Grouting nail for ground anchor construction and using method thereof

By designing grouting nails with admixture balls and check valves, the problems of single function and poor economy of grouting nails are solved. It realizes accurate measurement and adjustment of grout flow, improves grouting uniformity and ground anchor firmness, and has good economy and practicality.

CN118958298APending Publication Date: 2024-11-15CHINA THREE GORGES PROJECTS DEV CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411036811.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-31
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

Existing grouting nails have a single function, cannot measure the amount of grout injected, cannot add admixtures to the grout for adjustment, cannot prevent grout backflow, the main body of the grouting nail cannot be reused, resulting in poor economic efficiency. The grout curing speed is uneven, and the fluidity is reduced, resulting in poor grouting uniformity, which affects the firmness and stability of the ground anchor. Furthermore, the rapid setting, early strength, excessive viscosity, and excessive thinness of the grout make it inconvenient for long-distance transportation.

Method used

A grouting nail for ground anchor construction was designed, including a nail body and a nail head. The nail body has a first grouting channel, and the nail head has a second grouting channel, which are connected. An admixture ball is added into the first grouting channel. The nail head is equipped with a check valve and a flow meter. A contact induction sensor is connected through a signal line to realize the automatic statistics and transmission of grout flow. The nail body and nail head are designed separately for reuse.

Benefits of technology

It enables precise measurement and adjustment of grout flow, avoids grout leakage, improves grouting uniformity, enhances the stability of ground anchors, and improves the economy and practicality of grouting nails, making it suitable for long-distance transportation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958298A_ABST
    Figure CN118958298A_ABST
Patent Text Reader

Abstract

The invention provides a grouting nail for ground anchor construction and a using method thereof. The grouting nail comprises a nail body and a nail cap, a first grouting channel is formed in the nail body, a second grouting channel is formed in the nail cap, the second grouting channel is communicated with the first grouting channel, an additive ball is arranged on the first grouting channel, a necking is arranged on the first grouting channel, and the additive ball is clamped at one end of the necking. In the process that slurry extrudes the admixture ball, as the necking part is designed to be of a sharp structure, the ball shell is easily punctured, and liquid in the admixture ball is rapidly mixed with the slurry under the condition that the slurry flows at a high speed. The top cap and the nail body are connected in a separated and threaded mode, and the top cap is further provided with a flow meter and a signal receiving and transmitting device. And the whole design has strong novelty and practicability. The whole device avoids the phenomenon that the firmness and stability of the ground anchor are affected due to the fact that the solidification speed of grout is not uniform, the liquidity is reduced, injection holes are difficult to fill, the grouting uniformity is poor, and even grouting is insufficient. And the method has a relatively high popularization value.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of ground anchor construction, in particular to a grouting nail for ground anchor construction and a use method thereof. Background Art

[0002] Grouting nails are an important component of slurry pouring construction. They are usually made of steel. The function of grouting nails is to pour slurry into the gaps of rocks or concrete to ensure the adhesion between rocks or the filling of concrete gaps to achieve higher overall strength. During the construction of ground anchors, grouting nails need to be drilled into the rock formation or concrete first, and then the slurry is injected through the grouting pipe to fill the gaps of the rock or concrete with slurry to form a solid system that is tightly bonded to the formation. During the grouting process of grouting nails, there is generally no admixture in the slurry to adjust the slurry. The curing speed of the slurry may be uneven, the viscosity of the slurry is enhanced, and the fluidity is reduced. It is more difficult to completely and effectively fill the gaps, so that the established effect cannot be achieved well. However, adding it directly to the slurry in advance will cause the slurry to set quickly, early strength, over-viscosity, too thinness, and other situations that are not convenient for long-distance transportation. The general grouting nails also have the situation that it is difficult to accurately measure the grouting amount of a single nail. For this reason, we propose a new type of grouting nail to solve the above problems. Summary of the invention

[0003] The present invention provides a grouting nail for ground anchor construction and a method of using the same, which solves the problems that the grouting nail has a single function, cannot measure the slurry injection amount, cannot add admixtures to the slurry for adjustment, cannot avoid grouting, the grouting nail body cannot be reused, and has poor economy. The solidification speed of the slurry may be uneven, the grouting liquid property is enhanced, the fluidity is reduced, and it is difficult to fill the injection hole, resulting in poor grouting uniformity, and may even lead to insufficient grouting, affecting the firmness and stability of the ground anchor. However, adding it directly to the slurry in advance will cause the slurry to set quickly, strengthen early, be too sticky, be too thin, and other problems that are not convenient for long-distance transportation. By innovatively enriching the relevant functions, the practicality and economy of the grouting nail are greatly improved.

[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is: a grouting nail for ground anchor construction and a method of using the same, comprising a nail body and a nail cap, the nail body is provided with a first grouting channel, the nail cap is provided with a second grouting channel, the second grouting channel is connected to the first grouting channel, an admixture ball is added to the first grouting channel, a neck is provided on the first grouting channel, and the admixture ball is stuck at one end of the neck.

[0005] In the preferred embodiment, a check valve and a flow meter are provided on the nail cap, the flow meter is located in the second grouting channel, and one end of the check valve passes through the cross section of the second grouting channel.

[0006] In a preferred embodiment, the check valve comprises a cover, a sleeve is provided on the cover, a sliding check rod is provided on the sleeve, a second sealing ring is provided at the outer end of the sleeve, and a spring is provided between the check rod and the cover.

[0007] In the preferred embodiment, a pointed cone surface is provided at the end of the check rod facing the grouting cover surface, the pointed cone surface is an inclined slope surface, and the cover is installed on the inner wall of the nail cap.

[0008] In a preferred embodiment, a plurality of grouting ports are provided on the first grouting channel, the plurality of grouting ports are connected to the first grouting channel, and the cross-sectional area of ​​the necking is reduced on the side close to the nail body.

[0009] The contact portion between the first grouting channel and the admixture ball is provided with a pointed end.

[0010] In a preferred embodiment, the nail cap includes a cover body, a hollow connecting tube is provided at one end of the cover body, an external thread is provided on the connecting tube, a plurality of inner sealing rings are provided outside the external thread, and a plurality of sealing rings are provided outside the cover body.

[0011] In the preferred embodiment, the nail cap is threadedly connected to the nail body, a grouting cover is provided at one end of the nail cap, a contact sensing sensor is provided on the grouting cover, a grouting pipe is provided on one side of the grouting cover, and the grouting pipe is connected to the nail cap.

[0012] In the preferred embodiment, a contact sensing sensor is provided on one side of the grouting cover. The contact sensing sensor is a ring structure. The contact sensing sensor is connected to the signal contact of the flow meter through a signal line. The line-connected flow meter is a rotary capacity counting type flow meter.

[0013] In a preferred embodiment, additives are arranged inside the admixture ball, and the additives are accelerating agent, early strength agent, adhesive, cement or water, and the admixture ball contains one or more additives.

[0014] A method for using a grouting nail for ground anchor construction, the method comprising: S1, reasonably setting a plurality of grouting locations according to engineering needs, reasonably determining the number of holes punched at each grouting location according to the grouting amount and the area of ​​the grouting location, and the diameter of the grouting nail hole being slightly larger than the diameter of the grouting nail body; S2. Use a removable plug to temporarily seal the grouting nail hole. Before installation and use, remove the temporary plug according to the needs of the site and then use it. Do not remove the plug of the unused grouting nail hole. The plug that is not removed is used to prevent leakage during grouting; S3, nailing the grouting nail hole: manually drive the nailing machine to align the grouting nail with the hole to be installed, and quickly push the piston plunger out with air pressure or water pressure to quickly push the grouting nail into the grouting nail hole; S4. Adding a suitable type of additive to the admixture ball. The additive may be an accelerating agent, an early strength agent, an adhesive, cement or water. One or more of the above additives are added to the admixture ball. The admixture ball may also be a standardized product pre-packaged with the corresponding additives. S5, open the nail cap on the nail body, put the admixture ball into the nail body, tighten the nail body and the nail cap, so that the inner sealing ring is tightly against the nail body 1, so that after the nail body and the nail cap are screwed together, the inner sealing ring is tightly against the nail body 1 to play a sealing effect, thereby preventing the high-pressure slurry from leaking into the spiral thread mouth, and at the same time, the sealing ring 7 is against the hole wall of the grouting nail hole to prevent the slurry from leaking from the gap between the grouting nail and the grouting nail hole; S6. The grouting machine is driven to inject grout into the nail body through the grouting pipe. The flow meter can count the total amount of slurry injected by a single grouting nail during the grouting process. After summarizing and analyzing the slurry information of all grouting nails, the matching situation between the pull-out force of the entire anchor device and the design value is calculated. If there is a difference, additional grouting is performed; S7. After the grouting is completed, the nail cap is removed by grouting equipment or manually, and the nail cap is reused; S8. Repeat steps S2 to S7 until all grouting locations are grouted.

[0015] The beneficial effects of the present invention are as follows: the nail body connecting tube is provided with a nail body inner sealing ring, and a nail cap sealing ring is arranged at a corresponding appropriate position inside the nail cap section, so that after the nail body and the nail cap are screwed together and tightly attached, an ideal sealing effect is achieved, thereby preventing high-pressure slurry from leaking into the spiral thread opening of the connecting tube, causing the nail cap to be unable to be reused.

[0016] A flow meter is also embedded in the grouting channel of the nail cap. The flow meter is preferably a rotary volume counting type flow meter. The flow information is transmitted to the signal contact through the signal line, and the flow information of the grouting nail injection slurry can be automatically counted and transmitted. While the grouting equipment is grouting, the grouting port of the grouting equipment is in close contact with the grouting cover. In addition to preventing grout leakage during the grouting process, the grouting nail can also receive the slurry flow information of the grouting nail through the contact between the corresponding contact ring on the grouting port of the grouting equipment and the contact induction sensor on the grouting nail.

[0017] A check valve is provided at the front end of the grouting channel. Since a sealing ring is fixedly arranged at the tail of the grouting nail, when the grouting nail is squeezed into the gap of the grouting nail hole, a part of the sealing ring is also squeezed into the gap between the grouting nail and the grouting nail hole. This not only fixes the grouting nail, but also fills the gap to avoid leakage during the subsequent grouting process.

[0018] During the nailing operation, during the grouting design process of the grouting part, through standardized design, according to the anchoring force to be achieved, a number of grouting nail holes with a hole diameter matching the nail diameter are set at the grouting part. The grouting nail holes are slightly larger than the diameter of the grouting nail rod so that the grouting nail can be smoothly penetrated into place. The grouting holes are temporarily blocked with detachable plugs. Before installation and use, the temporary plugs are removed according to the needs of the site and the grouting nails are installed. The unused temporary plugs are used to prevent leakage during grouting. The operator drives the nailing grouting machine to align the nailing device with the hole where the grouting nail is to be installed. The air pressure or hydraulic pressure quickly pushes the piston punch out to quickly push the grouting nail into the grouting nail hole.

[0019] The slurry passes through the second grouting channel and the first grouting channel, and is ejected from the grouting port, bonding the grouting nails to the surrounding rock surface and gaps, thereby forming a larger overall joint force. When the grouting stops, the check valve returns to its position under the action of the spring, closing the grouting channel. Because the check valve has a sloped surface on one side and a cylindrical surface on the other side, the sloped surface will decompose the pressure into lateral pressure under the action of the slurry pressure, pushing the check valve and spring to compress, thereby opening the check valve and forming a grouting channel. However, the back of the check rod is a cylindrical surface. If the slurry flows from the back to the top cap, it will not be able to form a lateral force under the action of the slurry pressure, and the check valve will not be able to be pushed open.

[0020] The flowmeter can count the total amount of slurry injected by a single grouting nail during the grouting process. After the flow rate is calculated through the technical structure attached to the flowmeter, the flow information is transmitted after the top cap signal contact contacts the corresponding signal contact ring on the grouting cover. The purpose of setting a contact sensing sensor on the grouting cover is to ensure normal contact and signal transmission between the signal contact ring and the grouting cover on the nail cap no matter to which angle the grouting cover is rotated. After summarizing and analyzing the slurry information of all grouting nails, the matching of the pull-out resistance of the entire anchor device with the design value is calculated, and supplementary grouting is performed when there is a difference.

[0021] The purpose of the separate design of the nail body and the top cap is that after the grouting is completed, the nail cap can be removed and reused through grouting equipment or manually, because the main structure and equipment of the grouting nail are mostly concentrated on the nail cap, which effectively improves the economy. The sealing ring of the nail body and the sealing ring of the nail cap have a good protective effect on the thread of the nail cap, which facilitates the repeated recycling of the nail cap and accessories, and has good economy and great promotion value. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] The present invention will be further described below in conjunction with the accompanying drawings and embodiments; Figure 1 is a cross-sectional view of the overall structure of the present invention; Figure 2 is a cross-sectional schematic diagram of a nail cap of the present invention; Figure 3is a side view of a nail cap of the present invention; Figure 4 It is a structural schematic diagram of the check valve of the present invention; Figure 5 is a front view of the check valve of the present invention; In the figure: nail body 1; nail cap 2; external thread 201; inner sealing ring 202; cover body 203, connecting pipe 204; check valve 3; sealing cover 301; sleeve 302; check rod 303; spring 304; pointed cone surface 305; second sealing ring 306; first grouting channel 4; necking 401; tip 402; grouting port 5; additive ball 6; sealing ring 7; grouting cover 8; flow meter 9; contact sensing sensor 10; second grouting channel 11; signal line 12; grouting pipe 13. DETAILED DESCRIPTION

[0023] The technical solution of the present invention will be further described below in conjunction with the accompanying drawings.

[0024] Embodiment 1: like Figure 1-5 In the invention, a grouting nail for ground anchor construction includes a nail body 1 and a nail cap 2. The nail body 1 is provided with a first grouting channel 4, and the nail cap 2 is provided with a second grouting channel 11. The second grouting channel 11 is connected with the first grouting channel 4. An admixture ball 6 is added in the first grouting channel 4. The first grouting channel 4 is provided with a necking 401, and the admixture ball 6 is stuck at one end of the necking 401. According to this structure, the nail body connecting tube 204 is provided with an inner sealing ring 202 of the nail body, and a sealing ring 7 of the nail cap is arranged at a corresponding appropriate position on the outer side of the nail cap 2. So that the nail body 1 and the nail cap 2 can be tightly sealed after being screwed together, so as to prevent the high-pressure slurry from leaking into the spiral thread of the connecting tube 204, resulting in the nail cap 2 being unable to be reused.

[0025] A flow meter 9 is also embedded and installed in the grouting channel of the nail cap 2. The flow meter 9 is preferably a rotary volume counting type flow meter, which transmits the flow information to the signal contact through the signal line, and can automatically count and transmit the flow information of the grouting nail injection slurry. While the grouting equipment is grouting, the grouting cover 8 of the grouting equipment can not only grout the grouting channel, but also the contact ring on the grouting head of the corresponding grouting equipment contacts the contact induction sensor 10 on the grouting nail to receive the slurry flow information of the grouting nail.

[0026] A check valve 3 is provided at the front end of the grouting channel. Since a sealing ring 7 is fixedly arranged at the tail end of the grouting nail, when the grouting nail is squeezed into the gap of the grouting nail hole, a part of the sealing ring is also squeezed into the gap between the grouting nail and the grouting nail hole. This not only fixes the grouting nail, but also fills the gap to avoid leakage during the subsequent grouting process.

[0027] During the nailing operation, during the grouting design process of the grouting part, through standardized design, according to the anchoring force to be achieved, a number of grouting nail holes with a hole diameter matching the diameter of the nail are set at the grouting part. The grouting nail holes are slightly larger than the diameter of the grouting nail rod so that the grouting nail can be smoothly penetrated into place. The grouting holes are temporarily blocked with detachable plugs. Before installation and use, the temporary plugs are removed according to the needs of the site and the grouting nails are installed. The unused temporary plugs are used to prevent leakage during grouting. The operator drives the nailing grouting machine to align the nailing device with the hole where the grouting nail is to be installed. The air pressure or hydraulic pressure quickly pushes the piston punch out to quickly push the grouting nail into the grouting nail hole.

[0028] The slurry passes through the first grouting channel 4 and the second grouting channel 11, and is ejected from the grouting port, bonding the grouting nails to the surrounding rock surface and gaps, thereby forming a larger overall joint force. When the grouting stops, the check valve 3 returns to its position under the action of the spring 304, and the grouting channel is closed. Because the check valve 3 has a sloped surface on one side and a cylindrical surface on the other side, the sloped surface will decompose the pressure into lateral pressure under the action of the slurry pressure, pushing the check valve 3 and the spring 304 to compress, thereby opening the check valve 3 and forming a grouting channel. However, the back of the check rod 303 is a cylindrical surface. If the slurry flows from the back to the top cap, it will not be able to form a lateral force under the action of the slurry pressure, and the check valve 3 will not be pushed open.

[0029] The flow meter 9 can count the total amount of slurry injected by a single grouting nail during the grouting process. After the flow rate is calculated through the technical structure attached to the flow meter, the flow information is transmitted after the signal contact of the top cap 2 contacts the corresponding signal contact ring on the grouting cover. The purpose of setting the contact sensing sensor 10 on the grouting cover 8 is to ensure normal contact and signal transmission between the signal contact ring and the grouting cover 8 on the top cap 2 no matter to which angle the grouting cover 8 is rotated. After summarizing and analyzing the slurry information of all grouting nails, the matching of the pull-out resistance of the entire anchor device with the design value is calculated, and supplementary grouting is performed when a difference occurs.

[0030] The purpose of the separate design of the nail body 1 and the top cap 2 is that after the grouting is completed, the nail cap 2 can be removed and reused by grouting equipment or manually, because the main structure and equipment of the grouting nail are concentrated on the nail cap 2, which effectively improves the economy. The sealing ring of the nail body and the sealing ring of the nail cap 2 have a good protective effect on the nail cap thread, which facilitates the reuse of the nail cap 2.

[0031] The nail body 1 is a pointed cylindrical structure, with a nail cap 2 and a sealing ring 7 arranged at the tail, and a grouting channel is arranged inside the grouting nail 9 along the length direction. The spring 304 and the check rod 303 are enclosed in the cavity of the check valve 3 by a detachable, threaded nail cap 2. In the non-grouting state of the check valve 3, the spring 304 pushes the check rod 303 into the grouting channel to close the grouting channel. The check rod 303 is arranged in the form of a sloped pressure surface toward the second grouting channel 11, but there is no such structure arranged toward the first grouting channel 4.

[0032] The slurry first passes through the flow meter 9 for flow statistics, and then under the action of high pressure, the check valve 3 of the grouting channel is opened by the spring 304. During the process of the slurry passing through the flow channel at high pressure in the flow channel, the large pressure squeezes the admixture ball 6. The admixture ball 6 can be filled with raw materials such as quick setting agent, early strength agent, adhesive, cement, water, etc. in advance as needed. After mixing with the slurry, it plays a role in adjusting the slurry performance. The admixture ball can also be manufactured in a standardized manner. The quick setting agent can make the slurry solidify quickly after being squeezed out of the grouting port 5, the early strength agent can quickly increase the early strength of the slurry, the adhesive can increase the bonding force between the slurry and the rock surface, the cement can adjust the proportion when the water content of the slurry is too high, and the water can dilute the slurry. In the process of the slurry squeezing the admixture ball 6, since the necking 401 part is designed as a relatively sharp structure, the ball shell is easily punctured, and the admixture ball 6 body also adopts a material that melts when it encounters water and pressure. The liquid in the admixture ball 6 is quickly mixed with the slurry under the condition of high flow rate of the slurry. However, if these admixtures are directly added to the slurry in advance, the slurry will be inconvenient for long-distance transportation due to rapid setting, early strength, excessive viscosity, or excessive thinness. The design of the admixture ball 6 is highly novel and practical.

[0033] In the preferred embodiment, the nail cap 2 is provided with a check valve 3 and a flow meter 9, the flow meter 9 is located in the second grouting channel 11, and one end of the check valve 3 passes through the cross section of the second grouting channel 11. With this structure, the slurry first passes through the flow meter 9 for flow statistics, and then under the action of high pressure, the check valve 3 of the grouting channel supported by the spring 304 is opened. During the process of the slurry passing through the flow channel under high pressure in the flow channel, the additive ball 6 is squeezed with a large pressure.

[0034] In the preferred embodiment, the check valve 3 includes a cover 301, a sleeve 302 is provided on the cover 301, a sliding check rod 303 is provided on the sleeve 302, a second sealing ring 306 is provided at the outer end of the sleeve 302, and a spring 304 is provided between the check rod 303 and the cover 301. According to this structure, one side of the check rod 3 is a slope surface, and the other side is a cylindrical surface. The slope surface will decompose the pressure into lateral pressure under the action of slurry pressure, pushing the check rod 303 and the spring 304 to shrink toward the cover 301, thereby opening the check valve 3 and forming a grouting channel. However, the back side is a cylindrical surface, so that the lateral force cannot be formed under the action of slurry pressure, and the check valve 3 cannot be pushed open. The nail cap 2 and the nail body 1 are screwed together to facilitate installation and removal, and are also provided with a sealing gasket to prevent slurry leakage. After the nail cap 2 is removed, the check valve 3 can be installed, removed or repaired.

[0035] In the preferred embodiment, a pointed cone surface 305 is provided on the surface end of the check rod 303 facing the grouting cover 908, and the pointed cone surface 305 is an inclined slope. The cross-sectional shape of the check rod 303 in the second grouting channel 11 perfectly and seamlessly matches the cross-sectional shape of the second grouting channel 11, ensuring that no leakage occurs in the closed state, and can be opened quickly when needed. The sealing cover 301 is installed on the inner wall of the nail cap 2.

[0036] In a preferred embodiment, a plurality of grouting ports 5 are provided on the first grouting channel 4 , and the plurality of grouting ports 5 are connected to the first grouting channel 4 , and the cross-sectional area of ​​the neck 401 close to the nail body 1 is reduced.

[0037] The first grouting channel 4 is provided with a tip 402 at the contact portion with the admixture ball. With this structure, the necking 401 is designed to be a sharper structure, the cross-sectional area of ​​the necking 401 close to the nail body 1 is reduced, the ball shell is easily punctured, the slurry passes through the constricted part because the flow rate is reduced, and the pressure is increased to better ensure the grouting effect, and the admixture ball 6 is also made of a material that melts when it encounters water and pressure, and the liquid in the admixture ball 6 is quickly mixed with the slurry under the condition of high slurry flow rate.

[0038] In the preferred embodiment, the nail cap 2 includes a cover body 203 , a hollow connecting tube 204 is provided at one end of the cover body 203 , an external thread 201 is provided on the connecting tube 204 , a plurality of inner sealing rings 202 are provided outside the external thread 201 , and a plurality of sealing rings 7 are provided outside the cover body 203 .

[0039] In the preferred embodiment, the nail cap 2 is threadedly connected to the nail body 1 , a grouting cover 8 is provided at one end of the nail cap 2 , a contact sensing sensor 10 is provided on the grouting cover 8 , a grouting pipe 13 is provided on one side of the grouting cover 8 , and the grouting pipe 13 is connected to the nail cap 2 .

[0040] In the preferred embodiment, a contact sensing sensor 10 is provided on one side of the grouting cover 8. The contact sensing sensor 10 is a ring structure. The contact sensing sensor 10 is connected to the signal contact of the flow meter 9 via a signal line. The line-connected flow meter 9 is a rotary capacity counting type flow meter.

[0041] In the preferred embodiment, additives are provided inside the admixture ball 6, and the additives are accelerating setting agent, early strength agent, adhesive, cement or water, and the additives contained in the admixture ball 6 are one or more. With this structure, the interior of the admixture ball 6 can be filled with accelerating setting agent, early strength agent, adhesive, cement, water and other raw materials in advance as needed, and after mixing with the slurry, it plays a role in adjusting the performance of the slurry. The accelerating setting agent can make the slurry solidify quickly after being squeezed out of the grouting port 5, the early strength agent can quickly increase the early strength of the slurry, the adhesive can increase the bonding force between the slurry and the rock surface, the cement can adjust the proportion when the water content of the slurry is too high, and the water can dilute the slurry.

[0042] Embodiment 2: Further illustrate with reference to embodiment 1: A method for using a grouting nail for ground anchor construction, the method comprising: S1, reasonably setting a plurality of grouting locations according to engineering needs, reasonably determining the number of holes punched at each grouting location according to the grouting amount and the area of ​​the grouting location, and the diameter of the grouting nail hole being slightly larger than the diameter of the grouting nail body; S2. Use a removable plug to temporarily seal the grouting nail hole. Before installation and use, remove the temporary plug according to the needs of the site and then use it. Do not remove the plug of the unused grouting nail hole. The plug that is not removed is used to prevent leakage during grouting; S3, nailing the grouting nail hole: manually drive the nailing machine to align the grouting nail with the hole to be installed, and quickly push the piston plunger out with air pressure or water pressure to quickly push the grouting nail into the grouting nail hole; S4. Adding a suitable type of additive to the admixture ball. The additive may be an accelerating agent, an early strength agent, an adhesive, cement or water. One or more of the above additives are added to the admixture ball. The admixture ball may also be a standardized product pre-packaged with the corresponding additives. S5, open the nail cap on the nail body, put the admixture ball into the nail body, tighten the nail body and the nail cap, so that the inner sealing ring is tightly against the nail body 1, so that after the nail body and the nail cap are screwed together, the inner sealing ring is tightly against the nail body 1 to play a sealing effect, thereby preventing the high-pressure slurry from leaking into the spiral thread mouth, and at the same time, the sealing ring 7 is against the hole wall of the grouting nail hole to prevent the slurry from leaking from the gap between the grouting nail and the grouting nail hole; S6, driving the grouting machine, which injects grout into the nail body 1 through the grouting pipe 13, and the flow meter 9 can count the total amount of slurry injected by a single grouting nail during the grouting process, and after summarizing and analyzing the slurry information of all grouting nails, calculate the matching situation of the pull-out force of the entire anchor device with the design value, and perform supplementary grouting when there is a difference; S7. After the grouting is completed, the nail cap 2 is removed by the grouting equipment or manually, and the nail cap 2 is reused.

[0043] S8. Repeat steps S2 to S7 until all grouting locations are grouted.

[0044] The above-mentioned embodiments are only preferred technical solutions of the present invention and should not be regarded as limitations of the present invention. The protection scope of the present invention shall be the technical solutions recorded in the claims, including equivalent replacement solutions of the technical features in the technical solutions recorded in the claims. For ordinary technicians in the relevant field, other different forms of changes or modifications can be made on the basis of the above description. It is not necessary and impossible to list all the implementation methods here, that is, equivalent replacement improvements within this scope are also within the protection scope of the present invention.

Claims

1. A grouting nail for ground anchor construction, characterized in that: The nail body (1) comprises a nail cap (2), wherein the nail body (1) is provided with a first grouting channel (4), the nail cap (2) is provided with a second grouting channel (11), the second grouting channel (11) is connected to the first grouting channel (4), an admixture ball (6) is added into the first grouting channel (4), a necking (401) is provided on the first grouting channel (4), and the admixture ball (6) is clamped at one end of the necking (401).

2. A grouting nail for ground anchor construction according to claim 1, characterized in that: A check valve (3) and a flow meter (9) are provided on the nail cap (2); the flow meter (9) is located in the second grouting channel (11); and one end of the check valve (3) passes through the cross section of the second grouting channel (11).

3. A grouting nail for ground anchor construction according to claim 2, characterized in that: The check valve (3) comprises a cover (301), a sleeve (302) is provided on the cover (301), a sliding check rod (303) is provided on the sleeve (302), a second sealing ring (306) is provided at the outer end of the sleeve (302), and a spring (304) is provided between the check rod (303) and the cover (301).

4. A grouting nail for ground anchor construction according to claim 3, characterized in that: The end of the check rod (303) facing the grouting cover (908) is provided with a pointed cone surface (305), the pointed cone surface (305) is an inclined slope, and the sealing cover (301) is mounted on the inner wall of the nail cap (2).

5. A grouting nail for ground anchor construction according to claim 1, characterized in that: The first grouting channel (4) is provided with a plurality of grouting ports (5), the plurality of grouting ports (5) are in communication with the first grouting channel (4), and the cross-sectional area of ​​the neck (401) is reduced on the side close to the nail body (1). The portion of the first grouting channel (4) in contact with the admixture ball is provided with a tip (402).

6. A grouting nail for ground anchor construction according to claim 1, characterized in that: The nail cap (2) comprises a cover body (203), one end of which is provided with a hollow connecting tube (204), the connecting tube (204) is provided with an external thread (201), the outer side of the external thread (201) is provided with a plurality of inner sealing rings (202), and the outer side of the cover body (203) is provided with a plurality of sealing rings (7).

7. A grouting nail for ground anchor construction according to claim 1, characterized in that: The nail cap (2) is threadedly connected to the nail body (1); a grouting cover (8) is provided at one end of the nail cap (2); a contact sensing sensor (10) is provided on the grouting cover (8); a grouting pipe (13) is provided on one side of the grouting cover (8); and the grouting pipe (13) is communicated with the nail cap (2).

8. A grouting nail for ground anchor construction according to claim 7, characterized in that: A contact sensing sensor (10) is provided on one side of the grouting cover (8). The contact sensing sensor (10) is of an annular structure. The contact sensing sensor (10) is connected to a signal contact of a flow meter (9) via a signal line. The line-connected flow meter (9) is a rotary capacity counting type flow meter.

9. A grouting nail for ground anchor construction according to claim 1, characterized in that: An additive is arranged inside the admixture ball (6), and the additive is a quick-setting agent, an early strength agent, a binder, cement or water. The admixture ball (6) contains at least two or more additives.

10. A method for using a grouting nail for ground anchor construction according to any one of claims 1 to 9, wherein the method is: S1, multiple grouting locations are set as needed, the number of holes per grouting location is reasonably determined according to the grouting amount and the area of ​​the grouting location, and the diameter of the grouting nail hole is slightly larger than the diameter of the grouting nail body; S2. Use a removable plug to temporarily seal the grouting nail hole. Before installation and use, remove the temporary plug according to the needs of the site and then use it. Do not remove the plug of the unused grouting nail hole. The plug that is not removed is used to prevent leakage during grouting; S3, nailing the grouting nail hole: manually drive the nailing machine to align the grouting nail with the hole to be installed, and the air pressure quickly pushes the piston punch out to quickly push the grouting nail into the grouting nail hole; S4, adding additives to the admixture ball (6), wherein the additives are accelerating agent, early strength agent, adhesive, cement or water, and one or more of the above additives are added to the admixture ball (6); S5, opening the nail cap (2) on the nail body (1), placing the admixture ball (6) into the nail body (1), and tightening the nail body (1) and the nail cap (2) so that the inner sealing ring (202) is tightly against the nail body (1), so that after the nail body (1) and the nail cap (2) are screwed together, the inner sealing ring (202) is tightly attached to achieve a sealing effect to prevent high-pressure slurry from leaking into the spiral thread mouth, and at the same time, the sealing ring (7) is pressed against the hole wall of the grouting nail hole to prevent the slurry from leaking from the gap between the grouting nail and the grouting nail hole; S6, driving the grouting machine to inject grout into the nail body (1) through the grouting pipe (13), the flow meter (9) can count the total amount of grout injected into a single grouting nail during the grouting process, and after summarizing and analyzing the grouting information of all grouting nails, calculate the matching between the pull-out force of the entire anchor device and the design value, and perform additional grouting if a difference is found; S7. After the grouting is completed, the nail cap (2) is removed by a grouting device or manually, and the nail cap (2) is reused. S8. Repeat steps S2 to S7 until grouting is completed at all grouting locations.