Finite element analysis method for health state of power transmission and transformation equipment

By obtaining the prior data of power transmission and transformation equipment and pre-selected micrometeorological test schemes, adjusting and optimizing the finite element model and calculating the characteristic values ​​of the environment, the problem of modeling error in the existing technology is solved, and the health status evaluation of power transmission and transformation equipment is improved Accuracy and reliability.

CN118965911AInactive Publication Date: 2024-11-15STATE GRID SHANDONG ELECTRIC POWER CO LIAOCHENG POWER SUPPLY CO
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411357490.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-27
Publication Date
2024-11-15
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing health monitoring technology of power transmission and transformation equipment relies on automated modeling and cannot truly reflect the actual working status of the equipment and complex physical processes, resulting in the inability to quantify modeling errors, affecting the accuracy and reliability of health status evaluation.

Method used

By obtaining prior data of power transmission and transformation equipment types, calculating the model reduction degree, adjusting and optimizing the three-dimensional finite element model, combining micrometeorological test pre-selected schemes, calculating environmental characteristic values, comprehensively analyzing the data set to obtain a comprehensive health index, and providing health status warnings. .

Benefits of technology

The accuracy of finite element analysis is improved, the deviation between the model and the actual equipment is quantified, the accuracy and credibility of health status evaluation is enhanced, calculation errors and redundant data processing are reduced, and computing resources are saved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118965911A_ABST
    Figure CN118965911A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of finite element simulation, and particularly discloses a finite element analysis method for the health state of power transmission and transformation equipment, which comprises the following steps of: matching an initial three-dimensional finite element model corresponding to the type of the power transmission and transformation equipment, acquiring priori data of the power transmission and transformation equipment, and calculating the model reduction degree; determining a tried three-dimensional finite element model according to the model reduction degree, dividing each tried element, applying the microclimate test preselection scheme to the tried three-dimensional finite element model, and obtaining a tried environment characteristic value and a tried data set of each tried element, and comprehensively analyzing the tested data set and the tested environment characteristic value to calculate a comprehensive health index, and obtaining a health state early warning level based on the comprehensive health index and carrying out marking feedback. According to the method, the finite element analysis precision can be improved, and the comprehensive influence of the tested environment can be quantified, so that the comprehensive evaluation better conforms to the health condition of the power transmission and transformation equipment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of finite element simulation, and specifically relates to a finite element analysis method for the health status of power transmission and transformation equipment. Background Art

[0002] At present, power transmission and transformation equipment plays a vital role in the power system, and its failure may cause serious power outages or equipment damage. Therefore, health status monitoring and analysis of power transmission and transformation equipment is crucial for real-time monitoring of the operating status of equipment. Through this monitoring, early aging or abnormal conditions of equipment can be paid attention to in time, and appropriate maintenance and care measures can be taken. This preventive maintenance can not only effectively extend the service life of equipment, reduce frequent overhaul and replacement, and reduce operation and maintenance costs, but also provide detailed data on the operating status of equipment, help formulate reasonable maintenance and replacement plans, reduce unnecessary overhaul and downtime, and reduce production losses. In addition, health status monitoring can also detect and warn potential faults, prevent sudden equipment failures, and thus ensure the safe and stable operation of the power system.

[0003] However, existing health monitoring technologies have some shortcomings. Traditional modeling methods for health monitoring of power transmission and transformation equipment rely too much on the automated output of modeling software. This automated modeling is often based on standardized templates or preset parameters, resulting in the model being unable to truly reflect the actual working status and complex physical processes of the equipment. When running the model, it is easy to ignore boundary settings and the quantification of execution errors, which cannot fully fit the actual working structure and material properties of the power transmission and transformation equipment, resulting in the modeling errors being unable to be quantified and measured in the process of comprehensive health status evaluation. This may miss potential health problems or signs of failure, affecting the accuracy and reliability of the health status assessment and judgment of the power transmission and transformation equipment through the model. Summary of the invention

[0004] In view of the deficiencies of the prior art, the present invention provides a finite element analysis method for the health status of power transmission and transformation equipment, which can improve the accuracy of finite element analysis and quantify the comprehensive impact of the test environment, so that the comprehensive evaluation is more in line with the health status of the power transmission and transformation equipment.

[0005] To achieve the above objectives, the present invention is implemented through the following technical solutions: Acquire the type of power transmission and transformation equipment, and obtain an initial three-dimensional finite element model corresponding to the type of power transmission and transformation equipment from a database based on the type of power transmission and transformation equipment; Acquire the prior data of the power transmission and transformation equipment corresponding to the type of the power transmission and transformation equipment, the prior data of the power transmission and transformation equipment including model restoration data and test bearing capacity data; Calculate the model restoration degree based on the prior data of the power transmission and transformation equipment and determine whether to adjust and optimize the initial three-dimensional finite element model according to the model restoration degree to obtain the three-dimensional finite element model of the test object; Determine each test element of the three-dimensional finite element model of the test subject; Apply the micro-meteorological test pre-selected scheme stored in the database to the three-dimensional finite element model of the test subject and calculate the environmental characteristic values ​​after the test; After applying the micrometeorological test preselection scheme to the three-dimensional finite element model, the test data set of each test element is obtained; The comprehensive health index of the corresponding power transmission and transformation equipment type is calculated by comprehensively analyzing the test data set and the environmental characteristic values ​​after the test. The health status warning level is obtained based on the comprehensive health index and marked for feedback.

[0006] Preferably, the model restoration degree is calculated based on the prior data of the power transmission and transformation equipment, and it is determined whether to adjust and optimize the initial three-dimensional finite element model according to the model restoration degree to obtain the three-dimensional finite element model for trial use. The specific matching process is: Acquire initial data corresponding to the type of the power transmission and transformation equipment, the initial data including elastic modulus, thermal conductivity and electrical conductivity; The model restoration data is integrated and analyzed with the initial data to obtain the model restoration degree, and the model restoration data includes the model elastic modulus, the model thermal conductivity and the model electrical conductivity; Compare the model restoration degree with the model restoration threshold stored in the database: If the model restoration degree is less than the model restoration threshold stored in the database, the initial three-dimensional finite element model needs to be adjusted and optimized, and the three-dimensional finite element model of the subject after adjustment and optimization is output; If the degree of model restoration is greater than or equal to the model restoration threshold stored in the database, the initial three-dimensional finite element model does not need to be adjusted and optimized, and is output as a three-dimensional finite element model for trial use.

[0007] Preferably, the specific analysis process of determining each test element of the three-dimensional finite element model is as follows: The three-dimensional finite element model of the subject is randomly divided into a number of auxiliary positioning grids; Obtain the test bearing capacity data corresponding to any auxiliary positioning grid, and calculate the test bearing capacity evaluation value of the auxiliary positioning grid based on the test bearing capacity data; The test bearing capacity assessment values ​​of each auxiliary positioning grid are compared, and the center of the auxiliary positioning grid with the largest test bearing capacity assessment value is marked as the power transmission and transformation equipment positioning point. Based on the power transmission and transformation equipment positioning point, multiple test elements of the standard volume are marked divergently toward the boundary of the three-dimensional finite element model, and the remaining boundary part that is less than the standard volume is not marked as the test element.

[0008] Preferably, the tested bearing capacity data include average spacing distance of load points, yield strength per unit cross section, maximum tensile strength and crack volume ratio.

[0009] Preferably, the test tolerance evaluation value is specifically calculated by the following formula: ; Where c is the assessed value of the bearing capacity of the test piece, f is the average spacing of the load points, q is the yield strength per unit section, d is the maximum tensile strength, w is the crack volume percentage, and e is a natural constant.

[0010] Preferably, the specific analysis process of calculating the post-test environmental characteristic value is as follows: Obtain the post-test environmental characteristic set of the micro-meteorological test pre-selection scheme, which includes the atmospheric ion conductivity deviation value, aerosol concentration change value, cooling medium impurity increase rate and dust particle density increase value; Obtain the post-test environmental characteristic fusion factor set set in the database. The test micro-meteorological characteristic fusion factor set includes the atmospheric ion conductivity deviation value fusion factor, the aerosol concentration change value fusion factor, the cooling medium impurity rise rate fusion factor and the dust particle density rise value fusion factor; The post-test environment characteristic value is calculated based on the post-test environment characteristic set, the post-test environment characteristic fusion factor set set in the database and the test characteristic fusion model.

[0011] Preferably, the specific acquisition process of obtaining the test data set of each test element is as follows: Obtaining test feedback imaging of any test element, the test feedback imaging includes vibration waveform diagram, spectrum component diagram, power harmonic amplitude curve and load capacity margin curve; Acquire the test standard imaging and map the test feedback imaging onto the test standard imaging, wherein the test standard imaging includes a vibration waveform reference image, a spectrum component standard image, a power harmonic amplitude standard curve, and a load capacity margin standard curve; Obtain the deviations between the test feedback images and the test standard images of all the test elements and mark them in turn as the vibration waveform test value, the spectrum test value, the power harmonic amplitude test value and the load capacity margin test value; The vibration waveform test value, the frequency spectrum test value, the power harmonic amplitude test value and the load capacity margin test value are recorded as the test data set of the corresponding test element.

[0012] Preferably, the comprehensive analysis of the test data set and the post-test environmental characteristic values ​​to calculate the comprehensive health index of the corresponding power transmission and transformation equipment type is as follows: Performing mean processing on each test data set to obtain a test mean data set, the test mean data set includes a test mean of a vibration waveform, a test mean of a frequency spectrum, a test mean of an electric harmonic amplitude, and a test mean of a load capacity margin; Obtaining a set of tested weight factors set in a database, the tested weight factor set including a vibration waveform tested weight factor, a spectrum tested weight factor, a power harmonic amplitude tested weight factor, and a load capacity margin tested weight factor; The comprehensive health index is calculated based on the subject mean data set, the subject weight factor set set in the database, and the post-test environmental characteristic values.

[0013] Preferably, the comprehensive health index is specifically calculated by the following formula: ; In the formula, is the comprehensive health index, is the tested mean value of the vibration waveform, is the spectrum test mean, is the tested mean value of power harmonic amplitude, is the tested mean value of load capacity margin, is the vibration waveform test weight factor, is the spectrum subject weight factor, is the tested weight factor of power harmonic amplitude, is the load capacity margin test weight factor, T is the environmental characteristic value after the test, and e is a natural constant.

[0014] Preferably, the health status warning level is obtained based on the comprehensive health index and marked for feedback, and the specific analysis process is: Get a comprehensive health index; Obtain the health warning signal interval endpoints stored in the database; Compare the endpoints of the health warning signal interval stored in the database with the comprehensive health index to obtain the health status warning level corresponding to the comprehensive health index; Mark the health status warning level of the power transmission and transformation equipment, and send a warning signal to the power transmission and transformation equipment terminal based on the health status warning level.

[0015] Compared with the prior art, the present invention has the following beneficial effects: The present invention abandons the traditional modeling method of directly outputting modeling by modeling software when carrying out three-dimensional finite element modeling. Instead, it comprehensively considers the equipment structure and material properties based on the type matching prior data of the power transmission and transformation equipment, checks and compares the model restoration data to obtain the model restoration degree, and evaluates the three-dimensional finite element modeling effect on this basis. On the basis of accurately evaluating the three-dimensional finite element model to reflect the material characteristics of the actual equipment and improving the restoration degree of the equipment structure, the deviation between the model and the actual equipment is quantified to accurately express the degree of fit between the three-dimensional finite element modeling and the actual power transmission and transformation equipment, participate in subsequent adjustment and optimization of the modeling, and improve the accuracy of finite element analysis.

[0016] The present invention is based on the random division of a three-dimensional finite element model of a test subject into a number of auxiliary positioning grids, determines the positioning point of the power transmission and transformation equipment on the basis of the auxiliary positioning grids through the test bearing capacity data in the prior data of the power transmission and transformation equipment, quantifies the positioning characteristics of the power transmission and transformation equipment, and divides the test elements divergently with the positioning point of the power transmission and transformation equipment as the center, while improving the division accuracy, the remaining boundary parts that are less than the standard volume are not marked as test elements, which can effectively reduce the size of the calculation domain, significantly reduce redundant data processing and useless calculations in the calculation, save computing power resources, and overall by refining the test elements in the key areas and simplifying the test elements in the boundary areas, it can reduce local calculation errors and obtain more accurate simulation results.

[0017] In the process of obtaining the comprehensive health index by comprehensively evaluating the health status of the power transmission and transformation equipment, the present invention does not directly process the test data set of each test element, but comprehensively analyzes the test data set. In the specific numerical calculation process, the test data set is averaged, and the calculation results are ensured to be more in line with the actual conditions of the equipment by excluding abnormal data points, thereby improving the accuracy of data analysis, helping to remove the influence of extreme values ​​and noise in the data set on the calculation results, and making the comprehensive evaluation more stable and reliable. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the method flow of the present invention; Figure 2 A step diagram for obtaining the health status warning level based on the comprehensive health index and marking feedback; Figure 3 This is an image of the changes in the environmental characteristic values ​​and the rising rate of impurities in the cooling medium after the test. DETAILED DESCRIPTION

[0019] The technical solutions in the embodiments of the present invention are clearly and completely described below in conjunction with the accompanying drawings.

[0020] like Figure 1 As shown, the present invention provides a finite element analysis method for the health status of power transmission and transformation equipment, including: obtaining the type of power transmission and transformation equipment, and matching the initial three-dimensional finite element model corresponding to the type of power transmission and transformation equipment from a database based on the type of power transmission and transformation equipment, the initial three-dimensional finite element model is stored in the database, firstly the user inputs the type of power transmission and transformation equipment, performs a retrieval operation, and the database returns the initial three-dimensional finite element model that matches the query condition.

[0021] The prior data of the power transmission and transformation equipment corresponding to the power transmission and transformation equipment type is obtained. The prior data of the power transmission and transformation equipment includes model restoration data and test bearing capacity data. The process of obtaining the prior data of the power transmission and transformation equipment is as follows: the power transmission and transformation equipment type is stored as a designated tag of the power transmission and transformation equipment, the designated tag of the power transmission and transformation equipment is compared with the prior data of the power transmission and transformation equipment corresponding to each power transmission and transformation equipment matching tag stored in the database, and the power transmission and transformation equipment matching tag that is the same as the designated tag of the power transmission and transformation equipment is found, so as to obtain the prior data of the power transmission and transformation equipment corresponding to the matching tag of the power transmission and transformation equipment.

[0022] By using the designated tags stored corresponding to the types of power transmission and transformation equipment as the core matching basis, efficient and accurate data matching can be achieved, and standardized classification of power transmission and transformation equipment based on equipment types can be realized, greatly improving the efficiency of data management and utilization. Subsequent data matching and extraction can be performed more accurately on the basis of the working logic and specific structure corresponding to the specific types of power transmission and transformation equipment, and dynamic update matching can be achieved. At the same time, more targeted decision-making data support can be provided for the subsequent three-dimensional finite element modeling and test element positioning and division of power transmission and transformation equipment.

[0023] The degree of model restoration is calculated based on the prior data of the power transmission and transformation equipment, and according to the degree of model restoration, it is determined whether to adjust and optimize the initial three-dimensional finite element model to obtain the three-dimensional finite element model for trial use.

[0024] The specific analysis process is as follows: obtain the initial data corresponding to the type of power transmission and transformation equipment, which includes elastic modulus, thermal conductivity and electrical conductivity. The elastic modulus can be measured by material mechanics testing, such as tensile testing or compression testing, to measure the deformation of the material under stress, thereby calculating the elastic modulus. Thermal conductivity is measured by a steady-state method or a transient method. The steady-state method measures the temperature difference under a constant heat flow, and transient methods such as the laser flash method can measure the thermal conductivity of the material in a relatively short time. Electrical conductivity can be obtained by a resistance measurement method, which measures the current response of the material under a certain voltage to calculate the electrical conductivity. The model restoration data is fused and analyzed with the initial data to obtain the model restoration degree. The model restoration data includes the model elastic modulus, model thermal conductivity and model electrical conductivity. The model restoration data are all pre-stored in the database and can be directly obtained and used.

[0025] The specific calculation formula for obtaining the model restoration degree is as follows (before calculation, the relevant parameters are processed in scalar quantities and the units are deleted, the same below): ; In the formula, is the model reduction degree, St is the elastic modulus, Sr is the thermal conductivity, Sd is the electrical conductivity, Ct is the model elastic modulus, Cr is the model thermal conductivity, and Cd is the model electrical conductivity.

[0026] It is used to evaluate the degree of fit between the initial three-dimensional finite element modeling and the actual power transmission and transformation equipment through the model restoration data and the initial data, and to quantitatively evaluate the degree of restoration of the initial three-dimensional finite element modeling. The model restoration data is used to describe the restoration of various structural features of the three-dimensional finite element modeling of the power transmission and transformation equipment. The elastic modulus is an indicator of the rigidity of the material and affects the degree of deformation of the equipment under mechanical load. Materials with high thermal conductivity can quickly transfer heat, effectively reduce the operating temperature of the equipment, and improve efficiency and reliability. Electrical conductivity directly affects the resistance of the material. High electrical conductivity materials have low resistance, which helps to reduce energy loss and improve the overall efficiency of the electrical system.

[0027] These three parameters are used as the basis for the analysis of the reduction degree because these parameters are important for power transmission and transformation equipment, and there is a certain relationship between them: in power transmission and transformation equipment, selecting materials with high electrical conductivity and appropriate elastic modulus can ensure power transmission efficiency and mechanical stability of the equipment. For components that require good heat dissipation performance, it is also crucial to select materials with high thermal conductivity. In the same material, if it has a high electrical conductivity, it often also exhibits a high thermal conductivity, because both rely on the flow of free electrons.

[0028] When making a three-dimensional finite element model, we abandoned the traditional modeling method of directly outputting the model by modeling software. Instead, we matched the initial three-dimensional finite element model based on the type of power transmission and transformation equipment. The prior data comprehensively considered the equipment structure and material properties to check and compare the model restoration data with the initial data to obtain the model restoration degree. On this basis, we evaluated the three-dimensional finite element modeling effect, quantified the deviation between the model and the actual equipment, and then accurately expressed the degree of fit between the three-dimensional finite element modeling and the actual power transmission and transformation equipment, participated in the subsequent adjustment and optimization of the modeling, and improved the accuracy of the finite element analysis.

[0029] The model restoration degree is compared with the model restoration threshold stored in the database: if the model restoration degree is less than the model restoration threshold stored in the database, the initial three-dimensional finite element model needs to be adjusted and optimized, and after the adjustment and optimization, it is output as the three-dimensional finite element model for trial use; if the model restoration degree is greater than or equal to the model restoration threshold stored in the database, the initial three-dimensional finite element model does not need to be adjusted and optimized, and it is output as the three-dimensional finite element model for trial use.

[0030] The initial three-dimensional finite element model is adjusted and optimized mainly by importing the latest CAD drawings into the modeling software for verification and adjustment, adjusting the three-dimensional model to correct any geometric errors, reviewing the model restoration data one by one, and ensuring that the data collection can truly reflect the structural characteristics and material conditions of the equipment under actual working conditions.

[0031] Determine each test element of the three-dimensional finite element model for the test, and the specific analysis process is: randomly divide the three-dimensional finite element model of the test object into several auxiliary positioning grids; obtain the test bearing capacity data corresponding to any auxiliary positioning grid, and calculate the test bearing capacity evaluation value of the auxiliary positioning grid based on the test bearing capacity data; compare the test bearing capacity evaluation values ​​of each auxiliary positioning grid, mark the center of the auxiliary positioning grid with the largest test bearing capacity evaluation value as the power transmission and transformation equipment positioning point, and mark multiple test elements of standard volume based on the power transmission and transformation equipment positioning point toward the boundary of the three-dimensional finite element model, and the remaining boundary part that is less than the standard volume is not marked as a test element.

[0032] The standard volume can be 1 cubic meter or other volumes. It is randomly divided into several auxiliary positioning grids based on the three-dimensional finite element model of the test subject. The positioning point of the power transmission and transformation equipment is determined on the basis of the auxiliary positioning grid through the test bearing capacity data in the prior data of the power transmission and transformation equipment. The positioning characteristics of the power transmission and transformation equipment are quantified, and the test elements are divided divergently with the positioning point of the power transmission and transformation equipment as the center. While improving the division accuracy, the remaining boundary parts that are less than the standard volume are not marked as test elements, which can effectively reduce the size of the calculation domain, significantly reduce redundant data processing and useless calculations in the calculation, save computing power resources, and overall, by refining the test elements in the key areas and simplifying the test elements in the boundary areas, local calculation errors can be reduced and more accurate simulation results can be obtained.

[0033] The tested bearing capacity data include the average distance between load points, the yield strength per unit section, the maximum tensile strength, and the crack volume percentage. The average distance between load points refers to the average distance between two load points when the power transmission and transformation equipment is subjected to force. The measured values ​​of the distances between different load points in the material are statistically analyzed and the average value is finally taken. The yield strength per unit section refers to the maximum stress that the material can withstand before plastic deformation occurs. The yield strength per unit section can be determined by tensile testing, stretching the specimen to the yield point, and recording the stress value at this time to determine the yield strength. The maximum tensile strength refers to the maximum stress value that the material can withstand during the stretching process. When this value is exceeded, the material will break. The crack volume percentage refers to the proportion of the crack volume in the overall material volume, which is used to evaluate the integrity and durability of the material.

[0034] The specific calculation formula for the test bearing capacity assessment value is: ; Where c is the assessed value of the bearing capacity of the test piece, f is the average spacing of the load points, q is the yield strength per unit section, d is the maximum tensile strength, w is the crack volume percentage, and e is a natural constant.

[0035] c is used to characterize the comprehensive quality of the material structure of the auxiliary positioning grid when it bears the equipment load. The larger the c is, the heavier the load the corresponding auxiliary positioning grid material structure bears when the power transmission and transformation equipment is tested, and it is the key test part that deserves more attention. q and d are key indicators for evaluating the mechanical properties of power transmission and transformation materials, while w significantly reduces these strength values. As w increases, the q and d of the material will decrease, thereby increasing the failure risk of the power transmission and transformation equipment in response to environmental micro-meteorological changes. The larger the f is, the lower the safety of the power transmission and transformation equipment material under a specific load may be, especially in the presence of cracks, the worse the material quality stability of the power transmission and transformation equipment, and a larger f will lead to local stress concentration, thereby increasing the failure risk of the power transmission and transformation equipment at a specific location.

[0036] By analyzing the load point interval, potential local failure locations can be identified, thus providing a basis for equipment positioning design, ensuring that the material can be evenly stressed during the test, and reducing the impact of stress concentration on the material test quality measurement error. q is directly related to the material's load-bearing capacity, and d determines the material's ultimate load-bearing capacity. Both can be quantified to expand the allowable load range, thereby guiding the design positioning to a higher safety margin and ensuring the safety of health status testing of power transmission and transformation equipment under maximum operating conditions. A higher w may significantly reduce the overall strength and reliability of the material. Evaluating w helps to discover potential defects in the modeling results of power transmission and transformation equipment, predict the test quality of the power transmission and transformation equipment and the performance accuracy reflected, and then make the best decision for the positioning point of the modeling equipment.

[0037] The micrometeorological test preselection scheme stored in the database is applied to the three-dimensional finite element model of the test subject and the environmental characteristic values ​​after the test are calculated.

[0038] The micrometeorological test preselection plan is obtained from the power transmission and transformation equipment environmental experiment manual. The micrometeorological test preselection plan is obtained from the database when the power transmission and transformation equipment is produced and set up. The micrometeorological characteristic standard environment that needs to be met by the current power transmission and transformation equipment under normal working conditions is formulated based on industry standards. The plan includes specific requirements for temperature, humidity, wind speed, and radiation. The micrometeorological environment is created for the power transmission and transformation equipment environment so that the environment under normal working conditions of the power transmission and transformation equipment meets the numerical standards of temperature, humidity, wind speed, and radiation in the micrometeorological test preselection plan, ensuring that the selected data can cover the actual meteorological characteristics of the environment in which the model is located.

[0039] Calculate the characteristic values ​​of the post-test environment. The specific analysis process is: obtain the post-test environment characteristic set of the micrometeorological test pre-selection scheme, the post-test environment characteristic set includes the atmospheric ion conductivity deviation value, the aerosol concentration change value, the cooling medium impurity rise rate, and the dust particle density rise value; obtain the post-test environment characteristic fusion factor set set in the database, the test micrometeorological characteristic fusion factor set includes the atmospheric ion conductivity deviation value fusion factor, the aerosol concentration change value fusion factor, the cooling medium impurity rise rate fusion factor, and the dust particle density rise value fusion factor; calculate the post-test environment characteristic values ​​based on the post-test environment characteristic set, the post-test environment characteristic fusion factor set set in the database, and the test characteristic fusion model.

[0040] The calculation formula of the tested feature fusion model is as follows: ; In the formula, T is the environmental characteristic value after the test, D is the atmospheric ion conductivity deviation value, Q is the aerosol concentration change value, B is the cooling medium impurity increase rate, A is the dust particle density increase value, is the atmospheric ion conductivity deviation fusion factor, is the aerosol concentration change fusion factor, is the cooling medium impurity rise rate fusion factor, is the fusion factor of the dust particle density increase, and e is a natural constant.

[0041] T is used to indicate the change in the overall environment after the micrometeorological test pre-selected scheme is applied to the power transmission and transformation equipment and the comprehensive environmental conditions before the test. The larger T is, the greater the impact of the power transmission and transformation equipment on the overall environment after the test, and the comprehensive environmental conditions are lower than those before the test, indicating that the health status of the power transmission and transformation equipment will have more adverse effects on the environment. An increase in D usually means that there are more ionization phenomena beyond a reasonable range in the atmosphere, which can easily cause instability of the electromagnetic field around the power transmission and transformation equipment, increase the risk of local discharge, and make the comprehensive environmental conditions more unfavorable to the healthy operation of the power transmission and transformation equipment.

[0042] A too high Q will cause tiny solid and liquid particles to be suspended in the air on the surface of the insulator, affecting the heat dissipation efficiency, and further affecting the stability and life of the power transmission and transformation equipment. Environmental deterioration increases the possibility of equipment failure. A higher B means that the cooling medium's ability to absorb or release large amounts of heat in the case of small temperature changes becomes worse, and the power transmission and transformation equipment is difficult to maintain a safe operating temperature range in the micro-meteorological test environment. A higher A means that the concentration of solid particles in the environment becomes higher, resulting in increased surface wear of the equipment in the tested micro-meteorological environment, especially on mechanical parts and connection points, affecting the operating performance of the power transmission and transformation equipment.

[0043] Set atmospheric ion conductivity deviation value fusion factor , aerosol concentration change value fusion factor , cooling medium impurity rise rate fusion factor , dust particle density rise value fusion factor are extracted from the database and are all positive numbers. The historical measured atmospheric ion conductivity deviation values, aerosol concentration change values, cooling medium impurity increase rates, dust particle density increase values ​​and The mapping set is used to obtain the current atmospheric ion conductivity deviation value, aerosol concentration change value, cooling medium impurity increase rate, and dust particle density increase value corresponding to The acquisition of other factors is similar, such as vibration waveform test weight factor, spectrum test weight factor, power harmonic amplitude test weight factor and load capacity margin test weight factor.

[0044] A higher Q may increase the ion concentration by providing more ion sources, thereby increasing D. Aerosol concentration is essentially the concentration of dust and liquid particles per unit volume, so the two are directly related. An increase in Q will lead to an increase in the density of dust particles per unit volume. If there is a cooling medium that can evaporate effectively in the atmosphere, a higher B may mean that the evaporative cooling effect of the cooling medium is weakened, which may in turn affect meteorological conditions and ion generation rate. Therefore, under certain conditions, it may affect D. The effect of dust particles on airflow also affects the capacity of the cooling medium. When the dust density is high, the cooling process will be inhibited, thereby affecting the effect of B on the environment.

[0045] like Figure 3 As shown, Defined as 2, is 1, B increases from 0 to 1, and T also gradually increases, indicating that the comprehensive environmental conditions are not conducive to the healthy operation of power transmission and transformation equipment.

[0046] After applying the micrometeorological test preselection scheme to the three-dimensional finite element model, the test data set of each test element is obtained.

[0047] The test data set of each test element is obtained. The specific acquisition process is as follows: obtain the test feedback imaging of any test element, the test feedback imaging includes the vibration waveform diagram, the spectrum component diagram, the power harmonic amplitude curve and the load capacity margin curve; obtain the test standard imaging and map the test feedback imaging on the test standard imaging, the test standard imaging includes the vibration waveform reference diagram, the spectrum component standard diagram, the power harmonic amplitude standard curve and the load capacity margin standard curve; obtain the deviation between the test feedback imaging and the test standard imaging of all test elements and mark them as the vibration waveform test value, the spectrum test value, the power harmonic amplitude test value and the load capacity margin test value in turn; record the vibration waveform test value, the spectrum test value, the power harmonic amplitude test value and the load capacity margin test value as the test data set of the corresponding test element.

[0048] The vibration waveform diagram shows the vibration state of the power transmission and transformation equipment within a specific time. Usually, time is used as the horizontal axis and vibration amplitude is used as the vertical axis. The vibration frequency and its intensity caused by the fault characteristics are displayed by observing the waveform changes. Different faults (such as imbalance, looseness or wear) will produce different vibration waveforms. The spectrum component diagram shows the energy distribution of the vibration signal within a specific frequency range. The horizontal axis represents the frequency, and the vertical axis represents the energy amplitude of the vibration signal at each frequency. Through the spectrum diagram, the main frequency component, harmonics and potential fault frequencies can be identified. The power harmonic amplitude curve shows the amplitude of different harmonic components in the power system. Usually, the ordinal number of the harmonic (such as the second harmonic, the third harmonic, etc.) is used as the horizontal axis and the amplitude is used as the vertical axis. It is used to determine whether the harmonics in the system exceed the normal range, which may lead to increased power loss, equipment damage or power quality problems. The load capacity margin curve shows the available capacity margin of the power transmission and transformation equipment under different load conditions. The horizontal axis usually represents the load level, and the vertical axis represents the system margin, that is, the amount of additional load that can be tolerated. It is used to evaluate the safety and stability of the power transmission and transformation equipment under load fluctuations or emergencies.

[0049] Mapping and constructing the test standard imaging in the test feedback imaging is to spatially register the test feedback imaging and the test standard imaging by linear registration to ensure that the two are aligned in the same coordinate system, map the image of the test feedback imaging to the standard imaging of the test standard imaging, compare the coverage area of ​​the two images (the area between the curve and the horizontal axis), and statistically calculate the cumulative coverage area of ​​the deviation. The imaged information can intuitively show the state and performance of the test system. By constructing the standard imaging and comparing it with the feedback imaging, the deviation area can be quickly identified and expressed in the form of an image, making the comparison of the test results of the test element at different times and under different conditions more intuitive. The cumulative coverage area of ​​the deviation is statistically calculated, making the quantification of the deviation operational, which helps to form a data-driven decision-making basis and simplifies the analysis process of parameter acquisition and expression. In addition, the use of images can more sensitively capture subtle changes and deviations, which is very important for early fault warning and fault diagnosis. Timely detection of problems can reduce the losses that may be caused by failures.

[0050] The comprehensive health index of the corresponding power transmission and transformation equipment type is calculated by comprehensively analyzing the test data set and the environmental characteristic values ​​after the test. The health status warning level is obtained based on the comprehensive health index and marked for feedback.

[0051] The comprehensive health index of the corresponding power transmission and transformation equipment type is calculated by comprehensively analyzing the tested data sets and the environmental characteristic values ​​after the test. The specific analysis process is as follows: average processing is performed on each tested data set to obtain a tested mean data set, which includes the tested mean of vibration waveform, the tested mean of spectrum, the tested mean of power harmonic amplitude and the tested mean of load capacity margin; the tested weight factor set set in the database is obtained, which includes the tested weight factor of vibration waveform, the tested weight factor of spectrum, the tested weight factor of power harmonic amplitude and the tested weight factor of load capacity margin; the comprehensive health index is calculated based on the tested mean data set, the tested weight factor set set in the database and the environmental characteristic values ​​after the test.

[0052] In the process of comprehensive evaluation of the health status of power transmission and transformation equipment to obtain the comprehensive health index, the test data sets of each test element are not directly processed, but the test data sets are comprehensively analyzed. In the specific numerical calculation process, the test data sets are averaged. By excluding abnormal data points, it is ensured that the calculation results are more in line with the actual conditions of the equipment, the accuracy of data analysis is improved, and it is helpful to remove the influence of extreme values ​​and noise in the data set on the calculation results, making the comprehensive evaluation more stable and reliable.

[0053] The specific calculation formula of comprehensive health index is as follows: ; In the formula, is the comprehensive health index, is the tested mean value of the vibration waveform, is the spectrum test mean, is the tested mean value of power harmonic amplitude, is the tested mean value of load capacity margin, is the vibration waveform test weight factor, is the spectrum subject weight factor, is the tested weight factor of power harmonic amplitude, is the load capacity margin test weight factor, and T is the environmental characteristic value after the test.

[0054] Used to indicate the overall health status of the tested power transmission and transformation equipment. , , , It indicates the degree of deviation between the test results of each test element and the standard result. , , as well as Used to indicate , , , The contribution of the degree of deviation to the comprehensive health index is determined in the corresponding , , as well as Under the weighting effect of , , , The smaller it is, the better the overall health of the power transmission and transformation equipment is. The larger the value is, the larger the T is, indicating that the test results act on the environment and thus have an adverse impact on the environment, which will further affect the health of the power transmission and transformation equipment. Become smaller.

[0055] Based on the comprehensive health index, the health status warning level is obtained and marked for feedback. The specific analysis process is: obtain the comprehensive health index; obtain the endpoints of the health warning signal interval stored in the database; compare the health warning signal interval endpoints stored in the database with the comprehensive health index to obtain the health status warning level corresponding to the comprehensive health index; mark the health status warning level of the power transmission and transformation equipment, and send a warning signal to the power transmission and transformation equipment terminal based on the health status warning level.

[0056] For example, when the warning level is 1, the lower endpoint of the interval is 0 and the upper endpoint is 40. When the warning level is 2, the lower endpoint of the interval is 41 and the upper endpoint is 70. Assuming that the comprehensive health index of the power transmission and transformation equipment is 68 at this time, the matching process is to traverse the warning interval list from the database and check whether the comprehensive health index falls within the range of each interval. For example: for interval 1: 0≤68≤40, the matching result is no match, for interval 2: 41≤68≤70, the matching result is a successful match, and the warning level can be determined to be 2. Different levels of warnings can help operation and maintenance personnel quickly understand the health status of power transmission and transformation equipment, thereby effectively allocating human and material resources and taking corresponding measures in time to reduce the impact of equipment failures on overall operations.

Claims

1. Finite element analysis method for health status of power transmission and transformation equipment, It is characterized in that include: Acquire the type of power transmission and transformation equipment, and obtain an initial three-dimensional finite element model corresponding to the type of power transmission and transformation equipment from a database based on the type of power transmission and transformation equipment; Acquire the prior data of the power transmission and transformation equipment corresponding to the type of the power transmission and transformation equipment, the prior data of the power transmission and transformation equipment including model restoration data and test bearing capacity data; Calculate the model restoration degree based on the prior data of the power transmission and transformation equipment and determine whether to adjust and optimize the initial three-dimensional finite element model according to the model restoration degree to obtain the three-dimensional finite element model of the test object; Determine each test element of the three-dimensional finite element model of the test subject; Apply the micro-meteorological test pre-selected scheme stored in the database to the three-dimensional finite element model of the test subject and calculate the environmental characteristic values ​​after the test; After applying the pre-selected scheme of micro-meteorological testing to the three-dimensional finite element model, the test data set of each test element is obtained; The comprehensive health index of the corresponding power transmission and transformation equipment type is calculated by comprehensively analyzing the test data set and the environmental characteristic values ​​after the test. The health status warning level is obtained based on the comprehensive health index and marked for feedback.

2. The finite element analysis method for the health status of power transmission and transformation equipment according to claim 1, It is characterized in that The model restoration degree is calculated based on the prior data of the power transmission and transformation equipment, and whether to adjust and optimize the initial three-dimensional finite element model is determined according to the model restoration degree to obtain the three-dimensional finite element model of the test object. The specific matching process is as follows: Acquire initial data corresponding to the type of the power transmission and transformation equipment, the initial data including elastic modulus, thermal conductivity and electrical conductivity; The model restoration data is integrated and analyzed with the initial data to obtain the model restoration degree, and the model restoration data includes the model elastic modulus, the model thermal conductivity and the model electrical conductivity; Compare the model restoration degree with the model restoration threshold stored in the database: If the model restoration degree is less than the model restoration threshold stored in the database, the initial three-dimensional finite element model needs to be adjusted and optimized, and the three-dimensional finite element model of the subject after adjustment and optimization is output; If the degree of model restoration is greater than or equal to the model restoration threshold stored in the database, the initial three-dimensional finite element model does not need to be adjusted and optimized, and is output as a three-dimensional finite element model for trial use.

3. The finite element analysis method for the health status of power transmission and transformation equipment according to claim 2, It is characterized in that The specific analysis process of determining the test elements of the three-dimensional finite element model is as follows: The three-dimensional finite element model of the subject is randomly divided into a number of auxiliary positioning grids; Obtain the test bearing capacity data corresponding to any auxiliary positioning grid, and calculate the test bearing capacity evaluation value of the auxiliary positioning grid based on the test bearing capacity data; The test bearing capacity assessment values ​​of each auxiliary positioning grid are compared, and the center of the auxiliary positioning grid with the largest test bearing capacity assessment value is marked as the power transmission and transformation equipment positioning point. Based on the power transmission and transformation equipment positioning point, multiple test elements of the standard volume are marked divergently toward the boundary of the three-dimensional finite element model, and the remaining boundary part that is less than the standard volume is not marked as the test element.

4. The finite element analysis method for the health status of power transmission and transformation equipment according to claim 3, Features: The test bearing capacity data include the average spacing distance of load points, the yield strength per unit section, the maximum tensile strength and the crack volume ratio.

5. The finite element analysis method for the health status of power transmission and transformation equipment according to claim 4, It is characterized in that The specific calculation formula of the test bearing capacity evaluation value is: ; Where c is the assessed value of the bearing capacity of the test object, f is the average spacing of the load points, q is the yield strength per unit section, d is the maximum tensile strength, w is the crack volume percentage, and e is a natural constant.

6. The finite element analysis method for the health status of power transmission and transformation equipment according to claim 1, It is characterized in that The specific analysis process of calculating the post-test environmental characteristic value is as follows: Obtain the post-test environmental characteristic set of the micro-meteorological test pre-selection scheme, which includes the atmospheric ion conductivity deviation value, aerosol concentration change value, cooling medium impurity increase rate and dust particle density increase value; Obtain the post-test environmental characteristic fusion factor set set in the database. The test micro-meteorological characteristic fusion factor set includes the atmospheric ion conductivity deviation value fusion factor, the aerosol concentration change value fusion factor, the cooling medium impurity rise rate fusion factor and the dust particle density rise value fusion factor; The post-test environment characteristic value is calculated based on the post-test environment characteristic set, the post-test environment characteristic fusion factor set set in the database and the test characteristic fusion model.

7. The finite element analysis method for the health status of power transmission and transformation equipment according to claim 1, It is characterized in that The specific acquisition process of obtaining the test data set of each test element is as follows: Obtaining test feedback imaging of any test element, the test feedback imaging includes vibration waveform diagram, spectrum component diagram, power harmonic amplitude curve and load capacity margin curve; Acquire the test standard imaging and map the test feedback imaging onto the test standard imaging, wherein the test standard imaging includes a vibration waveform reference image, a spectrum component standard image, a power harmonic amplitude standard curve, and a load capacity margin standard curve; Obtain the deviations between the test feedback images and the test standard images of all the test elements and mark them in turn as the vibration waveform test value, the spectrum test value, the power harmonic amplitude test value and the load capacity margin test value; The vibration waveform test value, the frequency spectrum test value, the power harmonic amplitude test value and the load capacity margin test value are recorded as the test data set of the corresponding test element.

8. The finite element analysis method for the health status of power transmission and transformation equipment according to claim 7, It is characterized in that The comprehensive analysis of the test data set and the post-test environmental characteristic values ​​calculates the comprehensive health index of the corresponding power transmission and transformation equipment type. The specific analysis process is as follows: Performing mean processing on each test data set to obtain a test mean data set, the test mean data set includes a test mean of a vibration waveform, a test mean of a frequency spectrum, a test mean of an electric harmonic amplitude, and a test mean of a load capacity margin; Obtaining a set of tested weight factors set in a database, the tested weight factor set including a vibration waveform tested weight factor, a spectrum tested weight factor, a power harmonic amplitude tested weight factor, and a load capacity margin tested weight factor; The comprehensive health index is calculated based on the subject mean data set, the subject weight factor set set in the database, and the post-test environmental characteristic values.

9. The finite element analysis method for the health status of power transmission and transformation equipment according to claim 8, It is characterized in that The specific calculation formula of the comprehensive health index is as follows: ; In the formula, is the comprehensive health index, is the tested mean value of the vibration waveform, is the spectrum test mean, is the tested mean value of power harmonic amplitude, is the tested mean value of load capacity margin, is the vibration waveform test weight factor, is the spectrum subject weight factor, is the tested weight factor of power harmonic amplitude, is the load capacity margin test weight factor, T is the environmental characteristic value after the test, and e is a natural constant.

10. The finite element analysis method for the health status of power transmission and transformation equipment according to claim 8, It is characterized in that The health status warning level is obtained based on the comprehensive health index and marked for feedback. The specific analysis process is as follows: Get a comprehensive health index; Obtain the endpoints of the health warning signal interval stored in the database; Compare the endpoints of the health warning signal interval stored in the database with the comprehensive health index to obtain the health status warning level corresponding to the comprehensive health index; Mark the health status warning level of the power transmission and transformation equipment, and send a warning signal to the power transmission and transformation equipment terminal based on the health status warning level.