Auxiliary tool for mounting electric power metering box and mounting method

By designing an auxiliary tool for installation of power metering boxes including pulley sets and fixed hoops, the problems of safety risks and installation difficulties of high altitude operations in traditional methods are solved, and the rapid, safe and efficient power metering boxes on outdoor telephone poles are achieved. Install.

CN118929419APending Publication Date: 2024-11-12KUYTUN POWER SUPPLYING CO STATE GRID XINJIANG ELECTRIC POWER CO +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411321786.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-23
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The traditional power metering box installation method poses safety risks at high altitude operations and is difficult to install. Especially in complex environments, it is inefficient and has safety hazards, and cannot effectively solve the challenges of installing power metering boxes on outdoor telephone poles.

Method used

The auxiliary tools are adopted including the first fixing rod, the second fixing rod, the fixed clamping hoop, the beam, the pulley set, the wire rope collection wheel, the wire rope and the hook. The pulley set provides two sets of upward tension to reduce and enhance the working strength, and use the fixed clamping hoop. The metering box lifting fixing belt is used to achieve stable fixing and lifting, simplifying the installation process.

Benefits of technology

It reduces installation difficulty, improves installation efficiency, reduces manual operation risks, improves work efficiency and quality, reduces safety hazards, and adapts to the installation needs of complex environments.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118929419A_ABST
    Figure CN118929419A_ABST
Patent Text Reader

Abstract

The invention discloses an auxiliary tool for mounting an electric power metering box and a mounting method.The auxiliary tool comprises a first fixing rod, a second fixing rod, a fixing hoop, a cross beam, a pulley block, a steel wire rope collecting wheel, a steel wire rope and a hook, and the first fixing rod and the second fixing rod adopt steel pipelines; the fixing hoop is welded to the left side face of the first fixing rod and the left side face of the second fixing rod, the cross beam is welded to the upper end of the first fixing rod, pulleys of the pulley block are installed at the corresponding positions respectively, the steel wire rope collecting wheel is installed on the collecting wheel installing support, and the steel wire rope is connected with the hook, the pulley block and the steel wire rope collecting wheel. The tool adopts the pulley block to provide two groups of upward pulling forces for the hook, reduces the working intensity of lifting operation, is applied to an electric power metering box installation site, and can reduce the installation difficulty, improve the installation efficiency and reduce the manual operation risk.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of installing an electric power meter box on an outdoor electric pole, and in particular to an auxiliary tool and an installation method for installing the electric power meter box. Background Art

[0002] In the power industry, with the rapid development of smart grids and the continuous growth of residents' electricity demand, meter boxes, as an indispensable part of the power metering system, are facing increasingly severe challenges in their installation and maintenance. Meter boxes are usually installed at high places such as poles, towers or buildings to achieve accurate metering and monitoring of electric energy. However, with the continuous improvement of urban infrastructure, the installation environment of meter boxes is becoming more and more complex, and the difficulty of installation is gradually increasing.

[0003] Traditional meter box installation methods usually require manual lifting and fixing at high altitudes. High-altitude operations themselves pose certain safety risks and increase the technical requirements for installation personnel. This not only requires installers to have superb skills and rich experience, but also requires a lot of manpower and time. Especially in high-rise buildings or complex terrains, the difficulty of installation is multiplied, which brings great inconvenience and risks to the installation work.

[0004] After searching, it was found that a Chinese invention patent with patent application number 202310820334.2 proposed a meter box installation auxiliary device and a single-person operation method for wall installation of a meter box in the field of power meter box installation technology. The auxiliary device includes an inclined support rod, a winch, a hook, and a locking mechanism. The winch is arranged on the inclined support rod, and the movable end of the pull rope on the winch is connected to the hook after passing through the upper end of the inclined support rod. The hook can be clamped on the upper side wall of the meter box in a clamping manner. The winch can lift the meter box by using the hook. The locking mechanism is arranged on the inclined support rod, and the locking mechanism can realize the counterclockwise or clockwise rotation locking of the winch. The inclined support rod is tilted and placed between the wall and the ground to achieve stable support for the winch. By using the auxiliary device and the operating method, one staff member can realize the fast, safe and effective installation of the meter box. Although the technical scheme proposes a simple, safe and effective convenient installation auxiliary tool and installation method for the meter box, the use of the auxiliary device requires leaning on the installation position. For the installation of the power meter box on the outdoor electric pole, there will be a great safety hazard due to the arc-shaped structure of the outer surface of the electric pole and the lack of a stable leaning point. At the same time, the device needs to use a U-shaped hook to clamp on the upper edge of the meter box when lifting the meter box. Due to the limited bearing capacity of the hook, there is a safety hazard. At the same time, the installation of the U-shaped hook on the power meter box takes a certain amount of time and is inefficient, and cannot solve the technical problems currently faced by the installation of power meter boxes on electric poles. Summary of the invention

[0005] In order to overcome the above problems, the purpose of the present invention is to provide an auxiliary tool and installation method for the installation of an electric power meter box. The auxiliary device uses a pulley group to provide two sets of upward pulling forces to the hook, thereby reducing the work intensity of the lifting operation. The device is applied to the installation site of the electric power meter box, which can reduce the installation difficulty, improve the installation efficiency, and reduce the risk of manual operation. It needs to have the characteristics of lightness, flexibility, and stability, and can adapt to various complex installation environments. It can also quickly and accurately complete the installation of the meter box and improve work efficiency and work quality.

[0006] The technical solution adopted by the present invention is: an auxiliary tool for installing an electric power meter box, comprising a first fixing rod, a second fixing rod, a fixing hoop, a crossbeam, a pulley block, a wire rope collecting wheel, a wire rope, and a hook.

[0007] The first fixing rod and the second fixing rod are made of steel pipes, a pulley mounting groove is provided at the lower end of the first fixing rod, a collecting wheel mounting bracket is welded to the lower end of the first fixing rod below the pulley mounting groove, and a first pulley mounting bracket is welded to the upper end.

[0008] The fixing hoop is welded to the left side of the first fixing rod and the second fixing rod.

[0009] The crossbeam is welded to the upper end of the first fixing rod, a second pulley mounting bracket is welded on the left side above the crossbeam, the right side of the crossbeam is an open structure, a third pulley mounting bracket is designed, a fixing block is welded on the right side below the crossbeam, and a fixing hole is opened on the fixing block.

[0010] The pulleys of the pulley block are respectively installed in the third pulley mounting bracket, the second pulley mounting bracket, the first pulley mounting bracket and the pulley mounting groove.

[0011] The wire rope collecting wheel is fixedly mounted on the collecting wheel mounting bracket by bolts, and a handle is designed on the right side of the wire rope collecting wheel;

[0012] One end of the steel wire rope is fixedly connected in the fixing hole, and the other end passes through the hook, passes through the pulley of the pulley block after passing through the hook, and is finally fixedly connected to the steel wire rope collecting wheel.

[0013] As a further description of the present technical solution, the pulley group includes a first pulley, a second pulley, a third pulley, and a fourth pulley. The first pulley is connected to a first pulley mounting bracket, the second pulley is connected to a second pulley mounting bracket, the third pulley is connected to a third pulley mounting bracket, and the fourth pulley is connected to a pulley mounting groove.

[0014] As a further description of the technical solution, the wire rope is connected to the pulley block in the following manner: after passing through the hook, it is connected to the third pulley, after passing through the third pulley, it is connected to the second pulley, after passing through the second pulley, it is passed down along the hole of the first fixed rod to connect to the fourth pulley, after passing through the fourth pulley, it is connected to the first pulley, and after passing through the first pulley, it is fixedly connected to the wire rope collecting wheel.

[0015] As a further description of the technical solution, the hole below the first fixing rod is designed as a threaded structure, the top of the second fixing rod is designed as a threaded structure, and a base is designed below the second fixing rod.

[0016] As a further description of the technical solution, the hook is a self-locking hook, and the hook is rotatably connected to a self-locking buckle.

[0017] As a further description of the technical solution, the first fixing rod and the second fixing rod have the same height, both of which are 1.2 m.

[0018] As a further description of the technical solution, it also includes a meter box hoisting and fixing belt, which is a rectangular structure with connecting holes on its left and right ends.

[0019] As a further description of the technical solution, the length L1 of the meter box hoisting fixing belt is twice the height H of the power meter box plus 2.5 times its width W, that is:

[0020] L1=2H+2.5W

[0021] As a further description of the technical solution, the length L2 of the crossbeam is 1 / 2 of the length L of the power meter box plus 15 cm, that is:

[0022]

[0023] As a further description of the technical solution, the opening widths in the pulleys of the first pulley, the second pulley, the third pulley, and the fourth pulley are adapted to the diameter of the steel wire rope.

[0024] The method for using the above-mentioned power meter box installation auxiliary tool comprises the following steps:

[0025] S01: Assemble the first fixing rod and the second fixing rod, and thread the bottom of the first fixing rod and the top of the second fixing rod together;

[0026] S02: Use bolts to fix the fixing clamps on the left sides of the first fixing rod and the second fixing rod to the electric pole where the electric power meter box needs to be installed;

[0027] S03: Use the meter box lifting fixing belt to fix the power meter box and insert the hook into the connection hole;

[0028] S04: Shake the handle on the wire rope collection wheel to make the wire rope go along the pulley block to lift the power meter box on the hook;

[0029] S05: After lifting to the installation height, fix the handle, and the operator climbs up with the help of pole climbing tools to install a fixed cross arm at the installation position of the power meter box;

[0030] S06: Push the electricity meter box onto the cross arm and secure it to complete the installation.

[0031] Beneficial effects of the present invention:

[0032] The present invention discloses an auxiliary tool for installing an electric power meter box. The threaded connection structure of a first fixing rod and a second fixing rod is used to realize the assembly of the entire auxiliary tool at the installation site of the electric power meter box. The assembly method is simple and convenient, easy to operate in practice, and greatly improves work efficiency. At the same time, the length of the first fixing rod and the second fixing rod is designed to be 1.2m, which meets the transportation length requirement of a material transport vehicle at the actual installation site of the electric power meter box. The length of the first fixing rod and the second fixing rod after being connected meets the installation height requirement of the electric power meter box, which simplifies the connection process of the device in actual use. The height requirement is only achieved through threaded connection. The overall reliable and effective fixation of the device is achieved by fixing the clamp on the electric pole, and the device can be more efficiently applied to actual work.

[0033] The present invention discloses an auxiliary tool for installing an electricity meter box, wherein one end of the steel wire rope is fixedly connected in a fixing hole, and the other end passes through a hook, passes through the pulley of a pulley group after passing through the hook, and is finally fixedly connected to the steel wire rope collecting wheel. One end of the steel wire rope is fixed in the fixing hole, and the other end passes through the hook and is connected with each pulley of the pulley group. In this way, the hook slides on the steel wire rope between the fixing hole and the third pulley, and the hook needs to withstand two upward pulling forces on the fixing hole and the third pulley, so that the pulling force applied to the handle of the steel wire rope collecting wheel by the operator during the lifting process of the electricity meter box hung on the hook is reduced to half of the weight of the electricity meter box, thereby reducing labor intensity, improving work efficiency and work quality, and at the same time, compared with the traditional manual lifting method, the operation uses less human resources, saving labor costs.

[0034] The present invention provides an auxiliary tool for installing an electric power meter box, which also includes a meter box lifting and fixing belt. The fixing belt is a rectangular structure with connecting holes at its left and right ends. The electric power meter box is fixed by using the meter box lifting and fixing belt and the hook is inserted into the connecting hole. The operation step is simple and convenient. Since the electric power meter box is lifted in the meter box lifting and fixing belt, the fixing belt has a large area. It applies an upward pulling force to the electric power meter box while making the pressure per unit area of ​​the fixing belt small. Compared with the method of installing the buckle on the electric power meter box for lifting, it is safer and greatly reduces the potential safety hazards in the installation process of the electric power meter box.

[0035] The present invention provides an auxiliary tool for installing an electric power meter box. The opening widths in the pulleys of the first pulley, the second pulley, the third pulley and the fourth pulley are adapted to the diameter of the wire rope, so that the position of the wire rope in each pulley of the pulley group is fixed during the actual lifting process, avoiding deviation and improving the working efficiency and quality.

[0036] The present invention provides an auxiliary tool for installing an electric power meter box. The length L2 of the crossbeam is 1 / 2 of the length L of the electric power meter box plus 15 cm. The setting of this distance ensures that the electric power meter box is closer to a device that needs to be fixed during the lifting process. After being lifted to a corresponding appropriate position, it is more convenient to install without consuming more manpower and physical strength, thereby achieving efficient operation. The 15 cm is an operating distance reserved in actual operation, which is convenient for timely adjusting the posture of the electric power meter box. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] Figure 1 This is a schematic diagram of the overall three-dimensional structure of an auxiliary tool for installing an electric power meter box proposed by the present invention;

[0038] Figure 2 A schematic diagram of a first fixing rod and its connection relationship structure of an auxiliary tool for installing an electric power meter box proposed by the present invention;

[0039] Figure 3 A schematic diagram of a second fixing rod and its connection relationship structure of an auxiliary tool for installing an electric power meter box proposed by the present invention;

[0040] Figure 4 This is a schematic diagram of the structure below the first fixing rod of an auxiliary tool for installing an electric power meter box proposed by the present invention;

[0041] Figure 5 This is a schematic diagram of the upper end structure of a first fixing rod of an auxiliary tool for installing an electric power meter box proposed by the present invention;

[0042] Figure 6 A schematic diagram of a hook structure of an auxiliary tool for installing an electric power meter box proposed by the present invention;

[0043] Figure 7 A schematic diagram of the structure of a meter box hoisting fixing belt of an auxiliary tool for installing an electric power meter box proposed by the present invention;

[0044] Figure 8 A physical picture of an auxiliary tool for installing an electric power meter box proposed by the present invention;

[0045] Fig. 9 This is a physical structural diagram of a first fixing rod and its connection relationship of an auxiliary tool for installing an electric power meter box proposed by the present invention.

[0046] Description of Reference Numerals

[0047] 1-first fixed rod, 11-pulley mounting groove, 12-collection wheel mounting bracket, 13-first pulley mounting bracket, 2-second fixed rod, 21-base, 3-fixed hoop, 4-crossbeam, 41-second pulley mounting bracket, 42-third pulley mounting bracket, 43-fixed block, 431-fixed hole, 5-pulley block, 51-first pulley, 52-second pulley, 53-third pulley, 54-fourth pulley, 6-wire rope collecting wheel, 61-handle, 7-wire rope, 8-hook, 81-self-locking buckle, 9-metering box lifting fixing belt, 91-connecting hole. DETAILED DESCRIPTION

[0048] The specific implementation of the present invention is described below in conjunction with the accompanying drawings and embodiments:

[0049] It should be noted that the structures, proportions, sizes, etc. illustrated in the drawings of this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read, and are not used to limit the conditions under which the present invention can be implemented. Any structural modification, change in proportional relationship or adjustment of size should still fall within the scope of the technical contents disclosed in the present invention without affecting the effects and purposes that can be achieved by the present invention.

[0050] At the same time, the terms such as "upper", "lower", "left", "right", "middle" and "one" cited in this specification are only for the convenience of description and are not used to limit the scope of implementation of the present invention. Changes or adjustments to their relative relationships should be regarded as the scope of implementation of the present invention without substantially changing the technical content.

[0051] like Figures 1 to 7 As shown, it shows a specific embodiment of the present invention:

[0052] Embodiment 1

[0053] The present invention discloses an auxiliary tool for installing an electric power meter box, comprising a first fixing rod 1, a second fixing rod 2, a fixing hoop 3, a crossbeam 4, a pulley block 5, a wire rope collecting wheel 6, a wire rope 7, and a hook 8.

[0054] The first fixing rod 1 and the second fixing rod 2 are made of steel pipes. A pulley mounting groove 11 is provided at the lower end of the first fixing rod 1. A collecting wheel mounting bracket 12 is welded to the lower end of the first fixing rod 1 below the pulley mounting groove 11, and a first pulley mounting bracket 13 is welded to the upper end.

[0055] The fixing hoop 3 is welded to the left side of the first fixing rod 1 and the second fixing rod 2.

[0056] The cross beam 4 is welded to the upper end of the first fixing rod 1, a second pulley mounting bracket 41 is welded on the left side above the cross beam 4, the right side of the cross beam 4 is an open structure, and a third pulley mounting bracket 42 is designed, a fixing block 43 is welded on the right side below the cross beam 4, and a fixing hole 431 is opened on the fixing block 43,

[0057] The pulleys of the pulley block 5 are respectively mounted in the third pulley mounting bracket 42, the second pulley mounting bracket 41, the first pulley mounting bracket 13 and the pulley mounting groove 11.

[0058] The wire rope collecting wheel 6 is fixedly mounted on the collecting wheel mounting bracket 12 by bolts, and a handle 61 is designed on the right side of the wire rope collecting wheel 6;

[0059] One end of the steel wire rope 7 is fixedly connected in the fixing hole 431 , and the other end passes through the hook 8 , passes through the pulley of the pulley block 5 , and is finally fixedly connected to the steel wire rope collecting wheel 6 .

[0060] In the present invention, Figure 1 As shown, the overall structure of the auxiliary tool for installing the power meter box is used. The use of the auxiliary tool is achieved by assembling the first fixing rod 1 and the second fixing rod 2. The fixing clamp 3 is fixed to the electric pole where the power meter box needs to be installed to fix the entire device. Since the electric pole has been fixed and is in a stable state, the first fixing rod 1 and the second fixing rod 2 are also in a relatively stable state. They can provide effective supporting force for the power meter box that needs to be lifted, thereby ensuring the safe lifting of the power meter box.

[0061] like Figure 1As shown, the power meter box provides an upward pulling force to lift the power meter box through the wire rope 7 of the auxiliary tool passing through the hook 8. Since one end of the wire rope 7 is fixedly connected in the fixing hole 431, and the other end passes through the hook 8, it passes through the pulley of the pulley group 5 after passing through the hook 8 and is finally fixedly connected to the wire rope collecting wheel 6. In this connection method, the hook 8 slides on the wire rope 7 between the fixing hole 431 and the third pulley 43, and the hook 8 needs to withstand two upward pulling forces on the fixing hole 431 and the third pulley 43, so that the pulling force applied to the wire rope collecting wheel handle 61 by the operator during the lifting process of the power meter box hung on the hook 8 is reduced to half of the gravity of the power meter box, thereby reducing labor intensity, improving work efficiency and work quality. At the same time, compared with the traditional manual lifting method, this operation uses less human resources and saves labor costs.

[0062] like Figure 1 As shown, the wire rope collecting wheel 6 is located below the first fixing rod 1. When the device is fixed and the power meter box is lifted, the position of the wire rope collecting wheel 6 is convenient for operators to operate according to the height of the human body without bending over. The design of this position reduces the labor intensity of the operators and is also convenient for improving the working efficiency. A handle 61 is designed on the right side of the wire rope collecting wheel 6. The handle 61 can be a detachable design. When in use, it is installed on the right side of the wire rope collecting wheel 6. The handle is turned to realize the lifting and lowering of the power meter box. It is removed when not in use to avoid safety accidents caused by the operation of non-operators and ensure the safety of the use of the device.

[0063] Specifically, the pulley group 5 includes a first pulley 51, a second pulley 52, a third pulley 53, and a fourth pulley 54. The first pulley 51 is connected to the first pulley mounting bracket 13, the second pulley 52 is connected to the second pulley mounting bracket 41, the third pulley 53 is connected to the third pulley mounting bracket 42, and the fourth pulley 54 is connected to the pulley mounting groove 11.

[0064] Specifically, the wire rope 7 is connected to the pulley block 5 in the following manner: after passing through the hook 8, it is connected to the third pulley 53; after passing through the third pulley 53, it is connected to the second pulley 52; after passing through the second pulley 52, it passes down through the hole of the first fixed rod 1 and is connected to the fourth pulley 54; after passing through the fourth pulley 54, it is connected to the first pulley 51; after passing through the first pulley 51, it is fixedly connected to the wire rope collecting wheel 6.

[0065] like Figure 4 , Figure 5As shown, the pulleys of the pulley block 5 are respectively installed at relative positions, and the wire rope 7 is transmitted on each pulley, and the lifting of the hook 8 is achieved by shaking the handle 61. The specific process is that after the preliminary preparation work is completed, the operator installs the handle 61 on the right end of the wire rope collecting wheel 6 and rotates the handle 61. At this time, the right side of the first pulley 51 is affected by the tension of the wire rope 7 and moves downward. At the same time, the wire rope 7 on the left side of the first pulley 51 runs under the tension of the wire rope 7 on its right side, and the right side of the fourth pulley 54 is affected by the upward tension of the wire rope 7. At this time, the wire rope 7 on the left side of the fourth pulley 54 is affected by tension and runs under the tension of the wire rope 7 on its right side. The left side of the second pulley 52 is subjected to a downward pulling force, and the wire rope 7 on the right side of the second pulley 52 provides a pulling force to the left side of the third pulley 53 under the action of the pulling force on its left side, and the wire rope 7 on the right side of the third pulley 53 is subjected to an upward pulling force under the action of the pulling force on its left side. This is because one end of the wire rope 7 is subjected to the pulling force on the fixed block 43, and the other end is subjected to the pulling force on the right side of the third pulley 53. Under the action of two sets of pulling forces, the hook 8 connected to the wire rope 7 moves upward, so that the power meter box connected to the hook 8 is lifted. The pulley group 5 realizes the convenient and effective lifting of the power meter box by changing the direction of the force, thereby reducing the workload of the installation personnel and improving work efficiency.

[0066] In general, the auxiliary tool solves the difficulties encountered in the installation of the electricity meter box on the utility pole. It provides a stable support by fixing the clamp 3, changes the direction of force by the pulley group 5, and is convenient for the staff to operate. The handle 61 is set at a position convenient for the staff to operate, avoiding bending and other actions, reducing the labor intensity of the operation, and using the pulley group 5 to provide two groups of upward pulling forces to the hook 8 to reduce the work intensity of the lifting operation. The device is applied to the actual installation site of the electricity meter box, which can reduce the installation difficulty, improve the installation efficiency, and reduce the risk of manual operation. It needs to have the characteristics of lightness, flexibility, stability, etc., can adapt to various complex installation environments, and can quickly and accurately complete the installation of the meter box, improving work efficiency and work quality.

[0067] Embodiment 2

[0068] On the basis of the above-mentioned embodiment 1, in order to make the auxiliary tool more simple and convenient in actual on-site use, embodiment 2 is proposed:

[0069] Specifically, the hole below the first fixing rod 1 is designed as a threaded structure, the top of the second fixing rod 2 is designed as a threaded structure, and a base 21 is designed below the second fixing rod 2.

[0070] Specifically, the first fixing rod 1 and the second fixing rod 2 have the same height, which is 1.2 m.

[0071] like Figure 2, Figure 3 As shown, the assembly of the entire auxiliary tool at the installation site of the power meter box is achieved through the threaded connection structure of the first fixing rod 1 and the second fixing rod 2. This assembly method is simple and convenient, easy to operate in practice, and greatly improves work efficiency. At the same time, the length of the first fixing rod 1 and the second fixing rod 2 is designed to be 1.2m, which meets the transportation length requirement of the material transport vehicle at the actual power meter box installation site. A base 21 is designed under the second fixing rod 2 to facilitate its stable and effective installation.

[0072] The current power construction specifications require that the installation of a three-phase four-wire power meter box be 1.4m away from the bottom of the power meter box. Since the height of the three-phase four-wire power meter box itself is 0.8m, the length of the first fixing rod 1 and the second fixing rod 2 is designed to be 1.2m. The length of the first fixing rod 1 and the second fixing rod 2 after connection is 1.4m, which meets the installation height requirement of the power meter box and simplifies the connection process of the device in actual use. The height requirement is achieved only through threaded connection, and the overall reliable and effective fixation of the device is achieved by fixing the fixing clamp 3 on the pole, which can be more efficiently applied to actual work and improve work efficiency.

[0073] In general, the structural design of this embodiment makes it easier for the auxiliary tool to be assembled at the actual application site, making it easier for operators to complete the assembly and carry out the corresponding installation work in a short time. Its height design meets the requirements and ensures reliable and effective installation.

[0074] Embodiment 3

[0075] On the basis of the above-mentioned Embodiment 1 and Embodiment 2, in order to make the auxiliary tool safer in field application, reduce the probability of safety accidents, and ensure the safety of operators during the operation, Embodiment 3 is proposed:

[0076] Specifically, the hook 8 is a self-locking hook, and the hook 8 is rotatably connected to a self-locking buckle 81.

[0077] In this embodiment, if Figure 6 As shown, the self-locking buckle 81 is rotatably connected to the open position of the hook 8. Since the power meter box is heavy, safety is particularly important when performing corresponding operations at high altitudes. The design of the self-locking buckle 81 allows the operator to open the self-locking buckle 81 during connection to effectively connect the power meter box. During the lifting process, due to the presence of the self-locking buckle 81, the hook 8 is in a closed structure. When the power meter box swings, shakes, or other postures that are not conducive to installation occur during the lifting process, the hook 8 will not fall off, thereby ensuring operational safety and reducing safety hazards.

[0078] Specifically, it also includes a meter box hoisting and fixing belt 9, which is a rectangular structure with connecting holes 91 at its left and right ends.

[0079] In this embodiment, Figure 1 and Figure 7 As shown, the meter box hoisting and fixing belt 9 is used to fix the power meter box. The meter box hoisting and fixing belt 9 is a rectangular structure with connection holes 91 at both ends. The meter box hoisting and fixing belt 9 is used to fix the power meter box and the hook 8 is inserted into the connection hole 91. This operation step is simple and convenient to operate, easy to implement, and improves efficiency. Since the power meter box is lifted in the meter box hoisting and fixing belt 9, the fixing belt area is large. While it gives the power meter box an upward pulling force, the pressure per unit area of ​​the meter box hoisting and fixing belt 9 is small. Compared with the method of installing the buckle on the power meter box for lifting, it is safer and greatly reduces the potential safety hazards in the installation process of the power meter box.

[0080] In this embodiment, in order to ensure the effective and safe lifting of the electric meter box during the working process, a heavy-duty and wear-resistant material can be used as the manufacturing material of the meter box lifting and fixing belt 9, such as nylon. The nylon material molecular chain contains a large number of amide groups and imine groups. The covalent bonds and hydrogen bonds between these groups interact with each other, making the nylon molecular chain very stable and tight, showing extremely high strength and toughness. In addition, the tensile strength of nylon is higher than that of other synthetic fibers, and a light and sturdy product can be made. This material can be suitable for the use requirements of the meter box lifting and fixing belt 9 to ensure safe and reliable operation.

[0081] Embodiment 4

[0082] In the actual construction process of installing the power meter box on the electric pole, on the basis of the above three embodiments, the work efficiency is further improved, and the fourth embodiment is proposed:

[0083] Specifically, the length L1 of the meter box hoisting fixing belt 9 is twice the height H of the power meter box plus 2.5 times its width W, that is:

[0084] L1=2H+2.5W

[0085] Specifically, the length L2 of the crossbeam 4 is 1 / 2 of the length L of the power meter box plus 15 cm, that is:

[0086]

[0087] In this embodiment, the length of the meter box lifting fixing belt 9 is limited to ensure that the power meter box to be installed can be effectively fixed on the hook 8. Its length is designed to be twice the height H of the power meter box plus 2.5 times its width W, which can just wrap the four sides of the power meter box, and at the same time reserve a margin of 0.5 times the width to ensure the operating capacity.

[0088] In this embodiment, the length L2 of the crossbeam 4 is 1 / 2 of the length L of the power meter box plus 15 cm. The setting of this distance ensures that the power meter box is closer to the position that needs to be fixed during the lifting process. At the power meter box installation site, after the power meter box is lifted to the corresponding appropriate position, it is more convenient to install without consuming more manpower and physical strength, thereby achieving efficient operation. The 15 cm is the operating distance reserved in actual operation, which is convenient for timely adjustment of the posture of the power meter box.

[0089] Specifically, the opening widths of the first pulley 51 , the second pulley 52 , the third pulley 53 , and the fourth pulley 54 are adapted to the diameter of the steel wire rope 7 .

[0090] In this embodiment, the opening widths in the first pulley 51, the second pulley 52, the third pulley 53, and the fourth pulley 54 are adapted to the diameter of the wire rope 7, so that the position of the wire rope 7 in each pulley of the pulley block 5 is fixed during the actual lifting process, avoiding deviation and improving the working efficiency and quality.

[0091] Embodiment 5

[0092] On the basis of the above four embodiments, in order to make the auxiliary device better applied on site and enable the operators to complete the corresponding work more efficiently and with higher quality, the following embodiment 5 is specially proposed:

[0093] The method for using the above-mentioned power meter box installation auxiliary tool comprises the following steps:

[0094] S01: Assemble the first fixing rod 1 and the second fixing rod 2, and thread the bottom of the first fixing rod 1 and the top of the second fixing rod 2 together;

[0095] S02: Fix the fixing clamps 3 on the left sides of the first fixing rod 1 and the second fixing rod 2 to the electric pole where the electric power meter box needs to be installed using bolts;

[0096] S03: Use the meter box hoisting fixing belt 9 to fix the power meter box and insert the hook 8 into the connecting hole 91;

[0097] S04: Shake the handle 61 on the wire rope collecting wheel 6 to make the wire rope 7 move along the pulley block 5 to lift the power meter box on the hook 8;

[0098] S05: After the lifting is to the installation height, the handle 61 is fixed, and the operator climbs up with the help of a pole climbing tool to install a fixed cross arm at the installation position of the power meter box;

[0099] S06: Push the electricity meter box onto the cross arm and secure it to complete the installation.

[0100] In this embodiment, during the process of installing the power meter box on the electric pole using the above steps, the relevant operating steps are clarified to facilitate the actual work of the operators, ensure the safety during the operation, reduce safety hazards, and improve work efficiency.

[0101] The preferred embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge scope of ordinary technicians in this field without departing from the purpose of the present invention.

[0102] Many other changes and modifications may be made without departing from the concept and scope of the present invention.It should be understood that the present invention is not limited to the specific embodiments, and the scope of the present invention is defined by the appended claims.

Claims

1. An auxiliary tool for installing an electric power meter box, characterized in that: It comprises a first fixing rod (1), a second fixing rod (2), a fixing hoop (3), a crossbeam (4), a pulley block (5), a wire rope collecting wheel (6), a wire rope (7), and a hook (8). The first fixing rod (1) and the second fixing rod (2) are made of steel pipes. A pulley mounting groove (11) is provided at the lower end of the first fixing rod (1). A collecting wheel mounting bracket (12) is welded to the lower end of the first fixing rod (1) below the pulley mounting groove (11), and a first pulley mounting bracket (13) is welded to the upper end. The fixing hoop (3) is welded to the left side of the first fixing rod (1) and the second fixing rod (2). The cross beam (4) is welded to the upper end of the first fixing rod (1); a second pulley mounting bracket (41) is welded on the left side above the cross beam (4); the right side of the cross beam (4) is an open structure and is provided with a third pulley mounting bracket (42); a fixing block (43) is welded on the right side below the cross beam (4); a fixing hole (431) is provided on the fixing block (43); The pulleys of the pulley block (5) are respectively mounted in the third pulley mounting bracket (42), the second pulley mounting bracket (41), the first pulley mounting bracket (13) and the pulley mounting groove (11). The wire rope collecting wheel (6) is fixedly mounted on the collecting wheel mounting bracket (12) by means of bolts, and a handle (61) is designed on the right side of the wire rope collecting wheel (6); One end of the steel wire rope (7) is fixedly connected in the fixing hole (431), and the other end passes through the hook (8), passes through the pulley of the pulley block (5), and is finally fixedly connected to the steel wire rope collecting wheel (6).

2. An auxiliary tool for installing an electric power meter box according to claim 1, characterized in that: The pulley block (5) comprises a first pulley (51), a second pulley (52), a third pulley (53), and a fourth pulley (54); the first pulley (51) is connected to a first pulley mounting bracket (13); the second pulley (52) is connected to a second pulley mounting bracket (41); the third pulley (53) is connected to a third pulley mounting bracket (42); and the fourth pulley (54) is connected to a pulley mounting groove (11).

3. An auxiliary tool for installing an electric power meter box according to claim 2, characterized in that: The steel wire rope (7) is connected to the pulley block (5) in the following manner: after passing through the hook (8), it is connected to the third pulley (53), after passing through the third pulley (53), it is connected to the second pulley (52), after passing through the second pulley (52), it passes down along the hole of the first fixing rod (1) to connect to the fourth pulley (54), after passing through the fourth pulley (54), it is connected to the first pulley (51), after passing through the first pulley (51), it is fixedly connected to the steel wire rope collecting wheel (6).

4. The auxiliary tool for installing an electric power meter box according to claim 1, characterized in that: The hole below the first fixing rod (1) is designed with a threaded structure, the top of the second fixing rod (2) is designed with a threaded structure, and a base (21) is designed below the second fixing rod (2).

5. The auxiliary tool for installing an electric power meter box according to claim 1, characterized in that: The hook (8) is a self-locking hook, and the hook (8) is rotatably connected to a self-locking buckle (81).

6. The auxiliary tool for installing an electric power meter box according to claim 1, characterized in that: The first fixing rod (1) and the second fixing rod (2) have the same height, both of which are 1.2 m.

7. The auxiliary tool for installing an electric power meter box according to claim 1, characterized in that: It also includes a meter box hoisting and fixing belt (9), which is a rectangular structure with connection holes (91) at its left and right ends.

8. The auxiliary tool for installing an electric power meter box according to claim 7, characterized in that: The length L1 of the meter box hoisting fixing belt (9) is twice the height H of the power meter box plus 2.5 times its width W, that is: L2H + 2.5W.

9. The auxiliary tool for installing an electric power meter box according to claim 1, characterized in that: The length L2 of the crossbeam (4) is 1 / 2 of the length L of the power meter box plus 15 cm, that is:

10. The auxiliary tool for installing an electric power meter box according to claim 2, characterized in that: The opening widths in the first pulley (51), the second pulley (52), the third pulley (53) and the fourth pulley (54) are adapted to the diameter of the steel wire rope (7).

11. A method for using the power meter box installation auxiliary tool according to any one of claims 1 to 10, characterized in that: The following steps are involved: S01: Assembling the first fixing rod (1) and the second fixing rod (2), and threading the bottom of the first fixing rod (1) and the top of the second fixing rod (2) together; S02: Using bolts, fix the fixing clamps (3) on the left sides of the first fixing rod (1) and the second fixing rod (2) to the electric pole where the electric power meter box is to be installed; S03: Use the meter box hoisting fixing belt (9) to fix the power meter box and insert the hook (8) into the connecting hole (91); S04: Shake the handle (61) on the wire rope collecting wheel (6) to make the wire rope (7) move along the pulley block (5) to lift the power meter box on the hook (8); S05: After the pole is lifted to the installation height, the handle (61) is fixed, and the operator climbs up with the help of a pole climbing tool to install a fixed cross arm at the installation position of the power meter box; S06: Push the electricity meter box onto the cross arm and secure it to complete the installation.

Citation Information

Patent Citations

  • Metering box installation auxiliary device and metering box wall installation single-person operation method

    CN116812739A