Hydrogen energy storage configuration method based on comprehensive auxiliary service and wind power long-time fluctuation
By establishing a mathematical model of hydrogen energy storage and a comprehensive benefit objective function, combined with particle swarm algorithm optimization, the problem that the existing hydrogen energy storage configuration method cannot adapt to wind power fluctuations is solved, the wind power consumption rate and economic benefits are improved, and more efficient is achieved the power grid operation.
Patent Information
- Application Number
- CN202410983428.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-22
- Publication Date
- 2024-11-12
AI Technical Summary
The existing hydrogen energy storage optimization configuration methods lack comprehensive auxiliary service functions and cannot effectively adapt to the long-term fluctuation characteristics of wind power, resulting in low wind power consumption and low economic benefits.
The hydrogen storage configuration method based on comprehensive auxiliary services and long-term fluctuations in wind power are adopted. By establishing a mathematical model of hydrogen storage and a comprehensive income objective function, combined with particle swarm algorithm optimization, the operating parameters of electrolytic cells, hydrogen storage tanks and fuel cells are configured. To improve wind power consumption rate and economic benefits.
It improves the wind power consumption rate, reduces the wind and light abandonment, obtains more accurate and high economic benefits, improves the economicality of power grid operation, and adapts to the large-scale access environment of renewable energy.
Smart Images

Figure CN118944142A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of regional power grid energy storage configuration, and in particular to a hydrogen energy storage configuration method based on comprehensive auxiliary services and long-term fluctuations in wind power. Background Art
[0002] With the large-scale access of renewable energy, especially wind turbines, to regional power grids, how to effectively improve the wind power absorption rate and reduce wind and solar power abandonment is the main problem facing the current power grid. Therefore, the optimal configuration of energy storage, especially hydrogen energy storage, has been widely studied and applied.
[0003] However, the auxiliary services of the current hydrogen energy storage optimization configuration method are either aimed at peak-valley arbitrage income, peak-shaving compensation income, participation in the electric energy market and frequency regulation compensation income, or including frequency regulation compensation and hydrogen sales income, or considering the penalty costs caused by insufficient flexibility, energy storage equipment investment costs, transmission line construction costs, or external power transmission income, transmission line capacity replacement income, investment and operation and maintenance costs, or electricity sales, hydrogen sales, peak-shaving subsidies and investment costs, etc., lacking the auxiliary service function of comprehensive hydrogen energy storage configuration. In addition, the current hydrogen energy storage optimization is based on a daily cycle, lacking consideration of the long-term fluctuation characteristics of wind power, making it difficult for hydrogen energy storage configuration to apply to the actual fluctuation law of wind power, and the economic benefits need to be further improved. Summary of the invention
[0004] In order to solve the above-mentioned technical problems, the present invention provides a hydrogen energy storage configuration method based on comprehensive auxiliary services and long-term fluctuations in wind power, which helps to improve the wind power consumption rate by configuring hydrogen energy storage, obtain more accurate economic benefits, and improve the economy of power grid operation.
[0005] In order to achieve the above object, the technical solution adopted by the present invention is:
[0006] A method for configuring hydrogen energy storage based on comprehensive ancillary services and long-term fluctuations in wind power is implemented through the following steps:
[0007] S1: Input network parameters and the load P of a typical cycle L,i (t), predicted power of wind turbine P W,i (t), t=1,2,...,T, i=1,2,....,N, T is the wind power fluctuation period, N is the number of network nodes;
[0008] S2: Establish a mathematical model for hydrogen energy storage, including electrolyzer, hydrogen storage tank and fuel cell models;
[0009] The calculation formula for the amount of hydrogen produced by electrolyzing water in an electrolyzer is as follows:
[0010] Q E,i (t) = η E PE,i (t)ξ (1)
[0011] In the formula, Q E,i (t) is the hydrogen production in hour t, unit: kg (Nm 3 );η E is the electrolyzer efficiency; P E,i (t) is the input power of the electrolyzer in the tth hour, unit: MW; ξ is the amount of hydrogen produced by consuming 1 kW·h of electricity, unit: kg / kW·h;
[0012] P E,i (t) Satisfy the following capacity constraints:
[0013] P E,i (t)≤P E,i (2)
[0014] Where P E,i is the electrolyzer capacity at node i;
[0015] The calculation formula of hydrogen storage capacity of hydrogen storage tank is as follows:
[0016]
[0017] In the formula, Q Tank,i (t) is the hydrogen storage capacity of the hydrogen storage tank at hour t, unit: kg (Nm 3 );P FC,i (t) is the power output of the fuel cell in the tth hour, in kW; μ is the amount of hydrogen consumed by the fuel cell to produce 1 kW·h of electricity; η FC is the working efficiency of the fuel cell; η Tank is the efficiency of the hydrogen storage tank; Q S,i (t) is the hydrogen sales volume of node i in hour t;
[0018] Q Tank,i (t) and P FC,i (t)Meanwhile satisfying the capacity constraint:
[0019] Q Tank,i (t)≤Q Tank,i (4)
[0020] P FC,i (t)≤P FC,i (5)
[0021] In the formula, Q Tank,i is the hydrogen storage tank capacity of the i-th node; P FC,i is the fuel cell capacity of the ith node;
[0022] The calculation formula of fuel cell output power is as follows:
[0023] PFC,i (t) = η FC Q H,i (t) / μ (6)
[0024] In the formula, Q H,i (t) is the hydrogen consumption in the tth hour, unit: kg (Nm 3 );
[0025] S3: Establish a hydrogen energy storage configuration model with comprehensive ancillary services and long-term wind power fluctuation characteristics;
[0026] The comprehensive benefit objective function of hydrogen energy storage configuration is as follows:
[0027] F=max(F tf +F tp +F H +F L -F EHP -F G ) (7)
[0028] In the formula, F tf is the compensation income for peak load ancillary services; F tp is the revenue from frequency regulation ancillary services; F H is the revenue from hydrogen sales; F L is the benefit of delayed construction of transmission lines; F EHP is the investment cost of hydrogen energy storage system; F G Additional costs for conventional thermal power units;
[0029] ① Peak load ancillary service compensation income F tf :
[0030] When wind power is high / load is low, if the thermal power unit is required to reduce the minimum technical output to adjust the peak, the thermal power unit will output at the minimum power and consume wind power for water electrolysis, which is the peak-shaving power:
[0031]
[0032] In the formula, Ω tf is the peak load period set; c tf The unit power compensation price for hydrogen energy storage participating in peak load regulation, unit: 10,000 yuan / MWh;
[0033] ② Frequency regulation ancillary service income F tp :
[0034] The compensation benefits obtained by hydrogen energy storage participating in the frequency regulation auxiliary service market include frequency regulation capacity benefits and frequency regulation mileage compensation.
[0035]
[0036] In the formula, c capis the frequency regulation capacity compensation price, unit: yuan / MWh; c mil is the frequency regulation mileage clearing price, unit: yuan / MWh;
[0037] ③ Hydrogen sales revenue F H :
[0038]
[0039] In the formula, c H The price of hydrogen sold in the market, unit: RMB / kg (or RMB / Nm 3 );
[0040] ④ The benefits of delayed construction of transmission lines F L :
[0041] The benefit of delayed construction of transmission lines is the annual investment cost of line expansion before hydrogen energy storage is configured. LB Subtract the annual investment cost of line expansion after configuring hydrogen energy storage F LA , the calculation formula is as follows:
[0042]
[0043] In the formula, c jk ΔP is the unit power cost per unit length of the line, unit: 10,000 yuan / (MW·km); B,jk The active power transmitted by line ij before hydrogen energy storage configuration exceeds the limit, unit: MW; ΔP A,jk The active power transmitted by line jk after hydrogen energy storage configuration exceeds the limit, unit: MW; L jk is the length of line jk, unit: km; Ω Line is the set of lines; λ is the annual interest rate; y is the operating life;
[0044] Ignoring line losses, the power grid satisfies the following power balance equation before hydrogen energy storage configuration:
[0045]
[0046] Where P GB,i (t) is the output power of conventional thermal power units before hydrogen energy storage configuration; P WB,i (t) is the actual wind power absorbed by the grid before hydrogen energy storage configuration;
[0047] The constraints satisfied by the operation of conventional thermal power units are as follows:
[0048]
[0049] In the formula, and is the minimum and maximum output of conventional thermal power units at node i;
[0050]
[0051] In the formula, and is the upward and downward climbing rate of the conventional thermal power unit at node i;
[0052] The active power transmitted by line ij exceeds the limit ΔP before hydrogen energy storage configuration B,jk The calculation method is as follows: The wind power obtained by optimizing according to formulas (14)-(15) is P WB,i (t), conventional thermal power unit power P GB,i (t) and load power P L,i (t), DC power flow is used to calculate the transmission power of each branch. In the example, the maximum over-limit power of line jk is selected as ΔP B,jk ;
[0053] The power balance equation of node i after hydrogen energy storage configuration is as follows:
[0054]
[0055] Where P GA,i (t) is the output power of conventional thermal power units after hydrogen energy storage configuration; P WA,i (t) is the actual wind power absorbed by the power grid after hydrogen energy storage configuration; B(j,·) represents the branch set with node j as the starting node; B(·,j) is the branch set with node j as the end node;
[0056] Based on the DC power flow, the corresponding power and phase angle constraints are:
[0057] P jk (t) = B jk (θ j (t)-θ k (t)) (18)
[0058] -π≤θ j (t)≤π (19)
[0059] θ ref (t)=0 (20)
[0060] In the formula, B jk is the reactance of the transmission line jk; θ j (t),θ k (t) is the phase angle between node j and node k; θ ref (t) is the equilibrium node phase angle;
[0061] Conventional thermal power units also satisfy equations (15) and (16);
[0062] After hydrogen energy storage is configured, the active power transmitted by line jk exceeds the limit ΔP A,jk The calculation method is as follows:
[0063]
[0064] Where P jk (t) is the result calculated according to equations (15)-(20); is the maximum transmitted active power of branch jk;
[0065] ⑤ Investment cost of hydrogen energy storage system F EHP :
[0066] The investment cost of hydrogen energy storage system mainly includes the cost of electrolyzer, hydrogen storage tank and fuel cell. E,i is the planned power of the electrolyzer at the ith node, P FC,i is the planned output power of the fuel cell at the i-th node, and the calculation expression of the hydrogen energy storage investment cost is:
[0067]
[0068] In the formula, c E 、c FC is the unit investment cost of electrolyzer and fuel cell, unit: yuan / kW; c tank is the unit investment cost of hydrogen storage tank, unit: yuan / kg (Nm 3 );
[0069] ⑥ Additional cost of conventional thermal power units F G :
[0070] Compared with before hydrogen energy storage configuration, the calculation formula for the additional power cost of conventional thermal power units is as follows:
[0071]
[0072] In the formula, c G (t) is the electricity purchase cost of thermal power units, unit: yuan / kWh;
[0073] S4: Hydrogen energy storage optimization based on particle swarm algorithm;
[0074] S41: Initialize the particle swarm algorithm parameters, particle x p = {P E,i ,P FC,i ,Q Tank,i ,P E,i (t),P FC,i (t),Q S,i (t),P G,i (t),P WA,i (t)}, p=1,2,...,N p , Np is the population size, the velocity vector v p ={vP E,i ,vP FC,i ,vQ Tank,i ,vP FC,i (t),vQ S,i (t),vP G,i (t),vP WA,i (t)}, the initial value is 0, the local optimal solution and the global optimal solution F gb , the local optimal solution particle is a vector The global optimal particle is vector x gb ;Number of iterations N it , global and local learning factors c1, c2, inertia weight coefficient w, number of iterations it = 1;
[0075] S42: Obtain the local optimal solution for each particle Then obtain the global optimal solution F gb , that is, for p = 1, 2, ..., N p ,like make The local optimal solution of each particle Select the maximum value among them, if it is greater than F gb , assigned to F gb , and the corresponding Assign to x gb ;
[0076] S43: Update the particle position, that is, update the particle position according to equation (24), that is, for p = 1, 2, ..., N p have:
[0077]
[0078] S44: Let it=it+1, if it≤N it Or the difference between the global optimal solutions of the two iterations is less than the given allowable error ε, ε = 10 -5 , go to step S4; otherwise, go to step S43;
[0079] S5: Output comprehensive benefits and hydrogen energy storage configuration results, that is, output electrolyzer configuration power P E,i 、Fuel cell configuration power P FC,i 、Hydrogen storage tank configuration capacity Q Tank,i and comprehensive income F.
[0080] In step S1, the time t is in units of hours or a given time period.
[0081] In step S4, a genetic algorithm is used to find the solution.
[0082] The present invention first establishes a hydrogen energy storage mathematical model, and then establishes a hydrogen energy storage configuration model in combination with comprehensive auxiliary services and long-term fluctuation characteristics of wind power. Then, through a hydrogen energy storage optimization algorithm, the comprehensive benefits after hydrogen energy storage auxiliary services are comprehensively calculated. Through this optimization configuration method, the wind power consumption rate is effectively improved, the abandonment of wind and solar power is reduced, more accurate and higher economic benefits are obtained, the economy of power grid operation is improved, and it adapts to the current environment of full utilization of renewable energy. It provides a new idea for the more effective, safer and more economical utilization of wind turbines connected to the power grid, and is suitable for large-scale promotion and application in the field of regional power grids. BRIEF DESCRIPTION OF THE DRAWINGS
[0083] Figure 1 It is a schematic diagram of the process of the present invention;
[0084] Figure 2 The figure is a schematic diagram of the IEEE-24 node network structure of a specific embodiment of the present invention. DETAILED DESCRIPTION
[0085] The present invention is described in detail below with reference to the accompanying drawings and specific embodiments:
[0086] like Figure 1 As shown in FIG. 1 , the hydrogen energy storage configuration method based on comprehensive auxiliary services and long-term fluctuations in wind power is implemented through the following steps:
[0087] S1: Input network parameters and the load P of a typical cycle L,i (t), predicted power of wind turbine P W,i (t), t=1,2,...,T, i=1,2,....,N, T is the wind power fluctuation period, and N is the number of network nodes.
[0088] S2: Establish a mathematical model of hydrogen energy storage, including electrolyzer, hydrogen storage tank and fuel cell models.
[0089] The calculation formula for the amount of hydrogen produced by electrolyzing water in an electrolyzer is as follows:
[0090] Q E,i (t) = η E P E,i (t)ξ (1)
[0091] In the formula, Q E,i (t) is the amount of hydrogen produced in the tth hour, unit: Nm 3 ; η E is the efficiency of the electrolyzer, which is taken as 75%; P E,i (t) is the input power of the electrolyzer in the tth hour, unit: MW; ξ is the amount of hydrogen produced by consuming 1 kW·h of electricity, and its value is 0.25 Nm 3 / kW·h.
[0092] P E,i (t) Satisfy the following capacity constraints:
[0093] P E,i (t)≤P E,i (2)
[0094] Where P E,i is the electrolytic cell capacity at node i.
[0095] The calculation formula of hydrogen storage capacity of hydrogen storage tank is as follows:
[0096]
[0097] In the formula, Q Tank,i (t) is the hydrogen storage capacity of the hydrogen storage tank at hour t, unit: Nm 3 ;P FC,i (t) is the power output of the fuel cell in the tth hour, unit: MW; μ is the amount of hydrogen consumed by the fuel cell to produce 1kW·h of electricity, the value is 0.295Nm 3 / kW·h; η FC is the efficiency of the fuel cell, which is taken as 55%; η Tank is the efficiency of the hydrogen storage tank, which is taken as 100%; Q S,i (t) is the hydrogen sales volume of node i in the tth hour.
[0098] Q Tank,i (t) and P FC,i (t)Meanwhile satisfying the capacity constraint:
[0099] Q Tank,i (t)≤Q Tank,i (4)
[0100] P FC,i (t)≤P FC,i (5)
[0101] In the formula, Q Tank,i is the hydrogen storage tank capacity of the i-th node; P FC,i is the fuel cell capacity of the ith node.
[0102] The calculation formula of fuel cell output power is as follows:
[0103] P FC,i (t) = η FC Q H,i (t) / μ (6)
[0104] In the formula, Q H,i (t) is the hydrogen consumption in the tth hour, unit: Nm 3 .
[0105] S3: Establish a hydrogen energy storage configuration model with comprehensive ancillary services and long-term fluctuation characteristics of wind power.
[0106] The comprehensive benefit objective function of hydrogen energy storage configuration is as follows:
[0107] F=max(F tf +F tp +F H +F L -F EHP -F G ) (7)
[0108] In the formula, F tf is the compensation income for peak load ancillary services; F tp is the revenue from frequency regulation ancillary services; F H is the revenue from hydrogen sales; F L is the benefit of delayed construction of transmission lines; F EHP is the investment cost of hydrogen energy storage system; F G Additional costs for conventional thermal power units.
[0109] ①Peak load subsidy income F tf :
[0110] Conventional thermal power units are equipped with hydrogen energy storage for deep peak regulation. On the one hand, it increases the load of thermal power plants, reduces the external output of thermal power units, and obtains deep peak regulation subsidies; on the other hand, it sells hydrogen to achieve more profits. When wind power is generated at a high level / load is low, if the thermal power units are required to reduce the minimum technical output for peak regulation, the thermal power units will output at the minimum power and consume wind power for water electrolysis, which is the peak regulation power.
[0111]
[0112] In the formula, Ω tf is the peak load period set; c tf The unit power compensation price for hydrogen energy storage participating in peak regulation is RMB 5500 / MWh.
[0113] ② Frequency regulation subsidy income F tp :
[0114] The frequency regulation ancillary service market mainly adopts a two-part price system, which includes capacity price and mileage price. The compensation income obtained by hydrogen energy storage from participating in the frequency regulation ancillary service market includes frequency regulation capacity income and frequency regulation mileage compensation.
[0115]
[0116] In the formula, c cap is the frequency regulation capacity compensation price, which is 14 yuan / MWh; c mil The price for clearing frequency regulation mileage is 15 yuan / MWh.
[0117] ③ Hydrogen sales revenue F H :
[0118]
[0119] In the formula, c H is the hydrogen price in the market, 3.5 yuan / Nm 3 .
[0120] ④ The benefits of delayed construction of transmission lines F L :
[0121] After hydrogen energy storage is configured, it can effectively avoid the problem of excessive wind power input causing the line transmission power to exceed the limit, thus forming a line delay construction benefit. The transmission line delay construction benefit is the annual investment cost of line expansion before hydrogen energy storage is configured. LB Subtract the annual investment cost of line expansion after configuring hydrogen energy storage F LA , the calculation formula is as follows:
[0122]
[0123] In the formula, c jk is the unit power cost per unit length of the line, unit: 10,000 yuan / (MW·km), take 10,000 yuan / (MW·km); ΔP B,jk The active power transmitted by line ij before hydrogen energy storage configuration exceeds the limit, unit: MW; ΔP A,jk The active power transmitted by line jk after hydrogen energy storage configuration exceeds the limit, unit: MW; L jk is the length of line jk, unit: km; Ω Line is the set of routes; λ is the annual interest rate; y is the operating life.
[0124] Ignoring line losses, the power grid satisfies the following power balance equation before hydrogen energy storage configuration:
[0125]
[0126] Where P GB,i (t) is the output power of conventional thermal power units before hydrogen energy storage configuration; P WB,i (t) is the actual wind power absorbed by the grid before hydrogen energy storage configuration.
[0127] The constraints satisfied by the operation of conventional thermal power units are as follows:
[0128]
[0129] In the formula, and is the minimum and maximum output of conventional thermal power units at node i.
[0130]
[0131] In the formula, and is the upward and downward climbing rate of the conventional thermal power unit at node i.
[0132] The active power transmitted by line ij exceeds the limit ΔP before hydrogen energy storage configuration B,jk The calculation method is as follows: The wind power obtained by optimizing according to formulas (14)-(15) is P WB,i (t), conventional thermal power unit power P GB,i (t) and load power P L,i (t), DC power flow is used to calculate the transmission power of each branch. In the example, the maximum over-limit power of line jk is selected as ΔP B,jk .
[0133] The power balance equation of node i after hydrogen energy storage configuration is as follows:
[0134]
[0135] Where P GA,i (t) is the output power of conventional thermal power units after hydrogen energy storage configuration; P WA,i (t) is the actual wind power absorbed by the power grid after hydrogen energy storage configuration; B(j,·) represents the branch set with node j as the starting node; B(·,j) is the branch set with node j as the end node.
[0136] Based on the DC power flow, the corresponding power and phase angle constraints are:
[0137] P jk (t) = B jk (θ j (t)-θ k (t)) (18)
[0138] -π≤θ j (t)≤π (19)
[0139] θ ref (t)=0 (20)
[0140] In the formula, B jk is the reactance of the transmission line jk; θ j (t),θ k (t) is the phase angle between node j and node k; θ ref (t) is the equilibrium node phase angle.
[0141] Conventional thermal power units also satisfy equations (15) and (16).
[0142] After hydrogen energy storage is configured, the active power transmitted by line jk exceeds the limit ΔP A,jk The calculation method is as follows:
[0143]
[0144] Where P jk (t) is the result calculated according to equations (15)-(20); is the maximum transmitted active power of branch jk.
[0145] ⑤ Investment cost of hydrogen energy storage system F EHP :The investment cost of the hydrogen energy storage system mainly includes the cost of the electrolyzer, hydrogen storage tank and fuel cell.
[0146] Let P E,i is the planned power of the electrolyzer at the ith node, P FC,i is the planned output power of the fuel cell at the i-th node, and the calculation expression of the hydrogen energy storage investment cost is:
[0147]
[0148] In the formula, c E 、c FC is the unit investment cost of electrolyzer and fuel cell, unit: yuan / kW; c tank is the unit investment cost of hydrogen storage tank, unit: Yuan / Nm 3 The values are c E =2500 yuan / kW, c tank =280 yuan / Nm 3 (Standard working conditions), c FC =2500 yuan / kW.
[0149] ⑥ Additional cost of conventional thermal power units F G :
[0150] Compared with before hydrogen energy storage configuration, the calculation formula for the additional power cost of conventional thermal power units is as follows:
[0151]
[0152] In the formula, c G (t) is the electricity purchase cost of the thermal power unit, which is 0.262 yuan / kWh.
[0153] S4: Hydrogen energy storage optimization based on particle swarm algorithm.
[0154] S41: Initialize the particle swarm algorithm parameters, particle x p = {P E,i ,P FC,i ,Q Tank,i ,P E,i (t),PFC,i (t),Q S,i (t),P G,i (t),P WA,i (t)}, p=1,2,...,N p , N p is the population size, the velocity vector v p ={vP E,i ,vP FC,i ,vQ Tank,i ,vP FC,i (t),vQ S,i (t),vP G,i (t),vP WA,i (t)}, the initial value is 0, the local optimal solution and the global optimal solution F gb =1000000, the local optimal solution particle is a vector The global optimal particle is vector x gb ;Number of iterations N it , global and local learning factors c1, c2, inertia weight coefficient w, number of iterations it = 1;
[0155] S42: Obtain the local optimal solution for each particle Then obtain the global optimal solution F gb , that is, for p = 1, 2, ..., N p ,like make The local optimal solution of each particle Select the maximum value among them, if it is greater than F gb , assigned to F gb , and the corresponding Assign to x gb ;
[0156] S43: Update the particle position, that is, update the particle position according to equation (24), that is, for p = 1, 2, ..., N p have:
[0157]
[0158] S44: Let it=it+1, if it≤N it Or the difference between the global optimal solutions of the two iterations is less than the given allowable error ε, ε = 10 -5 , go to step S4; otherwise, go to step S43;
[0159] S5: Output comprehensive benefits and hydrogen energy storage configuration results, that is, output electrolyzer configuration power P E,i 、Fuel cell configuration power P FC,i 、Hydrogen storage tank configuration capacity Q Tank,iand comprehensive income F.
[0160] As a preferred manner, in step S1, the time t is in hours or a given time period.
[0161] As a preferred method, a genetic algorithm is used to find the solution in step S4.
[0162] Below Figure 2 The IEEE-24 node network shown is a specific embodiment for performing hydrogen energy storage configuration calculations. Some parameter values have been recorded in the above steps and will not be described later.
[0163] Step S1: According to the wind power fluctuation characteristics, the time period of this example is T = 48 hours, the number of nodes is 24, and node 13 is a balancing node. Add a wind turbine unit of 110MW each to nodes 1 and 15, and add a 200MW wind turbine to node 7. Table 1 gives the wind power and load values, Table 2 gives the output limit of conventional thermal power units, and Table 3 gives the network structure parameters.
[0164] Table 1 Wind power and load values
[0165]
[0166]
[0167] Table 2 Output limit table of conventional thermal power units
[0168] serial number node Maximum output(MW) Minimum output(MW) Upward climbing power (MW) Downward climbing power (MW) 1 1 152 30.4 40 40 2 2 152 30.4 40 40 7 7 350 75 70 70 13 13 591 206.85 180 180 15a 15 60 12 60 60 15b 15 155 54.25 30 30 16 16 155 54.25 30 30 18 18 400 100 0 0 21 21 400 100 0 0 22 22 300 300 0 0 23a 23 310 108.5 60 60 23b 23 350 140 40 40
[0169] Table 3 Network structure parameters
[0170]
[0171]
[0172] Step S2:
[0173] In this embodiment, an alkaline electrolyzer is selected as the water electrolysis hydrogen production equipment. The amount of hydrogen produced by the alkaline electrolyzer is related to the power input to the electrolyzer and the hydrogen production efficiency. The calculation formula for the amount of hydrogen produced by the water electrolysis of the electrolyzer is as follows:
[0174] Q E,i (t) = η E P E,i (t)ξ
[0175] Where η E is the electrolyzer efficiency, which is taken as 75%, ξ is the amount of hydrogen produced by consuming 1 kW·h of electricity, which is taken as 0.25 Nm 3 / kW·h.
[0176] High-pressure gaseous hydrogen storage tanks are used to store hydrogen produced by the electrolysis of water in alkaline electrolyzers and are also used to provide hydrogen fuel for fuel cells. Tank is the efficiency of the hydrogen storage tank, which is taken as 100%. The calculation formula for the hydrogen storage capacity of the hydrogen storage tank is as follows:
[0177]
[0178] The calculation formula for the output power of proton exchange membrane fuel cells is as follows:
[0179] P FC,i (t) = η FC Q H,i (t) / μ
[0180] Where μ is the amount of hydrogen consumed by the fuel cell to produce 1kW·h of electricity, and its value is 0.295Nm 3 / kW·h; η FC is the working efficiency of the fuel cell, which is taken as 55%.
[0181] Steps S3-S4:
[0182] It can be seen from Table 1 that the total output of the fan is large in the first 24 hours, and small in the last 24 hours. Therefore, the electrolyzer produces hydrogen in the first 24 hours of hydrogen energy storage, and the fuel cell discharges in the last 24 hours.
[0183] Initialize the particle swarm parameters and obtain the global optimal solution. The maximum over-limit power of branch 7-8 is 29MW, so hydrogen energy storage is planned at node 7. The electrolyzer configuration capacity is the sum of the maximum wind power abandonment and the maximum over-limit power, which is 43MW. Therefore, the total hydrogen production in the first 24 hours is:
[0184]
[0185]
[0186] In the last 24 hours, the fan output is small and the fuel cell outputs full power. The hourly evaluation output power is:
[0187] P FC,i (t) = η FC Q H,i (t) / μ=55%×2527 / 0.295≈4.7MW
[0188] According to the difference in peak and valley time-of-use electricity prices, in order to obtain maximum profit, the fuel cell outputs maximum power during peak electricity prices and outputs 0 during valley times. Therefore, the fuel cell configuration power is 9MW.
[0189] ①Peak load subsidy income F tf
[0190]
[0191] ② Frequency regulation subsidy income F tp
[0192]
[0193] ③ The benefits of delayed construction of transmission lines F L
[0194]
[0195] ④Hydrogen energy storage investment cost:
[0196]
[0197] ⑤ Additional cost of conventional thermal power units F G
[0198]
[0199] Comprehensive benefits after hydrogen energy storage configuration:
[0200] F=max(F tf +F tp +F H +F L -F EHP -F G )
[0201] =2451.735+10.125+232.07+37.27-1180.54-1188.67
[0202] =3.62 million yuan
[0203] Step S5:
[0204] The output hydrogen energy storage configuration has an annual comprehensive income of 3.62 million yuan, the electrolyzer is configured with a power of 43MW, and the hydrogen storage tank capacity is 60640Nm 3 The fuel cell configuration power is 9MW. Compared with no hydrogen energy storage, the annual wind power abandonment is reduced by 44,577MW, accounting for 2% of the total predicted output power of wind turbines.
[0205] Of course, the above description is not a limitation of the present invention, and the present invention is not limited to the above examples. Changes, modifications, additions or substitutions made by technicians in this technical field within the essential scope of the present invention should also fall within the protection scope of the present invention.
Claims
1. A hydrogen energy storage configuration method based on comprehensive auxiliary services and long-term fluctuations in wind power, characterized in that: This is accomplished by the following steps: S1: Input network parameters and the load P of a typical cycle L,i (t), predicted power of wind turbine P W,i (t), t=1,2,...,T, i=1,2,....,N, T is the wind power fluctuation period, N is the number of network nodes; S2: Establish a mathematical model for hydrogen energy storage, including electrolyzer, hydrogen storage tank and fuel cell models; The calculation formula for the amount of hydrogen produced by electrolyzing water in an electrolyzer is as follows: Q E,i (t)=η E P E,i (t)ξ (1) In the formula, Q E,i (t) is the hydrogen production in hour t, unit: kg (Nm 3 );η E is the electrolyzer efficiency; P E,i (t) is the input power of the electrolyzer in hour t, in MW; ξ is the amount of hydrogen produced by consuming 1 kW·h of electricity, unit: kg / kW·h; P E,i (t) Satisfy the following capacity constraints: P E,i (t)≤P E,i (2) Where P E,i is the electrolyzer capacity at node i; The calculation formula of hydrogen storage capacity of hydrogen storage tank is as follows: In the formula, Q Tank,i (t) is the hydrogen storage capacity of the hydrogen storage tank at hour t, unit: kg (Nm 3 );P FC,i (t) is the power output of the fuel cell in the tth hour, in kW; μ is the amount of hydrogen consumed by the fuel cell to produce 1 kW·h of electricity; η FC is the working efficiency of the fuel cell; η Tank is the efficiency of the hydrogen storage tank; Q S,i (t) is the hydrogen sales volume of node i in hour t; Q Tank,i (t) and P FC,i (t)Meanwhile satisfying the capacity constraint: Q Tank,i (t)≤Q Tank,i (4) P FC,i (t)≤P FC,i (5) In the formula, Q Tank,i is the hydrogen storage tank capacity of the i-th node; P FC,i is the fuel cell capacity of the ith node; The calculation formula of fuel cell output power is as follows: P FC,i (t)=η FC Q H,i (t) / m (6) In the formula, Q H,i (t) is the hydrogen consumption in the tth hour, unit: kg (Nm 3 ); S3: Establish a hydrogen energy storage configuration model with comprehensive ancillary services and long-term wind power fluctuation characteristics; The comprehensive benefit objective function of hydrogen energy storage configuration is as follows: F=max(F tf +F tp +F H +F L -F EHP -F G ) (7) In the formula, F tf is the compensation income for peak load ancillary services; F tp is the revenue from frequency regulation ancillary services; F H is the revenue from hydrogen sales; F L is the benefit of delayed construction of transmission lines; F EHP is the investment cost of hydrogen energy storage system; F G Additional costs for conventional thermal power units; ① Peak load ancillary service compensation income F tf : When wind power is high / load is low, if the thermal power unit is required to reduce the minimum technical output to adjust the peak, the thermal power unit will output at the minimum power and consume wind power for water electrolysis, which is the peak-shaving power: In the formula, Ω tf is the peak load period set; c tf The unit power compensation price for hydrogen energy storage participating in peak load regulation, unit: 10,000 yuan / MWh; ② Frequency regulation ancillary service income F tp : The compensation benefits obtained by hydrogen energy storage participating in the frequency regulation auxiliary service market include frequency regulation capacity benefits and frequency regulation mileage compensation. In the formula, c cap is the frequency regulation capacity compensation price, unit: yuan / MWh; c mil is the frequency regulation mileage clearing price, unit: yuan / MWh; ③ Hydrogen sales revenue F H : In the formula, c H The price of hydrogen sold in the market, unit: RMB / kg (or RMB / Nm 3 ); ④ The benefits of delayed construction of transmission lines F L : The benefit of delayed construction of transmission lines is the annual investment cost of line expansion before hydrogen storage is configured. LB Subtract the annual investment cost of line expansion after configuring hydrogen energy storage F LA , the calculation formula is as follows: In the formula, c jk ΔP is the unit power cost per unit length of the line, unit: 10,000 yuan / (MW·km); B,jk The active power transmitted by line ij before hydrogen energy storage configuration exceeds the limit, unit: MW; ΔP A,jk The active power transmitted by line jk after hydrogen energy storage configuration exceeds the limit, unit: MW; L jk is the length of line jk, unit: km; Ω Line is the set of lines; λ is the annual interest rate; y is the operating life; Ignoring line losses, the power grid satisfies the following power balance equation before hydrogen energy storage configuration: Where P GB,i (t) is the output power of conventional thermal power units before hydrogen energy storage configuration; P WB,i (t) is the actual wind power absorbed by the grid before hydrogen energy storage configuration; The constraints satisfied by the operation of conventional thermal power units are as follows: In the formula, and is the minimum and maximum output of conventional thermal power units at node i; In the formula, and is the upward and downward climbing rate of the conventional thermal power unit at node i; The active power transmitted by line ij before hydrogen energy storage configuration exceeds the limit ΔP B,jk The calculation method is as follows: The wind power obtained by optimizing according to formulas (14)-(15) is P WB,i (t), conventional thermal power unit power P GB,i (t) and load power P L,i (t), DC power flow is used to calculate the transmission power of each branch. In the example, the maximum over-limit power of line jk is selected as ΔP B,jk ; The power balance equation of node i after hydrogen energy storage configuration is as follows: Where P GA,i (t) is the output power of conventional thermal power units after hydrogen energy storage configuration; P WA,i (t) is the actual wind power absorbed by the power grid after hydrogen energy storage configuration; B(j,·) represents the branch set with node j as the starting node; B(·,j) is the branch set with node j as the end node; Based on the DC power flow, the corresponding power and phase angle constraints are: P jk (t)=B jk (θ j (t)-θ k (t)) (18) -π≤θ j (t)≤π (19) i ref (t)=0 (20) In the formula, B jk is the reactance of the transmission line jk; θ j (t),θ k (t) is the phase angle between node j and node k; θ ref (t) is the equilibrium node phase angle; Conventional thermal power units also satisfy equations (15) and (16); After hydrogen energy storage is configured, the active power transmitted by line jk exceeds the limit ΔP A,jk The calculation method is as follows: Where P jk (t) is the result calculated according to equations (15)-(20); is the maximum transmitted active power of branch jk; ⑤ Investment cost of hydrogen energy storage system F EHP : The investment cost of hydrogen energy storage system mainly includes the cost of electrolyzer, hydrogen storage tank and fuel cell. E,i is the planned power of the electrolyzer at the ith node, P FC,i is the planned output power of the fuel cell at the i-th node, and the calculation expression of the hydrogen energy storage investment cost is: In the formula, c E 、c FC is the unit investment cost of electrolyzer and fuel cell, unit: yuan / kW; c tank is the unit investment cost of hydrogen storage tank, unit: yuan / kg (Nm 3 ); ⑥ Additional cost of conventional thermal power units F G : Compared with before hydrogen energy storage configuration, the calculation formula for the additional power cost of conventional thermal power units is as follows: In the formula, c G (t) is the electricity purchase cost of thermal power units, unit: yuan / kWh; S4: Hydrogen energy storage optimization based on particle swarm algorithm; S41: Initialize the particle swarm algorithm parameters, particle x p = {P E,i ,P FC,i ,Q Tank,i ,P E,i (t),P FC,i (t),Q S,i (t),P G,i (t),P WA,i (t)}, p=1,2,...,N p , N p is the population size, the velocity vector v p ={vP E,i ,vP FC,i ,vQ Tank,i ,vP FC,i (t),vQ S,i (t),vP G,i (t),vP WA,i (t)}, the initial value is 0, the local optimal solution and the global optimal solution F gb , the local optimal solution particle is a vector The global optimal particle is vector x gb ;Number of iterations N it , global and local learning factors c1, c2, inertia weight coefficient w, number of iterations it = 1; S42: Obtain the local optimal solution for each particle Then obtain the global optimal solution F gb , that is, for p = 1, 2, ..., N p ,like make The local optimal solution of each particle Select the maximum value among them, if it is greater than F gb , assigned to F gb , and the corresponding Assign to x gb ; S43: Update the particle position, that is, update the particle position according to equation (24), that is, for p = 1, 2, ..., N p have: S44: Let it=it+1, if it≤N it Or the difference between the global optimal solutions of the two iterations is less than the given allowable error ε, ε = 10 -5 , go to step S4; otherwise, go to step S43; S5: Output comprehensive benefits and hydrogen energy storage configuration results, that is, output electrolyzer configuration power P E,i 、Fuel cell configuration power P FC,i 、Hydrogen storage tank configuration capacity Q Tank,i and comprehensive income F.
2. The hydrogen energy storage configuration method based on comprehensive auxiliary services and long-term wind power fluctuations according to claim 1 is characterized in that: In step S1, the time t is in units of hours or a given time period.
3. The hydrogen energy storage configuration method based on comprehensive auxiliary services and long-term wind power fluctuations according to claim 1 is characterized in that: In step S4, a genetic algorithm is used to find the solution.