Flexible coating method and flexible coating workshop layout
Through flexible coating methods and station layout optimization, the efficiency and energy consumption problems of traditional coating lines when facing low production capacity, high quality and diversity requirements are solved, and efficient, flexible and environmentally friendly coating production is achieved. , meets the needs of modern markets.
Patent Information
- Application Number
- CN202411097657.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-12
- Publication Date
- 2024-11-12
Smart Images

Figure CN118926061A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of coating workshops, and in particular to a flexible coating method. Background Art
[0002] With the growing demand for customized cars and small batches of multi-style models in recent years, the traditional painting line production model has exposed many shortcomings in the face of this trend. At present, the body painting process usually adopts a complex process, starting from the body being placed on the topcoat sled after electrophoresis, through a series of processes such as carbon fiber bonding, sealant application, bottom gluing, grinding, cleaning, painting, etc., the painting is finally completed and sent to the final assembly workshop. However, this traditional model has many problems in dealing with low-capacity, high-quality and diverse body painting needs. First, the equipment investment cost is high, and the mode is single, occupying a large amount of workshop area. Secondly, there are many manual operation links in the production process, which not only wastes human resources, but also leads to low production efficiency. In addition, the intermittent production method makes the equipment utilization rate low and increases the energy consumption of the workshop. In terms of plant construction, the traditional model requires a complex civil construction foundation, which increases the difficulty of work. Due to the long conveying route, the reciprocating sled transportation not only consumes a lot of energy, but also has low efficiency. More noteworthy is that the lack of intelligence in this model has brought great challenges to workshop management. Finally, due to the low utilization rate of the equipment that produces waste gas, a large amount of waste gas needs to be treated, further increasing the environmental burden. These problems highlight the limitations of the traditional coating line production model in the face of new market demands, and innovative solutions are urgently needed to improve production efficiency, reduce costs, reduce energy consumption, and achieve a more flexible and intelligent production process. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a flexible painting method in view of the defects in the prior art, which improves the efficiency of low-capacity car body painting workshops and the flexibility of conveying operations, meets the quality requirements of major commodities, improves the environmental protection level, and solves the problems of high equipment investment costs and high operating and maintenance costs.
[0004] The technical solution adopted by the present invention to solve its technical problems is as follows: the present invention provides a flexible coating method, which includes the following steps: hanging a car body on an AGV; performing carbon fiber bonding, sealant application, glue drying and strong cooling treatment on the car body; electrophoresis polishing, wiping and dry ice cleaning on the car body; flame treatment on the car body; BC robot external spray painting and BC manual internal spray painting on the car body in a water-based paint spraying room; flash drying and strong cooling treatment of the color paint on the painted car body; robot external spray varnish and manual internal spray varnish on the car body in a solvent-based paint spraying room; leveling and topcoat drying treatment on the painted car body; inspection, finishing and wax injection on the car body.
[0005] In a preferred embodiment of the present invention, the AGV has a 360-degree arbitrary angle adjustable conveying characteristic.
[0006] In a preferred embodiment of the present invention, the vehicle body that does not require electrophoresis first enters a pre-treatment station for wiping treatment.
[0007] In a preferred embodiment of the present invention, under the condition of low cycle, when the robot sprays paint according to the trajectory, the sprayed parts of the car body meet the air-drying time requirement, thus eliminating the air-drying station.
[0008] In a preferred embodiment of the present invention, both the mid-coat and the color paint using water-based paint are carried out in the same spray painting room.
[0009] In a preferred embodiment of the present invention, a buffer station is also designed according to whether the time for transferring the vehicle body to the drying oven meets the leveling time requirement.
[0010] In a preferred embodiment of the present invention, it also includes checking whether polishing is required in the buffer area after the varnish is dried, wherein the polishing station is compatible with the mid-coat polishing, and the finishing station can also take into account the spot repair station.
[0011] In a preferred embodiment of the present invention, a zeolite rotor is used to concentrate the paint booth gas, activated carbon is used to adsorb the workstation exhaust gas, and RTO is used to burn the gas concentrated by the rotor and the gas desorbed by the activated carbon at high temperature, so that the exhaust gas meets the emission standards.
[0012] In a preferred embodiment of the present invention, the method further includes identifying and sorting the vehicle bodies in the buffer area and the color separation area.
[0013] The present invention also discloses a flexible layout of a painting workshop, which comprises: a transfer hanging area, which is arranged in the southeast corner of the painting workshop; an assembly workshop, which is arranged in the northwest corner of the painting workshop; a first electrophoretic polishing area, a second electrophoretic polishing area, a wiping area and a dry ice cleaning area, which are arranged in sequence from south to north in the northeast corner of the painting workshop; a wax injection / final inspection area, an inspection / finishing area, a carbon fiber bonding area and a carbon fiber storage and hanging area, which are arranged in sequence from west to east between the assembly workshop and the dry ice cleaning area; a sealant line area, a glue drying area and a glue strong cooling area, which are arranged in parallel to the south of the carbon fiber bonding area and the carbon fiber storage and hanging area, and are arranged in sequence from west to east. East layout; flame treatment area, BC robot external spray painting area, BC manual internal spray painting area, air-drying area, color paint flashing area, flashing strong cooling area, robot external varnish spraying area, manual internal varnish spraying area, leveling area, topcoat drying area and strong cooling area, wherein: the flame treatment area, BC robot external spray painting area, BC manual internal spray painting area and air-drying area are arranged from west to east in sequence on the south side of the sealant line area and the glue drying area; the flashing strong cooling area, robot external spray varnish area, manual internal spray varnish area, leveling area, topcoat drying area and strong cooling area are arranged from east to west in sequence; the color paint flashing area is arranged between the air-drying area and the flashing strong cooling area, and is arranged along the north-south direction.
[0014] The beneficial effects of the present invention are as follows: the present invention significantly improves the overall performance of the coating line through the application of advanced equipment, information systems, and innovations in logistics and management.
[0015] The flexible coating workshop layout adopted by the present invention ensures the continuity and smoothness of the production process by carefully planning the position and process sequence of each functional area, reduces the ineffective movement of the car body between different workstations, and thus improves production efficiency. In particular, the design of arranging the first electrophoretic polishing area, the second electrophoretic polishing area, the wiping area and the dry ice cleaning area from south to north in sequence, and arranging the wax injection / final inspection area, the inspection / finishing area, the carbon fiber bonding area and the carbon fiber storage assembly area from west to east in sequence, helps to simplify the logistics path and reduce the distance and time of car body transportation. At the same time, the parallel layout of the sealant line area, the glue drying area and the glue strong cooling area makes the production process more compact and reduces space waste. In addition, the U-shaped layout design between the flame treatment area and the strong cooling area optimizes the connection between the various processes and avoids the bottleneck effect in the coating process.
[0016] The multi-mode design of the workstation layout and transportation method of the present invention not only solves the problems of workstation compatibility and disordered transportation routes, but also improves the utilization rate of the workstation, thereby improving the quality of body painting to the domestic advanced level. Under the background of the increasing demand for customized vehicles, the flexible workstation design meets the diverse product painting needs while reducing equipment investment and operating energy consumption. Especially for low-capacity body painting workshops, the present invention provides an efficient and flexible solution that significantly improves efficiency while ensuring quality. By adopting the AGV transportation mode and intelligent identification and sorting system, the flexibility and intelligence of the production process are greatly increased. In addition, the present invention also pays attention to environmental benefits, ensures that emissions meet standards through reasonable exhaust gas treatment design, and optimizes space utilization and inventory management. In general, through comprehensive technological innovation, the present invention has successfully found a balance between improving efficiency, reducing costs, improving quality and adapting to market demand, and provides a comprehensive improvement plan for the painting process of the modern automobile manufacturing industry. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The present invention will be further described below with reference to the accompanying drawings and embodiments, in which:
[0018] Figure 1 It is a schematic diagram of the process of the present invention;
[0019] Figure 2 It is a structural schematic diagram of the present invention. DETAILED DESCRIPTION
[0020] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0021] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0022] like Figure 1-2 As shown, the present invention provides a technical solution: the equipment in the painting room is arranged according to the function of the work area. For car bodies with high quality requirements, the subsequent intermediate coating and topcoat coating are generally carried out according to demand after pre-treatment electrophoresis and glue drying. Under the background of the increasing demand for customized cars, the flexible design of the workstation meets the product painting needs and reduces equipment investment and operating energy consumption.
[0023] According to the product characteristics and the requirements of the coating quality of the vehicle model grade, after entering the painting workshop, the car body transported from the outside is transferred to the AGV2 by the overhead crane 1. The transfer and transportation of the workpieces in each process in the workshop is mainly carried out by AGV. The painting line adopts the mature new process of 3C1B, and is arranged with a carbon fiber bonding line 9, which is mainly responsible for the bonding task of the carbon fiber covering parts of the car body; a coating / spraying line 13, which is mainly responsible for coating the car body weld sealant, laying the car body sound insulation damping pad, and spraying the anti-stone impact sound insulation coating on the bottom of the car, adopts a combination of robot and manual coating / spraying, and this gluing line is transported by a sled; a topcoat line 20, which is mainly responsible for the topcoat spraying and drying of the car body, adopts robot internal and external spraying, and manual touch-up paint, and this topcoat line is transported by a sled; the finishing station 31 is mainly responsible for the inspection and modification of the car body after painting, and this station is transported by a sled; the wax injection station 32 is mainly responsible for cavity wax injection, and this station is transported by a sled. The use of independent functional module partition layout can save the painting conveying and process path of customized vehicles. For example, the body that does not need to bond carbon fiber covers can directly enter the gluing line and topcoat line to complete the painting operation; for the body that does not need wax injection, it can go directly to the general assembly workshop; for some test vehicles, they can be painted separately at the test station without going through the entire process route in the workshop. For the process partition of independent modules, several modules can be selected for painting according to the body process requirements. Multiple modules can be synchronized or asynchronous according to the control system, and the process time can be adjusted according to product requirements. With the body recognition system, when a body enters the recognition area, the conveying and process equipment are started to complete the painting task in this area.
[0024] A flexible coating method of the present invention adopts an AGV conveying mode. In this coating line, the AGV can adjust the conveying characteristics at any angle of 360 degrees, thereby avoiding the arrangement of a rotating roller bed and a moving machine in the workshop. When the budget is low, the conveyor chain mode can be taken into consideration for transportation. For some car bodies that do not require electrophoresis, when entering this flexible process workshop, they first enter the pre-treatment station for cleaning. After the cleaning pre-treatment is completed, they enter the mid-coat spraying room for robot painting. Under the condition of a low beat, when the robot sprays paint according to the trajectory, the sprayed parts of the car body have reached the air-drying time requirement, and the air-drying station can be omitted. This process design is also applied when spraying topcoat. Both the mid-coat and the color paint using water-based paint can be operated in this spraying room. The car body can enter the flash drying furnace after leaving the water-based paint spraying room. After flash drying, the car body enters the solvent-based paint spray room, where clear varnish spraying is mainly carried out. After the clear varnish spraying is completed, whether a buffer station needs to be designed, or how many buffer stations need to be designed, can be considered based on whether the time for transferring it to the drying oven meets the leveling time requirements. After the clear varnish is dried, the buffer area is checked to see if it needs to be polished. This polishing station is compatible with mid-coat polishing, and the finishing station can also be considered for spot-filling station design. This type of polishing station can be considered and designed based on product requirements and polishing accuracy.
[0025] like Figure 2 As shown, it discloses a flexible layout of a painting workshop, the top view of the painting workshop is rectangular, the southeast corner of the painting workshop is provided with a transfer hanging area 1, the northwest corner is provided with a general assembly workshop 24, the northeast corner of the painting workshop is provided with a first electrophoretic polishing area 7, a second electrophoretic polishing area 8, a wiping area 9 and a dry ice cleaning area 10, the first electrophoretic polishing area 7, the second electrophoretic polishing area 8, the wiping area 9 and the dry ice cleaning area 10 are arranged in sequence from south to north, and a wax injection / final inspection area 23, an inspection / finishing area 22, a carbon fiber bonding area 3, and a carbon fiber storage group hanging area 2 are arranged between the general assembly workshop 24 and the dry ice cleaning area 10, the wax injection / final inspection area 23, the inspection / finishing area 22, the carbon fiber bonding area 3, and the carbon fiber storage group hanging area 2 are arranged in sequence from west to east, and the sealant line area 4, the glue drying area 5 and the glue strong cooling area 6 are arranged in parallel with the carbon fiber bonding area 3 and the carbon fiber storage group hanging area 2. On the south side, the sealant line area 4, the glue drying area 5 and the glue strong cooling area 6 are arranged from west to east. On the south side of the sealant line area 4 and the glue drying area 5, there are U-shaped flame treatment area 11, BC robot external spray painting area 12, BC manual internal spray painting area 13, air-drying area 14, color paint flashing area 15, flashing strong cooling area 16, robot external spray varnish area 17, manual internal spray varnish area 18, leveling area 19, topcoat drying area 20. , strong cooling zone 21, flame treatment zone 11, BC robot external spray painting zone 12, BC manual internal spray painting zone 13, and air-drying zone 14 are arranged in sequence from west to east; flash drying strong cooling zone 16, robot external varnish spraying zone 17, manual internal varnish spraying zone 18, leveling zone 19, topcoat drying zone 20, and strong cooling zone 21 are arranged in sequence from east to west; a color paint flash drying zone 15 arranged in the north-south direction is set between the air-drying zone 14 and the flash drying strong cooling zone 16.
[0026] Main process: The car body from the electrophoresis workshop is transferred to the AGV, and the car body is transported upward with the AGV to the carbon fiber storage assembly (carbon fiber storage assembly area 2). The AGV carries the car body and continues to move to the left to the carbon fiber bonding (carbon fiber bonding area 3). After the bonding work is completed, the AGV moves downward to send the car body to the sealant line (sealant line area 4), and runs along the right side to complete the glue drying (glue drying area 5) and glue strong cooling (glue strong cooling area 6) at one time. The AGV continues to move to the right and sends the car body to electrophoresis grinding (first electrophoresis grinding area 7, second electrophoresis grinding area 8), cleaning (cleaning area 9) and dry ice cleaning (dry ice cleaning area 10) in turn. After cleaning, the AGV moves to the lower left to send the car body to the paint line. The car body is transferred to the paint line and runs to the right along the paint line (in the U-shaped flame treatment area 11, BC robot external paint spraying area 12, BC manual internal paint spraying area 13, air-drying area 14, color paint flash-drying area 15, flash-drying strong cooling area 16, robot external varnish spraying area 17, manual internal varnish spraying area 18, leveling area 19, topcoat drying area 20, and strong cooling area 21, it undergoes flame treatment → BC robot external paint spraying → BC manual internal paint spraying → air-drying → color paint flash-drying → flash-drying strong cooling → robot external varnish spraying → manual internal varnish spraying → leveling → topcoat baking → strong cooling). After the painting line operation is completed, the car body is transferred to the AGV off the line and moves upward to the inspection / finishing (inspection / finishing area 22 for spot repair / repair). After the finishing operation is completed, it moves to the left to the wax injection / final inspection (wax injection / final inspection area 23) and goes to the final assembly workshop 24.
[0027] (1) Pre-processing station
[0028] The pre-treatment station is mainly used to clean the car bodies delivered to the workshop (pre-treatment electrophoresis and gluing have been completed) to meet the needs of subsequent spraying. The solvent used for wiping is selected according to the product quality requirements.
[0029] (2) Grinding station
[0030] The grinding station mainly involves mid-coat grinding, topcoat grinding and finishing. The three stations can be flexibly designed according to production capacity, and the three can be compatible. When the three are compatible as one grinding station, this station can be placed opposite the mid-coat and topcoat spraying area, with a short conveying distance and partitioning, to avoid the dust particles generated by grinding from affecting the quality of the car body.
[0031] (3) Paint spraying room
[0032] After the pre-treatment of wiping is completed, the car enters the spray booth for robot spraying. When using robot spraying, discrete spray booths are divided into water-based paint internal and external spray booths and solvent-based paint internal and external spray booths for design. Under the condition of low beat, when the robot sprays paint according to the trajectory, the sprayed parts of the car body have reached the air-drying time requirement, and the air-drying station can be omitted. This process design is also applied when spraying topcoat. After flash drying, the car body enters the solvent-based paint spray booth, mainly for clear varnish spraying. After the clear varnish spraying is completed, it can be considered whether to design a cache station, or how many cache stations to design, based on whether the time for transferring it to the drying furnace meets the leveling time requirements.
[0033] (4) Flash drying furnace, drying furnace
[0034] In this low-capacity coating line, the flash drying ovens for midcoat and color paint can be designed and used in a compatible manner according to the cycle and process requirements. The varnish drying oven is designed separately due to the longer process time and different process requirements.
[0035] (5) Conveying equipment
[0036] The conveying system is mainly composed of internal conveying and external conveying of each workstation room. The roller bed + slide mode is used inside the room according to the needs, and the external conveying of the room is the main conveying. The flexible movement of AGV avoids too much foundation inside the workshop, further improves the conveying flexibility, and also improves the utilization rate of each workstation room.
[0037] (6) Waste gas treatment equipment
[0038] Designed according to local environmental assessment requirements, the system uses a zeolite rotor to concentrate the paint room gas, and activated carbon to adsorb the workstation exhaust gas. The RTO burns the gas concentrated by the rotor and the gas desorbed by the activated carbon at high temperature to ensure that the exhaust gas meets the emission standards.
[0039] (7) Intelligent Application
[0040] The transmission rate between processes must match the production rhythm of the previous and next processes and meet production capacity. At the same time, according to product design requirements, the car bodies are identified and sorted in the buffer area and color separation area, and enter the subsequent process to complete the painting task.
[0041] It should be pointed out that Article 22, paragraph 3 of the Chinese Patent Law stipulates that an invention shall have outstanding substantive features and significant progress, that is, the invention shall be creative. The following is an analysis of why the layout of the present invention meets this requirement from the perspective of creativity: In the prior art, the layout design of the paint shop often focuses on meeting basic production needs, but has certain limitations in the compatibility of the workstation layout, the optimization of the logistics path, and the flexibility. The traditional layout of the paint shop may lead to problems such as poor connection between processes, chaotic logistics routes, and low utilization of workstations. In particular, it lacks sufficient flexibility and efficiency when dealing with diversified product coating needs.
[0042] In view of the shortcomings of the prior art, the present invention proposes a flexible coating workshop layout, which adopts the following innovative designs:
[0043] Optimized layout of functional areas: The various functional areas are arranged in a specific order and direction (such as the transfer area in the southeast corner, the final assembly workshop in the northwest corner, the polishing area, wiping area and washing area in the northeast corner, etc.), which ensures the rationality of the logistics path and reduces the ineffective movement of the car body between workstations.
[0044] Combination of parallel and U-shaped layout: The sealant line area, glue drying area and glue strong cooling area are arranged in parallel with the carbon fiber bonding area and storage area. At the same time, the flame treatment area to the strong cooling area adopts a U-shaped layout, making the coating process compact and efficient, avoiding bottlenecks between processes.
[0045] Sequential layout design: By rationally arranging the positions and sequences of functional areas, the continuity of production and the smoothness of the process are ensured.
[0046] The present invention has outstanding substantive features: the present invention is innovative in layout design and solves many problems in the prior art, such as poor process connection, unreasonable logistics path, low space utilization, etc. Through the optimized arrangement of functional areas and innovative design of layout mode, the present invention significantly improves the production efficiency and flexibility of the workshop.
[0047] The present invention has significant progress: compared with the existing paint shop layout, the layout of the present invention not only meets the diverse painting needs, but also reduces the investment in equipment and operating energy consumption, especially when facing low-capacity car body painting, it provides an efficient and flexible solution. These improvements make the paint shop layout of the present invention achieve significant progress in production efficiency, cost control and environmental benefits.
[0048] The present invention effectively improves production efficiency: by rationally planning the positions of various functional areas, ineffective movement of vehicle bodies between various workstations is reduced, thereby improving logistics efficiency.
[0049] The present invention effectively enhances flexibility: the flexible layout design can adapt to the painting needs of different types of car bodies and meet the requirements of customized production.
[0050] The present invention can reduce operating costs: optimize layout design, reduce unnecessary equipment investment and energy consumption, and bring significant economic benefits.
[0051] The invention has environmental benefits: reasonable layout design not only improves space utilization, but also reduces waste gas emissions and energy consumption, thus meeting environmental protection requirements.
[0052] In summary, the flexible paint shop layout of the present invention overcomes the shortcomings of the prior art through a series of innovative designs and technical means, and demonstrates outstanding substantive features and significant progress.
[0053] In the description of the present application, it should be noted that the terms "upper", "lower", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application. Unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present application can be understood according to the specific circumstances.
[0054] It should be noted that, in this application, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.
[0055] The above description is only a specific implementation of the present application, so that those skilled in the art can understand or implement the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest range consistent with the principles and novel features applied for herein.
Claims
1. A flexible coating method, characterized in that: The following steps are involved: The car body is transferred to the AGV; the car body is subjected to carbon fiber bonding, sealant application, glue drying and forced cooling treatment; The car body is electrophoretically polished, wiped and cleaned with dry ice; the car body is flame treated; the car body is BC robot-painted on the outside and BC manual-painted on the inside in the water-based paint spraying room; the car body after painting is flash-dried and subjected to strong cooling treatment; the car body is robot-painted on the outside and manual-painted on the inside in the solvent-based paint spraying room; the car body after painting is leveled and the topcoat is dried; the car body is inspected, finished and waxed.
2. The flexible coating method according to claim 1, characterized in that: The AGV has the ability to adjust the conveying function at any angle of 360 degrees.
3. The flexible coating method according to claim 1, characterized in that: When the budget is low, the conveyor chain mode is used for transportation.
4. The flexible coating method according to claim 1, characterized in that: For car bodies that do not require electrophoresis, they first enter the pre-treatment station for wiping and cleaning.
5. The flexible coating method according to claim 1, characterized in that: Under low cycle conditions, when the robot sprays paint along the trajectory, the painted parts of the car body reach the drying time requirement, eliminating the drying station.
6. The flexible coating method according to claim 1, characterized in that: The mid-coat and color paint using water-based paint are both carried out in the same spray booth.
7. The flexible coating method according to claim 1, characterized in that: It also includes designing a cache station based on whether the time it takes to transfer the car body to the drying oven meets the leveling time requirements.
8. The flexible coating method according to claim 1, characterized in that: It also includes checking whether sanding is needed in the buffer area after the varnish is dried. The sanding station is compatible with the mid-coat sanding, and the finishing station can also be used as the spot-filling station.
9. The flexible coating method according to claim 1, characterized in that: It also includes using a zeolite wheel to concentrate the paint booth gas, using activated carbon to adsorb the work station exhaust gas, and using RTO to burn the gas concentrated by the wheel and the gas desorbed by the activated carbon at high temperature, so that the exhaust gas meets the emission standards.
10. A flexible painting workshop layout, characterized in that: The paint shop includes: The transfer and hanging area (1) is arranged at the southeast corner of the painting workshop; The final assembly workshop (24) is arranged at the northwest corner of the painting workshop; The first electrophoretic polishing area (7), the second electrophoretic polishing area (8), the wiping area (9) and the dry ice cleaning area (10) are arranged in sequence from south to north at the northeast corner of the painting workshop; The wax injection / final inspection area (23), the inspection / finishing area (22), the carbon fiber bonding area (3) and the carbon fiber storage and hanging area (2) are arranged from west to east between the final assembly workshop (24) and the dry ice cleaning area (10); The sealant line area (4), the sealant drying area (5) and the sealant strong cooling area (6) are arranged in parallel to the south of the carbon fiber bonding area (3) and the carbon fiber storage and hanging area (2), and are arranged from west to east in sequence; Flame treatment area (11), BC robot external spray painting area (12), BC manual internal spray painting area (13), air-drying area (14), color paint flashing area (15), flashing strong cooling area (16), robot external spray varnish area (17), manual internal spray varnish area (18), leveling area (19), topcoat drying area (20) and strong cooling area (21), wherein: The flame treatment area (11), the BC robot external painting area (12), the BC manual internal painting area (13) and the air drying area (14) are arranged in sequence from west to east on the south side of the sealant line area (4) and the sealant drying area (5); The flash drying strong cooling zone (16), the robot external varnish spraying zone (17), the manual internal varnish spraying zone (18), the leveling zone (19), the topcoat drying zone (20) and the strong cooling zone (21) are arranged in sequence from east to west; The paint flash-drying zone (15) is arranged between the air-drying zone (14) and the flash-drying strong cooling zone (16), and is arranged in the north-south direction.
Citation Information
Cited By
Automobile body-in-white hanging method and system
CN119720395A