Novel full-prefabricated assembly modular steel structure building assembly joint
By adjusting the connection between the detachable unit and the fixed unit through the quick connection mechanism of the modular steel structure, the transportation and aesthetics of the prefabricated box structure when assembling a large space is solved, and the assembly and stability of a larger space is improved.
Patent Information
- Application Number
- CN202411304604.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-19
- Publication Date
- 2024-11-15
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The specifications of the existing prefabricated box structure are limited by road transport, making it impossible to assemble a larger open space, and will affect the aesthetics and usage of the space when assembling.
Modular units including columns, horizontal beams and prefabricated beams are adopted. Through quick connection mechanisms such as connection beams and support components, the detachable unit and fixed unit can be split and re-stitched, the space size is adjusted, and the structure is maintained during transportation. sex.
While ensuring the size of the construction space, transportation difficulties caused by excessive specifications are avoided, assembly and aesthetics of a larger space are achieved, and the stability and utilization rate of the structure are improved.
Smart Images

Figure CN118958492A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of modular steel structures, and in particular relates to a novel fully prefabricated modular steel structure building assembly node. Background Art
[0002] Prefabricated buildings are a type of building that uses factory-prefabricated components that are transported to the site for assembly. Depending on the degree of factory prefabrication, prefabricated units can be divided into: rod units, panel units, and module units. The corresponding structural systems are divided into: direct assembly system, prefabricated panel system, and modular building system.
[0003] Modular buildings prefabricate integrated building modules of suitable size for transportation in the factory, and arrange and decorate the interior of the modules. They are then transported to the construction site for hoisting and splicing to form the entire building. In the process of modular building construction, the core is the prefabricated box structure in the factory; the second is the completion of pipeline layout and indoor and outdoor decoration before installation; and the third is the use of modular construction methods.
[0004] However, the specifications of existing prefabricated box structures are limited by road transportation. Their width is usually around 4 meters, and their length is limited by the supporting force of the box-type structure corner column supporting module units, which is usually around 9 meters. Therefore, this leads to the existing steel structure modules needing two modules to be assembled when assembling larger open spaces. The assembly of two modules will result in two supporting columns inside the space, thus affecting the aesthetics of the interior space. Prefabricated box modules in large spaces cannot be transported by road due to the limited width of the road. Summary of the invention
[0005] In order to solve the above problems existing in the prior art, the present invention provides a new type of fully prefabricated modular steel structure building assembly node, which solves the problem that the existing prefabricated box modules cannot be assembled into a larger open space due to the limitation of road transportation.
[0006] The object of the present invention can be achieved through the following technical scheme: a new type of fully prefabricated modular steel structure building assembly node, including a module unit and a quick connection mechanism, the module unit includes a column, a horizontal beam and a prefabricated beam, the column is provided with four, the horizontal beam and the prefabricated beam are provided with four, the columns, horizontal beams and prefabricated beams form a module unit of a square frame structure, the horizontal beams and the prefabricated beams are arranged perpendicular to each other, the prefabricated beams are composed of fixed beams and connecting beams, the columns connected to the connecting beams constitute a detachable unit, the columns connected to the fixed beams constitute a fixed unit, the quick connection mechanism is used to connect the detachable unit and the fixed unit, the detachable unit, the fixed unit and the quick connection mechanism adjust the space of the module unit according to the preset module space size.
[0007] As a preferred technical solution of the present invention, the quick-connect mechanism includes a connecting beam and a support assembly. The connecting beam is used to connect the fixed beam and the connecting beam according to a preset module space size during the prefabricated construction process. The support assembly is used to support the detachable unit and the fixed unit during transportation so that they form a whole for transportation.
[0008] As a preferred technical solution of the present invention, both ends of the connecting beam have upper flanges with grooves, and both ends of the fixed beam and the connecting beam close to each other have upper flanges with grooves, and the connecting beam is connected to the fixed beam and the connecting beam by welding.
[0009] As a preferred technical solution of the present invention, a connecting plate is provided at the connection position between the connecting beam, the fixed beam and the connecting beam, and the connecting plate is installed at the vertical connection of the module unit.
[0010] As a preferred technical solution of the present invention, the support assembly includes a spiral rod, a support seat and a clamping seat, the support seat is installed on the inner side wall of the connecting beam and is located in the notch of the connecting beam, a rotating ring hole is opened on one side wall of the support seat close to the fixed beam, the spiral rod is rotatably connected in the rotating ring hole, the clamping seat is installed on the inner side wall of the fixed beam and is located in the notch of the fixed beam, a spiral groove is opened on one side wall of the clamping seat close to the connecting beam, the spiral groove matches the outer spiral of the spiral rod, and the detachable unit is fixed to the fixed unit by matching the spiral rod and the spiral groove.
[0011] As a preferred technical solution of the present invention, a through hole is opened on the spiral end surface of the spiral rod, and a connecting column is provided on the inner bottom surface of the spiral groove. The connecting column is slidably connected with the through hole when the spiral rod is connected to the spiral groove.
[0012] As a preferred technical solution of the present invention, the spiral rod is composed of a spiral part and a rotating part, the spiral part is spirally connected to the thread groove, the rotating part is rotatably connected in the rotating ring hole, and positioning holes are opened at the same vertical position of the rotating part, the support seat and the connecting beam, and a positioning pin is provided in the positioning hole.
[0013] As a preferred technical solution of the present invention, the detachable unit can be recycled.
[0014] As a preferred technical solution of the present invention, a decoration module is provided in the wall surface of the module unit, and a functional pipeline road is preset in the decoration module.
[0015] The beneficial effects of the present invention are as follows: during the construction process, the disassembly unit and the fixed unit are separated and the two fixed units are spliced together. Since the length of the fixed beam is greater than the length of the connecting beam, a larger assembly space can be obtained when the two fixed units are spliced together. At the same time, the space size of the preset module during the installation process can be changed by adjusting the connection length between the quick-connect mechanism and the detachable unit and the fixed unit, thereby ensuring that when the specifications of the prefabricated box-type structure are limited, different fixed units can be spliced together to form a larger space to meet the construction needs. Moreover, during the transportation process, the module unit will not be unable to be transported due to its too wide specifications, thereby solving the problem that the existing prefabricated box-type modules are unable to assemble into a larger open space due to the limitation of road transportation. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to facilitate understanding by those skilled in the art, the present invention is further described below with reference to the accompanying drawings.
[0017] Figure 1 It is a structural schematic diagram of the present invention;
[0018] Figure 2 For the present invention Figure 1 A magnified image of point A;
[0019] Figure 3 This is a schematic diagram of the structure of the card connector of the present invention;
[0020] Figure 4 This is a schematic diagram of the spiral rod structure of the present invention;
[0021] Figure 5 This is a schematic diagram of the vertical structure of the connecting beam installation of the present invention;
[0022] Main component symbols
[0023] In the figure: 1. module unit; 11. column; 12. horizontal beam; 131. fixed beam; 132. connecting beam; 2. quick-connect mechanism; 3. connecting beam; 4. connecting plate; 5. supporting assembly; 51. spiral rod; 511. through hole; 512. spiral part; 513. rotating part; 52. supporting seat; 53. snap-on seat; 531. spiral groove; 532. connecting column; 6. positioning hole; 7. positioning pin. DETAILED DESCRIPTION
[0024] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined invention purpose, the specific implementation methods, structures, features and effects of the present invention are described in detail below in conjunction with the accompanying drawings and preferred embodiments.
[0025] See also Figure 1-Figure 5The present embodiment provides a novel fully prefabricated modular steel structure building assembly node, including a module unit 1 and a quick connection mechanism 2, wherein the module unit 1 includes a column 11, a horizontal beam 12 and a prefabricated beam, wherein the column 11 is provided with four, the horizontal beam 12 and the prefabricated beam are provided with four, and the column 11, the horizontal beam 12 and the prefabricated beam form a module unit 1 of a square frame structure, wherein the horizontal beam 12 and the prefabricated beam are arranged perpendicular to each other, which is equivalent to the horizontal beam 12 being arranged as a beam in the length direction of the module unit 1, and the prefabricated beam being a beam in the width direction, and the prefabricated beam is composed of a fixed beam 131 and a connecting beam 132, wherein the length of the fixed beam 131 is greater than the length of the connecting beam 132, wherein the column 11 connected to the connecting beam 132 constitutes a detachable unit, and the column 11 connected to the fixed beam 131 constitutes a fixed unit.
[0026] In the process of modular building construction, the width of the prefabricated box is affected by the width of the road, making it impossible to transport wider prefabricated box structures. In addition, the construction locations of existing factories for prefabricated module construction are usually remote, and the width of the road transportation is smaller than that of urban transportation roads. Therefore, the specifications of the prefabricated boxes will be affected. Since the specifications of the prefabricated boxes are small, the process of assembling a large space will result in multiple columns 11 in the space, which not only affects the utilization rate of the space, but also affects the aesthetics of the space. Therefore, in order to avoid the above problems.
[0027] During the prefabrication process of the prefabricated box-type structure, the module unit 1 is composed of two parts, namely a detachable unit and a fixed unit, which are connected by a quick-connect mechanism 2 during transportation. The quick-connect mechanism 2 allows the detachable unit and the fixed unit to maintain stability during transportation, and avoids the detachable unit and the fixed unit themselves being semi-frame structures, which causes the prefabricated beam to shake during transportation and affect the structural strength. During the construction process, the detachable unit and the fixed unit are separated and the two fixed units are spliced. Since the length of the fixed beam 131 is greater than the length of the connecting beam 132, when the two fixed units are spliced, a larger assembly space can be obtained. At the same time, the space size of the preset module during the installation process can be changed by adjusting the connection length of the quick-connect mechanism 2 and the detachable unit and the fixed unit, so as to ensure that when the specifications of the prefabricated box-type structure are limited, different fixed units can be spliced to form a larger space to meet the construction needs. In addition, during transportation, the module unit 1 will not be unable to be transported due to the specifications being too wide.
[0028] In order to more accurately control the size of the prefabricated construction space and reduce the difficulty in the transportation process, in this embodiment, the quick-connect mechanism 2 includes a connecting beam 3 and a support assembly 5. The connecting beam 3 is used to connect the fixed beam 131 and the connecting beam 132 according to the preset module space size during the prefabricated construction process. The support assembly 5 is used to support the detachable unit and the fixed unit during transportation so that they can form a whole for transportation. The connecting beam 3 is a separate beam structure. Therefore, the setting of the fixed unit and the detachable unit in the width direction can be shortened as much as possible, as long as the preset value is retained in the length direction. During the transportation process, the fixed unit and the detachable unit can be transported separately. Since the fixed unit and the detachable unit are shorter in the width direction, they can also be supported by the support assembly 5 to form a whole for transportation. Transportation, to avoid shaking during transportation and affecting the strength of the structure itself; and in the construction process, after the module unit 1 is hoisted to the predetermined position by a crane, the support assembly 5 is removed, the detachable unit is removed, and then the length of the connecting beam 3 is adjusted according to the preset space size, and then the connecting beam 3 is used to connect the two fixed units, or the two fixed units and the detachable unit are reconnected to achieve the preset space size. Therefore, in the process of modular construction, the present application allows the structure of the prefabricated box structure to be changed to adapt to the requirements of a larger construction space by disassembling the module unit 1 and then reassembling it, while avoiding the situation that the space of the prefabricated box structure cannot be changed due to restrictions during road transportation, and the construction needs cannot be met when constructing a prefabricated factory with a large space.
[0029] Since the connecting beam 3, the fixed unit and the detachable unit need to be reconnected during the construction process, and in order to ensure that the weak connection node will not cause insufficient structural strength and insufficient supporting force after reconnection, in one embodiment, the upper flanges at both ends of the connecting beam 3 are provided with grooves, and the upper flanges of the ends of the fixed beam 131 and the connecting beam 132 close to each other are provided with grooves. The connecting beam 3 is connected to the fixed beam 131 and the connecting beam 132 by welding. After the connecting beam 3 is installed, the connection position is first preliminarily fixed by bolts, and then the upper flange groove is fully welded to ensure that the added steel beam component is strongly connected to the original structural component to avoid the occurrence of insufficient node strength.
[0030] In order to ensure the stability of the vertical wall after the connection of the connecting beam 3 is completed, in one embodiment, a connecting plate 4 is provided at the connection position of the connecting beam 3, the fixed beam 131 and the connecting beam 132. The connecting plate 4 is installed at the vertical connection of the module unit 1. Since the module unit 1 is not an integral structure during the construction process, but is spliced together by multiple units, the vertical wall of the module unit 1 is also spliced together. However, since the vertical wall is not subjected to force and cannot be connected by welding, a connecting plate 4 is provided at the connection of the vertical wall to improve the stability of the wall and prevent collapse.
[0031] Since the fixed unit and the detachable unit are two independent semi-frame structures during the prefabrication process, in order to ensure the stability of the fixed unit and the detachable unit during transportation, and because the fixed unit and the detachable unit are prefabricated and assembled in modular construction, if the construction space needs to be equipped with a connecting beam 3 to change the size of the space, it is necessary to ensure the stability of the fixed unit and the detachable unit when they are connected, that is, the stability of the fixed beam 131 and the connecting beam 132 when they are connected, because the fixed beam 131 and the connecting beam 132 were originally a complete steel beam, and its own structure has a good supporting effect. In order to meet the requirement that the modular space can be changed to achieve a larger module space, the fixed beam 131 The connection position with the connecting beam 132 becomes a weak connection node. Therefore, in order to ensure that the fixed beam 131 and the connecting beam 132 can have sufficient strength during connection, and at the same time to ensure the speed during construction, in one embodiment, the support assembly 5 includes a spiral rod 51, a support seat 52 and a clamping seat 53. The support seat 52 is installed on the inner side wall of the connecting beam 132 and is located in the notch of the connecting beam 132. A rotating ring hole is provided on one side wall of the support seat 52 close to the fixed beam 131. The spiral rod 51 is rotatably connected in the rotating ring hole. The clamping seat 53 is installed on the inner side wall of the fixed beam 131 and is located in the notch of the fixed beam 131. A spiral groove 531 is provided on one side wall of the clamping seat 53 close to the connecting beam 132. The spiral groove 531 and the outer spiral groove of the spiral rod 51 The detachable unit is fixed to the fixed unit by matching the spiral rod 51 with the spiral groove 531. Since the fixed beam 131 and the connecting beam 132 are both steel structure beams, the fixed beam 131 and the connecting beam 132 are hollow beams. Therefore, in the process of transporting the fixed unit and the detachable unit, the fixed unit and the detachable unit can be transported separately, thereby avoiding the situation that the space of the prefabricated modular steel structure is affected by the road and difficult to transport due to road restrictions when transporting to a remote construction factory, thereby reducing the road requirements during transportation. If the road meets the transportation requirements, the entire modular steel structure can also be transported. At this time, the card seat 53 is fixed to the fixed beam 131. The screw rod 51 is then aligned with the spiral groove 531 and the screw rod 51 is rotated forward along the spiral groove 531. When the end faces of the connecting beam 132 and the fixed beam 131 are in contact, the screw rod 51 is completely matched with the spiral groove 531. The fixed beam 131 and the connecting beam 132 are connected into a whole through the cooperation between the screw rod 51 and the spiral groove 531. In this way, the fixing beam 131 and the connecting beam 132 can be kept stable during transportation and hoisting. When modular construction is performed, if it is not necessary to add the connecting beam 3 to fill the space of the entire module,Welding can be directly performed on the grooves on the fixed beam 131 and the connecting beam 132 to re-form the fixed unit and the detachable unit into a whole for construction. Moreover, since the spiral rod 51 is located at the connection position between the fixed beam 131 and the connecting beam 132, it is equivalent to adding a reinforcing rib at the connection position between the fixed beam 131 and the connecting beam 132, thereby ensuring the stability of the connecting beam 132 and the fixed beam 131 when they are disconnected and then reconnected, and avoiding the occurrence of a weak connection node at the connection position between the connecting beam 132 and the fixed beam 131.
[0032] If it is necessary to add a connecting beam 3 to change the spatial size of the module, a support seat 52 and a spiral rod 51 are installed at one end of the connecting beam 3, and a clamping seat 53 is installed at the other end. Then, the clamping seat 53 on the fixed unit and the spiral rod 51 on the detachable unit are connected to complete the change of the spatial size of the module.
[0033] In order to further improve the strength of the connecting beam 132 and the fixed beam 131 at the connection position, in one embodiment, a through hole 511 is opened on the spiral end surface of the spiral rod 51, and a connecting column 532 is provided on the inner bottom surface of the spiral groove 531. The connecting column 532 is slidably connected with the through hole 511 when the spiral rod 51 is connected to the spiral groove 531. When the spiral rod 51 is spirally connected with the spiral groove 531, in order to ensure the smooth sliding of the spiral rod 51, a certain gap needs to be left between the spiral strip on the outer side of the spiral rod 51 and the spiral groove on the spiral groove 531 when the spiral connection is performed. The spiral rod 51 can smoothly rotate in the spiral groove 531. Therefore, this will result in insufficient connection strength of the spiral rod 51 due to the existence of a gap when the spiral rod 51 is connected to the spiral groove 531. A through hole 511 is opened at the spiral end of the spiral rod 51, and a connecting column 532 is set in the spiral groove 531, so that the connecting column 532 and the through hole 511 are slidably connected. In this way, sufficient connection strength can be maintained when the spiral rod 51 is connected to the spiral groove 531, thereby ensuring the strength of the connecting beam 132 and the fixed beam 131 at the connection node.
[0034] In order to ensure that the spiral rod 51 will not be separated from the spiral groove 531 due to vibration after connection, resulting in a gap between the fixed beam 131 and the connecting beam 132 being too large and affecting the connection strength, in one embodiment, the spiral rod 51 is composed of a spiral portion 512 and a rotating portion 513, the spiral portion 512 is spirally connected to the thread groove, the rotating portion 513 is rotatably connected in the rotating ring hole, and the rotating portion 513, the support seat 52 and the connecting beam 132 are all provided with a positioning hole 6 at the same vertical position, and a positioning pin 7 is provided in the positioning hole 6. The positioning hole 6 is provided at the vertical position of the rotating portion 513, the support seat 52 and the connecting beam 132 of the spiral rod 51, and the positioning pin 7 is provided, so that the relative position of each part is always fixed during connection. The positioning pin 7 can effectively prevent relative displacement caused by vibration, maintain the compactness of the connection, effectively improve the connection strength between the spiral rod 51 and the spiral groove 531, reduce the risk of separation caused by vibration, and ensure that the gap between the fixed beam 131 and the connecting beam 132 is controlled within an acceptable range, thereby improving the performance and safety of the overall structure.
[0035] In order to improve the utilization rate of the prefabricated module unit 1 and reduce the production cost, in one embodiment, the detachable unit can be recycled. In the process of prefabricated module construction, two fixed units will be connected by the connecting beam 3 to complete the construction process of the prefabricated module. This is because the length of the fixed beam 131 on the fixed unit is greater than the length of the connecting beam 132. Therefore, in the process of connecting with the connecting beam 3, the length of the connecting beam 3 can be reduced, so that the overall structure of the spliced module unit 1 itself is more, thereby providing better support and maintaining higher stability. If the length of the connecting beam 3 is longer, and the connecting beam 3 itself has no support, this will result in the supporting force and stability of the spliced module unit 1 being reduced when the length of the connecting beam 3 is longer. Therefore, in the process of prefabricated module construction, two fixed units are usually spliced to complete the construction process; therefore, the disassembled detachable unit can also change its own prefabricated space size through the connection of the connecting beam 3 to meet different prefabrication requirements, thereby avoiding waste of resources.
[0036] In order to improve the construction efficiency and greatly improve the engineering quality and building quality, in one embodiment, a decoration module is provided in the wall of the module unit 1, and a functional pipeline road is preset in the decoration module. Sanitary ware, furniture, equipment and corresponding various pipelines are pre-integrated in the wall in the factory for overall transportation. On the one hand, it avoids the steps of on-site pipeline and equipment installation for such modules in traditional container-type integral building units, greatly improving the engineering quality and building quality while improving the construction efficiency.
[0037] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technical personnel in this field can make some changes or modify the technical contents disclosed above into equivalent embodiments without departing from the scope of the technical solution of the present invention. However, any simple modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solution of the present invention still fall within the scope of the technical solution of the present invention.
Claims
1. A new type of fully prefabricated modular steel structure building assembly node, characterized by: It includes a module unit and a quick-connect mechanism. The module unit includes columns, horizontal beams and prefabricated beams. There are four columns, and there are four horizontal beams and four prefabricated beams. The columns, horizontal beams and prefabricated beams form a module unit with a square frame structure. The horizontal beams and prefabricated beams are arranged perpendicular to each other. The prefabricated beams are composed of fixed beams and connecting beams. The columns connected to the connecting beams constitute a detachable unit, and the columns connected to the fixed beams constitute a fixed unit. The quick-connect mechanism is used to connect the detachable unit and the fixed unit. The detachable unit, the fixed unit and the quick-connect mechanism adjust the space of the module unit according to the preset module space size.
2. According to claim 1, a novel fully prefabricated modular steel structure building assembly node is characterized by: The quick-connect mechanism includes a connecting beam and a supporting assembly. The connecting beam is used to connect the fixed beam and the connecting beam according to a preset module space size during the assembly construction process. The supporting assembly is used to support the detachable unit and the fixed unit during transportation so that they form a whole for transportation.
3. According to claim 2, a novel fully prefabricated modular steel structure building assembly node is characterized by: The upper flanges at both ends of the connecting beam are provided with grooves, the upper flanges of the ends of the fixed beam and the connecting beam close to each other are provided with grooves, and the connecting beam is connected to the fixed beam and the connecting beam by welding.
4. According to claim 2, a novel fully prefabricated modular steel structure building assembly node is characterized by: A connecting plate is provided at the connection position between the connecting beam, the fixed beam and the connecting beam, and the connecting plate is installed at the vertical surface connection of the module unit.
5. According to claim 2, a novel fully prefabricated modular steel structure building assembly node is characterized by: The support assembly includes a spiral rod, a support seat and a clamping seat. The support seat is installed on the inner side wall of the connecting beam and is located in the notch of the connecting beam. A rotating ring hole is opened on one side wall of the support seat close to the fixed beam. The spiral rod is rotatably connected in the rotating ring hole. The clamping seat is installed on the inner side wall of the fixed beam and is located in the notch of the fixed beam. A spiral groove is opened on one side wall of the clamping seat close to the connecting beam. The spiral groove matches the outer spiral of the spiral rod. The detachable unit is fixed to the fixing unit by matching the spiral rod and the spiral groove.
6. According to claim 5, a novel fully prefabricated modular steel structure building assembly node is characterized by: A through hole is formed on the spiral end surface of the spiral rod, and a connecting column is formed on the inner bottom surface of the spiral groove. The connecting column is slidably connected with the through hole when the spiral rod is connected to the spiral groove.
7. According to claim 5, a novel fully prefabricated modular steel structure building assembly node is characterized by: The spiral rod is composed of a spiral part and a rotating part, the spiral part is spirally connected to the thread groove, the rotating part is rotatably connected in the rotating ring hole, and the rotating part, the support seat and the connecting beam are all provided with positioning holes at the same vertical position, and the positioning pins are provided in the positioning holes.
8. According to claim 1, a novel fully prefabricated modular steel structure building assembly node is characterized by: The detachable unit can be recycled.
9. The novel fully prefabricated modular steel structure building assembly node according to claim 1 is characterized by: A decoration module is arranged inside the wall surface of the module unit, and a functional pipeline road is preset inside the decoration module.
Citation Information
Patent Citations
Assembly type steel structure building fixing mechanism
CN212427537U
Sectional bottom frame and top frame of box-type house and modular box-type house
CN214532107U
Steel structure fastening connection device
CN218060772U
Fabricated building cross beam connecting structure
CN218540958U
Assembled steel beam
CN218713987U