Emergency material allocation method and system for distributed building construction sites

By determining the type of material shortage projects and required materials based on road network and meteorological information during meteorological disasters, giving priority to allocating materials from unaffected areas, the problem of material shortage at decentralized construction sites has been solved, and the reasonable allocation of materials and construction has been achieved. Cost control.

CN118941040APending Publication Date: 2024-11-12CSCEC DIGITAL TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411035669.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-31
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

During meteorological disasters, the shortage of materials at the construction sites of decentralized buildings has led to increased construction costs and extended construction cycles, and it is difficult to dispatch materials at different construction sites of the same construction group.

Method used

By determining the type of projects in the construction area where a meteorological disaster occurs, the construction stage and the quantity of materials required, based on road network information and meteorological forecast information, the corresponding materials will be allocated from other construction areas that have not been affected, and the priority and distance will be used for the shortest Make allocations in principle, calculate the quantity of allocated materials and determine the distribution plan.

Benefits of technology

During meteorological disasters, the material allocation cycle will be shortened, the construction speed will be improved, and the project construction cost will be controlled.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118941040A_ABST
    Figure CN118941040A_ABST
Patent Text Reader

Abstract

The invention discloses an emergency material allocation method and system for distributed building construction sites, and the method comprises the steps: determining a first construction region where a meteorological disaster occurs, obtaining the number of building construction projects in the first construction region and the geographic positions of the building construction projects, determining the number of building construction projects with material shortage, and determining the number of the building construction projects with material shortage; recording the number as a first number; determining the project type, the project construction stage, the required material name and the required material quantity of the building construction project with the material shortage; based on the road network information, the weather forecast information and the first construction area, a plurality of second construction areas where meteorological disasters do not occur are determined, supply construction projects are determined from all the second construction areas, and the supply construction projects are construction projects capable of providing needed materials for building construction projects with material shortage. According to the method, materials can be reasonably distributed when the meteorological disaster occurs, and the project construction cost can be controlled when the meteorological disaster occurs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building construction, and in particular to an emergency material allocation method and system at a decentralized building construction site. Background Art

[0002] For large construction units, there are construction projects in many countries and regions around the world, and there are many types of construction projects, such as building construction, infrastructure, etc.

[0003] When conducting construction management, the materials needed for construction need to be adequately guaranteed, but meteorological disasters occur from time to time, which may cause a shortage of materials at a construction site. Transporting materials from manufacturers will increase the cost of project construction and extend the construction period. The same construction group has multiple construction sites, and the same materials or similar substitutes may exist. Dispatching materials nearby is beneficial to reducing costs and improving construction progress.

[0004] Therefore, how to dispatch materials at different construction sites of the same construction group, that is, decentralized construction sites, is a technical problem that needs to be solved urgently. Summary of the invention

[0005] In view of this, the present invention provides an emergency material allocation method and system for decentralized construction sites, which can solve the existing technical problem of how to dispatch materials at different construction sites of the same construction group, namely decentralized construction sites.

[0006] In order to solve the above technical problems, the present invention is implemented as follows.

[0007] A method for allocating emergency materials at a decentralized construction site, the method comprising the following steps:

[0008] Step S1: determine the first construction area where the meteorological disaster occurs, obtain the number of construction projects and the geographical locations of the construction projects in the first construction area, and determine the number of construction projects where material shortages occur, which is recorded as the first number; determine the project type, project construction stage, required material name and required material quantity of the construction project where material shortages occur;

[0009] Step S2: Based on the road network information, weather forecast information and the first construction area, several second construction areas where no meteorological disasters have occurred are determined, and supply construction projects are determined from each second construction area, wherein the supply construction project is a construction project that can provide the required materials to the construction project that is experiencing material shortages.

[0010] Preferably, the project types include building construction projects and infrastructure projects; the construction stages of the building construction projects include pile foundation and raft foundation construction stages, main construction stages, mechanical and electrical installation stages, and decoration and renovation stages; the construction stages of the infrastructure projects include pile foundation construction stages and main construction stages.

[0011] Preferably, the step S1: determining the first construction area where the meteorological disaster occurs, obtaining the number of construction projects and the geographical locations of the construction projects in the first construction area, and determining the number of construction projects where material shortages occur, recorded as the first number; determining the project type, the project construction stage, the name of the required materials, and the required quantity of the materials of the construction projects where material shortages occur, includes:

[0012] Step S11: determining a first construction area P1 where a meteorological disaster occurs, obtaining the number of construction projects in the first construction area and the geographical locations of the construction projects, and determining the number of construction projects where material shortages occur, recorded as a first number num1;

[0013] Step S12: Determine the set of construction projects T1 where material shortages occur, T1 = {T 11 ,…,T 1i ,…,T 1num1}, T 1i For construction projects with material shortages; construct a data table for each construction project with material shortages, each data table includes the project name, project number, project priority, and project type of the construction project with material shortages 1i , the project construction stage 1i , the name of the required materials, and the quantity of each required material, 1≤i≤num1.

[0014] Preferably, the project priority is determined by determining the number of on-site construction personnel for each construction project where material shortages occur. 1i , expected loss M 1i ;

[0015] M 1i =αperson 1i +βType1 1i +γA 1i

[0016] person

[0017]

[0018] Among them, α, β, γ are all weight coefficients, and α+β+γ=1, person is the total number of construction personnel in all projects in the first construction area P1, Type1 1i For the preset project type Type1 i The importance value of S1 1i The pre-set project construction phase S 1i Importance value, day 1i The number of days for building a house in a construction project with material shortages agreed in the contract, day1 1i The number of days that construction work has been ongoing for the construction project that experienced material shortages.

[0019] Preferably, the step S2: determining a number of second construction areas where no meteorological disaster has occurred based on the road network information, the weather forecast information and the first construction area, and determining the supply construction project from each second construction area, comprises:

[0020] Step S21: determining a number of second construction areas where no meteorological disaster has occurred based on the road network information, the weather forecast information and the first construction area, wherein the second construction area is a construction area where no meteorological disaster has occurred, where the connecting route with the first construction area is not blocked due to the meteorological disaster, and where the value of the connecting route with the first construction area is less than a second preset threshold;

[0021] Step S22: Determine a supply construction project set T2 from each second construction area, T2 = {T 21 ,…,T 2j ,…,T 2num2}; j is the supply construction project number, num2 is the number of supply construction projects in the supply construction project set T2;

[0022] Determine the materials and quantities of materials that can be provided for each construction project, where the materials are required for the construction project where the materials are in short supply:

[0023] When the supply project type is building construction, if the construction stage of the supply project is the pile foundation and raft foundation construction stage, and the allocated materials existing at the construction site are greater than the demand of the supply project for the allocated materials, then the amount of allocated materials z that the supply construction project can provide is: z=1.2*(xy), where x is the amount of allocated materials existing at the construction site of the supply project, and y is the demand of the supply project for the allocated materials; if the construction stage of the supply project is the main construction stage, and the allocated materials existing at the construction site are greater than the demand of the supply project for the allocated materials, then the amount of allocated materials z that the supply construction project can provide is: z=1.1*(xy); if the construction stage of the supply project is the electromechanical installation stage, then the amount of allocated materials z that the supply construction project can provide is: z=xy;

[0024] When the supply project type is infrastructure, if the construction stage of the supply project is the pile foundation construction stage, and the allocated materials existing at the construction site are greater than the demand of the supply project for the allocated materials, then the quantity z of allocated materials that the supply construction project can provide is: z=0.9*(xy), wherein x is the quantity of allocated materials existing at the construction site of the supply project, and y is the demand of the supply project for the allocated materials; if the construction stage of the supply project is the main construction stage, then the quantity z of allocated materials that the supply construction project can provide is: z=0.8*(xy).

[0025] The present invention provides an emergency material allocation system for a decentralized construction site, the system comprising:

[0026] Demand module: configured to determine the first construction area where the meteorological disaster occurs, obtain the number of construction projects and the geographical locations of the construction projects in the first construction area, and determine the number of construction projects where material shortages occur, recorded as the first number; determine the project type, project construction stage, required material name and required material quantity of the construction project where material shortages occur;

[0027] Supply module: configured to determine several second construction areas where no meteorological disasters have occurred based on road network information, weather forecast information and the first construction area, and determine supply construction projects from each second construction area, wherein the supply construction projects are construction projects that can provide the required materials to construction projects that are experiencing material shortages.

[0028] The present invention provides a computer-readable storage medium, wherein a plurality of instructions are stored in the storage medium; the plurality of instructions are used for a processor to load and execute the method as described above.

[0029] An electronic device provided by the present invention is characterized in that the electronic device comprises:

[0030] A processor, which is used to execute multiple instructions;

[0031] A memory for storing a plurality of instructions;

[0032] The plurality of instructions are used to be stored by the memory and loaded and executed by the processor to implement the method as described above.

[0033] Beneficial effects:

[0034] (1) The present invention helps to reasonably distribute materials when meteorological disasters occur.

[0035] (2) The present invention helps to shorten the material allocation cycle and improve the construction speed when meteorological disasters occur.

[0036] (3) The present invention helps to control project construction costs when meteorological disasters occur. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] Figure 1 It is a schematic flow chart of the method for allocating emergency materials at a decentralized construction site of the present invention. DETAILED DESCRIPTION

[0038] The present invention is described in detail below in conjunction with the accompanying drawings and embodiments.

[0039] like Figure 1 As shown, the present invention proposes a method for allocating emergency materials at a decentralized construction site, comprising:

[0040] Step S1: determine the first construction area where the meteorological disaster occurs, obtain the number of construction projects and the geographical locations of the construction projects in the first construction area, and determine the number of construction projects where material shortages occur, which is recorded as the first number; determine the project type, project construction stage, required material name and required material quantity of the construction project where material shortages occur;

[0041] Step S2: Based on the road network information, weather forecast information and the first construction area, several second construction areas where no meteorological disasters have occurred are determined, and supply construction projects are determined from each second construction area, wherein the supply construction project is a construction project that can provide the required materials to the construction project that is experiencing material shortages.

[0042] Furthermore, the project types include housing projects and infrastructure projects. The housing projects include, for example, residential buildings, affordable housing, commercial office buildings, shopping malls, government office buildings, cultural facilities, educational facilities, sports facilities, entertainment facilities, welfare facilities, medical buildings, hotel resort buildings, urban complexes, industrial processing plants, industrial manufacturing plants, conference and exhibition centers, warehousing and logistics, religious buildings, and municipal supporting buildings; infrastructure projects include, for example, highways, municipal roads, railways, urban rail transit, parking lots, bridges, tunnels, and airports. The construction phases of the housing projects include the pile foundation and raft foundation construction phases, the main construction phase, the electromechanical installation phase, and the decoration and renovation phase; the construction phases of the infrastructure projects include the pile foundation construction phase and the main construction phase.

[0043] Taking roads and bridges as an example, the construction phase includes the pile foundation construction phase, the main bridge structure, the bridge deck, the roadbed, and the pavement engineering; taking tunnel engineering as an example, the construction phase includes excavation, support, secondary lining, and tunnel electromechanical.

[0044] The step S1: determining the first construction area where the meteorological disaster occurs, obtaining the number of construction projects and the geographical locations of the construction projects in the first construction area, and determining the number of construction projects where material shortages occur, recorded as the first number; determining the project type, the project construction stage, the name of the required materials, and the required quantity of the materials of the construction projects where material shortages occur, including:

[0045] Step S11: determining a first construction area P1 where a meteorological disaster occurs, obtaining the number of construction projects in the first construction area and the geographical locations of the construction projects, and determining the number of construction projects where material shortages occur, recorded as a first number num1;

[0046] Step S12: Determine the set of construction projects T1 where material shortages occur, T1 = {T 11 ,…,T 1i ,…,T 1num1}, T 1i For construction projects with material shortages; construct a data table for each construction project with material shortages, each data table includes the project name, project number, project priority, and project type of the construction project with material shortages 1i , the project construction stage 1i , the names of the materials required, and the quantity of each material required.

[0047] Furthermore, the project priority is determined by determining the number of on-site construction personnel for each construction project where material shortages occur. 1i , expected loss M 1i ;

[0048]

[0049] Among them, α, β, γ are all weight coefficients, and α+β+γ=1, person is the total number of construction personnel in all projects in the first construction area P1, Type1 1i The default project type 1i The importance value of S1 1i The pre-set project construction phase S 1i Importance value, day 1i The number of days for building a house in a construction project with material shortages agreed in the contract, day1 1i The number of days that construction work has been ongoing for the construction project that experienced material shortages.

[0050] The step S2: determining a number of second construction areas where no meteorological disaster has occurred based on the road network information, the weather forecast information and the first construction area, and determining supply construction projects from each second construction area, including:

[0051] Step S21: determining a number of second construction areas where no meteorological disaster has occurred based on the road network information, the weather forecast information and the first construction area, wherein the second construction area is a construction area where no meteorological disaster has occurred, where the connecting route with the first construction area is not blocked due to the meteorological disaster, and where the value of the connecting route with the first construction area is less than a second preset threshold;

[0052] Step S22: Determine a supply construction project set T2 from each second construction area, T2 = {T 21 ,…,T 2j ,…,T 2num2}; j is the supply construction project number, num2 is the number of supply construction projects in the supply construction project set T2;

[0053] Determine the materials and quantities of materials that can be provided for each construction project, where the materials are required for the construction project where the materials are in short supply:

[0054] When the supply project type is building construction, if the construction stage of the supply project is the pile foundation and raft foundation construction stage, and the allocated materials existing at the construction site are greater than the demand of the supply project for the allocated materials, then the amount of allocated materials z that the supply construction project can provide is: z=1.2*(xy), where x is the amount of allocated materials existing at the construction site of the supply project, and y is the demand of the supply project for the allocated materials; if the construction stage of the supply project is the main construction stage, and the allocated materials existing at the construction site are greater than the demand of the supply project for the allocated materials, then the amount of allocated materials z that the supply construction project can provide is: z=1.1*(xy); if the construction stage of the supply project is the electromechanical installation stage, then the amount of allocated materials z that the supply construction project can provide is: z=xy;

[0055] When the supply project type is infrastructure, if the construction stage of the supply project is the pile foundation construction stage, and the allocated materials existing at the construction site are greater than the demand of the supply project for the allocated materials, then the quantity z of allocated materials that the supply construction project can provide is: z=0.9*(xy), wherein x is the quantity of allocated materials existing at the construction site of the supply project, and y is the demand of the supply project for the allocated materials; if the construction stage of the supply project is the main construction stage, then the quantity z of allocated materials that the supply construction project can provide is: z=0.8*(xy).

[0056] Furthermore, the step S2 also includes obtaining the allocated materials and the quantity of allocated materials for each supply construction project, and using a path planning algorithm to determine a distribution plan for the allocated materials based on the priority of each construction project that has material shortages, the quantity of materials, the geographical location of each supply construction project, and the allocated materials and the quantity of allocated materials for each supply construction project.

[0057] In the present invention, in the first construction area where the meteorological disaster occurs, the allocation work is carried out in order from high to low according to the project priority. According to the principle of shortest distance, the closest project with the materials required by the disaster-affected project is selected from the second construction area first, and the allocation quantity is calculated in the above manner. If the allocation quantity of a single project does not meet the needs of the construction project in the first construction area where the meteorological disaster occurs, the next one is searched according to the principle of shortest distance until the materials required by the disaster-affected project are met.

[0058] The present invention provides an emergency material allocation system for a decentralized construction site, the system comprising:

[0059] Demand module: configured to determine the first construction area where the meteorological disaster occurs, obtain the number of construction projects and the geographical locations of the construction projects in the first construction area, and determine the number of construction projects where material shortages occur, recorded as the first number; determine the project type, project construction stage, required material name and required material quantity of the construction project where material shortages occur;

[0060] Supply module: configured to determine several second construction areas where no meteorological disasters have occurred based on road network information, weather forecast information and the first construction area, and determine supply construction projects from each second construction area, wherein the supply construction projects are construction projects that can provide the required materials to construction projects that are experiencing material shortages.

[0061] The present invention does not elaborate on some of the well-known technologies that belong to those skilled in the art.

[0062] The above specific embodiments only describe the design principle of the present invention. The shapes and names of the components in the description may be different and are not limited. Therefore, those skilled in the art in the field of the present invention may modify or replace the technical solutions recorded in the above embodiments; and these modifications and replacements do not deviate from the creative purpose and technical solutions of the present invention and should all fall within the protection scope of the present invention.

Claims

1. A method for allocating emergency materials at a decentralized construction site, characterized in that: The method comprises: Step S1: determine the first construction area where the meteorological disaster occurs, obtain the number of construction projects and the geographical locations of the construction projects in the first construction area, and determine the number of construction projects where material shortages occur, which is recorded as the first number; determine the project type, project construction stage, required material name and required material quantity of the construction project where material shortages occur; Step S2: Based on the road network information, weather forecast information and the first construction area, several second construction areas where no meteorological disasters have occurred are determined, and supply construction projects are determined from each second construction area, wherein the supply construction project is a construction project that can provide the required materials to the construction project that is experiencing material shortages.

2. The method according to claim 1, characterized in that The project types include building construction projects and infrastructure projects; the construction stages of the building construction projects include pile foundation and raft foundation construction stages, main construction stages, mechanical and electrical installation stages, and decoration and renovation stages; the construction stages of the infrastructure projects include pile foundation construction stages and main construction stages.

3. The method according to any one of claims 1 to 2, characterized in that: Step S1: determining a first construction area where a meteorological disaster occurs, obtaining the number of construction projects and the geographical locations of the construction projects in the first construction area, and determining the number of construction projects where material shortages occur, which is recorded as a first number; Determine the type of construction project where material shortages occur, the project construction stage, the name of the materials required, and the quantity of materials required, including: Step S11: determining a first construction area P1 where a meteorological disaster occurs, obtaining the number of construction projects in the first construction area and the geographical locations of the construction projects, and determining the number of construction projects where material shortages occur, recorded as a first number num1; Step S12: Determine the set of construction projects T1 where material shortages occur, T1 = {T 11 ,…,T 1i ,…,T 1num1 }, T 1i For construction projects with material shortages; construct a data table for each construction project with material shortages, each data table includes the project name, project number, project priority, and project type of the construction project with material shortages 1i , the project construction stage 1i , the name of the required materials, and the quantity of each required material, 1≤i≤num1.

4. The method according to claim 3, characterized in that The project priority is determined by determining the number of on-site construction personnel for each construction project where material shortages occur. 1i , expected loss M 1i ; Among them, α, β, γ are all weight coefficients, and α+β+γ=1, person is the total number of construction personnel in all projects in the first construction area P1, Type1 1i The default project type 1i The importance value of S1 1i The pre-set project construction phase S 1i Importance value, day 1i The number of days for building a house in a construction project with material shortages agreed in the contract, day1 1i The number of days that construction work has been ongoing for the construction project that experienced material shortages.

5. The method according to claim 4, characterized in that The step S2: determining a number of second construction areas where no meteorological disaster has occurred based on the road network information, the weather forecast information and the first construction area, and determining supply construction projects from each second construction area, including: Step S21: determining a number of second construction areas where no meteorological disaster has occurred based on the road network information, the weather forecast information and the first construction area, wherein the second construction area is a construction area where no meteorological disaster has occurred, where the connecting route with the first construction area is not blocked due to the meteorological disaster, and where the value of the connecting route with the first construction area is less than a second preset threshold; Step S22: Determine a supply construction project set T2 from each second construction area, T2 = {T 21 ,…,T 2j ,…,T 2num2 }; j is the supply construction project number, num2 is the number of supply construction projects in the supply construction project set T2; Determine the materials and quantities that can be provided for each supply construction project, where the materials are required for the construction project where the materials are in short supply: When the supply project type is building construction, if the construction stage of the supply project is the pile foundation and raft foundation construction stage, and the allocated materials existing at the construction site are greater than the demand of the supply project for the allocated materials, then the amount of allocated materials z that the supply construction project can provide is: z=1.2*(xy), where x is the amount of allocated materials existing at the construction site of the supply project, and y is the demand of the supply project for the allocated materials; if the construction stage of the supply project is the main construction stage, and the allocated materials existing at the construction site are greater than the demand of the supply project for the allocated materials, then the amount of allocated materials z that the supply construction project can provide is: z=1.1*(xy); if the construction stage of the supply project is the electromechanical installation stage, then the amount of allocated materials z that the supply construction project can provide is: z=xy; When the supply project type is infrastructure, if the construction stage of the supply project is the pile foundation construction stage, and the allocated materials existing at the construction site are greater than the demand of the supply project for the allocated materials, then the quantity z of allocated materials that the supply construction project can provide is: z=0.9*(xy), wherein x is the quantity of allocated materials existing at the construction site of the supply project, and y is the demand of the supply project for the allocated materials; if the construction stage of the supply project is the main construction stage, then the quantity z of allocated materials that the supply construction project can provide is: z=0.8*(xy).

6. An emergency material allocation system for decentralized construction sites, characterized in that: The system comprises: Demand module: configured to determine the first construction area where the meteorological disaster occurs, obtain the number of construction projects and the geographical locations of the construction projects in the first construction area, and determine the number of construction projects where material shortages occur, recorded as the first number; determine the project type, project construction stage, required material name and required material quantity of the construction project where material shortages occur; Supply module: configured to determine several second construction areas where no meteorological disasters have occurred based on road network information, weather forecast information and the first construction area, and determine supply construction projects from each second construction area, wherein the supply construction projects are construction projects that can provide the required materials to construction projects that are experiencing material shortages.

7. A computer-readable storage medium, wherein a plurality of instructions are stored in the storage medium; the plurality of instructions are used for a processor to load and execute the method as claimed in any one of claims 1 to 5.

8. An electronic device, characterized in that: The electronic device comprises: A processor, which is used to execute multiple instructions; A memory for storing a plurality of instructions; The plurality of instructions are used to be stored in the memory and loaded and executed by the processor according to any one of claims 1 to 5.