Water electrolysis hydrogen production automatic nitrogen charging replacement device
By using a combination of pressure reducer, solenoid valve and flowmeter in the water electrolytic nitrogen production device, automated control is achieved, solving the problems of slow operation and insufficient safety of traditional nitrogen replacement devices, ensuring fast and safe nitrogen filling process.
Patent Information
- Application Number
- CN202280083634.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2022-12-15
- Publication Date
- 2024-11-12
AI Technical Summary
The traditional nitrogen replacement device requires manual operation, the nitrogen filling speed is slow, and manual adjustment is required when the liquid level difference is too large, which can easily lead to hydrogen and oxygen mix explosion and insufficient automation.
An automatic nitrogen charging device for electrolytic nitrogen production is designed, using two pressure reducers, two solenoid valves and two flowmeters to realize automatic nitrogen charging through remote signal control to ensure the liquid level of the oxygen separator and hydrogen separator. The difference is within the right range, avoids mixing, and can quickly complete the replacement.
It realizes fast nitrogen charging without on-site operation, ensures the safety and automation of the equipment, reduces the risk of personnel misoperation, and improves the operating efficiency of the equipment.
Smart Images

Figure CN118946685A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of water electrolysis hydrogen production, and in particular to an automatic nitrogen filling and replacement device for water electrolysis hydrogen production. Background Art
[0002] The alkaline water electrolysis hydrogen production device is equipped with two gas separators. In the working state, the lower half of the separator is filled with alkali solution and the upper half is filled with gas. The hydrogen produced by electrolysis in the electrolyzer enters the hydrogen separator with the alkali solution, and the oxygen produced by electrolysis enters the oxygen separator with the oxygen. The anode and cathode in each small chamber of the electrolyzer are separated by a diaphragm. Water and ions can pass through the diaphragm, but gas cannot pass through the diaphragm. The diaphragm is very sensitive to the pressure difference on both sides. Therefore, the bottom of the hydrogen separator and the oxygen separator are connected by a connecting pipe. The liquid level difference on both sides is the pressure difference on the electrolyzer diaphragm. The alkali solution in the separator has the function of liquid sealing.
[0003] Before producing hydrogen by water electrolysis, the air inside the container storing hydrogen and oxygen needs to be discharged, otherwise the hydrogen or oxygen mixed with air will easily cause an explosion when ignited. Therefore, it is necessary to replace the containers storing hydrogen and oxygen, and replace the air with inert gas nitrogen. When the hydrogen production equipment is not in operation for a long time, in order to prevent the liquid level change on both sides caused by factors such as internal leakage of the rear-end valve, causing hydrogen / oxygen to enter the separator on the other side through the connecting pipe, resulting in the danger of hydrogen-oxygen mixture explosion; when the equipment needs to be repaired, the hydrogen / oxygen in the equipment also needs to be replaced with inert gas nitrogen.
[0004] The conventional nitrogen replacement device is relatively simple in setting, consisting of a check valve and a stop valve, which are installed on a horizontal pipe. It only relies on one pipe for replacement, and requires manual operation on site. In order to maintain the liquid level balance on both sides, it is necessary to control the nitrogen filling speed very slowly (each nitrogen filling takes several hours). If the liquid level difference is too large, it is also necessary to manually adjust the hydrogen and oxygen outlet bypass valve to empty it. Otherwise, when the liquid level on one side returns to zero, hydrogen / oxygen will enter the container on the other side through the connecting pipe, and hydrogen and oxygen will mix dangerously. With the continuous improvement of the automation level of equipment, this traditional nitrogen filling method is no longer suitable for the operation requirements of the equipment.
[0005] In order to solve the above problems, it is necessary to provide an automatic nitrogen filling and replacement device for hydrogen production by water electrolysis. Summary of the invention
[0006] In order to solve the above technical problems, an automatic nitrogen filling and replacement device for hydrogen production by water electrolysis is provided. The technical solution solves the conventional nitrogen replacement device proposed in the above background technology. The device is relatively simple in configuration and consists of a check valve and a stop valve. It is arranged on a flat horizontal pipe and requires manual operation on site. In order to maintain the liquid level balance on both sides, it is necessary to control a very slow nitrogen filling speed (each nitrogen filling takes several hours). If the liquid level difference is too large, it is also necessary to manually adjust the hydrogen and oxygen outlet bypass valve to vent. Otherwise, when the liquid level on one side returns to zero, hydrogen / oxygen will enter the container on the other side through the connecting pipe, resulting in dangerous mixing of hydrogen and oxygen.
[0007] In order to achieve the above purpose, the technical solution adopted by the present invention is:
[0008] Provided is an automatic nitrogen filling and replacement device for hydrogen production by water electrolysis, comprising a nitrogen inlet and a pipeline, wherein the nitrogen inlet is connected to a check valve through the pipeline, the check valve is connected to two flow meters through the pipeline, the pipeline connecting the check valve and the flow meter is bifurcated and arranged in two paths, the flow meter is connected to an electromagnetic valve through the pipeline, the electromagnetic valve is connected to a pressure reducer through the pipeline, the pressure reducer on the left side is connected to an oxygen separator through the pipeline, and the pressure reducer on the right side is connected to a hydrogen separator through the pipeline, and the lower parts of the hydrogen separator and the oxygen separator are filled with alkaline liquid.
[0009] Preferably, the oxygen separator and hydrogen separator are both arranged behind the electrolytic cell, the oxygen separator and hydrogen separator are hollow inside, and the bottoms of the oxygen separator and hydrogen separator are connected to the gas alkali outlet of the electrolytic cell.
[0010] Preferably, a plurality of plates are arranged inside the electrolytic cell, one side of the plate is an anode, the other side of the plate inside the electrolytic cell is a cathode, the oxygen separator is arranged behind the outlet where the anodes converge, and the hydrogen separator is arranged behind the outlet where the cathodes converge.
[0011] Preferably, the electrolytic cell is filled with alkaline liquid.
[0012] Preferably, a connecting pipe is fixedly connected between the bottom of the oxygen separator and the bottom of the hydrogen separator.
[0013] Preferably, a regulating valve group is fixedly connected to the left side of the oxygen separator, and a regulating valve group is fixedly connected to the right side of the hydrogen separator.
[0014] Compared with the prior art, the present invention provides an automatic nitrogen filling and replacement device for hydrogen production by water electrolysis, which has the following beneficial effects:
[0015] By setting two pressure reducers, two solenoid valves and two flow meters, when in use, only a remote signal is needed to control the opening of the automatic nitrogen filling valve, so that nitrogen enters the device from the nitrogen inlet. After the system pressure reaches the set value A, the automatic nitrogen filling valve is closed, and the flow on both sides can be adjusted by the throttling device (pressure reducer, etc.). During debugging, the throttling device (pressure reducer, etc.) can be adjusted by the flow meter indication to make the flow on both sides equal, thereby ensuring that the liquid level difference in the oxygen separator and the hydrogen separator is maintained in an appropriate range to avoid the mixing of oxygen and hydrogen. At the same time, there is no need to deliberately slow down the speed of nitrogen entry, so that the replacement speed can be guaranteed. In addition, the device can be remotely and automatically controlled without on-site operation, and the nitrogen filling and replacement operation can be automatically completed with one button, thereby improving the degree of automation of the equipment and reducing the risk caused by human error. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a structural schematic diagram of the present invention;
[0017] Figure 2 It is a schematic diagram of the electrolytic cell structure of the present invention.
[0018] The numbers in the figure are:
[0019] 1. Check valve; 2. Pressure reducer; 3. Solenoid valve; 4. Flow meter; 5. Pipeline; 6. Oxygen separator; 7. Nitrogen inlet; 8. Hydrogen separator; 9. Connecting pipe; 10. Alkaline liquid; 11. Electrolyzer; 12. Regulating valve group. DETAILED DESCRIPTION
[0020] The following description is used to disclose the present invention so that those skilled in the art can implement the present invention. The preferred embodiments described below are only examples, and those skilled in the art may think of other obvious variations.
[0021] Reference Figure 1-2As shown, an automatic nitrogen filling and replacement device for hydrogen production by water electrolysis comprises a nitrogen inlet 7 and a pipeline 5, wherein the nitrogen inlet 7 is connected to a check valve 1 through the pipeline 5, the check valve 1 is connected to two flow meters 4 through the pipeline 5, the pipeline 5 connecting the check valve 1 and the flow meter 4 is bifurcated into two paths, the flow meter 4 is connected to a solenoid valve 3 through the pipeline 5, the solenoid valve 3 is connected to a pressure reducer 2 through the pipeline 5, the pressure reducer 2 on the left side is connected to an oxygen separator 6 through the pipeline 5, and the pressure reducer 2 on the right side is connected to a hydrogen separator 8 through the pipeline 5, and the lower parts of the hydrogen separator 8 and the oxygen separator 6 are filled with alkaline liquid 10; the solenoid valves 3 are opened simultaneously by remote signal control to realize nitrogen filling at the same speed on both sides at the same time, so that nitrogen is filled into the device from the nitrogen inlet 7, and the nitrogen passes through the check valve 1, and the check valve 1 is used to prevent the liquid in the separator from The nitrogen gas flows back to the nitrogen system, and the pressure of the pressure reducer 2 is controlled. The pressure of the pressure reducer 2 is adjusted to keep the flow rate on both sides the same, and to set a reasonable and faster flow rate, thereby ensuring that the pressure on both sides is the same when nitrogen is filled at the same time, and the liquid levels of the oxygen separator 6 and the hydrogen separator 8 are roughly equal, so that the mixing of hydrogen and oxygen does not occur. The nitrogen enters the oxygen separator 6 and the hydrogen separator 8 through the pipeline 5. When the internal pressure of the oxygen separator 6 and the hydrogen separator 8 reaches a given value B, the regulating valve group 12 of the oxygen separator 6 and the hydrogen separator 8 is opened, so that the internal air is discharged from the regulating valve group 12. When the internal pressure of the oxygen separator 6 and the hydrogen separator 8 reaches a given value C, (3) the regulating valve group 12 is closed, so that the internal air of the oxygen separator 6 and the hydrogen separator 8 can be replaced. The above operation is automatically repeated three times to complete the nitrogen filling and replacement process.
[0022] Specifically, the oxygen separator 6 and the hydrogen separator 8 are both arranged behind the electrolytic cell 11 , the oxygen separator 6 and the hydrogen separator 8 are hollow inside, and the bottoms of the oxygen separator 6 and the hydrogen separator 8 are connected to the gas alkali outlet of the electrolytic cell 11 .
[0023] A plurality of plates are arranged inside the electrolytic cell 11, one side of the plate of the electrolytic cell 11 is an anode, and the other side of the plate of the electrolytic cell 11 is a cathode. The oxygen separator 6 is arranged behind the outlet where the anodes are collected, and the hydrogen separator 8 is arranged behind the outlet where the cathodes are collected.
[0024] The electrolytic cell 11 is filled with alkaline liquid 10 .
[0025] A connecting pipe 9 is fixedly connected between the bottom of the oxygen separator 6 and the bottom of the hydrogen separator 8 .
[0026] The left side of the oxygen separator 6 is fixedly connected with a regulating valve group 12 , and the right side of the hydrogen separator 8 is fixedly connected with a regulating valve group 12 .
[0027] The working principle and use process of the present invention are as follows: by setting two pressure reducers 2, two solenoid valves 3 and two flow meters 4, when in use, only a remote signal is needed to control the opening of the automatic nitrogen filling valve, so that nitrogen enters the device from the nitrogen inlet 7. After the system pressure reaches the set value A, the automatic nitrogen filling valve is closed, and the flow rates on both sides can be adjusted by the throttling device (pressure reducer 2, etc.). During debugging, the throttling device (pressure reducer 2, etc.) can be adjusted by the flow meter 4 to make the flow rates on both sides equal, thereby ensuring that the liquid level difference in the oxygen separator 6 and the hydrogen separator 8 is maintained within a suitable range to avoid mixing of oxygen and hydrogen. At the same time, there is no need to deliberately slow down the speed of nitrogen entry, so that the replacement speed can be guaranteed. In addition, the device can be remotely and automatically controlled without on-site operation, and the nitrogen filling and replacement operation can be automatically completed with one key, thereby improving the degree of automation of the equipment and reducing the risks caused by human misoperation.
[0028] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions only describe the principles of the present invention. The present invention may be subject to various changes and improvements without departing from the spirit and scope of the present invention. These changes and improvements fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.
Claims
1. A water electrolysis hydrogen production automatic nitrogen filling and replacement device, comprising a series of connecting ports, including a nitrogen inlet (7) and a pipeline (5), wherein the nitrogen inlet (7) is connected to a check valve (1) through the pipeline (5), the check valve (1) is connected to two flow meters (4) through the pipeline (5), the pipeline (5) connecting the check valve (1) and the flow meter (4) is bifurcated into two paths, the flow meter (4) is connected to a solenoid valve (3) through the pipeline (5), the solenoid valve (3) is connected to a pressure reducer (2) through the pipeline (5), the pressure reducer (2) on the left side is connected to an oxygen separator (6) through the pipeline (5), and the pressure reducer (2) on the right side is connected to a hydrogen separator (8) through the pipeline (5), and the hydrogen separator (8) and the oxygen separator (6) are both filled with alkaline liquid (10) at the bottom.
2. The automatic nitrogen filling and replacement device for hydrogen production by water electrolysis according to claim 1, characterized in that: The oxygen separator (6) and the hydrogen separator (8) are both arranged behind the electrolytic cell (11); the interiors of the oxygen separator (6) and the hydrogen separator (8) are hollow; the bottoms of the oxygen separator (6) and the hydrogen separator (8) are connected to the gas alkali outlet of the electrolytic cell (11).
3. The automatic nitrogen filling and replacement device for hydrogen production by water electrolysis according to claim 2, characterized in that: A plurality of electrode plates are arranged inside the electrolytic cell (11), one side of the electrode plate of the electrolytic cell (11) is an anode, and the other side of the electrode plate of the electrolytic cell (11) is a cathode. The oxygen separator (6) is arranged behind the outlet where the anodes are collected, and the hydrogen separator (8) is arranged behind the outlet where the cathodes are collected.
4. The automatic nitrogen filling and replacement device for hydrogen production by water electrolysis according to claim 3 is characterized by: The electrolytic cell (11) is filled with alkaline liquid (10).
5. The automatic nitrogen filling and replacement device for hydrogen production by water electrolysis according to claim 1, characterized in that: A connecting pipe (9) is fixedly connected between the bottoms of the oxygen separator (6) and the hydrogen separator (8).
6. The automatic nitrogen filling and replacement device for hydrogen production by water electrolysis according to claim 1, characterized in that: The left side of the oxygen separator (6) is fixedly connected to a regulating valve group (12), and the right side of the hydrogen separator (8) is fixedly connected to a regulating valve group (12).