Multi-arch tunnel construction method

By adjusting the construction method of the continuous arch tunnel, the first hole and the rear hole are used to different excavation methods and the middle partition wall construction sequence is adjusted, which solves the problems of complex processes and high costs in the existing technology, and achieves the effect of shortening construction period and reducing costs. .

CN118958992APending Publication Date: 2024-11-15中铁长江交通设计集团有限公司 +2
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411025326.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-26
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The existing continuous arch tunnel construction methods are complex, with many temporary support structures, many perimeters of surrounding rock, long cycles and high costs.

Method used

The construction methods of pioneer holes and rear holes are adopted. The pioneer holes are excavated by the upper and lower steps method, and the rear holes are excavated by the CD method. The construction sequence of the middle partition walls is adjusted to reduce construction processes and surrounding rock disturbances and reduce costs.

Benefits of technology

The construction steps have been optimized, the construction period has been shortened, the number of surrounding rock disturbances and construction costs have been reduced, and the construction efficiency has been improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958992A_ABST
    Figure CN118958992A_ABST
Patent Text Reader

Abstract

The invention discloses a multi-arch tunnel construction method, and relates to the technical field of tunnel engineering excavation construction methods. The multi-arch tunnel comprises a preceding hole and a following hole, a middle partition wall is arranged between the preceding hole and the following hole, and the construction method comprises the following steps that firstly, the preceding hole is supported in advance, secondly, the preceding hole is excavated, thirdly, the following hole and the middle partition wall are supported in advance, and fourthly, the following hole and the middle partition wall are excavated. According to the multi-arch tunnel construction method, by changing the construction sequence of the preceding hole, the following hole and the middle partition wall and optimizing excavation steps, the construction opportunity of the middle partition wall is optimized, excavation and primary support of the middle pilot tunnel are reduced, construction procedures are reduced, the construction period is effectively shortened, the disturbance frequency on surrounding rock is reduced, and cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of tunnel engineering excavation methods, and more particularly to a multi-arch tunnel construction method. Background Art

[0002] my country has a vast mountainous area, accounting for about two-thirds of the total area. In the construction of expressways, in order to meet the needs of driving, the selection and construction of tunnels are particularly important. There are three main types of tunnel structures. One is a double-hole separated tunnel. The clear distance of this tunnel is not less than 1.5 to 3.0 times the diameter of the tunnel. In cities or mountainous areas with special geology, this type of tunnel often has great limitations; the other is a small clear distance tunnel. The distance between the two tunnels is less than the distance of the separated tunnel specified in the specification; the third is a continuous arch tunnel, which can avoid the division of the roadbed at the entrance and connect smoothly with the external connection of the tunnel. Especially in mountainous terrain, it can shorten the overall length of the tunnel and effectively reduce the difficulty and cost of construction. In order to ensure the technical indicators of the route plan and ensure the safety and quality of tunnel construction, the role of continuous arch tunnels has become increasingly prominent. With the continuous increase in infrastructure construction investment in the southwestern mountainous areas of China, continuous arch tunnel projects carried out under poor geological conditions are becoming more and more common.

[0003] The more common construction method for multi-arch tunnels is the three-guide tunnel construction method, that is, first excavate the middle guide tunnel, construct the middle partition wall after the middle guide tunnel is penetrated, and then excavate the left and right tunnels (tunnels) after the middle partition wall is completed. This excavation method is relatively conservative, but the process is complicated, there are many temporary support structures, many excavation steps, many disturbances to the surrounding rock, long cycle, slow effect, long construction period and high cost. Summary of the invention

[0004] In view of this, the present invention provides a method for constructing a multi-arch tunnel, which first excavates a leading tunnel and a trailing tunnel, and then constructs a middle partition wall, thereby reducing construction procedures, reducing the number of surrounding rock disturbances, and reducing costs.

[0005] In order to achieve the above object, the present invention adopts the following technical solution:

[0006] The present invention provides a method for constructing a multi-arch tunnel, wherein the multi-arch tunnel comprises a leading tunnel and a trailing tunnel, wherein a middle partition wall is arranged between the leading tunnel and the trailing tunnel, and the construction method comprises the following steps:

[0007] Step 1: Advance support of the pilot tunnel: constructing a sleeve arch and a pipe shed outside the pilot tunnel;

[0008] Step 2: Excavation of the pilot hole: The pilot hole is excavated by using the upper and lower steps method, and the upper steps of the pilot hole are excavated;

[0009] providing initial support for the upper step;

[0010] Excavation of the lower step of the pilot tunnel;

[0011] providing initial support for the lower step;

[0012] Anchor rods are constructed at the base of the pilot tunnel, and the invert arch of the pilot tunnel is cast;

[0013] First, waterproofing boards are laid in the tunnel and secondary lining is carried out;

[0014] Step 3: Advance support of the rear tunnel and the middle partition wall: construct sleeve arches and pipe sheds on the upper part of the rear tunnel and the middle partition wall;

[0015] Step 4: Excavation of the rear tunnel and the middle partition wall: The rear tunnel is excavated by the CD method, and the upper right side of the rear tunnel is excavated;

[0016] The upper right side of the rear tunnel is initially supported;

[0017] Excavation of the lower right side of the rear tunnel;

[0018] The lower right side of the rear tunnel is initially supported;

[0019] The middle partition wall is excavated in sections;

[0020] Cast the middle partition wall and complete the initial support on the right side of the tunnel;

[0021] The left upper part of the rear tunnel was excavated;

[0022] Provide initial support to the upper left side of the rear tunnel;

[0023] The lower left side of the rear tunnel was excavated;

[0024] Carry out initial support on the lower left side of the rear tunnel and remove the temporary support;

[0025] Anchor rods are constructed in the rear tunnel, and the invert arch of the rear tunnel is cast;

[0026] After that, waterproof board is laid in the tunnel and secondary lining is carried out.

[0027] Furthermore, in the step 2, the bottom of the pilot hole close to one end of the middle partition wall is first poured, and then the pilot hole invert concrete is poured, and a certain length of steel bars is reserved before pouring the invert concrete.

[0028] Furthermore, the lower right side of the rear tunnel in step 4 is initially supported, and the initial support of the lower right side of the rear tunnel is only made of steel frames without spraying. Excavation is carried out between the steel frames toward the middle partition wall, and a steel frame for casting the middle partition wall is built at the middle partition wall. The outer side of the steel frame for casting the middle partition wall is made of bamboo plywood to make a template, and a temporary steel frame is set around the template. The other end of the temporary steel frame is connected to the leading tunnel or the rear tunnel, and concrete is poured into the template. The steel bars at the base of the casting middle partition wall and the steel bars reserved for the leading tunnel are connected by welding. After the casting of the middle partition wall is completed, the temporary steel frame is removed, and the steel frame for initial support of the lower right side of the rear tunnel and the steel frame embedded in the middle partition wall are used to connect the casting middle partition wall to the rear tunnel, and concrete is sprayed.

[0029] Furthermore, after the right side of the rear tunnel is penetrated from the tunnel, the left side of the rear tunnel is then excavated.

[0030] Furthermore, the waterproof panels in the leading tunnel and the trailing tunnel are laid using a formwork trolley for full-section one-time molding and secondary lining.

[0031] Furthermore, the secondary lining and the inverted arch annular settlement joints and construction joints use embedded rubber waterstops and back-attached rubber waterstops.

[0032] It can be seen from the above technical scheme that, compared with the prior art, the present invention discloses a method for constructing a continuous arch tunnel, in which a leading tunnel is constructed by the up-and-down step method, and then a trailing tunnel is constructed by the CD method. After the trailing tunnel is constructed on one side close to the middle partition wall, the middle partition wall is constructed. After the middle partition wall is completed, the other side of the trailing tunnel is constructed. By changing the construction sequence of the leading tunnel, the trailing tunnel and the middle partition wall, the excavation steps are optimized, the timing of the construction of the middle partition wall is optimized, the excavation and initial support of the middle guide tunnel are reduced, the construction process is reduced, the construction period is effectively shortened, the number of disturbances to the surrounding rock is reduced, and the cost is reduced. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.

[0034] Figure 1 A vertical view of the construction scheme of the multi-arch tunnel construction method provided by the present invention;

[0035] Figure 2 A construction step diagram of the multi-arch tunnel construction method provided by the present invention.

[0036] In the figure: 1. Lower step; 2. Initial support; 3. Waterproof board; 4. Upper step; 5. Pipe shed; 6. Lower right part; 7. Upper right part; 8. Upper left part; 9. Lower left part. DETAILED DESCRIPTION

[0037] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0038] See also Figure 1-2 The embodiment of the present invention discloses a construction method of a multi-arch tunnel, wherein the multi-arch tunnel comprises a leading tunnel and a trailing tunnel, and a middle partition wall is arranged between the leading tunnel and the trailing tunnel. The construction method comprises the following steps:

[0039] Step 1: Advance support of the pilot tunnel: construct a sleeve arch and a pipe shed 5 outside the pilot tunnel;

[0040] Step 2: Excavation of the pilot hole: The pilot hole is excavated using the upper and lower steps method, and the upper step 4 of the pilot hole is excavated;

[0041] Perform initial support 2 on the upper step 4;

[0042] The lower step 1 of the pilot tunnel was excavated;

[0043] Carry out initial support 2 on the lower step 1;

[0044] Anchor rods are constructed at the base of the pilot tunnel, and the invert arch of the pilot tunnel is cast;

[0045] The waterproof board 3 is laid in the first tunnel and the secondary lining is carried out;

[0046] Step 3: Advance support of the rear tunnel and the middle partition wall: construct the sleeve arch and pipe shed 5 on the upper part of the rear tunnel and the middle partition wall;

[0047] Step 4: Excavation of rear tunnel and middle partition wall: The rear tunnel is excavated by CD method, and the upper right part 7 of the rear tunnel is excavated;

[0048] The upper right part 7 of the rear tunnel is initially supported 2;

[0049] The lower right side of the rear tunnel is excavated 6;

[0050] The lower right part 6 of the rear tunnel is initially supported 2;

[0051] The middle partition wall is excavated in sections;

[0052] Cast the middle partition wall and complete the initial support 2 on the right side of the tunnel;

[0053] The left upper part 8 of the rear tunnel is excavated;

[0054] Perform initial support 2 on the upper left side 8 of the rear tunnel;

[0055] The lower left side of the rear tunnel is excavated 9;

[0056] Carry out initial support 2 on the left lower part 9 of the rear tunnel and remove the temporary support;

[0057] Anchor rods are constructed in the rear tunnel, and the invert arch of the rear tunnel is cast;

[0058] After that, waterproof board 3 is laid in the tunnel and secondary lining is carried out.

[0059] Changing the construction sequence of the first tunnel, the subsequent tunnel and the middle partition wall eliminates the need to construct a through-hole, reduces the number of temporary support structures, reduces the number of excavation steps, reduces the construction period and reduces construction costs.

[0060] In some embodiments, the excavation length of the upper step 4 and the lower step 1 of the pilot tunnel each time is not greater than the spacing between 2 steel frames, and the excavation height is 7m.

[0061] In some embodiments, the initial support 2-type steel arch frame of the upper step 4 and the lower step 1 of the pilot tunnel uses I22b I-beams, the I-beam spacing is 50cm, φ6 steel mesh, the anchor rod is R25 hollow grouting anchor rod, and the C25 shotcrete is 28cm thick.

[0062] In some embodiments, a non-woven fabric buffer layer (400 g / m 2 )+EVA waterproof membrane (1.5mm thick)+back-sticked rubber waterstop. The secondary lining concrete of the tunnel adopts C35 concrete.

[0063] In some embodiments, the rear tunnel and the upper arch and pipe shed 5 of the middle partition wall are constructed as the pipe shed 5 within 120° of the left tunnel and the pipe shed 5 on the upper part of the middle partition wall.

[0064] In some embodiments, the excavation length of each time on the right side of the rear tunnel is no more than the distance between 2 steel frames, and the excavation height is 7m.

[0065] In some embodiments, the initial support 2-type steel arch frame on the right side of the rear tunnel uses I22b I-beams, the I-beam spacing is 50cm, φ6 steel mesh, the anchor rod is R25 hollow grouting anchor rod, and the C25 shotcrete is 28cm thick.

[0066] In some embodiments, the initial support 2-type steel arch frame on the left side of the rear tunnel uses I22b I-beams with an I-beam spacing of 50 cm, φ6 steel mesh, and R25 hollow grouting anchors with a length of 4 m and a spacing of 1 m×0.5 m (circular×longitudinal) arranged in a plum blossom shape. The C25 shotcrete is 28 cm thick.

[0067] In some embodiments, the excavation length of the invert arch in the first tunnel and the back tunnel is the length of the trolley used, and φ25 low prestressed anchor rods are applied to the base during excavation to enhance the bearing capacity of the foundation and keep the pad close to the rock surface.

[0068] In some embodiments, in step 2, the bottom of the pilot hole near one end of the middle partition wall is first poured, and then the pilot hole invert concrete is poured, and a certain length of steel bars is reserved before pouring concrete for the invert.

[0069] In some embodiments, the lower right side 6 of the rear tunnel in step four is initially supported 2, and the initial support 2 of the lower right side 6 of the rear tunnel is only made of steel frames, and no spraying is performed. Excavation is carried out between the steel frames toward the middle partition wall, and a steel frame for casting the middle partition wall is built at the middle partition wall. The outer side of the steel frame for casting the middle partition wall is made of bamboo plywood to make a template, and a temporary steel frame is set around the template. The other end of the temporary steel frame is connected to the leading tunnel or the rear tunnel, and concrete is poured into the template. The steel bars at the base of the cast middle partition wall and the steel bars reserved for the leading tunnel are connected by welding. After the casting of the middle partition wall is completed, the temporary steel frame is removed, and the steel frame of the initial support 2 of the lower right side 6 of the rear tunnel and the steel frame embedded in the middle partition wall are used to connect the cast middle partition wall to the rear tunnel, and concrete is sprayed.

[0070] After the pouring of the middle partition wall is completed, the concrete of the initial support 2 of the lower right side 6 of the rear tunnel is poured to strengthen the connection between the poured middle partition wall and the rear tunnel.

[0071] In some embodiments, the excavation length of the left side of the rear tunnel is no more than 2 frames each time, and the excavation height is 5m. After the right side of the rear tunnel is penetrated from the tunnel, the left side of the rear tunnel is then excavated.

[0072] In some embodiments, the waterproof panels 3 are laid in both the first tunnel and the second tunnel using a formwork trolley to form the entire section in one go and build the secondary lining.

[0073] In some embodiments, the secondary lining and the invert annular settlement joints and construction joints use embedded rubber waterstops and back-attached rubber waterstops.

[0074] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. For the device disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part.

[0075] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A method for constructing a multi-arch tunnel, wherein the multi-arch tunnel comprises a leading tunnel and a trailing tunnel, wherein a middle partition wall is provided between the leading tunnel and the trailing tunnel, wherein: The construction method comprises the following steps: Step 1: Advance support of the pilot tunnel: constructing a sleeve arch and a pipe shed outside the pilot tunnel; Step 2: Excavation of the pilot hole: The pilot hole is excavated using the upper and lower steps method, and the upper steps of the pilot hole are excavated; providing initial support for the upper step; Excavation of the lower step of the pilot tunnel; providing initial support for the lower step; Anchor rods are constructed at the base of the pilot tunnel, and the invert arch of the pilot tunnel is cast; First, waterproofing sheets are laid in the tunnel and secondary lining is carried out; Step 3: Advance support of the rear tunnel and the middle partition wall: construct sleeve arches and pipe scaffolds on the upper part of the rear tunnel and the middle partition wall; Step 4: Excavation of the rear tunnel and the middle partition wall: The rear tunnel is excavated using the CD method, and the upper right side of the rear tunnel is excavated; The upper right side of the rear tunnel is initially supported; Excavation of the lower right side of the rear tunnel; The lower right side of the rear tunnel is initially supported; The middle partition wall is excavated in sections; Cast the middle partition wall and complete the initial support on the right side of the tunnel; The upper left side of the back tunnel was excavated; Provide initial support to the upper left side of the rear tunnel; The lower left side of the back tunnel was excavated; Carry out initial support on the lower left side of the rear tunnel and remove the temporary support; Anchor rods are constructed in the rear tunnel and the invert arch of the rear tunnel is cast; After that, waterproof board is laid in the tunnel and secondary lining is carried out.

2. The multi-arch tunnel construction method according to claim 1, characterized in that: In the step 2, the bottom of the pilot hole close to one end of the middle partition wall is first poured, and then the pilot hole inverted arch concrete is poured, and a certain length of steel bars is reserved before pouring the inverted arch concrete.

3. The multi-arch tunnel construction method according to claim 1, characterized in that: The lower right side of the rear tunnel in step 4 is initially supported. The initial support of the lower right side of the rear tunnel is only made of steel frames, and no spraying is performed. Excavation is carried out between the steel frames toward the middle partition wall. A steel frame for casting the middle partition wall is built at the middle partition wall. The outer side of the steel frame for casting the middle partition wall is made of bamboo plywood to make a template. Temporary steel frames are set around the template. The other end of the temporary steel frame is connected to the leading tunnel or the rear tunnel, and concrete is poured into the template. The steel bars of the base of the cast middle partition wall and the steel bars reserved for the leading tunnel are connected by welding. After the casting of the middle partition wall is completed, the temporary steel frame is removed, and the steel frame for the initial support of the lower right side of the rear tunnel and the steel frame embedded in the middle partition wall are used to connect the cast middle partition wall to the rear tunnel, and concrete is sprayed.

4. The multi-arch tunnel construction method according to claim 1, characterized in that: After the right side of the rear tunnel is penetrated from the tunnel, the left side of the rear tunnel is excavated.

5. The multi-arch tunnel construction method according to claim 1, characterized in that: The waterproof panels laid in the pilot tunnel and the rear tunnel are both constructed by using a formwork trolley to form the entire section in one go and then form the secondary lining.

6. The multi-arch tunnel construction method according to claim 1, characterized in that: The secondary lining and inverted arch circumferential settlement joints and construction joints use embedded rubber waterstops and back-stick rubber waterstops.