Method and device for determining equipment capacity in power generation system

By optimizing the output power and operating costs of wind turbines, photovoltaic power stations, heat storage systems and pumped storage systems, and using particle swarm algorithm to determine the equipment capacity, the problem of difficult to meet power demand and increase costs in the existing technology is solved. , achieving more accurate and economical capacity configuration.

CN118920588APending Publication Date: 2024-11-08华电福新周宁抽水蓄能有限公司 +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411120091.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-15
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

When determining the equipment capacity, existing power generation systems are difficult to effectively coordinate wind power generation, photovoltaic power generation, heat storage systems and pumped storage systems, resulting in the inability to meet power demand and increase costs.

Method used

By determining the output power and operating costs of wind turbines, photovoltaic power plants, heat storage systems and pumped storage systems, and optimizing equipment capacity in combination with particle swarm algorithms to ensure that costs are reduced while meeting power demands.

Benefits of technology

It achieves a more accurate and reasonable determination of equipment capacity, reduces sampling points that do not meet power requirements, and reduces the total cost of the power generation system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118920588A_ABST
    Figure CN118920588A_ABST
Patent Text Reader

Abstract

The invention discloses a method and device for determining equipment capacity in a power generation system, and relates to the field of electric power, and the method comprises the steps: determining the operation power of a heat storage system and the operation power of a pumped storage system according to the output power of a wind driven generator, the output power of a photovoltaic power station and the load demand of a power grid; determining the operation cost of each device in the power generation system, wherein the sum of the operation cost of each device and the initial cost is the total cost of the power generation system; determining the proportion of the sampling points which do not meet the power demand in the preset time to the total sampling points; and when the proportion and the cost reach the minimum value, the capacity of the wind driven generator, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system are determined. In the process of determining the capacity of the wind driven generator, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system, sampling points which do not meet the power requirement are reduced, the cost of a power generation system is reduced, and the capacity of the equipment is determined more accurately and reasonably.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of power generation systems, and in particular to a method and a device for determining equipment capacity in a power generation system. Background Art

[0002] In recent years, the randomness and intermittency of solar and wind energy have made the combination of renewable energy and energy storage technology an inevitable trend. Pumped storage is currently the most widely used energy storage method in the power grid, but its capacity is limited by geographical conditions and cannot meet the storage of electrical energy. Therefore, hybrid renewable energy systems based on the complementary characteristics of renewable energy are increasingly attracting people's attention. The system can coordinate multiple forms of renewable energy generation, achieve complementary power generation, and reduce adverse effects on the power grid. Capacity optimization is the key to the design of hybrid renewable energy systems and the basis for optimized scheduling. Summary of the invention

[0003] The purpose of the present invention is to provide a method and device for determining the capacity of equipment in a power generation system. In the process of determining the capacity of a wind turbine, the capacity of a photovoltaic power station, the capacity of a heat storage system and the capacity of a pumped storage system, not only the sampling points that do not meet the power demand are reduced, but also the cost of the power generation system is reduced, and the capacity of the equipment is determined more accurately and reasonably.

[0004] In order to solve the above technical problems, the present invention provides a method for determining the capacity of equipment in a power generation system, comprising:

[0005] Determine the output power of the wind turbines in the wind farm and the output power of the photovoltaic power station;

[0006] Determining the operating power of the heat storage system and the operating power of the pumped storage system according to the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid;

[0007] Determine the operating cost of the wind turbine, the operating cost of the photovoltaic power station, the operating cost of the heat storage system and the operating cost of the pumped storage system according to the output power of the wind turbine, the output power of the photovoltaic power station, the operating power of the heat storage system and the operating power of the pumped storage system;

[0008] determining the cost of the power generation system according to the initial cost, the operating cost of the wind turbine, the operating cost of the photovoltaic power station, the operating cost of the heat storage system and the operating cost of the pumped storage system, wherein the initial cost is positively correlated with the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system;

[0009] Determine the proportion of sampling points whose electricity demand is not met within a preset time to the total sampling points;

[0010] When the ratio and the cost both reach minimum values, the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system are determined.

[0011] On the other hand, the output power of the wind turbine generators and the output power of the photovoltaic power station in the wind farm are determined, including:

[0012] Determine the output power of the wind turbine generator of the wind farm. The expression of the output power of the wind turbine generator is: ;

[0013] Among them, P wind is the output power of the wind turbine, the v i is the cut-in wind speed of the wind turbine, v o is the cut-out wind speed of the wind turbine, v r is the rated wind speed of the wind turbine, v is the real-time wind speed, and Pr is the rated power of the wind turbine;

[0014] Determine the output power of the photovoltaic power station. The expression of the output power of the photovoltaic power station is: ;

[0015] Among them, P pv is the output power of the photovoltaic power station, P STC is the maximum output power of the photovoltaic power station under standard test conditions, β T is the temperature coefficient, T1 is the surface operating temperature of the photovoltaic cells of the photovoltaic power station, , T amb is the ambient temperature, T STC is the surface temperature of the photovoltaic cell under standard test conditions, I is the solar illumination intensity, and I STC is the sunlight intensity under standard test conditions.

[0016] On the other hand, the operating power of the heat storage system and the operating power of the pumped storage system are determined according to the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid, including:

[0017] When the battery is charged, the electric energy stored in the battery is determined to be ;

[0018] When the battery is discharged, the electric energy stored in the battery is determined to be ;

[0019] Among them, E bat (t) is the electric energy stored in the battery at time t, E bat(t-1) is the electric energy stored in the battery at time t-1, is the self-discharge rate of the battery, P bat,c (t) is the charging power of the battery at time t, η bat,c is the charging efficiency of the battery, P bat,d (t) is the discharge power of the battery at time t, η bat,d is the discharge efficiency of the battery;

[0020] The expression for determining the heat storage model is: and ;

[0021] The heat storage system includes a cold tank, a hot tank and a heat transfer medium, M is the instantaneous mass of the heat transfer medium, m i is the net inlet flow rate of the heat storage system, m o is the net outlet flow of the heat storage system, C p is the specific heat capacity of the heat transfer medium, T2 is the instantaneous temperature of the heat transfer medium, T h is the inlet temperature of the heat transfer medium, (UA) t is the total heat loss coefficient of the heat outlet pipe at time t;

[0022] The expression for the electric potential to water potential conversion module of the pumped storage system is determined as follows: and ;

[0023] The expression for the water potential to electric potential conversion module of the pumped storage system is determined as follows: and ;

[0024] The electric potential to water potential conversion model includes an electric potential to water potential conversion module and a water potential to electric potential conversion module. i (t) is the water pumping capacity of the water pump at time t, E p (t) is the grid load demand at time t, ρ is the water density, g is the gravity coefficient, h is the average water head, η p is the efficiency of the water pump, η m is the efficiency of the motor, η pipe is the efficiency of the pipeline, E g (t) is the output power of the turbine at time t, W o (t) is the water consumption at time t, η tr is the efficiency of the turbine, η nr is the efficiency of the generator;

[0025] The operating power of the heat storage system and the operating power of the pumped storage system are determined based on the electric energy stored in the battery, the heat storage model of the heat storage system, the electric potential-water potential conversion model of the pumped storage system, the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid.

[0026] On the other hand, when the wind turbine, the photovoltaic power station, the storage battery and the pumped storage system work together, the operating power of the pumped storage system is determined according to the electric energy stored in the storage battery, the electric potential-water potential conversion model of the pumped storage system, the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid, including:

[0027] The net load of the power grid is determined according to the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid. , d p (i) is the net load of the power grid at time i, p r (i) is the load demand of the power grid at time i, p w (i) is the output power of the wind turbine generator at time i, p v (i) is the output power of the photovoltaic power station at time i;

[0028] When the net load is less than 0 and When the pumped storage system is saturated, the pumped storage system is preferentially controlled to store electric energy, and the battery is used to store energy when the pumped storage system is saturated;

[0029] When the net load is less than 0 and When the battery is used for energy storage, the battery is preferably used for energy storage;

[0030] When the net load is less than 0 and When the power is stored in the battery and pumped storage system, the remaining power that cannot be consumed is discarded;

[0031] When the net load is greater than 0 and When the load demand is met, the pumped storage system is used for power supply first. If the load demand cannot be met and the energy stored in the battery is greater than the minimum state of charge, the battery will continue to supply power.

[0032] When the net load is greater than 0 and When using, battery power supply is preferred;

[0033] When the net load is greater than 0 and When the power is supplied by batteries and pumped storage systems,

[0034] Wherein, n is the energy storage capacity of the pumped storage system, η p is the operating efficiency of the pump, ηc is the charging efficiency of the battery, η g is the power generation efficiency of the turbine, η d is the discharge efficiency of the battery, and b is the energy storage capacity of the battery;

[0035] The operating power of the pumped-storage system is determined when the pumped-storage system is storing energy or supplying power.

[0036] On the other hand, when the wind turbine, the photovoltaic power station, the storage battery and the heat storage system work together, the operating power of the heat storage system is determined according to the electric energy stored in the storage battery, the heat storage model of the heat storage system, the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid, including:

[0037] The net load of the power grid is determined according to the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid. , d p (i) is the net load of the power grid at time i, p r (i) is the load demand of the power grid at time i, p w (i) is the output power of the wind turbine generator at time i, p v (i) is the output power of the photovoltaic power station at time i;

[0038] When the net load is less than 0 and When the electric energy is converted into heat energy by an electric heater, the electric energy is stored in the heat storage system, and the remaining electric energy that cannot be consumed is discarded;

[0039] When the net load is less than 0 and When the current energy storage space of the battery is greater than the energy storage capacity, the battery is used to store energy, otherwise the heat storage system is used to store energy;

[0040] When the net load is greater than 0 and When the load demand is not met, the heat storage system is used to supply power. If the power stored in the battery is greater than the minimum state of charge, the battery is used to supply power.

[0041] When the net load is greater than 0 and When the battery is used for power supply;

[0042] When the net load is greater than 0 and When the battery and the heat storage system are used to supply power together;

[0043] Wherein, m is the energy storage capacity of the heat storage system, η e is the operating efficiency of the electric heater of the heat storage system, η sis the charging efficiency of the power generation module of the thermal storage system;

[0044] The operating power of the pumped storage system is determined when the thermal storage system stores energy or supplies electricity.

[0045] On the other hand, the cost of the power generation system is determined according to the operating cost of the wind turbine, the operating cost of the photovoltaic power station, the operating cost of the thermal storage system, the operating cost of the pumped storage system and the initial cost, including:

[0046] The cost expression of the power generation system is determined based on the operating cost of the wind turbine, the operating cost of the photovoltaic power station, the operating cost of the heat storage system, the operating cost of the pumped storage system and the initial cost: ,IC w =ic w *x w ,IC pv =ic pv *x pv ,IC csp =ic csp *x csp ,IC w =ic phs *x phs , A.C. w =om w *P w , A.C. pv =om pv *P pv , A.C. csp =om csp *P csp , A.C. phs =om phs *P phs ;

[0047] Among them, IC w is the initial cost of the wind turbine, ic w is the unit investment cost of the wind turbine, x w is the equipment capacity of the wind turbine, IC pv is the initial cost of the photovoltaic power station, ic pv is the unit investment cost of the photovoltaic power station, x pv is the equipment capacity of the photovoltaic power station, IC csp is the initial cost of the thermal storage system, ic csp is the unit investment cost of the thermal storage system, x csp is the equipment capacity of the thermal storage system, IC phs is the initial cost of the pumped storage system, ic phsis the unit investment cost of the pumped storage system, x phs is the equipment capacity of the pumped storage system, AC w is the operating cost of the wind turbine, om w is the unit operating cost of the wind turbine, P w is the operating power of the wind turbine, AC pv is the operating cost of the photovoltaic power station, om pv is the unit operating cost of the photovoltaic power station, P pv is the operating power of the photovoltaic power station, AC csp is the operating cost of the thermal storage system, om csp is the unit operating cost of the heat storage system, P csp is the operating power of the thermal storage system, AC phs is the operating cost of the pumped storage system, om phs is the unit operating cost of the pumped storage system, P phs is the operating power of the pumped storage system, E sys is the annual power generation of the power generation system, d sys is the decay rate, i is the discount rate, N is the maximum life cycle, and ni is the life cycle.

[0048] On the other hand, the proportion of sampling points with unsatisfied electricity demand within a preset time to the total sampling points is determined, including:

[0049] Determine the proportion of sampling points that do not meet power demand within the preset time to the total sampling points ;

[0050] Among them, P1(t) is the power load of the sampling point at time t, P w (t) is the output power of the wind turbine generator at time t, P pv (t) is the output power of the photovoltaic power station at time t, P csp (t) is the output power of the heat storage system at time t, P phs (t) is the output power of the pumped storage system at time t, and m1 is the number of sampling points that meet the load.

[0051] On the other hand, when the ratio and the cost reach a minimum value, determining the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system includes:

[0052] Determine the expression of the first objective function as ;

[0053] The expression of the second objective function is determined as ;

[0054] Using a particle swarm algorithm to determine a minimum value of the first objective function and a minimum value of the second objective function, when the first objective function and the second objective function reach a minimum value, the proportion and the cost reach a minimum value;

[0055] in, For the The cost of the scenario, In the The proportion of the scene, C w is the capacity of the wind turbine, Cpv is the capacity of the photovoltaic power station, C BS is the capacity of the heat storage system, C PHS is the capacity of the battery, C PES is the capacity of the pumped storage system.

[0056] On the other hand, when the ratio and the cost reach a minimum value, determining the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system includes:

[0057] When the ratio and the cost reach a minimum and the heat storage system constraint, the battery constraint and the pumped storage system constraint are satisfied, determining the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system;

[0058] The heat storage system constraint is and , the battery constraint is , the pumped storage system constraints ;

[0059] is the minimum storage capacity of the thermal storage system, is the storage capacity of the thermal storage system at time t, is the maximum storage capacity of the thermal storage system, is the minimum output power of the thermal storage system, is the output power of the heat storage system at time t, is the maximum output power of the thermal storage system, DOD is the depth of discharge of the battery, The maximum electrical energy stored in the battery, is the electrical energy stored in the battery at time t, is the minimum water storage capacity of the reservoir, is the reservoir capacity, The maximum water storage capacity of the reservoir.

[0060] In order to solve the above technical problems, the present invention further provides a device for determining equipment capacity in a power generation system, which is characterized by comprising:

[0061] Memory for storing computer programs;

[0062] A processor is used to implement the steps of the method for determining the equipment capacity in the above-mentioned power generation system when executing the computer program.

[0063] The present invention discloses a method and device for determining the capacity of equipment in a power generation system, which relates to the field of electric power, including: determining the operating power of a heat storage system and the operating power of a pumped storage system according to the output power of a wind turbine, the output power of a photovoltaic power station and the load demand of a power grid; then determining the operating cost of each device in the power generation system, the sum of the operating cost of each device and the initial cost being the total cost of the power generation system; determining the proportion of sampling points that do not meet the power demand within a preset time to the total sampling points; when both the proportion and the cost reach a minimum value, determining the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system. In the process of determining the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system, not only the sampling points that do not meet the power demand are reduced, but also the cost of the power generation system is reduced, and the capacity of the equipment is determined more accurately and reasonably. BRIEF DESCRIPTION OF THE DRAWINGS

[0064] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the prior art and the drawings required for use in the embodiments are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0065] Figure 1 A flow chart of a method for determining equipment capacity in a power generation system provided by the present invention;

[0066] Figure 2 A schematic diagram of the structure of a power generation system provided by the present invention;

[0067] Figure 3 A schematic structural diagram of another power generation system provided by the present invention;

[0068] Figure 4 A schematic structural diagram of a device for determining equipment capacity in a power generation system provided by the present invention. DETAILED DESCRIPTION

[0069] The core of the present invention is to provide a method and device for determining the capacity of equipment in a power generation system. In the process of determining the capacity of wind turbines, photovoltaic power stations, heat storage systems and pumped storage systems, not only the sampling points that do not meet the power demand are reduced, but also the cost of the power generation system is reduced, and the capacity of the equipment is determined more accurately and reasonably.

[0070] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0071] Figure 1 A flow chart of a method for determining equipment capacity in a power generation system provided by the present invention, wherein the method for determining equipment capacity in the power generation system is characterized by comprising:

[0072] S11: Determine the output power of the wind turbine generator of the wind farm and the output power of the photovoltaic power station;

[0073] S12: Determine the operating power of the heat storage system and the operating power of the pumped storage system according to the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid;

[0074] Due to the uncertainty of wind power generation and photovoltaic power generation, the current environment, such as wind speed, must be taken into account when determining the output power of wind turbines; the current environment, such as light intensity and temperature, must also be taken into account when determining the output power of photovoltaic power stations. Since the functions of the heat storage system and the pumped storage system are to store the electric energy generated by wind turbines and photovoltaic power stations, it is necessary to determine the operating power of the heat storage system and the operating power of the pumped storage system based on the output power of wind turbines, the output power of photovoltaic power stations and the load demand of the power grid. The specific operating power of the heat storage system and the operating power of the pumped storage system can be the remaining electric energy after the heat storage system and the pumped storage system store the power generated by photovoltaic power stations and wind turbines to meet the load demand of the power grid, or the heat storage system and the pumped storage system supplement the missing electric energy when the power generated by photovoltaic power stations and wind turbines does not meet the load demand of the power grid.

[0075] S13: determining the operating cost of the wind turbine, the operating cost of the photovoltaic power station, the operating cost of the heat storage system, and the operating cost of the pumped storage system according to the output power of the wind turbine, the output power of the photovoltaic power station, the operating power of the heat storage system, and the operating power of the pumped storage system;

[0076] S14: determining the cost of the power generation system according to the initial cost, the operating cost of the wind turbine, the operating cost of the photovoltaic power station, the operating cost of the heat storage system and the operating cost of the pumped storage system, wherein the initial cost is positively correlated with the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system;

[0077] It is understandable that the larger the capacity of wind turbines, photovoltaic power plants, heat storage systems and pumped storage systems, the higher the initial cost; the higher the output power of wind turbines, the output power of photovoltaic power plants, the operating power of heat storage systems and the operating power of pumped storage systems, the higher the operating cost. In order to reduce costs, it is necessary to reduce operating power and capacity, and in order to meet the load requirements of the power grid, it is necessary to increase operating power and capacity, so it is necessary to balance the two.

[0078] S15: Determine the proportion of sampling points that fail to meet power demand within a preset time to the total sampling points;

[0079] S16: When both the proportion and the cost reach minimum values, determine the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the thermal storage system, and the capacity of the pumped storage system.

[0080] If the cost is infinitely reduced, it will affect the normal operation of the power generation system, that is, there will be fewer sampling points that meet the power demand during power generation. Even if the cost is reduced, the user experience will be poor. If the proportion of sampling points that meet the power demand is increased infinitely, the cost for the power plant will increase. Therefore, when both the proportion and the cost reach the minimum value, determining the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system can better balance the relationship between cost and demand, and the final capacity will be more reasonable.

[0081] The present invention discloses a method and device for determining the capacity of equipment in a power generation system, which relates to the field of electric power, including: determining the operating power of a heat storage system and the operating power of a pumped storage system according to the output power of a wind turbine, the output power of a photovoltaic power station and the load demand of a power grid; then determining the operating cost of each device in the power generation system, the sum of the operating cost of each device and the initial cost being the total cost of the power generation system; determining the proportion of sampling points that do not meet the power demand within a preset time to the total sampling points; when both the proportion and the cost reach a minimum value, determining the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system. In the process of determining the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system, not only the sampling points that do not meet the power demand are reduced, but also the cost of the power generation system is reduced, and the capacity of the equipment is determined more accurately and reasonably.

[0082] Based on the above embodiments:

[0083] Figure 2 A schematic diagram of the structure of a power generation system provided by the present invention;

[0084] Figure 3 A schematic structural diagram of another power generation system provided by the present invention;

[0085] In some embodiments, determining the output power of the wind turbine generators of the wind farm and the output power of the photovoltaic power station includes:

[0086] Determine the output power of the wind turbine generator in the wind farm. The expression of the output power of the wind turbine generator is ;

[0087] Among them, P wind is the output power of the wind turbine, v i is the cut-in wind speed of the wind turbine, v o is the cut-out wind speed of the wind turbine, v r is the rated wind speed of the wind turbine, v is the real-time wind speed, and Pr is the rated power of the wind turbine;

[0088] Determine the output power of the photovoltaic power station. The expression of the output power of the photovoltaic power station is ;

[0089] Among them, P pv is the output power of the photovoltaic power station, P STC is the maximum output power of the photovoltaic power station under standard test conditions, β T is the temperature coefficient, T1 is the surface operating temperature of the photovoltaic cells in the photovoltaic power station, , T amb is the ambient temperature, T STC is the surface temperature of the photovoltaic cell under standard test conditions, I is the solar intensity, and I STC is the sunlight intensity under standard test conditions.

[0090] According to the rated power and wind speed uncertainty parameters of the wind turbine, the calculation of the wind turbine output power needs to take into account the cut-in wind speed and the cut-out wind speed. When the real-time wind speed is less than the cut-in wind speed and greater than the cut-out wind speed, the wind turbine will not generate electricity. Above the rated wind speed, the wind turbine output power will not exceed the rated power. The output power of photovoltaic cells is mainly related to solar radiation and temperature.

[0091] Specifically, the application will obtain environmental data under multiple scenarios, namely real-time wind speed and solar temperature, and calculate the output power of the wind turbine generator and the output power of the photovoltaic power station in the wind farm according to the environmental temperature under different scenarios.

[0092] In some embodiments, the operating power of the thermal storage system and the operating power of the pumped storage system are determined according to the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid, including:

[0093] When the battery is charged, determine the electrical energy stored in the battery ;

[0094] When the battery is discharged, determine the electrical energy stored in the battery ;

[0095] Among them, E bat (t) is the electric energy stored in the battery at time t, E bat (t-1) is the electric energy stored in the battery at time t-1, is the self-discharge rate of the battery, P bat,c (t) is the charging power of the battery at time t, η bat,c is the charging efficiency of the battery, P bat,d (t) is the discharge power of the battery at time t, η bat,d is the discharge efficiency of the battery;

[0096] The expression for determining the heat storage model is and ;

[0097] The heat storage system includes a cold tank, a hot tank and a heat transfer medium. M is the instantaneous mass of the heat transfer medium. i is the net inlet flow of the heat storage system, m o is the net outlet flow of the heat storage system, C p is the specific heat capacity of the heat transfer medium, T2 is the instantaneous temperature of the heat transfer medium, T h is the inlet temperature of the heat transfer medium, (UA) t is the total heat loss coefficient of the heat outlet pipe at time t;

[0098] The expression for the electric potential to water potential conversion module of the pumped storage system is determined as follows: and ;

[0099] The expression for the water potential to electric potential conversion module of the pumped storage system is determined as follows: and ;

[0100] The electric potential to water potential conversion model includes an electric potential to water potential conversion module and a water potential to electric potential conversion module. i (t) is the water pumping capacity of the water pump at time t, E p (t) is the grid load demand at time t, ρ is the water density, g is the gravity coefficient, h is the average water head, η pis the efficiency of the pump, η m is the efficiency of the motor, η pipe is the efficiency of the pipeline, E g (t) is the output power of the turbine at time t, W o (t) is the water consumption at time t, η tr is the efficiency of the turbine, η nr is the efficiency of the generator;

[0101] The operating power of the heat storage system and the pumped storage system are determined based on the electric energy stored in the battery, the heat storage model of the heat storage system, the electric potential-water potential conversion model of the pumped storage system, the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid.

[0102] When considering the electrical energy stored in the battery, it is necessary not only to consider whether the battery is in a charging or discharging state, but also based on the electrical energy at the previous moment, and that the battery will self-discharge under natural conditions. Considering the above issues, the electrical energy stored in the battery is obtained.

[0103] The heat storage system uses two storage methods: cold tank and hot tank. Molten salt is used as the heat transfer medium. The heat transfer medium from the cold tank to the hot tank is to store heat, and the heat transfer medium from the hot tank to the cold tank is to release heat. Storing heat is storing electrical energy, and releasing heat is releasing electrical energy.

[0104] In a pumped storage system, energy is stored from electric potential to water potential, and energy is released from water potential to electric potential.

[0105] In some embodiments, when the wind turbine, the photovoltaic power station, the storage battery and the pumped storage system work together, the operating power of the pumped storage system is determined according to the electric energy stored in the storage battery, the electric potential-water potential conversion model of the pumped storage system, the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid, including:

[0106] Determine the net load of the grid based on the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the grid , d p (i) is the net load of the power grid at time i, p r (i) is the load demand of the power grid at time i, p w (i) is the output power of the wind turbine at time i, p v (i) is the output power of the photovoltaic power station at time i;

[0107] When the net load is less than 0 and When the pumped storage system is saturated, the pumped storage system is given priority to store electric energy, and the battery is used to store energy when the pumped storage system is saturated;

[0108] When the net load is less than 0 and When using batteries, battery energy storage is preferred;

[0109] When the net load is less than 0 and When the power is stored in the battery and pumped storage system, the remaining power that cannot be consumed is discarded;

[0110] When the net load is greater than 0 and When the load demand is met, the pumped storage system is used for power supply first. If the load demand cannot be met and the energy stored in the battery is greater than the minimum state of charge, the battery will continue to supply power.

[0111] When the net load is greater than 0 and When using, battery power supply is preferred;

[0112] When the net load is greater than 0 and When the power is supplied by batteries and pumped storage systems,

[0113] Where n is the energy storage capacity of the pumped storage system, η p is the operating efficiency of the pump, η c is the charging efficiency of the battery, η g is the power generation efficiency of the turbine, η d is the discharge efficiency of the battery, b is the energy storage capacity of the battery;

[0114] Determine the operating power of the pumped storage system when it is storing energy or supplying power.

[0115] when and When , it means that the net load is negative and the excess power is greater than 20% of the rated power of the pump. At this time, the pump can operate efficiently, so the pumped storage power station is used for energy storage first; if it cannot be completely absorbed and the battery state of charge (SOC) is less than 100%, the battery is used for energy storage.

[0116] when and When , it means the net load is negative and the excess power is less than 20% of the rated power of the pump. At this time, in order to avoid the long-term low-efficiency operation of the pump, the battery is used for energy storage first.

[0117] when and When , it means that the net load is negative and the excess power is greater than the hourly storage capacity of the battery and pumped storage power station. At this time, both energy storage systems are used to absorb the excess power and discard the remaining power that cannot be absorbed.

[0118] when and When , it means that the net load is positive and the excess power is greater than 30% of the rated power of the turbine. At this time, the turbine can operate with high efficiency, so the pumped storage power station is used for power supply first; if the load demand cannot be met and the battery storage capacity is If the state of charge is greater than the minimum, the battery will continue to supply power.

[0119] when and When , it means the net load is positive and the excess power is less than 30% of the rated power of the turbine. At this time, in order to avoid the turbine running inefficiently for a long time, the battery is used for power supply first.

[0120] when and When , it means that the net load is positive and the excess power is greater than the hourly generating capacity of the battery and pumped storage power station. At this time, both energy storage systems are used to supply power.

[0121] In some embodiments, when the wind turbine, photovoltaic power station, battery and heat storage system work together, the operating power of the heat storage system is determined according to the electric energy stored in the battery, the heat storage model of the heat storage system, the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid, including:

[0122] Determine the net load of the grid based on the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the grid , d p (i) is the net load of the power grid at time i, p r (i) is the load demand of the power grid at time i, p w (i) is the output power of the wind turbine at time i, p v (i) is the output power of the photovoltaic power station at time i;

[0123] When the net load is less than 0 and When the power is high, an electric heater is used to convert the electrical energy into thermal energy and store the electricity in the heat storage system, and the remaining electricity that cannot be consumed is discarded;

[0124] When the net load is less than 0 and When the current energy storage space of the battery is greater than the energy storage capacity, the battery is used for energy storage, otherwise the heat storage system is used to store energy;

[0125] When the net load is greater than 0 and When the load demand is met, the heat storage system is used for power supply first. If the load demand cannot be met and the electric energy stored in the battery is greater than the minimum state of charge, the battery will continue to supply power.

[0126] When the net load is greater than 0 and When using, it is powered by batteries;

[0127] When the net load is greater than 0 and When the heat is stored, the battery and the heat storage system are used to supply power;

[0128] Where m is the energy storage capacity of the thermal storage system, η e is the operating efficiency of the electric heater of the heat storage system, η s The charging efficiency of the power generation module of the thermal storage system;

[0129] Determine the operating power of the pumped storage system when the thermal storage system is storing energy or supplying electricity.

[0130] when and When , it means that the net load is negative and the excess power cannot be completely absorbed by the battery. At this time, the electric heater is used to convert the electrical energy into heat energy and store it in the heat storage tank; if it still cannot be completely absorbed, the remaining power is discarded.

[0131] when and When , it means that the net load is negative, and the current energy storage space bs of the battery is greater than the hourly energy storage capacity b, and the excess electricity can be consumed by the battery. At this time, there is no need to use an electric heater to convert electrical energy. If the battery energy storage space bs is less than the hourly energy storage capacity b, and therefore cannot completely consume the excess electricity, then the heat storage system absorbs heat and stores energy.

[0132] when and When , it means that the net load is positive and the excess power is greater than 44% of the rated power of the power generation module. At this time, the power generation module can operate at a higher efficiency, so the thermal storage system is given priority for power supply; if the load demand cannot be met and the battery storage capacity If the state of charge is greater than the minimum, the battery will continue to supply power.

[0133] when and When , it means the net load is positive and the excess power is less than 44% of the rated power of the power generation module. At this time, only the battery is used to supplement the power shortage of the load.

[0134] when and When , it means that the net load is positive and the excess power is greater than the hourly power generation capacity of the battery and thermal storage system. At this time, both energy storage systems are used to supply power.

[0135] In some embodiments, the cost of the power generation system is determined based on the operating cost of the wind turbine, the operating cost of the photovoltaic power station, the operating cost of the thermal storage system, the operating cost of the pumped storage system, and the initial cost, including:

[0136] According to the operating cost of wind turbines, photovoltaic power stations, thermal storage systems, pumped storage systems and initial costs, the cost expression of the power generation system is: ,IC w =ic w *x w ,IC pv =ic pv *x pv ,IC csp =ic csp *x csp ,IC w =ic phs *x phs , A.C. w =om w *P w , A.C. pv =om pv *P pv , A.C. csp =om csp *P csp , A.C. phs =om phs *P phs ;

[0137] Among them, IC w is the initial cost of the wind turbine, ic w is the unit investment cost of wind turbines, x w is the equipment capacity of the wind turbine, IC pv is the initial cost of the photovoltaic power station, ic pv is the unit investment cost of the photovoltaic power station, x pv is the equipment capacity of the photovoltaic power station, IC csp is the initial cost of the thermal storage system, ic csp is the unit investment cost of the thermal storage system, x csp is the equipment capacity of the thermal storage system, IC phs is the initial cost of the pumped storage system, ic phs is the unit investment cost of the pumped storage system, x phs is the equipment capacity of the pumped storage system, AC w is the operating cost of the wind turbine, om w is the unit operating cost of the wind turbine, P w is the operating power of the wind turbine, AC pv is the operating cost of the photovoltaic power station, om pv is the unit operating cost of the photovoltaic power station, P pv is the operating power of the photovoltaic power station, AC csp is the operating cost of the thermal storage system, omcsp is the unit operating cost of the heat storage system, P csp is the operating power of the thermal storage system, AC phs is the operating cost of the pumped storage system, om phs is the unit operating cost of the pumped storage system, P phs is the operating power of the pumped storage system, E sys is the annual power generation of the power generation system, d sys is the decay rate, i is the discount rate, N is the maximum life cycle, and ni is the life cycle.

[0138] The initial cost is calculated as the product of the unit investment cost and the equipment capacity, and the operating cost is the product of the unit operating cost and the operating power. At the same time, the attenuation and life cycle of the equipment should be taken into account when calculating the cost.

[0139] In some embodiments, determining the proportion of sampling points that do not meet power demand within a preset time to the total sampling points includes:

[0140] Determine the proportion of sampling points that do not meet power demand within the preset time to the total sampling points ;

[0141] Among them, P1(t) is the power load of the sampling point at time t, P w (t) is the output power of the wind turbine at time t, P pv (t) is the output power of the photovoltaic power station at time t, P csp (t) is the output power of the heat storage system at time t, P phs (t) is the output power of the pumped storage system at time t, and m1 is the number of sampling points that meet the load.

[0142] LPSP is the proportion of sampling points with unmet electricity demand to the total sampling points within one year.

[0143] In some embodiments, when the ratio and the cost reach a minimum, determining the capacity of the wind turbine generator, the capacity of the photovoltaic power station, the capacity of the thermal storage system, and the capacity of the pumped storage system includes:

[0144] Determine the expression of the first objective function as ;

[0145] The expression of the second objective function is determined as ;

[0146] The particle swarm algorithm is used to determine the minimum value of the first objective function and the minimum value of the second objective function. When the first objective function and the second objective function reach their minimum values, the proportion and the cost reach their minimum values.

[0147] in, For the The cost of the scenario, In the The proportion of the scene, C w is the capacity of the wind turbine, Cpv is the capacity of the photovoltaic power station, C BS is the capacity of the heat storage system, C PHS is the capacity of the battery, C PES is the capacity of the pumped storage system.

[0148] The examples in the particle swarm algorithm are used as decision variables, namely different equipment capacities. The fitness of the particle swarm algorithm is the first objective function and the second objective function. When the optimal solution is reached, the largest first objective function and the largest second objective function can be minimized.

[0149] In some embodiments, when the ratio and the cost reach a minimum, determining the capacity of the wind turbine generator, the capacity of the photovoltaic power station, the capacity of the thermal storage system, and the capacity of the pumped storage system includes:

[0150] When the ratio and cost reach the minimum and the constraints of the heat storage system, the battery and the pumped storage system are met, the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system are determined;

[0151] The heat storage system constraint is and , the battery constraint is , Pumped Storage System Constraints ;

[0152] is the minimum storage capacity of the thermal storage system, is the storage capacity of the thermal storage system at time t, is the maximum storage capacity of the thermal storage system, is the minimum output power of the thermal storage system, is the output power of the heat storage system at time t, is the maximum output power of the thermal storage system, DOD is the depth of discharge of the battery, The maximum electrical energy stored in the battery, is the electrical energy stored in the battery at time t, is the minimum water storage capacity of the reservoir, is the reservoir capacity, The maximum water storage capacity of the reservoir.

[0153] In practical applications, constraints need to be considered, such as the storage capacity of the thermal storage system, the maximum amount of electricity that the battery can store, and the reservoir capacity. The storage capacity of the thermal storage system must be within the corresponding maximum and minimum storage capacities. The reservoir capacity of the pumped storage system must be within the corresponding maximum and minimum water storage capacities.

[0154] Figure 4 A schematic diagram of a structure of a device for determining equipment capacity in a power generation system provided by the present invention, wherein the device for determining equipment capacity in the power generation system comprises:

[0155] A memory 41, used for storing computer programs;

[0156] The processor 42 is used to implement the steps of the method for determining the equipment capacity in the power generation system when executing the computer program.

[0157] For an introduction to the device for determining the capacity of equipment in the power generation system provided in the present application, please refer to the above-mentioned embodiments, which will not be repeated here.

[0158] It should also be noted that, in this specification, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "comprise", "include" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, an element defined by the statement "comprises a ..." does not exclude the presence of other identical elements in the process, method, article or device including the element.

[0159] Professionals may further appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, computer software, or a combination of the two. In order to clearly illustrate the interchangeability of hardware and software, the composition and steps of each example have been generally described in the above description according to function. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professionals and technicians may use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention.

[0160] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A method for determining equipment capacity in a power generation system, characterized in that: include: Determine the output power of the wind turbines in the wind farm and the output power of the photovoltaic power station; Determining the operating power of the heat storage system and the operating power of the pumped storage system according to the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid; Determine the operating cost of the wind turbine, the operating cost of the photovoltaic power station, the operating cost of the heat storage system and the operating cost of the pumped storage system according to the output power of the wind turbine, the output power of the photovoltaic power station, the operating power of the heat storage system and the operating power of the pumped storage system; determining the cost of the power generation system according to the initial cost, the operating cost of the wind turbine, the operating cost of the photovoltaic power station, the operating cost of the heat storage system and the operating cost of the pumped storage system, wherein the initial cost is positively correlated with the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system; Determine the proportion of sampling points whose electricity demand is not met within a preset time to the total sampling points; When both the ratio and the cost reach minimum values, the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system are determined.

2. The method for determining the equipment capacity in the power generation system according to claim 1, characterized in that: Determine the output power of the wind turbines in the wind farm and the output power of the photovoltaic power station, including: Determine the output power of the wind turbine generator of the wind farm. The expression of the output power of the wind turbine generator is: ; Among them, P wind is the output power of the wind turbine, the v i is the cut-in wind speed of the wind turbine, v o is the cut-out wind speed of the wind turbine, v r is the rated wind speed of the wind turbine, v is the real-time wind speed, and Pr is the rated power of the wind turbine; Determine the output power of the photovoltaic power station. The expression of the output power of the photovoltaic power station is: ; Among them, P pv is the output power of the photovoltaic power station, P STC is the maximum output power of the photovoltaic power station under standard test conditions, β T is the temperature coefficient, T1 is the surface operating temperature of the photovoltaic cells of the photovoltaic power station, , T amb is the ambient temperature, T STC is the surface temperature of the photovoltaic cell under standard test conditions, I is the solar illumination intensity, and I STC is the sunlight intensity under standard test conditions.

3. The method for determining the equipment capacity in the power generation system according to claim 2, characterized in that: Determining the operating power of the heat storage system and the operating power of the pumped storage system according to the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid includes: When the battery is charged, the electric energy stored in the battery is determined to be ; When the battery is discharged, the electric energy stored in the battery is determined to be ; Among them, E bat (t) is the electric energy stored in the battery at time t, E bat (t-1) is the electric energy stored in the battery at time t-1, is the self-discharge rate of the battery, P bat,c (t) is the charging power of the battery at time t, η bat,c is the charging efficiency of the battery, P bat,d (t) is the discharge power of the battery at time t, η bat,d is the discharge efficiency of the battery; The expression for determining the heat storage model is and ; The heat storage system includes a cold tank, a hot tank and a heat transfer medium, M is the instantaneous mass of the heat transfer medium, m i is the net inlet flow rate of the heat storage system, m o is the net outlet flow of the heat storage system, C p is the specific heat capacity of the heat transfer medium, T2 is the instantaneous temperature of the heat transfer medium, T h is the inlet temperature of the heat transfer medium, (UA) t is the total heat loss coefficient of the heat outlet pipe at time t; The expression for the electric potential to water potential conversion module of the pumped storage system is determined as follows: and ; The expression for the water potential to electric potential conversion module of the pumped storage system is determined as follows: and ; The electric potential to water potential conversion model includes an electric potential to water potential conversion module and a water potential to electric potential conversion module. i (t) is the water pumping capacity of the water pump at time t, E p (t) is the grid load demand at time t, ρ is the water density, g is the gravity coefficient, h is the average water head, η p is the efficiency of the water pump, η m is the efficiency of the motor, η pipe is the efficiency of the pipeline, E g (t) is the output power of the turbine at time t, W o (t) is the water consumption at time t, η tr is the efficiency of the turbine, η nr is the efficiency of the generator; The operating power of the heat storage system and the operating power of the pumped storage system are determined based on the electric energy stored in the battery, the heat storage model of the heat storage system, the electric potential-water potential conversion model of the pumped storage system, the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid.

4. The method for determining the equipment capacity in the power generation system according to claim 3, characterized in that: When the wind turbine, the photovoltaic power station, the storage battery and the pumped storage system work together, the operating power of the pumped storage system is determined according to the electric energy stored in the storage battery, the electric potential-water potential conversion model of the pumped storage system, the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid, including: The net load of the power grid is determined according to the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid. , d p (i) is the net load of the power grid at time i, p r (i) is the load demand of the power grid at time i, p w (i) is the output power of the wind turbine generator at time i, p v (i) is the output power of the photovoltaic power station at time i; When the net load is less than 0 and When the pumped storage system is saturated, the pumped storage system is preferentially controlled to store electric energy, and the battery is used to store energy when the pumped storage system is saturated; When the net load is less than 0 and When the battery is used for energy storage, the battery is preferably used for energy storage; When the net load is less than 0 and When the power is stored in the battery and pumped storage system, the remaining power that cannot be consumed is discarded; When the net load is greater than 0 and When the load demand is met, the pumped storage system is used for power supply first. If the load demand cannot be met and the energy stored in the battery is greater than the minimum state of charge, the battery will continue to supply power. When the net load is greater than 0 and When using, battery power supply is preferred; When the net load is greater than 0 and When the power is supplied by batteries and pumped storage systems, Wherein, n is the energy storage capacity of the pumped storage system, η p is the operating efficiency of the pump, η c is the charging efficiency of the battery, η g is the power generation efficiency of the turbine, η d is the discharge efficiency of the battery, and b is the energy storage capacity of the battery; The operating power of the pumped-storage system is determined when the pumped-storage system is storing energy or supplying power.

5. The method for determining the equipment capacity in the power generation system according to claim 3, characterized in that: When the wind turbine, the photovoltaic power station, the storage battery and the heat storage system work together, the operating power of the heat storage system is determined according to the electric energy stored in the storage battery, the heat storage model of the heat storage system, the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid, including: The net load of the power grid is determined according to the output power of the wind turbine, the output power of the photovoltaic power station and the load demand of the power grid. , d p (i) is the net load of the power grid at time i, p r (i) is the load demand of the power grid at time i, p w (i) is the output power of the wind turbine generator at time i, p v (i) is the output power of the photovoltaic power station at time i; When the net load is less than 0 and When the electric energy is converted into heat energy by an electric heater, the electric energy is stored in the heat storage system, and the remaining electric energy that cannot be consumed is discarded; When the net load is less than 0 and When the current energy storage space of the battery is greater than the energy storage capacity, the battery is used to store energy, otherwise the heat storage system is used to store energy; When the net load is greater than 0 and When the load demand is not met, the heat storage system is used to supply power. If the power stored in the battery is greater than the minimum state of charge, the battery is used to supply power. When the net load is greater than 0 and When the battery is used for power supply; When the net load is greater than 0 and When the battery and the heat storage system are used to supply power together; Wherein, m is the energy storage capacity of the heat storage system, η e is the operating efficiency of the electric heater of the heat storage system, η s is the charging efficiency of the power generation module of the thermal storage system; The operating power of the pumped storage system is determined when the thermal storage system stores energy or supplies electricity.

6. The method for determining equipment capacity in a power generation system according to claim 1, characterized in that: The cost of the power generation system is determined according to the operating cost of the wind turbine, the operating cost of the photovoltaic power station, the operating cost of the thermal storage system, the operating cost of the pumped storage system and the initial cost, including: The cost expression of the power generation system is determined based on the operating cost of the wind turbine, the operating cost of the photovoltaic power station, the operating cost of the heat storage system, the operating cost of the pumped storage system and the initial cost: ,IC w =ic w *x w ,IC pv =ic pv *x pv ,IC csp =ic csp *x csp ,IC w =ic phs *x phs , A.C. w =om w *P w , A.C. pv =om pv *P pv , A.C. csp =om csp *P csp , A.C. phs =om phs *P phs ; Among them, IC w is the initial cost of the wind turbine, ic w is the unit investment cost of the wind turbine, x w is the equipment capacity of the wind turbine, IC pv is the initial cost of the photovoltaic power station, ic pv is the unit investment cost of the photovoltaic power station, x pv is the equipment capacity of the photovoltaic power station, IC csp is the initial cost of the thermal storage system, ic csp is the unit investment cost of the thermal storage system, x csp is the equipment capacity of the thermal storage system, IC phs is the initial cost of the pumped storage system, ic phs is the unit investment cost of the pumped storage system, x phs is the equipment capacity of the pumped storage system, AC w is the operating cost of the wind turbine, om w is the unit operating cost of the wind turbine, P w is the operating power of the wind turbine, AC pv is the operating cost of the photovoltaic power station, om pv is the unit operating cost of the photovoltaic power station, P pv is the operating power of the photovoltaic power station, AC csp is the operating cost of the thermal storage system, om csp is the unit operating cost of the heat storage system, P csp is the operating power of the thermal storage system, AC phs is the operating cost of the pumped storage system, om phs is the unit operating cost of the pumped storage system, P phs is the operating power of the pumped storage system, E sys is the annual power generation of the power generation system, d sys is the decay rate, i is the discount rate, N is the maximum life cycle, and ni is the life cycle.

7. The method for determining equipment capacity in a power generation system according to claim 1, characterized in that: Determine the proportion of sampling points that do not meet power demand within a preset time to the total number of sampling points, including: Determine the proportion of sampling points that do not meet power demand within the preset time to the total sampling points ; Among them, P1(t) is the power load of the sampling point at time t, P w (t) is the output power of the wind turbine generator at time t, P pv (t) is the output power of the photovoltaic power station at time t, P csp (t) is the output power of the heat storage system at time t, P phs (t) is the output power of the pumped storage system at time t, and m1 is the number of sampling points that meet the load.

8. The method for determining equipment capacity in a power generation system according to any one of claims 1 to 7, characterized in that: When the ratio and the cost reach a minimum value, determining the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system includes: Determine the expression of the first objective function as ; The expression of the second objective function is determined as ; Using a particle swarm algorithm to determine a minimum value of the first objective function and a minimum value of the second objective function, when the first objective function and the second objective function reach a minimum value, the proportion and the cost reach a minimum value; in, For the The cost of the scenario, In the The proportion of the scene, C w is the capacity of the wind turbine, Cpv is the capacity of the photovoltaic power station, C BS is the capacity of the heat storage system, C PHS is the capacity of the battery, C PES is the capacity of the pumped storage system.

9. The method for determining equipment capacity in a power generation system according to claim 8, characterized in that: When the ratio and the cost reach a minimum value, determining the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system includes: When the ratio and the cost reach a minimum and the heat storage system constraint, the battery constraint and the pumped storage system constraint are satisfied, determining the capacity of the wind turbine, the capacity of the photovoltaic power station, the capacity of the heat storage system and the capacity of the pumped storage system; The heat storage system constraint is and , the battery constraint is , the pumped storage system constraints ; is the minimum storage capacity of the thermal storage system, is the storage capacity of the thermal storage system at time t, is the maximum storage capacity of the thermal storage system, is the minimum output power of the thermal storage system, is the output power of the heat storage system at time t, is the maximum output power of the thermal storage system, DOD is the depth of discharge of the battery, is the maximum electrical energy stored in the battery, is the electrical energy stored in the battery at time t, is the minimum water storage capacity of the reservoir, is the reservoir capacity, The maximum water storage capacity of the reservoir.

10. A device for determining equipment capacity in a power generation system, characterized in that: include: Memory for storing computer programs; A processor, configured to implement the steps of the method for determining the capacity of equipment in a power generation system according to any one of claims 1 to 9 when executing the computer program.

Citation Information

Cited By

  • Wind-solar integrated power generation system and method coupled with biomass heat storage

    CN119813381A