Raw material continuous synthesis system and preparation method of tetrafluoroethane-beta-sultone

By setting up a diversion cylinder in the reactor to form a circulation channel, the static pressure difference is used to realize the circulating flow of liquid and gas raw materials, the low efficiency and safety of tetrafluoroethane-β-sulfonolide preparation are solved, and high efficiency and low energy are achieved The preparation effect of consumption.

CN118976434APending Publication Date: 2024-11-19JUHUA GROUP TECH CENT
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411071366.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-06
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

The existing preparation process of tetrafluoroethane-β-sulfonolide is low in efficiency, high energy consumption, and local overheating points and self-polymerization safety problems, making it difficult to meet the needs of high efficiency, low energy consumption and high safety coefficient.

Method used

A continuous raw material synthesis system is adopted to form a circulation channel in the reactor through a flow guide cylinder, and the static pressure difference is used to realize the circulating flow of liquid raw materials and gas raw materials, avoid external stirring, and improve the mixing reaction efficiency and heat transfer performance.

Benefits of technology

It improves the preparation efficiency of tetrafluoroethane-β-sulfonolide, reduces energy consumption, reduces local overheating spots and self-polymerization safety issues, and meets the preparation needs of high efficiency, low energy consumption and high safety coefficient.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118976434A_ABST
    Figure CN118976434A_ABST
Patent Text Reader

Abstract

The invention provides a raw material continuous synthesis system and a preparation method of tetrafluoroethane-beta-sultone, and the raw material continuous synthesis system comprises: a first feeding device; a second feeding device; the reaction device comprises a reaction kettle and a guide cylinder, the liquid inlet end of the reaction kettle is communicated with the liquid outlet end of the first feeding device, the guide cylinder is arranged in the reaction kettle, a first channel is formed in the guide cylinder, and a second channel is formed outside the guide cylinder; wherein the gas outlet end of the second feeding device extends into the reaction kettle and is opposite to one end of the first channel, so that the liquid raw material and the gas raw material in the reaction kettle circularly flow between the first channel and the second channel and react to generate a target product. According to the raw material continuous synthesis system and the tetrafluoroethane-beta-sultone preparation method disclosed by the invention, the preparation requirements of high efficiency, low energy consumption and high safety coefficient of a target product are met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the technical field of tetrafluoroethane-β-sultone preparation, and in particular to a raw material continuous synthesis system and a method for preparing tetrafluoroethane-β-sultone. Background Art

[0002] Tetrafluoroethane-β-sultone is a special fluorine-containing fine chemical. The tetrafluoroethane-β-sultone produced by the existing process is a mixture of a cyclic structure and a linear structure, in which the cyclic structure can be converted into a linear structure. Due to its special structure, it can react with many olefins, cycloalkanes, nucleophiles, etc. to prepare functional polymer materials and fine chemicals, such as PSVE, fluorinated surfactants and fluorinated oils.

[0003] Tetrafluoroethane-β-sultone is obtained by mixing sulfur trioxide and tetrafluoroethylene, but the current mixing process is mostly intermittent, resulting in low preparation efficiency of tetrafluoroethane-β-sultone. At the same time, the mixing of sulfur trioxide and tetrafluoroethylene by stirring not only has high energy consumption, but also poor overall heat transfer, which is prone to safety problems such as local hot spots and tetrafluoroethylene self-polymerization, making it difficult to meet the preparation requirements of tetrafluoroethane-β-sultone with high efficiency, low energy consumption and high safety factor. Summary of the invention

[0004] The present disclosure aims to solve one of the technical problems in the related art at least to some extent.

[0005] To this end, the object of the present disclosure is to provide a raw material continuous synthesis system and a method for preparing tetrafluoroethane-β-sultone.

[0006] To achieve the above-mentioned purpose, the first aspect of the present disclosure provides a raw material continuous synthesis system, comprising: a first feeding device, the first feeding device is used to convey liquid raw materials; a second feeding device, the second feeding device is used to convey gaseous raw materials; a reaction device, the reaction device comprising: a reactor and a guide tube, the liquid inlet end of the reactor is connected to the liquid outlet end of the first feeding device, the guide tube is arranged in the reactor, and a first channel is formed inside the guide tube, and a second channel is formed outside the guide tube; wherein the gas outlet end of the second feeding device extends into the interior of the reactor and is arranged opposite to one end of the first channel, so that the liquid raw material and the gaseous raw material in the reactor circulate between the first channel and the second channel and react to generate a target product.

[0007] Optionally, the reaction device also includes: a gas distributor, which is arranged in the reactor, and the gas outlet end of the gas distributor is arranged opposite to one end of the first channel, and the gas outlet end of the second feeding device extends into the interior of the reactor and is connected to the gas inlet end of the gas distributor.

[0008] Optionally, the ratio between the diameter of the guide tube and the diameter of the reactor is in the range of 0.2-0.8.

[0009] Optionally, the first feeding device includes: a metering tank, in which the liquid raw material is arranged; a metering pump, the liquid inlet end of the metering pump is connected to the liquid outlet end of the metering tank; a first flow meter, the liquid inlet end of the first flow meter is connected to the liquid outlet end of the metering pump; a first cut-off valve, the liquid inlet end of the first cut-off valve is connected to the liquid outlet end of the first flow meter; a first check valve, the liquid inlet end of the first check valve is connected to the liquid outlet end of the first cut-off valve, and the liquid outlet end of the first check valve is connected to the liquid inlet end of the reactor.

[0010] Optionally, the second feeding device includes: a metering tank, in which the gas raw material is arranged; a second flow meter, the air inlet end of the second flow meter is connected to the air outlet end of the metering tank; a second cut-off valve, the air inlet end of the second cut-off valve is connected to the air outlet end of the second flow meter; a second check valve, the air inlet end of the second check valve is connected to the air outlet end of the second cut-off valve, and the air outlet end of the second check valve extends to the interior of the reactor and is arranged opposite to one end of the first channel.

[0011] Optionally, the reaction device also includes: a back pressure valve, the liquid inlet end of the back pressure valve is connected to the liquid outlet end of the reactor; a stop valve, the liquid inlet end of the stop valve is connected to the liquid outlet end of the back pressure valve, and the liquid outlet end of the stop valve is used to discharge the target product.

[0012] The second aspect of the present disclosure provides a method for preparing tetrafluoroethane-β-sultone. The method is based on the raw material continuous synthesis system provided in the first aspect of the present disclosure, and comprises: conveying sulfur trioxide from a first feeding device of the raw material continuous synthesis system to a reactor of the raw material continuous synthesis system, and conveying tetrafluoroethylene from a second feeding device of the raw material continuous synthesis system to a first channel of the raw material continuous synthesis system; controlling the reaction temperature of the reactor according to a preset temperature, controlling the reaction pressure of the reactor according to a preset pressure, and controlling the reaction liquid level of the reactor according to a first preset liquid level; when the reaction time of the reactor reaches the preset time, discharging the target product in the reactor to obtain the tetrafluoroethane-β-sultone.

[0013] Optionally, the preset temperature ranges from 30°C to 50°C; and / or the preset pressure ranges from 0.05MPa to 0.2MPa; and / or the first preset liquid level ranges from 70% to 95% of the total liquid level of the reactor; and / or the preset time ranges from 1h to 5h.

[0014] Optionally, the preparation method further includes: before conveying the sulfur trioxide to the reactor and conveying the tetrafluoroethylene to the first channel, adding a second preset liquid level of the tetrafluoroethane-β-sultone to the reactor; wherein the second preset liquid level is lower than the first preset liquid level.

[0015] Optionally, the preparation method further comprises: after obtaining the tetrafluoroethane-β-sultone, continuously distilling and separating the tetrafluoroethane-β-sultone until the purity of the tetrafluoroethane-β-sultone reaches a preset purity.

[0016] The technical solution provided by the present disclosure may have the following beneficial effects:

[0017] The first feeding device can continuously deliver liquid raw materials into the reactor, and the second feeding device can continuously deliver gaseous raw materials into the reactor, so that the liquid raw materials and the gaseous raw materials can continuously circulate between the first channel and the second channel, thereby realizing a sufficient continuous mixing reaction, thereby realizing continuous preparation of the target product, effectively improving the preparation efficiency of the target product, and the static pressure difference between the first channel and the second channel is used to realize the circulation of liquid raw materials and gaseous raw materials, thereby avoiding the input of external power such as stirring, thereby effectively reducing the overall energy consumption, and at the same time, the method of realizing the mixing reaction through the circulating flow has better uniformity, thereby improving the overall heat transfer performance, thereby greatly reducing local hot spots and safety issues such as tetrafluoroethylene self-polymerization, thereby meeting the preparation requirements of the target product with high efficiency, low energy consumption and high safety factor.

[0018] Additional aspects and advantages of the present disclosure will be given in part in the following description and in part will be obvious from the following description or learned through practice of the present disclosure. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] The above and / or additional aspects and advantages of the present disclosure will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:

[0020] Figure 1 is a schematic structural diagram of a raw material continuous synthesis system proposed in one embodiment of the present disclosure;

[0021] Figure 2 This is a schematic diagram of the liquid path of the first feeding device in the raw material continuous synthesis system proposed in one embodiment of the present disclosure;

[0022] Figure 3 Schematic diagram of the gas path of the second feeding device in the raw material continuous synthesis system proposed in one embodiment of the present disclosure;

[0023] Figure 4 It is a schematic flow chart of a method for preparing tetrafluoroethane-β-sultone proposed in one embodiment of the present disclosure;

[0024] As shown in the figure: 1. first feeding device, 11. metering tank, 12. metering pump, 13. first flow meter, 14. first cut-off valve, 15. first check valve;

[0025] 2. a second feeding device, 21. a metering tank, 22. a second flow meter, 23. a second shut-off valve, 24. a second check valve;

[0026] 3. reaction device, 31. reaction kettle, 32. flow guide tube, 33. gas distributor, 34. first channel, 35. second channel;

[0027] 4. Back pressure valve, 5. Stop valve. DETAILED DESCRIPTION

[0028] Embodiments of the present disclosure are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present disclosure, and are not to be construed as limitations of the present disclosure. On the contrary, the embodiments of the present disclosure include all changes, modifications, and equivalents that fall within the spirit and connotation of the appended claims.

[0029] like Figure 1 As shown, the embodiment of the present disclosure proposes a system for continuous synthesis of raw materials, including: a first feeding device 1, a second feeding device 2 and a reaction device 3, the first feeding device 1 is used to transport liquid raw materials, the second feeding device 2 is used to transport gaseous raw materials, and the reaction device 3 includes: a reactor 31 and a guide tube 32, the liquid inlet end of the reactor 31 is connected to the liquid outlet end of the first feeding device 1, the guide tube 32 is arranged in the reactor 31, and the interior of the guide tube 32 forms a first channel 34, and the exterior of the guide tube 32 forms a second channel 35. Among them, the gas outlet end of the second feeding device 2 extends to the interior of the reactor 31 and is arranged opposite to one end of the first channel 34, so that the liquid raw materials and gaseous raw materials in the reactor 31 circulate between the first channel 34 and the second channel 35 and react to generate the target product.

[0030] It can be understood that since the guide tube 32 is arranged in the reactor 31, and the first channel 34 is formed inside the guide tube 32, and the second channel 35 is formed outside the guide tube 32, the first channel 34 and the second channel 35 cooperate to provide a circulation channel for the mixing of liquid raw materials and gaseous raw materials, and since the liquid outlet end of the first feeding device 1 is connected to the liquid inlet end of the reactor 31, and the gas outlet end of the second feeding device 2 extends to the interior of the reactor 31 and is arranged opposite to one end of the first channel 34, the first channel 34 and the second channel 35 have different gas contents under the action of the gas raw material, thereby generating a static pressure difference, and then under the action of the static pressure difference, the liquid raw material and the gas raw material in the reactor 31 are continuously circulated between the first channel 34 and the second channel 35, so as to fully mix and react to generate the target product.

[0031] Among them, the first feeding device 1 can continuously convey liquid raw materials into the reactor 31, and the second feeding device 2 can continuously convey gaseous raw materials into the reactor 31, so that the liquid raw materials and the gaseous raw materials are continuously circulated between the first channel 34 and the second channel 35, thereby realizing a sufficient continuous mixing reaction, thereby realizing continuous preparation of the target product, effectively improving the preparation efficiency of the target product, and the static pressure difference between the first channel 34 and the second channel 35 is used to realize the circulation of liquid raw materials and gaseous raw materials, thereby avoiding the input of external power such as stirring, thereby effectively reducing the overall energy consumption, and at the same time, the method of realizing the mixing reaction through the circulating flow has better uniformity, thereby improving the overall heat transfer performance, thereby greatly reducing local hot spots and safety problems such as tetrafluoroethylene self-polymerization, thereby meeting the preparation requirements of the target product with high efficiency, low energy consumption and high safety factor.

[0032] It should be noted that the liquid raw material and the gaseous raw material are used for a mixed reaction to generate a target product, wherein the specific types of the liquid raw material, the gaseous raw material and the target product can be set according to actual needs, and there is no limitation on this. For example, the liquid raw material can be sulfur trioxide (SO3), and the gaseous raw material can be tetrafluoroethylene (C2F4). The target product generated by the mixed reaction of sulfur trioxide and tetrafluoroethylene is tetrafluoroethane beta-sultone (C2F4O3S). By using the raw material continuous synthesis system of this embodiment, a cyclic mixed reaction of sulfur trioxide and tetrafluoroethylene can be achieved, thereby meeting the preparation requirements of tetrafluoroethane beta-sultone with high efficiency, low energy consumption and high safety factor.

[0033] The first feeding device 1 is used to transport liquid raw materials. The specific type of the first feeding device 1 can be set according to actual needs and is not limited to this.

[0034] The second feeding device 2 is used to transport gas raw materials. The specific type of the second feeding device 2 can be set according to actual needs and is not limited to this.

[0035] The reaction device 3 is used for the mixed reaction of liquid raw materials and gas raw materials, wherein the guide tube 32 forms a first channel 34 and a second channel 35 in communication in the reactor 31. When the gas raw material enters the first channel 34, a static pressure difference is formed between the first channel 34 and the second channel 35, thereby realizing the circulation of the liquid raw material and the gas raw material between the first channel 34 and the second channel 35. The specific types of the reactor 31 and the guide tube 32 can be set according to actual needs and are not limited to this. For example, the reactor 31 is a cylindrical barrel structure, and the guide tube 32 is a cylindrical barrel structure, the axial direction of the reactor 31 and the axial direction of the guide tube 32 are respectively located in the vertical direction, and the reactor 31 and the guide tube 32 are coaxially arranged, thereby making the first channel 34 form a cylindrical channel, the second channel 35 form an annular channel, and the upper end of the first channel 34 and the upper end of the second channel 35 as well as the lower end of the first channel 34 and the lower end of the second channel 35 are connected, the liquid outlet end of the first feeding device 1 is connected to the bottom of the reactor 31, and the gas outlet end of the second feeding device 2 extends from the bottom of the reactor 31 to the lower end of the guide tube 32.

[0036] like Figure 1 As shown, in some embodiments, the reaction device 3 also includes: a gas distributor 33, the gas distributor 33 is arranged in the reaction kettle 31, and the gas outlet end of the gas distributor 33 is arranged opposite to one end of the first channel 34, and the gas outlet end of the second feeding device 2 extends to the interior of the reaction kettle 31 and is connected to the gas inlet end of the gas distributor 33.

[0037] It can be understood that since the gas outlet end of the gas distributor 33 and one end of the first channel 34 are arranged relative to each other, and the gas outlet end of the second feeding device 2 extends to the interior of the reactor 31 and is connected to the gas inlet end of the gas distributor 33, the gas raw material transported by the second feeding device 2 can enter the first channel 34 using the gas distributor 33, thereby using the gas raw material to form a static pressure difference between the first channel 34 and the second channel 35, and then using the static pressure difference to achieve the circulation of liquid raw material and gas raw material between the first channel 34 and the second channel 35. In addition, through the setting of the gas distributor 33, the gas raw material can enter the first channel 34 more evenly, so that the contact between the gas raw material and the liquid raw material is more sufficient, the mixing reaction efficiency is higher, and the preparation efficiency of the target product is improved.

[0038] It should be noted that the gas distributor 33 is a device that makes the gas introduced evenly distributed over the entire cross section. The specific type of the gas distributor 33 can be set according to actual needs and is not limited thereto. There is a certain distance between the gas outlet end of the gas distributor 33 and the feed end of the first channel 34, which can not only ensure that the gas raw material can stably enter the first channel 34, but also ensure that the mixed material returned from the second channel 35 continues to enter the first channel 34 to participate in the next cycle.

[0039] In some embodiments, the ratio between the diameter of the draft tube 32 and the diameter of the reactor 31 is in the range of 0.2-0.8.

[0040] It can be understood that by setting the ratio range between the diameter of the guide tube 32 and the diameter of the reactor 31 to 0.2-0.8, a reasonable ratio is achieved between the flow rate of the first channel 34 and the flow rate of the second channel 35, thereby ensuring stable and efficient circulation of gas raw materials and liquid raw materials between the first channel 34 and the second channel 35, thereby ensuring a higher mixing reaction efficiency.

[0041] It should be noted that the ratio between the diameter of the guide tube 32 and the diameter of the reactor 31 can be set according to actual needs, and there is no limitation on this. For example, the ratio between the diameter of the guide tube 32 and the diameter of the reactor 31 can be 0.2, 0.3, 0.4, 0.5, 0.6, 0.7, 0.8, etc.

[0042] like Figure 2 As shown, in some embodiments, the first feeding device 1 includes: a metering tank 11, a metering pump 12, a first flowmeter 13, a first shut-off valve 14 and a first check valve 15. Liquid raw material is arranged in the metering tank 11. The liquid inlet end of the metering pump 12 is connected to the liquid outlet end of the metering tank 11, the liquid inlet end of the first flowmeter 13 is connected to the liquid outlet end of the metering pump 12, the liquid inlet end of the first shut-off valve 14 is connected to the liquid outlet end of the first flowmeter 13, the liquid inlet end of the first check valve 15 is connected to the liquid outlet end of the first shut-off valve 14, and the liquid outlet end of the first check valve 15 is connected to the liquid inlet end of the reactor 31.

[0043] It can be understood that under the pressure-boosting action of the metering pump 12, the liquid raw material is transported from the metering tank 11 through the first flowmeter 13, the first shut-off valve 14 and the first check valve 15 in sequence to the reactor 31, thereby ensuring the circulation of the liquid raw material and the gaseous raw material in the reactor 31, thereby achieving a full mixing reaction of the liquid raw material and the gaseous raw material and efficiently generating the target product. In addition, through the metering and storage of the metering tank 11, the flow detection of the first flowmeter 13, the on-off control of the first shut-off valve 14 and the unidirectional conduction of the first check valve 15, the transportation of the liquid raw material is more flexible and accurate, thereby improving the preparation quality and efficiency of the target product.

[0044] It should be noted that the metering tank 11 is used to store the liquid raw material and measure the amount of the liquid raw material. The specific type of the metering tank 11 can be set according to actual needs and is not limited to this.

[0045] The metering pump 12 is used to pressurize and deliver the liquid raw material according to a preset flow rate. The specific type of the metering pump 12 can be set according to actual needs and is not limited to this.

[0046] The first flow meter 13 is used to detect the flow rate of the liquid raw material so as to realize flow rate monitoring by utilizing the detected flow rate. The specific type of the first flow meter 13 can be set according to actual needs and is not limited thereto.

[0047] The first cut-off valve 14 is used for controlling the delivery of liquid raw materials. When the first cut-off valve 14 is turned on, the liquid raw materials can be delivered normally. When the first cut-off valve 14 is turned off, the liquid raw materials cannot be delivered. The specific type of the first cut-off valve 14 can be set according to actual needs and is not limited to this.

[0048] The first check valve 15 is used for unidirectional conduction to prevent the liquid raw material and / or gas raw material in the reaction kettle 31 from flowing back. The specific type of the first check valve 15 can be set according to actual needs and is not limited to this.

[0049] like Figure 3 As shown, in some embodiments, the second feeding device 2 includes: a metering tank 21, a second flow meter 22, a second shut-off valve 23 and a second check valve 24, the metering tank 21 is provided with a gas raw material, the air inlet end of the second flow meter 22 is connected to the air outlet end of the metering tank 21, the air inlet end of the second shut-off valve 23 is connected to the air outlet end of the second flow meter 22, the air inlet end of the second check valve 24 is connected to the air outlet end of the second shut-off valve 23, and the air outlet end of the second check valve 24 extends to the interior of the reactor 31 and is arranged opposite to one end of the first channel 34.

[0050] It can be understood that the gas raw material is transported from the metering tank 21 to the reactor 31 through the second flow meter 22, the second shut-off valve 23 and the second check valve 24 in sequence under the action of its own gas pressure, thereby ensuring the circulation of the gas raw material and the liquid raw material in the reactor 31, thereby achieving a full mixing reaction of the liquid raw material and the gas raw material and efficiently generating the target product. In addition, through the metering and storage of the metering tank 21, the flow detection of the second flow meter 22, the on-off control of the second shut-off valve 23 and the unidirectional conduction of the second check valve 24, the transportation of the gas raw material is more flexible and accurate, thereby improving the preparation quality and efficiency of the target product.

[0051] It should be noted that the metering tank 21 is used to store gas raw materials with a certain pressure and to measure the amount of gas raw materials. The specific type of the metering tank 21 can be set according to actual needs and is not limited to this.

[0052] The second flow meter 22 is used to detect the flow rate of the gas raw material so as to realize flow rate monitoring by using the detected flow rate. The specific type of the second flow meter 22 can be set according to actual needs and is not limited thereto.

[0053] The second cut-off valve 23 is used for controlling the delivery of gas raw materials. When the second cut-off valve 23 is turned on, the gas raw materials can be delivered normally. When the second cut-off valve 23 is turned off, the gas raw materials cannot be delivered. The specific type of the second cut-off valve 23 can be set according to actual needs and is not limited to this.

[0054] The second check valve 24 is used for one-way conduction to prevent the gas raw material and / or liquid raw material in the reaction kettle 31 from flowing back. The specific type of the second check valve 24 can be set according to actual needs and is not limited to this.

[0055] like Figure 1 As shown, in some embodiments, the reaction device 3 also includes: a back pressure valve 4 and a stop valve 5, the liquid inlet end of the back pressure valve 4 is connected to the liquid outlet end of the reaction kettle 31, the liquid inlet end of the stop valve 5 is connected to the liquid outlet end of the back pressure valve 4, and the liquid outlet end of the stop valve 5 is used to discharge the target product.

[0056] It can be understood that the liquid raw material and the gaseous raw material are fully mixed and reacted in the reactor 31 to generate the target product. The target product is discharged after passing through the back pressure valve 4 and the stop valve 5 in sequence under the action of the pressure in the reactor 31, so that the target product can be further processed in the next step. In addition, through the pressure stabilization of the back pressure valve 4 and the on-off control of the stop valve 5, the discharge of the target product is more flexible and stable, thereby improving the preparation quality and efficiency of the target product.

[0057] It should be noted that the back pressure valve 4 is used to stabilize the discharge pressure of the target product. The specific type of the back pressure valve 4 can be set according to actual needs and is not limited to this. The liquid outlet of the reactor 31 can be located on the side.

[0058] The stop valve 5 is used to control the discharge of the target product. When the stop valve 5 is turned on, the target product can be discharged normally. When the stop valve 5 is turned off, the target product cannot be discharged. The specific type of the stop valve 5 can be set according to actual needs and is not limited to this.

[0059] like Figure 4 As shown, the present disclosure also provides a method for preparing tetrafluoroethane-β-sultone. The preparation method is based on the raw material continuous synthesis system of the present disclosure, and the preparation method includes:

[0060] S1: transporting sulfur trioxide from the first feeding device 1 of the raw material continuous synthesis system to the reactor 31 of the raw material continuous synthesis system, and transporting tetrafluoroethylene from the second feeding device 2 of the raw material continuous synthesis system to the first channel 34 of the raw material continuous synthesis system;

[0061] S2: controlling the reaction temperature of the reactor 31 according to a preset temperature, controlling the reaction pressure of the reactor 31 according to a preset pressure, and controlling the reaction liquid level of the reactor 31 according to a first preset liquid level;

[0062] S3: When the reaction time of the reactor 31 reaches a preset time, the target product in the reactor 31 is discharged to obtain tetrafluoroethane-β-sultone.

[0063] It can be understood that sulfur trioxide is transported from the first feeding device 1 to the reactor 31, and tetrafluoroethylene is transported from the second feeding device 2 to the first channel 34, so that the first channel 34 and the second channel 35 have different gas contents, thereby generating a static pressure difference, and then under the action of the static pressure difference, the sulfur trioxide and tetrafluoroethylene in the reactor 31 are continuously circulated between the first channel 34 and the second channel 35, and the reaction temperature of the reactor 31 is controlled at a preset temperature, the reaction pressure of the reactor 31 is controlled at a preset pressure, the reaction liquid level of the reactor 31 is controlled at a first preset liquid level, and the reaction time of the reactor 31 is controlled at a preset time, thereby achieving a full mixing reaction of sulfur trioxide and tetrafluoroethylene and ensuring the stable preparation of tetrafluoroethane-β-sultone.

[0064] Among them, the first feeding device 1 can continuously convey sulfur trioxide into the reactor 31, and the second feeding device 2 can continuously convey tetrafluoroethylene into the reactor 31, so that sulfur trioxide and tetrafluoroethylene can continuously circulate between the first channel 34 and the second channel 35, thereby realizing a sufficient continuous mixing reaction, thereby realizing the continuous preparation of tetrafluoroethane-β-sultone, effectively improving the preparation efficiency of tetrafluoroethane-β-sultone, and the static pressure difference between the first channel 34 and the second channel 35 is used to realize the circulation of sulfur trioxide and tetrafluoroethylene, thereby avoiding the input of external power such as stirring, thereby effectively reducing the overall energy consumption, and at the same time, the method of realizing the mixing reaction through the circulating flow has better uniformity, thereby improving the overall heat transfer performance, thereby greatly reducing the safety problems such as local hot spots and tetrafluoroethylene self-polymerization, thereby meeting the preparation requirements of tetrafluoroethane-β-sultone with high efficiency, low energy consumption and high safety factor.

[0065] It should be noted that the preset temperature, preset pressure, first preset liquid level and preset time as reaction parameters of sulfur trioxide and tetrafluoroethylene in the reactor 31 can be set according to actual needs, and there is no limitation on this. Different parameter combinations can produce different effects, that is, different efficiencies of tetrafluoroethane-β-sultone preparation and different qualities of tetrafluoroethane-β-sultone preparation. Therefore, when selecting the value of a certain parameter, the value selection of other parameters should be considered.

[0066] In some embodiments, the preset temperature ranges from 30°C to 50°C, the preset pressure ranges from 0.05MPa to 0.2MPa, the first preset liquid level ranges from 70% to 95% of the total liquid level of the reactor 31, and the preset time ranges from 1h to 5h.

[0067] It can be understood that the preset temperature range is set to 30°C-50°C, the preset pressure range is set to 0.05MPa-0.2MPa, the first preset liquid level range is set to 70%-95% of the total liquid level of the reactor 31, and the preset time range is set to 1h-5h, so that the reaction temperature, reaction pressure, reaction liquid level and reaction time in the reactor 31 can be within a reasonable range, thereby ensuring high efficiency and high quality preparation of tetrafluoroethane-β-sultone.

[0068] It should be noted that the specific value of the preset temperature can be set according to actual needs and is not limited to this. For example, the preset temperature can be 30°C, 35°C, 40°C, 45°C, 50°C, etc.

[0069] The specific value of the preset pressure can be set according to actual needs and is not limited to this. For example, the preset pressure can be 0.05MPa, 0.1MPa, 0.15MPa, 0.2MPa, etc.

[0070] The specific value of the first preset liquid level can be set according to actual needs, and there is no limitation on this. For example, the first preset liquid level can be 70%, 75%, 80%, 85%, 90%, 95% and the like of the total liquid level of the reactor 31.

[0071] The specific value of the preset time can be set according to actual needs and is not limited to this. For example, the preset time can be 1h, 2h, 2.5h, 3h, 4h, 5h, etc.

[0072] In some embodiments, the preparation method further includes: before delivering sulfur trioxide to the reactor 31 and delivering tetrafluoroethylene to the first channel 34, adding a second preset liquid level of tetrafluoroethane-β-sultone to the reactor 31; wherein the second preset liquid level is lower than the first preset liquid level.

[0073] It can be understood that before the mixing reaction of sulfur trioxide and tetrafluoroethylene, adding tetrafluoroethane-β-sultone at a second preset liquid level into the reactor 31 can ensure that when sulfur trioxide and tetrafluoroethylene are first added, there is a certain circulation volume between the first channel 34 and the second channel 35, thereby ensuring an efficient mixing reaction of sulfur trioxide and tetrafluoroethylene.

[0074] It should be noted that the second preset liquid level is lower than the first preset liquid level, and the specific value of the second preset liquid level can be set according to actual needs, and there is no restriction on this. Among them, the second preset liquid level should ensure that there is a small amount of tetrafluoroethane-β-sultone in the reactor 31, and ensure that sulfur trioxide and tetrafluoroethylene can be circulated between the first channel 34 and the second channel 35 when they are first added.

[0075] In some embodiments, the preparation method further comprises: after obtaining tetrafluoroethane-β-sultone, continuously distilling and separating the tetrafluoroethane-β-sultone until the purity of the tetrafluoroethane-β-sultone reaches a preset purity.

[0076] It is understandable that after tetrafluoroethane-β-sultone is obtained, tetrafluoroethane-β-sultone is continuously distilled and separated, so that the purity of tetrafluoroethane-β-sultone is higher, thereby meeting the high-quality preparation requirements of tetrafluoroethane-β-sultone.

[0077] It should be noted that the specific value of the preset purity can be set according to actual needs and is not limited thereto. For example, the preset purity can be 99.8%, that is, when the purity of tetrafluoroethane-β-sultone reaches above 99.8%, the distillation separation of tetrafluoroethane-β-sultone is stopped.

[0078] As a first embodiment of the method for preparing tetrafluoroethane-β-sultone: the ratio of the diameter of the guide tube 32 to the diameter of the reactor 31 is set to 0.8; first, tetrafluoroethane-β-sultone of a second preset liquid level is added to the reactor 31, and the reaction liquid level of the reactor 31 is set to 90%, the reaction pressure of the reactor 31 is set to 0.2 MPa, and the reaction temperature of the reactor 31 is set to 40°C; thereafter, tetrafluoroethylene and sulfur trioxide are continuously introduced into the reactor 31, and the reaction time of the reactor 31 is controlled to be 2.5 hours; finally, the tetrafluoroethane-β-sultone discharged from the reactor 31 is separated by continuous distillation, and the purity reaches 99.9%.

[0079] As a second embodiment of the method for preparing tetrafluoroethane-β-sultone: the ratio of the diameter of the guide tube 32 to the diameter of the reactor 31 is set to 0.6; first, tetrafluoroethane-β-sultone of a second preset liquid level is added to the reactor 31, and the reaction liquid level of the reactor 31 is set to 80%, the reaction pressure of the reactor 31 is set to 0.1 MPa, and the reaction temperature of the reactor 31 is set to 35°C; thereafter, tetrafluoroethylene and sulfur trioxide are continuously introduced into the reactor 31, and the reaction time of the reactor 31 is controlled to be 1 hour; finally, the tetrafluoroethane-β-sultone discharged from the reactor 31 is separated by continuous distillation, and the purity reaches 99.8%.

[0080] As a third embodiment of the method for preparing tetrafluoroethane-β-sultone: the ratio of the diameter of the guide tube 32 to the diameter of the reactor 31 is set to 0.5; first, tetrafluoroethane-β-sultone of a second preset liquid level is added to the reactor 31, and the reaction liquid level of the reactor 31 is set to 70%, the reaction pressure of the reactor 31 is set to 0.2 MPa, and the reaction temperature of the reactor 31 is set to 45°C; thereafter, tetrafluoroethylene and sulfur trioxide are continuously introduced into the reactor 31, and the reaction time of the reactor 31 is controlled to be 3 hours; finally, the tetrafluoroethane-β-sultone discharged from the reactor 31 is separated by continuous distillation, and the purity reaches 99.8%.

[0081] As a fourth embodiment of the method for preparing tetrafluoroethane-β-sultone: the ratio of the diameter of the guide tube 32 to the diameter of the reactor 31 is set to 0.7; first, tetrafluoroethane-β-sultone of a second preset liquid level is added to the reactor 31, and the reaction liquid level of the reactor 31 is set to 85%, the reaction pressure of the reactor 31 is set to 0.15 MPa, and the reaction temperature of the reactor 31 is set to 30°C; thereafter, tetrafluoroethylene and sulfur trioxide are continuously introduced into the reactor 31, and the reaction time of the reactor 31 is controlled to be 4 hours; finally, the tetrafluoroethane-β-sultone discharged from the reactor 31 is separated by continuous distillation, and the purity reaches 99.9%.

[0082] It should be noted that, in the description of the present disclosure, the terms "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying relative importance. In addition, in the description of the present disclosure, unless otherwise specified, the meaning of "plurality" is two or more.

[0083] Any process or method description in a flowchart or otherwise described herein may be understood to represent a module, segment or portion of code that includes one or more executable instructions for implementing the steps of a specific logical function or process, and the scope of the preferred embodiments of the present disclosure includes alternative implementations in which functions may not be performed in the order shown or discussed, including performing functions in a substantially simultaneous manner or in the reverse order depending on the functions involved, which should be understood by those skilled in the art to which the embodiments of the present disclosure belong.

[0084] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present disclosure. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.

[0085] Although the embodiments of the present disclosure have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present disclosure. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present disclosure.

Claims

1. A raw material continuous synthesis system, characterized in that: include: A first feeding device, the first feeding device is used to transport liquid raw materials; a second feeding device, the second feeding device being used for conveying gas raw materials; A reaction device, comprising: a reaction kettle and a guide tube, wherein a liquid inlet end of the reaction kettle is connected to a liquid outlet end of the first feeding device, the guide tube is arranged in the reaction kettle, a first channel is formed inside the guide tube, and a second channel is formed outside the guide tube; Among them, the gas outlet end of the second feeding device extends into the interior of the reactor and is arranged opposite to one end of the first channel, so that the liquid raw material and the gas raw material in the reactor circulate between the first channel and the second channel and react to generate the target product.

2. The raw material continuous synthesis system according to claim 1, characterized in that: The reaction device also includes: A gas distributor is arranged in the reactor, and the gas outlet end of the gas distributor is arranged opposite to one end of the first channel, and the gas outlet end of the second feeding device extends into the interior of the reactor and is connected to the gas inlet end of the gas distributor.

3. The raw material continuous synthesis system according to claim 1, characterized in that: The ratio between the diameter of the guide tube and the diameter of the reactor is in the range of 0.2-0.

8.

4. The raw material continuous synthesis system according to claim 1, characterized in that: The first feeding device comprises: A metering tank, in which the liquid raw material is arranged; A metering pump, wherein a liquid inlet end of the metering pump is connected to a liquid outlet end of the metering tank; a first flow meter, wherein a liquid inlet end of the first flow meter is connected to a liquid outlet end of the metering pump; a first cut-off valve, wherein a liquid inlet end of the first cut-off valve is connected to a liquid outlet end of the first flow meter; A first check valve, wherein a liquid inlet end of the first check valve is connected to a liquid outlet end of the first cut-off valve, and a liquid outlet end of the first check valve is connected to a liquid inlet end of the reactor.

5. The raw material continuous synthesis system according to claim 1, characterized in that: The second feeding device comprises: A metering tank, in which the gas raw material is arranged; a second flow meter, wherein an air inlet end of the second flow meter is connected to an air outlet end of the metering tank; a second cut-off valve, wherein an air inlet end of the second cut-off valve is connected to an air outlet end of the second flow meter; A second check valve, wherein the air inlet end of the second check valve is connected to the air outlet end of the second cut-off valve, and the air outlet end of the second check valve extends into the interior of the reactor and is arranged opposite to one end of the first channel.

6. The raw material continuous synthesis system according to claim 1, characterized in that: The reaction device also includes: A back pressure valve, wherein the liquid inlet end of the back pressure valve is connected to the liquid outlet end of the reactor; A stop valve, wherein the liquid inlet end of the stop valve is connected to the liquid outlet end of the back pressure valve, and the liquid outlet end of the stop valve is used to discharge the target product.

7. A method for preparing tetrafluoroethane-β-sultone, characterized in that: The preparation method is based on the raw material continuous synthesis system described in any one of claims 1 to X, and the preparation method comprises: delivering sulfur trioxide from the first feeding device of the raw material continuous synthesis system to the reaction kettle of the raw material continuous synthesis system, and delivering tetrafluoroethylene from the second feeding device of the raw material continuous synthesis system to the first channel of the raw material continuous synthesis system; Controlling the reaction temperature of the reactor according to a preset temperature, controlling the reaction pressure of the reactor according to a preset pressure, and controlling the reaction liquid level of the reactor according to a first preset liquid level; When the reaction time of the reactor reaches a preset time, the target product in the reactor is discharged to obtain the tetrafluoroethane-β-sultone.

8. The method for preparing tetrafluoroethane-β-sultone according to claim 7, characterized in that: The preset temperature range is 30°C-50°C; and / or, The preset pressure ranges from 0.05MPa to 0.2MPa; and / or, The range of the first preset liquid level is 70%-95% of the total liquid level of the reactor; and / or, The preset time ranges from 1h to 5h.

9. The method for preparing tetrafluoroethane-β-sultone according to claim 7, characterized in that: The preparation method further comprises: Before delivering the sulfur trioxide to the reactor and delivering the tetrafluoroethylene to the first channel, adding a second preset liquid level of the tetrafluoroethane-β-sultone to the reactor; Wherein, the second preset liquid level is lower than the first preset liquid level.

10. The method for preparing tetrafluoroethane-β-sultone according to claim 7, characterized in that: The preparation method further comprises: After the tetrafluoroethane-β-sultone is obtained, the tetrafluoroethane-β-sultone is continuously distilled and separated until the purity of the tetrafluoroethane-β-sultone reaches a preset purity.