Optimized operation method and system for integrated energy transformer substation
By constructing an optimized operation model of comprehensive energy substations, considering the dispatchability and mobile energy storage characteristics of electric vehicles, optimizing battery planning and charging and swapping service fees, the problems of uneven distribution of charging and swapping loads and insufficient reserves are solved, and the comprehensive Maximize returns of energy stations and reasonable battery scheduling.
Patent Information
- Application Number
- CN202411091354.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-11-15
AI Technical Summary
The existing comprehensive energy substation optimization operation plan failed to effectively consider the coordinated pricing of electric vehicles for charging and swapping, resulting in uneven distribution of charging and swapping loads, insufficient battery storage and low utilization rate of charging piles, neglecting the dispatchability of electric vehicles. and mobile energy storage characteristics affect the benefits of integrated energy stations.
Build a comprehensive energy substation optimization operation model with battery planning scheme and charging and swapping service fee scheme as decision variables. Consider the schedulingability and mobile energy storage characteristics of electric vehicles, and obtain the battery planning scheme and charging and swapping service fee scheme through model solution. , maximize the net profit of comprehensive energy stations.
By reasonably planning the battery and optimizing the charging and swapping service fee, the problems of insufficient battery replacement battery reserves and low utilization rate of charging piles are solved, and the benefits of the comprehensive energy station are maximized, ensuring the reasonable scheduling of the battery and the coordinated operation of charging and swapping are carried out. .
Smart Images

Figure CN118971093A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of substation optimization, and in particular relates to an optimized operation method and system for a comprehensive energy substation. Background Art
[0002] With the increasing demand for energy conservation and emission reduction, the integrated development of the energy sector will become the next step in achieving the "dual carbon" goals. The construction of integrated energy substations is a beneficial exploration of this integrated development trend. Integrated energy substations, with substation resources at their core, integrate multiple resources, including renewable energy, data centers, 5G base stations, and charging stations. Through deep cooperation between the power grid and users, they provide external services such as 5G base stations and charging and swapping services, achieving coordinated and mutually beneficial business cooperation, reducing user energy costs while improving the overall economic benefits of the power grid. Specifically, 5G base stations and data centers can provide data storage, computing, and communication services for electric vehicle charging and swapping stations. Charging and swapping stations, with their dual attributes of "source" and "load," not only serve users to increase the revenue of integrated energy substations, but also transmit excess electricity to the grid, achieving peak load shifting and valley filling, reducing the operating costs of integrated energy substations.
[0003] Existing research on optimized operation schemes for integrated energy substations primarily focuses on maximizing energy storage revenue through battery scheduling within these schemes. However, these studies often consider only separate pricing strategies for charging and battery swapping, lacking research on coordinated pricing for charging and battery swapping. This also overlooks the impact of electric vehicles' dispatchability and mobile energy storage characteristics on integrated energy station revenue. Consequently, optimized operation schemes (battery scheduling / battery planning) derived from these studies are often inadequate and inaccurate. Furthermore, with the rapid growth of electric vehicles, existing research lacks consideration of coordinated pricing for charging and battery swapping for integrated energy stations that offer electric vehicle charging and battery swapping services. Failure to consider the charging and battery swapping characteristics of electric vehicles, such as plug-and-charge for charging and swapping for swapping, can easily lead to uneven distribution of charging and battery swapping loads, resulting in insufficient battery swapping reserves or low charging station utilization. Furthermore, the varying time and energy cost requirements of users complicate coordinated pricing for charging and battery swapping. While some existing technologies utilize battery swapping for grid regulation through B2G services, these technologies fail to consider the varying charging demand driven by user charging costs.
[0004] Therefore, how to design an optimized operation method and system for an integrated energy substation to achieve reasonable planning of batteries in the integrated energy substation is an urgent problem to be solved by those skilled in the art. Summary of the Invention
[0005] In order to solve the problems existing in the prior art, the present invention proposes a method and system for optimizing the operation of a comprehensive energy substation.
[0006] The technical solutions of the present invention are as follows:
[0007] A method for optimizing the operation of an integrated energy substation, wherein the integrated energy substation is provided with a plurality of batteries for replacing batteries for electric vehicles and for performing grid peak regulation through B2G services, comprising:
[0008] Based on the basic model of the integrated energy substation, an optimized operation model for the integrated energy substation is constructed, with the battery planning scheme and the charging and swapping service fee scheme as decision variables and the goal of maximizing the net profit of the integrated energy substation. The constraints of the optimized operation model for the integrated energy substation include electric vehicle power constraints, power balance constraints, electric vehicle queuing time constraints, remaining battery SOC constraints, net profit constraints, user demand constraints, and battery strategy constraints that consider the dispatchability of electric vehicles and the characteristics of mobile energy storage.
[0009] The optimized operation model of the integrated energy substation is solved to obtain an optimized operation plan of the integrated energy substation.
[0010] Furthermore, the basic model of the integrated energy substation includes a photovoltaic power station model, a data center model, a 5G base station model, a charging station model and a battery swap station model; wherein,
[0011] The photovoltaic power station model is expressed as: P PV,t =η PV AG t (1-κ(T t -T ref ))
[0012] Where, P PV,t is the output power of the photovoltaic power station during period t; η PV is the photoelectric conversion efficiency of the photovoltaic module; A is the total area of the photovoltaic module; G t is the solar radiation intensity during period t; κ is the photovoltaic temperature coefficient; T t and T ref are the ambient temperature and reference temperature during period t respectively;
[0013] The data center model is expressed as: P DC,t =L[γ IT +ΨL load,t ]
[0014] Where, P DC,t is the total energy consumption of the data center during period t; L is the number of servers in the data center; Ψ is the peak power of a single server P peak and idle power P idle The difference, that is: Ψ=P peak -P idle ; γIT is the fixed value of energy consumption of a single server under no-load condition, γ IT =P idle +(PUE-1)P peak ; PUE is the ratio of total energy consumption of data center to energy consumption of IT equipment; L load,t is the average utilization of the data center server, δ t is the amount of IT load being processed by the data center during period t; μ IT The average speed at which the server can handle IT load;
[0015] The 5G base station model is expressed as: P 5G,t =P BBU +3P AAU,t +P else
[0016] Where, P 5G,t is the total energy consumption of the 5G base station in period t; P BBU 、P AAU,t 、P AC,t and P else are the BBU energy consumption, AAU energy consumption, air conditioning energy consumption and other energy consumption of the 5G base station in period t; P AAU,t =α0U t +β0,U t Wireless utilization U t ∈[0,1]; α0 and β0 are both constants;
[0017] P else =P PTN +P SP +P MON , P PTN 、P SP and P MON They are the power of transmission equipment, switching power supply and monitoring equipment respectively;
[0018] The charging station model includes a charging price model for the charging station, a charging cost model for electric vehicle users, a charging station operation and maintenance cost model, a charging service fee constraint model, and an electric vehicle off-station SOC constraint model; the charging price model for the charging station is expressed as: c,t =e 0,t +e cs,t
[0019] Where, e c,t is the charging price of the charging station during period t; e 0,t is the time-of-use electricity price during period t; e cs,t is the service fee of the charging station during period t;
[0020] The charging cost of the electric vehicle user charging cost model is expressed as:
[0021] Where, is the charging cost of electric vehicle user i at the charging station; a and b are the starting and ending time periods of electric vehicle charging respectively; P0 is the charging power of the charging pile; is the charging time of electric vehicle i in period t;
[0022] The charging station operation and maintenance cost model is expressed as: C c =(α1+β1)P day
[0023] Where, P day is the daily operating capacity of the charging station, P day =T d P0N c ; C c is the daily operation and maintenance cost of the charging station; α1 is the labor cost ratio coefficient; β1 is the grid connection cost ratio coefficient; T d is the average operating time of the charging station in a day; N c is the number of charging piles in the charging station;
[0024] The charging service fee constraint model is: cs,max ≤e cs ≤e cs,min
[0025] The SOC constraint model of the electric vehicle leaving the station is: c,e ≤S end ≤1
[0026] Where, e cs,max and e cs,min Respectively represent the upper and lower limits of charging service fees; S c,e The expected SOC of electric vehicle users; S end The SOC when the user leaves the charging station;
[0027] The battery swap station model includes a battery swap price model, a battery depreciation cost model, a battery swap service fee constraint model, and a battery swap SOC constraint model; wherein the battery swap price model is expressed as: b,t =e 0,t +e bs,t
[0028] Where, e b,t is the price per kilowatt-hour of electricity exchanged at the battery exchange station during period t; e bs,t is the service fee of the battery swap station during period t;
[0029] The battery depreciation cost model is expressed as:
[0030] Where Cbat is the depreciation cost of the battery in the battery swap station; τ is the depreciation coefficient of the battery in the battery swap station; is the number of batteries used for battery replacement within period t; P dis,t is the discharge power of the battery; E b is the capacity of the battery at the battery swap station;
[0031] The battery swap service fee constraint model is expressed as: bs,max ≤e bs ≤e bs,min
[0032] The battery swap SOC constraint model is expressed as: S chg,min ≤S chg ≤1
[0033] Where, e bs,max and e bs,min Respectively represent the upper and lower limits of the battery replacement service fee; S chg,min The lower limit of SOC of the battery replacement that is acceptable to electric vehicle users; S chg It is the SOC of the battery for battery replacement.
[0034] Furthermore, the objective function of the integrated energy substation optimization operation model is
[0035]
[0036] in,
[0037]
[0038] Where M dis The revenue from the battery swap station's participation in peak-shaving auxiliary services and the electricity cost savings from the battery swap station's use of B2G to supply power to the station's loads when photovoltaic power is insufficient; The amount of electricity purchased from the power grid by the integrated energy substation during period t; is the number of discharged batteries in period t; is the number of batteries used for peak load regulation during period t; ω is the unit reward obtained by reducing peak load.
[0039] Furthermore, the electric vehicle power constraint is: i ≤r i S i
[0040] Where r i is the power consumption per unit mileage of electric vehicle i; S i The remaining power when charging demand is generated for electric vehicle i;
[0041] The power balance constraint is:
[0042] Where, P c 、P b are the power requirements of charging stations and battery swap stations respectively;
[0043] The electric vehicle queue time constraint is: T w ≤T w,max
[0044] Where, T w The waiting time for users at charging and swapping stations;
[0045] The remaining battery SOC constraint is: S start ≥20%
[0046] The net profit constraint: F ≥ F0
[0047] Where F0 is the net profit of the integrated energy substation when the charging and swapping station prices are not dynamically priced.
[0048] Furthermore, the battery strategy constraints that take into account the dispatchability and mobile energy storage characteristics of electric vehicles include battery state transfer constraints, battery scheduling constraints, total battery quantity constraints, battery swap quantity constraints, and charge and discharge battery quantity constraints;
[0049] Among them, the battery state transfer constraint is
[0050] Where, are the number of batteries to be charged, charging batteries, fully charged batteries and discharged batteries in the t+1 period respectively; are the number of remaining batteries to be charged, charged batteries, fully charged batteries, and discharged batteries in time period t; are the number of charging batteries and discharging batteries at the kth SOC level in period t+1, respectively; is the number of batteries replaced during the t+1 period;
[0051] The battery scheduling constraints include the following four items:
[0052] First, for batteries to be charged, follow the principle of charging low-charge batteries first and then high-charge batteries; for discharging batteries, only use fully charged batteries for discharge;
[0053] Second, for the battery replacement service, if the number of fully charged batteries in the t+1 period Greater than or equal to the battery replacement demand D b,t+1 , then reserve D b,t+1 batteries are used for battery replacement service, and the remaining batteries are used for B2G service; otherwise, D b,t+1 All batteries are reserved for battery replacement services. The insufficient number will be supplemented by batteries that meet the lower limit of SOC acceptable to electric vehicle users in descending order of SOC;
[0054] Third, the compensation mechanism for partially charged batteries. The compensation cost for partially charged batteries at battery swap stations is calculated as follows:
[0055] C d =e b,t (1-ρ b )
[0056] Where C d Compensation to electric vehicle users for battery swap stations; ρ b The discount rate for replacing the battery of an electric vehicle depends on the amount of battery power S that the user receives. chg The difference between the battery and the full charge is S b,ρ , S b,ρ =1-S chg ; S′ b,ρ is the inflection point of the discount rate curve;
[0057] The user will eventually need to pay electricity and service fees based on the number of battery swaps, where the number of battery swaps is the difference in power between the two batteries before and after the swap, i.e.: ΔP b =S chg E0-P old
[0058] Where ΔP b is the number of battery swaps for electric vehicle user i; P old is the amount of electricity before the electric vehicle is replaced; therefore, after taking into account the compensation for partially charged batteries, the actual replacement cost for electric vehicle users can be obtained: C b =ΔP b [e 0,t +e bs,t ]-C d Where C b The actual battery replacement cost for electric vehicle users;
[0059] Fourth, only fully charged batteries are used for B2G services, and the SOC lower limit of the discharged battery is constrained. When the SOC of the discharged battery drops to S dis,min When , the battery stops discharging and the discharged battery is converted into a battery to be charged. The expression is,
[0060] S dis ≥S dis,min
[0061] Where S dis is the SOC of the discharged battery; S dis,min is the lower limit of SOC of the discharged battery;
[0062] The total number of batteries constraint includes:
[0063] Where Nb is the total number of batteries in the battery swap station;
[0064] The battery quantity constraints include:
[0065] Where, D is the number of rechargeable batteries in the battery swap station that meet the user's acceptable SOC constraint during the t+1 period; b,t+1 is the battery replacement demand of electric vehicle users in period t+1; ε is the battery replacement reserve coefficient, which should be greater than or equal to 1;
[0066] The charge and discharge battery quantity constraint includes:
[0067] Where Z b is the total number of charging / discharging machines in the battery swap station.
[0068] Furthermore, the discount rate r is the discount rate coefficient.
[0069] Furthermore, the user demand constraints include:
[0070] CPV k =max{CPV1,CPV2,...,CPV M}
[0071] D c,t =D c,0 +ΔD c,1 +ΔD c,2
[0072] D b,t =D b,0 +ΔD b,1 +ΔD b,2 +(n full +n cha,avl -D b,0 )
[0073] in,
[0074]
[0075]
[0076] V=ω t V t +ω c V c
[0077]
[0078] Where V is the comprehensive value function; V t and Vc are time value function and cost value function respectively; ω t and ω c are the time weight coefficient and the cost weight coefficient respectively, and ω t +ω c =1;
[0079] t ref C is the sum of the longest travel time and waiting time acceptable to the user; ref The maximum charging cost acceptable to the user; total For a certain sum of travel time and waiting time, that is, t total =T dri +W q ; C is a certain charging cost; α and β are the risk preference coefficients of the user in the case of gain and loss, respectively, where α>0 and β<1; λ is the loss aversion coefficient, and λ≥1; p is the objective probability of the event; W(p) + and W(p) - is the user's subjective perception probability; γ and δ are the risk-return attitude coefficient and risk-loss attitude coefficient, respectively; and The decision weight function for users when they are in the state of gain and loss;
[0080] CPV1, CPV2, ..., CPV M The cumulative prospect value of the first, second, ..., Mth charging and swapping schemes respectively; CPV k is the cumulative prospect value corresponding to the final charging and swapping solution;
[0081] χ 1,c and χ 1,b are the self-elasticity coefficients of the charging station and the battery swap station respectively; 2,c and χ 2,b is the cross elasticity coefficient between the charging station and the battery swap station; ΔD c,1 and ΔD b,1 The changes in demand for charging and swapping caused by the price difference between the fixed service fee model and the dynamic pricing model; D c,0 and D b,0 are the charging demand of charging stations and the battery swapping demand of battery swapping stations under the fixed service fee model; e c,0 and e b,0 is the electricity price of the charging and swapping station under the fixed service fee model; ΔD c,2 and ΔD b,2 These are the changes in demand for charging and battery swapping caused by the price difference of charging and battery swapping in integrated energy substations.
[0082] A system for optimizing the operation of an integrated energy substation, wherein the integrated energy substation is equipped with a plurality of batteries for replacing batteries in electric vehicles and for peak shaving of the power grid through B2G services, includes a model building module and a model solving module:
[0083] The model construction module is used to construct an integrated energy substation optimization operation model based on the basic model of the integrated energy substation, with the battery planning scheme and the charging and swapping service fee scheme as decision variables and the goal of maximizing the net profit of the integrated energy substation. The constraints of the integrated energy substation optimization operation model include electric vehicle power constraints, power balance constraints, electric vehicle queuing time constraints, remaining battery SOC constraints, net profit constraints, user demand constraints, and battery strategy constraints that take into account the dispatchability of electric vehicles and mobile energy storage characteristics;
[0084] The model solving module is used to solve the integrated energy substation optimization operation model to obtain the integrated energy substation optimization operation plan.
[0085] An electronic device comprises a memory and a processor, wherein the memory stores a computer program, and the processor is configured to call and run the computer program stored in the memory to execute any of the above methods.
[0086] A computer-readable storage medium stores a computer program, wherein the computer program implements the steps of any of the above methods when executed by a processor.
[0087] Compared with the prior art, the present invention has the following beneficial effects:
[0088] This paper proposes a method for optimizing the operation of an integrated energy substation. This method constructs an optimized operation model for an integrated energy substation, using battery planning and charging / swapping service fee plans as decision variables, with the goal of maximizing the net profit of the integrated energy substation. By solving the model, the battery planning and charging / swapping service fee plans are derived. This method maximizes the revenue of the integrated energy station by optimizing the battery planning within the substation.
[0089] The model constructed by the operating method of the present invention takes into account the battery strategy constraints of the dispatchability and mobile energy storage characteristics of electric vehicles, solves the problem of insufficient battery reserves for battery swapping, and realizes the reasonable scheduling of batteries in battery swap stations.
[0090] The model constructed by the operating method of the present invention adopts user demand constraints for coordinated pricing of charging and battery swapping, which solves the problem of uneven distribution of charging and battery swapping loads, resulting in insufficient battery reserves for battery swapping or low utilization of charging piles, and realizes the coordinated operation of charging and battery swapping stations. BRIEF DESCRIPTION OF THE DRAWINGS
[0091] Figure 1 Schematic diagram of the process of optimizing the operation of the integrated energy substation in the embodiment;
[0092] Figure 2 This is a structural diagram of a comprehensive energy substation;
[0093] Figure 3 Schematic diagram of wireless utilization rate change in the embodiment;
[0094] Figure 4 This is a schematic diagram of battery classification for battery swap stations;
[0095] Figure 5 This is a diagram showing the relationship between the SOC shortfall and the discount rate;
[0096] Figure 6 Schematic diagram of the locations of integrated energy substation A, charging stations B and C in the study area;
[0097] Figure 7 It is the time-of-use electricity price curve;
[0098] Figure 8 is the relationship curve between the self-elasticity coefficient and the time period;
[0099] Figure 9 The relationship curve between the cross elasticity coefficient and the time period
[0100] Figure 10 This is a curve diagram showing the relationship between charging and swapping demand and time period under the fixed service fee model.
[0101] Figure 11 A curve chart showing the relationship between dynamic pricing results and time periods
[0102] Figure 12 This is a curve diagram showing the relationship between charging and swapping demand and time period under the dynamic pricing model.
[0103] Figure 13 This is a curve diagram showing the relationship between the battery scheduling plan and the time period. DETAILED DESCRIPTION
[0104] Example 1:
[0105] The present invention provides an optimized operation method for a comprehensive energy substation, wherein the comprehensive energy substation is provided with a plurality of batteries for supplying electric vehicles with power and for performing grid peak regulation through B2G services, including:
[0106] Based on the basic model of the integrated energy substation, an integrated energy substation optimization operation model is constructed with the battery planning scheme as the decision variable and the goal of maximizing the net profit of the integrated energy substation. The constraints of the integrated energy substation optimization operation model include electric vehicle power constraints, power balance constraints, electric vehicle queuing time constraints, remaining battery SOC constraints, net profit constraints, user demand constraints, and battery strategy constraints considering the dispatchability and mobile energy storage characteristics of electric vehicles; the integrated energy substation optimization operation model is solved to obtain the integrated energy substation optimization operation plan.
[0107] Example 2:
[0108] This embodiment is further designed on the basis of the first embodiment in that the structure of the integrated energy substation in this embodiment is as follows: Figure 2 As shown, it includes a substation, photovoltaic power station, charging station, battery swap station, data center, and 5G base station. The electricity generated by the on-site photovoltaic power station is used to power the on-site loads, which primarily include the data center, 5G base station, charging station, and battery swap station. The substation is supplied by the mains. When the photovoltaic power generation is insufficient to supply the on-site loads, photovoltaic power is preferentially supplied to the data center and 5G base station, with the shortfall supplemented by the mains. For battery swap stations, due to their dual "source" and "load" characteristics, they can assist the system in "peak shaving" and valley filling, achieving energy conservation and consumption reduction. Therefore, while meeting user battery swap needs, fully charged idle batteries at the station can participate in peak-shaving auxiliary services through B2G (battery-to-grid) or power other on-site power stations during peak electricity price periods, thereby reducing the operating costs of the integrated energy substation.
[0109] The basic model of the integrated energy substation includes a photovoltaic power station model, a data center model, a 5G base station model, a charging station model, and a battery swap station model. Photovoltaic power generation is the process of converting light energy into electrical energy using solar radiation. The photovoltaic power station output model usually considers factors such as solar radiation intensity and temperature. The photovoltaic power station model is a photovoltaic power generation output model, which can be expressed as: P PV,t =η PV AG t (1-κ(T t -T ref ))
[0110] Where, P PV,t is the output power of the photovoltaic power station during period t; η PV is the photoelectric conversion efficiency of the photovoltaic module; A is the total area of the photovoltaic module; G t is the solar radiation intensity during period t; κ is the photovoltaic temperature coefficient; T t and T ref are the ambient temperature and reference temperature during period t respectively;
[0111] The core part of the data center is IT equipment, which mainly includes servers, storage and communication equipment that handle workloads. To ensure the smooth operation of IT equipment, the data center is also equipped with non-IT equipment such as air conditioning systems, lighting facilities, and UPS power supplies. The energy consumption of electrical equipment is directly related to the workload handled by the server. As the number of workloads processed increases, the power consumption of the server increases, the heat dissipated increases, the working density of the air conditioning system increases, and the overall energy consumption of the data center increases. Since the present invention only considers the scenario of normal operation of the integrated energy substation, and the UPS power supply is the equipment that supplies power to the data center after the mains power is cut off, during normal use, it only needs to be charged and discharged once every 3-6 months. Therefore, without considering the charging and discharging of the data center UPS. The data center model is the data center energy consumption model, which can be expressed as: P DC,t =L[γ IT +ΨL load,t ]
[0112] Where, P DC,t is the total energy consumption of the data center during period t; L is the number of servers in the data center; Ψ is the peak power of a single server P peak and idle power P idle The difference, that is: Ψ=P peak -P idle ; γ IT is the fixed value of energy consumption of a single server under no-load condition, γ IT =P idle +(PUE-1)P peak ; PUE is the ratio of total energy consumption of data center to energy consumption of IT equipment; L load,t is the average utilization of the data center server, δ t is the amount of IT load being processed by the data center during period t; μ IT The average speed at which the server can handle IT load;
[0113] The load of a 5G base station is mainly composed of communication equipment, transmission equipment, power supply equipment, air conditioning, monitoring equipment, and lighting equipment. The communication equipment mainly includes the active antenna unit (AAU) and the baseband unit (BBU). The energy consumption of the BBU is generally stable and has little to do with the number of users accessing the base station. The energy consumption of the AAU is closely related to the business volume of the base station. The greater the number of users accessing, the higher the energy consumption. According to the standard configuration of 1 BBU and 3 AAUs, the 5G base station model is the energy consumption model of the 5G base station, which can be expressed as: P 5G,t =P BBU +3P AAU,t +P else
[0114] Where, P 5G,t is the total energy consumption of the 5G base station in period t; P BBU 、P AAU,t 、P AC,t and P else are the BBU energy consumption, AAU energy consumption, air conditioning energy consumption and other energy consumption of the 5G base station in period t; P AAU,t =α0U t +β0,U t Wireless utilization is an important indicator reflecting the utilization of network resources. t ∈[0,1]; α0 and β0 are both constants; P else =P PTN +P SP +P MON , P PTN 、P SP and P MON They are the power of transmission equipment, switching power supply, and monitoring equipment, and the power of these devices is basically constant; the change of wireless utilization rate in a day is as follows Figure 3 As shown;
[0115] α0 and β0 can be obtained by a fitting method. The fitting process is illustrated below with an example. In this example, the power of the main device of a 5G base station at different wireless utilization rates is shown in Table 1 below.
[0116] Table 1 5G base station main equipment power at different wireless utilization rates
[0117]
[0118] According to the data in Table 1, the AAU energy consumption P AAU,t and wireless utilization U t Perform linear fitting, and the fitting results are as follows: P AAU,t =0.5013U t +0.6892
[0119] The charging station model includes the charging price model of the charging station, the charging cost model of the electric vehicle user, the operation and maintenance cost model of the charging station, the charging service fee constraint model and the electric vehicle off-station SOC constraint model; among them, the charging price of the charging station is composed of the basic electricity price and the service fee. The charging price model of the charging station is expressed as: c,t =e 0,t +e cs,t
[0120] Where, e c,t is the charging price of the charging station during period t; e 0,t is the time-of-use electricity price during period t; e cs,t is the service fee of the charging station during period t;
[0121] The charging cost of the electric vehicle user charging cost model is expressed as:
[0122] Where, is the charging cost of electric vehicle user i at the charging station; a and b are the starting and ending time periods of electric vehicle charging respectively; P0 is the charging power of the charging pile; is the charging time of electric vehicle i in period t;
[0123] The operation and maintenance cost model of the charging station is expressed as: C c =(α1+β1)P day
[0124] Where, P day is the daily operating capacity of the charging station, P day =T d P0N c ; C c is the daily operation and maintenance cost of the charging station; α1 is the labor cost ratio coefficient; β1 is the grid connection cost ratio coefficient; T d is the average operating time of the charging station in a day; N c is the number of charging piles in the charging station;
[0125] The charging service fee constraint model is: e cs,max ≤e cs ≤e cs,min
[0126] The SOC constraint model of electric vehicles leaving the station is: S c,e ≤S end ≤1
[0127] Where, e cs,max and e cs,min Respectively represent the upper and lower limits of charging service fees; S c,e The expected SOC of electric vehicle users; S end The SOC when the user leaves the charging station;
[0128] The battery swap station model includes a battery swap price model, a battery depreciation cost model, a battery swap service fee constraint model, and a battery swap SOC constraint model. The battery swap price at the battery swap station is similar to the charging price, and is also composed of electricity charges and service fees. The battery swap price model is used to describe the user's battery swap price per kilowatt-hour, expressed as: e b,t =e 0,t +e bs,t
[0129] Where, e b,t is the price per kilowatt-hour of electricity exchanged at the battery exchange station during period t; e bs,tis the service fee of the battery swap station during period t;
[0130] The battery depreciation cost model is used to describe the battery depreciation cost of the battery swap station, which is expressed as:
[0131] Where C bat is the depreciation cost of the battery in the battery swap station; τ is the depreciation coefficient of the battery in the battery swap station; is the number of batteries used for battery replacement within period t; P dis,t is the discharge power of the battery; E b is the capacity of the battery at the battery swap station;
[0132] The battery swap service fee constraint model is expressed as: e bs,max ≤e bs ≤e bs,min ; The battery swap SOC constraint model is expressed as: S chg,min ≤S chg ≤1; where e bs,max and e bs,min Respectively represent the upper and lower limits of the battery replacement service fee; S chg,min The lower limit of SOC of the battery replacement that is acceptable to electric vehicle users; S chg It is the SOC of the battery for battery replacement.
[0133] Example 3:
[0134] This embodiment is further designed on the basis of the second embodiment in that the objective function of the integrated energy substation optimization operation model in this embodiment is:
[0135] in,
[0136] Where M dis The revenue from the battery swap station's participation in peak-shaving auxiliary services and the electricity cost savings from the battery swap station's use of B2G to supply power to the station's loads when photovoltaic power is insufficient; The amount of electricity purchased from the power grid by the integrated energy substation during period t; is the number of discharged batteries in period t; is the number of batteries used for peak load regulation during period t; ω is the unit reward obtained by reducing peak load.
[0137] Example 4:
[0138] This embodiment is further designed based on the third embodiment in that the electric vehicle in this embodiment should ensure that its remaining power is sufficient to travel to the target charging station. The electric vehicle power constraint is: i ≤r i S i Where r i is the power consumption per unit mileage of electric vehicle i; Si The remaining power when charging demand is generated for electric vehicle i;
[0139] The power balance constraint is:
[0140] Where, P c 、P b are the power requirements of charging stations and battery swap stations respectively;
[0141] In order to avoid users queuing too long at charging and swapping stations, it is assumed that the maximum queuing time acceptable to electric vehicle users is T w,max , then the electric vehicle queue time constraint is: T w ≤T w,max Where, T w The waiting time for users at charging and swapping stations;
[0142] In order to extend the service life of the battery and take into account the possibility of emergency situations, the SOC of the electric vehicle is required to be no less than 20% when charging is required, and the remaining battery SOC constraint is: S start ≥20%
[0143] In order to ensure that the net profit of the integrated energy substation does not decrease, the price of the charging and swapping stations is dynamically adjusted to maximize the net profit of the integrated energy substation. The net profit constraint is: F ≥ F0; where F0 is the net profit of the integrated energy substation when the charging and swapping station prices are not dynamically priced.
[0144] Embodiment 5:
[0145] This embodiment is further designed on the basis of the fourth embodiment in that the battery strategy constraints considering the dispatchability and mobile energy storage characteristics of electric vehicles in this embodiment include battery state transfer constraints, battery scheduling constraints, total battery quantity constraints, battery swap quantity constraints and charge and discharge battery quantity constraints; for a battery with N b The battery integrated energy substation is divided into four categories according to the working status of the battery, namely, batteries to be charged, charging batteries, fully charged batteries and discharged batteries. Figure 4 As shown in the figure, these four types of batteries can be converted into each other. The uncharged battery is converted into a rechargeable battery after entering the charging state, and the rechargeable battery is converted into a fully charged battery after being fully charged. The fully charged battery can be converted into a discharged battery to participate in the B2G service of the battery swap station after meeting the battery swap demand within the time period.
[0146] The research object of this invention is the power battery. Its charging and discharging process can be approximately regarded as a constant power charging and discharging process. Based on this, the SOC change ΔSOC of a battery in unit time Δt can be calculated: Where P is the rated charge and discharge power of the battery at the battery swap station. Therefore, various types of batteries can be grouped according to their SOC ranges, that is, divided into K SOC levels. The grouping diagram is shown in Table 2.
[0147] Table 2 Battery grouping diagram
[0148] SOC level 1 …… k …… K SOC range (0,ΔSOC] …… ((k-1)ΔSOC,kΔSOC] …… ((K-1)ΔSOC,1]
[0149] Among them, the battery state transition constraint is
[0150] Where, are the number of batteries to be charged, charging batteries, fully charged batteries and discharged batteries in the t+1 period respectively; are the number of remaining batteries to be charged, charged batteries, fully charged batteries, and discharged batteries in time period t; are the number of charging batteries and discharging batteries at the kth SOC level in period t+1, respectively; is the number of batteries replaced during the t+1 period;
[0151] The main function of a battery swap station is to serve electric vehicle users who need battery swaps. Therefore, a battery swap station that can provide B2G services should not only meet the battery swap service requirements but also make profits through B2G services. A battery swap station can use a reasonable battery scheduling strategy to adjust the number of batteries used for battery swap services and B2G services to reduce the cost of the battery swap station. Assuming that all batteries in the battery swap station are of the same specification and the actual performance differences of each battery are not considered, battery scheduling constraints are set. The battery scheduling constraints include the following four items:
[0152] First, for batteries to be charged, follow the principle of charging low-charge batteries first and then high-charge batteries; for discharging batteries, only use fully charged batteries for discharge;
[0153] Second, for the battery replacement service, if the number of fully charged batteries in the t+1 period Greater than or equal to the battery replacement demand D b,t+1 , then reserve D b,t+1 batteries are used for battery replacement service, and the remaining batteries are used for B2G service; otherwise, D b,t+1 All batteries are reserved for battery replacement services. The insufficient number will be supplemented by batteries that meet the lower limit of SOC acceptable to electric vehicle users in descending order of SOC;
[0154] Third, the partial charge compensation mechanism. When the fully charged battery is insufficient, a partially charged battery will be used for battery replacement service. This is a loss for the user, so these users need to be compensated. The partial charge compensation cost of the battery swap station is calculated as follows: C d =e b,t (1-ρ b);where C d Compensation to electric vehicle users for battery swap stations; ρ b The discount rate for replacing the battery of an electric vehicle depends on the amount of battery power S that the user receives. chg The difference between the battery and the full charge is S b,ρ , the larger the shortfall, the smaller the discount rate, then S b,ρ =1-S chg ;S b ' ,ρ is the inflection point of the discount rate curve; the relationship between SOC deficit and discount rate is as follows Figure 5 shown.
[0155] The user will eventually need to pay electricity and service fees based on the number of battery swaps, where the number of battery swaps is the difference in power between the two batteries before and after the swap, i.e.: ΔP b =S chg E0-P old Where, ΔP b is the number of battery swaps for electric vehicle user i; P old is the amount of electricity before the electric vehicle is replaced; therefore, after taking into account the compensation for partially charged batteries, the actual replacement cost for electric vehicle users can be obtained: C b =ΔP b [e 0,t +e bs,t ]-C d Where, C b The actual battery replacement cost for electric vehicle users;
[0156] Fourth, for B2G services, since deep charge and discharge have a greater impact on battery life, the present invention only uses fully charged batteries for B2G services and constrains the lower limit of the SOC of the discharged battery. When the SOC of the discharged battery drops to S dis,min When the battery stops discharging, the discharged battery is converted into a battery to be charged, and the expression is S dis ≥S dis,min Where S dis is the SOC of the discharged battery; S dis,min is the lower limit of SOC of the discharged battery;
[0157] The total number of battery constraints include: Where N b is the total number of batteries in the battery swap station;
[0158] The restrictions on the number of swappable batteries include: Where, D is the number of rechargeable batteries in the battery swap station that meet the user's acceptable SOC constraint during the t+1 period; b,t+1is the battery replacement demand of electric vehicle users in period t+1; ε is the battery replacement reserve coefficient, which should be greater than or equal to 1;
[0159] Constraints on the number of charge and discharge batteries include: Where Z b is the total number of charging / discharging machines in the battery swap station;
[0160] In the actual model solving process, the number of charging and discharging batteries at the kth SOC level in the t+1 period can be calculated according to the battery strategy constraints. Then calculate the number of replacement batteries in the t+1 period In the next period, the strategy will be followed Dispatching is performed to obtain the sum of the peak load regulation income of the battery swap station and the electricity cost saved by discharging the battery in the station M dis .
[0161] Example 6:
[0162] This embodiment is further designed based on the fifth embodiment in that the Richards model is used to determine the discount rate ρ b Size, discount rate r is the discount rate coefficient.
[0163] Embodiment seven:
[0164] This embodiment is further designed based on the fourth embodiment in that the user demand constraints in this embodiment include:
[0165] CPV k =max{CPV1,CPV2,...,CPV M}
[0166] D c,t =D c,0 +ΔD c,1 +ΔD c,2
[0167] D b,t =D b,0 +ΔD b,1 +ΔD b,2 +(n full +n cha,avl -D b,0 )
[0168] in,
[0169]
[0170]
[0171] V=ω t Vt +ω c V c
[0172]
[0173] Where V is the comprehensive value function; V t and V c are time value function and cost value function respectively; ω t and ω c are the time weight coefficient and the cost weight coefficient respectively, and ω t +ω c =1; t ref C is the sum of the longest travel time and waiting time acceptable to the user; ref The maximum charging cost acceptable to the user; total For a certain sum of travel time and waiting time, that is, t total =T dri +W q ; C is a certain charging cost; α and β are the risk preference coefficients of the user in the case of gain and loss, respectively, where α>0 and β<1; λ is the loss aversion coefficient, and λ≥1; p is the objective probability of the event; W(p) + and W(p) - is the user's subjective perception probability; γ and δ are the risk-return attitude coefficient and risk-loss attitude coefficient, respectively; and is the decision weight function when the user is in the state of gain and loss; CPV1, CPV2, ..., CPV M The cumulative prospect value of the first, second, ..., Mth charging and swapping schemes respectively; CPV k is the cumulative prospect value corresponding to the final charging and swapping solution; 1,c and χ 1,b are the self-elasticity coefficients of the charging station and the battery swap station respectively; 2,c and χ 2,b is the cross elasticity coefficient between the charging station and the battery swap station; ΔD c,1 and ΔD b,1 The changes in demand for charging and swapping caused by the price difference between the fixed service fee model and the dynamic pricing model; D c,0 and D b,0 are the charging demand of charging stations and the battery swapping demand of battery swapping stations under the fixed service fee model; e c,0 and e b,0 is the electricity price of the charging and swapping station under the fixed service fee model; ΔD c,2 and ΔD b,2 These are the changes in demand for charging and battery swapping caused by the price difference of charging and battery swapping in integrated energy substations.
[0174] Embodiment 8:
[0175] The present invention provides an integrated energy substation optimization operation system, in which a plurality of batteries for electric vehicle battery replacement and grid peak regulation through B2G services are provided in the integrated energy substation, including a model construction module and a model solving module: the model construction module is used to construct an integrated energy substation optimization operation model based on a basic model of the integrated energy substation, with a battery planning scheme as a decision variable and with the goal of maximizing the net profit of the integrated energy substation, wherein the constraints of the integrated energy substation optimization operation model include electric vehicle power constraints, power balance constraints, electric vehicle queuing time constraints, remaining battery SOC constraints, net profit constraints, user demand constraints, and battery strategy constraints considering the dispatchability and mobile energy storage characteristics of electric vehicles; the model solving module is used to solve the integrated energy substation optimization operation model to obtain an integrated energy substation optimization operation plan.
[0176] Embodiment 9:
[0177] An electronic device of the present invention includes a memory and a processor. The memory stores a computer program. The processor is used to call and run the computer program stored in the memory to execute the method described in any of the above embodiments.
[0178] A computer-readable storage medium of the present invention stores a computer program, and when the computer program is executed by a processor, the steps of the method described in any of the above embodiments are implemented.
[0179] Application examples:
[0180] This example simulates the implementation of the optimization operation method of the present invention on a certain integrated energy substation. Figure 6 As shown in the figure, the integrated energy substation is located in the city center. The marked areas in the figure are the locations of integrated energy substation A, charging stations B, and charging stations C. The integrated energy substation includes charging station A and a battery swap station. Charging stations A, B, and C have 8, 10, and 10 charging piles, respectively, with a charging power of 120kW each. The number of electric vehicles is set to 800, of which 60% are charging electric vehicles and the remaining 40% are charging and swapping electric vehicles. It is assumed that the battery capacity of all electric vehicle users is 100kWh.
[0181] In this example, a basic model of the integrated energy substation is constructed, and then an optimized operation model of the integrated energy substation is constructed. The optimized operation model of the integrated energy substation is then solved to obtain an optimized operation plan for the integrated energy substation. The specific implementation steps are as follows:
[0182] First, the load conditions of photovoltaic power stations, data centers, and 5G base stations are calculated respectively according to their models, and the remaining electricity available after photovoltaics power the data centers and 5G base stations is calculated.
[0183] Then, the charging and swapping costs are calculated based on each user's charging needs, and the charging and swapping decision results for each electric vehicle user are obtained by applying user demand constraints. Based on the decision results, the charging and swapping demand of each charging and swapping station under a fixed service fee and the initial net profit value of the integrated energy substation are calculated.
[0184] Finally, based on the demand function, the electricity price of the charging and swapping station is optimized and solved with the objective of maximizing the net profit of the integrated energy substation. The solved electricity price and the net profit of the integrated energy substation are obtained, and the effectiveness of the integrated energy substation optimization operation strategy proposed in this paper based on dynamic guidance of charging and swapping is verified.
[0185] In this example, the charging and swapping are dynamically priced based on the time-of-use electricity price. The time-of-use electricity price and price elasticity coefficient are as follows: Figure 7-Figure 9 As shown in the figure, before piloting, integrated energy substation A and charging stations B and C all use a fixed service fee model. The charging service fee is 0.54 yuan / kWh, and the battery swapping service fee is 0.52 yuan / kWh. Assume that the battery swapping station is large, equipped with 100 swappable batteries and 60 chargers with a rated charge and discharge power of 25kW each. The initial number of fully charged batteries is 70. The peak load periods are 10-12 and 18-20. The remaining parameters involved in this example are shown in Table 3.
[0186] Table 3 Parameter settings
[0187]
[0188]
[0189] The following is an analysis of the demand for charging and swapping based on a fixed service fee model:
[0190] Based on the time-of-use electricity price, this example first simulates the demand for charging and swapping under the fixed service fee model. The results are as follows: Figure 10 As shown in the figure, since electric vehicles usually charge and swap at public charging and swapping stations while traveling, the demand for charging and swapping shows the characteristics of double peaks in the morning and evening.
[0191] For Charging Station A within the integrated energy substation, the figure shows that during periods 8 and 19, when charging demand peaked, Charging Stations B and C experienced much higher charging demand than Charging Station A. This is because Charging Station A and the battery swap station are located in the same geographic location, and the time and distance required for users to travel from their departure point to both stations are the same. Furthermore, battery swapping takes much less time than charging, and the price of battery swapping is lower than charging. Therefore, the battery swap station attracted most of Charging Station A's electric vehicle users, resulting in a sharp increase in battery swapping demand while the charging station remained empty. However, this phenomenon can lead to high battery swapping demand for several consecutive periods during peak demand periods at the battery swap station, resulting in a shortage of available battery swap batteries at the station. This ultimately increases waiting times for some users, reducing the service efficiency of the battery swap station and worsening the user experience.
[0192] The following is an analysis of the dynamic pricing results:
[0193] Figure 11 、 Figure 12 They are the dynamic pricing results of the charging and swapping stations in the integrated energy substation and the charging and swapping demand under this mode. Figure 11 It can be seen that the charging and swapping prices during the 1-7 periods are basically higher than those of charging stations B and C. This is because the photovoltaic power station has no power output at night, and the loads in the station are all supplied by the city power. At this time, if the electricity price is lowered to attract electric vehicles to come for charging and swapping, the operating costs of the integrated energy substation will increase to a certain extent. Therefore, the charging and swapping electricity price during this period is basically higher than that of charging stations B and C.
[0194] The 8-10 period is the first peak period for charging and battery swapping. In order to guide users to the integrated energy station for charging and battery swapping, the electricity price during this period will be lower than the electricity price under the fixed service fee model. At the same time, a large number of batteries in the battery swap station have been charged at night during this period, and the number of fully charged batteries is relatively high. However, multiple consecutive peak periods of battery swapping may cause insufficient reserves of swappable batteries during a certain period. Therefore, the electricity price of the battery swap station at this time is slightly higher than that of the charging station, so as to transfer part of the load to the charging station in the integrated energy station, balancing the charging and battery swapping load while reducing the pressure of battery swapping. Taking period 8 as an example, before dynamic pricing, the charging demand was 0 and the battery swapping demand was 39 batteries. After dynamic pricing, the charging demand increased to 284.26kW and the battery swapping demand dropped to 35 batteries, realizing the transfer of part of the battery swapping demand. The period from 17 to 19 is the second peak period for charging and battery swapping. At this time, some batteries from the previous peak period have been charged, but there is still pressure to meet all battery swapping demands under the fixed service fee model. Therefore, the battery swapping price during this period is higher than the charging price, thereby reducing users' demand for battery swapping and transferring this part of the load to charging stations.
[0195] Under the dynamic pricing model, the changing trend of charging and battery swapping demand in the integrated energy station is roughly the same as that in the fixed service fee model, but part of the battery swapping demand during peak hours is transferred to the charging station, causing the charging demand to increase by 25.26% and the battery swapping demand to decrease by 27.38%, balancing the load within the station, reducing the pressure of battery swapping, and improving the utilization rate of charging piles.
[0196] Figure 13 This figure shows the battery scheduling of the battery swap station under the dynamic pricing model. As can be seen from the figure, the number of fully charged batteries in periods 1-4 increased significantly. This is because periods 1-4 are all in the off-peak electricity price period, and the battery charging cost is low, so a large number of batteries are charged during this time period. Starting from period 8, the integrated energy substation enters the first peak period of charging and swapping demand. At this time, the number of fully charged batteries drops significantly. To ensure the subsequent battery swapping demand, a large number of batteries to be charged begin to charge during this period. At the same time, starting from period 9, the battery swap station uses some batteries for peak load regulation while ensuring the user's battery swapping demand. When the peak load regulation period ends, some batteries are still not fully discharged. At this time, the discharged batteries can supply power to the load in the station, saving some electricity costs. During the second peak period of charging and swapping demand, the number of fully charged batteries decreases significantly, and the batteries to be charged begin to accumulate gradually. At this time, to ensure that there is still a certain number of batteries available for swapping in the future, the battery swap station raises the battery swap price and transfers the load to the charging station.
[0197] Table 4 Comparison before and after optimization
[0198]
[0199] Table 4 compares the revenue and expenditure of the integrated energy station before and after optimizing charging and swapping prices. As can be seen, net profit increased by 10.37% after optimization. Furthermore, before optimization, fully charged batteries available for peak load shaving were used for swapping services during the two peak swapping periods, leaving virtually no fully charged batteries available for peak load shaving, resulting in lower peak load shaving revenue. The dynamic pricing model shifts some of the load to the charging station. While this reduces swapping revenue, the remaining fully charged batteries can be used for peak load shaving and in-station power supply. This not only increases peak load shaving revenue by 606.43 yuan, but also saves the integrated energy station an additional 1,033.25 yuan in electricity costs.
[0200] In summary, this paper considers the impact of charging and swapping prices on the revenue of integrated energy stations and addresses the difficulty of collaborative pricing for charging and swapping. It proposes an optimized operation method and system for integrated energy substations and optimizes them using a particle swarm algorithm and Yalmip in MATLAB. The following conclusions can be drawn from simulation analysis:
[0201] The present invention takes into account the price difference between in-station and out-station prices, as well as the price difference between charging and swapping within the station, adopts user demand constraints for collaborative pricing of charging and swapping, and implements a dynamic pricing strategy for charging and swapping. Compared with the fixed service fee model, the integrated energy station saved an additional 1,033.25 yuan in electricity expenses, increased peak-shaving revenue by 606.43 yuan, and increased operating net profit by 10.37%, proving the effectiveness of the strategy proposed by the present invention. At the same time, the dynamic pricing strategy for charging and swapping takes into account the collaborative pricing between charging and swapping facilities within the integrated energy station, and can dynamically adjust the charging and swapping demand during the peak charging and swapping period, causing charging demand to increase by 25.26% and swapping demand to decrease by 27.38%. While improving the utilization rate of charging piles, it also reduces the swapping pressure on the swapping station.
[0202] The present invention also takes into account the battery reserve and peak-shaving needs of battery swapping, and adopts battery strategy constraints that take into account the dispatchability and mobile energy storage characteristics of electric vehicles to form a battery scheduling strategy for battery swap stations. On the basis of ensuring the user's battery swap needs, it can dynamically adjust the charging and discharging power according to the battery status and quantity of the battery swap station, and achieve peak shaving and valley filling during peak load periods.
[0203] Although the present invention has been disclosed above in terms of preferred embodiments, they are not intended to limit the present invention. Anyone skilled in the art can make various changes or modifications without departing from the spirit and scope of the present invention. Therefore, the scope of protection of the present invention should be based on the scope of protection defined by the claims of this application.
Claims
1. A method for optimizing the operation of a comprehensive energy substation, wherein the comprehensive energy substation is provided with a plurality of batteries for replacing electric vehicles and for peak load regulation of the power grid through B2G services, characterized in that: include: Based on the basic model of the integrated energy substation, an integrated energy substation optimization operation model is constructed with the battery planning scheme and the charging and swapping service fee scheme as decision variables and the goal of maximizing the net profit of the integrated energy substation. The constraints of the integrated energy substation optimization operation model include electric vehicle power constraints, power balance constraints, electric vehicle queuing time constraints, remaining battery SOC constraints, net profit constraints, user demand constraints, and battery strategy constraints considering the dispatchability of electric vehicles and mobile energy storage characteristics; The optimized operation model of the integrated energy substation is solved to obtain an optimized operation plan of the integrated energy substation.
2. The integrated energy substation optimization operation method according to claim 1 is characterized in that: The basic model of the integrated energy substation includes a photovoltaic power station model, a data center model, a 5G base station model, a charging station model and a battery swap station model; wherein, The photovoltaic power station model is expressed as: P PV,t =η PV AG t (1-κ(T t -T ref )) Where P PV,t is the output power of the photovoltaic power station during period t; η PV is the photoelectric conversion efficiency of the photovoltaic module; A is the total area of the photovoltaic module; G t is the solar radiation intensity during period t; κ is the photovoltaic temperature coefficient; T t and T ref are the ambient temperature and reference temperature during period t respectively; The data center model is expressed as: P DC,t =L[γ IT +ΨL load,t ] Where P DC,t is the total energy consumption of the data center during period t; L is the number of servers in the data center; Ψ is the peak power of a single server P peak and idle power P idle The difference is: Ψ=P peak -P idle ; γ IT is the fixed value of energy consumption of a single server under no-load condition, γ IT =P idle +(PUE-1)P peak ; PUE is the ratio of total energy consumption of data center to energy consumption of IT equipment; L load,t is the average utilization of the data center servers, δ t is the amount of IT load being processed by the data center during period t; μ IT The average speed at which the server handles IT load; The 5G base station model is expressed as: P 5G,t =P BBU +3P AAU,t +P else Where P 5G,t is the total energy consumption of the 5G base station in period t; P BBU , P AAU,t , P AC,t and P else are the BBU energy consumption, AAU energy consumption, air conditioning energy consumption and other energy consumption of the 5G base station in period t; P AAU,t =α0U t +β0,U t The wireless utilization rate U t ∈[0,1]; α0 and β0 are both constants; P else =P PTN +P SP +P MON , P PTN , P SP and P MON They are the power of transmission equipment, switching power supply, and monitoring equipment respectively; The charging station model includes a charging price model for the charging station, a charging cost model for electric vehicle users, a charging station operation and maintenance cost model, a charging service fee constraint model, and an electric vehicle off-station SOC constraint model; the charging price model for the charging station is expressed as: And c,t =and 0,t +e cs,t In the formula, e c,t is the charging price of the charging station during period t; e 0,t is the time-of-use electricity price during period t; e cs,t is the service fee of the charging station during period t; The charging cost of the electric vehicle user charging cost model is expressed as: In the formula, is the charging cost of electric vehicle user i at the charging station; a and b are the starting time and ending time of electric vehicle charging respectively; P0 is the charging power of the charging pile; is the charging time of electric vehicle i in period t; The charging station operation and maintenance cost model is expressed as: C c =(α1+β1)P day Where P day is the operating capacity of the charging station for one day, P day =T d P0N c ; C c is the daily operation and maintenance cost of the charging station; α1 is the labor cost ratio coefficient; β1 is the grid connection cost ratio coefficient; T d is the average operation time of the charging station in a day; N c is the number of charging piles in the charging station; The charging service fee constraint model is: and cs,max ≤e cs ≤e cs,min The electric vehicle leaving station SOC constraint model is: S c,e ≤S end ≤1 In the formula, e cs,max and e cs,min Respectively represent the upper and lower limits of the charging service fee; S c,e The expected SOC of electric vehicle users; S end The SOC when the user leaves the charging station; The battery swap station model includes a battery swap price model, a battery depreciation cost model, a battery swap service fee constraint model, and a battery swap SOC constraint model; wherein the battery swap price model is expressed as: And b,t =and 0,t +e bs,t In the formula, e b,t is the price per kWh of electricity exchanged at the exchange station during period t; e bs,t is the service fee of the battery swap station during time period t; The battery depreciation cost model is expressed as: In the formula, C bat is the depreciation cost of the battery in the battery swap station; τ is the depreciation coefficient of the battery in the battery swap station; is the number of batteries used for battery replacement within period t; P dis,t is the discharge power of the battery; E b is the capacity of the battery in the battery swap station; The battery swap service fee constraint model is expressed as: and bs,max ≤e bs ≤e bs,min The battery swap SOC constraint model is expressed as: S chg,min ≤S chg ≤1 In the formula, e bs,max and e bs,min Respectively represent the upper and lower limits of the battery replacement service fee; S chg,min The lower limit of SOC of the battery replacement that is acceptable to electric vehicle users; S chg It is the SOC of the battery replacement.
3. The integrated energy substation optimization operation method according to claim 2 is characterized in that: The objective function of the comprehensive energy substation optimization operation model is: in, Where M dis The revenue from the battery swap station’s participation in peak load regulation auxiliary services and the electricity cost saved by the battery swap station when the photovoltaic power supply is insufficient to supply power to the load in the station through B2G; The amount of electricity purchased by the integrated energy substation from the power grid during period t; is the number of discharged batteries in period t; is the number of batteries used for peak load regulation during period t; ω is the unit reward obtained by reducing peak load.
4. The integrated energy substation optimization operation method according to claim 3 is characterized in that: The electric vehicle power constraint is: l i ≤r i S i In the formula, r i is the power consumption per unit mileage of electric vehicle i; S i The remaining power when charging demand is generated for electric vehicle i; The power balance constraint is: Where P c , P b are the power requirements of charging stations and battery swap stations respectively; The electric vehicle queuing time constraint is: T w ≤T w,max Where, T w The waiting time for users at charging and swapping stations; The remaining battery SOC constraint is: S start ≥20% The net profit constraint is: F≥F0 Where F0 is the net profit of the integrated energy substation when the charging and swapping station prices are not dynamically priced.
5. The integrated energy substation optimization operation method according to claim 4 is characterized in that: The battery strategy constraints that take into account the dispatchability and mobile energy storage characteristics of electric vehicles include battery state transfer constraints, battery scheduling constraints, total battery quantity constraints, battery swap quantity constraints, and charge and discharge battery quantity constraints; Among them, the battery state transfer constraint is In the formula, are the number of batteries to be charged, charged batteries, fully charged batteries and discharged batteries in the time period t+1 respectively; are the number of batteries to be charged, charged batteries, fully charged batteries and discharged batteries remaining in time period t respectively; are the number of charging batteries and discharging batteries at the kth SOC level in period t+1, respectively; is the number of batteries replaced during the t+1 period; The battery scheduling constraints include the following four items: First, for batteries to be charged, follow the principle of charging low-charge batteries first and then high-charge batteries; for batteries to be discharged, only use fully charged batteries for discharge; Second, for the battery replacement service, if the number of fully charged batteries in the t+1 period Greater than or equal to the battery replacement demand D b,t+1 , then reserve D b,t+1 batteries are used for battery replacement services, and the remaining batteries are used for B2G services; otherwise, D b,t+1 All batteries are reserved for battery replacement services, and the insufficient number will be supplemented by batteries that meet the lower limit of SOC acceptable to electric vehicle users in descending order of SOC; Third, the compensation mechanism for partially charged batteries. The compensation cost of partially charged batteries at the battery swap station is calculated as follows: d =e b,t (1-ρ b ) where C d Compensation for electric vehicle users for battery swap stations; ρ b The discount rate for replacing the battery of an electric vehicle depends on the amount of battery power S that the user receives. chg The shortfall between the fully charged battery and b,ρ , S b,ρ =1-S chg ; S′ b,ρ is the inflection point of the discount rate curve; The user will eventually need to pay electricity and service fees based on the number of swapped batteries, where the number of swapped batteries is the difference in power between the two batteries before and after the swap, i.e.: ΔP b =S chg E0-P old In the formula, ΔP b P is the number of battery replacements of electric vehicle user i; old is the amount of electricity before the electric vehicle is replaced; therefore, after taking into account the compensation for partially charged batteries, the actual replacement cost for electric vehicle users can be obtained: C b =ΔP b [e 0,t +e bs,t ]-C d In the formula, C b The actual battery replacement cost for electric vehicle users; Fourth, only fully charged batteries are used for B2G services, and the SOC lower limit of the discharged battery is constrained. When the SOC of the discharged battery drops to S dis,min When , the battery stops discharging, and the discharged battery is converted into a battery to be charged. The expression is, S dis ≥S dis,min In the formula, S dis is the SOC of the discharged battery; S dis,min is the SOC lower limit of the discharged battery; The total number of batteries constraint includes: Where N b is the total number of batteries in the battery swap station; The battery quantity constraints include: In the formula, D is the number of rechargeable batteries in the battery swap station that meet the user's acceptable SOC constraint during period t+1; b,t+1 is the battery replacement demand of electric vehicle users in period t+1; ε is the battery replacement reserve coefficient, which should be greater than or equal to 1; The charge and discharge battery quantity constraint includes: In the formula, Z b is the total number of charging / discharging machines in the battery swap station.
6. The integrated energy substation optimization operation method according to claim 5 is characterized in that: The discount rate r is the discount rate coefficient.
7. The integrated energy substation optimization operation method according to claim 4 is characterized in that: The user demand constraints include: CPV k =max{CPV1,CPV2,...,CPV M } D c,t =D c,0 +ΔD c,1 +ΔD c,2 D b,t =D b,0 +ΔD b,1 +ΔD b,2 +(n full +n cha,avl -D b,0 ) in, V=ω t V t +ω c V c Where V is the comprehensive value function; V t and V c are time value function and cost value function respectively; ω t and ω c are the time weight coefficient and the cost weight coefficient respectively, and ω t +ω c =1; t ref is the sum of the longest travel time and waiting time acceptable to the user; C ref The maximum charging cost acceptable to the user; t total For a certain sum of travel time and waiting time, that is, t total =T dri +W q ; C is a certain charging cost; α and β are the risk preference coefficients of the user under the conditions of gain and loss, where α>0, β<1; λ is the loss aversion coefficient, and λ≥1; p is the objective probability of the event; W(p) + and W(p) - is the user's subjective perceived probability; γ and δ are the risk-return attitude coefficient and risk-loss attitude coefficient respectively; and It is the decision weight function when the user is in the state of gain and loss; CPV1, CPV2, ..., CPV M The cumulative prospect values of the first, second, ..., Mth charging and swapping solutions respectively; CPV k is the cumulative prospect value corresponding to the final charging and swapping solution; χ 1,c and χ 1,b are the self-elasticity coefficients of the charging station and the battery swap station respectively; 2,c and χ 2,b is the cross elasticity coefficient between the charging station and the battery swap station; ΔD c,1 and ΔD b,1 The changes in demand for charging and swapping caused by the price difference between the fixed service fee model and the dynamic pricing model; D c,0 and D b,0 are the charging demand of charging stations and the battery swapping demand of battery swapping stations under the fixed service fee model; e c,0 and e b,0 is the electricity price of the charging and swapping station under the fixed service fee model; ΔD c,2 and ΔD b,2 They are the changes in demand for charging and battery swapping caused by the price difference of charging and battery swapping in integrated energy substations.
8. An optimized operation system for an integrated energy substation, wherein the integrated energy substation is provided with a plurality of batteries for replacing electric vehicles and for peak load regulation of the power grid through B2G services, characterized in that: Includes model building module and model solving module: The model building module is used to build an integrated energy substation optimization operation model based on the basic model of the integrated energy substation, with the battery planning scheme and the charging and swapping service fee scheme as decision variables and the goal of maximizing the net profit of the integrated energy substation. The constraints of the integrated energy substation optimization operation model include electric vehicle power constraints, power balance constraints, electric vehicle queuing time constraints, remaining battery SOC constraints, net profit constraints, user demand constraints, and battery strategy constraints considering the dispatchability of electric vehicles and mobile energy storage characteristics; The model solving module is used to solve the integrated energy substation optimization operation model to obtain the integrated energy substation optimization operation plan.
9. An electronic device, characterized in that: The electronic device comprises a memory and a processor, wherein the memory stores a computer program, and the processor is configured to call and run the computer program stored in the memory to execute the method according to any one of claims 1 to 7.
10. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of the method as claimed in any one of claims 1 to 7 are implemented.