Real-time monitoring method for construction of large-span hyperbolic steel connecting bridge
By setting sensors on the steel bridge to monitor stress and strain, temperature and dynamic characteristics in real time, the problem of the existing technology being unable to monitor the strain and deformation of key parts of the structure is solved, ensuring safety during the construction and operation period, reducing the risk of accidents and Save costs.
Patent Information
- Application Number
- CN202411150723.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-21
- Publication Date
- 2024-11-15
AI Technical Summary
The existing technology cannot effectively monitor the strain, deformation, temperature and vibration characteristics of key parts of steel bridge structures, and cannot evaluate structural safety in real time, resulting in the inability to ensure the safety of the construction and operation periods, which may lead to major engineering accidents.
Set up sensors on the main structure and columns of the steel bridge to monitor stress and strain, temperature, deflection and dynamic characteristics in real time, select appropriate monitoring points, and issue early warning reminders through a comprehensive evaluation and feedback mechanism to avoid situations that endanger the safety of the structure.
Real-time monitoring of steel bridge structures is achieved, ensuring safety during construction and operation periods, reducing the risk of major accidents, reducing the impact on the lives of surrounding residents, and saving construction periods and costs.
Smart Images

Figure CN118960854A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of steel bridge construction, and in particular to a real-time monitoring method for the construction of a large-span hyperbolic steel bridge. Background Art
[0002] The steel bridge of a certain project spans the main urban road. The width of the main urban road is 40 meters, with 8 lanes in both directions and a span of 72.5 meters. The highest installation elevation is 19.4 meters. The net height below the steel bridge is 12.495 meters. The horizontal and vertical surfaces of the steel bridge are curved surfaces, and the columns of the steel bridge are Y-shaped columns. There are subway stations and bus stations under the steel bridge. There are high-voltage cables such as 220KV on the east side and 110KV on the west side. The single-hole spans are 10.5m, 48m, and 13.5m respectively. The left and right sides are connected to the main structure through spherical steel bearings. The bridge width at the bearing is about 12m. There are twisted Y-shaped steel columns on both sides of the middle span. The load is transferred to the foundation through the pile foundation cap. The bridge width in the middle span is 6m, and the total area of the overpass is 711㎡.
[0003] Due to the complexity of the project, it is necessary to monitor and evaluate the stress and damage of the steel bridge structure before, during and after the construction, and to issue early warnings for situations that endanger the safety of the structure, so as to avoid major engineering accidents to the greatest extent and maintain the safety of the structure during construction and operation. The conventional method of using a total station to monitor the settlement of the steel bridge cannot monitor key indicators such as strain, deformation, temperature, and vibration characteristics of key parts of the structure. It also cannot evaluate the safety of the structure in real time and cannot ensure the safety of normal use of the structure. Summary of the invention
[0004] In order to overcome the defects existing in the prior art, the present invention provides a real-time monitoring method for the construction of a large-span hyperbolic steel bridge, which conducts real-time monitoring of the stress, deformation and vibration of the structure around the clock, maintains the safety of the structure during construction and operation, and avoids the occurrence of major engineering accidents to the greatest extent.
[0005] In order to achieve the above object, the present invention provides a real-time monitoring method for the construction of a large-span hyperbolic steel bridge. The steel bridge includes a main steel structure and columns supported at the bottom of the main steel structure. The real-time monitoring method includes the following steps:
[0006] Select different monitoring points on the main steel structure and columns of the steel bridge;
[0007] A number of sensors are arranged at each monitoring point to monitor the stress, strain, temperature, deflection and dynamic characteristics of the point;
[0008] Real-time monitoring of stress, strain, temperature, and deflection during structural construction, and real-time monitoring of stress, strain, temperature, and dynamic characteristics during operation after construction is completed;
[0009] A comprehensive assessment of the stress and damage status of the structure is conducted based on the real-time monitoring data of each sensor, and corresponding feedback is given based on the assessment results.
[0010] Preferably, when different monitoring points are selected on the main steel structure and columns of the steel bridge, the selection method specifically includes:
[0011] At least 6 deflection monitoring points are arranged at both ends and in the middle of the main steel structure;
[0012] Multiple stress-strain and temperature monitoring points are arranged at the maximum stress-bearing positions on the trusses of the main steel structure and at the bottom of the columns.
[0013] Preferably, after a plurality of temperature monitoring points are arranged, a temperature sensor is installed at each temperature monitoring point.
[0014] Preferably, after multiple stress-strain monitoring points are arranged, a strain sensor is provided at each stress-strain monitoring point, and at least two acceleration sensors are provided one-to-one correspondingly at at least two stress-strain monitoring points located at the mid-span position of the mid-span of the truss.
[0015] Preferably, when multiple stress-strain and temperature monitoring points are arranged on the truss of the main steel structure, the arrangement positions include the upper chord, lower chord, diagonal rods, vertical rods, upper chord beams and lower chord beams constituting the truss of the main steel structure.
[0016] Preferably, when comprehensively evaluating the stress and damage state of the structure based on the data measured by each sensor and providing corresponding feedback based on the evaluation results, the evaluation method includes:
[0017] Compare the real-time monitoring data of each sensor with the corresponding monitoring threshold. If the real-time monitoring data of the sensor is less than the monitoring threshold, it is considered safe and no processing is done.
[0018] If the data monitored by the sensor in real time is greater than the monitoring threshold, it is considered to be in a dangerous stage and an early warning reminder is issued.
[0019] Due to the adoption of the above technical solution, the present invention has the following beneficial effects:
[0020] 1) It changes the traditional method of using total stations to monitor the settlement of steel bridges. It cannot monitor key indicators such as strain, deformation, temperature, vibration characteristics of key parts of the structure, cannot evaluate the safety of the structure in real time, and cannot ensure the safety of normal use of the structure.
[0021] 2) Through monitoring of stress, strain, temperature and deflection during the structural construction process; monitoring of stress, strain, temperature and dynamic characteristics during the operation period, and measuring key indicators such as strain, deformation, temperature and vibration characteristics of the structure around the clock, the safety of structural construction and operation is ensured, which reduces the impact on the lives of surrounding residents. At the same time, it can also ensure the safety and controllability of on-site construction and operation, saving construction time and costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0023] Figure 1 1 is a diagram of the arrangement of stress, strain and temperature monitoring in an embodiment of the present invention.
[0024] Figure 2 Schematic diagram of the position of the upper chord beam monitoring point in the embodiment of the present invention.
[0025] Figure 3 Schematic diagram of the position of the monitoring point of the lower chord beam in an embodiment of the present invention.
[0026] Figure 4 Schematic diagram of the acceleration monitoring point arrangement in the embodiment of the present invention.
[0027] The corresponding relationship of the numbers in the accompanying drawings is as follows:
[0028] 1-Main steel structure; 2-Column; 3-Upper chord; 4-Lower chord; 5-Diagonal brace; 6-Vertical bar; 7-Upper chord cross beam; 8-Lower chord cross beam; 9-Acceleration monitoring point. DETAILED DESCRIPTION
[0029] The specific embodiments of the present invention are further described below in conjunction with the accompanying drawings. It should be noted that the description of these embodiments is used to help understand the present invention, but does not constitute a limitation of the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.
[0030] See also Figures 1 to 4 As shown, an embodiment of the present invention provides a real-time monitoring method for the construction of a large-span hyperbolic steel bridge. The steel bridge includes a main steel structure and columns supported at the bottom of the main steel structure. The real-time monitoring method includes the following steps:
[0031] Select different monitoring points on the main steel structure 1 and the column 2 of the steel bridge;
[0032] A number of sensors are arranged at each monitoring point to monitor the stress, strain, temperature, deflection and dynamic characteristics of the point;
[0033] Real-time monitoring of stress, strain, temperature, and deflection during structural construction, and real-time monitoring of stress, strain, temperature, and dynamic characteristics during operation after construction is completed;
[0034] Comprehensively evaluate the stress and damage status of the structure based on the real-time monitoring data of each sensor, and make corresponding feedback based on the evaluation results. The evaluation methods include:
[0035] Compare the real-time monitoring data of each sensor with the corresponding monitoring threshold. If the real-time monitoring data of the sensor is less than the monitoring threshold, it is considered safe and no processing is done.
[0036] If the data monitored by the sensor in real time is greater than the monitoring threshold, it is considered to be in a dangerous stage and an early warning reminder is issued.
[0037] Furthermore, when different monitoring points are selected on the main steel structure 1 and the column 2 of the steel bridge, the selection method specifically includes:
[0038] At least 6 deflection monitoring points are arranged at both ends and in the middle of the main steel structure;
[0039] A plurality of stress-strain and temperature monitoring points are arranged at the maximum stress-bearing position on the truss of the main steel structure 1 and at the bottom of the column 2. Preferably, after the plurality of temperature monitoring points are arranged, a temperature sensor is installed at each temperature monitoring point, after the plurality of stress-strain monitoring points are arranged, a strain sensor is installed at each stress-strain monitoring point, and at least two acceleration sensors are arranged one by one at at least two stress-strain monitoring points located at the mid-span position of the mid-span of the truss as acceleration monitoring points 9 for measuring the displacement, velocity and acceleration response spectrum of the structure under dynamic load.
[0040] It should be noted that, in the present embodiment, in the multi-span continuous beam, the middle span support and the middle span position are respectively the points where the positive and negative bending moments are maximum in the plane and out of the plane (under the uniformly distributed lateral action of wind, etc.); the stress of the vertical rod and the diagonal rod at about 1 / 4 of the middle span is greater than that of the same type of rods; the pre-tension is applied to the diagonal rod of the side span and the diagonal rod in the middle span, resulting in the stress of the upper beam of the side span and the diagonal rod in the middle span being greater than that of the same type of rods, that is, the layout position includes the upper chord rod 3, the lower chord rod 4, the diagonal rod 5, the vertical rod 6, the upper chord cross beam 7 and the lower chord cross beam 8 ( Figure 1 The middle number is the corresponding monitoring point). At the same time, column 2 is a key force-transmitting component, so the position near the bottom of column 2 where the force is the largest is also the layout position.
[0041] The embodiments of the present invention are described in detail above with reference to the accompanying drawings, but the present invention is not limited to the described embodiments. For those skilled in the art, various changes, modifications, substitutions and variations of these embodiments are made without departing from the principles and spirit of the present invention, and still fall within the scope of protection of the present invention.
Claims
1. A real-time monitoring method for the construction of a large-span hyperbolic steel bridge, wherein the steel bridge comprises a main steel structure and columns supported at the bottom of the main steel structure, characterized in that: The real-time monitoring method comprises the following steps: Select different monitoring points on the main steel structure and columns of the steel bridge; A number of sensors are arranged at each monitoring point to monitor the stress, strain, temperature, deflection and dynamic characteristics of the point; Real-time monitoring of stress, strain, temperature, and deflection during structural construction, and real-time monitoring of stress, strain, temperature, and dynamic characteristics during operation after construction is completed; A comprehensive assessment of the stress and damage status of the structure is conducted based on the real-time monitoring data of each sensor, and corresponding feedback is given based on the assessment results.
2. The real-time monitoring method for the construction of a long-span hyperbolic steel bridge according to claim 1, characterized in that: When selecting different monitoring points on the main steel structure and columns of the steel bridge, the selection method specifically includes: At least 6 deflection monitoring points are arranged at both ends and in the middle of the main steel structure; Multiple stress-strain and temperature monitoring points are arranged at the maximum stress-bearing positions on the trusses of the main steel structure and at the bottom of the columns.
3. The real-time monitoring method for the construction of a long-span hyperbolic steel bridge according to claim 2, characterized in that: After multiple temperature monitoring points are laid out, a temperature sensor is installed at each temperature monitoring point.
4. The real-time monitoring method for the construction of a long-span hyperbolic steel bridge according to claim 2, characterized in that: After multiple stress-strain monitoring points are arranged, a strain sensor is placed on each stress-strain monitoring point, and at least two acceleration sensors are correspondingly placed on at least two stress-strain monitoring points located at the mid-span position of the mid-span of the truss.
5. The real-time monitoring method for the construction of a long-span hyperbolic steel bridge according to claim 2, characterized in that: When multiple stress-strain and temperature monitoring points are arranged on the truss of the main steel structure, the arrangement positions include the upper chord, lower chord, diagonal rods, vertical rods, upper chord beams and lower chord beams that constitute the main steel structure truss.
6. The real-time monitoring method for the construction of a long-span hyperbolic steel bridge according to claim 2, characterized in that: When comprehensively evaluating the stress and damage status of the structure based on the data measured by each sensor and providing corresponding feedback based on the evaluation results, the evaluation method includes: Compare the real-time monitoring data of each sensor with the corresponding monitoring threshold. If the real-time monitoring data of the sensor is less than the monitoring threshold, it is considered safe and no processing is done. If the data monitored by the sensor in real time is greater than the monitoring threshold, it is considered to be in a dangerous stage and an early warning reminder is issued.
Citation Information
Patent Citations
Movable rapid monitoring system for prefabricated bridge
CN110686726A
Steel structure remote health monitoring platform based on Internet of Things and application method
CN113900381A
Operation period old bridge inspection and evaluation method and system based on mixing of machine vision and sensor
CN118133603A
Novel bridge health monitoring system based on continuous box girder bridge
CN207832236U
Bridge remote monitoring system suitable for suspension bridge
CN211085336U
Cited By
Large-span bidirectional fish-bellied steel truss slippage monitoring method
CN120766492A