Shallow-buried excavation method under advanced assembly type preformed ring support

By adopting the advanced prefabricated pre-ring support method in the Quaternary strata, the problems of high pre-support costs, complex processes and unreliable reinforcement effects of traditional shallow burial and dark excavation methods are solved, and higher construction safety and Reliability shortens construction cycle and reduces disturbances to the surrounding environment.

CN118933810AActive Publication Date: 2024-11-12CHINA RAILWAY SIYUAN SURVEY & DESIGN GRP CO LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202411158871.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-22
Publication Date
2024-11-12
Estimated Expiration
2044-08-22

AI Technical Summary

Technical Problem

The traditional shallow burial and hidden excavation method faces high pre-maintenance costs, complex processes, unreliable reinforcement effects and long engineering cycle problems in the Quaternary strata with abundant groundwater and poor self-stabilization capabilities, resulting in collapse and ground during tunnel construction. Undesirable consequences such as collapse, water and sand gushing in tunnels and ground settlement.

Method used

Adopting the advanced pre-ring support method, by constructing work wells at both ends of the tunnel, setting up grooves and water-stop ring plates, using rope saws to form disturbing profile belts, and grouting bentonite slurry inside them, to produce on-site prefabricated The steel shield ring is closed and the advance pre-support system is formed by dragging and anchoring through the wire rope to reduce disturbance to the surrounding environment and shorten the construction cycle.

Benefits of technology

It improves the safety and reliability of tunnel construction, reduces project costs, reduces disturbances in the surrounding environment, shortens the construction cycle, ensures the stability and construction accuracy of the tunnel excavation process, and improves resource utilization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933810A_ABST
    Figure CN118933810A_ABST
Patent Text Reader

Abstract

The invention discloses an advanced assembly type preformed ring support shallow-buried excavation method which comprises the steps that working wells are constructed at the two ends of a tunnel, a groove is formed in the side wall of the tunnel, a water stop ring plate is installed, a rope saw penetrates through a horizontal drill hole and is tensioned, and the rope saw disturbs a soil body outside a tunnel excavation contour in a segmented mode along the contour of a pre-cutting groove in the straightened state to form a disturbance contour belt; bentonite slurry is injected into the disturbance contour belt through grouting equipment to form a lubricating belt, a steel shield ring assembled on site is manufactured according to the disturbance contour belt, the steel shield ring is assembled and positioned in the working well, the steel shield ring is dragged in the working well at the other end through a steel wire rope, and continuous splicing is conducted in the dragging process. The steel shield ring is connected with the side wall in an anchoring mode after reaching the working well at the other end, and an advanced pre-supporting system is formed. The pre-cutting groove is formed by tensioning the rope saw, then the steel shield ring is dragged to the designated position to form the closed steel shield ring, it is guaranteed that collapse and leakage are avoided in the tunnel excavation process, and the method has the advantages of being efficient, economical and safe and is suitable for various underground engineering and tunnel engineering fields.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of underground engineering or tunnel engineering such as highway, municipal engineering, rail transit, etc., and in particular to a shallow buried dark excavation method under advanced assembled preformed ring support. Background Art

[0002] The main methods of tunnel construction are open excavation and dark excavation (including shield method, pipe jacking method, mining method, shallow buried dark excavation method, etc.). The determination of tunnel construction methods is affected by many factors such as hydrogeology, engineering geology, surrounding environment, tunnel burial depth, excavation width, etc., and has a direct impact on the surrounding environment, construction period, cost, operation and other aspects. When constructing short-distance shallow-covered urban tunnels under the Quaternary strata, open excavation construction is more difficult due to the control of factors such as ground traffic, underground pipe network and surrounding environment; and due to the short construction distance, the use of shield construction is not economical, so shallow buried dark excavation or pipe jacking and other dark excavation construction techniques are usually used, such as urban crosswalks, subway entrances and exits, and integrated pipe corridors. In the Quaternary strata with abundant groundwater and poor self-stabilization ability, when using shallow buried dark excavation or pipe jacking techniques, it is usually necessary to take strong advance pre-support measures, lower the groundwater level and improve the stratum and other engineering reinforcement measures. Advanced pre-support generally adopts measures such as advanced pre-grouting, advanced pipe roof (pipe curtain), full-section curtain grouting and freezing method.

[0003] Due to the complexity and uncertainty of underground engineering hydrogeology, as well as the unreliability of reinforcement measures, the traditional shallow buried dark excavation method usually faces the following problems in the Quaternary strata with abundant groundwater and poor self-stabilization capacity: some advanced pre-support costs are high, such as full-section curtain grouting, advanced pipe curtain and freezing method; some advanced pre-support processes are complicated, such as advanced pipe curtain and freezing method; some advanced pre-support reinforcement effects are not very reliable, such as full-section curtain grouting, whose grouting effect cannot improve the stratum uniformly and has poor water-stopping effect; long engineering cycle, such as freezing method, etc. These problems can easily lead to adverse consequences such as tunnel collapse, ground collapse, water and sand gushing in the tunnel and ground subsidence during tunnel excavation. Summary of the invention

[0004] In view of the shortcomings of the prior art, the present invention proposes an advanced assembled pre-formed ring support shallow buried tunneling method, which aims to solve the problems of high pre-support costs, complex processes, unreliable reinforcement effects and long engineering periods faced by traditional shallow buried tunneling methods in Quaternary strata with abundant groundwater and poor self-stabilization ability. By adopting a pre-formed ring support structure, higher safety and reliability can be achieved in the tunnel construction process, while reducing disturbances to the surrounding environment, shortening the construction period and reducing engineering costs.

[0005] To achieve the above object, the technical solution of the present invention is as follows: an advanced assembled pre-formed ring support shallow buried dark excavation method, comprising the following steps:

[0006] S1, construct the working wells at both ends of the tunnel, the first working well and the second working well respectively;

[0007] S2, setting grooves on the side walls of the tunnel in the working pits at both ends, and the contour of the grooves extends a certain distance outside the tunnel excavation contour range;

[0008] S3, applying a water stop ring plate outside the contour range of the cutting groove;

[0009] S4, drilling a hole horizontally at the groove cutting position of the tunnel side wall through the first working well at one end to the second working well at the other end, and inserting a rope saw;

[0010] S5, tensioning the rope saw so that the rope saw is in a straight state;

[0011] S6, repeatedly moving the rope saw in a stretched state, and disturbing the soil outside the tunnel excavation contour in sections along the contours of the grooves pre-set on the tunnel side walls of the first working shaft and the second working shaft, to form a disturbed contour zone;

[0012] S7, injecting bentonite slurry into the disturbed contour zone through a grouting device to form a lubricating zone;

[0013] S8, a steel shield ring that can be assembled on site is manufactured according to the disturbance contour band of the tunnel, and a towing device is reserved at one end of the steel shield ring;

[0014] S9, assembling the steel shield ring in the first working shaft and positioning it according to the disturbance contour band;

[0015] S10, dragging the steel shield ring in the second working shaft at the other end through the steel wire rope, and continuously splicing the steel shield ring as the dragging progresses;

[0016] S11, after the steel shield ring reaches the second working shaft at the other end, the steel shield ring is anchored and connected to the side wall of the second working shaft to form an advanced pre-support system;

[0017] S12, excavate the soil inside the tunnel, carry out initial support and pour reinforced concrete secondary lining to complete the entire tunnel construction.

[0018] Preferably, the excavation profile of the tunnel is elliptical, horseshoe-shaped, rectangular or circular.

[0019] Preferably, a wire brush is provided on the water stop ring plate.

[0020] Preferably, the steel shield ring is a closed steel shield ring, and the steel shield ring can be pulled out and reused.

[0021] Preferably, the steel shield ring can be welded into a ring in the working well and then dragged into the ground along the disturbance contour belt, or it can be divided into blocks with reserved interconnected joints, and each block can be directly dragged into the ground along the disturbance contour belt.

[0022] Preferably, the steel shield ring has twelve towing points evenly distributed on the circular ring for steel wire ropes to act on to tow the steel shield ring.

[0023] Preferably, the steel shield ring is divided into blocks according to the size and shape of the tunnel excavation profile, and the entire ring can be divided into 4 or 6 blocks.

[0024] Preferably, the blocks of the steel shield ring are connected by bent joints, and grouting pipes are arranged at the contact points of the two bent joints, so as to ensure the sealing and connection stability between the blocks by grouting.

[0025] Preferably, the thickness of the steel shield ring is determined according to engineering geology, hydrogeology, surrounding environment, cover depth and excavation width.

[0026] Preferably, the disturbed contour zone of the tunnel is formed by segmented disturbance using a wire saw.

[0027] The beneficial effects of the present invention are as follows:

[0028] (1) The use of a closed steel shield ring ensures that there will be no collapse or leakage during tunnel excavation. At the same time, the use of tension positioning can accurately position the steel shield ring according to the predetermined position to avoid deviation and ensure construction accuracy. The use of a closed steel shield ring has high pre-reinforcement strength and small stratum settlement; there is no need to lower the groundwater level, thereby reducing disturbance to the surrounding environment and maintaining environmental stability.

[0029] (2) Compared with the traditional grouting reinforcement measures, the present invention only injects a small amount of bentonite slurry within the disturbance zone, which plays a role in lubrication and reducing friction when dragging the steel shield ring. In addition, after the main construction of the tunnel is completed, the steel shield ring can be pulled out and reused, which improves resource utilization and reduces environmental pollution. During the construction process, pre-cutting is performed first, and then the steel shield ring is dragged into place. The entire construction period is greatly shortened, the construction efficiency is improved, and the strict requirements of modern engineering on the construction period are met. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 It is a flow chart of the advanced assembled pre-formed ring support shallow buried dark excavation method according to an embodiment of the present invention;

[0031] Figure 2 It is a plan view of the working well arrangement at both ends of the tunnel to be excavated according to an embodiment of the present invention;

[0032] Figure 3 It is a cross-sectional view of the arrangement of working wells at both ends of a tunnel to be excavated according to an embodiment of the present invention;

[0033] Figure 4 is a cutting profile diagram of an embodiment of the present invention;

[0034] Figure 5 is a layout diagram of a water stop ring plate according to an embodiment of the present invention;

[0035] Figure 6 yes Figure 5 A local enlarged view of point A;

[0036] Figure 7 : is a layout diagram of horizontal drilling and wire rope insertion in a slot according to an embodiment of the present invention;

[0037] Figure 8 yes Figure 7 1-1 cross-sectional view;

[0038] Fig. 9 This is a schematic diagram of assembling a steel shield ring in a working pit according to an embodiment of the present invention;

[0039] Fig.10 yes Fig. 9 2-2 section view;

[0040] Fig.11 is a schematic diagram of the structure of an assembled steel shield ring according to an embodiment of the present invention;

[0041] Fig.12 Schematic diagram of dragging a steel shield ring into the ground according to an embodiment of the present invention;

[0042] Fig.13 Schematic diagram of a pre-support system in which all steel shield rings of an embodiment of the present invention are buried in the ground;

[0043] Fig.14 Schematic diagram of the steel shield ring blocks of an embodiment of the present invention;

[0044] Fig.15 It is a schematic diagram of a steel shield ring block-to-soil connection interface according to an embodiment of the present invention;

[0045] Fig.16 yes Fig.15 A local enlarged view of point B;

[0046] Fig.17 It is a schematic diagram of a connection interface of a steel shield ring in another embodiment of the present invention where the steel shield ring is embedded in the ground in blocks;

[0047] Fig.18 yes Fig.17 A partial enlarged view of point C.

[0048] Figure numerals: 1-first working shaft; 2-second working shaft; 3-tunnel side wall; 4-cutting groove; 5-water stop ring plate; 6-rope saw; 7-disturbance profile belt; 8-steel shield ring; 9-towing device; 10-wire rope; 11-wire brush; 12-joint; 13-grouting pipe; 14-bracket. DETAILED DESCRIPTION

[0049] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention belong to the present invention.

[0050] In addition, described feature, structure or characteristic can be combined in one or more embodiments in any suitable manner. In the following description, many specific details are provided to provide a full understanding of the embodiments of the present application. However, those skilled in the art will appreciate that the technical scheme of the present application can be put into practice without one or more of the specific details, or other methods, components, devices, steps, etc. can be adopted. In other cases, known methods, devices, realizations or operations are not shown or described in detail to avoid blurring the various aspects of the application.

[0051] See also Figure 1-18 This embodiment provides a prefabricated pre-formed ring support shallow buried dark excavation method, including the following steps:

[0052] S1, the working shafts at both ends of the construction tunnel are the first working shaft 1 and the second working shaft 2 respectively.

[0053] This step is the starting step of the entire shallow buried tunneling method. It is necessary to construct a working well at each end of the tunnel. These two working wells are the first working well 1 and the second working well 2. The construction of the working well is the starting point of the entire tunnel construction process. Ensure that the position and size of the working well meet the design requirements, and provide a basis for the subsequent installation of the groove 4 and the steel shield ring 8.

[0054] S2, a groove 4 is provided on the tunnel side wall 3 in the working shaft at both ends, and the outline of the groove 4 is extended a certain distance outside the tunnel excavation outline range.

[0055] In this step, a groove cutting 4 is performed on the tunnel side wall 3 in the first working shaft 1 and the second working shaft 2. The outline of the groove 4 should be expanded a certain distance outside the tunnel excavation outline range. The purpose of this step is to create conditions for the installation of the water-stopping ring plate 5 and the subsequent soil disturbance. The excavation outline of the tunnel is elliptical, horseshoe, rectangular or circular. Different tunnel outline shapes can be selected according to specific engineering requirements and geological conditions to adapt to different construction environments and structural requirements. The elliptical outline is suitable for areas with more complex geological conditions because this shape can evenly distribute the force. The horseshoe outline is often used in tunnels that require a larger space, such as subway and highway tunnels. The rectangular outline is suitable for underground pipe galleries and some special-purpose tunnels because this shape is convenient for arranging equipment and pipelines. The circular outline is usually used for pressure tunnels and deep buried tunnels because the circular structure can best withstand pressure from all directions.

[0056] S3, apply the water stop ring plate 5 on the outside of the contour range of the groove 4.

[0057] In this step, a water stop ring plate 5 is installed outside the contour range of the cutting groove 4. The water stop ring plate 5 can be made of I-beam. The function of the water stop ring plate 5 is to prevent soil and water loss outside the working well from entering the working wells 1 and 2 during the process of cutting the groove, forming the disturbed contour belt by the rope saw, and dragging the steel ring in the later stage, so as to ensure that soil and water do not lose or only a small amount of water seeps but no sand leaks. A wire brush 11 is arranged on the water stop ring plate 5. The wire brush 11, through its flexibility and close arrangement, ensures that the rope saw 6 prevents groundwater from overflowing from the soil with mud and sand in large quantities during the process of disturbing and cutting the soil. The sealing grease can also be continuously filled in the wire brush 11 to further enhance its sealing effect.

[0058] S4, drilling a hole horizontally at the position of the groove 4 of the tunnel side wall 3 through the first working well 1 at one end to the second working well 2 at the other end, and inserting a rope saw 6.

[0059] In this step, a horizontal hole is drilled from the first working shaft 1 to the second working shaft 2 at the location of the groove 4 in the tunnel side wall 3, and a rope saw 6 is inserted. The rope saw 6 will be used to disturb the soil and form a disturbed contour zone 7 in subsequent steps.

[0060] S5, tensioning the wire saw 6, so that the wire saw 6 is in a stretched state.

[0061] In this step, the wire saw 6 is tensioned to be in a straight state, so as to ensure that the wire saw 6 can accurately move along a predetermined path when disturbing the soil, thereby forming a uniform disturbance contour zone 7 .

[0062] S6, the rope saw 6 is repeatedly moved in a stretched state, and the soil outside the tunnel excavation contour is disturbed in sections along the contour of the pre-set grooves 4 on the tunnel side walls 3 of the first working shaft 1 and the second working shaft 2, to form a disturbed contour zone 7.

[0063] In this step, the tensioned wire saw 6 is repeatedly moved in a stretched state, and the soil outside the tunnel excavation contour is disturbed in sections along the contour of the pre-set groove 4 of the tunnel side wall 3 of the first working shaft 1 and the second working shaft 2 to form a disturbed contour belt 7. The purpose of this step is to reduce the friction of the soil and facilitate the subsequent grouting and installation of the steel shield ring 8. The disturbed contour belt 7 of the tunnel is formed by the segmented disturbance of the wire saw 6. The segmented disturbance operation of the wire saw 6 is flexible and can be adjusted according to specific geological conditions and construction requirements to ensure that the formation of the disturbed belt 7 is uniform and meets the design requirements.

[0064] S7, injecting bentonite slurry into the disturbed contour zone 7 through a grouting device to form a lubricating zone.

[0065] In this step, a grouting device is used to inject bentonite slurry into the disturbed contour zone 7 to form a lubricating zone. Other materials can also be selected as the lubricating material. The lubricating zone can reduce the friction resistance of the steel shield ring 8 during the dragging process and improve the construction efficiency and accuracy.

[0066] S8, a steel shield ring 8 that can be assembled on site is manufactured according to the tunnel disturbance contour band 7, and a towing device 9 is reserved at one end of the steel shield ring 8.

[0067] In this step, a steel shield ring 8 that can be assembled on site is made according to the disturbance contour band 7 of the tunnel, and a towing device 9 is reserved at one end of the shield ring 8. The towing device 9 can be in the form of holes, etc. These holes are used to drag the steel shield ring 8 to a predetermined position. The steel shield ring 8 is the core component of the present invention as a pre-assembled prefabricated ring support system. It is ensured to adapt to the actual situation through on-site assembly, and the friction resistance is reduced during the towing process, so that it can reach the predetermined position smoothly.

[0068] S9, assemble the steel shield ring 8 in the first working shaft 1 and position it according to the disturbed contour band 7.

[0069] In this step, a steel shield ring 8 is assembled in the first working shaft 1. The steel shield ring 8 is assembled from multiple steel rings and is positioned according to the position of the disturbance contour band 7 to ensure that the steel shield ring 8 can accurately enter the disturbance contour band 7 of the tunnel. A bracket 14 is provided at the bottom of the steel shield ring 8 for support.

[0070] S10, drag the steel shield ring 8 in the second working shaft 2 through the steel wire rope 10, and continuously splice the steel shield ring 8 as the dragging progresses.

[0071] In this step, the steel shield ring 8 is dragged in the second working shaft 2 using the steel wire rope 10, and new steel shield rings 8 are continuously spliced ​​as the dragging progresses until all the shield rings 8 are in place.

[0072] S11, after the steel shield ring 8 reaches the second working shaft 2, the steel shield ring 8 is anchored and connected to the side wall of the second working shaft 2 to form an advanced pre-support system.

[0073] In this step, when the steel shield ring 8 reaches the second working shaft 2, it is anchored and connected to the side wall of the second working shaft 2 to form a complete advance pre-support system, which will provide reliable support for the safe excavation of the tunnel.

[0074] S12, excavate the soil inside the tunnel, carry out initial support and pour reinforced concrete secondary lining to complete the entire tunnel construction.

[0075] This step is the final step of the entire shallow buried tunneling method. It involves excavating the soil in the tunnel, carrying out initial support, and pouring reinforced concrete secondary lining to complete the entire tunnel construction process. Initial support and secondary lining ensure the stability and durability of the tunnel structure.

[0076] Furthermore, the steel shield ring 8 is a closed steel shield ring. This design ensures that a complete annular support structure is formed during the tunnel construction process, which can effectively prevent the infiltration of soil and groundwater and provide strong support. The steel shield ring 8 can be pulled out and reused, and this feature greatly improves the construction efficiency and economy. After the tunnel construction is completed, the steel shield ring 8 can be pulled out and reused in other similar projects, reducing material waste and construction costs. The steel shield ring 8 can also be welded into a ring in the working well according to different tunnel contour requirements and then dragged into the soil along the disturbance contour belt 7 to a predetermined position. In addition, it can also be divided into blocks and reserved with interconnected joints 12, and each block can be directly dragged into the soil along the disturbance contour belt 7. In this case, the steel shield ring 8 is divided into several blocks, and each block is reserved with interconnected joints 12. Each block can be dragged into the soil separately, and then spliced ​​at a predetermined position. This method is suitable for environments with limited construction space and is convenient for construction operations and adjustments.

[0077] In order to facilitate uniform force during the process of dragging the steel shield ring 8 in step S10, the steel shield ring 8 has twelve dragging points, which are evenly distributed on the circular ring for the steel wire rope 10 to act on to drag the steel shield ring 8. These dragging points are reasonably designed to effectively reduce friction resistance, improve dragging efficiency, ensure the stability and safety of the steel shield ring 8 during movement, and avoid deformation or damage due to uneven force.

[0078] See also Fig.14The steel shield ring 8 can be divided into blocks according to the size and shape of the tunnel excavation profile, and the whole ring can be divided into 4 or 6 blocks for easy transportation and installation. For example, for a larger diameter tunnel, the steel shield ring 8 can be divided into 6 blocks, while for a smaller diameter tunnel, it can be divided into 4 blocks. This block design improves the flexibility of construction and is convenient for adjustment and adaptation in different construction environments.

[0079] See also Figure 15-18 , which discloses two embodiments, in which the blocks of the steel shield ring 8 are connected by a bent joint 12, and a grouting pipe 13 is arranged at the contact point of the two bent joints 12. Grouting is used to ensure the sealing and connection stability between the blocks. The design of the bent joint 12 enables the blocks to be tightly connected together to form a complete annular structure. The difference between the two embodiments lies in the different designs of the joint 12. A grouting pipe 13 is arranged at the contact point of the joint 12, and by injecting slurry into the joint 12, the gap between the joints 12 can be effectively filled, ensuring the sealing between the blocks, preventing groundwater from infiltrating, and improving the stability of the connection. This design not only ensures the integrity and safety of the tunnel structure, but also facilitates the adjustment and reinforcement of the joint 12 during the actual construction process to ensure the construction quality.

[0080] The thickness of the steel shield ring 8 is determined according to factors such as engineering geology, hydrogeology, surrounding environment, cover depth and excavation width. When designing and manufacturing the steel shield ring 8, multiple factors need to be considered comprehensively. The engineering geology and hydrogeology conditions determine the stability of the soil layer around the tunnel and the influence of groundwater, thereby affecting the stress condition of the steel shield ring 8. The surrounding environment involves the surface buildings and facilities in the construction area. It must be ensured that the thickness of the steel shield ring 8 is sufficient to support the tunnel structure without affecting the surrounding facilities. The cover depth and excavation width directly affect the required strength and rigidity of the steel shield ring 8. It must be ensured that the steel shield ring 8 can provide sufficient support and protection at different depths and widths.

[0081] In summary, the present invention provides a pre-assembled pre-formed ring support shallow buried dark excavation method, which has significant advantages and practicality. The method includes constructing a working well 1 at both ends of the tunnel, cutting a groove 4 on the side wall 3 of the tunnel, and installing a water stop ring plate 5, inserting a rope saw 6 through a horizontal drilling hole and tensioning it, so that the rope saw 6 disturbs the soil outside the tunnel excavation contour in sections along the contour of the pre-cut groove 4 in a straight state, forming a disturbed contour belt 7. Then, bentonite slurry is injected into the disturbed contour belt 7 through a grouting device to form a lubricating belt. According to the disturbed contour belt 7, a steel shield ring 8 assembled on site is made, assembled and positioned in the working well 1, and the steel shield ring 8 is dragged in the working well 2 at the other end by a steel wire rope 10. As the dragging process continues to splice, it is finally anchored and connected to the side wall of the working well 2 to form an advanced pre-support system, and finally the excavation, initial support and secondary lining construction of the soil in the tunnel are carried out. This method ensures that there is no collapse or leakage during tunnel excavation through the closed steel shield ring 8 and the tensioning wire saw 6, and has the advantages of high efficiency, economy and safety. The application of the closed steel shield ring 8 improves the reliability of pre-reinforcement and the accuracy of positioning, reduces the disturbance to the surrounding environment, and reduces the risk of stratum subsidence. In addition, due to the use of bentonite mud lubrication belt, large-scale grouting reinforcement measures are not required, so it is more environmentally friendly. The steel shield ring 8 can be pulled out and reused after the construction is completed, further improving resource utilization and economic benefits. This method has a short construction period and can quickly complete the dragging and positioning of the pre-cut groove 4 and the steel shield ring 8, significantly shortening the project period and reducing the project cost. It is suitable for various underground engineering and tunnel engineering fields.

[0082] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit them. Under the concept of the present invention, the technical features in the above embodiments or different embodiments may also be combined, the steps may be implemented in any order, and there are many other changes in different aspects of the present invention as described above, which are not provided in detail for the sake of simplicity. Although the present invention has been described in detail with reference to the above embodiments, a person of ordinary skill in the art should understand that the technical solutions described in the above embodiments may still be modified, or some of the technical features may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A prefabricated pre-formed ring support shallow buried dark excavation method, characterized in that: The following steps are involved: S1, constructing working wells at both ends of the tunnel, namely, the first working well (1) and the second working well (2); S2, a groove (4) is provided on the tunnel side wall (3) in the working shaft at both ends, and the outline of the groove (4) is extended by a certain distance according to the tunnel excavation outline range; S3, applying a water stop ring plate (5) on the outside of the contour range of the cutting groove (4); S4, drilling a hole horizontally at the position of the cut groove (4) of the tunnel side wall (3) through the first working well (1) at one end to the second working well (2) at the other end, and inserting a rope saw (6); S5, tensioning the rope saw (6) so that the rope saw (6) is in a stretched state; S6, the rope saw (6) is repeatedly moved in a stretched state, and the soil outside the tunnel excavation contour is disturbed in sections along the contour of the pre-set grooves (4) on the tunnel side walls (3) of the first working shaft (1) and the second working shaft (2), thereby forming a disturbed contour zone (7); S7, injecting bentonite slurry into the disturbance contour zone (7) through a grouting device to form a lubricating zone; S8, a steel shield ring (8) that can be assembled on site is manufactured according to the disturbance contour band (7) of the tunnel, and a towing device (9) is reserved at one end of the steel shield ring (8); S9, assembling the steel shield ring (8) in the first working well (1) and positioning it according to the disturbance contour band (7); S10, dragging the steel shield ring (8) in the second working shaft (2) at the other end through the steel wire rope (10), and continuously splicing the steel shield ring (8) as the dragging progresses; S11, after the steel shield ring (8) reaches the second working shaft (2) at the other end, the steel shield ring (8) is anchored and connected to the side wall of the second working shaft (2) to form an advanced pre-support system; S12, excavate the soil inside the tunnel, carry out initial support and pour reinforced concrete secondary lining to complete the entire tunnel construction.

2. The advanced prefabricated preformed ring support shallow buried dark excavation method according to claim 1 is characterized in that: The excavation profile of the tunnel is elliptical, horseshoe-shaped, rectangular or circular.

3. The advanced prefabricated preformed ring support shallow buried dark excavation method according to claim 1 is characterized in that: A steel wire brush (11) is provided on the water stop ring plate (5).

4. The advanced prefabricated preformed ring support shallow buried dark excavation method according to claim 1 is characterized in that: The steel shield ring (8) is a closed steel shield ring, and the steel shield ring (8) can be pulled out and reused.

5. The advanced prefabricated preformed ring support shallow buried dark excavation method according to claim 1 is characterized in that: The steel shield ring (8) can be welded into a ring in the working pit and then dragged into the soil along the disturbance contour belt (7), or it can be divided into blocks with reserved joints connected to each other, and each block can be directly dragged into the soil along the disturbance contour belt (7).

6. The advanced prefabricated preformed ring support shallow buried dark excavation method according to claim 5 is characterized in that: The steel shield ring (8) has twelve pulling points evenly distributed on the ring for the steel wire rope (10) to act on to pull the steel shield ring (8).

7. The advanced prefabricated preformed ring support shallow buried dark excavation method according to claim 5 is characterized in that: The steel shield ring (8) is divided into blocks according to the size and shape of the tunnel excavation profile, and the entire ring can be divided into 4 or 6 blocks.

8. The advanced prefabricated preformed ring support shallow buried dark excavation method according to claim 7 is characterized in that: The blocks of the steel shield ring (8) are connected via bent joints (12), and a grouting pipe (13) is arranged at the contact point of the two bent joints to ensure the sealing and connection stability between the blocks through grouting.

9. The advanced prefabricated preformed ring support shallow buried dark excavation method according to claim 1 is characterized in that: The thickness of the steel shield ring (8) is determined according to engineering geology, hydrogeology, surrounding environment, soil cover depth and excavation width.

10. The advanced prefabricated preformed ring support shallow buried dark excavation method according to claim 1 is characterized in that: The disturbed contour zone (7) of the tunnel is formed by segmented disturbance by the wire saw (6).

Citation Information

Patent Citations

  • Method for excavating connectional passage portal in hard rock stratum

    CN109854263A

  • Construction method of external tunnel portal later poured ring beam

    CN110952995A

  • Advanced support structure for shallow buried and dark excavated tunnel in water-rich miscellaneous fill area and construction method

    CN111502674A

  • Shield interval contact channel hard rock rope saw construction method

    CN115726791A

  • Tunnel rope saw tunneling method

    CN116291526A