Asphalt construction management method and device

By using RFID technology interaction on transport vehicles and pavers, the problems of complex and high cost in the existing technology are solved, efficient management and accurate cost accounting of asphalt construction are achieved, and construction quality and efficiency are improved.

CN118917807AInactive Publication Date: 2024-11-08BEIJING JIUQI JINJIAN TECH CO LTD

Patent Information

Application Number
CN202411401567.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-09
Publication Date
2024-11-08
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

During the construction process, the existing asphalt information management system has problems such as complex equipment installation, high cost and large initial data errors, making it difficult to achieve full monitoring and management.

Method used

Using RFID technology, an RFID card is installed on the transport vehicle, an RFID reader is installed on the pound room and paver, and through the interaction between the RFID card and the reader, the information of the transport vehicle and the construction part data are obtained and recorded to realize asphalt construction. Management and costing.

Benefits of technology

It simplifies the equipment installation process, reduces costs, reduces data errors, improves the efficiency and accuracy of construction management, and can promptly feedback abnormal data and construction costs, ensuring the accuracy of construction quality and dosage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118917807A_ABST
    Figure CN118917807A_ABST
Patent Text Reader

Abstract

The invention discloses an asphalt construction management method and device. According to the scheme, after a transport vehicle provided with an RFID card arrives at an asphalt paver provided with a first RFID reader-writer, and the asphalt paver reads information in the RFID card through the first RFID reader-writer, information recorded in the first RFID reader-writer is obtained; and based on the acquired information recorded in the first RFID reader-writer, asphalt construction management is carried out according to the construction part. Different from the prior art in which monitoring equipment is mounted at an asphalt mixing station, a transport vehicle, a paver and the like to record and analyze asphalt construction data and realize monitoring and management of asphalt construction, the RFID technology is introduced, an RFID card is mounted on the transport vehicle, and RFID reader-writers are mounted on a weight house and the paver. Compared with installation of monitoring equipment, the RFID technology has obvious advantages, and is simple and easy to implement and low in cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of engineering technology, and in particular to an asphalt construction management method and device. Background Art

[0002] In order to achieve full-process monitoring and management of asphalt construction and ensure that the quality and dosage of asphalt meet the requirements, an asphalt information management system is usually used to record and analyze the data of asphalt construction to provide a basis for traceability of asphalt construction quality.

[0003] Currently, most asphalt information management systems adopt the following approach: at the production end, an asphalt mixing station monitoring and management platform is built to realize the data connection between the data acquisition equipment and the mixing station control console. The platform continuously collects real-time parameters of the asphalt production process through the data acquisition terminal; at the transportation end, positioning systems and temperature monitoring equipment are installed on the transportation vehicles to monitor the vehicle's driving trajectory and temperature changes in real time; at the construction end, monitoring equipment is installed on the paver to monitor the paver's operating status and paving thickness in real time.

[0004] By installing monitoring equipment at asphalt mixing plants, transport vehicles and pavers, although the construction quality is guaranteed and the quality can be traced, there are still many defects in the actual construction process: asphalt construction basically adopts a professional subcontracting model, the required paving equipment and transportation equipment are not owned by the construction unit, and the installation of hardware monitoring equipment is difficult to implement; hardware monitoring equipment needs to be invested, and the connection of some hardware requires changes to the settings of the monitored equipment itself, such as the engine of the paver, the asphalt mixing plant terminal, etc. Changes to the software and hardware of the monitoring equipment may cause software instability and hardware safety hazards; due to the differences in the installation locations of the monitoring equipment, the adjustment of the monitoring equipment requires a process, and there are cases where the initial data errors are large. Summary of the invention

[0005] Based on the above problems, the present application provides an asphalt construction management method and device, the purpose of which is to propose a simple, easy and low-cost asphalt construction management method.

[0006] The embodiments of the present application disclose the following technical solutions: The first aspect of the present application provides an asphalt construction management method, the method comprising: After a transport vehicle equipped with an RFID card arrives at an asphalt paver equipped with a first RFID reader / writer, and the asphalt paver reads the information in the RFID card through the first RFID reader / writer, the information recorded in the first RFID reader / writer is obtained; wherein the information in the RFID card includes the weighing data written to the RFID card by the second RFID reader / writer in the weighing room; the weighing data includes the license plate number of the transport vehicle, the material information transported by the transport vehicle, the weight of the material transported by the transport vehicle, and the weighing time information of the transport vehicle; the information recorded in the first RFID reader / writer includes the weighing data and also includes the construction site information, the paving time information, and the paving equipment information; Based on the information recorded in the first RFID reader / writer, asphalt construction management is performed according to the construction site.

[0007] In an optional implementation, the asphalt construction management method further includes: Before asphalt construction, determine the starting construction distance, construction location and starting and ending pile numbers of the construction location; Generate the paving area, paving density and paving thickness through the starting construction distance, the construction site and the starting and ending pile numbers of the construction site; Calculate the theoretical total weight of materials according to the paving area, the paving density and the paving thickness; A working surface plan is constructed using the starting construction distance, the construction site, the starting and ending pile numbers of the construction site, the paving area, the paving thickness, the paving density and the theoretical total material weight, and the working surface plan is sent to the asphalt mixing station so that the asphalt mixing station can collect construction raw materials according to the received information and load the asphalt mixture after mixing the raw materials into the transport vehicle.

[0008] The second RFID reader / writer in the weighing room writes the weighing data into the RFID card, including: After the transport vehicle carrying the asphalt mixture is weighed in the weighing room, the second RFID reader-writer in the weighing room writes the weighing data into the RFID card.

[0009] The asphalt construction management according to the construction site includes: Feedback of abnormal data or calculation of construction costs are carried out according to the construction site.

[0010] The feedback of the abnormal data includes: receiving an actual value of a target indicator; the target indicator being one of the indicators in the working face plan; Calculating the deviation between the theoretical value of the target indicator in the working face plan and the actual value of the target indicator; If the deviation exceeds the preset deviation tolerance threshold of the target indicator, an abnormal alarm of the target indicator is triggered.

[0011] After the abnormal alarm of the target indicator is triggered, the following is also included: If any indicator in the working surface plan triggers an abnormal alarm, the construction sites involved in the same batch of asphalt mixture in the working surface plan are traced back according to the information recorded in the first RFID reader.

[0012] The calculation of construction costs includes: Obtaining a material requisition list; wherein the material requisition list is generated by the asphalt mixing plant after receiving the construction raw materials according to the received information; Calculate the material cost of each construction site based on the construction site, materials, material weight, material unit price and amount on the material requisition form; Calculate the cost of machinery and equipment based on the cost of the transport truck and the cost of the asphalt paver; The labor cost is calculated based on the labor unit price and labor working hours; the labor unit price is determined by the construction contract; the labor working hours are obtained through the clocking in and out time of the mobile phone APP.

[0013] The cost acquisition method of the transport vehicle includes: Calculation is carried out based on the transportation distance, transportation weight or transportation unit price; the transportation distance is calculated through the starting construction distance in the working surface plan and the starting and ending pile numbers of the construction site; the transportation weight is obtained by obtaining the paving time information of the construction site through the information recorded in the first RFID reader, and the sum of the weights of the asphalt mixture transported by the transport vehicles involved within the paving time range of the construction site is calculated; the transportation unit price is determined by the construction contract.

[0014] The cost acquisition method of the asphalt paver includes: The calculation is performed based on the working time of the asphalt paver and the paving unit price; the working time of the asphalt paver is obtained by obtaining the paving time of the first and last transport vehicles at the construction site through the information recorded in the first RFID reader / writer. The paving time of the first transport vehicle at the construction site is t0, and the paving time of the last transport vehicle at the construction site is t1. The time spent on paving each vehicle of asphalt mixture is l p = (t1-t0) / (total number of vehicles-1), then the working time t of the asphalt paver at the construction site is t1-t0+1 p ; The paving unit price is determined by the construction contract.

[0015] The second aspect of the present application provides an asphalt construction management device, which includes: An asphalt construction information acquisition module is used to acquire information recorded in the first RFID reader / writer after a transport vehicle equipped with an RFID card arrives at an asphalt paver equipped with a first RFID reader / writer and the asphalt paver reads the information in the RFID card through the first RFID reader / writer; the information in the RFID card includes weighing data written to the RFID card by a second RFID reader / writer in a weighing room; the weighing data includes the license plate number of the transport vehicle, information about materials transported by the transport vehicle, weight of materials transported by the transport vehicle, and weighing time information of the transport vehicle; the information recorded in the first RFID reader / writer includes the weighing data and also includes construction site information, paving time information, and paving equipment information; The asphalt construction management module is used to manage the asphalt construction according to the construction site based on the information recorded in the first RFID reader / writer.

[0016] Compared with the prior art, this application has the following beneficial effects: This application introduces RFID technology, installing RFID cards on transport vehicles, and installing RFID readers on weighing rooms and pavers. Compared with installing monitoring equipment, RFID installation is easy to implement; the RFID installation process is simpler, and there is no need to modify the settings of the monitored equipment itself; the installation cost of RFID is almost negligible, so the data collection cost is also low, and the data recorded by RFID has a small error.

[0017] The information recorded by the construction project management system can provide managers with the conditions of each construction site in a timely manner as a basis for business decision-making. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0019] Figure 1 A flowchart of an asphalt construction management method provided in an embodiment of the present application; Figure 2 A flowchart of another asphalt construction management method provided in an embodiment of the present application; Figure 3 A structural schematic diagram of an asphalt construction management device provided in an embodiment of the present application. DETAILED DESCRIPTION

[0020] As described above, most of the current asphalt information management systems are as follows: at the production end, an asphalt mixing station monitoring and management platform is built to realize the data connection between the data acquisition equipment and the mixing station console. The platform continuously collects real-time parameters in the asphalt production process through the data acquisition terminal; at the transportation end, a positioning system and temperature monitoring equipment are installed on the transport vehicle to monitor the vehicle's driving trajectory and temperature changes in real time; at the construction end, monitoring equipment is installed on the paver to monitor the paver's operating status and paving thickness in real time. By installing monitoring equipment at asphalt mixing plants, transport vehicles, and pavers, although the construction quality is guaranteed and the quality can be traced, there are problems with the complex installation process and high installation costs in the actual construction process.

[0021] In view of the above problems, the inventor has proposed a method and device for asphalt construction management after research. This application introduces RFID technology, installs RFID cards on transport vehicles, installs RFID readers on weighing rooms and paver machines, and after the transport vehicle equipped with RFID cards arrives at the asphalt paver equipped with the first RFID reader, and the asphalt paver reads the information in the RFID card through the first RFID reader, it obtains the information recorded in the first RFID reader; based on the information recorded in the first RFID reader, asphalt construction management is performed according to the construction site. Compared with installing monitoring equipment, RFID technology has obvious advantages, it is simple and easy to use and has low cost.

[0022] The method and device proposed in this application are applied to the construction project management system. RFID technology is used to realize the information interaction between the construction project management system and RFID cards, RFID readers, transport vehicles, weighing rooms and asphalt pavers. Through information interaction, the purpose of asphalt construction management according to the construction site is achieved.

[0023] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0024] See also Figure 1 , which is a flow chart of an asphalt construction management method provided in an embodiment of the present application. Figure 1 As shown, the method comprises the following steps: S101. After a transport vehicle equipped with an RFID card arrives at an asphalt paver equipped with a first RFID reader / writer, and the asphalt paver reads information in the RFID card through the first RFID reader / writer, the information recorded in the first RFID reader / writer is obtained.

[0025] Among them, the information in the RFID card includes the weighing data written to the RFID card by the second RFID reader in the weighing room; the weighing data includes the license plate number of the transport vehicle, the material information transported by the transport vehicle, the weight of the material transported by the transport vehicle and the weighing time information of the transport vehicle; the information recorded in the first RFID reader includes the weighing data, and also includes construction site information, paving time information and paving equipment information.

[0026] An RFID card is a small tag with a microchip and an antenna that can store information and be read without physical contact; an RFID reader is a device that can transmit signals and communicate with an RFID card. It can read the information from the RFID card and transmit the information to the control system.

[0027] The transport vehicle is equipped with an RFID card, the asphalt paver is equipped with a first RFID reader-writer, and the weighing room is equipped with a second RFID reader-writer. After the transport vehicle is weighed in the weighing room, the second RFID reader-writer will write the weighing data into the RFID card, and the weighing data includes the license plate number of the transport vehicle, the material information transported by the transport vehicle, the weight of the material transported by the transport vehicle, and the weighing time information of the transport vehicle; when the transport vehicle arrives at the asphalt paving site, the first RFID reader-writer reads the information of the RFID card, so the information recorded by the first RFID reader-writer includes the weighing data of the transport vehicle, and also includes the construction site information, paving time information and paving equipment information recorded by the first RFID reader-writer.

[0028] S102: Based on the information recorded in the first RFID reader / writer, asphalt construction management is performed according to the construction site.

[0029] Summarize the acquired information and put the information of the same construction site together to facilitate subsequent analysis and management.

[0030] By introducing RFID technology, installing RFID cards on transport vehicles, and installing RFID readers on weighing rooms and pavers, construction management personnel can accurately grasp the situation of each construction site and adjust resource allocation in a timely manner to improve construction efficiency and quality.

[0031] See also Figure 2 , which is a flow chart of another asphalt construction management method provided in the embodiment of the present application. Figure 2As shown, the method comprises the following steps: S201. Before asphalt construction, establish a working surface plan.

[0032] The construction worker registers the working surface plan for asphalt construction and approves it. The working surface plan includes information such as starting construction distance, construction location, starting and ending pile numbers of the construction location, designed paving area, designed paving thickness, designed paving density and calculated theoretical material usage.

[0033] Starting construction distance: records the distance from the asphalt mixing plant to the starting position of the working surface for paving. It is used to calculate the transportation distance of each transport vehicle in the future.

[0034] Construction location: A conceptual description of the specific construction location. Depending on factors such as the project management level and the actual construction environment, the construction location can be coarse or fine. The labor, machinery, material and other costs consumed can be calculated based on the construction location dimension.

[0035] Construction site start and end pile numbers: refers to the pile numbers marked at the start and end of a section of road or engineering project. These pile numbers are used to identify the start and end points of a specific road section or project. For example, K3+000~K4+200 means that the starting point of the construction site is 3000 meters of the highway and the end point is 4200 meters. The transportation distance of the vehicle is subsequently calculated in combination with the starting construction distance.

[0036] Designed paving area, designed paving thickness, designed paving density and calculated theoretical total material weight: used to record the area, thickness and material quantity when designing the drawing. Used for subsequent comparative analysis with actual values.

[0037] S202. After receiving the approved working surface plan, the asphalt mixing station will collect the raw materials and fill out the material collection form, and load the asphalt mixture after asphalt mixing into the transport vehicle.

[0038] Wherein, the transport vehicle is equipped with an RFID card.

[0039] The material requisition list contains information such as the construction site, materials, material weight and asphalt mixing time. This information is used to subsequently calculate the material consumption cost at the construction site.

[0040] S203, the transport vehicle is weighed in the weighing room, and after the weighing is completed, the weighing data is written into the RFID card of the transport vehicle through the second RFID reader / writer installed in the weighing room.

[0041] The weighing data includes the license plate number of the transport vehicle, information about the materials transported by the transport vehicle, the weight of the materials transported by the transport vehicle, and information about the weighing time of the transport vehicle.

[0042] S204: When the transport vehicle arrives at the asphalt paver to unload, the first RFID reader installed in the asphalt paver reads the information of the RFID card of the transport vehicle, and manages the construction site based on the information recorded by the first RFID reader.

[0043] The information recorded in the first RFID reader / writer includes the weighing data, as well as construction site information, paving time information and paving equipment information. The first RFID reader / writer transmits the recorded information to the project management system for storage. The asphalt paving information stored in the project management system is shown in Table 1.

[0044] Table 1 Example of asphalt paving record

[0045] Asphalt construction management is carried out according to the construction site, including feedback of abnormal data or calculation of construction costs.

[0046] The feedback of the abnormal data includes: receiving an actual value of a target indicator; the target indicator being one of the indicators in the working face plan; Calculating the deviation between the theoretical value of the target indicator in the working face plan and the actual value of the target indicator; If the deviation exceeds the preset deviation tolerance threshold of the target indicator, an abnormal alarm of the target indicator is triggered.

[0047] By comparing and analyzing the indicators included in the working face plan, the asphalt construction situation can be effectively identified and feedback can be provided.

[0048] For example, the paving area: The asphalt paving area is calculated based on the design, width and length of the road. This calculation provides a theoretical value, and the actual paving area is adjusted according to the specific engineering design and construction requirements. The actual paving area is recorded in the system during on-site construction and compared with the designed paving area in the working surface plan. The system can be set to trigger an alarm if the deviation between the actual paving area and the designed paving area in the working surface plan exceeds the preset tolerance threshold.

[0049] Another example is paving density: the density of asphalt mixture has a direct impact on the quality and service life of the road. Too low density of asphalt mixture may cause the road surface to be easily damaged, while too high density will increase the difficulty of construction. Therefore, in the process of road asphalt construction, it is very important to strictly control the density of asphalt mixture to ensure the quality of the road surface. The actual paving density is obtained through core sampling test during on-site construction and registered in the system, and compared with the designed paving density in the working surface plan. If the deviation between the designed paving density in the working surface plan and the actual paving density exceeds the preset tolerance threshold, it indicates that there may be quality problems, triggering an alarm reminder.

[0050] Another example is paving thickness: the correct paving thickness is an important factor in ensuring the quality and service life of asphalt pavement. When constructing asphalt pavement, it is necessary to strictly follow the specifications for design and construction to ensure the quality and safety of the pavement. The paving thickness of the asphalt pavement cannot be too thick or too thin. If the paving thickness is too thick, the asphalt mixture cannot be compacted evenly, and defects and cracks are easily formed, affecting the quality and service life of the pavement; if the paving thickness is too thin, it cannot provide the necessary bearing capacity and flatness of the pavement. The actual paving thickness is generally taken as the average thickness, which can be calculated according to the formula: average thickness = actual paving total weight / actual paving area. The actual paving thickness is compared with the designed paving thickness in the working surface plan. If the deviation exceeds the preset tolerance threshold, it indicates that there may be quality problems, triggering an alarm reminder.

[0051] And the total weight of materials used: the actual total weight of materials used can be obtained by summarizing the data in the asphalt paving record sheet and compared with the theoretical total weight of materials used in the working surface plan.

[0052] Take the total weight of materials as an example, and set the tolerance threshold of deviation to 5%. In the work surface plan, the theoretical total weight of materials for the construction site "North District Asphalt Concrete Road (K8+380~K8+480)" is set to 66 tons, and the actual total weight of materials for the construction site in the asphalt paving record table is 60 tons. (Actual total weight of materials - theoretical total weight of materials) / theoretical total weight of materials * 100% = (66-60) / 60 * 100% = 10% > 5%, then the abnormal alarm is triggered.

[0053] After the abnormal alarm of the target indicator is triggered, the following is also included: If any indicator in the working surface plan triggers an abnormal alarm, the construction sites involved in the same batch of asphalt mixture in the working surface plan are traced back according to the information recorded in the first RFID reader.

[0054] Taking construction site A as an example, if there is a quality problem in construction site A, the weighing time T1 of each transport vehicle can be found through the asphalt paving record sheet. The two most recent asphalt mixing times T2 and T3 that are less than time T1 and the corresponding transport vehicles C1 and C2 can be found at the asphalt mixing station through the weighing time T1. Then, the asphalt paving record sheet can be used to query the construction site B corresponding to the most recent record whose transport vehicles are C1 and C2 and whose weighing times are greater than T2 and T3. In this case, the quality of construction site B may also have problems.

[0055] The calculation of construction costs includes: Calculate the material cost of each construction site based on the construction site, materials, material weight, material unit price and amount on the material requisition form; Calculate the cost of machinery and equipment based on the cost of the transport truck and the cost of the asphalt paver; The labor cost is calculated based on the labor unit price and labor working hours; the labor unit price is determined by the construction contract; the labor working hours are obtained through the clocking in and out time of the mobile phone APP.

[0056] The cost acquisition method of the transport vehicle includes: calculating according to the transport distance, transport weight or transport unit price; the transport distance is calculated by the starting construction distance in the working surface plan and the starting and ending pile numbers of the construction site; the transport weight is obtained by obtaining the paving time information of the construction site through the information recorded in the first RFID reader, and calculating the sum of the weights of the asphalt mixture transported by the transport vehicles involved within the paving time range of the construction site; the transport unit price is determined by the construction contract.

[0057] The cost acquisition method of the asphalt paver includes: calculating according to the working time of the asphalt paver and the paving unit price; the working time of the asphalt paver is obtained by the information recorded in the first RFID reader-writer, and the paving time of the first transport vehicle and the last transport vehicle at the construction site is t0, and the paving time of the last transport vehicle at the construction site is t1, then the time spent on paving each vehicle of asphalt mixture is l p = (t1-t0) / (total number of vehicles-1), then the working time t of the asphalt paver at the construction site is t1-t0+1 p ; The paving unit price is determined by the construction contract.

[0058] By introducing RFID technology, RFID cards are installed on transport vehicles, and RFID readers are installed on weighing rooms and pavers. When the paving of each construction site is completed, the labor, machine and material costs of each construction site can be calculated and provided to managers in a timely manner as a basis for business decisions; early warnings can be triggered based on data such as the deviation threshold of theoretical and actual materials, and relevant personnel can be notified in a timely manner; the quality of asphalt construction can be traced. If there is a problem with the asphalt quality of a construction site, all construction sites where the same batch of asphalt has been paved can be traced back based on the records; the installation cost of RFID is almost negligible, the data collection cost is low, and the collected data has small errors.

[0059] Based on the asphalt construction management method introduced in the above embodiments, the present application also provides an asphalt construction management device accordingly. Figure 3 Figure 1 is a schematic diagram of the structure of the device. Figure 3 As shown, the asphalt construction management device includes: Asphalt construction information acquisition module 301: used for acquiring information recorded in the first RFID reader / writer after a transport vehicle equipped with an RFID card arrives at an asphalt paver equipped with a first RFID reader / writer and the asphalt paver reads the information in the RFID card through the first RFID reader / writer; the information in the RFID card includes weighing data written to the RFID card by a second RFID reader / writer in a weighing room; the weighing data includes the license plate number of the transport vehicle, information about materials transported by the transport vehicle, weight of materials transported by the transport vehicle, and weighing time information of the transport vehicle; the information recorded in the first RFID reader / writer includes the weighing data and also includes construction site information, paving time information, and paving equipment information; Asphalt construction management module 302: used to manage asphalt construction according to construction sites based on the information recorded in the first RFID reader / writer.

[0060] In an optional implementation, the asphalt construction management device further includes a working surface plan building module, which is used to build a working surface plan for the construction site. The working surface plan building module is used to: Before asphalt construction, determine the starting construction distance, construction location and starting and ending pile numbers of the construction location; Generate the paving area, paving density and paving thickness through the starting construction distance, the construction site and the starting and ending pile numbers of the construction site; Calculate the theoretical total weight of materials according to the paving area, the paving density and the paving thickness; A working surface plan is constructed using the starting construction distance, the construction site, the starting and ending pile numbers of the construction site, the paving area, the paving thickness, the paving density and the theoretical total material weight, and the working surface plan is sent to the asphalt mixing station so that the asphalt mixing station can collect construction raw materials according to the received information and load the asphalt mixture after mixing the raw materials into the transport vehicle.

[0061] The second RFID reader / writer in the weighing room in the asphalt construction information acquisition module writes the weighing data to the RFID card, which is specifically used for: After the transport vehicle carrying the asphalt mixture is weighed in the weighing room, the second RFID reader-writer in the weighing room writes the weighing data into the RFID card.

[0062] The asphalt construction management module includes an abnormal data feedback module and a construction cost accounting module. The abnormal data feedback module is used to feedback abnormal data according to the construction site, and the construction cost accounting module is used to calculate the construction cost according to the construction site.

[0063] The abnormal data feedback module is specifically used for: receiving an actual value of a target indicator; the target indicator being one of the indicators in the working face plan; Calculating the deviation between the theoretical value of the target indicator in the working face plan and the actual value of the target indicator; If the deviation exceeds the preset deviation tolerance threshold of the target indicator, an abnormal alarm of the target indicator is triggered.

[0064] Optionally, the asphalt construction management device further includes a tracing module, which is used to: If any indicator in the working surface plan triggers an abnormal alarm, the construction sites involved in the same batch of asphalt mixture in the working surface plan are traced back according to the information recorded in the first RFID reader.

[0065] The construction cost accounting module is specifically used for: Obtaining a material requisition list; wherein the material requisition list is generated by the asphalt mixing plant after receiving the construction raw materials according to the received information; Calculate the material cost of each construction site based on the construction site, materials, material weight, material unit price and amount on the material requisition form; Calculate the cost of machinery and equipment based on the cost of the transport truck and the cost of the asphalt paver; The labor cost is calculated based on the labor unit price and labor working hours; the labor unit price is determined by the construction contract; the labor working hours are obtained through the clocking in and out time of the mobile phone APP.

[0066] The cost acquisition method of the transport vehicle includes: Calculation is carried out based on the transportation distance, transportation weight or transportation unit price; the transportation distance is calculated through the starting construction distance in the working surface plan and the starting and ending pile numbers of the construction site; the transportation weight is obtained by obtaining the paving time information of the construction site through the information recorded in the first RFID reader, and the sum of the weights of the asphalt mixture transported by the transport vehicles involved within the paving time range of the construction site is calculated; the transportation unit price is determined by the construction contract.

[0067] The cost acquisition method of the asphalt paver includes: The calculation is performed based on the working time of the asphalt paver and the paving unit price; the working time of the asphalt paver is obtained by obtaining the paving time of the first and last transport vehicles at the construction site through the information recorded in the first RFID reader / writer. The paving time of the first transport vehicle at the construction site is t0, and the paving time of the last transport vehicle at the construction site is t1. The time spent on paving each vehicle of asphalt mixture is l p = (t1-t0) / (total number of vehicles-1), then the working time t of the asphalt paver at the construction site is t1-t0+1 p ; The paving unit price is determined by the construction contract.

[0068] It should be noted that each embodiment in this specification is described in a progressive manner, and the same or similar parts between the embodiments can be referred to each other, and each embodiment focuses on the differences from other embodiments. In particular, for the device embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment. The device embodiment described above is merely schematic, in which the unit described as a separate component may or may not be physically separated, and the component prompted as a unit may or may not be a physical unit, that is, it may be located in one place, or it may be distributed on multiple network units. Some or all of the modules can be selected according to actual needs to achieve the purpose of the scheme of this embodiment. Ordinary technicians in this field can understand and implement it without paying creative work.

[0069] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed in the present application should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.

Claims

1. An asphalt construction management method, characterized in that: The method is applied to a construction project management system, and the method comprises: After a transport vehicle equipped with an RFID card arrives at an asphalt paver equipped with a first RFID reader / writer, and the asphalt paver reads the information in the RFID card through the first RFID reader / writer, the information recorded in the first RFID reader / writer is obtained; wherein the information in the RFID card includes the weighing data written to the RFID card by the second RFID reader / writer in the weighing room; the weighing data includes the license plate number of the transport vehicle, the material information transported by the transport vehicle, the weight of the material transported by the transport vehicle, and the weighing time information of the transport vehicle; the information recorded in the first RFID reader / writer includes the weighing data and also includes the construction site information, the paving time information, and the paving equipment information; Based on the information recorded in the first RFID reader / writer, asphalt construction management is performed according to the construction site.

2. The method according to claim 1, characterized in that: Also includes: Before asphalt construction, determine the starting construction distance, construction location and starting and ending pile numbers of the construction location; Generate the paving area, paving density and paving thickness through the starting construction distance, the construction site and the starting and ending pile numbers of the construction site; Calculate the theoretical total weight of materials according to the paving area, the paving density and the paving thickness; A working surface plan is constructed using the starting construction distance, the construction site, the starting and ending pile numbers of the construction site, the paving area, the paving thickness, the paving density and the theoretical total material weight, and the working surface plan is sent to the asphalt mixing station so that the asphalt mixing station can collect construction raw materials according to the received information and load the asphalt mixture after mixing the raw materials into the transport vehicle.

3. The method according to claim 2, characterized in that The second RFID reader / writer in the weighing room writes the weighing data into the RFID card, including: After the transport vehicle carrying the asphalt mixture is weighed in the weighing room, the second RFID reader-writer in the weighing room writes the weighing data into the RFID card.

4. The method according to claim 2, characterized in that: The asphalt construction management according to the construction site includes: Feedback of abnormal data or calculation of construction costs are carried out according to the construction site.

5. The method according to claim 4, characterized in that The feedback of the abnormal data includes: receiving an actual value of a target indicator; the target indicator being one of the indicators in the working face plan; Calculating the deviation between the theoretical value of the target indicator in the working face plan and the actual value of the target indicator; If the deviation exceeds the preset deviation tolerance threshold of the target indicator, an abnormal alarm of the target indicator is triggered.

6. The method according to claim 5, characterized in that After the abnormal alarm of the target indicator is triggered, the following is also included: If any indicator in the working surface plan triggers an abnormal alarm, the construction sites involved in the same batch of asphalt mixture in the working surface plan are traced back according to the information recorded in the first RFID reader.

7. The method according to claim 4, characterized in that The calculation of construction costs includes: Obtaining a material requisition list; wherein the material requisition list is generated by the asphalt mixing plant after receiving the construction raw materials according to the received information; Calculate the material cost of each construction site based on the construction site, materials, material weight, material unit price and amount on the material requisition form; Calculate the cost of machinery and equipment based on the cost of the transport truck and the cost of the asphalt paver; The labor cost is calculated based on the labor unit price and labor working hours; the labor unit price is determined by the construction contract; the labor working hours are obtained through the clocking in and out time of the mobile phone APP.

8. The method according to claim 7, characterized in that The cost acquisition method of the transport vehicle includes: Calculation is carried out based on the transportation distance, transportation weight or transportation unit price; the transportation distance is calculated through the starting construction distance in the working surface plan and the starting and ending pile numbers of the construction site; the transportation weight is obtained by obtaining the paving time information of the construction site through the information recorded in the first RFID reader, and the sum of the weights of the asphalt mixture transported by the transport vehicles involved within the paving time range of the construction site is calculated; the transportation unit price is determined by the construction contract.

9. The method according to claim 7, characterized in that: The cost acquisition method of the asphalt paver includes: The calculation is performed based on the working time of the asphalt paver and the paving unit price; the working time of the asphalt paver is obtained by obtaining the paving time of the first and last transport vehicles at the construction site through the information recorded in the first RFID reader / writer. The paving time of the first transport vehicle at the construction site is t0, and the paving time of the last transport vehicle at the construction site is t1. The time spent on paving each vehicle of asphalt mixture is l p = (t1-t0) / (total number of vehicles-1), then the working time t of the asphalt paver at the construction site is t1-t0+1 p ; The paving unit price is determined by the construction contract.

10. An asphalt construction management device, characterized in that: The device is applied to a construction project management system, and the device comprises: An asphalt construction information acquisition module is used to acquire information recorded in the first RFID reader / writer after a transport vehicle equipped with an RFID card arrives at an asphalt paver equipped with a first RFID reader / writer and the asphalt paver reads the information in the RFID card through the first RFID reader / writer; the information in the RFID card includes weighing data written to the RFID card by a second RFID reader / writer in a weighing room; the weighing data includes the license plate number of the transport vehicle, information about materials transported by the transport vehicle, weight of materials transported by the transport vehicle, and weighing time information of the transport vehicle; the information recorded in the first RFID reader / writer includes the weighing data and also includes construction site information, paving time information, and paving equipment information; The asphalt construction management module is used to manage the asphalt construction according to the construction site based on the information recorded in the first RFID reader / writer.

Citation Information

Patent Citations

  • Acquisition and test method of bituminous mixture transport time period

    CN106228216A

  • Asphalt mixing production construction process monitoring system based on Internet of Things

    CN111679638A

  • Paver haul truck grouping

    US20200219400A1

Cited By

  • Asphalt paving temperature monitoring method and system

    CN119374743A