Waterproof construction method for tunnel main body structure

By using T-shaped support frames for segmented installation and waterproof membrane fixing devices in the main structure of the tunnel, the problem of gaps between the waterproof membrane and the T-shaped steel was solved, achieving better waterproofing effect and laying accuracy.

CN118933083APending Publication Date: 2024-11-12FANGYUAN CONSTR GRP REAL ESTATE DEVT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411282506.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-13
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In existing technologies, when drainage pipes are installed in the main structure of tunnels, gaps are easily formed between the waterproof membrane and the web of the T-shaped steel, resulting in poor waterproofing performance.

Method used

The T-shaped support frame is installed in sections. The support frame is formed by welding steel plate one and steel plate two. The waterproof membrane connection unit one and the fixing device are used to fix the waterproof membrane connection unit one to the steel plate and the base surface to ensure the accurate laying position of the waterproof membrane.

Benefits of technology

It effectively avoids gaps between the waterproof membrane and the steel plate, improves the waterproofing effect between the support frame and the base surface, ensures the accuracy of the waterproof membrane laying and the connection strength, and meets the requirements for pouring the concrete protective layer.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933083A_ABST
    Figure CN118933083A_ABST
Patent Text Reader

Abstract

The invention discloses a waterproof construction method for a tunnel main body structure. The waterproof construction method comprises the following steps that S1, a base plane is treated; s2, a first steel plate is installed on the base plane; s3, the first waterproof roll connecting unit is fixed to the supporting frame; s4, the first waterproof roll connecting unit is fixed to the base plane; s5, a second waterproof roll connecting unit is fixed; and S6, a concrete protection layer with the thickness of 50 mm is poured above the first waterproof roll connecting unit and the second waterproof roll connecting unit. The T-shaped supporting frame is installed in a segmented mode, the first waterproof roll connecting unit can be fixed to the first steel plate, the second steel plate and the base face, the connecting position of the first steel plate and the base face and the connecting position of the first steel plate and the second steel plate are shielded by the first waterproof roll connecting unit, and it is avoided that gaps exist between waterproof rolls and the first steel plate; and the waterproof effect between the support frame and the base plane is improved. In addition, the first waterproof roll connecting unit is laid on the basis of the supporting frame, and it is guaranteed that the laying position of the first waterproof roll connecting unit is accurate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of ground road waterproofing, and in particular relates to a waterproofing construction method for a main structure of a tunnel. Background Art

[0002] With the continuous development of urban construction, the construction of urban pedestrian tunnels is becoming more and more common, which can not only ensure the personal safety of pedestrians crossing the street, but also combine with the utilization of urban underground space. Because various pipelines need to be arranged in the soil layer above the urban tunnel, the buried depth is usually large, and most of them are placed below the groundwater level. Therefore, the waterproofing of the tunnel is particularly important.

[0003] The prior art sets a waterproof layer on the outer side of the tunnel structure, the waterproof layer adopts a self-adhesive waterproof membrane, and then sets fine stone concrete on the outer side of the self-adhesive waterproof membrane. For example, a Chinese patent discloses a utility model patent named a waterproof system for urban tunnel structure (authorization announcement number: CN204804859U), which can effectively reduce the leakage points of the tunnel.

[0004] When a drainage pipe is set in the main structure of the tunnel, it is necessary to set T-shaped steel on the main structure of the tunnel so that the drainage pipe is supported on the T-shaped steel. However, gaps are likely to exist between the waterproof membrane and the web of the T-shaped steel, resulting in poor waterproofing effect between the waterproof membrane and the web of the T-shaped steel. Summary of the invention

[0005] The purpose of the present invention is to solve the above-mentioned technical problems existing in the prior art, and to provide a waterproof construction method for the main structure of the tunnel, wherein the T-shaped support frame is installed in sections, so that the waterproof coiled material connection unit 1 can be fixed on the steel plate 1, the steel plate 2 and the base surface, so that the waterproof coiled material connection unit 1 is outsourced to the support frame, and the connection between the steel plate 1 and the base surface, and the connection between the steel plate 1 and the steel plate 2 are all shielded by the waterproof coiled material connection unit 1, so as to avoid the existence of a gap between the waterproof coiled material and the steel plate 1, and improve the waterproof effect between the support frame and the base surface. Moreover, the waterproof coiled material connection unit 1 is laid based on the T-shaped support frame to ensure that the laying position of the waterproof coiled material connection unit 1 is accurate.

[0006] In order to solve the above technical problems, the present invention adopts the following technical solutions:

[0007] The waterproof construction method of the main structure of the tunnel is characterized by comprising the following steps:

[0008] S1. Base surface treatment:

[0009] (1) Level the base surface;

[0010] (2) Before laying the waterproof membrane, the leaking parts of the enclosure structure should be blocked or temporarily drained to ensure that there is no visible water flow on the base surface;

[0011] S2. Install steel plate on the base surface:

[0012] (1) Measure and lay out the base surface to determine the installation position of the steel plate;

[0013] (2) opening an installation groove at the installation position of the steel plate 1, placing the steel plate 1 in the installation groove, and then filling the installation groove with mortar so that the steel plate 1 is kept in a vertical state and fixed on the base surface;

[0014] S3. Fix the waterproof membrane connection unit 1 on the support frame:

[0015] (1) Two waterproofing coiled material connection units 1 are provided for each steel plate 1, and the waterproofing coiled material connection unit 1 is divided into connection section 1, connection section 2 and connection section 3. The connection section 2 is provided between the connection section 1 and the connection section 3, and then the waterproofing coiled material connection unit 1 is positioned;

[0016] (2) Fixing the bonding surface of the second connecting section to the side surface of the first steel plate;

[0017] (3) The second steel plate is placed horizontally on the top of the first steel plate, and the bonding surface of the connecting section 3 is fixed on the bottom surface of the second steel plate;

[0018] (4) Welding and fixing the second steel plate and the first steel plate to form a T-shaped support frame;

[0019] S4. Fix the waterproof membrane connection unit 1 on the base surface:

[0020] Straighten the connection section 1, and fix the bonding surface of the connection section 1 to the base surface, so as to complete the fixing of the waterproof membrane connection unit 1 between the support frame and the base surface;

[0021] S5, Fixed waterproof membrane connection unit 2:

[0022] (1) The second waterproofing membrane connection unit is arranged between two adjacent first waterproofing membrane connection units and laid flat on the base surface;

[0023] (2) Fix the bonding surface of the waterproof membrane connection unit 2 on the base surface, and then overlap the waterproof membrane connection unit 2 and the connection section 1, with the width of the overlap section being 10 cm;

[0024] S6. Pour a 50 mm thick concrete protective layer above the waterproof membrane connection unit 1 and the waterproof membrane connection unit 2, and the concrete protective layer is arranged between two adjacent steel plates 1.

[0025] Furthermore, a waterproof roll material fixing device is used to fix the waterproof roll material connection unit 1 on the support frame. The waterproof roll material fixing device includes a base and a clamping structure. The clamping structure includes a clamping seat and a clamping plate. The clamping seat includes a plate body 1 and a plate body 2. The plate body 2 is welded between the two plate bodies 1. The plate body 2 is formed with a vertically arranged positioning surface 1 and a horizontally arranged positioning surface 2. The positioning surface 2 is welded with a vertical connecting column 1.

[0026] The specific fixing steps are:

[0027] (1) The width direction of the steel plate 1 is defined as the X-axis direction, and the length direction of the steel plate 1 is defined as the Y-axis direction. The base is first fixed on the base surface, and two symmetrical bases are arranged along the Y-axis direction. The steel plate 1 is arranged between the two bases in the X-axis direction.

[0028] (2) Attach the connection section 2 of the waterproof roll material connection unit 1 to the positioning surface 1 of the plate body 2, and at the same time, attach the connection section 3 of the waterproof roll material connection unit 1 to the positioning surface 2 of the plate body 2, and then install the clamping plate on the connection column 1. The connection column 1 passes through the through hole 1 of the clamping plate. The clamping plate and the positioning surface 2 clamp the connection section 3, and then screw the locking nut 1 on the connection column 1. At this time, the waterproof roll material connection unit 1 is clamped by the clamping structure, and then the clamping seat is installed on the two bases in the Y-axis direction to complete the positioning operation of the waterproof roll material connection unit 1;

[0029] (3) Apply adhesive to the two sides of the steel plate 1, then move the clamping structure on the base toward the steel plate 1, fix the bonding surface of the connecting section 2 to the side of the steel plate 1 through the adhesive, and then limit the clamping structure on the base;

[0030] (4) Unscrew the locking nut 1, remove the clamping plate from the connecting column 1, apply adhesive on the bottom surface of the steel plate 2, and place the steel plate 2 horizontally on the top of the steel plate 1. At the same time, the plate body 2 supports the steel plate 2, and the bonding surface of the connecting section 3 is fixed to the bottom surface of the steel plate 2 by the adhesive;

[0031] (5) Welding is performed at the exposed contact point between the second steel plate and the first steel plate to form a support frame.

[0032] (6) Remove the clamping seat from the base, and then remove the base from the base surface.

[0033] In this step, the connection section 2 of the waterproof membrane connection unit 1 can be fixed flatly on the side of the steel plate 1, and the connection section 3 of the waterproof membrane connection unit 1 can be fixed flatly on the bottom surface of the steel plate 2, so as to avoid wrinkles, warping, etc. of the waterproof membrane connection unit 1, and improve the connection strength between the waterproof membrane connection unit 1 and the support frame to meet the requirements for subsequent pouring of the concrete protective layer.

[0034] Furthermore, in order to facilitate the rapid fixing or removal of the base, the steps for fixing the base to the base surface are as follows: a vertical fixing bolt is set at the base surface, and then an ear plate is welded on the base, the ear plate is provided with a through hole 2, the ear plate of the base is installed on the fixing bolt, the fixing bolt passes through the through hole 2, and then the locking nut 2 is screwed into the fixing bolt. When the base needs to be removed, the locking nut 2 is unscrewed from the fixing bolt, and then the ear plate of the base is removed from the fixing bolt, and then the fixing bolt is cut so that the end of the fixing bolt is flush with the base surface.

[0035] Furthermore, after the base is fixed on the base surface, a connecting rod is installed on the two bases in the X-axis direction, the connecting rod passes through the through hole three of the base, and then the locking nuts three are screwed into the two ends of the connecting rod, and the locking nuts three are locked on the base. When the base needs to be removed, the locking nuts three are screwed out from the connecting rod, and then the connecting rod is taken out from the base. The two bases in the X-axis direction can be fixedly connected, the force bearing capacity of the base is improved, and the clamping structure can be moved on the base conveniently.

[0036] Furthermore, the base is provided with a sliding groove and a notch, the notch and the sliding groove are connected, and the top surface of the plate body 1 is provided with a vertical connecting column 2. When the clamping seat is installed on the base, the plate body 1 is slid into the sliding groove, and the connecting column 2 slides into the notch, and the plate body 1 is moved in the sliding groove toward the steel plate 1. When the bonding surface of the connecting section 2 is fixed to the side of the steel plate 1 by an adhesive, a locking nut 4 is screwed into the connecting column 2. When the clamping seat needs to be removed, the locking nut 4 is screwed out from the connecting column 2, and then the plate body 1 is taken out of the sliding groove. The movement and limiting of the clamping structure on the base can be realized, and at the same time, the stability of the movement of the clamping structure is improved, ensuring that the bonding surface of the connecting section 2 can be tightly attached to the side of the steel plate 1.

[0037] Furthermore, when the clamping structure is limited on the base, a connecting plate is installed on the two bases in the Y-axis direction, and the connecting plate and the base are connected by connecting bolts, so that the bases in the X-axis and Y-axis directions can be connected as a whole, further improving the force-bearing capacity of the base and facilitating the subsequent welding requirements of steel plate 2 and steel plate 1.

[0038] Furthermore, when the clamping structure is limited on the base, a pressure plate is used to press the connecting section 1 to limit the connecting section 1 on the base surface, thereby preventing the connecting section 1 from wrinkling and affecting the later fixed connection between the connecting section 1 and the base surface.

[0039] Furthermore, the plate body 1 is provided with a limiting groove, and the pressure plate is provided with a limiting protrusion. When the pressure plate presses the connecting section 1, the limiting protrusion is embedded in the limiting groove, so that the pressure plate is limited on the plate body 1, avoiding the pressure plate from sliding and causing damage to the connecting section 1.

[0040] The present invention has the following beneficial effects due to the adoption of the above technical solution:

[0041] (1) The present invention installs the T-shaped support frame in sections, first installing steel plate 1, then fixing the bonding surface of connection section 2 on the side of steel plate 1, then fixing the bonding surface of connection section 3 on the bottom of steel plate 2, and then welding steel plate 2 and steel plate 1 to form a T-shaped support frame. The T-shaped support frame replaces the T-shaped steel, and then the connection section 1 is fixed to the base surface, so that the waterproof roll material connection unit 1 can be fixed on steel plate 1, steel plate 2 and the base surface, so that the waterproof roll material connection unit 1 is outsourced to the support frame, and the connection between steel plate 1 and the base surface, and the connection between steel plate 1 and steel plate 2 are all blocked by the waterproof roll material connection unit 1, avoiding the existence of a gap between the waterproof roll material and steel plate 1, thereby improving the waterproof effect between the support frame and the base surface. Moreover, the waterproof roll material connection unit 1 is laid based on the T-shaped support frame to ensure that the laying position of the waterproof roll material connection unit 1 is accurate.

[0042] (2) The present invention adopts a waterproof membrane fixing device to fix the waterproof membrane connection unit 1 on the support frame, and can fix the connection section 2 of the waterproof membrane connection unit 1 flatly on the side of the steel plate 1, and at the same time, fix the connection section 3 of the waterproof membrane connection unit 1 flatly on the bottom surface of the steel plate 2, thereby avoiding wrinkles, warping, etc. of the waterproof membrane connection unit 1, and can improve the connection strength between the waterproof membrane connection unit 1 and the support frame to meet the requirements of the subsequent pouring of the concrete protective layer. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] The present invention will be further described below in conjunction with the accompanying drawings:

[0044] Figure 1 This is a schematic structural diagram of the present invention when a steel plate is installed on a base surface;

[0045] Figure 2 It is a structural schematic diagram of the base in the present invention;

[0046] Figure 3 The present invention is a plan view of fixing the base on the base surface;

[0047] Figure 4 The present invention is a three-dimensional diagram of the base being fixed on the base surface;

[0048] Figure 5 It is a structural schematic diagram of the clamping seat in the present invention;

[0049] Figure 6 It is a structural schematic diagram of the present invention in which the waterproof coiled material connection unit 1 is attached to the plate body 2;

[0050] Figure 7 It is a schematic structural diagram of the waterproof coiled material connection unit 1 in the present invention when it is clamped by the clamping structure;

[0051] Figure 8It is a structural schematic diagram of the clamping plate in the present invention;

[0052] Fig. 9 It is a structural schematic diagram of the present invention when the clamping structure is limited on the base;

[0053] Fig.10 for Fig. 9 The main view;

[0054] Fig.11 This is a schematic diagram of the structure of the present invention after the pressing plate is installed;

[0055] Fig.12 It is a structural schematic diagram of the pressure plate in the present invention;

[0056] Fig.13 This is a schematic diagram of the structure of the present invention when the second steel plate and the first steel plate are welded;

[0057] Fig.14 This is a schematic diagram of the structure of the present invention when the clamping seat is removed;

[0058] Fig.15 A schematic diagram of a structure in which a waterproof coiled material connection unit between a support frame and a base surface is fixed in the present invention;

[0059] Fig.16 This is a schematic diagram of the structure of the second fixing unit of the waterproof coiled material connection completed by the present invention;

[0060] Fig.17 It is a schematic diagram of the structure of the tunnel main structure after the waterproof construction of the present invention is completed.

[0061] In the figure, a-base surface; 1-steel plate 1; 2-mortar; 3-base; 4-sliding groove; 5-notch; 6-through hole 3; 7-ear plate; 8-through hole 2; 9-fixing bolt; 10-locking nut 2; 11-plate body 2; 12-positioning surface 1; 13-positioning surface 2; 14-plate body 1; 15-connecting column 1; 16-connecting column 2; 17-limiting groove; 18-waterproof membrane connection unit 1; 19-connection Section 1; 20-connecting section 2; 21-connecting section 3; 22-clamping plate; 23-locking nut 1; 24-through hole 1; 25-connecting rod; 26-locking nut 3; 27-locking nut 4; 28-connecting plate; 29-connecting bolt; 30-pressing plate; 31-limiting protrusion; 32-steel plate 2; 33-waterproof membrane connection unit 2; 34-support frame; 35-lap section; 36-concrete protective layer. DETAILED DESCRIPTION

[0062] like Figures 1 to 17 As shown, the waterproof construction method of the main structure of the tunnel of the present invention comprises the following steps:

[0063] S1. Base surface a treatment:

[0064] (1) The base surface a should be leveled without looseness, sanding or peeling. The flatness should meet the requirement of D / L ≤ 1 / 20 (D is the maximum depth between two adjacent convex surfaces; L is the minimum distance between two adjacent convex surfaces). The convex and concave parts should be smooth and flat.

[0065] (2) The waterproof roll material of the present invention is a self-adhesive waterproof roll material, which is divided into a waterproof roll material connection unit 18 and a waterproof roll material connection unit 2 33. Before the waterproof roll material is laid, the water leakage part of the enclosure structure is blocked or temporarily drained to ensure that there is no visible water flow on the base surface a.

[0066] S2. Install steel plate 1 at base surface a:

[0067] (1) Measure and lay out the base surface a to determine the installation position of steel plate 1.

[0068] (2) A mounting groove is opened at the mounting position of the steel plate 1, and the steel plate 1 is placed in the mounting groove. Then, mortar 2 is filled into the mounting groove so that the steel plate 1 remains vertically fixed on the base surface a.

[0069] S3. A waterproof roll material fixing device is used to fix the waterproof roll material connection unit 18 on the support frame 34. The waterproof roll material fixing device includes a base 3 and a clamping structure. The clamping structure includes a clamping seat and a clamping plate 22. The clamping seat includes a plate body 14 and a plate body 2 11. The plate body 2 11 is welded between two plate bodies 14. The plate body 2 11 is formed with a vertically arranged positioning surface 12 and a horizontally arranged positioning surface 2 13. The positioning surface 2 13 is welded with a vertical connecting column 15.

[0070] The specific fixing steps are:

[0071] (1) The width direction of the steel plate 1 is defined as the X-axis direction, and the length direction of the steel plate 1 is defined as the Y-axis direction (e.g. Figure 3 shown).

[0072] First, fix the base 3 on the base surface a, set two symmetrical bases 3 along the Y-axis direction, and set the steel plate 1 between the two bases 3 in the X-axis direction.

[0073] In order to facilitate the quick fixing or removal of the base 3, the steps for fixing the base 3 on the base surface a are as follows: a vertical fixing bolt 9 is set at the base surface a, and then an ear plate 7 is welded on the base 3, and the ear plate 7 is provided with a second through hole 8, and the ear plate 7 of the base 3 is installed on the fixing bolt 9, the fixing bolt 9 passes through the second through hole 8, and then the locking nut 10 is screwed into the fixing bolt 9.

[0074] After the base 3 is fixed on the base surface a, a connecting rod 25 is installed on the two bases 3 in the X-axis direction, the connecting rod 25 passes through the through hole 3 6 of the base 3, and then the locking nuts 3 26 are screwed into the two ends of the connecting rod 25, and the locking nuts 3 26 are locked on the base 3. The two bases 3 in the X-axis direction can be fixedly connected, the force bearing capacity of the base 3 is improved, and it is convenient to move the clamping structure on the base 3 later.

[0075] (2) Two waterproofing coiled material connection units 18 are correspondingly arranged for each steel plate 1. The waterproofing coiled material connection unit 18 is divided into a connection section 19, a connection section 20 and a connection section 3 21. The connection section 20 is arranged between the connection section 19 and the connection section 3 21.

[0076] The connection section 20 of the waterproof coiled material connection unit 18 is attached to the positioning surface 12 of the plate body 11, and the connection section 3 21 of the waterproof coiled material connection unit 18 is attached to the positioning surface 13 of the plate body 11 (such as Figure 6 Then install the clamping plate 22 on the connecting column 15, the connecting column 15 passes through the through hole 124 of the clamping plate 22, clamp the connecting section 3 21 with the clamping plate 22 and the positioning surface 2 13, and then screw the locking nut 1 23 into the connecting column 15. At this time, the waterproof membrane connecting unit 18 is clamped by the clamping structure (as shown in FIG. Figure 7 Then, the clamping seat is installed on the two bases 3 in the Y-axis direction. The base 3 is provided with a sliding groove 4 and a notch 5. The notch 5 is connected to the sliding groove 4. The top surface of the plate body 14 is provided with a vertical connecting column 2 16. When the clamping seat is installed on the base 3, the plate body 14 is slid into the sliding groove 4. At this time, the connecting column 2 16 slides into the notch 5, and the positioning operation of the waterproof coiled material connecting unit 18 is completed.

[0077] (3) Apply adhesive to the two sides of the steel plate 1, and then move the plate body 14 in the sliding groove 4 toward the steel plate 1. When the bonding surface of the connecting section 20 is fixed to the side of the steel plate 1 by the adhesive, screw the locking nut 4 27 into the connecting column 2 16 to limit the clamping structure on the base 3 (such as Fig. 9 shown).

[0078] When the clamping structure is limited on the base 3, a connecting plate 28 is installed on the two bases 3 in the Y-axis direction. The connecting plate 28 and the base 3 are connected by connecting bolts 29, so that the bases 3 in the X-axis and Y-axis directions can be connected as a whole, further improving the force-bearing capacity of the base 3 and facilitating the later welding requirements of steel plate 2 and steel plate 1.

[0079] When the clamping structure is limited on the base 3, the pressure plate 30 is used to press the connecting section 19, and the connecting section 19 is limited on the base surface a, so as to avoid wrinkles on the connecting section 19 and affect the later fixed connection between the connecting section 19 and the base surface a. The plate body 14 of the present invention is provided with a limiting groove 17, and the pressure plate 30 is provided with a limiting protrusion 31. When the pressure plate 30 presses the connecting section 19, the limiting protrusion 31 is embedded in the limiting groove 17, so that the pressure plate 30 is limited on the plate body 14, so as to avoid the pressure plate 30 sliding and causing damage to the connecting section 19.

[0080] (4) Unscrew the locking nut 23, remove the clamping plate 22 from the connecting column 15, apply adhesive on the bottom surface of the steel plate 32, and place the steel plate 32 horizontally on the top of the steel plate 1. At the same time, the plate body 11 supports the steel plate 32, and the bonding surface of the connecting section 3 21 is fixed to the bottom surface of the steel plate 32 by the adhesive.

[0081] (5) The exposed contact parts of the steel plate 2 32 and the steel plate 1 are welded to form a T-shaped support frame 34 with the steel plate 2 32 and the steel plate 1 1 .

[0082] (6) When removing the clamping seat from the base 3, unscrew the connecting bolt 29, remove the connecting plate 28, and then remove the pressing plate 30. Then unscrew the locking nut 27 from the connecting column 16, and then remove the plate 14 from the sliding groove 4. When removing the base 3 from the base surface a, unscrew the locking nut 3 26 from the connecting rod 25, and then remove the connecting rod 25 from the base 3. Then unscrew the locking nut 2 10 from the fixing bolt 9, and then remove the ear plate 7 of the base 3 from the fixing bolt 9, and then cut the fixing bolt 9 so that the end of the fixing bolt 9 is flush with the base surface a.

[0083] In step S3, the connection section 20 of the waterproof membrane connection unit 18 can be fixed flatly on the side of the steel plate 1, and the connection section 3 21 of the waterproof membrane connection unit 18 can be fixed flatly on the bottom surface of the steel plate 32, so as to avoid wrinkles, warping, etc. of the waterproof membrane connection unit 18, and improve the connection strength between the waterproof membrane connection unit 18 and the support frame 34 to meet the requirements of the subsequent pouring of the concrete protective layer.

[0084] S4. Fix the waterproof membrane connection unit 18 on the base surface a:

[0085] The connecting section 19 is straightened, and the bonding surface of the connecting section 19 is fixed to the base surface a, so as to complete the fixing of the waterproof membrane connecting unit 18 between the support frame 34 and the base surface a.

[0086] S5, fixed waterproof membrane connection unit 2 33:

[0087] (1) The second waterproofing coiled material connection unit 33 is arranged between two adjacent waterproofing coiled material connection units 18 and laid flat on the base surface a.

[0088] (2) The bonding surface of the second waterproof membrane connection unit 33 is fixed to the base surface a, and then the second waterproof membrane connection unit 33 and the connection section 19 are overlapped, and the width of the overlap section 35 is 10 cm.

[0089] S6. Pour a 50 mm thick concrete protective layer 36 above the waterproof membrane connection unit 18 and the waterproof membrane connection unit 2 33. The concrete protective layer 36 is C20 fine stone concrete. The concrete protective layer 36 is arranged between two adjacent steel plates 1.

[0090] The present invention installs the T-shaped support frame 34 in sections, first installing the steel plate 1, then fixing the bonding surface of the connecting section 20 to the side of the steel plate 1, then fixing the bonding surface of the connecting section 3 21 to the bottom surface of the steel plate 2 32, and then welding the steel plate 2 32 and the steel plate 1 to form a T-shaped support frame 34. The T-shaped support frame 34 replaces the T-shaped steel, and then the connecting section 19 is fixed to the base surface a, so that the waterproof coiled material connection unit 18 can be fixed on the steel plate 1, the steel plate 2 32 and the base surface a, so that the waterproof coiled material connection unit 18 is outsourced to the support frame 34, and the connection between the steel plate 1 and the base surface a, and the connection between the steel plate 1 and the steel plate 2 32 are all blocked by the waterproof coiled material connection unit 18, so as to avoid the existence of a gap between the waterproof coiled material and the steel plate 1, thereby improving the waterproof effect between the support frame 34 and the base surface a. Moreover, the waterproofing membrane connection unit 18 is laid based on the T-shaped support frame 34 to ensure that the waterproofing membrane connection unit 18 is laid accurately.

[0091] The construction process control measures of the present invention are as follows:

[0092] 1. Quality control in the construction preparation stage:

[0093] ①. Adhere to the study and review of drawings, understand the design intent, and put forward our suggestions for modifying the foundation pit support system to avoid technical accidents and engineering quality problems.

[0094] ②. Continuously improve and optimize the construction organization design to make the construction plan scientific and reasonable, and the measures detailed, feasible and reliable.

[0095] ③. Strictly organize technical briefings and convey the technical requirements and quality control points of foundation pit construction to every operator.

[0096] ④. Control the procurement of materials, conduct evaluation of suppliers and inspection of incoming materials. All materials used in this project shall be sampled and tested in accordance with regulations. Materials that fail the inspection shall not be allowed to enter the site.

[0097] 2. Quality control during the construction phase:

[0098] ①. Strictly carry out inspection, testing and engineering testing of materials, components and parts.

[0099] ②. Implement process quality monitoring. First, monitor the conditions of process activities, that is, "people, machines, materials, methods, and environment" must meet quality requirements; second, monitor the quality of the results of process activities.

[0100] ③. Strengthen quality inspections, including self-inspection, mutual inspection, professional inspection, process handover inspection, hidden project acceptance inspection, project pre-inspection, foundation and main project inspection and acceptance, etc., and implement on-site supervision of key processes.

[0101] ④. Strengthen the protection of finished products. During the construction process, protective measures should be formulated to protect the completed sub-items and sub-projects. For the protection of products, emphasis should be placed on the construction sequence and protective measures. The procedures should not be reversed. Construction should be organized according to the correct construction process to prevent the previous process from damaging or contaminating the subsequent process.

[0102] ⑤. Pay attention to accumulating construction technical information, keeping a project log, recording test (inspection) data comprehensively, scientifically, accurately and timely, completing procedures, and calculating, organizing and archiving according to regulations.

[0103] The above are only specific embodiments of the present invention, but the technical features of the present invention are not limited thereto. Any simple changes, equivalent replacements or modifications made based on the present invention to solve basically the same technical problems and achieve basically the same technical effects are all included in the protection scope of the present invention.

Claims

1. A waterproof construction method for a tunnel main structure, characterized in that: The steps include: S1. Base surface treatment: (1) Level the base surface; (2) Before laying the waterproof membrane, the leaking parts of the enclosure structure should be blocked or temporarily drained to ensure that there is no visible water flow on the base surface; S2. Install steel plate on the base surface: (1) Measure and lay out the base surface to determine the installation position of the steel plate; (2) opening an installation groove at the installation position of the steel plate 1, placing the steel plate 1 in the installation groove, and then filling the installation groove with mortar so that the steel plate 1 is kept in a vertical state and fixed on the base surface; S3. Fix the waterproof membrane connection unit 1 on the support frame: (1) Two waterproof coiled material connection units 1 are provided corresponding to each steel plate 1, and the waterproof coiled material connection unit 1 is divided into a connection section 1, a connection section 2 and a connection section 3, and the connection section 2 is provided between the connection section 1 and the connection section 3, and then the waterproof coiled material connection unit 1 is positioned; (2) Fixing the bonding surface of the second connecting section to the side surface of the first steel plate; (3) The second steel plate is placed horizontally on the top of the first steel plate, and the bonding surface of the connecting section 3 is fixed on the bottom surface of the second steel plate; (4) Welding and fixing the second steel plate and the first steel plate to form a T-shaped support frame; S4. Fix the waterproof membrane connection unit 1 on the base surface: Straighten the connection section 1, and fix the bonding surface of the connection section 1 to the base surface, so as to complete the fixing of the waterproof membrane connection unit 1 between the support frame and the base surface; S5, Fixed waterproof membrane connection unit 2: (1) The second waterproofing membrane connection unit is arranged between two adjacent first waterproofing membrane connection units and laid flat on the base surface; (2) Fix the bonding surface of the waterproof membrane connection unit 2 on the base surface, and then overlap the waterproof membrane connection unit 2 and the connection section 1, with the width of the overlap section being 10 cm; S6. Pour a 50 mm thick concrete protective layer above the waterproof membrane connection unit 1 and the waterproof membrane connection unit 2, and the concrete protective layer is arranged between two adjacent steel plates 1.

2. The waterproof construction method for the main structure of the tunnel according to claim 1 is characterized by: A waterproof coiled material fixing device is used to fix the waterproof coiled material connection unit 1 on the support frame, the waterproof coiled material fixing device includes a base and a clamping structure, the clamping structure includes a clamping seat and a clamping plate, the clamping seat includes a plate body 1 and a plate body 2, the plate body 2 is welded between the two plate bodies 1, the plate body 2 is formed with a vertically arranged positioning surface 1 and a horizontally arranged positioning surface 2, and the positioning surface 2 is welded with a vertical connecting column 1; The specific fixing steps are: (1) The width direction of the steel plate 1 is defined as the X-axis direction, and the length direction of the steel plate 1 is defined as the Y-axis direction. The base is first fixed on the base surface, and two symmetrical bases are arranged along the Y-axis direction. The steel plate 1 is arranged between the two bases in the X-axis direction. (2) Attach the connection section 2 of the waterproof roll material connection unit 1 to the positioning surface 1 of the plate body 2, and at the same time, attach the connection section 3 of the waterproof roll material connection unit 1 to the positioning surface 2 of the plate body 2, and then install the clamping plate on the connection column 1. The connection column 1 passes through the through hole 1 of the clamping plate. The clamping plate and the positioning surface 2 clamp the connection section 3, and then screw the locking nut 1 on the connection column 1. At this time, the waterproof roll material connection unit 1 is clamped by the clamping structure, and then the clamping seat is installed on the two bases in the Y-axis direction to complete the positioning operation of the waterproof roll material connection unit 1; (3) Apply adhesive to the two sides of the steel plate 1, then move the clamping structure on the base toward the steel plate 1, fix the bonding surface of the connecting section 2 to the side of the steel plate 1 through the adhesive, and then limit the clamping structure on the base; (4) Unscrew the locking nut 1, remove the clamping plate from the connecting column 1, apply adhesive on the bottom surface of the steel plate 2, and place the steel plate 2 horizontally on the top of the steel plate 1. At the same time, the plate body 2 supports the steel plate 2, and the bonding surface of the connecting section 3 is fixed to the bottom surface of the steel plate 2 by the adhesive; (5) Welding is performed at the exposed contact point between the second steel plate and the first steel plate to form a support frame. (6) Remove the clamping seat from the base, and then remove the base from the base surface.

3. The waterproof construction method for the main structure of the tunnel according to claim 2 is characterized by: The steps for fixing the base on the base surface are as follows: a vertical fixing bolt is set at the base surface, and then an ear plate is welded on the base, the ear plate is provided with a second through hole, the ear plate of the base is installed on the fixing bolt, the fixing bolt passes through the second through hole, and then the locking nut second is screwed into the fixing bolt. When the base needs to be removed, the locking nut second is screwed out from the fixing bolt, and then the ear plate of the base is removed from the fixing bolt, and then the fixing bolt is cut so that the end of the fixing bolt is flush with the base surface.

4. The waterproof construction method for the main structure of the tunnel according to claim 2 is characterized by: After the base is fixed on the base surface, a connecting rod is installed on the two bases in the X-axis direction. The connecting rod passes through the through hole three of the base, and then the locking nuts three are screwed into the two ends of the connecting rod. The locking nuts three are locked on the base. When the base needs to be removed, the locking nuts three are screwed out from the connecting rod, and then the connecting rod is taken out from the base.

5. The waterproof construction method for the main structure of the tunnel according to claim 2 is characterized by: The base is provided with a sliding groove and a notch, the notch is connected to the sliding groove, and the top surface of the plate body 1 is provided with a vertical connecting column 2; When the clamping seat is installed on the base, slide the plate body 1 into the sliding groove. At this time, the connecting column 2 slides into the groove, and the plate body 1 is moved in the sliding groove toward the steel plate 1, so that the clamping structure moves toward the steel plate 1 on the base. When the bonding surface of the connecting section 2 is fixed to the side of the steel plate 1 by the adhesive, the locking nut 4 is screwed into the connecting column 2. When the clamping seat needs to be removed, the locking nut 4 is unscrewed from the connecting column 2, and then the plate body 1 is taken out of the sliding groove.

6. The waterproof construction method for the main structure of the tunnel according to claim 2 is characterized by: When the clamping structure is limited on the base, a connecting plate is installed on the two bases in the Y-axis direction, and the connecting plate and the base are connected by connecting bolts.

7. The waterproof construction method for the main structure of the tunnel according to claim 2 is characterized by: When the clamping structure is limited on the base, the pressure plate is used to press the connecting section 1 to limit the connecting section 1 on the base surface.

8. The waterproof construction method for the main structure of the tunnel according to claim 7 is characterized by: The plate body 1 is provided with a limiting groove, and the pressing plate is provided with a limiting protrusion. When the pressing plate presses the connecting section 1, the limiting protrusion is embedded in the limiting groove, so that the pressing plate is limited on the plate body 1.