Irregular mountain wall surface mounting method

By using galvanized steel plates and aluminum veneer partitions on irregular gables and making aluminum profile grilles combined with aluminum plate glue seam positioning lines, the problems of aluminum plate inappropriate and unsightly joints are solved, and the problems of aluminum plates are not adapted and the joints are not beautiful are simplified. The assembly process and improves installation efficiency.

CN118933294AActive Publication Date: 2024-11-12BEIJING URBAN CONSTR GROUP
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411168838.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-23
Publication Date
2024-11-12
Estimated Expiration
2044-08-23

AI Technical Summary

Technical Problem

In irregular gable installation of steel frame structures, the aluminum plates are not adaptable and the joints are not beautiful, resulting in the complex assembly of aluminum profiles.

Method used

Galvanized steel plates are used as the basis, and standard aluminum veneers are processed by partitioning, cutting and numbering, and aluminum profile grilles are made in combination with aluminum plate glue seam positioning lines, and rock wool boards are installed on the galvanized steel plates to simplify assembly.

Benefits of technology

The adaptability and seam aesthetics of aluminum plates are achieved, the assembly process of aluminum profiles is simplified, and the construction complexity is reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933294A_ABST
    Figure CN118933294A_ABST
Patent Text Reader

Abstract

An irregular mountain wall surface mounting method comprises the following steps that a plurality of steel keels are fixedly mounted between a roof framework and the ground; collecting the size of each position of the wall surface, cutting a galvanized steel sheet according to the collected size, and fixedly mounting the galvanized steel sheet on the outer side of the steel keel; the method comprises the following steps: filling standard aluminum veneers on a galvanized steel sheet, partitioning the galvanized steel sheet into regular regions and irregular regions according to whether the standard aluminum veneers completely fall on the galvanized steel sheet, calculating the number of the aluminum veneers required by the regular regions, dividing the irregular regions into a plurality of small regions, and cutting the aluminum veneers at special positions according to the sizes of the small regions. The aluminum veneers and the small partitions are numbered in a one-to-one correspondence mode; firstly, a complete aluminum veneer is fixedly installed in the regular area, and then the aluminum veneer and the small subareas of the irregular area are fixedly installed; the standard aluminum veneer is divided into the regular area and the irregular area, the aluminum plates matched with the standard aluminum veneer are installed at all positions, the joints of the aluminum plates are more attractive, and assembly of the aluminum profile is simplified.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of building construction, and in particular to a method for installing an irregular gable surface. Background Art

[0002] With the gradual development of steel frame construction technology, more and more building exterior walls have abandoned traditional brick and stone stacking methods or reinforced concrete methods and instead adopted steel frame structures that are simpler to build and maintain; especially for gable walls that do not play a major supporting role, the application of steel frame structures is more common and diverse.

[0003] In the prior art, the main structural features of buildings such as station platforms and snack street shelters are that they only have a plurality of supporting beams located in the middle and a roof installed on the top of the supporting beams for sheltering from rain. In essence, they are open-air buildings with only a roof. However, in many cases, for the sake of the aesthetics of the building, the roof structure design is complicated to give it a graceful curve. At the same time, gables are built at both ends of such buildings. The function of such gables is only to isolate wind and rain and for decorative purposes. When such gables are constructed using a steel frame construction method, their outer surfaces are usually covered with a plurality of aluminum plates to improve their aesthetics. However, due to the complexity of the roofs of such buildings, the aluminum plates need to be manufactured separately to match them with the shape of the roofs. Usually, during construction, workers rely on manual measurement, cutting, and installation, which can easily cause the aluminum plates to be unmatched and the joints at the edges of the aluminum plates to be unsightly, which in turn makes the assembly of aluminum profiles used to cover the joints more troublesome.

[0004] Therefore, it is necessary for the inventor to design a new irregular gable surface installation method to overcome the above problems. Summary of the invention

[0005] The main purpose of the present application is to provide an irregular gable installation method to solve the problems in the related art of the aluminum plate of the gable being unsuitable, the seams being unsightly, and the aluminum profile being difficult to assemble.

[0006] In order to achieve the above object, the present application provides an irregular gable surface installation method, the method comprising the following steps:

[0007] S100. Fix and install several steel keels between the roof frame and the ground;

[0008] S200, collect the dimensions of each position of the wall, cut the galvanized steel plate according to the collected dimensions, and fix the galvanized steel plate on the outside of the steel keel;

[0009] S300, filling the galvanized steel plate with a standard aluminum veneer, partitioning the galvanized steel plate into a regular area and an irregular area according to whether the standard aluminum veneer falls completely on the galvanized steel plate, calculating the number of aluminum veneers required for the regular area, dividing the irregular area into a plurality of small areas, cutting aluminum veneers at special positions according to the size of the small areas, and numbering the aluminum veneers and the small areas in one-to-one correspondence;

[0010] S400, first fix and install the complete aluminum veneer in the regular area, and then fix and install the aluminum veneer in the special position and the small partition in the irregular area one by one;

[0011] S500, manufacturing an aluminum profile grille according to the size of the joints between the filled aluminum veneers, and cutting the edge of the irregular area on the aluminum profile;

[0012] S600, hoist the aluminum profile grille to the outside of the aluminum veneer and fix it to the aluminum veneer;

[0013] S700, install the rock wool board between adjacent keels.

[0014] Preferably, the step S200 includes:

[0015] Select the appropriate galvanized steel plate according to the maximum horizontal and vertical dimensions of the wall;

[0016] According to the other dimensions of the wall, the outline of the wall is carved on the galvanized steel plate;

[0017] Cut the galvanized steel sheets according to the contours of the wall;

[0018] The cut galvanized steel plates are hoisted to the outside of the steel keel and fixed on the steel keel.

[0019] Preferably, the step S300 includes:

[0020] Plane modeling is performed based on the collected wall dimensions, and the standard aluminum veneer is filled into the modeled plane. The area where the standard aluminum veneer completely falls into the modeling plane is the regular area, the area where the standard aluminum veneer does not completely fall into the modeling plane is the irregular area, and the area occupied by each part of the standard aluminum veneer that falls on the modeling plane is the small partition.

[0021] Preferably, the step S400 comprises: drawing aluminum plate glue seam positioning lines between adjacent aluminum plates on the galvanized steel plate according to the filling positions of the aluminum plates, and the areas divided by all the aluminum plate glue seam positioning lines are the areas filled with the aluminum plates.

[0022] Preferably, the step S400 further includes: the aluminum veneers in the regular area do not need to be numbered, and the aluminum veneers in any regular area can be directly replaced and installed;

[0023] Before installing aluminum veneers in irregular areas, carefully check the number, confirm the installation direction and installation position;

[0024] Before installing the aluminum veneer, pre-install the aluminum plate fixing angle code according to the aluminum plate glue seam positioning line, and then install the aluminum veneer on the aluminum plate fixing angle code.

[0025] Preferably, the step S500 includes:

[0026] The aluminum plate glue seam positioning line is the dividing line of the filled aluminum veneer. The horizontal and vertical frames of the aluminum profile grille are manufactured according to the length and position of each aluminum plate glue seam positioning line.

[0027] The horizontal and vertical frames of the aluminum profile grille have a certain width. The edge tangent direction of the irregular area does not necessarily coincide with the horizontal and vertical cut directions of the frame. Therefore, the horizontal and vertical frames of the aluminum profile grille are cut according to the edge lines of the irregular area so that the outer contour of the aluminum profile grille does not exceed the outer contour of the galvanized steel plate.

[0028] Preferably, the step S600 includes:

[0029] The aluminum profile grille is hoisted to the outside of the aluminum veneer so that the aluminum profile grille overlaps with the galvanized steel plate, and then rivets are used on both sides of the aluminum profile grille to fix it to the aluminum veneer.

[0030] Preferably, step S700 includes: cutting the rock wool board according to the size between two adjacent steel keels, filling the cut rock wool board between adjacent steel keels, clamping the rock wool board on the galvanized steel plate through a wire mesh or a deck, and then sealing and waterproofing the inner wall.

[0031] The irregular gable surface installation method provided by the present invention has the following beneficial effects compared with the prior art:

[0032] By zoning the galvanized steel plates, the standard aluminum panels are divided into regular areas and irregular areas. For the standard aluminum panels in the regular areas, the construction workers can replace and install them at will, and the aluminum panels in the irregular areas are adaptively cut, and suitable aluminum panels are installed in all positions. The aluminum plate joints are made more beautiful by drawing aluminum plate glue seam positioning lines, and one-piece aluminum profiles are made according to the aluminum plate glue seam positioning lines, which simplifies the assembly of aluminum profiles. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] The drawings constituting a part of this application are used to provide a further understanding of this application, so that other features, purposes and advantages of this application become more obvious. The schematic embodiment drawings and their descriptions of this application are used to explain this application and do not constitute an improper limitation on this application. In the drawings:

[0034] Figure 1It is the overall flow chart of the present invention;

[0035] Figure 2 is a flow chart of step 2 of the present invention;

[0036] Figure 3 It is an example diagram of the installation of the aluminum profile grille of the present invention. DETAILED DESCRIPTION

[0037] In order to enable those skilled in the art to better understand the present application, the technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of this application.

[0038] It should be noted that the terms "first", "second", etc. in the specification of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequential order. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present application described here. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0039] In the present application, the terms "upper", "lower", "left", "right", "front", "back", "top", "bottom", "inner", "outer", "middle", "vertical", "horizontal", "lateral", "longitudinal" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings. These terms are mainly used to better describe the present application and its embodiments, and are not used to limit the indicated devices, elements or components to have a specific orientation, or to be constructed and operated in a specific orientation.

[0040] In addition, some of the above terms may be used to express other meanings in addition to indicating orientation or positional relationship. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For those of ordinary skill in the art, the specific meanings of these terms in this application can be understood according to specific circumstances.

[0041] In addition, the term "plurality" shall mean two or more.

[0042] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0043] like Figure 1 , Figure 2 As shown, a method for installing an irregular gable surface comprises the following steps:

[0044] S100. Fix and install several steel keels between the roof frame and the ground.

[0045] Specifically, the lower end of the keel is fixed to the ground, and the upper end is fixed to the frame of the roof. The lengths of the keels are different and are cut according to the height of the roof from the ground at different locations. The keels are used to fix and support the structure of the entire gable surface.

[0046] S200, collecting dimensions of each position of the wall, cutting the galvanized steel plate according to the collected dimensions, and fixing the galvanized steel plate on the outside of the steel keel; the step S200 includes:

[0047] Select the appropriate galvanized steel plate according to the maximum horizontal and vertical dimensions of the wall;

[0048] According to the other dimensions of the wall, the outline of the wall is carved on the galvanized steel plate;

[0049] Cut the galvanized steel sheets according to the contours of the wall;

[0050] The cut galvanized steel plates are hoisted to the outside of the steel keel and fixed on the steel keel.

[0051] Specifically, according to the cross-sectional shapes at both ends of the building, measure the height of the irregular roof from the ground and the width of the wall at different heights, or copy the shape of the roof on the galvanized steel plate, and hollow out the positions where windows are needed. Then, lift the galvanized steel plate and install it on the steel frame. The galvanized steel plate can provide auxiliary support and reinforcement for the wall structure, and has waterproof and anti-corrosion functions to resist rain erosion.

[0052] S300, filling the galvanized steel plate with a standard aluminum veneer, partitioning the galvanized steel plate into a regular area and an irregular area according to whether the standard aluminum veneer falls completely on the galvanized steel plate, calculating the number of aluminum veneers required for the regular area, dividing the irregular area into multiple small areas, cutting aluminum veneers at special positions according to the size of the small areas, and numbering the aluminum veneers and the small areas in a one-to-one correspondence; the step S300 includes:

[0053] Plane modeling is performed based on the collected wall dimensions, and the standard aluminum veneer is filled into the modeled plane. The area where the standard aluminum veneer completely falls into the modeling plane is the regular area, the area where the standard aluminum veneer does not completely fall into the modeling plane is the irregular area, and the area occupied by each part of the standard aluminum veneer that falls on the modeling plane is the small partition.

[0054] Specifically, the use of standard aluminum veneers that can be purchased directly on the market can reduce installation costs. For regular areas, standard aluminum veneers can be exchanged and installed at will without affecting the final effect. For irregular areas, separate numbering is required. The numbering information may include installation location, installation direction, etc., to facilitate workers to carry out construction.

[0055] S400, firstly, the complete aluminum veneer is fixedly installed in the regular area, and then the aluminum veneers in the special positions corresponding to each other and the small partitions in the irregular area are fixedly installed; the step S400 includes: drawing the aluminum plate glue seam positioning lines between the adjacent aluminum plates on the galvanized steel plate according to the filling positions of the aluminum plates, and the areas divided by all the aluminum plate glue seam positioning lines are the areas filled with the aluminum plates; the step S400 also includes: the aluminum plates in the regular area do not need to be numbered, and the aluminum plates in any regular area can be directly replaced and installed;

[0056] Before installing aluminum veneers in irregular areas, carefully check the number, confirm the installation direction and installation position;

[0057] Before installing the aluminum veneer, pre-install the aluminum plate fixing angle code according to the aluminum plate glue seam positioning line, and then install the aluminum veneer on the aluminum plate fixing angle code.

[0058] Specifically, aluminum veneers are mainly installed using scissor cars. Depending on the height of each unit, when the scissor car cannot be lifted to the required height for installation, a climbing car can be used for installation. After the aluminum veneer is processed in the processing plant, it is covered with a protective film and transported to the site and work surface. Before installing the aluminum veneer, the positioning line of the aluminum plate glue seam should be measured and set on the steel keel to control the installation position. Before installation, the number, quantity, installation direction and position should be carefully checked. The aluminum plate fixing angle code should be installed in advance, and the installation should be firm and not loose, and no missing. After hanging in place, the fixing angle code is fastened with self-tapping screws. The spacing between the aluminum veneer fixing angle codes is between 300-500mm (the specific arrangement spacing is adjusted according to the length of the board), and each angle code is fixed with a self-tapping screw. The number of self-tapping screws cannot be missed or reduced at will. After the aluminum plate is hung and fastened, it should be carefully adjusted so that the size of the gap between adjacent plates meets the design requirements, and the horizontal and straight diameters are uniform in width and narrowness. Use high-quality weather-resistant glue. During installation, the interior is filled with foam rods, and professional workers apply weather-resistant glue and conduct a comprehensive inspection.

[0059] S500, manufacturing an aluminum profile grid according to the joint size between the filled aluminum veneers, and cutting the edge portion of the irregular area on the aluminum profile; the step S500 includes:

[0060] The aluminum plate glue seam positioning line is the dividing line of the filled aluminum veneer. The horizontal and vertical frames of the aluminum profile grille are manufactured according to the length and position of each aluminum plate glue seam positioning line.

[0061] The horizontal and vertical frames of the aluminum profile grille have a certain width. The edge tangent direction of the irregular area does not necessarily coincide with the horizontal and vertical cut directions of the frame. Therefore, the horizontal and vertical frames of the aluminum profile grille are cut according to the edge lines of the irregular area so that the outer contour of the aluminum profile grille does not exceed the outer contour of the galvanized steel plate.

[0062] Specifically, Figure 3 As shown, before the grille is processed, the horizontal spacing of the grille needs to be adjusted according to the vertical plate seams of the aluminum veneer installed on site to ensure that the grille can cover the aluminum veneer plate seams after installation.

[0063] After the grille is processed in the processing plant, it is assembled into a finished product and covered with a protective film before being transported to the site and work surface. It is fixed to the aluminum panel with rivets. During the process, care must be taken to avoid collision between the grille and the aluminum panel, and pay attention to the protection of the finished product.

[0064] S600, hoisting the aluminum profile grille to the outside of the aluminum veneer and fixing it to the aluminum veneer; the step S600 includes:

[0065] The aluminum profile grille is hoisted to the outside of the aluminum veneer so that the aluminum profile grille overlaps with the galvanized steel plate, and then rivets are used on both sides of the aluminum profile grille to fix it to the aluminum veneer.

[0066] Specifically, the grille installation requires a 25-ton truck crane to lift the material to the installation location, and workers use two scissor lifts to coordinate the installation and fixation. Depending on the height of each unit, if the scissor lift cannot be lifted to the required height, a climbing vehicle can be used for installation.

[0067] S700, fixing and installing the rock wool board between adjacent steel keels; step S700 includes: cutting the rock wool board according to the size between two adjacent steel keels, filling the cut rock wool board between adjacent steel keels, and then clamping the rock wool board on the galvanized steel plate through a wire mesh or a deck, and then sealing and waterproofing the inner wall.

[0068] By zoning the galvanized steel plates, the standard aluminum panels are divided into regular areas and irregular areas. For the standard aluminum panels in the regular areas, the construction workers can replace and install them at will, and the aluminum panels in the irregular areas are adaptively cut, and suitable aluminum panels are installed in all positions. The aluminum plate joints are made more beautiful by drawing aluminum plate glue seam positioning lines, and one-piece aluminum profiles are made according to the aluminum plate glue seam positioning lines, which simplifies the assembly of aluminum profiles.

[0069] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. An irregular gable surface installation method, characterized in that: The method comprises the following steps: S100. Fix and install several steel keels between the roof frame and the ground; S200, collect the dimensions of each position of the wall, cut the galvanized steel plate according to the collected dimensions, and fix the galvanized steel plate on the outside of the steel keel; S300, filling the galvanized steel plate with a standard aluminum veneer, partitioning the galvanized steel plate into a regular area and an irregular area according to whether the standard aluminum veneer falls completely on the galvanized steel plate, calculating the number of aluminum veneers required for the regular area, dividing the irregular area into a plurality of small areas, cutting aluminum veneers at special positions according to the size of the small areas, and numbering the aluminum veneers and the small areas in one-to-one correspondence; S400, first fix and install the complete aluminum veneer in the regular area, and then fix and install the aluminum veneer in the special position and the small partition in the irregular area one by one; S500, manufacturing an aluminum profile grille according to the size of the joints between the filled aluminum veneers, and cutting the edge of the irregular area on the aluminum profile; S600, hoist the aluminum profile grille to the outside of the aluminum veneer and fix it to the aluminum veneer; S700, install the rock wool board between adjacent keels.

2. The irregular gable surface installation method according to claim 1, characterized in that: The step S200 includes: Select the appropriate galvanized steel plate according to the maximum horizontal and vertical dimensions of the wall; According to the other dimensions of the wall, the outline of the wall is carved on the galvanized steel plate; Cut the galvanized steel sheets according to the contours of the wall; The cut galvanized steel plates are hoisted to the outside of the steel keel and fixed on the steel keel.

3. The irregular gable surface installation method according to claim 1, characterized in that: The step S300 includes: Plane modeling is performed based on the collected wall dimensions, and the standard aluminum veneer is filled into the modeled plane. The area where the standard aluminum veneer completely falls into the modeling plane is the regular area, the area where the standard aluminum veneer does not completely fall into the modeling plane is the irregular area, and the area occupied by each part of the standard aluminum veneer that falls on the modeling plane is the small partition.

4. The irregular gable surface installation method according to claim 1, characterized in that: The step S400 includes: drawing aluminum plate glue seam positioning lines between adjacent aluminum plates on the galvanized steel plate according to the filling positions of the aluminum plates, and the areas divided by all the aluminum plate glue seam positioning lines are the areas filled with the aluminum plates.

5. The irregular gable surface installation method according to claim 4, characterized in that: The step S400 also includes: the aluminum veneers in the regular area do not need to be numbered, and the aluminum veneers in any regular area can be directly replaced and installed; Before installing aluminum veneers in irregular areas, carefully check the number, confirm the installation direction and installation position; Before installing the aluminum veneer, pre-install the aluminum plate fixing angle code according to the aluminum plate glue seam positioning line, and then install the aluminum veneer on the aluminum plate fixing angle code.

6. The irregular gable surface installation method according to claim 4, characterized in that: The step S500 includes: The aluminum plate glue seam positioning line is the dividing line of the filled aluminum veneer. The horizontal and vertical frames of the aluminum profile grille are manufactured according to the length and position of each aluminum plate glue seam positioning line. The horizontal and vertical frames of the aluminum profile grille have a certain width. The edge tangent direction of the irregular area does not necessarily coincide with the horizontal and vertical cut directions of the frame. Therefore, the horizontal and vertical frames of the aluminum profile grille are cut according to the edge lines of the irregular area so that the outer contour of the aluminum profile grille does not exceed the outer contour of the galvanized steel plate.

7. The irregular gable surface installation method according to claim 1, characterized in that: The step S600 includes: The aluminum profile grille is hoisted to the outside of the aluminum veneer so that the aluminum profile grille overlaps with the galvanized steel plate, and then rivets are used on both sides of the aluminum profile grille to fix it to the aluminum veneer.

8. The irregular gable surface installation method according to claim 1, characterized in that: Step S700 includes: The rock wool board is cut according to the size between two adjacent steel keels, and the cut rock wool board is filled between adjacent steel keels. The rock wool board is then clamped on the galvanized steel plate through a wire mesh or deck, and then the inner wall is sealed and waterproofed.

Citation Information

Patent Citations

  • Construction method of complicated form structure formwork

    CN107590334A

  • Special-shaped metal composite roof construction method

    CN116464282A

  • Construction method for installing decoration panel on large-span wall

    CN118390757A

  • Construction method of roof material, precut material, cut material, and set of roof material

    JP2020153119A

  • Roofing material allocation device

    JP7264356B1