Multi-layer karst cave area building pile foundation construction risk pre-judgment system
By constructing three-dimensional geological models and mechanical behavior models in multi-layer cave areas, combining numerical simulation and real-time monitoring data, identifying and adjusting pile foundation construction risk points and generating early warning signals, it solves the difficulty in predicting construction risks in multi-layer cave areas in the existing technology. The problem of the construction safety and scientific decision-making have improved.
Patent Information
- Application Number
- CN202411036240.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-31
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-07-31
AI Technical Summary
In multi-layer cave areas, it is difficult for the existing technology to effectively predict the construction risks of building pile foundations, resulting in increased construction progress and costs, and a great threat to safety, mainly because traditional geological exploration methods are difficult to fully cover irregular and complex geological structures.
The risk prediction system for building pile foundation construction in multi-layer cave areas is adopted, including survey data integration module, mechanical model construction module, pile foundation construction simulation module, pile foundation construction monitoring module and construction risk warning module, through three-dimensional geological model, numerical simulation and Real-time monitoring of data comparison, identify and adjust risk points, and generate early warning signals.
It improves construction safety and adaptability, reduces the additional costs caused by construction accidents, provides scientific decision-making basis, and ensures the rationality and safety of the construction process.
Smart Images

Figure CN118966770A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of civil engineering, and in particular relates to a risk prediction system for building pile foundation construction in a multi-layer karst cave area. Background Art
[0002] There are many challenges and risks in building pile foundation construction in multi-layer karst areas, which not only affect the progress and cost of the project, but also may threaten the safety of construction workers. The distribution of karst caves underground is often irregular and discontinuous, which makes it difficult for traditional geological survey methods to fully cover all karst cave areas. The shapes and sizes of karst caves vary, from small karst caves to large karst caves, and even complex karst cave networks, which increases the difficulty and uncertainty of construction. The interaction between karst caves and surrounding rock formations is complex, and there may be problems such as rock formation instability and crack development, which increases the risk of construction.
[0003] Existing risk prediction methods mostly rely on empirical judgment and simple model analysis, lacking in-depth understanding and prediction capabilities of complex geological conditions and construction processes. Therefore, in order to effectively predict construction risks and improve construction safety, it is urgent to propose a risk prediction system for pile foundation construction in multi-layer karst areas. Summary of the invention
[0004] In order to solve the above technical problems, the present invention proposes a risk prediction system for building pile foundation construction in multi-layer karst cave areas to solve the problems existing in the above-mentioned prior art.
[0005] To achieve the above object, the present invention provides a risk prediction system for pile foundation construction in multi-layer karst cave areas, comprising:
[0006] A survey data integration module is used to obtain geological survey data of multi-layer karst cave areas and establish a three-dimensional geological model based on the geological survey data;
[0007] The mechanical model building module is used to establish the mechanical behavior model of the cave area based on the three-dimensional geological model of the multi-layer cave using geological theoretical analysis methods;
[0008] The pile foundation construction simulation module is used to simulate the pile foundation construction process based on the mechanical behavior model of the karst cave area using numerical simulation methods, and to predict the risk points and risk levels of the pile foundation based on the numerical simulation results;
[0009] The pile foundation construction monitoring module is used to collect geological information of the pile foundation construction area in real time based on monitoring equipment, compare and analyze it with the numerical simulation results, and dynamically adjust the pile foundation risk points;
[0010] The construction risk warning module is used to calculate the risk index of the risk point based on real-time monitoring data and numerical simulation results, and issue an early warning when the risk index exceeds the preset risk threshold.
[0011] Optionally, the survey data integration module includes a data acquisition unit and a model building unit;
[0012] The data acquisition unit is used to obtain drilling data of karst rocks based on drilling technology and core analysis technology; collect seismic wave data, electromagnetic wave data and earth gravity data to obtain geophysical data; and obtain geological mapping data of rock formations based on a total station and a geological profile.
[0013] The model building unit is used to build a preliminary three-dimensional geological model based on geological surveying data, and to refine the rock layer properties and rock layer structures in the preliminary three-dimensional geological model based on drilling data and geophysical data to obtain a final three-dimensional geological model.
[0014] Optionally, the mechanical model construction module includes a mechanical parameter determination unit, a mechanical model construction unit and a model verification and calibration unit;
[0015] The mechanical parameter determination unit is used to perform load tests and lateral pressure tests on the cave rock layer to obtain mechanical parameters of the rock and soil body;
[0016] The mechanical model construction unit is used to set the boundary conditions and external loads of the mechanical behavior model by using a numerical analysis method, and to perform unstructured grid division on the three-dimensional geological model, assign the mechanical parameters of the rock and soil body to the corresponding grid units, and complete the construction of the mechanical behavior model;
[0017] The model verification and calibration unit is used to perform preliminary verification of the mechanical behavior model based on historical karst cave pile foundation construction data, perform parameter sensitivity analysis on the mechanical behavior model, and calibrate the model parameters.
[0018] Optionally, the pile foundation construction simulation module includes a construction simulation unit, a risk assessment unit and a result generation unit;
[0019] The construction simulation unit is used to simulate the drilling stage, hole cleaning stage, steel cage installation stage, concrete pouring stage and pile formation stage in pile foundation construction by using a numerical simulation method based on the mechanical behavior model of the karst cave area;
[0020] The risk assessment unit is used to analyze the stress and deformation distribution of the pile foundation at different construction stages based on the numerical simulation results of the construction simulation unit, identify the stress concentration area and the high deformation area, and then obtain the risk points of the pile foundation, preset risk indicators, and divide the risk points into different risk levels;
[0021] The result generating unit is used to display the distribution of risk points and risk levels in the form of a cloud map.
[0022] Optionally, the pile foundation construction monitoring module includes a monitoring equipment deployment unit, a data fusion analysis unit and a risk point adjustment unit;
[0023] The monitoring equipment deployment unit is used to deploy geological radar, sonic detector, optical fiber sensor, inclinometer and pore water pressure gauge at the pile foundation construction site in the karst cave area;
[0024] The data fusion analysis unit is used to fuse the data collected by each monitoring device and comprehensively analyze the geological information and pile foundation status of the pile foundation construction area;
[0025] The risk point adjustment unit is used to compare and analyze the real-time monitoring data with the numerical simulation results, identify new risk points and changes in original risk points, and then make real-time adjustments to the pile foundation risk points and re-evaluate the risk level of each risk point.
[0026] Optionally, the construction risk warning module includes a risk index determination unit, a warning signal triggering unit and a warning signal transmission unit;
[0027] The risk index determination unit is used to select risk assessment indicators including maximum principal stress, displacement and safety factor, assign different weight coefficients to each indicator based on its importance, and obtain the risk index by weighted summation method;
[0028] The warning signal triggering unit is used to obtain the current risk index in real time based on the risk index determination unit, and compare the current risk index with a preset risk threshold. When the risk index exceeds the preset risk threshold, different levels of warning signals are automatically generated for warning;
[0029] The warning signal transmission unit is used to notify construction management personnel via SMS, email or mobile phone APP push, and automatically match the corresponding emergency plan according to the warning level.
[0030] The present invention also provides a method for predicting the risk of building pile foundation construction in a multi-layer karst cave area, based on a system for predicting the risk of building pile foundation construction in a multi-layer karst cave area, comprising the following steps:
[0031] Acquire geological survey data of a multi-layer karst cave area, and establish a three-dimensional geological model based on the geological survey data;
[0032] Based on the three-dimensional geological model of multi-layer karst caves, the mechanical behavior model of the karst cave area is established using geological theoretical analysis methods;
[0033] Based on the mechanical behavior model of the karst cave area, the pile foundation construction process is simulated by numerical simulation method, and the risk points and risk levels of the pile foundation are predicted based on the numerical simulation results;
[0034] Based on the real-time collection of geological information of the pile foundation construction area by monitoring equipment, the geological information is compared with the numerical simulation results to dynamically adjust the risk points of the pile foundation;
[0035] Based on real-time monitoring data and numerical simulation results, the risk index of the risk point is calculated, and an early warning is issued when the risk index exceeds the preset risk threshold.
[0036] The present invention also provides an electronic device, comprising: a memory and a processor; the memory is used to store programs; the processor is used to execute the programs to implement various modules of the risk prediction system for building pile foundation construction in multi-layer karst cave areas.
[0037] The present invention also provides a readable storage medium on which a computer program is stored. When the computer program is executed by a processor, each module of the risk prediction system for building pile foundation construction in a multi-layer karst cave area is implemented.
[0038] Compared with the prior art, the present invention has the following advantages and technical effects:
[0039] The present invention ensures the comprehensiveness and accuracy of geological survey data through the survey data integration module. The three-dimensional geological model established based on the comprehensive data can more realistically reflect the geological structure of the cave area and provide an accurate basis for subsequent analysis.
[0040] The present invention can predict the mechanical response of the cave under different geological conditions through the mechanical model construction module, and provide important mechanical parameters and risk assessment basis for pile foundation construction.
[0041] The present invention can predict the problems and risks that may occur during the construction process through the pile foundation construction simulation module, and can identify the key risk points and risk levels in the pile foundation construction process based on the numerical simulation results, providing a basis for optimizing the construction plan.
[0042] The present invention ensures the real-time and accuracy of data through a pile foundation construction monitoring module, compares and analyzes real-time monitoring data with numerical simulation results, can dynamically adjust pile foundation risk points, and improve construction safety and adaptability.
[0043] The present invention can reduce the additional costs caused by construction accidents by identifying and handling risk points in advance, provide a scientific basis for construction decisions, and support construction teams to make more reasonable and safe decisions. BRIEF DESCRIPTION OF THE DRAWINGS
[0044] The drawings constituting a part of the present application are used to provide a further understanding of the present application. The illustrative embodiments and descriptions of the present application are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:
[0045] Figure 1It is a structural schematic diagram of a risk prediction system for building pile foundation construction in a multi-layer karst cave area according to an embodiment of the present invention. DETAILED DESCRIPTION
[0046] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0047] It should be noted that the steps shown in the flowcharts of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and that, although a logical order is shown in the flowcharts, in some cases, the steps shown or described can be executed in an order different from that shown here.
[0048] Embodiment 1
[0049] like Figure 1 As shown, in this embodiment, a risk prediction system for building pile foundation construction in a multi-layer karst cave area is provided, comprising: a survey data integration module, a mechanical model construction module, a pile foundation construction simulation module, a pile foundation construction monitoring module and a construction risk early warning module connected in sequence;
[0050] A survey data integration module is used to obtain geological survey data of multi-layer karst cave areas and establish a three-dimensional geological model based on the geological survey data;
[0051] The mechanical model building module is used to establish the mechanical behavior model of the cave area based on the three-dimensional geological model of the multi-layer cave using geological theoretical analysis methods;
[0052] The pile foundation construction simulation module is used to simulate the pile foundation construction process based on the mechanical behavior model of the karst cave area using numerical simulation methods, and to predict the risk points and risk levels of the pile foundation based on the numerical simulation results;
[0053] The pile foundation construction monitoring module is used to collect geological information of the pile foundation construction area in real time based on monitoring equipment, compare and analyze it with the numerical simulation results, and dynamically adjust the pile foundation risk points;
[0054] The construction risk warning module is used to calculate the risk index of the risk point based on real-time monitoring data and numerical simulation results, and issue an early warning when the risk index exceeds the preset risk threshold.
[0055] It can be implemented that the survey data integration module includes a data acquisition unit and a model building unit; the data acquisition unit is used to obtain the drilling data of the cave rock based on the drilling technology and the core analysis technology; collect seismic wave data, electromagnetic wave data and earth gravity data to obtain geophysical data; obtain the geological surveying data of the rock layer based on the total station and the geological profile; the model building unit is used to construct a preliminary three-dimensional geological model based on the geological surveying data, and refine the rock layer properties and rock layer structure in the preliminary three-dimensional geological model based on the drilling data and the geophysical data to obtain the final three-dimensional geological model.
[0056] It is feasible that the mechanical model construction module includes a mechanical parameter determination unit, a mechanical model construction unit and a model verification and calibration unit; the mechanical parameter determination unit is used to perform load tests and lateral pressure tests on the karst rock layer to obtain the mechanical parameters of the rock and soil body; the mechanical model construction unit is used to set the boundary conditions and external loads of the mechanical behavior model using a numerical analysis method, and to perform unstructured grid division on the three-dimensional geological model, assign the mechanical parameters of the rock and soil body to the corresponding grid units, and complete the construction of the mechanical behavior model; the model verification and calibration unit is used to perform preliminary verification of the mechanical behavior model based on historical karst pile foundation construction data, perform parameter sensitivity analysis on the mechanical behavior model, and calibrate the model parameters.
[0057] Commonly used numerical simulation software in this embodiment includes ABAQUS, ANSYS, FLAC3D, PFC, etc. These software provide powerful numerical calculation capabilities and pre-processing and post-processing functions.
[0058] It is feasible that the pile foundation construction simulation module includes a construction simulation unit, a risk assessment unit and a result generation unit; the construction simulation unit is used to simulate the drilling stage, hole cleaning stage, steel cage installation stage, concrete pouring stage and pile formation stage in pile foundation construction based on the mechanical behavior model of the cave area and the numerical simulation method; the risk assessment unit is used to analyze the stress and deformation distribution of the pile foundation at different construction stages based on the numerical simulation results of the construction simulation unit, identify stress concentration areas and high deformation areas, and then obtain pile foundation risk points, preset risk indicators, and divide risk points into different risk levels; the result generation unit is used to display the distribution of risk points and the degree of risk in the form of a cloud map.
[0059] As a specific embodiment, this embodiment uses professional tools such as HyperMesh and GID for meshing to ensure the accuracy and efficiency of the simulation. Use laboratory test and field test data to obtain accurate rock and soil and concrete material parameters to ensure the reliability of the simulation results. Set reasonable boundary conditions, such as fixed boundaries, free boundaries, far-field boundaries, etc., to ensure the rationality of the simulation results. Considering the nonlinear characteristics of geotechnical materials, appropriate constitutive models, such as the Mohr-Coulomb model, the Drucker-Prager model, etc., are used for analysis.
[0060] It is feasible that the pile foundation construction monitoring module includes a monitoring equipment deployment unit, a data fusion analysis unit and a risk point adjustment unit; the monitoring equipment deployment unit is used to deploy geological radars, acoustic wave detectors, optical fiber sensors, inclinometers and pore water pressure gauges at the pile foundation construction site in the karst area; the data fusion analysis unit is used to fuse the data collected by each monitoring device, and comprehensively analyze the geological information and pile foundation status of the pile foundation construction area; the risk point adjustment unit is used to compare and analyze the real-time monitoring data with the numerical simulation results, identify new risk points and changes in the original risk points, and then make real-time adjustments to the pile foundation risk points, and re-evaluate the risk level of each risk point.
[0061] As a specific embodiment, this embodiment sets a reasonable monitoring frequency according to the construction progress and geological conditions to ensure the real-time and effectiveness of the data. It adopts advanced data processing algorithms, such as Kalman filtering and wavelet transform, to improve the accuracy and efficiency of data processing. It adopts reliable communication protocols, such as LoRa and NB-IoT, to ensure the stability and security of data transmission.
[0062] It can be implemented that the construction risk warning module includes a risk index determination unit, a warning signal trigger unit and a warning signal transmission unit; the risk index determination unit is used to select risk assessment indicators including maximum principal stress, displacement and safety factor, assign different weight coefficients to each indicator based on its importance, and obtain the risk index by weighted summation method; the warning signal trigger unit is used to obtain the current risk index in real time based on the risk index determination unit, and compare the current risk index with a preset risk threshold. When the risk index exceeds the preset risk threshold, different levels of warning signals are automatically generated for warning; the warning signal transmission unit is used to notify construction management personnel by SMS, email or mobile phone APP push, and automatically match the corresponding emergency plan according to the warning level.
[0063] As a specific embodiment, this embodiment uses machine learning algorithms, such as random forests and support vector machines, to analyze monitoring data to improve the accuracy of risk index calculation. The risk warning module is seamlessly integrated with other modules to achieve data sharing and process automation. In addition, encryption technology is used during data transmission to ensure the security of data transmission, and a redundancy mechanism is designed to ensure the stable operation of the system.
[0064] Embodiment 2
[0065] The present invention also provides a method for predicting the risk of building pile foundation construction in a multi-layer karst cave area, based on a system for predicting the risk of building pile foundation construction in a multi-layer karst cave area, comprising the following steps:
[0066] Acquire geological survey data of a multi-layer karst cave area, and establish a three-dimensional geological model based on the geological survey data;
[0067] Based on the three-dimensional geological model of multi-layer karst caves, the mechanical behavior model of the karst cave area is established using geological theoretical analysis methods;
[0068] Based on the mechanical behavior model of the karst cave area, the pile foundation construction process is simulated by numerical simulation method, and the risk points and risk levels of the pile foundation are predicted based on the numerical simulation results;
[0069] Based on the real-time collection of geological information of the pile foundation construction area by monitoring equipment, the geological information is compared with the numerical simulation results to dynamically adjust the risk points of the pile foundation;
[0070] Based on real-time monitoring data and numerical simulation results, the risk index of the risk point is calculated, and an early warning is issued when the risk index exceeds the preset risk threshold.
[0071] Embodiment 3
[0072] The present invention also provides an electronic device, comprising: a memory and a processor; the memory is used to store programs; the processor is used to execute the programs to implement various modules of the risk prediction system for building pile foundation construction in multi-layer karst cave areas.
[0073] Embodiment 4
[0074] The present invention also provides a readable storage medium on which a computer program is stored. When the computer program is executed by a processor, each module of the risk prediction system for building pile foundation construction in a multi-layer karst cave area is implemented.
[0075] The above are only preferred specific implementations of the present application, but the protection scope of the present application is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed in the present application should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
Claims
1. A risk prediction system for pile foundation construction in multi-layer karst areas, characterized in that: include: The survey data integration module, mechanical model building module, pile foundation construction simulation module, pile foundation construction monitoring module and construction risk early warning module are connected in sequence; The survey data integration module is used to obtain geological survey data of multi-layer karst cave areas and establish a three-dimensional geological model based on the geological survey data; The mechanical model building module is used to establish a mechanical behavior model of the cave area based on a three-dimensional geological model of a multi-layer cave using a geological theory analysis method; The pile foundation construction simulation module is used to simulate the pile foundation construction process based on the mechanical behavior model of the karst cave area by using a numerical simulation method, and predict the risk points and risk levels of the pile foundation based on the numerical simulation results; The pile foundation construction monitoring module is used to collect geological information of the pile foundation construction area in real time based on the monitoring equipment, compare and analyze it with the numerical simulation results, and dynamically adjust the pile foundation risk points; The construction risk warning module is used to calculate the risk index of the risk point based on real-time monitoring data and numerical simulation results, and issue an early warning when the risk index exceeds a preset risk threshold.
2. The risk prediction system for pile foundation construction in multi-layer karst cave areas according to claim 1 is characterized in that: The survey data integration module includes a data acquisition unit and a model building unit; The data acquisition unit is used to obtain drilling data of karst rocks based on drilling technology and core analysis technology; collect seismic wave data, electromagnetic wave data and earth gravity data to obtain geophysical data; and obtain geological mapping data of rock formations based on a total station and a geological profile. The model building unit is used to build a preliminary three-dimensional geological model based on geological surveying data, and to refine the rock layer properties and rock layer structures in the preliminary three-dimensional geological model based on drilling data and geophysical data to obtain a final three-dimensional geological model.
3. The risk prediction system for pile foundation construction in multi-layer karst cave areas according to claim 1 is characterized in that: The mechanical model construction module includes a mechanical parameter determination unit, a mechanical model construction unit and a model verification and calibration unit; The mechanical parameter determination unit is used to perform load tests and lateral pressure tests on the cave rock layer to obtain mechanical parameters of the rock and soil body; The mechanical model construction unit is used to set the boundary conditions and external loads of the mechanical behavior model by using a numerical analysis method, and to perform unstructured grid division on the three-dimensional geological model, assign the mechanical parameters of the rock and soil body to the corresponding grid units, and complete the construction of the mechanical behavior model; The model verification and calibration unit is used to perform preliminary verification of the mechanical behavior model based on historical karst cave pile foundation construction data, perform parameter sensitivity analysis on the mechanical behavior model, and calibrate the model parameters.
4. The risk prediction system for pile foundation construction in multi-layer karst cave areas according to claim 1 is characterized in that: The pile foundation construction simulation module includes a construction simulation unit, a risk assessment unit and a result generation unit; The construction simulation unit is used to simulate the drilling stage, hole cleaning stage, steel cage installation stage, concrete pouring stage and pile formation stage in pile foundation construction by using a numerical simulation method based on the mechanical behavior model of the karst cave area; The risk assessment unit is used to analyze the stress and deformation distribution of the pile foundation at different construction stages based on the numerical simulation results of the construction simulation unit, identify the stress concentration area and the high deformation area, and then obtain the risk points of the pile foundation, preset risk indicators, and divide the risk points into different risk levels; The result generating unit is used to display the distribution of risk points and risk levels in the form of a cloud map.
5. The risk prediction system for pile foundation construction in multi-layer karst cave areas according to claim 1 is characterized in that: The pile foundation construction monitoring module includes a monitoring equipment deployment unit, a data fusion analysis unit and a risk point adjustment unit; The monitoring equipment deployment unit is used to deploy geological radar, sonic detector, optical fiber sensor, inclinometer and pore water pressure gauge at the pile foundation construction site in the karst cave area; The data fusion analysis unit is used to fuse the data collected by each monitoring device and comprehensively analyze the geological information and pile foundation status of the pile foundation construction area; The risk point adjustment unit is used to compare and analyze the real-time monitoring data with the numerical simulation results, identify new risk points and changes in original risk points, and then make real-time adjustments to the pile foundation risk points and re-evaluate the risk level of each risk point.
6. The risk prediction system for pile foundation construction in multi-layer karst cave areas according to claim 1 is characterized in that: The construction risk warning module includes a risk index determination unit, a warning signal triggering unit and a warning signal transmission unit; The risk index determination unit is used to select risk assessment indicators including maximum principal stress, displacement and safety factor, assign different weight coefficients to each indicator based on its importance, and obtain the risk index by weighted summation method; The warning signal triggering unit is used to obtain the current risk index in real time based on the risk index determination unit, and compare the current risk index with a preset risk threshold. When the risk index exceeds the preset risk threshold, different levels of warning signals are automatically generated for warning; The warning signal transmission unit is used to notify construction management personnel via SMS, email or mobile phone APP push, and automatically match the corresponding emergency plan according to the warning level.
7. A method for predicting the risk of pile foundation construction in multi-layer karst cave areas, characterized in that: The risk prediction system for pile foundation construction in multi-layer karst cave areas according to any one of claims 1 to 6 comprises the following steps: Acquire geological survey data of a multi-layer karst cave area, and establish a three-dimensional geological model based on the geological survey data; Based on the three-dimensional geological model of multi-layer karst caves, the mechanical behavior model of the karst cave area is established using geological theoretical analysis methods; Based on the mechanical behavior model of the karst cave area, the pile foundation construction process is simulated by numerical simulation method, and the risk points and risk levels of the pile foundation are predicted based on the numerical simulation results; Based on the real-time collection of geological information of the pile foundation construction area by monitoring equipment, the geological information is compared with the numerical simulation results to dynamically adjust the risk points of the pile foundation; Based on real-time monitoring data and numerical simulation results, the risk index of the risk point is calculated, and an early warning is issued when the risk index exceeds the preset risk threshold.
8. An electronic device, characterized in that: include: Memory and processor; The memory is used to store programs; the processor is used to execute the programs to implement the various modules of the risk prediction system for building pile foundation construction in multi-layer karst cave areas as described in any one of claims 1-6.
9. A readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by the processor, each module of the risk prediction system for building pile foundation construction in multi-layer karst cave areas as described in any one of claims 1-6 is implemented.
Citation Information
Patent Citations
Real-time visual early warning method for risks in construction process of subway station
CN112926110A
Pile foundation stress analysis method, device and equipment based on BIM (Building Information Modeling) and storage medium
CN117077253A
Karst area rotary excavating cast-in-place pile construction method based on BIM three-dimensional geological model
CN117702724A
Building construction quality traceability management method and system
CN117852963A
Cited By
Geotechnical investigation risk analysis method, system, equipment, medium and product
CN119849955A
Early warning method and system for preventing slurry leakage of karst pile foundation
CN120429940A
Pile foundation pore-forming quality control method under complex karst geology
CN120524580A
A method for quality control of pile foundation drilling in complex karst geology
CN120524580B
Pile foundation position karst cave exploration optimization and classification processing method
CN121009438A