Construction method of underground diaphragm wall below important pipeline
By dividing the diaphragm wall into three sections and connecting the reinforcing cage with I-beam joints and convex-concave joints, the problem of interference with important pipelines during diaphragm wall construction was solved, and the stability and pouring effect during the construction process were improved.
Patent Information
- Application Number
- CN202411397766.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-09
- Publication Date
- 2024-11-15
AI Technical Summary
During subway construction, when there are important pipelines in the diaphragm wall construction area, the reinforcement cage may interfere with the important pipelines, affecting the construction progress and the normal operation of the pipelines.
The underground diaphragm wall is divided into three sections, namely the first section, the second section, and the third section. The retaining structure is constructed around the important pipelines, and the steel cage is connected by I-beam joints or convex-concave joints. The steel cage is lowered by segmented hoisting and translation, and combined with guide walls and channel steel supports, it is ensured that the steel cage does not interfere with the pipelines.
This effectively prevents damage to important pipelines by the steel reinforcement cage, ensures the stability of pipelines during construction, and improves the pouring effect of the diaphragm wall and the waterproofing performance of the joints.
Smart Images

Figure CN118958271A_ABST
Abstract
Description
Technical Field
[0001] The present application belongs to the technical field of underground continuous wall construction, and in particular, relates to a method for constructing an underground continuous wall below an important pipeline. Background Art
[0002] Most subway construction projects are located in bustling urban areas with complex surrounding environments, constant traffic, and intricate underground pipelines. Once important pipelines of the station, such as military cables, oil pipelines, and power pipelines, are affected and fail to be relocated in time, they will become bottlenecks restricting the progress of station construction.
[0003] When constructing underground space on subway lines, underground continuous walls are usually used to support the foundation pit to meet the needs of foundation pit enclosure and foundation pit waterproofing. When constructing underground continuous walls, if there are important pipelines in the construction area of the underground continuous wall, when the steel cage in the underground continuous wall is lowered, the steel cage and the important pipelines interfere with each other, which will affect the smooth construction of the underground continuous wall.
[0004] Therefore, a construction method for underground continuous wall construction under important pipelines is needed to reduce the impact of underground continuous wall construction on important underground pipelines. Summary of the invention
[0005] The present application provides a method for constructing an underground continuous wall under an important pipeline, which is used to solve the problem that when the underground continuous wall construction area passes through the important pipeline, the construction of the underground continuous wall is likely to affect the normal operation of the important pipeline.
[0006] The present application provides a method for constructing an underground continuous wall under an important pipeline, including the following construction steps:
[0007] S1. Divide the underground continuous wall into sections, with the underground continuous wall below the important pipeline as the first section of the underground continuous wall, the underground continuous wall on one side of the important pipeline as the second section of the underground continuous wall, and the underground continuous wall on the other side of the important pipeline as the third section of the underground continuous wall;
[0008] S2. Manually excavate the earth downwards at the important pipelines until the important pipelines are exposed, and construct enclosure structures around the important pipelines;
[0009] S3. Use trenching machinery to excavate the underground continuous wall to form a trench to be poured;
[0010] S4, lowering the steel cage into the casting trough, first lowering the second or third ground-anchored wall steel cage, then lowering the first ground-anchored wall steel cage, and horizontally moving the first ground-anchored wall steel cage to below the important pipeline, and finally lowering the remaining steel cage;
[0011] S5. Pour concrete for the underground continuous wall to form an underground continuous wall.
[0012] Furthermore, before carrying out the construction of step S2, guide walls are constructed on both sides of the wall to be constructed along the underground continuous wall construction section, and the guide walls are poured downward from the ground surface to below the important pipelines.
[0013] Furthermore, the construction of the enclosure structure includes the following steps:
[0014] S21. Install steel plates at the bottom of important pipelines and use the steel plates as pipeline trays;
[0015] S22. After the installation of the pipe tray is completed, vertical steel plates are installed on both sides of the important pipelines. The vertical steel plates are fully welded to the pipe tray and both ends of the vertical steel plates are tightly pressed against the guide walls on both sides.
[0016] S23. After the vertical steel plates are installed, overlap the channel steels between the guide walls on both sides above the important pipelines, and fix the channel steels to the vertical steel plates by welding.
[0017] Furthermore, when casting the side wall of the guide wall, a steel bar joint is reserved on the side wall of the guide wall located in the important pipeline area. In step S22, when the vertical steel plate is installed, the reserved steel bar joint is welded and fixed to the vertical steel plate.
[0018] Furthermore, an I-beam joint is provided between two adjacent steel cages.
[0019] Furthermore, a concave-convex female-female joint is formed between two adjacent steel cages.
[0020] Furthermore, in step S3, when the width of the important pipeline is less than or equal to 1 meter, a trench grabber is used to excavate the earth below the important pipeline, and an expansion bucket tooth is installed on the trench grabber bucket.
[0021] Furthermore, in step S3, when the width of the important pipeline is greater than 1 meter, the earth near the bottom of the important pipeline is excavated using a long-arm excavator, and the earth in the remaining area is excavated using a trenching machine.
[0022] Furthermore, in step S4, when hoisting the first ground-anchored wall steel cage, a double-machine lifting method is used. The main crane is used to first lower the first ground-anchored wall steel cage from the position on the vacant side of the important pipeline to the bottom of the trench, and then the steel cage is lifted up and down, and slowly approaches the side of the important pipeline; when the steel cage approaches the important pipeline, the auxiliary crane is used to connect the steel cage on the other side of the important pipeline, and the main crane and the auxiliary crane are used to cooperate in translation of the steel cage.
[0023] Furthermore, the gaps formed by the first ground-anchored wall steel cage, the second ground-anchored wall steel cage and the third ground-anchored wall steel cage around the important pipeline are spaced greater than 25 cm from the important pipeline.
[0024] In summary, the present application includes at least one of the following beneficial effects:
[0025] 1. This application re-divides the steel cages around important pipelines into sections and hoists the steel cages in sections, thereby forming gaps in the steel cages around important pipelines. This makes it less likely to cause damage to important pipelines when pouring underground continuous walls. The construction enclosure structure can isolate important pipelines from underground continuous walls, and can monitor the status of important pipelines in real time when pouring underground continuous walls to ensure the stability of important pipelines.
[0026] 2. An I-beam joint or a concave-convex female-female joint is set between two adjacent steel cages to improve the connection effect between the two adjacent steel cages, so that after the underground continuous wall is poured, the pouring effect at the joint is also better, reducing the possibility of water seepage at the wall joints;
[0027] 3. By setting up channel steel and reserving steel bar joints in the guide wall, the enclosure structure around the important pipeline can be stably installed around the important pipeline, and it is not easy to shift when pouring concrete in the underground continuous wall, thereby better protecting the important pipeline. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 It is a plan view of the underground continuous wall of the present application after being divided into sections, in which two adjacent steel cages are connected by an I-beam joint;
[0029] Figure 2 It is a cross-sectional view after the construction of the enclosure structure of this application is completed;
[0030] Figure 3 It is a top view of the enclosure structure of this application after construction is completed;
[0031] Figure 4 It is a top view of the concave-convex female-female joint formed between two adjacent steel cages of the present application.
[0032] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0033] 1. The first ground-anchored wall; 2. The second ground-anchored wall; 3. The third ground-anchored wall; 4. Important pipelines; 5. Guide walls; 6. Pipe trays; 7. Vertical steel plates; 8. Channel steels; 9. Rebar joints; 10. I-beam joints; 11. Underground continuous walls. DETAILED DESCRIPTION
[0034] The following is combined with Figures 1 to 4 This application is described in further detail.
[0035] The present application discloses a method for constructing an underground continuous wall below an important pipeline, including the following construction steps:
[0036] S1. Adjust the ground-connected wall according to the plane position of the important pipeline 4, the burial situation of the important pipeline 4 and the size of the important pipeline 4. Generally speaking, the width of the wall-type straight-line slot section should not be greater than 6m, and the sum of the widths of the limbs of the T-shaped and zigzag slot sections should not be greater than 6m. Before construction, the relative position of the important pipeline 4 and the ground-connected wall and the width of the slotting machine grab should be analyzed, and the ground-connected wall should be reserved. Generally, at least 2 ground-connected walls are reserved for construction at the same time. After re-division, the original 2 ground-connected walls are adjusted to 3 ground-connected walls. The width of a single wall should be greater than the width of the slotting machine grab, and less than 6m.
[0037] Specifically, in the embodiment of the present application, the underground continuous wall below the important pipeline 4 is used as the first ground-connected wall 1, the underground continuous wall on one side of the important pipeline 4 is used as the second ground-connected wall 2, and the underground continuous wall on the other side of the important pipeline 4 is used as the third ground-connected wall 3, so as to better explain the design ideas of the construction method of the present application in the following.
[0038] When processing the steel cage in each ground-connected wall, a gap in the steel cage should be reserved according to the position of the important pipeline 4, that is, after the three steel cages are spliced and installed around the important pipeline 4, a gap is formed around the important pipeline 4. The size of the gap is: width of important pipeline 4 + 50cm × bottom depth of important pipeline 4 + 25cm × height of steel cage. Enlarging the gap compared to the cross-sectional area of important pipeline 4 can facilitate the normal translation of the steel cage into place without being hindered by important pipeline 4.
[0039] S2. After the ground-connected wall is divided into sections, the guide wall 5 of the underground continuous wall is constructed. The guide wall 5 is constructed on both sides of the wall to be constructed along the construction section of the underground continuous wall. The guide wall 5 is poured from the surface to the bottom of the important pipeline 4. When constructing the guide wall 5, manual excavation is used; after the trench excavation of the guide wall 5 is completed, the steel bars are quickly tied and concrete is poured. During the pouring process, it is strictly forbidden to tilt the concrete above the important pipeline, and the shovel is used to shovel the concrete near the important pipeline 4.
[0040] When tying the steel bars in the guide wall 5, steel bar joints 9 should be pre-embedded vertically in the guide wall 5 on both sides of the important pipeline 4, and the steel bar joints 9 need to be welded and fixed to the enclosure structure in the subsequent steps.
[0041] After the guide wall 5 is constructed, earth is excavated manually downward at the important pipeline 4 until the important pipeline 4 is exposed, and a retaining structure is constructed around the important pipeline 4. Figure 3 and Figure 4 , the construction of the enclosure structure includes the following construction steps:
[0042] Step 1: After the concrete strength of the guide wall 5 reaches the design requirement, a steel plate is installed at the bottom of the important pipeline 4 and used as a pipeline tray 6.
[0043] Step 2. After the pipe tray 6 is installed, vertical steel plates 7 are installed on both sides of the important pipeline 4. The vertical steel plates 7 and the pipe tray 6 are fully welded and fixed, and both ends of the vertical steel plates 7 are pressed against the guide walls 5 on both sides. The welds between the vertical steel plates 7 and the pipe tray 6 are required to be welded throughout the length, with a weld width of 8 mm and a height of 3 mm. When installing the vertical steel plates 7, weld the vertical steel plates 7 to the embedded steel bar joints 9 extending out of the guide walls 5 to enhance the installation firmness of the enclosure structure.
[0044] Step 3: After the vertical steel plate 7 is installed, overlap the channel steel 8 between the guide walls 5 on both sides above the important pipeline 4, and the channel steel 8 is tightly attached to the vertical steel plate 7 and fully welded. The channel steel 8 can support the retaining structure and reduce the possibility of the retaining structure falling down after the excavation of the earth in the underground continuous wall. In addition, the arrangement of the channel steel 8 and the retaining structure can fully enclose the important pipeline 4. When pouring the concrete in the underground continuous wall, the construction workers can observe the situation of the important pipeline 4 from the ground between the two vertical steel plates 7, so that when the underground continuous wall is poured, the important pipeline 4 can be adjusted and maintained in time if there is any problem.
[0045] S3. After the construction of the retaining structure is completed, trenching machinery is used to excavate the underground continuous wall casting area to form a trench to be cast.
[0046] During the trenching process, the soil below the important pipeline 4 is generally difficult to grab. When the pipeline width is ≤1 meter, the trenching machine tool holder height is 10m, which includes the grab bucket. The expansion bucket teeth are installed on the grab bucket to complete the soil grabbing from 10m below the important pipeline 4 to the bottom of the trench. When grabbing the trench, slowly lower the grab bucket. According to the height and width of the grab bucket measured in advance, lower the entire tool holder below the pipeline, and then slowly move it horizontally toward the pipeline to grab the soil below the important pipeline 4. During the translation of the tool holder, ensure that the top of the tool holder is below the important pipeline 4 and the steel rope on the tool holder does not touch the important pipeline 4.
[0047] When the width of the important pipeline 4 is greater than 1 meter, it is difficult to grab all the soil under the important pipeline 4 without affecting the important pipeline 4 using only a trenching machine. At this time, a long-arm excavator can be used in conjunction with a trenching machine to carry out soil grabbing construction of the underground continuous wall.
[0048] For the soil grabbing construction from 10m below the important pipeline 4 to the bottom of the trench, the specific construction steps include:
[0049] First, a steel wire rope is passed under the important pipeline 4 and connected to the tool holder of the trench grab machine, and the other end is fixed on the excavator bucket; secondly, the grab bucket is lowered, and the excavator simultaneously lowers the steel wire rope and pulls the steel wire rope to adjust the grab bucket to stop on the excavation surface below the pipeline; then the trench grab machine grabs the soil; finally, the excavator relaxes the steel wire rope, lifts the grab bucket, and dumps the soil into the dump truck, and repeats the cycle of excavating to the designed elevation.
[0050] A long-arm excavator is used to excavate the earth between 0m and 10m below the pipeline. Before construction, a bucket with the same width as the ground-anchored wall needs to be configured. During the excavation of the earth by the long-arm excavator, a dedicated person will direct on one side. The long-arm excavator rides on top of the trench, and the mud in the trench is 500mm below the important pipeline 4, which makes it easy to observe the height of the excavator bucket and prevent it from touching the pipeline.
[0051] S4. After the excavation of the casting trough is completed, the steel cage is lowered into the casting trough. The steel cage of the second ground-connected wall 2 or the third ground-connected wall 3 is lowered first, and then the steel cage of the first ground-connected wall 1 is lowered, and the steel cage of the first ground-connected wall 1 is horizontally moved to the bottom of the important pipeline 4, and finally the remaining steel cage is lowered. For the convenience of explanation, one embodiment is used as an example. It should be noted that this application Figure 1 The shapes of the second ground-connected wall 2 steel cage and the third ground-connected wall 3 steel cage are only for reference. Figure 1 For the middle steel cage shape, the second ground-connected wall 2 steel cage needs to be lowered first, then the first ground-connected wall 1 steel cage, and finally the third ground-connected wall 3 steel cage.
[0052] The joints of the underground continuous wall reinforcement cages adopt flexible I-beam joints. Specifically, when the second ground-connected wall 2 reinforcement cage is lowered, an I-beam joint 10 is welded on one side of the second ground-connected wall 2 reinforcement cage, and the end of the second ground-connected wall 2 is inserted between the upper and lower flange plates of the I-beam joint 10 and welded and fixed to the web of the I-beam joint 10; when the first ground-connected wall 1 reinforcement cage is lowered, the I-beam joint 10 is welded and fixed on one side of the first ground-connected wall 1 reinforcement cage, and the side without the I-beam joint 10 is inserted into the I-beam joint 10 on the second ground-connected wall 2 reinforcement cage, thereby realizing the connection between the first ground-connected wall 1 and the second ground-connected wall 2 reinforcement cages; when the third ground-connected wall 3 reinforcement cage is lowered, one end of the third ground-connected wall 3 reinforcement cage is inserted into the I-beam joint 10 fixed on the first ground-connected wall 1 reinforcement cage.
[0053] When the adjusted dividing line conflicts with the shield tunnel portal and the I-beam flexible joint cannot be used, the steel cage female joint can be used, that is, steel bars of the same type as the steel cage distribution bars are bent into concave and convex shapes with socket functions, and the steel frame height is the same.
[0054] By setting flexible I-beam joints or concave-convex mother-and-child joints, the connection stability between two adjacent steel cages can be improved. The use of concave-convex mother-and-child joints can further save the use of steel plates and save resources.
[0055] First, after the installation and placement of the second ground-connected wall 2 steel cage is completed, the first ground-connected wall 1 steel cage is hoisted and lowered. The first ground-connected wall 1 steel cage is lifted by two machines. When lowering, the main crane is used to first lower the first ground-connected wall 1 steel cage from the installation position of the third ground-connected wall 3 steel cage to the bottom of the groove, and then lift and lower the first ground-connected wall 1 steel cage, and slowly drive the first ground-connected wall 1 steel cage to the side of the important pipeline 4. The lifting height is controlled within 500mm. During the translation process of the first ground-connected wall 1 steel cage, the speed is slow, and the translation speed needs to be controlled within 2cm / min. It is strictly forbidden to use the main crane to pull obliquely.
[0056] When the first ground-connected wall 1 steel cage is close to the important pipeline 4, the auxiliary crane is used to connect the first ground-connected wall 1 steel cage on the other side of the important pipeline 4, and the main crane and auxiliary crane are used to move the steel cage together. After the first ground-connected wall 1 steel cage is moved to the right position, the third ground-connected wall 3 steel bars are hoisted to the designed position, thereby completing the hoisting of the steel cage in the underground continuous wall.
[0057] S5. After the steel cage is installed, pour the concrete of the underground continuous wall to form the underground continuous wall.
[0058] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A method for constructing underground continuous walls under important pipelines. It is characterized in that The construction steps include: S1. Divide the underground continuous wall (11) into sections, wherein the underground continuous wall (11) below the important pipeline (4) is used as the first section of the underground continuous wall (1), the underground continuous wall (11) on one side of the important pipeline (4) is used as the second section of the underground continuous wall (2), and the underground continuous wall (11) on the other side of the important pipeline (4) is used as the third section of the underground continuous wall (3); S2. Manually excavate earth downward at the important pipeline (4) until the important pipeline (4) is exposed, and construct a retaining structure around the important pipeline (4); S3, using a trenching machine to excavate the underground continuous wall (11) to form a trench to be poured; S4, lowering the steel cage into the casting trough, first lowering the steel cage of the second ground-anchored wall (2) or the third ground-anchored wall (3), then lowering the steel cage of the first ground-anchored wall (1), and horizontally moving the steel cage of the first ground-anchored wall (1) to below the important pipeline (4), and finally lowering the remaining steel cage; S5, pouring concrete for the underground continuous wall (11) to form the underground continuous wall (11).
2. A method for constructing an underground continuous wall under an important pipeline according to claim 1, It is characterized in that Before the construction of step S2 is carried out, guide walls (5) are constructed on both sides of the wall to be constructed along the construction section of the underground continuous wall (11), and the guide walls (5) are poured from the ground surface downward to below the important pipeline (4).
3. The underground continuous wall construction method under an important pipeline according to claim 1, It is characterized in that The construction of the enclosure structure includes the following steps: S21, installing a steel plate at the bottom of the important pipeline (4), and using the steel plate as a pipeline tray (6); S22. After the pipe tray (6) is installed, vertical steel plates (7) are respectively installed on both sides of the important pipeline (4). The vertical steel plates (7) and the pipe tray (6) are fully welded and fixed, and both ends of the vertical steel plates (7) are tightly pressed against the guide walls (5) on both sides. S23. After the vertical steel plate (7) is installed, the channel steel (8) is overlapped between the guide walls (5) on both sides above the important pipeline (4), and the channel steel (8) is welded and fixed to the vertical steel plate (7).
4. A method for constructing an underground continuous wall under an important pipeline according to claim 3, It is characterized in that When the side wall of the guide wall (5) is cast, a steel bar joint (9) is reserved on the side wall of the guide wall (5) located in the area of the important pipeline (4). In step S22, when the vertical steel plate (7) is installed, the reserved steel bar joint (9) is welded and fixed to the vertical steel plate (7).
5. The underground continuous wall construction method under an important pipeline according to claim 1, It is characterized in that An I-beam joint (10) is provided between two adjacent steel cages.
6. The method for constructing an underground continuous wall under an important pipeline according to claim 1, It is characterized in that A concave-convex female-female joint is formed between two adjacent steel cages.
7. The method for constructing an underground continuous wall under an important pipeline according to claim 1, It is characterized in that In step S3, when the width of the important pipeline (4) is not greater than 1 meter, a trench grabbing machine is used to excavate the earth below the important pipeline (4), and an expansion bucket tooth is installed on the trench grabbing machine bucket.
8. The method for constructing an underground continuous wall below an important pipeline according to claim 1, It is characterized in that In step S3, when the width of the important pipeline (4) is greater than 1 meter, the earth near the bottom of the important pipeline (4) is excavated using a long-arm excavator, and the earth in the remaining area is excavated using a trenching machine.
9. The method for constructing an underground continuous wall below an important pipeline according to claim 1, It is characterized in that In step S4, when the steel cage of the first ground-connected wall (1) is hoisted, a double crane is used. The main crane is used to first lower the steel cage of the first ground-connected wall (1) from the position on the spare side of the important pipeline (4) to the bottom of the trench, and then the steel cage is lifted up and down and slowly approaches the important pipeline (4). When the steel cage of the first ground-connected wall (1) approaches the important pipeline (4), the auxiliary crane is used to connect the steel cage of the first ground-connected wall (1) on the other side of the important pipeline (4), and the main crane and the auxiliary crane are used to cooperate to translate the steel cage of the first ground-connected wall (1).
10. A method for constructing an underground continuous wall under an important pipeline according to claim 9, It is characterized in that The gaps formed by the steel cages of the first ground-connected wall (1), the second ground-connected wall (2) and the third ground-connected wall (3) on the sides of the important pipeline (4) are spaced greater than 25 cm from the important pipeline (4).