Construction method for hoisting air pipe in vertical shaft
By setting up a light lifting structure and lifting device in the shaft, lifting air ducts one by one solves the installation difficulties when the construction of the two walls on the shaft is completed, and the efficient and firm installation of air ducts is achieved, which is suitable for renovation projects.
Patent Information
- Application Number
- CN202410936547.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-12
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-07-12
AI Technical Summary
When installing air ducts in the shaft, the construction of both sides or even three sides of the shaft has been completed, making it extremely difficult to install air ducts, and the existing technology is difficult to effectively solve this problem.
By removing at least one wall in the shaft, a light lifting structure and lifting device are provided, and the air duct is lifted into position one by one by one using the reverse chain and the lifting ring. The lifting device is adjusted in combination with the rotating parts and the air duct flange fixing assembly to adapt to different Specification air duct.
It realizes efficient and firm installation of air ducts, avoids repeated removal of four walls, and is especially suitable for renovation projects, simplifying the installation process of air ducts in the vertical shaft.
Smart Images

Figure CN118935088A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of air duct hoisting, and in particular to a construction method for hoisting an air duct in a vertical shaft. Background Art
[0002] As building functions become more diverse and renovation projects increase, mechanical and electrical shafts become more important, and the installation of pipelines involved becomes more and more difficult. When constructing wind system shafts, the ground is usually a large reserved hole, and whether it is a new construction project or a renovation project, the bottom plate and top plate of the shaft are usually completed before the installation of the air duct. As the size of the air duct becomes larger and larger, it becomes more and more difficult to install the air duct in each floor of the shaft. In some projects, it is extremely difficult to install the air duct in the shaft because two or even three walls of the shaft have been completed.
[0003] The applicant's prior application CN114893623A discloses a duct installation structure in a narrow shaft and a construction method thereof. The duct installation structure in a narrow shaft comprises four vertical support rails, which are arranged in a vertical direction and fixedly installed on the shaft wall outside the four corners of the duct respectively. The plane projection points of the four vertical support rails are located at the four corner points of the same rectangle, and the central axis of the rectangle coincides with the central axis of the duct. Two vertical support rails arranged opposite to each other in the depth direction of the shaft are provided with a vertically extending slide groove on one side close to each other, and a cross brace screw is slidably installed in the slide groove. The rod is arranged horizontally, and the diameter of its rod body is smaller than the opening width of the slide slot, and the diameters of its screw head and fastening nut are larger than the opening width of the slide slot, and one end of the rod body with the screw head is slidably embedded in a supporting vertical rail arranged on the well wall on the side of the vertical shaft away from the construction opening, and the other end of the rod body with the fastening nut is slidably embedded in a supporting vertical rail arranged on the well wall on the side of the vertical shaft with the construction opening, and part of the cross-bracing screw is supported on the bottom end surface of the duct flange, and the fastening nut is sleeved on the rod body extending from the cross-bracing screw to the inside of the supporting vertical rail, and an operating port for construction personnel to screw the fastening nut is provided on the supporting vertical rail close to the fastening nut. Summary of the invention
[0004] The purpose of the present invention is to provide a method for hoisting and installing an air duct in a vertical shaft to solve the problems raised in the above-mentioned background technology.
[0005] To achieve the above object, the present invention provides a method for hoisting and installing an air duct in a vertical shaft, comprising: S1. Preparation for construction, and ensuring that at least one wall of the shaft is in an unconstructed or demolished state; S2. Add a lifting structure at the top of the ventilation shaft; S3. Reserve holes on the ground of each vertical shaft to build a construction platform; S4, assemble the lifting device; S5. Assemble the air duct with the lifting device, and use the lifting device to lift multiple sections of air duct into place: Assemble the first section of air duct with the lifting device, and lift the first section of air duct to a height higher than the second section of air duct and lower than the bottom of the reserved hole in the top plate of the bottom layer of the shaft, then stop lifting, firmly connect the second section of air duct with the first section of air duct through flanges, and then lift the whole for a second time, and lift the third to the last section of air duct into place in sequence until the entire section of air duct is lifted.
[0006] In a preferred embodiment, in step S2, a lifting structure is added to the top of the ventilation shaft, including: placing a fall chain tripod centered on the ground at the highest point of the shaft, fixing the fixed steel plate at the bottom of the fall chain tripod to the ground with expansion bolts, and installing the fall chain on the tripod cross arm, wherein columns are fixedly provided below both ends of the tripod cross arm, the inner distance between the two columns is greater than the length of the long side of the shaft, a plurality of groups of diagonal braces are symmetrically provided on both sides of the columns, and fixed steel plates are provided at the bottom of the columns and the diagonal braces.
[0007] In a preferred embodiment, the lifting device comprises: A lifting steel plate, a lifting ring is welded on the top of the lifting steel plate, and four sets of hinges are welded on the outside of the lifting steel plate in a circular array, the hinge includes a first hinge blade and a second hinge blade, and the first hinge blade is fixed to the outside of the lifting steel plate, the first hinge blade is rotatably connected with the second hinge blade through a hinge shaft, and two sets of first connection holes are opened in the second hinge blade in a through-type manner; A cross brace structure, which is arranged outside the lifting steel plate, and four cross braces are arranged in a circular array; The rotating component is arranged on the outside of the cross-bracing structure, and a duct flange fixing component is arranged on the inside of the rotating component. The rotating component and the duct flange fixing component are arranged symmetrically, and two rotating components and two duct flange fixing components are arranged on the outside of each cross-bracing structure.
[0008] In a preferred embodiment, the cross-bracing structure includes: a channel steel, a fixed steel plate, a second connecting hole, a round steel and a locking nut. The channel steel is movably arranged on the outside of the lifting steel plate, and the fixed steel plate is welded to the outside of both ends of the channel steel. A first bolt is movably arranged inside the first connecting hole, and a first nut is threadedly arranged on the outside of the first bolt. The second connecting hole is through-opened inside the fixed steel plate, and a first bolt is movably arranged inside the second connecting hole, and the inner side of the fixed steel plate is fitted with the outer side of the first nut. A circular hole is opened inside one end of the channel steel, and two groups of circular holes are symmetrically opened. The round steel is movably arranged inside the circular hole, and both ends of the round steel are arranged as threaded structures. The locking nuts are threadedly connected to the outside of both ends of the round steel.
[0009] In a preferred embodiment, the rotating component includes: a first rectangular steel plate, a second rectangular steel plate and an arc-shaped steel plate, the first rectangular steel plate is movably arranged on both sides of the end of the channel steel, and the outer side of the first rectangular steel plate is in contact with the outer side of the locking nut, the second rectangular steel plate is welded to the end of the first rectangular steel plate, and the second rectangular steel plate is vertically arranged to the first rectangular steel plate, the arc-shaped steel plate is symmetrically fixed between the second rectangular steel plate and the first rectangular steel plate, a first bolt hole is through-opened in the first rectangular steel plate, a round steel is movably arranged in the first bolt hole, a second bolt hole is through-opened in the arc-shaped steel plate, and a third bolt hole is through-opened in the second rectangular steel plate.
[0010] In a preferred embodiment, the duct flange fixing assembly includes: an angle steel, a bolt groove and a fourth bolt hole, the angle steel is movably arranged on the inner side of the two groups of arc-shaped steel plates, and a rounded corner is opened at one end of the angle steel, the bolt groove is opened in a through-type at the bottom of the angle steel, the fourth bolt hole is opened in a through-type inside the side of the angle steel, a second bolt is movably arranged between the bolt groove and the second bolt hole, the second nut is arranged on the outside of the second bolt through a threaded connection, and the top of the second nut is fitted with the bottom of the arc-shaped steel plate, a third bolt is movably arranged between the fourth bolt hole and the third bolt hole, the third nut is arranged on the outside of the third bolt through a threaded connection, and the outside of the third nut is fitted with the inner side of the angle steel.
[0011] In a preferred embodiment, in step S3, a construction platform is set up in the reserved holes on the ground of each layer of the shaft, including: using construction platform channel steels in combination with steel perforated plates to set up the construction platform in the reserved holes on the ground of each layer of the shaft, all construction platform channel steels are arranged parallel to the short sides of the shaft, and are connected to the ground or walls around the ventilation shaft by welding or bolts. When the construction platform is set up, the construction platform channel steels are first fixed firmly, and then the steel perforated plates are firmly laid on the construction platform channel steels and fixed by steel wires.
[0012] In a preferred embodiment, in step S5, the first section of the air duct is assembled with the lifting device, and the first section of the air duct is lifted to a height higher than the second section of the air duct and lower than the bottom of the reserved hole on the top plate of the bottom layer of the shaft, including: making the angle steel and the channel steel in a horizontally open state, and firmly connecting the angle steel with the flange bolt hole corresponding to the air duct to be lifted by bolts through the bolt groove, after the lifting device is firmly connected to the first section of the air duct, firmly fixing the fall chain with the lifting belt and the lifting ring, and then starting the lifting structure, lifting the first section of the air duct to a height higher than the second section of the air duct and lower than the bottom of the reserved hole on the top plate of the bottom layer of the shaft, stopping the lifting, disassembling the lifting device from the flange of the first section of the air duct, and firmly installing and fixing the two sections of the air duct before the next lifting.
[0013] In a preferred embodiment, when the long side and wide side of the duct flange are smaller than the length or width when the lifting device is fully open, the four groups of channel steels are retracted inward through the hinges to reduce the outer diameter of the lifting device, and at the same time, the duct flange fixing assembly that matches the duct specifications is replaced, and the angle between the channel steel and the rotating component is adjusted using round steel and locking nuts so that the angle steel and the duct flange remain horizontal.
[0014] In a preferred embodiment, a large rope is used to wrap around and knot the middle of the first section of the air duct, and after confirming that the fall chain is wrapped and fastened around the inner center part of the first section of the air duct lifting device, the fall chain is pulled to lift the first section of the air duct, and the large rope is tightened during the lifting process.
[0015] Compared with the prior art, the beneficial effect of the present invention is that in some projects, since two or even three walls of the shaft have been completed, it is extremely difficult to install the air duct in the shaft. The present invention does not need to demolish the four walls on each floor, especially for the renovation project, only one wall can be demolished, and a hoisting point is set at the highest point of the shaft. By installing a light lifting structure (such as a fall chain, a small electric hoist, etc.), in conjunction with the hoisting device of the present invention, the installation of the air duct in the shaft can be completed, thereby solving the problem that it is extremely difficult to install the air duct in the shaft when two or even three walls of the shaft have been completed. During the hoisting, the air duct is first fixed to the hoisting device, and the first section of the air duct is lifted from the bottom of the shaft to a certain position below the reserved hole of the top plate at the bottom of the shaft by using the fall chain. The second section of the air duct is firmly connected to the means air duct by bolts, and then lifted to the lower opening of the reserved hole on the top plate to connect the third section of the air duct. This is repeated until the entire air duct is lifted, and the air duct can be firmly and efficiently installed. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 is a flow chart of the method of the present invention; Figure 2 It is a schematic diagram of the overall structure of the lifting device of the present invention; Figure 3 It is a schematic diagram of the split structure of the cross bracing structure of the present invention; Figure 4 It is a schematic diagram of the connection structure of the cross bracing structure, the rotating component and the air duct flange fixing assembly of the present invention; Figure 5 It is a schematic diagram of the disassembled structure of the air duct flange fixing assembly of the present invention; Figure 6 It is a schematic diagram of the folded structure of the air duct flange fixing assembly of the present invention; Figure 7 is a schematic diagram of the folded structure of the cross bracing structure of the present invention; Figure 8 It is a schematic diagram of the lifting structure of the present invention; Fig. 9It is a schematic diagram of the structure of the chain-falling tripod of the present invention; Fig.10 yes Fig. 9 Left view of; Fig.11 It is a schematic diagram of the installation of a single-row air duct construction platform in a vertical shaft of the present invention; Fig.12 It is a schematic diagram of the installation of a multi-row air duct construction platform in a vertical shaft of the present invention; Fig.13 It is a schematic diagram of the hoisting of the first section of the air duct and the second section of the air duct of the present invention. DETAILED DESCRIPTION
[0017] The technical solutions in the embodiments of the present invention are described clearly and completely below. The embodiments of the present invention and all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present invention.
[0018] like Figure 1-Figure 13 As shown, the method for hoisting and installing the air duct in the shaft of the present invention comprises the following steps: Step S1, preparation for construction, and making at least one wall of the shaft unconstructed or demolished; Step S2, adding a lifting point at the top of the ventilation shaft and installing a lifting structure; Step S3, setting up a construction platform in the reserved holes on the ground of each vertical shaft; Step S4, assembling the lifting device; Step S5, assembling the air duct with the hoisting device, and using the hoisting device to hoist multiple sections of the air duct into place: assemble the first section of the air duct with the hoisting device, and lift the first section of the air duct to a height higher than the second section of the air duct and lower than the bottom of the reserved hole on the top plate of the bottom layer of the shaft, then stop lifting, firmly connect the second section of the air duct with the first section of the air duct through the flange, and then lift the whole for a second time, and complete the hoisting of the third to the last section of the air duct in place in sequence until the hoisting of the entire section of the air duct is completed.
[0019] Specifically, in step S2, a lifting point is added to the top of the ventilation shaft and a lifting structure is installed, including: placing the chain tripod 10 in the center at the highest point of the shaft, fixing the fixed steel plate 111 at the bottom of the chain tripod to the ground with expansion bolts (detachable connection), and installing the chain 116 on the tripod cross arm 113, wherein columns 114 are fixedly arranged below both ends of the tripod cross arm 113, the inner distance between the two columns 114 is greater than the length of the long side of the shaft, multiple groups of diagonal braces 115 are symmetrically arranged on both sides of the columns 114, and the bottoms of the columns 114 and the diagonal braces 115 are both provided with fixed steel plates 111. In addition, if the shaft is too high, a transfer lifting point can be set, and the chain tripod can be set to be movable.
[0020] Specifically, the hoisting device includes: a hoisting steel plate 1, a cross bracing structure 2, a rotating component 3 and a duct flange fixing assembly 4. A hoisting ring 101 is welded on the top of the hoisting steel plate 1, and four sets of hinges 102 are welded in a circular array on the outside of the hoisting steel plate 1. The hinge 102 includes a first hinge blade and a second hinge blade, and the first hinge blade is fixed to the outside of the hoisting steel plate 1. The first hinge blade and the second hinge blade are rotatably connected through a hinge shaft, and two sets of first connecting holes 103 are opened in the second hinge blade in a through-type. The cross bracing structure 2 is arranged on the outside of the hoisting steel plate 1, and four cross bracing structures 2 are arranged in a circular array. The rotating component 3 is arranged on the outside of the cross bracing structure 2, and the duct flange fixing assembly 4 is arranged on the inside of the rotating component 3. The rotating component 3 and the duct flange fixing assembly 4 are arranged symmetrically, and two rotating components 3 and two duct flange fixing assemblies 4 are arranged on the outside of each cross bracing structure 2. The hoisting device of the present invention can retract four groups of channel steels 201 inward through the hinges 102 to appropriately reduce the outer diameter of the device. At the same time, the duct flange fixing assembly 4 that matches the duct specifications is replaced, and the angle between the channel steel 201 and the rotating component 3 is adjusted, so that the device can hoist ducts with smaller specifications.
[0021] Further, the cross bracing structure 2 includes: a channel steel 201, a fixed steel plate 202, a second connection hole 203, a round steel 205 and a locking nut 206. The channel steel 201 is movably arranged outside the hoisting steel plate 1, and the fixed steel plate 202 is welded to the outside of both ends of the channel steel 201. A first bolt 104 is movably arranged inside the first connection hole 103, and a first nut 105 is arranged on the outside of the first bolt 104 through a threaded connection. The second connection hole 203 is opened in the fixed steel plate 202 in a through-type manner, and a first bolt 104 is movably arranged inside the second connection hole 203, and the inner side of the fixed steel plate 202 is fitted with the outer side of the first nut 105. A circular hole 204 is opened inside one end of the channel steel 201, and the circular hole 204 is opened in two groups in a symmetrical manner. The round steel 205 is movably arranged inside the circular hole 204, and both ends of the round steel 205 are arranged as a threaded structure, and the locking nut 206 is arranged on the outside of both ends of the round steel 205 through a threaded connection. The angle between the channel steel 201 and the rotating component 3 is adjusted by using the round steel 205 and the locking nut 206 so that the angle steel 401 and the air duct flange remain in a horizontal state.
[0022] The rotating component 3 includes: a first rectangular steel plate 301, a second rectangular steel plate 302 and an arc-shaped steel plate 303. The first rectangular steel plate 301 is movably arranged on both sides of the end of the channel steel 201, and the outer side of the first rectangular steel plate 301 is in contact with the outer side of the locking nut 206. The second rectangular steel plate 302 is welded to the end of the first rectangular steel plate 301, and the second rectangular steel plate 302 is vertically arranged with the first rectangular steel plate 301. The arc-shaped steel plate 303 is symmetrically fixedly arranged between the second rectangular steel plate 302 and the first rectangular steel plate 301. The first rectangular steel plate 301 has a first bolt hole 304 through-opened inside, and the round steel 205 is movably arranged inside the first bolt hole 304. The arc-shaped steel plate 303 has a second bolt hole 305 through-opened inside, and the second rectangular steel plate 302 has a third bolt hole 306 through-opened inside.
[0023] The duct flange fixing assembly 4 includes: an angle steel 401, a bolt slot 402 and a fourth bolt hole 403. The angle steel 401 is movably arranged inside the two groups of arc-shaped steel plates 303, and one end of the angle steel 401 is provided with a rounded corner. The bolt slot 402 is provided through the bottom of the angle steel 401, and the fourth bolt hole 403 is provided through the inside of the side of the angle steel 401. A second bolt 404 is movably arranged between the bolt slot 402 and the second bolt hole 305, a second nut 405 is provided on the outside of the second bolt 404 through a threaded connection, and the top of the second nut 405 is fitted with the bottom of the arc-shaped steel plate 303, a third bolt 406 is movably arranged between the fourth bolt hole 403 and the third bolt hole 306, a third nut 407 is provided on the outside of the third bolt 406 through a threaded connection, and the outside of the third nut 407 is fitted with the inside of the angle steel 401. By setting the third bolt 406 and the third nut 407 and the fourth bolt hole 403 and the third bolt hole 306, the side of the angle steel 401 can be fixed to the second rectangular steel plate 302. At the same time, the second bolt 404 and the second nut 405 and the bolt groove 402 and the second bolt hole 305 can be used to fix the bottom edge of the angle steel 401 and the arc steel plate 303, so that the angle steel 401 can be quickly disassembled and installed.
[0024] In step S3, a construction platform is set up in the reserved holes on the ground of each layer of the shaft, including: using construction platform channel steel 512 combined with steel hole plate 511 to set up a construction platform in the reserved holes 501 on the ground of each layer of the shaft, all construction platform channel steels 512 are arranged parallel to the short sides of the shaft, and are connected to the ground or wall around the ventilation shaft by welding or bolts. When setting up the construction platform, first fix the construction platform channel steel 512 firmly, then lay the steel hole plate 511 firmly on the construction platform channel steel 512, and fix it with steel wire.
[0025] In step S5, the first section of the air duct is assembled with the lifting device, and the first section of the air duct is lifted to a height higher than the second section of the air duct and lower than the bottom of the reserved hole on the top plate of the bottom layer of the shaft, including: making the angle steel 401 and the channel steel 201 in a horizontally open state, and firmly connecting the angle steel 401 with the flange bolt hole corresponding to the air duct to be lifted by bolts through the bolt groove 402, and after the lifting device is firmly connected to the first section of the air duct 601, the fall chain 116 is firmly fixed by the lifting belt and the lifting ring 101, and then the lifting structure is started, and the first section of the air duct 601 is lifted to a height higher than the second section of the air duct 602 and lower than the bottom of the reserved hole 603 on the top plate of the bottom layer of the shaft, and then the lifting is stopped, the lifting device is disassembled from the flange 604 of the first section of the air duct, and the two sections of the air duct are firmly installed and fixed, and then the next lifting is carried out.
[0026] When the long side and wide side of the duct flange are smaller than the length or width when the lifting device is fully opened, the four sets of channel steels 201 are retracted inwardly through the hinges 102 to reduce the outer diameter of the lifting device. At the same time, the duct flange fixing assembly 4 that matches the duct specifications is replaced, and the round steel 205 and the locking nut 206 are used to adjust the angle between the channel steel 201 and the rotating component 3 so that the angle steel 401 and the duct flange remain horizontal.
[0027] In addition, if the height of the shaft is high, a large rope can be used to wrap around and knot the middle of the first section of the air duct to secure it. After confirming that the fall chain is wrapped and fastened around the center part of the flange hanger of the first section of the hoisted air duct, start pulling the fall chain to lift the air duct and tighten the large rope during the lifting process to ensure overall stability during the air duct hoisting process.
[0028] If it involves the use of a construction platform to complete the installation of multiple rows of air ducts, such as Fig.12 As shown, the operator first uses the platform to complete the hoisting of the innermost air duct 513 on the wall side, then removes the construction platform channel steel 512 adjacent to the installed air duct, and moves the steel perforated plate 511 backward to hoist the second row of air ducts, and repeats the above operations in sequence until all air ducts are hoisted.
[0029] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A method for hoisting and installing an air duct in a vertical shaft, characterized in that: The steps include: S1. Preparation for construction, and ensuring that at least one wall of the shaft is in an unconstructed or demolished state; S2. Add a lifting structure at the top of the ventilation shaft; S3. Reserve holes on the ground of each vertical shaft to build a construction platform; S4, assemble the lifting device; S5. Assemble the air duct with the hoisting device, and use the hoisting device to hoist multiple sections of the air duct into place: assemble the first section of the air duct with the hoisting device, and lift the first section of the air duct to a height higher than the second section of the air duct and lower than the bottom of the reserved hole in the top plate of the bottom layer of the shaft, then stop lifting, firmly connect the second section of the air duct with the first section of the air duct through the flange, and then lift the whole for a second time, and complete the hoisting of the third to the last section of the air duct in place in sequence until the hoisting of the entire section of the air duct is completed.
2. The method for hoisting and installing the air duct in the shaft according to claim 1 is characterized in that: In step S2, a lifting structure is added to the top of the ventilation shaft, including: placing a fall chain tripod (10) in the center at the highest point of the shaft, fixing a fixed steel plate (111) at the bottom of the fall chain tripod to the ground with expansion bolts, and installing a fall chain (116) on a tripod cross arm (113), wherein columns (114) are fixedly arranged below both ends of the tripod cross arm (113), the inner distance between the two columns (114) is greater than the length of the long side of the shaft, a plurality of groups of diagonal braces (115) are symmetrically arranged on both sides of the columns (114), and fixed steel plates (111) are arranged at the bottom of the columns (114) and the diagonal braces (115).
3. The method for hoisting and installing the air duct in the shaft according to claim 1 is characterized in that: The lifting device comprises: A lifting steel plate (1), wherein a lifting ring (101) is welded to the top of the lifting steel plate (1), and four sets of hinges (102) are welded to the outside of the lifting steel plate (1) in a ring array, the hinges (102) include a first hinge blade and a second hinge blade, and the first hinge blade is fixed to the outside of the lifting steel plate (1), the first hinge blade is rotatably connected to the second hinge blade via a hinge shaft, and the second hinge blade is provided with two sets of first connection holes (103) in a through-type manner; A cross bracing structure (2), wherein the cross bracing structure (2) is arranged outside the hoisting steel plate (1), and four cross bracing structures (2) are arranged in a ring array; A rotating component (3), the rotating component (3) being arranged on the outside of the cross bracing structure (2), and an air duct flange fixing assembly (4) being arranged on the inside of the rotating component (3), the rotating component (3) and the air duct flange fixing assembly (4) being arranged symmetrically, and two rotating components (3) and two air duct flange fixing assemblies (4) being arranged on the outside of each cross bracing structure (2).
4. The method for hoisting and installing the air duct in the vertical shaft according to claim 3 is characterized in that: The cross bracing structure (2) comprises: a channel steel (201), a fixing steel plate (202), a second connection hole (203), a round steel (205) and a locking nut (206); the channel steel (201) is movably arranged on the outside of the lifting steel plate (1); the fixing steel plate (202) is welded to the outside of both ends of the channel steel (201); a first bolt (104) is movably arranged inside the first connection hole (103); a first nut (105) is arranged on the outside of the first bolt (104) through a threaded connection; the second connection hole (203) is a through-opening The first bolt (104) is movably arranged inside the fixed steel plate (202), and the inside of the second connection hole (203) is fitted with the outside of the first nut (105). A circular hole (204) is opened inside one end of the channel steel (201), and the circular holes (204) are opened in two groups in a symmetrical manner. The round steel (205) is movably arranged inside the circular hole (204), and the two ends of the round steel (205) are arranged as threaded structures. The locking nuts (206) are arranged on the outside of the two ends of the round steel (205) through threaded connection.
5. The method for hoisting and installing the air duct in the vertical shaft according to claim 4 is characterized in that: The rotating component (3) comprises: a first rectangular steel plate (301), a second rectangular steel plate (302) and an arc-shaped steel plate (303); the first rectangular steel plate (301) is movably arranged on both sides of the end of the channel steel (201), and the outer side of the first rectangular steel plate (301) is in contact with the outer side of the locking nut (206); the second rectangular steel plate (302) is welded to the end of the first rectangular steel plate (301), and the second rectangular steel plate (302) is arranged vertically to the first rectangular steel plate (301). The arc-shaped steel plate (303) is symmetrically fixedly arranged between the second rectangular steel plate (302) and the first rectangular steel plate (301); a first bolt hole (304) is provided in the first rectangular steel plate (301) in a through-type manner; a round steel (205) is movably arranged in the first bolt hole (304); a second bolt hole (305) is provided in the arc-shaped steel plate (303) in a through-type manner; and a third bolt hole (306) is provided in the second rectangular steel plate (302) in a through-type manner.
6. The method for hoisting and installing the wind pipe in the vertical shaft according to claim 5 is characterized in that: The duct flange fixing assembly (4) comprises: an angle steel (401), a bolt slot (402) and a fourth bolt hole (403); the angle steel (401) is movably arranged inside the two sets of arc-shaped steel plates (303); one end of the angle steel (401) is provided with a rounded corner; the bolt slot (402) is provided through the bottom of the angle steel (401); the fourth bolt hole (403) is provided through the inside of the side of the angle steel (401); and a space between the bolt slot (402) and the second bolt hole (305) is provided. A second bolt (404) is movably arranged, a second nut (405) is arranged on the outside of the second bolt (404) by threaded connection, and the top of the second nut (405) is fitted with the bottom of the arc-shaped steel plate (303), a third bolt (406) is movably arranged between the fourth bolt hole (403) and the third bolt hole (306), a third nut (407) is arranged on the outside of the third bolt (406) by threaded connection, and the outside of the third nut (407) is fitted with the inside of the angle steel (401).
7. The method for hoisting and installing the air duct in a vertical shaft according to claim 1, characterized in that: In step S3, a construction platform is set up in the reserved holes on the ground of each layer of the shaft, including: using construction platform channel steel (512) and steel hole plate (511) to set up the construction platform in the reserved holes (501) on the ground of each layer of the shaft, all construction platform channel steels (512) are arranged in parallel with the short sides of the shaft, and are connected to the ground or wall around the ventilation shaft by welding or bolting. When setting up the construction platform, the construction platform channel steel (512) is first fixed firmly, and then the steel hole plate (511) is firmly laid on the construction platform channel steel (512) and fixed by steel wire.
8. The method for hoisting and installing the air duct in a vertical shaft according to claim 6, characterized in that: In step S5, the first section of the air duct is assembled with the lifting device, and the first section of the air duct is lifted to a height higher than the second section of the air duct and lower than the bottom of the reserved hole on the top plate of the bottom layer of the shaft, including: the angle steel (401) and the channel steel (201) are in a horizontally open state, the angle steel (401) is firmly connected to the flange bolt hole corresponding to the air duct to be lifted by bolts through the bolt groove (402), after the lifting device is firmly connected to the first section of the air duct, the fall chain is firmly fixed by the lifting belt and the lifting ring (101), and then the lifting structure is started to lift the first section of the air duct to a height higher than the second section of the air duct and lower than the bottom of the reserved hole on the top plate of the bottom layer of the shaft, and then the lifting is stopped, the lifting device is disassembled from the flange of the first section of the air duct, and the two sections of the air duct are firmly installed and fixed, and then the next lifting is performed.
9. The method for hoisting and installing the air duct in the vertical shaft according to claim 8, characterized in that: When the long side or wide side of the duct flange is smaller than the length or width of the suspending device in the fully opened state, the four sets of channel steels (201) are retracted inwardly by the hinges (102) to reduce the outer diameter of the suspending device, and the duct flange fixing assembly (4) matching the duct specifications is replaced. The angle between the channel steel (201) and the rotating component (3) is adjusted by using the round steel (205) and the locking nut (206) so that the angle steel (401) and the duct flange remain in a horizontal state.
10. The method for hoisting and installing the air duct in a vertical shaft according to claim 8, characterized in that: Use a large rope to wrap around the middle of the first section of air duct and tie a knot to secure it. After confirming that the fall chain is wrapped tightly around the center part of the first section of air duct lifting device, start pulling the fall chain to lift the first section of air duct and tighten the large rope during the lifting process.
Citation Information
Patent Citations
Pipeline cradle
CA2892644A1
Adjustable clamp for hoisting in air hoses
CN104649121A
Inverted installation method for large-height-difference stainless steel oil smoke exhaust air pipe
CN116221497A
Platform facilitating transportation and conveying of construction materials
CN116461579A
PWR is deep winding device for nuclear power station
CN204823653U