River ecological sheet pile construction system and method

By using mobile water operation platforms and guide positioning devices in the river and surfing area, the problems of inconvenience and low efficiency are solved, and efficient slope protection and flood prevention effects are achieved.

CN118933001APending Publication Date: 2024-11-12GUANGDONG YUANTIAN ENG
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410989730.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-23
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The construction of existing river surfing sheet piles has problems such as inconvenience and low construction efficiency. Especially in river surfing areas in large cities, due to the existence of houses and buildings on the shore, it is difficult to carry out ecological sheet pile construction on the shore.

Method used

Provide a Hechun ecological sheet pile construction system, including a mobile water operation platform, lifting and pile driving equipment and guide positioning devices, and lifting ecological sheet piles are lifted, pile driving and positioning grooves through the water operation platform to ensure installation accuracy and efficiency .

Benefits of technology

Through the combination of the water operation platform and the guide positioning device, the problems of inconvenience and low efficiency are solved, precise installation of ecological sheet piles is achieved, construction efficiency is improved, and the protection of shore slopes and flood prevention needs are ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933001A_ABST
    Figure CN118933001A_ABST
Patent Text Reader

Abstract

The invention relates to a river ecological sheet pile construction system and method.The river ecological sheet pile construction system comprises a movable type overwater operation platform, hoisting and piling equipment installed on the movable type overwater operation platform and a guiding and positioning device placed on the movable type overwater operation platform; the guiding and positioning device is provided with a positioning groove in a vertically-through mode, and the ecological sheet pile can be vertically inserted into the positioning groove. By the adoption of the technical scheme, the technical problems that an existing river branch sheet pile is inconvenient to construct and low in construction efficiency can be solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of riverbank pile foundation engineering, and in particular to a river stream ecological sheet pile construction system and method. Background Art

[0002] In some coastal areas, due to the long-term erosion of river water and tidal backflow of seawater, it is necessary to set up protective projects to control the slope collapse of the river and effectively control and protect the river from erosion by river water and tides. Setting up ecological sheet piles on both sides of the river to form protection can not only promote flood control work, but also form an overall engineering structure more quickly to achieve the purpose of preliminary flood control. Especially in salty and corrosive environments, ecological sheet piles can better meet environmental requirements.

[0003] At present, most ecological sheet piles are basically driven on land or on embankments. This construction method has high requirements on the bearing capacity of the shore, and needs to meet the traffic requirements of pile drivers and ecological sheet pile transporters, and may have a certain impact on existing structures or preparations on the shore. For rivers and creeks in large cities, due to the presence of residential houses or other buildings on both sides of the banks, the construction requirements for driving ecological sheet piles on the shore are not met. Therefore, the existing river and creek sheet piles have the problems of inconvenient construction and low construction efficiency. Summary of the invention

[0004] Aiming at the technical problems of inconvenient construction and low construction efficiency of existing river creek sheet piles, the present invention provides a river creek ecological sheet pile construction system and method.

[0005] The technical solution of the present invention to solve the above technical problems is as follows:

[0006] On the one hand, the present invention provides a river ecological sheet pile construction system, including a mobile water working platform, a lifting and piling equipment installed on the mobile water working platform, and a guiding and positioning device placed on the mobile water working platform, wherein the guiding and positioning device is provided with a positioning groove for the vertical insertion of the ecological sheet piles through the upper and lower parts.

[0007] The beneficial effects of the present invention are as follows: a mobile water working platform is provided to facilitate water working, thus avoiding the problem of limited working space in shore working in the prior art, which affects the working progress; and lifting and piling equipment is provided to lift and pile the guiding and positioning device and the ecological sheet piles. That is, after the guiding and positioning device placed on the mobile water working platform is lifted and fixed in the waiting working area by the lifting and piling equipment, the ecological sheet pile is lifted and piled from the positioning groove by the lifting and piling equipment, and the guiding installation is completed by the positioning groove, thereby ensuring the installation accuracy and improving the technical problems of the existing river creek sheet piles, such as the inconvenience in construction and the low construction efficiency.

[0008] Based on the above technical solution, the present invention can also be improved as follows.

[0009] Furthermore, the guiding and positioning device includes a positioning guide beam and a central positioning component fixed to one end of the positioning guide beam, the positioning groove is opened on the positioning guide beam, and an installation groove connected to the positioning groove is opened at the bottom of the central positioning component, and the installation groove is used for vertical insertion of ecological sheet piles.

[0010] The beneficial effect of adopting the above-mentioned further scheme is: when the guiding and positioning device is lifted and fixed in the work area by the lifting and piling equipment, the first ecological sheet pile is lifted and piled by the lifting and piling equipment, and then the guiding and positioning device is lifted and piled, so that the first ecological sheet pile is inserted into the installation groove, and the positioning installation of the guiding and positioning device is completed, so that the lifting and piling operations of other ecological sheet piles can be carried out accurately in sequence.

[0011] Furthermore, the guiding and positioning device also includes an axis positioning pile, which includes an elevation positioning sleeve detachably connected to the middle end of the positioning guide beam and a pile body slidably connected to the elevation positioning sleeve, and the pile body is inserted into the positioning groove.

[0012] The beneficial effect of adopting the above-mentioned further scheme is: the guide positioning device is lifted and piled so that the first ecological sheet pile is inserted into the installation groove. After the positioning and installation of the guide positioning device is completed, the pile body is lifted and piled to complete the positioning and installation of the guide positioning device by utilizing the action of the pile body and the first ecological sheet pile, thereby ensuring the accuracy of subsequent ecological sheet pile construction.

[0013] Furthermore, both ends of the guiding and positioning device are fixed with lifting rings.

[0014] The beneficial effect of adopting the above further solution is that the lifting and piling equipment can be used to lift the guide positioning device through the lifting ring.

[0015] Furthermore, the guide positioning device is equipped with a locking device, which includes two hoist tensioners installed at one end of the guide positioning device and spaced apart on both sides of the positioning groove, two pull ropes parallel to each other and one end of which is respectively connected to the two hoist tensioners, and a locking piece simultaneously connected to the other ends of the two pull ropes.

[0016] The beneficial effect of adopting the above-mentioned further scheme is that when the ecological sheet pile is hoisted in the positioning groove, the locking piece can be tightened by two sets of hoist tensioners to drive the ecological sheet pile to move horizontally and press against the previous ecological sheet pile. At the same time, during the piling process, the tightened locking piece can be used to ensure the verticality of the vertical movement of the ecological sheet pile.

[0017] Furthermore, the locking member includes a roller and two pull plates, one end of which is rotatably connected to the end of the roller, and the other ends of the two pull plates are respectively connected to the two pull ropes.

[0018] The beneficial effect of adopting the above further solution is that during the process of tightening the locking member, the roller is in close contact with the ecological sheet pile.

[0019] Furthermore, the mobile water working platform includes a water working platform, a plurality of platform anchoring devices installed on the water working platform, and a driving device for driving the water working platform to move forward.

[0020] The beneficial effect of adopting the above further scheme is that when in use, the water working platform is used as an operating platform for lifting and piling equipment; specifically, the water working platform is moved to the designated construction area through the driving device, and anchor cables are set through the platform anchoring device to fix the platform at the set position.

[0021] Furthermore, the above-water operation platform is provided with a stacking area for storing ecological sheet piles.

[0022] The beneficial effect of adopting the above further solution is that the ecological sheet piles to be injected can be piled up in the stacking area, thereby improving the injection efficiency.

[0023] Furthermore, the above-water operation platform is provided with an operation area, and the lifting and piling equipment is arranged in the operation area.

[0024] The beneficial effect of adopting the above further solution is that it is possible to carry out related operations such as lifting and piling in the operating area.

[0025] On the other hand, the present invention provides a river stream ecological sheet pile construction method, which is applied to the river stream ecological sheet pile construction system, and comprises the following steps:

[0026] The mobile water operation platform moves and stops at the waiting operation area;

[0027] The guiding and positioning device is hoisted into place;

[0028] The hoisting and piling of multiple ecological sheet piles are carried out in sequence. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 It is an overall diagram of the river ecological sheet pile construction system of the present invention;

[0030] Figure 2 for Figure 1 Middle partial enlarged picture;

[0031] Figure 3 for Figure 2 Middle partial enlarged picture;

[0032] Figure 4 The present invention is a flow chart of the river stream ecological sheet pile construction method.

[0033] In the accompanying drawings, the components represented by the reference numerals are listed as follows:

[0034] 1. Ecological sheet piles;

[0035] 2. Mobile water operation platform; 21. Water operation platform; 211. Stacking area; 212. Operation area; 22. Platform anchoring device; 23. Driving device;

[0036] 3. Lifting and piling equipment;

[0037] 4. Guide and positioning device; 41. Positioning guide beam; 42. Center positioning assembly; 421. Mounting groove; 43. Axis positioning pile; 431. Elevation positioning sleeve; 432. Pile body; 44. Lifting ring;

[0038] 5. Positioning slot;

[0039] 6. Locking device; 61. Hoist tensioner; 62. Pull rope; 63. Locking piece; 631. Roller; 632. Pull plate. DETAILED DESCRIPTION

[0040] The principles and features of the present invention are described below. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.

[0041] On the one hand, the present invention provides a river ecological sheet pile construction system, which is described in detail below.

[0042] Example 1

[0043] like Figure 1 and Figure 2 A river ecological sheet pile construction system includes a mobile water working platform 2, a lifting and piling device 3 installed on the mobile water working platform 2, and a guide positioning device 4 placed on the mobile water working platform 2. The guide positioning device 4 is provided with a positioning groove 5 for vertical insertion of the ecological sheet pile 1 from top to bottom.

[0044] The beneficial effects of this embodiment are: a mobile water operation platform 2 is set up to facilitate water operations, avoiding the problem of limited working space in shore operations in the prior art, which affects the progress of operations, and a lifting and piling device 3 is set up to lift and pile the guide positioning device 4 and the ecological sheet pile 1. That is, after the guide positioning device 4 is lifted and fixed to the work area by the lifting and piling device 3, the ecological sheet pile 1 is lifted and piled from the positioning groove 5 by the lifting and piling device 3, and the positioning groove 5 is used to complete the guided installation, thereby ensuring the installation accuracy and improving the technical problems of the existing river creek sheet piles, such as inconvenient construction and low construction efficiency.

[0045] As a specific solution of the above-mentioned embodiment, the mobile water operation platform 2 is used to provide a construction platform and a temporary stacking site for the ecological sheet piles 1 and the lifting and piling equipment 3 on the water surface of the river.

[0046] Among them, one side of the ecological sheet pile 1 is integrally formed with a raised semi-cylinder, and the other side is relatively provided with an arc groove matching the raised semi-cylinder, so that a tight tongue-and-groove device is formed between the two ecological sheet piles 1 by setting the raised semi-cylinder and the recessed arc groove, which can improve the tightness and integrity between the ecological sheet piles, prevent soil erosion on the slope, and protect the bank slope.

[0047] The lifting and piling equipment 3 may be a pile driver, and during the lifting work, the clamping mechanism is performed through the chuck of the pile driver.

[0048] The distance of the guiding and positioning device 4 relative to the mobile water working platform 2 can be determined through actual use. The mobile water working platform 2 is located on the horizontal plane, and the guiding and positioning device 4 is located in the working area of ​​the ecological sheet pile 1.

[0049] Example 2

[0050] like Figure 2 and Figure 3 On the basis of Example 1, the guiding and positioning device 4 includes a positioning guiding beam 41 and a central positioning component 42 fixed to one end of the positioning guiding beam 41, the positioning groove 5 is opened on the positioning guiding beam 41, and an installation groove 421 connected to the positioning groove 5 is opened at the bottom of the central positioning component 42, and the installation groove 421 is used for inserting the ecological sheet pile 1.

[0051] The beneficial effect of adopting the preferred scheme in the above embodiment is that when the guiding and positioning device 4 is lifted and fixed to the work area by the lifting and piling equipment 3, the first ecological sheet pile 1 is first lifted and piled by the lifting and piling equipment 3, and then the guiding and positioning device 4 is lifted and piled, so that the first ecological sheet pile 1 is vertically inserted into the installation groove 421, completing the positioning and installation of the guiding and positioning device 4, so as to accurately carry out the lifting and piling operations of other ecological sheet piles 1 in sequence.

[0052] As a specific solution of the above embodiment, the positioning guide beam 41 includes two parallel I-beams and fixing plates welded to both ends of the two I-beams to form a rectangular frame structure, and a positioning groove 5 is formed in the middle of the rectangular frame structure.

[0053] On the basis of the above-mentioned embodiment, when the guide positioning device 4 is hoisted by the hoisting and piling equipment 3 , a steel wire rope may be used to assist in the hoisting so as to maintain the balance of the guide positioning device 4 during the hoisting process.

[0054] Specifically, when performing the lifting and piling operation of the first ecological sheet pile 1, RTK can be used in conjunction with the theodolite and measurement and positioning to perform positioning measurement of the first ecological sheet pile 1. After determining the position and axis of the first ecological sheet pile 1, the first ecological sheet pile 1 is driven through the lifting and piling equipment 3 until it reaches the predetermined elevation, thereby completing the driving of the first ecological sheet pile 1.

[0055] Example 3

[0056] like Figure 2 and Figure 3 On the basis of embodiments 1 and 2, the guiding and positioning device 4 also includes an axis positioning pile 43, which includes an elevation positioning sleeve 431 detachably connected to the middle end of the positioning guide beam 41 and a pile body 432 slidably connected to the elevation positioning sleeve 431, and the pile body 432 is inserted into the positioning groove 5.

[0057] The beneficial effect of adopting the preferred scheme in the above embodiment is that the guide positioning device 4 is lifted and piled so that the first ecological sheet pile 1 is inserted into the installation groove 421. After the positioning and installation of the guide positioning device 4 is completed, the pile body 432 is lifted and piled, so as to utilize the pile body 432 and the first ecological sheet pile 1 to complete the positioning and installation of the guide positioning device 4, thereby ensuring the accuracy of the subsequent construction of the ecological sheet pile 1.

[0058] Based on the above embodiment, the elevation positioning sleeve 431 is detachably connected to the positioning guide beam 41 by bolts (not shown in the figure) so as to adjust the position of the elevation positioning sleeve 431 by the detachable connection.

[0059] The bottom of the pile body 432 is conical, which facilitates the rapid driving and pulling of the pile body 432 .

[0060] Example 4

[0061] like Figure 2 and Figure 3 On the basis of embodiments 1-3, both ends of the guide positioning device 4 are fixed with lifting rings 44.

[0062] The beneficial effect of adopting the preferred solution in the above embodiment is that the lifting and piling equipment 3 can be used to lift the guide positioning device 4 through the lifting ring 44.

[0063] As a specific solution of the above embodiment, two hanging rings 44 are fixedly installed on the fixing plate and the top of the center positioning assembly 42 respectively.

[0064] Example 5

[0065] like Figure 2 and Figure 3On the basis of Examples 1-4, the guide positioning device 4 is installed with a locking device 6, which includes two hoist tensioners 61 installed at one end of the guide positioning device 4 and spaced apart on both sides of the positioning groove 5, two pull ropes 62 that are parallel to each other and one end of which is respectively connected to the two hoist tensioners 61, and a locking member 63 that is simultaneously connected to the other ends of the two pull ropes 62.

[0066] The beneficial effect of adopting the preferred scheme in the above embodiment is that when the ecological sheet pile 1 is hoisted in the positioning groove 5, the locking piece 63 can be tightened by two sets of hoist tensioners 61 to drive the ecological sheet pile 1 to move horizontally and press against the previous ecological sheet pile 1. At the same time, during the piling process, the tightened locking piece 63 can be used to ensure the verticality of the vertical movement of the ecological sheet pile 1.

[0067] The hoist tensioner 61 can be installed on the positioning guide beam 41 or the center positioning component 42 .

[0068] Example 6

[0069] like Figure 2 and Figure 3 On the basis of embodiments 1-5, the locking member 63 includes a roller 631 and two pull plates 632 whose one ends are rotatably connected to the ends of the roller 631, and the other ends of the two pull plates 632 are respectively connected to the two pull ropes 62.

[0070] The beneficial effect of adopting the preferred solution in the above embodiment is that, during the process of tightening the locking member 63 , the roller 631 is closely attached to the ecological sheet pile 1 .

[0071] The specific operation is as follows: first, fix one end of the pull rope 62 on the hoist tensioner 61, and then use the lifting and piling equipment 3 to slowly sink the ecological sheet pile 1 close to the tongue and groove position of the previous ecological sheet pile 1 until it passes through the guide positioning device 4. By adjusting the pull rope 62, both sides are adjusted evenly until the roller 631 is close to the ecological sheet pile 1. At this time, the lifting and piling equipment 3 continues to drive the ecological sheet pile 1 to the target elevation. During the driving process, with the assistance of the tongue and groove device, the guide positioning device 4 and the locking device 6, the verticality and axis control of the ecological sheet pile 1 are well guaranteed. At the same time, the rolling of the roller 631 can effectively avoid damage to the pile body.

[0072] Example 7

[0073] like Figure 2 and Figure 3 On the basis of Examples 1-6, the mobile water working platform 2 includes a water working platform 21, a plurality of platform anchoring devices 22 installed on the water working platform 21, and a driving device 23 for driving the water working platform 21 to move forward.

[0074] The beneficial effect of adopting the preferred scheme in the above embodiment is that, when in use, the water working platform 21 is used as an operating platform for the lifting and piling equipment 3 to perform operations; specifically, the water working platform 21 is moved to the designated construction area through the driving device 23, and anchor cables are set through the platform anchoring device 22 to fix the platform at the set position.

[0075] The platform anchoring device 22 is a ship anchor, located on both sides of the water working platform, used to fix the working platform to prevent the platform from being displaced due to the water flow and the reverse force during the injection process. The driving device 23 is composed of two diesel engines to provide power.

[0076] Example 8

[0077] like Figure 2 and Figure 3 On the basis of Embodiments 1-7, the above-water operation platform 21 is provided with a stacking area 211 for storing the ecological sheet piles 1 .

[0078] The beneficial effect of adopting the preferred solution in the above embodiment is that the ecological sheet piles to be injected can be piled up in the stacking area 211, thereby improving the injection efficiency.

[0079] Example 9

[0080] like Figure 2 and Figure 3 On the basis of Embodiments 1-8, the water operation platform 21 is provided with an operation area 212, and the lifting and piling equipment 3 is provided in the operation area 212. The stacking area 211 and the operation area 212 are respectively located at two ends of the water operation platform 21.

[0081] The beneficial effect of adopting the preferred solution in the above embodiment is that the operation area 212 and the stacking area 211 are respectively placed at the two ends of the above-water operation platform 21, which can provide a stable construction platform to ensure that the pile driver does not tip over during the driving process.

[0082] On the other hand, the present invention provides a river ecological sheet pile construction method, which is described in detail below.

[0083] Example 10

[0084] like Figure 4 A river ecological sheet pile construction method comprises the following steps:

[0085] The mobile water operation platform 2 moves and stops at the waiting operation area;

[0086] The guide positioning device 4 is hoisted into place;

[0087] The plurality of ecological sheet piles 1 are hoisted and piled in sequence.

[0088] Specifically, the construction procedure is: equipment in place → pile removal → entering the guide positioning device 4 → adjusting the verticality (or inclination) of the flat pile → positioning → vibrating the pile → verifying the pile plane and verticality deviation → vibration pile sinking → adjusting the deviation → pile sinking → to the designed elevation → construction record → driving the next pile according to the unified steps.

[0089] Among them, baseline measurement is required: before the pile driving construction, the on-site measurement control baseline and baseline points are reviewed, and the construction plane coordinate control points and elevation reference points are surveyed according to the on-site conditions, and the pile driving construction baseline is laid out.

[0090] When the equipment is in place: the mobile water working platform 2 is driven to the corresponding construction area through the river, the platform anchoring device 22 is lowered, the water working platform 21 is fixed, the ecological sheet pile 1 equipment is driven in place, and the debugging is completed.

[0091] When installing the guiding and positioning device 4, the axial position of the sheet pile wall is controlled, the plane distortion of the pile is reduced and the piling efficiency is improved; that is, after the first ecological sheet pile 1 is driven into place, the guiding and positioning device 4 is lowered to allow the first ecological sheet pile 1 to enter the installation groove 421, and the pile body 432 is driven into place to control the axial position of the sheet pile wall.

[0092] Then use RTK in conjunction with the theodolite to conduct verticality measurement again to ensure that the piles are completed in one go.

[0093] Afterwards, the ecological sheet pile 1 is clamped by the lifting and piling equipment 3, and is initially tightly connected with the previous ecological sheet pile 1 through the tongue and groove device according to the direction of the guiding and positioning device 4, and the locking device 6 is firmly connected.

[0094] The pile driver uses vibration to sink piles. During the process, always observe and measure whether there is deviation. If deviation occurs, timely adjustment is made and the pile is sunk to the designed elevation. According to the actual construction situation, detailed construction records are recorded to form complete and valid data for acceptance and archiving.

[0095] The beneficial effect of adopting the preferred scheme in the above embodiment is that the installation of the ecological sheet piles 1 is carried out by using a mobile water working platform 2 and setting a guiding and positioning device 4, which improves the efficiency of the construction of the ecological sheet piles 1, ensures the quality of the construction and installation of the ecological sheet piles 1, effectively protects the slope from soil erosion, and the formed protective engineering structure is stable and reliable and can meet flood control needs.

[0096] In the description of the present invention, it is to be understood that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, “axial”, “radial”, “circumferential”, etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.

[0097] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0098] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0099] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0100] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0101] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present invention.

Claims

1. A river ecological sheet pile construction system, characterized in that: The invention comprises a mobile water working platform (2), a lifting and piling device (3) installed on the mobile water working platform (2), and a guiding and positioning device (4) placed on the mobile water working platform (2), wherein the guiding and positioning device (4) is provided with a positioning groove (5) for vertically inserting an ecological sheet pile (1) through the upper and lower parts.

2. According to claim 1, a river ecological sheet pile construction system is characterized in that: The guiding and positioning device (4) comprises a positioning and guiding beam (41) and a central positioning component (42) fixed to one end of the positioning and guiding beam (41); the positioning groove (5) is provided on the positioning and guiding beam (41); a mounting groove (421) connected to the positioning groove (5) is provided at the bottom of the central positioning component (42); the mounting groove (421) is used for vertical insertion of the ecological sheet pile (1).

3. According to claim 2, a river ecological sheet pile construction system is characterized in that: The guide positioning device (4) further comprises an axis positioning pile (43), wherein the axis positioning pile (43) comprises an elevation positioning sleeve (431) detachably connected to the middle end of the positioning guide crossbeam (41) and a pile body (432) slidably connected to the elevation positioning sleeve (431) up and down, and the pile body (432) is inserted into the positioning groove (5).

4. According to claim 1, a river ecological sheet pile construction system is characterized in that: Both ends of the guiding and positioning device (4) are fixed with lifting rings (44).

5. A river ecological sheet pile construction system according to any one of claims 1 to 4, characterized in that: The guide positioning device (4) is equipped with a locking device (6), and the locking device (6) comprises two hoist tensioners (61) installed at one end of the guide positioning device (4) and spaced apart on both sides of the positioning groove (5), two pull ropes (62) parallel to each other and one end of which is respectively connected to the two hoist tensioners (61), and a locking member (63) simultaneously connected to the other ends of the two pull ropes (62).

6. According to claim 5, a river ecological sheet pile construction system is characterized in that: The locking member (63) comprises a roller (631) and two pull plates (632) one end of which is rotatably connected to the end of the roller (631), and the other ends of the two pull plates (632) are respectively connected to the two pull ropes (62).

7. A river stream ecological sheet pile construction system according to any one of claims 1 to 4, characterized in that: The mobile water working platform (2) comprises a water working platform (21), a plurality of platform anchoring devices (22) installed on the water working platform (21), and a driving device (23) for driving the water working platform (21) to move forward.

8. The river ecological sheet pile construction system according to claim 7, characterized in that: The above-water operation platform (21) is provided with a stacking area (211) for storing ecological sheet piles (1).

9. The river ecological sheet pile construction system according to claim 8, characterized in that: The above-water operation platform (21) is provided with an operation area (212), and the lifting and piling equipment (3) is arranged in the operation area (212).

10. A river stream ecological sheet pile construction method, applied to a river stream ecological sheet pile construction system according to any one of claims 1 to 9, characterized in that: The following steps are involved: The mobile water operation platform (2) moves and stops at the waiting operation area; The guide positioning device (4) is hoisted into place; The plurality of ecological sheet piles (1) are hoisted and piled in sequence.