compliance constraints.
2. The sewage treatment plant group interconnection design method according to claim 1 is characterized in that: The classification of sewage treatment plants according to technical indicators includes: If the daily frequency of the inflow of a sewage treatment plant exceeding the design scale k1 times exceeds the set threshold, the sewage treatment plant is defined as an external discharge plant; If the frequency of the inflow of the sewage treatment plant being less than k2 times of the design scale exceeds the set threshold, the sewage treatment plant is defined as a receiving plant; The rest are transit plants; among them, k1 and k2 are preset coefficients, which can be preset according to the actual requirements of projects in various places.
3. The sewage treatment plant group interconnection design method according to claim 1 is characterized in that: When connecting the polluted zones, all sewage treatment plants are traversed, and the connection operation is determined according to the locations of the two adjacent sewage treatment plants, including: If the adjacent sewage treatment plants are positioned as receiving plants and external discharge plants, the adjacent pollution receiving zones are divided into interconnected zones; If the adjacent sewage treatment plants are positioned as receiving plants and transfer plants or external discharge plants and transfer plants, the adjacent pollution receiving areas are divided into transfer areas; If adjacent sewage treatment plants have the same location, the adjacent pollution receiving zones are divided into co-flow zones; The adjacent pollution-receiving zones refer to pollution-receiving zones that belong to two different sewage treatment plants and are geographically adjacent to each other.
4. The sewage treatment plant group interconnection design method according to claim 3 is characterized in that: The step of dividing adjacent pollution-receiving areas into interconnected areas comprises the following steps: Find the sewage mains in each zone according to the sewage transfer direction; Connect and arrange interconnecting pipes on the sewage main pipe or pump station so that sewage in the sewage receiving area of the external discharge plant enters the sewage receiving area of the receiving plant through the interconnecting pipes; wherein the interconnecting pipe set is recorded as GPSL = {GPSL1, GPSL2, ... GPSLn}, and n is the number of interconnecting pipes arranged; The step of dividing adjacent pollution receiving areas into transfer areas comprises the following steps: Find the sewage mains in each zone according to the sewage transfer direction; Connect and arrange interconnecting pipes on the sewage main pipe or pump station, so that sewage in the sewage receiving area of the external discharge plant enters the sewage receiving area of the transfer plant through the interconnecting pipes, and sewage in the sewage receiving area of the transfer plant enters the sewage receiving area of the receiving plant through the interconnecting pipes; the interconnecting pipe set is recorded as GZZL = {GZZL1, GZZL2, ... GZZLn}, where n is the number of interconnecting pipes arranged; The step of dividing adjacent pollution receiving zones into co-flow zones comprises the following steps: Find the sewage mains in each zone according to the sewage transfer direction; Connecting pipes are arranged on the sewage main pipe or pump station to connect the sewage in the pollution receiving areas of the two sewage treatment plants through the connecting pipes, and the sewage flows to the pollution receiving areas of the receiving plant. The connecting pipe set is recorded as GTTL = {GTTL1, GTTL2, ... GTTLn}, where n is the number of connecting pipes arranged.
5. The sewage treatment plant group interconnection design method according to claim 4 is characterized in that: The updating of the location of the interconnected sewage treatment plant cluster includes: Statistics and calculation of the amount of sewage discharged or received by each sewage treatment plant after the sewage treatment plant cluster is connected; Compare the relationship between the corresponding sewage changes of each sewage treatment plant and the corresponding water volume of WKS and WKP, and update the location of each sewage treatment plant, which is expressed as: receiving plant WS′, external discharge plant WS′, transfer plant WZ′; The update method is: Among them, ∑QS ij is the total value of the sewage volume flowing into the i-th receiving plant through the interconnecting pipes of each pollution receiving zone, ∑QP ij It is the total value of the amount of sewage flowing out of the i-th discharge plant through the connecting pipe in each pollution-receiving area.
6. The sewage treatment plant group interconnection design method according to claim 5 is characterized in that: The factors to be considered when constructing the plant cluster system include: sewage treatment plants, connecting pipes, the total amount of sewage discharged from each sewage treatment plant, and the total amount of sewage received; The sewage treatment plant is The connecting pipe is, and the total amount of sewage that needs to be discharged from the sewage treatment plant is WKP′=∑WKP i ′, the total amount of sewage that the sewage treatment plant needs to receive is WKS′=∑WKS i ′.
7. The sewage treatment plant group interconnection design method according to claim 4 is characterized in that: The identification of the pollution receiving zones of each sewage treatment plant refers to: identifying the topological relationship of the sewage collection system in the sewage zone, wherein the sewage collection system includes a pump station, a pipeline, and a manhole; The connecting the pollution-accepting partitions comprises the following steps: Subdivide the sewage area into internal subdivisions and calculate the sewage volume Q of each internal subdivision after subdivision 转 ; Establish a multi-objective decision-making model, expressed as: Among them, ∑Q 转 The flow rate that can be transferred by this interconnecting pipe; The optimal connecting pipe set is obtained through the multi-objective decision model, including: taking the pump station or inspection well of the sewage outflow zone as the starting point of the connecting pipe and traversing the inspection well; taking the pump station or inspection well of the sewage inflow zone as the ending point of the connecting pipe, traversing the starting point and the ending point in turn to obtain several connecting pipe construction routes, and using a genetic algorithm to solve the connecting pipe construction multi-objective decision model to obtain the optimal connecting pipe set.
8. The sewage treatment plant group interconnection design method according to claim 6 is characterized in that: The selection of the optimal plant cluster system construction plan includes: A multi-objective decision-making model for the sewage treatment plant interconnection scheme based on sewage transfer objectives and engineering cost objectives is established, which can be expressed as: Among them, c i 、c j 、c k is the construction cost of each section of the interconnecting pipe, a and b are the set thresholds, And: 0≤WKS′≤WKS, 0≤WKP′≤WKP×60%, 0≤GPSL′, 0≤GZZL′, 0≤GTTL′, 0≤a, 0≤b; Genetic algorithm is used to solve the multi-objective decision-making model of sewage treatment plant interconnection scheme to obtain the optimal solution.
9. The sewage treatment plant group interconnection design method according to claim 2, characterized in that: The scale of sewage that can be received by each sewage treatment plant is WKS, which is the scale of sewage that can be received by each sewage treatment plant. The scale of sewage discharged by each sewage treatment plant is WKP, which is the scale of sewage that can be discharged by each sewage treatment plant. Among them, the method for calculating the scale of retained sewage is: selecting the average value of the data of the water inflow of each receiving plant in the past two years that is less than the design scale as the scale of retained sewage; the method for calculating the external discharge scale is: selecting the average value of the data of the water inflow of each external discharge plant in the past two years that is greater than the design scale as the external discharge scale.