Slope surface thin-layer plain concrete pouring mold and construction method

By pouring thin layer plain concrete in sections on the slope surface, using molds and construction methods of side molds and multiple cover plates, the problems of concrete aggregate concentration and separation are solved, and the construction quality is improved.

CN118933334APending Publication Date: 2024-11-12CHINA HUASHUI HYDROPOWER DEV CO LTD +2
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411108695.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-13
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

When pouring thin layer plain concrete on the slope surface, concrete aggregates are prone to concentrated bottom and segregation, resulting in poor construction quality.

Method used

Provide a slope surface thin-layer plain concrete pouring mold and construction method, including side molds and multiple cover plates. By first installing the bottom cover plate and pouring, and then installing the adjacent upper cover plate after the concrete is compacted. Pour concrete in sections to reduce the sliding force of concrete aggregate.

Benefits of technology

It effectively avoids the sliding and separation of concrete aggregates, improves the construction quality of thin-layer concrete on the slope surface, and ensures the appearance quality and compactness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933334A_ABST
    Figure CN118933334A_ABST
Patent Text Reader

Abstract

The invention relates to a slope surface thin-layer plain concrete pouring mold and a construction method, the slope surface thin-layer plain concrete pouring mold comprises a side mold and a plurality of cover plates, the side mold is of a frame-shaped structure and is provided with an upper opening, and the cover plates can be arranged on the side mold to seal the upper opening of the side mold. The slope surface thin-layer plain concrete pouring construction method comprises the following steps: S1, finishing a slope surface; s2, measuring and laying a geomembrane; s3, side films are installed, and graded pouring is conducted from bottom to top; s4, removing the side film and the cover plate after initial setting of the concrete; and S5, curing the initially set concrete. Compared with the prior art, the slope surface thin-layer plain concrete pouring construction method provided by the invention has the advantages that the abrupt slope is divided into a plurality of sections for respectively pouring concrete, and the amount of poured concrete each time is greatly reduced, so that the gliding force of concrete aggregate is reduced, and the phenomena of aggregate concentration and segregation are avoided; and the construction quality of thin-layer concrete on the slope surface is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of concrete construction, and in particular to a slope surface thin-layer plain concrete pouring mould and a construction method. Background Art

[0002] In traditional slope surface plain concrete pouring construction, the method of directly pouring and compacting after installing the side formwork on the bottom of the slope is often adopted. However, for slopes with large slopes, when pouring thin layers of plain concrete (thickness not more than 12cm), the concrete aggregates are often concentrated at the bottom and segregated during the vibration process, and the compaction of concrete pouring is difficult to control, and the construction quality is difficult to achieve the expected effect. This leaves common problems such as poor appearance quality and many leakage risks in the construction of plain concrete structures. Summary of the invention

[0003] In view of this, it is necessary to provide a slope surface thin layer plain concrete casting mold and construction method to solve the technical problems in the prior art that when pouring thin layer plain concrete on a slope surface, concrete aggregates are easily concentrated at the bottom and segregated, resulting in poor construction quality.

[0004] The invention provides a slope surface thin-layer plain concrete casting mold, which comprises: a side mold and a plurality of cover plates. The side mold is a frame-shaped structure with an upper opening. The plurality of cover plates can be respectively arranged on the side mold to seal the upper opening of the side film.

[0005] Furthermore, the side mold is a rectangular structure, including a bottom plate, a top plate and two side plates, and the two ends of the side plates are detachably connected to the bottom plate and the top plate, and / or the bottom plate, the top plate and the side plates are detachably connected to the slope surface.

[0006] Furthermore, the length of the cover plate is the same as that of the bottom plate, and both ends of the cover plate are detachably connected to the two side plates.

[0007] The invention provides a construction method for pouring thin-layer plain concrete on a slope surface, which comprises the following steps: S1, trimming the slope surface; S2, measuring and laying a geomembrane; S3, installing a side membrane, installing a first cover plate at the bottom, and then pouring plain concrete into the space below the first cover plate, vibrating while pouring, installing a second cover plate close to the first cover plate after checking that the concrete is vibrated and compacted, and pouring plain concrete into the space below the second cover plate and vibrating, and so on until all the pouring of the thin-layer plain concrete pouring mold on the slope surface is completed; S4, removing the side membrane and the cover plate after the concrete is initially set; S5, curing the concrete after the initial setting.

[0008] Furthermore, in step S1, the slope surface is excavated and trimmed according to the slope ratio, the loose areas are compacted, and garbage and debris on the slope surface are cleaned.

[0009] Furthermore, in step S2, after the design drawings are verified to be correct, the on-site leveling points and coordinate points are checked, a control coordinate network and leveling reference points are established on-site, and measurement and positioning are performed.

[0010] Furthermore, step S2 also includes cutting the geomembrane according to the layout positioning data and the design drawings, and laying and fixing the geomembrane.

[0011] Furthermore, in step S3, after the cover plate is installed, a counterweight is set on the cover plate to prevent the cover plate from running out of the mold or expanding the mold.

[0012] Furthermore, in step S5, the concrete is cured immediately after the side form and the cover plate are removed, and the surface of the concrete is covered with curing materials and sealed to prevent moisture evaporation.

[0013] Furthermore, the method also includes step S6, firstly pouring concrete at intervals on the first slope surface, then pouring concrete at intervals on the second slope surface, the concrete on the two slope surfaces are staggered, then pouring concrete at intervals on the first slope surface, and finally pouring concrete at intervals on the second slope surface.

[0014] Compared with the prior art, the slope surface thin layer plain concrete casting mold provided by the present invention can install multiple cover plates on the side membrane. During construction, the lowest cover plate is installed first and cast, and the adjacent upper cover plate is installed after the concrete is dense, and then cast; by dividing the steep slope into multiple sections and casting concrete separately, the amount of concrete cast each time is greatly reduced, thereby reducing the sliding force of concrete aggregate, avoiding aggregate concentration and segregation, and ensuring the construction quality of the slope surface thin layer concrete.

[0015] The above description is only an overview of the technical solution of the present invention. In order to more clearly understand the technical means of the present invention and implement it according to the contents of the specification, the preferred embodiments of the present invention are described in detail as follows with reference to the accompanying drawings. The specific implementation of the present invention is given in detail by the following embodiments and their accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of this application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings: FIG1 is a side view of a preferred embodiment of a thin-layer plain concrete casting mold for a slope surface provided by the present invention; Figure 2 A top view of a preferred embodiment of a thin-layer plain concrete casting mold for a slope surface provided by the present invention; Figure 3 A flow chart of the method for pouring thin-layer plain concrete on a slope surface provided by the present invention; Figure 4 This is a schematic diagram of step S6 in the method for pouring thin-layer plain concrete on a slope surface provided by the present invention. DETAILED DESCRIPTION

[0017] The preferred embodiments of the present invention will be described in detail below in conjunction with the accompanying drawings, wherein the accompanying drawings constitute a part of this application and are used together with the embodiments of the present invention to illustrate the principles of the present invention, but are not used to limit the scope of the present invention.

[0018] See also Figure 1 and Figure 2 The thin layer plain concrete casting mold for the slope surface comprises a side mold 1 and a plurality of cover plates 2. The side mold 1 is a frame-shaped structure with an upper opening. The side mold 1 is used to limit the concrete on the side to form the edge of the concrete casting layer. The plurality of cover plates 2 can be respectively arranged on the side mold 1 to cover the upper opening of the side film 1. The cover plates 2 are used to limit the concrete on the top surface to eliminate the collapse phenomenon that is easy to occur in the thin layer of concrete.

[0019] In this embodiment, the side mold 1 is a rectangular structure, including a bottom plate 11, a top plate 12 and two side plates 13. It is easy to understand that the bottom plate 11 is arranged at the bottom of the slope surface, the top plate 12 is arranged at the top of the slope surface, and the side plates 13 are arranged along the slope surface. The two ends of the side plate 13 are detachably connected to the bottom plate 11 and the top plate 12, and / or the bottom plate 11, the top plate 12 and the side plates 13 are detachably connected to the slope surface.

[0020] In some embodiments, the bottom plate 11 and the top plate 12 are made of two layers of 18mm hardened plywood, and the longitudinal joints of adjacent plywood are connected with steel nails. To ensure a perfect fit, glue can be embedded before the joints are joined. The side plate 13 is made of 12# channel steel (12cm*5.5cm*0.6cm) by welding, and holes are drilled every 0.9m on one side (hole diameter 12mm, used to fix the side plate 13 with slope surface reinforcement).

[0021] In this embodiment, the length of the cover plate 2 is the same as that of the bottom plate 11, and the two ends of the cover plate 2 are detachably connected to the two side plates 13. Multiple cover plates 2 can be connected to the two side plates 13 in a side-by-side arrangement to close the upper opening of the side membrane 1.

[0022] In some embodiments, the cover plate 2 has a specification of 0.6m×5.4m and is made of aluminum alloy square tubes (specifications of 80mm×40mm×3mm) and hardened plywood (1830mm×915mm×18mm or 2440mm×1220mm×18mm) after cutting. The square tube welding joints are tight and the plywood joints are filled to ensure a tight fit.

[0023] See also Figure 3The present invention also provides a method for pouring a thin layer of plain concrete on a slope surface, the method comprising the following steps: S1. Repair the slope surface.

[0024] S2. Measure and lay geomembrane.

[0025] S3, install the side membrane 1, and fix the side membrane 1 at the selected position on the slope surface. Install the first cover plate at the bottom, and then pour plain concrete into the space below the first cover plate, and vibrate while pouring. After checking and vibrating to make it dense, install the second cover plate against the first cover plate above the first cover plate, and pour plain concrete into the space below the second cover plate and vibrate. And so on until the entire casting of the thin layer of plain concrete casting mold on the slope surface is completed.

[0026] S4. Remove the side membrane and cover plate after the concrete has initially set.

[0027] S5. Curing of concrete after initial setting.

[0028] The method for pouring thin-layer plain concrete on a slope surface provided by the present invention divides a steep slope into multiple sections and pours concrete separately, so that the amount of concrete poured each time is greatly reduced, thereby reducing the sliding force of concrete aggregates, avoiding aggregate concentration and segregation, and ensuring the construction quality of the thin-layer concrete on the slope surface.

[0029] In some embodiments, step S1 is to trim the slope surface. Specifically, the slope surface can be leveled according to the slope ratio using construction machinery (such as an excavator), and loose soil areas can be compacted or replaced with compaction treatments. Support measures are adopted for special geological structures. After mechanical slope trimming, manual inspection and review are carried out according to the design slope ratio and flatness requirements; unqualified areas are manually trimmed. After the slope surface is trimmed, the construction waste and debris on the slope surface are cleaned up in a timely manner.

[0030] In some embodiments, the measurement part of step S2 specifically includes checking the design drawings for correctness, verifying the on-site leveling points and coordinate points, and formally positioning after eliminating problems such as excessive errors. A control coordinate network and leveling reference points are established on site. The leveling reference points need to be introduced by permanent leveling points, which are set in a stable and reliable soil layer near the building. The leveling points should take protective measures to ensure that the leveling points are not damaged. After measuring and positioning, the relevant units and departments shall be reported for acceptance, and construction can only begin after passing the inspection.

[0031] The laying of geomembrane in step S2 specifically includes cutting the geomembrane according to the design drawings based on the positioning data of the layout. The geomembrane is laid and fixed in the following order: spread along the slope → find a point for positioning → fix at the top of the slope → smooth out along the slope → fix at the bottom of the slope → smooth out horizontally along both sides → fix on both sides → review and clean the surface. Before laying, check the quality of the geomembrane to ensure that there is no damage and quality problems, and clean the construction surface in advance to ensure that the construction surface is flat, clean and free of debris. When laying, attention should be paid to the flatness and tension of the fabric to avoid wrinkles and creases. The joints and edges of the geomembrane are welded to ensure that the joints are firm, flat and leak-free. When fixing, set fixing points at the edge of the geomembrane and fix the geomembrane to the ground with ground nails or other fixing devices.

[0032] In some embodiments, the geomembrane adopts roughened filament composite geomembrane (ie "two cloths and one membrane") with specifications of 300 / 0.5 / 300, and the breaking strength (longitudinal ≥19.3kN / m, transverse ≥19.3kN / m), tear strength (longitudinal ≥0.67kN, transverse ≥0.67kN), CBR bursting strength (≥3.1kN), vertical permeability coefficient, and hydrostatic pressure resistance (≥1.0MPa) all meet the design and specification requirements.

[0033] In some embodiments, in step S3, when pouring concrete, the bottom of the slope is used as the starting surface, and the concrete is poured from the middle to the angles on both sides. Each cover plate 2 is laid as the first level of concrete is poured, and the concrete is vibrated with a vibrator while pouring. After the current level of concrete is verified to be poured and vibrated densely, the previous level of construction can be carried out from the bottom to the top along the slope. After pouring the next level, the cover plate 2 of the previous level can be installed. The cover plate 2 is installed step by step, and then concrete is poured step by step, and the process is repeated in sequence until the pouring is completed. In addition, the slump of the concrete entering the warehouse should be controlled between 120-140, with a minimum of 110 and a maximum of 160.

[0034] Concrete can be C30W6F100 commercial concrete, the slump is controlled within the range of 100~150, the mix ratio should comply with the requirements of relevant specifications, and the aggregate particle size should meet the on-site casting thickness limit requirements.

[0035] After the cover plate 2 is installed, a counterweight is set on the cover plate 2 to prevent the cover plate 2 from running out of the mold or expanding the mold when pouring concrete. The counterweight can be in the form of sand, gravel and soil filled in a woven bag. The advantage is that it can be made from local materials and is more convenient to use. For example, a 60cm*90cm woven bag is used, and about 60% to 70% of sand is filled in, and then tied or threaded to seal it.

[0036] In some embodiments, the specific operation of step S5 is to perform curing immediately after pouring to prevent the concrete from cracking due to excessive water loss. When the curing material is covered on the concrete surface, the material should be well sealed to prevent water evaporation. During the curing period, the concrete surface should not be subjected to any gravity impact or vertical pressure. During the curing period, no additional load or turbulence should be applied to the concrete surface. Any damage during the concrete curing process should be repaired in time.

[0037] See also Figure 4 In some embodiments, after step S5, there is a step S6. For a longer slope surface, concrete needs to be poured in blocks. The following is an example of a ditch, which has two slope surfaces: a first slope surface A and a second slope surface B. First, concrete is poured on the first slope surface A at intervals, and then concrete is poured on the second slope surface B at intervals, and the concrete on the two slope surfaces is staggered. Then, concrete is poured in the intervals on the first slope surface A, and finally, concrete is poured in the intervals on the second slope surface B. That is, concrete is poured in the order of the first slope surface A (①→③→⑤→⑦→…) → the second slope surface B (②→④→⑥→⑧→…) → the first slope surface A (②→④→⑥→⑧→…) → the second slope surface B (①→③→⑤→⑦→…). If there is only one slope surface, concrete is poured in the order of the first slope surface A (①→③→⑤→⑦→…) → the first slope surface A (②→④→⑥→⑧→…)).

[0038] Compared with the prior art, the slope surface thin layer plain concrete casting mold provided by the present invention can install multiple cover plates on the side membrane. During construction, the lowest cover plate is installed first and cast, and the adjacent upper cover plate is installed after the concrete is dense, and then cast; by dividing the steep slope into multiple sections and casting concrete separately, the amount of concrete cast each time is greatly reduced, thereby reducing the sliding force of concrete aggregate, avoiding aggregate concentration and segregation, and ensuring the construction quality of the slope surface thin layer concrete.

[0039] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily conceived by any technician familiar with the technical field within the technical scope disclosed by the present invention should be covered within the protection scope of the present invention.

Claims

1. A thin layer of plain concrete casting mold for slope surface, It is characterized in that It includes: The side mold and a plurality of cover plates, wherein the side mold is a frame-shaped structure and has an upper opening, and the plurality of cover plates can be respectively arranged on the side mold to cover the upper opening of the side membrane.

2. The slope surface thin layer plain concrete casting mold according to claim 1, It is characterized in that The side mold is a rectangular structure, including a bottom plate, a top plate and two side plates, the two ends of the side plates are detachably connected to the bottom plate and the top plate, and / or the bottom plate, the top plate and the side plates are detachably connected to the slope surface.

3. The slope surface thin layer plain concrete casting mold and construction method according to claim 2, It is characterized in that The length of the cover plate is the same as that of the bottom plate, and two ends of the cover plate are detachably connected to the two side plates.

4. A construction method for pouring thin-layer plain concrete on a slope surface. It is characterized in that It includes the following steps: S1, trim the slope surface; S2. Measure and lay geomembrane; S3. Install the side membrane according to any one of claims 1 to 3, and install the first cover plate at the bottom, then pour plain concrete into the space below the first cover plate, and vibrate while pouring, after checking that the concrete is compacted by vibration, install the second cover plate close to the first cover plate, and pour plain concrete into the space below the second cover plate and vibrate, and so on until the entire casting of the thin layer of plain concrete casting mold on the slope surface is completed; S4, after the initial setting of the concrete, the side membrane and the cover plate are removed; S5. Curing of concrete after initial setting.

5. The method for pouring thin-layer plain concrete on a slope surface according to claim 4, It is characterized in that In step S1, the slope surface is excavated and trimmed according to the slope ratio, the loose areas are compacted, and garbage and debris on the slope surface are cleaned.

6. The method for pouring thin-layer plain concrete on a slope surface according to claim 4, It is characterized in that In step S2, after the design drawings are verified to be correct, the on-site leveling points and coordinate points are checked, a control coordinate network and leveling reference points are established on-site, and measurement and positioning are performed.

7. The method for pouring thin-layer plain concrete on a slope surface according to claim 6, It is characterized in that Step S2 also includes cutting the geomembrane according to the layout positioning data and the design drawings, and laying and fixing the geomembrane.

8. The method for pouring thin-layer plain concrete on a slope surface according to claim 4, It is characterized in that In step S3, after the cover plate is installed, a counterweight is arranged on the cover plate to prevent the cover plate from running out of the mold or expanding the mold.

9. The method for pouring thin-layer plain concrete on a slope surface according to claim 4, It is characterized in that In step S5, the concrete is cured immediately after the side form and the cover plate are removed, and the surface of the concrete is covered with curing materials and sealed to prevent water evaporation.

10. The method for pouring thin-layer plain concrete on a slope surface according to claim 4, It is characterized in that The method also includes step S6, firstly pouring concrete at intervals on the first slope surface, then pouring concrete at intervals on the second slope surface, with the concrete on the two slope surfaces staggered, then pouring concrete at intervals on the first slope surface, and finally pouring concrete at intervals on the second slope surface.

Citation Information

Patent Citations

  • Spaced formwork supporting and concrete pouring method for pitched roof

    CN104674999A

  • Construction method and double-layer formwork structure for cast-in-situ slope roof

    CN106437142A

  • Slope protection concrete pouring mold for highly steep slope surface and slope protection construction method

    CN110644429A

  • A drawer -type formwork that is used for heavy grade slope concrete to strut

    CN205776079U

  • Slope construction aid and slope construction method

    JP6319864B1