Pipe gallery cable bracket and construction method for cable installation
By opening a set position hole on the embedded parts to fix it on the wall formwork, using the bracket and spiral jack to quickly locate the vertical angle steel, and laying the cable layered with the roller laying device, the complex positioning and labor intensity of embedded parts in traditional construction are solved. The major problem is that efficient cable bracket and cable installation is achieved.
Patent Information
- Application Number
- CN202411033829.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-11-15
AI Technical Summary
In the construction of urban pipeline corridors, traditional cable brackets and cable installation construction methods have problems such as large positioning workload, high labor intensity and low construction efficiency. The embedded parts are prone to concave after being fixed on the steel frame. This leads to waste of materials and complex installation.
Setting holes are used to open on the embedded parts, fix them on the wall formwork with bolts, and the vertical angle steel height is quickly positioned through the bracket and the spiral jack, and cables are laid layer by using roller laying devices to reduce manpower support and material waste.
It improves the installation accuracy of embedded parts, reduces the difficulty of vertical angle steel installation, reduces labor intensity, improves the construction efficiency of cable brackets and cable installation, saves materials and manpower, and simplifies the construction process.
Smart Images

Figure CN118970735A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of power compartments in pipe corridors, and in particular to a pipe corridor cable bracket and a construction method for cable installation. Background Art
[0002] In the construction of urban pipe corridors, power compartments and integrated compartments are generally set up. High-voltage power cables are laid in the power compartments. The cable cross-section is large, and the brackets need to have a higher bearing capacity. A single set of brackets consists of a vertical angle steel and multiple rows of horizontal short angle steels. The vertical angle steels are welded and fixed to the embedded parts of the concrete wall. The spacing between the brackets is 800 to 1000, and the cables are laid directly on the horizontal short angle steels.
[0003] The traditional construction method of cable brackets and cable installation is: first, each embedded part is installed and fixed on the steel bars of the corridor wall according to the designed position, and then the wall side formwork is sealed; after the formwork is removed, the wire is laid on the embedded parts; then the vertical angle steel is installed, and then the multi-layer brackets are installed in order from low to high; after the bracket is installed, a winch is used for traction and manpower is used for laying.
[0004] The traditional cable tray and cable installation construction scheme has the following problems:
[0005] 1) Due to the undulating terrain of the corridor or the road, the elevation of each embedded part is different, and the workload of measuring and positioning the embedded parts is extremely large;
[0006] 2) The embedded parts are first fixed on the steel skeleton, and after the mold is sealed, concrete is poured, and most of the embedded parts are recessed into the wall surface; before installing the bracket, it is necessary to chisel off the concrete on the surface of the embedded parts, and then weld transition plates of different thicknesses, which is labor-intensive and wastes materials;
[0007] 3) The weight of a single vertical angle steel is about 35kg. When the vertical angle steel is in place, manpower is needed to adjust the height and verticality, and spot welding is required to fix it. The entire process is completed by manpower, which requires high labor intensity, high labor costs, and low construction efficiency. Summary of the invention
[0008] The technical problem to be solved by the present invention is to provide a cable bracket and a construction method for cable installation, which can improve the installation accuracy of embedded parts, reduce the difficulty of vertical angle steel installation, reduce labor intensity, and improve the installation efficiency of cable bracket and cable.
[0009] In order to solve the above technical problems, the present invention adopts the following technical solutions:
[0010] A construction method for a pipe gallery cable bracket and cable installation, the construction method comprising the following construction steps:
[0011] Step 1) Installation of embedded parts: at least two positioning holes are opened on the embedded parts, and the embedded parts are fixed to the template of the pipe gallery wall by passing bolts through the two positioning holes of the embedded parts;
[0012] Step 2) Installation of vertical angle steel and brackets:
[0013] Step 21) Laying out the lines: Laying out the vertical position control lines and horizontal elevation control lines of each bracket group, and the horizontal elevation control lines are set on the bottom end surface of the vertical angle steel;
[0014] Step 22) Making a bracket: The bracket is welded by a limit ring, a flat plate, a positioning plate, and a limit plate;
[0015] Step 23) Installation of the bracket and vertical angle steel: install the bracket on the screw jack, adjust the bottom surface of the positioning plate of the bracket to coincide with the horizontal elevation control line of the bracket, place the bottom end surface of the vertical angle steel on the bracket, and weld the vertical angle steel;
[0016] Step 3) Cable laying:
[0017] Step 31) making a roller laying device: the roller laying device is composed of a limit folding plate, two sets of supports, a rotating shaft, a roller structure, and a retaining ring;
[0018] Step 32) Layered laying of cables: A roller laying device is installed at the outer end of the bracket, and the cables are laid from the inside to the outside of each layer, and the cables are laid in layers.
[0019] Further, in step 22), the limiting ring of the bracket is fixed to the lower end of the flat plate, the positioning plate and the limiting plate are respectively fixed to the left and right sides of the upper end of the flat plate, and a receiving space matching the shape of the vertical angle steel is formed between the positioning plate and the limiting plate. The bracket is connected to the top of the screw jack through the limiting ring, and the vertical angle steel is placed on the receiving space of the bracket.
[0020] Furthermore, step 23) the installation of the bracket and the vertical angle steel includes the following steps:
[0021] Step 231) by moving the screw jack, the positioning plate of the bracket on the screw jack is made to coincide with the vertical control line of the bracket;
[0022] Step 232) raising and lowering the screw jack so that the bottom surface of the positioning plate of the bracket on the screw jack coincides with the horizontal elevation control line of the bracket;
[0023] Step 233) Place the bottom end face of the vertical angle steel directly on the bracket, with the back of one limb of the vertical angle steel close to the positioning plate, and the back of the other limb of the vertical angle steel close to the embedded parts on the tunnel wall formwork. Use a spirit level to measure the vertical angle steel and adjust it. After the verticality of the vertical angle steel meets the requirements, weld the vertical angle steel.
[0024] Step 234) lower the screw jack, move the mobile screw jack, move the mobile screw jack to the adjacent bracket position, and install the next set of brackets according to the above installation steps.
[0025] Further, in step 31), the limiting folding plate of the roller laying device is fixed below the two groups of fixed supports and the roller structure, the two groups of fixed supports are symmetrically welded at the middle position of the upper surface of the limiting folding plate, and the roller structure is fixed between the two groups of fixed supports.
[0026] Furthermore, a first limiting groove and a second limiting groove are respectively formed on both sides of the lower end of the limiting folding plate, and the two ends of the bracket are respectively inserted into the first limiting groove and the second limiting groove of the limiting folding plate to install the roller structure on the bracket.
[0027] Furthermore, the roller structure includes a cable drum and a rotating shaft, the rotating shaft is fixed between two groups of fixed supports, the cable drum is installed on the outer surface of the rotating shaft, and the cable is laid on the cable drum.
[0028] Furthermore, a retaining ring is installed on the outer end of the cable drum.
[0029] Furthermore, the bracket is an L-shaped angle steel structure, and a first clamping position is formed on the edge of one end of the short side steel plate of the L-shaped angle steel structure, and a second clamping position is formed on the other end of the short side steel plate of the L-shaped angle steel structure. The bracket is clamped into the first limiting groove and the second limiting groove of the limiting folding plate through the first clamping position and the second clamping position at both ends of the short side steel plate of the L-shaped angle steel structure to insert the bracket into the lower end of the limiting folding plate, thereby realizing the installation of the rolling device and the bracket.
[0030] Further, in step 32), the cable layered laying includes:
[0031] Step 321) first install the cables of the uppermost layer, install the roller laying device on the first section of the laying bracket of the layer, and the roller laying device is installed on the end of the bracket;
[0032] Step 322) first lay the innermost cable at the base of the bracket of the first segment. After the cable of this segment is pulled, the first cable is manually moved from the roller structure to the installation position. The second innermost cable is pulled in this order, and then the second cable is manually moved from the roller structure to the installation position. After the outermost cable of this layer is pulled, the cable needs to be moved from the roller structure to the bracket surface, and then the roller laying device is removed, and then the cable is moved to the installation position;
[0033] Step 323) Laying the next segment of cable, first install the roller structure, and then complete the laying of all cables in the above order until all segments are laid;
[0034] Step 324) After the first layer of cables is laid, the next layer of cables may be laid;
[0035] Step 325) After the next layer of cable laying is completed, all layers of cable laying can be completed in the above-mentioned laying sequence.
[0036] Furthermore, the template in step 1) is a wooden template, the templates are arranged in groups, four templates form a group of template units, and the wooden templates can be reused.
[0037] Compared with the prior art, the present invention has the following beneficial effects:
[0038] The construction method of the present invention includes: opening at least two positioning holes on the embedded parts, fixing the embedded parts on the template of the tunnel wall by passing bolts through the two positioning holes of the embedded parts; installing the bracket on the screw jack, adjusting the bottom surface of the positioning plate of the bracket to coincide with the horizontal elevation control line of the bracket, placing the bottom end surface of the vertical angle steel on the bracket, and welding the vertical angle steel; making a roller laying device, the roller laying device is installed on the outer end of the bracket, and the cables are laid from the inside to the outside of each layer, and the cables are laid in layers. The present invention uses bolts to pass through the two positioning holes of the embedded parts to fix the embedded parts on the template of the tunnel wall, changing the traditional method of installing and positioning the embedded parts on the steel skeleton, and directly fixing the embedded parts on the wall template, reducing a large number of embedded parts positioning and welding operations, and the bracket supports to determine the installation height of the vertical angle steel, and no manpower is required to support the weight of the vertical angle steel. The roller laying device is provided, the cable traction force is small, the laying is convenient, and the cable jacket will not be damaged, and it can be conveniently reused. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] Figure 1 A flow chart of the cable bracket and cable installation of the present invention;
[0040] Figure 2 It is a schematic diagram of the relationship between the template and the embedded parts of the present invention;
[0041] Figure 3 It is a structural diagram of the embedded part of the present invention;
[0042] Figure 4 This is a schematic diagram of the relationship between the embedded parts of the present invention being fixed to the template by bolts;
[0043] Figure 5 It is a schematic diagram of the relationship between the vertical angle steel and the bracket of the present invention;
[0044] Figure 6 For the present invention Figure 5 Cross-section of the middle AA;
[0045] Figure 7 It is a structural schematic diagram of the bracket of the present invention;
[0046] Figure 8 A top view of the bracket of the present invention;
[0047] Fig. 9 It is a side elevation schematic diagram of the roller laying device of the present invention;
[0048] Fig.10 It is a schematic front elevation view of the roller laying device of the present invention;
[0049] Fig.11 It is a side elevation schematic diagram of the cable traction of the present invention;
[0050] Fig.12 It is a front elevation schematic diagram of the cable traction of the present invention;
[0051] Fig.13 It is a side elevation schematic diagram of the position-limiting folding plate of the present invention;
[0052] Fig.14 is a side elevational schematic diagram of the bracket of the present invention;
[0053] Fig.15 It is a schematic elevation view of the cross section of the power compartment of the pipe gallery of the present invention;
[0054] Fig.16 This is a schematic diagram of the installation of the vertical angle steel of the present invention placed on the bracket;
[0055] Figure 17-Figure 24 It is a schematic diagram of the sequence of layered cable laying by the roller laying device of the present invention.
[0056] In the figure, the corridor power compartment 1, the bracket 11, the first clamping position 111, the second clamping position 112, the vertical angle steel 12, the corridor wall 13, the roller laying device 2, the fixed support 21, the roller structure 22, the cable drum 221, the rotating shaft 222, the retaining ring 223, the limiting folding plate 23, the first limiting groove 231, the second limiting groove 232, the first folding plate 233, the second folding plate 234, the third folding plate 235, the fourth folding plate 236, the cable 3, the embedded part 4, the positioning hole 41, the bolt 42, the template 5, the bracket 6, the limiting ring 61, the flat plate 62, the positioning plate 63, the limiting plate 64, the accommodating space 65, the screw jack 7, and the integrated cabin 8. DETAILED DESCRIPTION
[0057] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0058] like Figure 1-8As shown, the first embodiment of the present invention provides a construction method for installing a cable 3 bracket 11 and a cable 3 in a pipe gallery, and the construction method includes the following construction steps:
[0059] Step 1) Installation of embedded parts 4: at least two positioning holes 41 are provided on the embedded parts 4, and bolts 42 are used to pass through the two positioning holes 41 of the embedded parts 4 to fix the embedded parts 4 to the template 5 of the pipe gallery wall 13. In specific implementation, each embedded part 4 has two positioning holes 41, the aperture of the positioning holes 41 is 11 mm, and the spacing between the positioning holes 41 and the positioning holes 41 is 150 mm. The bolts 42 are M10 bolts 42. The template 5 is a wooden template, and the templates 5 are arranged in groups. Four templates 5 form a group of template units, and the wooden templates can be reused;
[0060] Step 2) Installation of vertical angle steel 12 and bracket 11:
[0061] Step 21) Laying out the lines: Laying out the vertical position control lines and horizontal elevation control lines of each set of brackets 11, and the horizontal elevation control lines are set on the bottom end surface of the vertical angle steel 12;
[0062] Step 22) manufacturing the bracket 6: the bracket 6 is welded together by a limiting ring 61, a flat plate 62, a positioning plate 63, and a limiting plate 64;
[0063] Step 23) Installation of the bracket 6 and the vertical angle steel 12: Install the bracket 6 on the screw jack 7, adjust the bottom surface of the positioning plate 63 of the bracket 6 to coincide with the horizontal elevation control line of the bracket 11, place the bottom end surface of the vertical angle steel 12 on the bracket 6, and weld the vertical angle steel 12; the vertical angle steel 12 adopts the support method of the screw jack 7 combined with the bracket 6, which can not only quickly locate the height of the vertical angle steel 12, but also support the weight of the vertical angle steel 12, which is convenient for adjusting the verticality and welding and fixing the vertical angle steel 12;
[0064] Step 3) Cable 3 laying:
[0065] Step 31) manufacturing the roller laying device 2: the roller laying device 2 is assembled by a limit folding plate 23, two sets of supports, a rotating shaft 222, a roller structure 22, and a retaining ring 223;
[0066] Step 32) Cables 3 are laid in layers: the roller laying device 2 is installed at the outer end of the bracket 11, and cables 3 are laid from the inside to the outside in each layer, and the cables 3 are laid in layers.
[0067] The present invention uses bolts 42 to pass through two positioning holes 41 of the embedded parts 4 to fix the embedded parts 4 on the template 5 of the pipe gallery wall 13, changing the traditional method of installing and positioning the embedded parts 4 on the steel frame, and directly fixing the embedded parts 4 on the wall template 5, reducing a large number of embedded parts 4 positioning and welding operations, saving a large amount of materials and manpower, and making the installation easier, simplifying the installation process of the embedded parts 4, saving a large amount of manpower and material resources, improving the installation accuracy of the embedded parts 4, saving a large amount of manpower and material resources, and directly fixing the embedded parts 4 on the template 5 of the pipe gallery wall 13 with bolts 42. The surface of the embedded part 4 is flush with the concrete surface, which saves a lot of chiseling and repairing work caused by the embedded part 4 being recessed in the concrete surface. The installation height of the vertical angle steel 12 is now supported by the bracket 6, and there is no need for manpower to support the weight of the vertical angle steel 12. It only needs to be supported by manpower to prevent it from overturning. The designed bracket 6 has a simple structure. By cooperating with the screw jack 7, the angle and height of the vertical angle steel 12 can be adjusted, and the adjustment is convenient. A roller laying device 2 is provided, the traction force of the cable 3 is small, the laying is convenient, and the outer jacket of the cable 3 will not be damaged, so it can be easily reused.
[0068] When the present invention is implemented specifically, in step 22), the limiting ring 61 of the bracket 6 is fixed to the lower end of the flat plate 62, the positioning plate 63 and the limiting plate 64 are respectively fixed to the left and right sides of the upper end of the flat plate 62, and a receiving space 65 matching the shape of the vertical angle steel 12 is formed between the positioning plate 63 and the limiting plate 64. The bracket 6 is connected to the top of the screw jack 7 through the limiting ring 61, and the vertical angle steel 12 is placed on the receiving space 65 of the bracket 6.
[0069] In specific implementation, the installation of the bracket 6 and the vertical angle steel 12 in step 23) of the present invention includes the following steps:
[0070] Step 231) by moving the screw jack 7, the positioning plate 63 of the bracket 6 on the screw jack 7 is made to coincide with the vertical control line of the bracket 11;
[0071] Step 232) by lifting the screw jack 7, the bottom surface of the positioning plate 63 of the bracket 6 on the screw jack 7 is made to coincide with the horizontal elevation control line of the bracket 11;
[0072] Step 233) Place the bottom end surface of the vertical angle steel 12 directly on the bracket 6, with the back of one angle steel limb of the vertical angle steel 12 close to the positioning plate 63, and the back of the other angle steel limb of the vertical angle steel 12 close to the embedded part 4 on the tunnel wall 13 template 5, measure the vertical angle steel 12 with a spirit level and adjust it. After the verticality of the vertical angle steel 12 meets the requirements, weld the vertical angle steel 12.
[0073] Step 234) lower the screw jack 7, move the screw jack 7, move the movable screw jack 7 to the position of the adjacent bracket 11, and install the next group of brackets 11 according to the above installation steps.
[0074] like Figure 9-14 As shown, when the embodiment of the present invention is specifically implemented, in step 31), the limiting folding plate 23 of the roller laying device 2 is fixed below the two groups of fixed supports 21 and the roller structure 22, and the two groups of fixed supports 21 are symmetrically welded at the middle position of the upper surface of the limiting folding plate 23, and the roller structure 22 is fixed between the two groups of fixed supports 21 to realize the installation of the roller laying device 2, and the first limiting groove 231 and the second limiting groove 232 are respectively formed on both sides of the lower end of the limiting folding plate 23, and the two ends of the bracket 11 are respectively inserted into the first limiting groove 231 and the second limiting groove 232 of the limiting folding plate 23 to install the roller structure 22 on the bracket 11, thereby realizing the installation of the roller laying device 2 and the bracket 11. By setting the limiting folding plate 23, it is convenient to insert the bracket 11 into or move it out of the limiting folding plate 23, so that the roller laying device 2 can be firmly fixed. It can also reduce the friction between the cable 3 and the surface of the bracket 11, and solve the problems of large traction resistance, difficult laying, and damage to the cable 3 caused by the friction between the outer jacket of the cable 3 and the surface of the bracket 11 when laying the cable 3. The cable 3 adopts a layered and segmented laying method to achieve the purpose of isolating the cables 3 from each other and not interfering with each other, thereby achieving the effect of protecting the cable 3 and facilitating and quickly laying the cable.
[0075] The roller structure 22 of the present invention includes a cable drum 221 and a rotating shaft 222, the rotating shaft 222 is fixed between the two sets of fixed supports 21, the cable drum 221 is installed on the outer surface of the rotating shaft 222, the cable 3 is laid on the cable drum 221, and a retaining ring 223 is installed at the outer end of the cable drum 221, and the retaining ring 223 can prevent the cable 3 from escaping from the cable drum 221, and the bracket 11 is an L-shaped angle steel structure, and the edge of one end of the short side steel plate of the L-shaped angle steel structure is formed with a first clamping position 111, and the other end of the short side steel plate of the L-shaped angle steel structure is formed with a second clamping position 112, and the bracket 11 is clamped by the first clamping position 111 and the second clamping position 112 at both ends of the short side steel plate of the L-shaped angle steel structure. The first limiting groove 231 and the second limiting groove 232 of the limiting folding plate 23 are inserted into the lower end of the limiting folding plate 23 to insert the bracket 11 into the lower end of the limiting folding plate 23, so as to realize the installation of the rolling device and the bracket 11. The first limiting groove 231 is set to a groove structure that matches the shape of the first clamping position 111 of the bracket 11, and the second limiting groove 232 is set to an L-groove structure that matches the shape of the second clamping position 112 of the bracket 11. The installation and disassembly are simple, and the first limiting groove 231 and the second limiting groove 232 of the limiting folding plate 23 can play a limiting role to prevent the roller structure 22 from falling off the bracket 11. When the cable 3 is laid on the roller structure 22 and all are pulled into place, they are manually translated to the bracket 11.
[0076] When the embodiment of the present invention is specifically implemented, in step 32 of the present invention, the layered laying of the cables 3 includes:
[0077] Step 321) first install the cable 3 of the top layer, install the roller laying device 2 on the first section of the laying bracket 11 of the layer, and the roller laying device 2 is installed at the end of the bracket 11;
[0078] Step 322) first lay the innermost cable 3 at the root of the bracket 11 of the first segment. After the cable 3 of this segment is pulled, the first cable 3 is manually moved from the roller structure 22 to the installation position. The second innermost cable 3 is pulled in this order, and then the second cable 3 is manually moved from the roller structure 22 to the installation position. After the outermost cable 3 of this layer is pulled, the cable 3 needs to be moved from the roller structure 22 to the surface of the bracket 11, and then the roller laying device 2 is removed, and then the cable 3 is moved to the installation position;
[0079] Step 323) Laying the next segmented cable 3, first installing the roller structure 22, and then completing the laying of all cables 3 in the above-mentioned laying order until all the segments are laid;
[0080] Step 324) After the first layer of cables 3 is laid, the next layer of cables 3 may be laid;
[0081] Step 325) After the next layer of laying is completed, the laying of all layers of cables 3 can be completed in the above-mentioned laying order.
[0082] Figure 15-Figure 24 The specific operation process of the construction method of the present invention for installing the cable 3 bracket 11 and the cable 3 in the power compartment 1 of the pipe gallery is as follows:
[0083] The length of the pipe gallery is about 3.5 km, and the cross-sectional dimensions of the pipe gallery are 6.760 m × 3.800 m. It is equipped with a comprehensive cabin 8 and a power cabin. Two rows of cable 3 brackets 11 are arranged along the walls on both sides of the power cabin, with 8 layers. The spacing between each set of brackets 11 is 800, and the length of the vertical angle steel 12 of each set of brackets 11 is 3300 mm, with a cross-sectional dimension of ∠100×100×10; the length of the bracket 11 is 755 mm, the root cross-sectional dimension of the vertical angle steel 12 is ∠150×100×6, and the root cross-sectional dimension of the bracket 11 is ∠100×100×6;
[0084] The height of the side wall of the pipe gallery wall 13 is 3800mm, and the standard size of a single template 5 is 1220mmx2440mm. A batch of 1220mmx1360mm templates 5 are made, and every four templates 5 form a group of template units. The lower part of the template unit is distributed with two 2440mm high templates, and the upper part of the template unit is distributed with two 1360mm high templates. Every four templates 5 form a 2440mmx3800mm template unit, and each template 5 in the template unit is numbered, and the number is written on the outside of the template 5 with a large oil-based marker;
[0085] Step 1) Installation of embedded parts 4:
[0086] Arrange the positioning holes 41 of the embedded parts 4 of each group of templates 5 to form a processing drawing of templates 5 numbered 1 to 4;
[0087] The adjacent spacing m of each bracket group 11 is optimized as follows:
[0088] m = 1220a / b, (a, b are integers, m = 800 to 1000)
[0089] Wherein, a is the number of templates 5. If a is less than 5, the template 5 can be reused 8 to 10 times. If the corridor is very long, it also needs to be constructed in sections.
[0090] Finally, it is optimized to 1220*2 / 3=813.3mm, so that the positioning holes 41 on each set of templates 5 are exactly the same, so as to facilitate the installation of the templates 5;
[0091] Arrange the positioning holes 41 of the embedded parts 4 on the template 5, use a CNC drilling machine to drill holes on the template 5 according to the layout drawing, use the CNC drilling machine to process the positioning holes 41 of all embedded parts 4, and process the installation holes of all templates 5 according to the template processing drawing. The hole diameter is 10.5mm, and the templates 5 numbered 1 to 4 are processed for no less than 60 pieces each;
[0092] The length of the pipe gallery is poured with concrete in sections, and the length of each section of concrete pouring is 250m. It is necessary to process about 60 sets of templates 5, and the outer surface of each template 5 of the template unit is marked with numbers, namely template No. 1, template No. 2, template No. 3, and template No. 4;
[0093] Install the template units in the order of numbers. Before installing the template 5, use two M10 bolts 42 to fix each embedded part 4 to the corresponding hole position of the template 5, with the tail of the bolt 42 facing outward, and use nuts to fix the bolt 42 and the embedded part 4 to the template 5 of the corridor wall 13;
[0094] After pouring is completed, remove the nuts first and then remove the formwork 5;
[0095] Carry the template 5 to the next working section in this order, and install the template 5 and the embedded part 4 in the above order. As long as the group template units numbered as template 1, template 2, template 3, and template 4 are installed;
[0096] After the template 5 is installed, concrete is poured, and the concrete strength reaches the requirement, the template 5 can be removed. The removed template 5 can be used for the next segmented pipe gallery, and the next segmented pipe gallery embedded parts 4 can be directly installed; if a small number of templates 5 are damaged, they can be directly replaced according to the number, and the template 5 set by the present invention can be reused.
[0097] Step 2) Installation of vertical angle steel 12:
[0098] First, lay out the lines, including the vertical position control lines and horizontal elevation control lines of each bracket 11. The horizontal elevation control lines are set on the bottom end surface of the vertical angle steel 12;
[0099] A bracket 6 is manufactured, wherein the bracket 6 is welded together by a limiting ring 61, a flat plate 62, a positioning plate 63, and a limiting plate 64;
[0100] The bracket 6 is directly mounted on the screw jack 7, and the positioning plate 63 of the bracket 6 is made to coincide with the vertical control line of the bracket 11 by moving the screw jack 7; then the screw jack 7 is raised and lowered to coincide with the upper surface of the plate 62 and the bottom end surface of the vertical angle steel 12;
[0101] Place the bottom end face of the vertical angle steel 12 directly on the bracket 6, with one limb of the vertical angle steel 12 close to the positioning plate 63, and the other limb of the vertical angle steel 12 close to the pre-embedded part 4. Use a level ruler to measure the vertical angle steel 12 and adjust it. After the verticality of the vertical angle steel 12 meets the requirements, the vertical angle steel 12 can be welded;
[0102] Lower the screw jack 7, move to the adjacent position and install the next set of brackets 11 according to the above method;
[0103] Step 3) Laying of cable 3:
[0104] Step 31) Make the roller laying device 2: The roller laying device 2 is composed of a limiting folding plate 23, two groups of supports, a rotating shaft 222, a roller structure 22, and a retaining ring 223. The limiting folding plate 23 is fixed below the two groups of fixed supports 21 and the roller structure 22. The two groups of fixed supports 21 are symmetrically welded at the middle position of the upper surface of the limiting folding plate 23. The roller structure 22 is fixed between the two groups of fixed supports 21 to realize the installation of the roller laying device 2. The first limiting groove 231 and the second limiting groove 232 are respectively formed on both sides of the lower end of the limiting folding plate 23. The two ends of the bracket 11 are respectively inserted into the first limiting groove 231 and the second limiting groove 232 of the limiting folding plate 23 to install the roller structure 22 on the bracket 11, thereby realizing the installation of the roller laying device 2 and the bracket 11. The limiting folding plate 23 is formed by bending a steel plate with a thickness of 4 mm, and the limiting folding plate 23 is respectively bent into a first folding plate 233, a second folding plate 234, a third folding plate 235, and a fourth folding plate 236. The first folding plate 233, the second folding plate 234, the third folding plate 235, and the fourth folding plate 236 are connected end to end in sequence, one end of the second folding plate 234 is connected to the first folding plate 233, and the other end of the second folding plate 234 is connected to one end of the third folding plate 235 to form a first limiting groove 231, and the other end of the third folding plate 235 is connected to the fourth folding plate 236 to form a second limiting groove 232. The length of the first folding plate 233 is 40 mm, the length of the second folding plate 234 is 8 mm, the length of the third folding plate 235 is 102 mm, and the length of the fourth folding plate 236 is 40 mm.
[0105] Step 32) Cable 3 is laid in layers: the roller laying device 2 is installed at the outer end of the bracket 11, and the cables 3 are laid from the inside to the outside of each layer. The cables 3 are laid in layers, and the cables 3 of the top layer are installed first. The roller laying device 2 is installed on the first section of the laying bracket 11 of the layer, and the roller laying device 2 is installed at the end of the bracket 11;
[0106] First, the innermost cable 3 at the root of the bracket 11 of the first segment is laid. After the cable 3 of this segment is pulled, the first cable 3 is manually moved from the roller structure 22 to the installation position; the second innermost cable 3 is pulled in this order, and then the second cable 3 is manually moved from the roller structure 22 to the installation position; after the outermost cable 3 of this layer is pulled, the cable 3 needs to be moved from the roller structure 22 to the surface of the bracket 11, and then the roller laying device 2 is removed, and then the cable 3 is moved to the installation position;
[0107] To lay the next segmented cable 3, first install the roller structure 22, and then complete the laying of all cables 3 in the above-mentioned order until all the segments are laid;
[0108] After the first layer of cables 3 is laid, the next layer of cables 3 can be laid; after the next layer is laid, all layers of cables 3 can be laid in sequence.
[0109] Compared with the prior art, the technical solution disclosed in the above embodiment has the following beneficial effects:
[0110] In the above embodiment, the installation method of the embedded parts 4 adopted in the construction method of the present invention changes the traditional construction method of a single installation and fixation on the steel skeleton. The vertical angle steel 12 is fixed by welding with multiple embedded parts 4. The embedded parts 4 have a small deviation in the height direction, which does not affect the connection strength of the vertical angle steel 12. The installation deviation of the template 5 of the corridor wall 13 in the vertical direction generally does not exceed 10 mm. In addition, by limiting the verticality of the template 5, the deviation control of the embedded parts 4 in another direction is guaranteed. Therefore, using the template 5 to fix the embedded parts 4 meets the installation accuracy requirements. The templates 5 are arranged in groups and the templates 5 are numbered and combined so that all the templates 5 are divided into only four specifications and can be replaced with each other, ensuring that the templates 5 can be reused and the embedded parts 4 can be repeatedly positioned when they are used for the second time; the installation of the vertical angle steel 12 of the present invention adopts a support method with a screw jack 7+bracket 6, which can not only quickly locate the height of the vertical angle steel 12, but also support the weight of the angle steel, making it convenient to adjust the verticality and weld and fix the angle steel; the roller laying device 2 of the present invention is provided with a limiting folding plate 23, so that the rolling structure can be firmly fixed on the bracket 11, facilitating the installation and removal of the rolling structure; the cables 3 are laid in a layered order, and the rolling structure is installed at the outer end of the bracket 11, and the cables 3 are laid from the inside to the outside.
[0111] The present invention has been described in detail above. The above description is only a preferred embodiment of the present invention and should not limit the scope of implementation of the present invention. That is, all equivalent changes and modifications made within the scope of this application should still fall within the scope of the present invention.
Claims
1. A construction method for a pipe gallery cable bracket and cable installation, Features: The construction method comprises the following construction steps: Step 1) Installation of embedded parts: at least two positioning holes are opened on the embedded parts, and the embedded parts are fixed to the template of the pipe gallery wall by passing bolts through the two positioning holes of the embedded parts; Step 2) Installation of vertical angle steel and brackets: Step 21) Laying out the lines: Laying out the vertical position control lines and horizontal elevation control lines of each bracket group, and the horizontal elevation control lines are set on the bottom end surface of the vertical angle steel; Step 22) Making a bracket: The bracket is welded by a limit ring, a flat plate, a positioning plate, and a limit plate; Step 23) Installation of the bracket and vertical angle steel: install the bracket on the screw jack, adjust the bottom surface of the positioning plate of the bracket to coincide with the horizontal elevation control line of the bracket, place the bottom end surface of the vertical angle steel on the bracket, and weld the vertical angle steel; Step 3) Cable laying: Step 31) making a roller laying device: the roller laying device is composed of a limit folding plate, two sets of supports, a rotating shaft, a roller structure, and a retaining ring; Step 32) Layered laying of cables: A roller laying device is installed at the outer end of the bracket, and the cables are laid from the inside to the outside of each layer, and the cables are laid in layers.
2. The construction method for installing the cable bracket and the cable in the pipe gallery according to claim 1, Features: In step 22), the limiting ring of the bracket is fixed to the lower end of the flat plate, the positioning plate and the limiting plate are respectively fixed to the left and right sides of the upper end of the flat plate, and a receiving space matching the shape of the vertical angle steel is formed between the positioning plate and the limiting plate. The bracket is connected to the top of the screw jack through the limiting ring, and the vertical angle steel is placed on the receiving space of the bracket.
3. The construction method for installing the cable bracket and cable in the pipe gallery according to claim 1, Features: Step 23) The installation of the bracket and vertical angle steel includes the following steps: Step 231) by moving the screw jack, the positioning plate of the bracket on the screw jack is made to coincide with the vertical control line of the bracket; Step 232) raising and lowering the screw jack so that the bottom surface of the positioning plate of the bracket on the screw jack coincides with the horizontal elevation control line of the bracket; Step 233) Place the bottom end face of the vertical angle steel directly on the bracket, with the back of one limb of the vertical angle steel close to the positioning plate, and the back of the other limb of the vertical angle steel close to the embedded parts on the tunnel wall formwork. Use a spirit level to measure the vertical angle steel and adjust it. After the verticality of the vertical angle steel meets the requirements, weld the vertical angle steel. Step 234) lower the screw jack, move the mobile screw jack, move the mobile screw jack to the adjacent bracket position, and install the next set of brackets according to the above installation steps.
4. The cable bracket and cable installation method for the pipe gallery according to claim 1, Features: In step 31), the limiting folding plate of the roller laying device is fixed below the two groups of fixed supports and the roller structure, the two groups of fixed supports are symmetrically welded at the middle position of the upper surface of the limiting folding plate, and the roller structure is fixed between the two groups of fixed supports.
5. The construction method for installing the cable bracket and the cable in the pipe gallery according to claim 1, Features: A first limiting groove and a second limiting groove are respectively formed on both sides of the lower end of the limiting folding plate, and the two ends of the bracket are respectively inserted into the first limiting groove and the second limiting groove of the limiting folding plate to install the roller structure on the bracket.
6. The construction method for installing the cable bracket and cable in the pipe gallery according to claim 4, Features: The roller structure comprises a cable drum and a rotating shaft, wherein the rotating shaft is fixed between two groups of fixed supports, the cable drum is installed on the outer surface of the rotating shaft, and the cable is laid on the cable drum.
7. The cable bracket and cable installation construction method of the pipe gallery according to claim 6, Features: A retaining ring is installed at the outer end of the cable drum.
8. The cable bracket and cable installation construction method of the pipe gallery according to claim 5, Features: The bracket is an L-shaped angle steel structure, and a first clamping position is formed at one end edge of the short side steel plate of the L-shaped angle steel structure, and a second clamping position is formed at the other end of the short side steel plate of the L-shaped angle steel structure. The bracket is clamped into the first limiting groove and the second limiting groove of the limiting folding plate through the first clamping position and the second clamping position at both ends of the short side steel plate of the L-shaped angle steel structure to insert the bracket into the lower end of the limiting folding plate, thereby realizing the installation of the rolling device and the bracket.
9. The cable bracket and cable installation construction method of the pipe gallery according to claim 1, Features: In step 32), the cable layered laying includes: Step 321) first install the cables of the uppermost layer, install the roller laying device on the first section of the laying bracket of the layer, and the roller laying device is installed on the end of the bracket; Step 322) first lay the innermost cable at the base of the bracket of the first segment. After the cable of this segment is pulled, the first cable is manually moved from the roller structure to the installation position. The second innermost cable is pulled in this order, and then the second cable is manually moved from the roller structure to the installation position. After the outermost cable of this layer is pulled, the cable needs to be moved from the roller structure to the bracket surface, and then the roller laying device is removed, and then the cable is moved to the installation position; Step 323) Laying the next segment of cable, first install the roller structure, and then complete the laying of all cables in the above order until all segments are laid; Step 324) After the first layer of cables is laid, the next layer of cables may be laid; Step 325) After the next layer of cable laying is completed, all layers of cable laying can be completed in the above-mentioned laying sequence.
10. The cable bracket and cable installation construction method of the pipe gallery according to claim 1, Features: The template described in step 1) is a wooden template. The templates are arranged in groups, and four templates form a group of template units. The wooden templates can be reused.