Construction method for entrance and exit of metro in mountain city
By using a combination of open excavation sections and hidden excavation sections in the construction of the Shancheng subway entrance and exit, combined with mechanical supporting selection and non-explosion excavation process, the problems of extended construction period and high technical requirements are solved, and construction efficiency and safety are achieved Improvement.
Patent Information
- Application Number
- CN202411118425.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-15
- Publication Date
- 2024-11-15
AI Technical Summary
During the construction of the Shancheng Metro entrance and exit, it is difficult for the existing technology to complete the project without destroying the terrain and geological structure, resulting in an extension of the construction period and an increase in technical requirements.
Using the construction method of combining open excavation sections and concealed excavation sections, optimize the excavation operation time management through technical means such as mechanical supporting selection, layered excavation, spray anchor support, advanced large pipe shed and the second set of arches to ensure that the excavation operation time is Stratigraphic stability and adapt to different geological conditions through non-explosion excavation process.
The construction period is shortened, construction efficiency and safety is improved, the risk of formation movement and landslide collapse is reduced, and the impact on the surrounding environment is reduced.
Smart Images

Figure CN118958994A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel construction, and in particular to a mountain city subway entrance and exit construction method. Background Art
[0002] With the current acceleration of urbanization, in order to alleviate urban ground traffic congestion, the development of a subway system based on rail transit has become the preferred choice for solving traffic problems. In mountainous cities with complex terrain, the construction of subways is particularly critical. Due to the significant ups and downs in the terrain of mountainous cities, conventional ground transportation faces major restrictions. The construction of subways can not only effectively avoid natural terrain obstacles, but also provide a fast and stable transportation solution.
[0003] However, in the process of building mountain city subways, especially in the construction of mountain city subway entrances and exits, many difficulties will be encountered. First, the changeable and complex geological conditions in mountain city areas can easily cause uneven settlement of the strata, which not only brings great technical difficulty to the construction, but also greatly increases the engineering risk; second, the construction site of mountain city subway entrances and exits is often located in the densely populated urban core area and needs to pass through existing buildings and infrastructure, which requires precise control during the construction process to ensure harmonious coexistence with surrounding structures; third, the natural obstacles that subway entrances and exits often need to overcome include complex structures such as large longitudinal slopes, long distances and multiple corners. These characteristics make the use of non-blasting excavation technology face more technical challenges.
[0004] How to complete the project without destroying the terrain and geological structure is a major challenge in the construction process, which usually also means a longer construction period and higher technical requirements. Summary of the invention
[0005] In view of the shortcomings of the prior art, the present invention proposes a method for constructing subway entrances and exits in mountain cities to solve the technical problem raised in the above background technology that the currently used subway entrance and exit construction method cannot complete the project without destroying the terrain and geological structure during construction, thereby resulting in the entire construction process requiring a longer construction period and higher technical requirements.
[0006] To achieve the above object, the present invention provides the following technical solution, a mountain city subway entrance and exit construction method, comprising the following steps:
[0007] Clarify the ground conditions and determine the open-cut section and dark-cut section of the subway entrance and exit, wherein the dark-cut section includes a first shallow buried area, a second shallow buried area and a deep buried area;
[0008] Select supporting machinery and choose different excavation methods according to different cross-section strata;
[0009] Leveling the entrance and exit construction site, setting up intercepting ditches around the open-cut section foundation pit and the vertical shaft, then excavating the open-cut section in layers, and constructing a first set of arches at the entrance of the first shallow buried area;
[0010] Determine the boundary line between the second set of arches and the dark excavation section, which is the boundary line between the second shallow buried area and the deep buried area, measure and lay out the tunnel axis and the guide wall construction section, and then construct the second set of arches and the advanced large pipe shed of the dark excavation section;
[0011] Two independent working faces are set up at both ends of the tunnel for zoned excavation, and initial support construction is carried out on the dark excavation section, and soil and muck transportation is carried out during excavation;
[0012] The entire construction process is monitored and measured, and the construction environment is monitored.
[0013] In a preferred embodiment, the specific steps of selecting different excavation methods according to different cross-section strata are:
[0014] For large-section broken sections, mechanical excavation with a breaker hammer is used. For areas that cannot be excavated by a breaker hammer, coring and splitting excavation with a water-grinding drill is used. For small-section hard sections, coring and splitting excavation with a water-grinding drill is used.
[0015] In a preferred embodiment, when the water-grinding drill is used for core splitting excavation, the overlap distance between the two holes is controlled at 20 mm, and drainage work is performed when water accumulates in the tunnel due to water seepage through cracks.
[0016] In a preferred embodiment, while the open cut section is being excavated in layers, each layer is subjected to the sprayed anchor support structure construction in an alternating cycle, and after the excavation and support of all layers are completed, the entrance and exit floor cushion layer is poured to seal the bottom, preparing for the construction of the dark cut section.
[0017] In a preferred embodiment, when the open cut section is excavated in layers, an excavator is used for excavation of the soil section, and a breaker is used for crushing and excavation of the rock section. The excavation is carried out in layers of 1.5 m, and support is completed in time after each 1.5 m of excavation.
[0018] In a preferred embodiment, the specific steps of carrying out initial support construction on the dark excavation section are:
[0019] Drive mortar anchors into the arch and side walls, install steel frames and meshes, carry out the first locking anchor construction and spray concrete layer construction on the meshes.
[0020] In a preferred embodiment, the specific steps of simultaneously setting up two independent working surfaces at both ends of the tunnel for zoned excavation are:
[0021] The full-section method or step method is adopted for construction, and excavation is carried out from the open-cut section to the main station side. When the excavation conditions are met on the main station side, the deep buried area is excavated from the main station side to the open-cut section simultaneously. When the excavation reaches the dividing line, the two-way excavation is stopped and switched to one-way excavation of the deep buried area.
[0022] In a preferred embodiment, when performing the zoned excavation, the excavation cycle footage of the second shallow buried area and the first shallow buried area is carried out according to the spacing of 1 steel frame, while the excavation cycle footage of the deep buried area does not exceed the spacing of 2 steel frames.
[0023] In a preferred embodiment, the specific steps of constructing the second set of arches and the advanced large pipe shed in the dark excavation section are:
[0024] Excavate the upper slope of the second set of arches and install slope anchors;
[0025] Excavate the upper step of the arch, reserve a core rock column of the upper step with a thickness of not less than 3m, continue to construct the I-beam and the second set of arches, install the second locking anchor at the arch foot of the second set of arches, and install an advanced large pipe shed above the second set of arches; and
[0026] Excavate the earth and stone of the steps under the arch, construct the I-beams of the lower steps and the second set of arches around the outline of the tunnel side walls.
[0027] In a preferred embodiment, the specific steps of transporting the slag are:
[0028] Differentiated methods of slag transportation were adopted for the different entrances and exits of the deep buried area and the first shallow buried area. For the deep buried area, the slag was transported to the ground through the station construction channel by using the cooperation of excavators and slag transport vehicles;
[0029] At the straight section at the station end, the muck truck stops for loading, and the muck is turned over by the excavator to the straight section in sequence. At the deep-buried slope section, the muck of the supported slag section formed by the excavated section is used for filling construction;
[0030] For the second shallow buried area and the first shallow buried area, excavators and crawler transporters are selected to work together to transport the debris directly out through the entrance and exit channels.
[0031] Compared with the prior art, the present invention has the following beneficial effects:
[0032] 1. This construction method combines open-cut and dark-cut sections at both ends of the tunnel, sets up intercepting ditches around the foundation pit and shaft of the open-cut section, starts layered excavation of the open-cut section, strictly controls the layer height, and alternately cycles to build the shotcrete support structure of each layer; in the dark-cut section, deep and shallow buried zoning excavation is carried out, and the excavation is divided into two working faces at the same time, which effectively optimizes the time management of the excavation operation, thereby accelerating the progress of the project and shortening the construction period.
[0033] Reinforcement measures such as the construction of an advance large pipe shed and a second set of arches in the dark excavation section were adopted, and the excavation boundary line between the arch and the dark excavation section was calibrated. At the same time, the tunnel axis and the guide wall construction section were measured and laid out. When the open excavation section was completed, the advance large pipe shed and the second set of arches in the dark excavation section were constructed simultaneously. This effectively prevented ground movement and landslides in the complex geological environment, enhanced the structural stability of the tunnel, and reduced technical requirements during the construction process.
[0034] 2. This construction method adopts non-explosive excavation technology. By accurately selecting the matching machinery and construction methods according to the design drawings and stratum conditions, a breaker is selected for the broken stratum, and a water-grinding drill is selected for core splitting excavation for the harder stratum. This ensures that the construction method can adapt to different geological conditions and improves the reliability and safety of the construction. In terms of slag treatment, an efficient mechanical coordination strategy is adopted, such as the coordinated use of excavators and slag trucks, and the slag is loaded in sections with deep and shallow burials at the entrances and exits, which optimizes the slag transportation route and reduces environmental pollution during construction and the impact on the surrounding environment. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] In order to more clearly illustrate the specific implementation of the present invention, the following will briefly introduce the drawings required for use in the specific implementation. In all the drawings, each element or part is not necessarily drawn according to the actual scale.
[0036] Figure 1 A flow chart of a mountain city subway entrance and exit construction method provided by the present invention;
[0037] Figure 2 This is a schematic diagram of the construction of an advanced large pipe shed in a mountain city subway entrance and exit construction method of the present invention;
[0038] Figure 3 It is a construction schematic diagram of the dark excavation section and the open excavation section in a mountain city subway entrance and exit construction method of the present invention;
[0039] Figure 4 It is a structural schematic diagram of the secondary lining in a mountain city subway entrance and exit construction method of the present invention;
[0040] Figure 5 It is a cross-sectional schematic diagram of a steel frame in a mountain city subway entrance and exit construction method of the present invention;
[0041] Reference numerals:
[0042] 1. Mortar anchor rods; 2. Excavation contour line; 3. Concrete layer; 4. Waterproof layer; 5. Secondary lining; 6. Steel frame; 7. First locking foot anchor rods; 8. Open excavation section; 9. Main station; 10. First shallow buried area; 11. Second shallow buried area; 12. Deep buried area; 13. Demarcation line; 14. First set of arches; 15. Intercepting ditch; 16. Backslope anchor rods; 17. Earthwork of the upper step of the arch; 18. Core rock column of the upper step; 19. Second set of arches; 20. Advance large pipe shed; 21. Second locking foot anchor rods; 22. Earthwork of the step below the arch; 23. I-beam. DETAILED DESCRIPTION
[0043] The present invention is further described in detail below in conjunction with the accompanying drawings. It is necessary to point out here that the following specific implementation methods are only used to further illustrate the present invention and cannot be understood as limiting the scope of protection of the present invention. Technicians in this field can make some non-essential improvements and adjustments to the present invention based on the above application content.
[0044] Example:
[0045] like Figure 1 , 3 As shown, the present invention provides a method for constructing a mountain city subway entrance and exit, comprising the following steps: clarifying the geological conditions, determining the open excavation section 8 and the dark excavation section of the subway entrance and exit, the dark excavation section comprising a first shallow buried area 10, a second shallow buried area 11 and a deep buried area 12, wherein it can be understood that the first shallow buried area 10 is an ultra-shallow buried area, and the soil cover thickness of the tunnel top is between 2m and 5m, the second shallow buried area 11 is an ordinary shallow buried area, and the soil cover thickness of the tunnel top is between 5m and 10m, and the soil cover thickness of the tunnel top of the deep buried area 12 is more than 10m.
[0046] Select the supporting machinery and choose different excavation methods according to different cross-section strata. The specific steps for selecting different excavation methods according to different cross-section strata are: use a breaker hammer to excavate the broken section of the large-section strata, use a water-mill drill to excavate the area where the breaker hammer cannot be excavated, and use a water-mill drill to excavate the hard section of the small-section strata. Among them, when using a water-mill drill to excavate the core, the overlap distance between the two holes is controlled at 20mm, and when the water in the tunnel is deep due to water seepage in the cracks, which affects the drilling construction, drainage should be carried out.
[0047] like Figure 2As shown, in this embodiment, after the construction preparation is completed, the entrance and exit construction site is leveled, and a ditches 15 are set around the foundation pit and shaft of the open-cut section 8, and then the open-cut section 8 is excavated in layers, and the first set of arches 14 are constructed at the entrance of the first shallow buried area 10. The entrance of the first shallow buried area 10 is supported by the first set of arches 14 to improve the safety during construction. When the open-cut section 8 is excavated in layers, the soil section is directly excavated by an excavator, and the rock section is crushed and excavated by a breaker. The excavation is layered by 1.5m, and the support is completed in time after each 1.5m of excavation. In the process of layered excavation, the spray anchor support structure is constructed for each layer in an alternating cycle. After the excavation and support of all layers are completed, the entrance and exit floor cushion layer is poured to seal the bottom, and the dark excavation section is prepared for construction.
[0048] like Figure 2 , 3 As shown, in this embodiment, the boundary line 13 between the second set of arches 19 and the dark excavation section is determined, the tunnel axis and the guide wall construction operation section are measured and laid out, and then the second set of arches 19 and the advance large pipe shed 20 of the dark excavation section are constructed to reinforce the tunnel excavation area. Among them, the boundary line 13 between the second set of arches 19 and the dark excavation section is also the boundary line between the open excavation section 8 and the dark excavation section. The specific steps of constructing the second set of arches 19 and the advance large pipe shed 20 of the dark excavation section are as follows: excavate the upper backslope of the second set of arches 19 and construct the backslope anchor rods 16; excavate the earthwork 17 of the upper step of the arch, reserve the upper step core rock column 18 with a thickness of not less than 3m, continue to construct the upper step I-beam 23 and the second set of arches 19 here, and set the second locking foot anchor rod 21 at the arch foot of the second set of arches 19, and set the advance large pipe shed 20 above the second set of arches 19; excavate the earthwork 22 of the lower step of the arch, construct the lower step I-beam 23 and the second set of arches 19 around the contour of the tunnel side wall.
[0049] like Figures 2 to 5 As shown, two independent working faces are set up at both ends of the tunnel for zoned excavation, and initial support construction is carried out on the dark excavation section, and the slag is transported during the excavation. The specific steps of setting up two independent working faces at both ends of the tunnel for zoned excavation are: combined with a breaker hammer and a water-grinding drill, the full-section method or the step method is used for construction, and excavation is carried out from the open excavation section 8 to the main station 9 side. After the main station 9 side is ready for excavation, the deep buried area 12 is excavated from the main station 9 side to the open excavation section 8. When the excavation reaches the dividing line 13, the two-way excavation is stopped and the deep buried area 12 is converted to one-way excavation. Among them, it is necessary to ensure that the minimum spacing of the two-way excavation is not less than 10m. When performing zoned excavation, the excavation cycle footage of the second shallow buried area 11 and the first shallow buried area 10 is carried out according to the spacing of 1 steel frame 6, while the excavation cycle footage of the deep buried area 12 does not exceed the spacing of 2 steel frames 6.
[0050] The specific steps of the initial support construction of the dark excavation section are: mortar anchor rods 1 are installed on the arch and side walls, steel frames 6 and meshes are installed, and the first locking foot anchor rods 7 are constructed and the meshes are sprayed with concrete layers 3. In the initial support construction of the dark excavation section of the tunnel, the contour line 2 is first excavated on the exposed rock surface, and a layer of concrete is sprayed to seal it. Then, the mortar anchor rods 1 and the steel frame 6 are installed on the arch and side walls. Specifically, two first locking foot anchor rods 7 with an incident angle of about 35° will be installed at the bottom of the steel frame 6 to enhance the stability of the structure. In addition, combined with the use of meshes, the entire structure is sprayed with a concrete layer 3 to form a more solid support body. A waterproof layer 4 is laid on the secondary lining 5. Before laying the waterproof layer 4, it should be ensured that there is no obvious water accumulation on the surface of the secondary lining 5; if leakage is found in some areas, grouting should be carried out immediately to seal the leakage point, and the grouting pressure should be strictly controlled to prevent possible structural damage.
[0051] The specific steps of slag transportation are as follows: for the different entrances and exits of the deep buried area 12 and the first shallow buried area 10, a differentiated slag transportation method is adopted. For the deep buried area 12, the slag is transported to the ground through the station construction channel by using the cooperation of the excavator and the slag transport vehicle; at the straight section at the station end, the slag truck stops for loading, and the slag is turned over to the straight section by the excavator in sequence; for the second shallow buried area 11 and the first shallow buried area 10, an excavator and a crawler transport vehicle are selected to work together to directly transport the slag out through the entrance and exit channels. In addition, in some embodiments, in the slope section of the deep buried area 12, due to the steep slope, the use of a breaker for excavation may cause the equipment to become unstable, so the excavation of the deep buried slope section requires the use of the slag filling construction of the supported slag section formed by the excavated section.
[0052] During the construction period, strict monitoring measures are implemented to monitor the status of surrounding rock, support structure, surface and adjacent pipelines; through real-time data analysis and prediction, the construction design is adjusted in time to ensure construction safety and project progress.
[0053] In summary, the present invention provides a mountain city subway entrance and exit construction method, which includes the selection of mechanical matching for the dark excavation section, the construction of the open excavation section 8 foundation pit, and the deep and shallow buried zoning excavation of the dark excavation section of the entrance and exit tunnel, mainly including selecting suitable dark excavation section mechanical equipment according to the degree of rock fragmentation and the change of cross-sectional size, wherein a breaker hammer is selected for the broken rock layer, and a water-grinding drill is selected for the relatively hard layer for construction; after the construction preparation is completed, the site of the open excavation section 8 of the entrance and exit needs to be leveled, and a drainage ditch 15 is set up, and then the open excavation section 8 is started for layered slope excavation, the excavation layer height is strictly controlled, the sprayed anchor support is completed in time and the monitoring data is recorded in detail; next, the advanced large pipe shed 20 and the second set of arches 19 of the dark excavation section are constructed to achieve grouting reinforcement. Furthermore, the excavation of the dark-cut section of the entrance and exit is divided into two working faces. One is from the open-cut section 8 to the first shallow buried area 10 and the second shallow buried area 11 on the side of the main station 9. The second is when conditions on the side of the main station 9 permit, excavation is carried out simultaneously from the side of the main station 9 to the open-cut section 8 to the boundary line 13 of the deep and shallow buried areas, and then it is switched to one-way excavation to support the deep buried area 12. During the excavation process, mechanical equipment and working methods are reasonably converted according to the size of the cross-section. Then, different slag discharge methods are used to improve slag discharge efficiency. Finally, through continuous geological monitoring, the safety and stability of the subway entrances and exits and surrounding structures are ensured.
[0054] Specific usage and beneficial effects of the present invention:
[0055] The construction preparation part of this construction method selects appropriate mechanical equipment according to the degree of rock fragmentation and cross-sectional changes to ensure construction safety and reduce construction difficulty. The open-cut section 8 adopts layered excavation and shotcrete support to reduce ground settlement and the impact on existing structures. An advance large pipe shed 20 and a second set of arches 19 are set up in the dark-cut section for support and reinforcement. The dark-cut section adopts zoned excavation support to solve the disturbance to the building during the dark-cut process, reduce construction risks, and ensure construction efficiency.
[0056] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. It is obvious to those skilled in the art that the present invention is not limited to the details of the above exemplary embodiments. On the basis of the present invention, some modifications or improvements can be made thereto, which is obvious to those skilled in the art. Therefore, these modifications or improvements made on the basis of not departing from the spirit of the present invention all belong to the scope of protection claimed by the present invention.
Claims
1. A construction method for mountain city subway entrances and exits, It is characterized in that The following steps are involved: The ground conditions are clarified, and the open excavation section (8) and the dark excavation section of the subway entrance and exit are determined, wherein the dark excavation section includes a first shallow buried area (10), a second shallow buried area (11) and a deep buried area (12); Select supporting machinery and choose different excavation methods according to different cross-section strata; Leveling the entrance and exit construction site, and setting a water intercepting ditch (15) around the foundation pit and the vertical shaft of the open-cut section (8), then excavating the open-cut section (8) in layers, and constructing a first set of arches (14) at the entrance of the first shallow buried area (10); Determine the boundary line (13) between the second set of arches (19) and the dark excavation section, the boundary line (13) being the boundary line between the second shallow buried area (11) and the deep buried area (12), measure and lay out the tunnel axis and the guide wall construction operation section, and then construct the second set of arches (19) and the advance large pipe shed (20) of the dark excavation section; Two independent working faces are set up at both ends of the tunnel for zoned excavation, and initial support construction is carried out on the dark excavation section, and soil and muck transportation is carried out during excavation; The entire construction process is monitored and measured, and the construction environment is monitored.
2. A mountain city subway entrance and exit construction method according to claim 1, It is characterized in that The specific steps of selecting different excavation methods according to different cross-section strata are: For large-section broken sections, mechanical excavation with a breaker hammer is used. For areas that cannot be excavated by a breaker hammer, coring and splitting excavation with a water-grinding drill is used. For small-section hard sections, coring and splitting excavation with a water-grinding drill is used.
3. A mountain city subway entrance and exit construction method according to claim 2, Features: When the water-grinding drill is used for core splitting excavation, the overlap distance between the two holes is controlled at 20 mm, and drainage work is performed when water accumulates in the tunnel due to water seepage through cracks.
4. A mountain city subway entrance and exit construction method according to claim 1, Features: While the open cut section (8) is being excavated in layers, the sprayed anchor support structure is constructed on each layer in an alternating cycle. After the excavation and support of all layers are completed, the entrance and exit floor cushion layer is poured to seal the bottom, preparing for the construction of the dark cut section.
5. A mountain city subway entrance and exit construction method according to claim 4, Features: When the open cut section (8) is excavated in layers, an excavator is used for excavation of the soil section, and a breaker is used for crushing and excavation of the rock section. The excavation is carried out in layers of 1.5 m, and support is completed in time after each 1.5 m of excavation.
6. A mountain city subway entrance and exit construction method according to claim 5, It is characterized in that The specific steps of the initial support construction of the dark excavation section are: Mortar anchor rods (1) are installed on the arch and the side wall, a steel frame (6) and a mesh are installed, a first locking anchor rod (7) is constructed, and a sprayed concrete layer (3) is constructed on the mesh.
7. A mountain city subway entrance and exit construction method according to claim 1, It is characterized in that The specific steps of setting up two independent working faces at both ends of the tunnel for partitioned excavation are: The full-section method or step method is adopted for construction, and excavation is carried out from the open-cut section (8) to the main station (9) side. When the main station (9) side is ready for excavation, the deep buried area (12) is excavated from the main station (9) side to the open-cut section (8). When the excavation reaches the dividing line (13), the two-way excavation is stopped and the deep buried area (12) is excavated in one direction.
8. A mountain city subway entrance and exit construction method according to claim 7, Features: When performing the zoned excavation, the excavation cycle footage of the second shallow buried area (11) and the first shallow buried area (10) is carried out at a spacing of one steel frame (6), while the excavation cycle footage of the deep buried area (12) does not exceed a spacing of two steel frames (6).
9. A mountain city subway entrance and exit construction method according to claim 1, It is characterized in that The specific steps of constructing the second set of arches (19) and the advanced large pipe shed (20) of the dark excavation section are as follows: Excavating the upper backslope of the second set of arches (19) and installing backslope anchors (16); Excavate the upper step of the arch (17), reserve the upper step core rock column (18) with a thickness of not less than 3m, continue to construct the upper step I-beam (23) and the second arch (19) here, set the second foot locking anchor rod (21) at the arch foot of the second arch (19), and set the advance large pipe shed (20) above the second arch (19); and The earth and stone of the step below the arch are excavated (22), and the I-beam (23) of the step below and the second set of arches (19) around the outline of the tunnel side wall are constructed.
10. A mountain city subway entrance and exit construction method according to claim 1, It is characterized in that The specific steps of the slag transportation are: Differentiated methods of transporting slag are adopted for different entrances and exits of the deep buried area (12) and the first shallow buried area (10). For the deep buried area (12), the slag is transported to the ground through the station construction passage by using the cooperation of an excavator and a slag transport vehicle; At the straight section at the station end, the muck truck stops for loading, and the muck is turned over by the excavator to the straight section in sequence. At the deep-buried slope section, the muck of the supported slag section formed by the excavated section is used for filling construction; For the second shallow buried area (11) and the first shallow buried area (10), an excavator and a crawler transport vehicle are selected to work together to directly transport the slag out through the entrance and exit passages.