Shore crane control method and system and electronic equipment
Through the shore bridge control method and system, the control mode and working state of the shore bridge are switched, and the problem of underutilization of the operation table is solved, and efficient utilization of resources and the improvement of safety and efficiency of dock loading and unloading operations are achieved.
Patent Information
- Application Number
- CN202411371069.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-27
- Publication Date
- 2024-11-19
AI Technical Summary
In dock loading and unloading operations, the operating table is not fully utilized, resulting in waste of resources. Especially when the seaside loading and unloading work needs to be manually completed by the operator, the operating table is idle during the automation work phase, resulting in waste of resources.
Provide a shore bridge control method and system, which switches the control mode of the shore bridge through the communication connection between the operating table and the shore bridge. Monitoring mode and manual operation mode are allowed to switch the working state of the shore bridge as needed, from the automatic working state. Switch to manual operation and force the automatic operation to be completed if necessary for manual control.
Effectively utilize the operation table resources, reduce resource waste, ensure that operators can safely control the shore and bridges, and improve the efficiency and safety of dock loading and unloading operations.
Smart Images

Figure CN118978095A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of container loading and unloading, and in particular to a quay crane control method, system and electronic equipment. Background Art
[0002] With the development of technology, more and more new technologies are being applied to container loading and unloading at the terminal, which has led to the development of terminal loading and unloading operations. Among them, the land-side loading and unloading work and the intermediate process of the loading and unloading process have gradually been fully automated, but the sea-side loading and unloading work has not yet been fully automated due to the complex environment and other reasons, and operators are required to complete the loading and unloading work manually.
[0003] A complete operation cycle includes land-side loading and unloading, intermediate process and sea-side loading and unloading work, and reset. When the operator controls the quay crane to carry out terminal loading and unloading operations, the operating console is idle during the automated working stage and is not fully utilized. The operator is also in a state of having nothing to do, resulting in a large waste of resources. Summary of the invention
[0004] In view of this, the present application is dedicated to providing a quay crane control method, system and electronic equipment to solve the technical problem that the operating platform is not fully utilized and resources are wasted during terminal loading and unloading operations.
[0005] In a first aspect, an embodiment of the present application provides a quay crane control method, which is applied to an operating console, wherein the operating console is communicatively connected to a quay crane, wherein the quay crane includes a first quay crane and a second quay crane, and the method includes:
[0006] When receiving a manual operation instruction, the control mode of the quay crane is switched from the monitoring mode to the manual operation mode and the manually operated quay crane is instructed to switch the working state from the automatic working state to the manual operation state, wherein the manual operation instruction includes selecting one of the first quay crane and the second quay crane as the manually operated quay crane, the manual operation mode is used to receive the operation instruction input by the operator to manually control the manually operated quay crane, and the monitoring mode is used to display the working information of the first quay crane and the second quay crane;
[0007] When an automatic working instruction is received, the control mode of the quay crane is switched from the manual operation mode to the monitoring mode and the manually operated quay crane is instructed to switch the working state from the manual operation state to the automatic working state.
[0008] Optionally, the manual operation instruction includes an active intervention operation instruction and a passive intervention operation instruction;
[0009] When receiving the manual operation instruction, switching the control mode of the quay crane from the monitoring mode to the manual operation mode and instructing the manually operated quay crane to switch the working state from the automatic working state to the manual operation state comprises:
[0010] When receiving the active intervention operation instruction, the control mode of the quay crane is switched from the monitoring mode to the manual operation mode and the manually operated quay crane is instructed to forcibly stop the ongoing loading and unloading work, forcibly end the automatic working state and switch to the manual operation state;
[0011] or,
[0012] When the passive intervention operation instruction for responding to a manual operation request is received, the control mode of the quay crane is switched from the monitoring mode to the manual operation mode, instructing the manually operated quay crane to switch from the automatic working state to the manual operation state. The manual operation request is used to request manual control from the operator when the loading and unloading work enters the sea side working stage.
[0013] Optionally, the method further includes:
[0014] When a quick intervention operation instruction is received in the manual operation mode, the control mode of the quay crane is maintained in the manual operation mode, and the manual operation quay crane selected in the passive intervention operation instruction is instructed to switch the working state from the automatic working state to the manual operation state.
[0015] Optionally, the method further includes:
[0016] When an intervention operation instruction is received, adding the manually operated quay crane selected in the intervention operation instruction to a manual operation request queue, wherein the intervention operation instruction is the active intervention operation instruction, the passive intervention operation instruction or the quick intervention operation instruction;
[0017] When the manually operated quay crane selected in the intervention operation instruction is at the head of the manual operation request queue, the control mode of the quay crane is placed in the manual operation mode and the manually operated quay crane selected in the intervention operation instruction is instructed to switch the working state from the automatic working state to the manual operation state.
[0018] Optionally, when the active intervention operation instruction is received, after instructing the manually operated quay crane to forcibly stop the ongoing loading and unloading work, forcibly end the automatic working state and switch to the manual operation state, the method further includes:
[0019] When the automatic work instruction is received, obtaining the interrupted work that is forcibly stopped by the active intervention operation instruction;
[0020] The manually operated quay crane is instructed to start with the next stage of the interrupted work in the loading and unloading operation process, and the working state is switched from the manual operation state to the automatic working state.
[0021] Optionally, the method further includes:
[0022] In the monitoring mode, setting the display area for displaying the working information of the first quay crane equal to the display area for displaying the working information of the second quay crane;
[0023] In the manual operation mode, a display area for displaying the working information of the manually operated quay crane is set to be larger than a display area for displaying the working information of quay cranes other than the manually operated quay crane.
[0024] Optionally, receiving an intervention operation instruction includes:
[0025] When it is detected that the lifting operating handle deviates to the left or right, and the deviation angle is greater than the preset angle, and the deviation time is greater than the preset time, the intervention operation instruction is received.
[0026] In a second aspect, an embodiment of the present application provides a quay crane control system, including:
[0027] A quay crane and an operating platform, wherein the operating platform is communicatively connected with the quay crane, and the quay crane comprises a first quay crane and a second quay crane;
[0028] The operating console is used to switch the control mode of the quay crane from the monitoring mode to the manual operation mode and instruct the manually operated quay crane to switch the working state from the automatic working state to the manual operation state when receiving a manual operation instruction. The manual operation instruction includes selecting one between the first quay crane and the second quay crane as the manually operated quay crane. The manual operation mode is used to receive the operation instructions input by the operator to manually control the manually operated quay crane. The monitoring mode is used to display the working information of the first quay crane and the second quay crane. When an automatic working instruction is received, the control mode of the quay crane is switched from the manual operation mode to the monitoring mode and the manually operated quay crane is instructing to switch the working state from the manual operation state to the automatic working state.
[0029] Optionally, the automation controllers of the first quay crane and the second quay crane are communicatively connected with the controller of the operating console to form a control network of the quay crane control system;
[0030] The first quay crane and the second quay crane are connected to the operating console through server communication, forming an information flow network of the quay crane control system.
[0031] In a third aspect, an embodiment of the present application provides an electronic device, including a memory and a processor;
[0032] The memory is connected to the processor and is used to store programs;
[0033] The processor is used to implement the quay crane control method as described in the first aspect by running the program in the memory.
[0034] The present application provides a quay crane control method, which clearly defines the switching logic of the quay crane control mode between the monitoring mode and the manual operation mode, and the control logic of the manual operation quay crane corresponding to the switching working state when receiving the corresponding instruction issued by the operator. The working information of each quay crane is displayed in the monitoring mode; the operation instruction for manually controlling the manually operated quay crane will be received in the manual operation mode. The quay crane control method provided in the present application helps the operator to accurately recognize the quay crane being controlled according to the control mode of the current quay crane, provides safety protection for one operator to control two quay crane equipment at the same time, reduces the number of operating stations, and reduces the waste of resources in terminal loading and unloading operations. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying any creative work.
[0036] Figure 1 A schematic flow chart of a quay crane control method provided in an embodiment of the present application;
[0037] Figure 2 A schematic diagram of the structure of an operating table provided in an embodiment of the present application;
[0038] Figure 3 A schematic diagram of a screen display mode of an operation console in a monitoring mode provided in an embodiment of the present application;
[0039] Figure 4 A schematic diagram of a screen display mode of an operation console in a manual operation mode provided in an embodiment of the present application;
[0040] Figure 5 A schematic diagram of the structure of a quay crane control system provided in an embodiment of the present application;
[0041] Figure 6 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION
[0042] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0043] In the terminal loading and unloading work, the complete operation process of a container includes land-side loading and unloading, intermediate process, sea-side loading and unloading, and reset. The terminal loading and unloading work specifically includes two types, unloading and loading. Unloading is to unload the container from the transport ship, and loading is to load the container from land to the transport ship. Taking the scenario of unloading the container from the transport ship as an example, the operation process is described in more detail. After completing the unloading of the previous container, the hoist on the quay crane moves from above the land-side container truck to above the ship's position on the sea side. Then the operator manually operates the hoist to open and close the lock on the sea side and then pulls it up, and then enters the automatic process from the sea side to the land-side container truck, and then automatically places the container on the land-side container truck, opens and closes the lock and automatically lifts it. Through the repetition of the above process, batch loading and unloading of containers is realized.
[0044] Whether unloading or loading, containers need to be operated on the sea side. Due to the complex environment of the seaside transport ship, the operation of containers on the sea side has not yet been fully automated. The operation of lifting or lowering the container after the lifting device is opened and locked on the sea side is mainly performed manually by the operator.
[0045] When an operator operates a quay crane, the operator will not mistake the quay crane he is operating. However, when an operator operates multiple quay cranes, if the operator cannot accurately determine which quay crane he is operating, serious safety accidents may occur. In view of the above situation, the first embodiment of the present application provides a quay crane control method, which is applied to an operating station, and the operating station is connected to the quay crane in communication. The quay crane includes a first quay crane and a second quay crane, such as Figure 1 As shown, the method may specifically include the following steps:
[0046] Step 101. When a manual operation instruction is received, the control mode of the quay crane is switched from the monitoring mode to the manual operation mode and the manually operated quay crane is instructed to switch the working state from the automatic working state to the manual operation state. The manual operation instruction includes selecting one of the first quay crane and the second quay crane as a manually operated quay crane. The manual operation mode is used to receive the operation instructions input by the operator to manually control the manually operated quay crane. The monitoring mode is used to display the working information of the first quay crane and the second quay crane.
[0047] In this embodiment, a control mode of the quay crane is proposed to describe the working logic of the operation console. The control mode of the quay crane can be switched between a monitoring mode and a manual operation mode. In this embodiment, a working state of the quay crane is also proposed to describe the working logic of the quay crane. The working state of the quay crane can be switched between an automatic working state and a manual operation state.
[0048] In this embodiment, the safety of loading and unloading is ensured by the operation mode and working state of the quay crane. Specifically, the operation instruction input by the operator can be executed only when the operation mode, working state and corresponding relationship between the operation mode and working state of the quay crane are correct. The switching of the operation mode and working state of the quay crane can be triggered only under specified circumstances.
[0049] For example, when all quay cranes are in automatic working state, the control mode of the quay crane is in monitoring mode, and only the working information of the first quay crane and the second quay crane will be displayed to the operator. No operation instructions other than manual operation instructions will be received to avoid safety accidents caused by operator's misoperation in monitoring mode.
[0050] When the loading and unloading work of a quay crane enters the seaside working stage, since it is necessary to manually control the quay crane to open, close, lock, pull up or put down the container, the operator will use the quay crane as a manual operation quay crane and issue the corresponding manual operation command. After receiving the manual operation command, the control mode of the quay crane is switched from the monitoring mode to the manual operation mode and the manual operation quay crane is instructed to switch the working state from the automatic working state to the manual operation state. At this time, other quay cranes are not affected and remain in the automatic working state. In the manual operation mode, various operation commands received by the operator will only take effect on the manual operation quay crane in the manual operation state, and will not take effect on other quay cranes in the automatic working state.
[0051] In summary, only when the console side is in manual operation mode and there is a manually operated quay crane in manual operation, can the operator manually control only the manual quay crane. In other cases, the operator's operation of the quay crane is restricted. Since the manual operation instructions for switching between the console side and the quay crane side are issued by the operator, it can be considered that before the operator operates the manually operated quay crane, he has accurately recognized the quay crane that will be manually controlled next, providing safety protection for one operator to control two quay crane equipment at the same time, reducing the number of consoles invested, and reducing the waste of resources in terminal loading and unloading operations.
[0052] Step 102: When receiving an automatic working instruction, the control mode of the quay crane is switched from the manual operation mode to the monitoring mode and the manually operated quay crane is instructed to switch the working state from the manual operation state to the automatic working state.
[0053] When the operator completes the container loading and unloading work on the sea side under manual control, the operator will issue an automatic work instruction. After receiving the automatic work instruction, the control mode of the quay crane is switched from the manual operation mode to the monitoring mode and the manually operated quay crane is instructed to switch the working state from the manual operation state to the automatic working state, so that the quay crane can continue to carry out other container loading and unloading work that can be performed automatically.
[0054] According to statistics, it takes about 40 seconds to complete a manual operation on the sea side. The process of moving the intermediate spreader and the work on the land side container truck has been basically fully automated. According to statistics, it takes about 80 seconds to automatically complete an automated spreader movement and loading and unloading work on the land side container truck. In a one-to-one operation cycle, that is, one operator operates one quay crane, the operating console is idle most of the time. This embodiment provides a quay crane control method to ensure that the operator can safely control two quay cranes to load and unload containers.
[0055] The second embodiment of the present application further defines the quay crane control method in the first embodiment in more detail and specificity. Some or all of the technical features in the second embodiment can be combined with or replaced with the first embodiment individually or in combination, so as to obtain more feasible quay crane control methods.
[0056] The following is a detailed description of the quay crane control method in the second embodiment of the present application:
[0057] Optionally, the manual operation instructions include active intervention operation instructions and passive intervention operation instructions; when the manual operation instruction is received, the control mode of the quay crane is switched from the monitoring mode to the manual operation mode and the manually operated quay crane is instructed to switch the working state from the automatic working state to the manual operation state, including: when the active intervention operation instruction is received, the control mode of the quay crane is switched from the monitoring mode to the manual operation mode and the manually operated quay crane is instructed to forcibly stop the ongoing loading and unloading work, forcibly end the automatic working state and switch to the manual operation state; or, when a passive intervention operation instruction for responding to a manual operation request is received, the control mode of the quay crane is switched from the monitoring mode to the manual operation mode and the manually operated quay crane is instructed to switch from the automatic working state to the manual operation state, and the manual operation request is used to request manual control from the operator when the loading and unloading work enters the sea side working stage.
[0058] Although the land-side container truck loading and unloading work and the intermediate stage of spreader movement in the terminal container loading and unloading work have been basically automated, when the working environment becomes complicated, the automated control logic is difficult to guarantee 100% rationality and safety. For example, when the port throughput is large and the terminal business is busy, the land-side container trucks may pass by due to a large number of other container trucks, making it difficult to carry out the automated loading and unloading work that relies on image recognition.
[0059] Therefore, this embodiment proposes that manual operation instructions include active intervention operation instructions and passive intervention operation instructions. Among them, when the loading and unloading work enters the sea side working stage, a manual operation request is sent to the operator, prompting the operator to request manual control, and the operator responds to the manual operation request and issues a passive intervention operation instruction. When the operator finds an unexpected situation in the monitoring mode, such as the failure of the above-mentioned automated loading and unloading work of the land side container truck, the operator can actively issue an active intervention operation instruction, switch the control mode of the quay crane on the operating station side from the monitoring mode to the manual operation mode, and instruct the manually operated quay crane to forcibly stop the ongoing loading and unloading work, forcibly end the automatic working state and switch to the manual operation state, so as to manually take over the current work of the manually operated quay crane.
[0060] Optionally, the quay crane control method also includes: when a quick intervention operation instruction is received in the manual operation mode, maintaining the control mode of the quay crane in the manual operation mode, and instructing the manual operation quay crane selected in the passive intervention operation instruction to switch the working state from the automatic working state to the manual operation state.
[0061] As mentioned above, statistics show that it takes about 40 seconds to complete a manual operation on the sea side, and about 80 seconds for other automated operations. Ideally, the time for the first and second quay cranes to enter the sea side work phase can be reasonably arranged to avoid the situation where manual operation requests "collide", that is, the manual operation of the previous quay crane has not been completed, and the next quay crane has already requested manual control.
[0062] However, the situation in actual application is more complicated, and it is inevitable that manual operation requests will "collide". Under normal circumstances, it is necessary to issue an automatic work instruction to switch the control mode of the quay crane on the operating console side from the manual operation mode to the monitoring mode and instruct the previous quay crane to switch the working state from the manual operation state to the automatic working state, and then respond to the manual operation instruction of the next quay crane again, switch the control mode of the quay crane on the operating console side from the monitoring mode to the manual operation mode and instruct the next quay crane to switch the working state from the automatic working state to the manual operation state. Obviously, the steps of repeatedly switching between the manual operation mode and the monitoring mode of the operating console in the above process are somewhat redundant, which reduces the work efficiency of loading and unloading work.
[0063] Therefore, this embodiment proposes a quick intervention operation instruction. When a manual operation request "collides", the operator can issue a quick intervention operation instruction after completing the manual control work of the previous quay crane and instructing the previous quay crane to enter the automatic working state. When a quick intervention operation instruction is received in the manual operation mode, the control mode of the quay crane on the operating console side is kept in the manual operation mode, and the next quay crane selected in the passive intervention operation instruction is directly instructed to switch the working state from the automatic working state to the manual operation state.
[0064] The quay crane control method provided in this embodiment optimizes the control logic for switching the working state of the quay crane when a manual operation request "collisions", omits the redundant step of repeatedly switching the operating console between manual operation mode and monitoring mode in this case, and improves the work efficiency of loading and unloading work.
[0065] Optionally, the quay crane control method also includes: when an intervention operation instruction is received, adding the manually operated quay crane selected in the intervention operation instruction to a manual operation request queue, the intervention operation instruction being an active intervention operation instruction, a passive intervention operation instruction or a quick intervention operation instruction; when the manually operated quay crane selected in the intervention operation instruction is at the head of the manual operation request queue, the control mode of the quay crane is put into manual operation mode and the manually operated quay crane selected in the intervention operation instruction is instructing to switch the working state from the automatic working state to the manual operation state.
[0066] This embodiment proposes a further optimization method for the situation where multiple quay cranes request manual operation. Specifically, multiple quay cranes are manually controlled in an orderly manner by means of a queue.
[0067] When an active intervention operation instruction, a passive intervention operation instruction or a quick intervention operation instruction is received, the manually operated quay crane selected by the instruction is added to the manual operation request queue. The queue follows the first-come-first-served rule, and the operator always manually operates the quay crane at the head of the queue. When the operator completes the manual operation of other quay cranes in front, the manually operated quay crane selected in the intervention operation instruction will be at the head of the manual operation request queue. At this time, the control mode of the quay crane is put into the manual operation mode and the manually operated quay crane selected in the intervention operation instruction is instructed to switch the working state from the automatic working state to the manual operation state.
[0068] The quay crane control method proposed in this embodiment further improves the control logic in complex situations where multiple quay cranes request manual control, and retains expansion space by introducing a queue. With the development of technology, the quay crane control method proposed in this embodiment can be further extended to situations where one operator operates three, four or even more quay cranes.
[0069] Optionally, when an active intervention operation instruction is received, the manually-operated quay crane is instructed to forcibly stop the ongoing loading and unloading work, forcibly end the automatic working state and switch to the manual operation state, and it also includes: when an automatic work instruction is received, obtaining the interrupted work that is forcibly stopped by the active intervention operation instruction; instructing the manually-operated quay crane to start with the next stage of the interrupted work in the loading and unloading operation process, and switch the working state from the manual operation state to the automatic working state.
[0070] In the quay crane control method provided in this embodiment, the operator can actively issue an active intervention operation instruction to instruct the manually operated quay crane to forcibly stop the ongoing loading and unloading work, forcibly end the automatic working state and switch to the manual operation state, so as to manually take over the work currently being performed by the manually operated quay crane. The above operation will disrupt the original working logic of the automated loading and unloading work. This embodiment proposes a method for restoring the normal automatic operation of the quay crane after the operator actively intervenes.
[0071] Specifically, the interrupted work that is forcibly stopped by the active intervention operation instruction is obtained. After the operator actively intervenes in the interrupted work, the interrupted work will be completed. Therefore, the manually operated quay crane is instructed to start with the next stage of the interrupted work in the loading and unloading operation process, and the working state is switched from the manual operation state to the automatic working state. For example, after the operator manually intervenes in the loading and unloading work of the land-side container truck, when the automatic work instruction issued by the operator is received, the next stage of the loading and unloading work of the land-side container truck is started, that is, the work of moving the spreader to the sea side is started to continue the automated terminal loading and unloading work.
[0072] Optionally, the quay crane control method also includes: in the monitoring mode, setting the display area for displaying the working information of the first quay crane to be equal to the display area for displaying the working information of the second quay crane; in the manual operation mode, setting the display area for displaying the working information of the manually operated quay crane to be larger than the display area for displaying the working information of quay cranes other than the manually operated quay cranes.
[0073] In monitoring mode, each quay crane is in automatic working state and there is no manual operation of the quay crane. Therefore, the display area for displaying the working information of each quay crane is set equal to facilitate the operator to monitor the working conditions of all quay cranes equally.
[0074] In the manual operation mode, the operator's energy is mainly focused on manually controlling the manually operated quay crane. Therefore, the display area for displaying the working information of the manually operated quay crane is set to be larger than the display area for displaying the working information of quay cranes other than the manually operated quay crane, so that the operator can obtain more working information of the manually operated quay crane.
[0075] For example, Figure 2The figure shows a common 6-screen quay crane remote control console. The console is equipped with 6 screens, numbered 1-6, a touch screen display for operation, a voice telephone terminal and an intercom terminal. Each screen on the remote control console can be further split to display the camera and operation information. For example, screens 1, 3, 4 and 6 can be divided into four parts, and screens 2 and 5 can be divided into two parts, upper and lower.
[0076] like Figure 3 As shown, it is Figure 2 An example of the 6-screen quay crane remote control console in monitoring mode. In monitoring mode, screens 1-3 display the camera and operation information of the first quay crane, and screens 4-6 display the camera and operation information of the second quay crane.
[0077] like Figure 4 As shown in the figure, it is an example of the screen display when one of the quay cranes is manually controlled as a manually operated quay crane. In the manual operation mode, screen 2 and screen 5 display the video information of the spreader of the manually operated quay crane. Specifically, screen 2 displays the video of the front camera of the spreader (trolley frame), and screen 5 displays the video of the rear camera of the spreader (trolley frame) without splitting the screen. At this time, the working information of the manually operated quay crane occupies 4 screens for display, and the working information of other quay cranes occupies 2 screens for display.
[0078] Optionally, receiving an intervention operation instruction includes: when it is detected that the lifting operation handle is offset to the left or right, and the offset angle is greater than a preset angle, and the offset time is greater than a preset time, receiving the intervention operation instruction.
[0079] This embodiment limits the way in which the operator issues intervention operation instructions. Specifically, Figure 2 As shown, Figure 3 The reference numeral 7 in the figure is a lifting operation handle. This embodiment proposes to reuse this handle to realize the function of issuing an intervention operation instruction.
[0080] Specifically, under normal circumstances, the lifting operating handle only defines the front and rear offsets, which is used to control the hoisting equipment of the quay crane for loading and unloading; but the left and right offsets of the lifting operating handle are not defined. Therefore, this embodiment proposes that when it is detected that the lifting operating handle is offset to the left and right, and the offset angle is greater than the preset angle, and the offset time is greater than the preset time, an intervention operation instruction is received.
[0081] Different offset directions can be used to select the manually operated quay crane. For example, setting the left offset corresponds to selecting the first quay crane as the manually operated quay crane, and setting the right offset corresponds to selecting the second quay crane as the manually operated quay crane.
[0082] The preset time and preset angle can be adaptively set for different intervention operation instructions according to actual needs. For example, after receiving a manual operation request, when the left or right deviation is greater than 5° and the offset signal is maintained for more than 200ms, it is considered that the first or second quay crane is selected as the manual operation quay crane to issue a passive intervention operation instruction; when no manual operation request is received, it is detected that the manual operation request is greater than 10° and the offset signal is maintained for more than 200ms, it is considered that the first or second quay crane is selected as the manual operation quay crane to issue an active intervention operation instruction.
[0083] The third embodiment of the present application further provides a quay crane control system, comprising:
[0084] A quay crane and an operating platform, wherein the operating platform is communicatively connected with the quay crane, and the quay crane comprises a first quay crane and a second quay crane;
[0085] An operating console is used to switch the control mode of the quay crane from the monitoring mode to the manual operation mode and instruct the manually operated quay crane to switch the working state from the automatic working state to the manual operation state when a manual operation instruction is received. The manual operation instruction includes selecting one of the first quay crane and the second quay crane as a manually operated quay crane. The manual operation mode is used to receive the operation instructions input by the operator to manually control the manually operated quay crane. The monitoring mode is used to display the working information of the first quay crane and the second quay crane. When an automatic working instruction is received, the control mode of the quay crane is switched from the manual operation mode to the monitoring mode and the manually operated quay crane is instructed to switch the working state from the manual operation state to the automatic working state.
[0086] This embodiment proposes a quay crane operating system, wherein the first quay crane and the second quay crane are used to accept control of an operating console to complete container loading and unloading work, and the operating console is used to implement the quay crane control method described in the first embodiment to complete the control of the quay crane.
[0087] Before implementing the remote control operation of the quay crane control method described in the first embodiment, it is necessary to check whether the system meets the conditions for implementing the method. For example, on the touch screen of the console, select the first quay crane and the second quay crane for remote control merging, and then select the 1 control 2 operation mode; the console controller determines whether the two quay cranes are in remote control automatic operation conditions based on the configuration information of the quay crane controller, such as checking that the communication of their respective automation subsystems is normal and fault-free. When the quay crane subsystems and equipment meet the requirements of remote control operations, the initial settings of each quay crane before operation are performed through the touch screen, including setting the ship side ranking information, the order of loading and unloading operations, the initial safety height of the operation, the selection of the container truck lane, etc. After the settings are completed, the inspection work is completed, and the quay crane control method described in the first embodiment can be implemented.
[0088] Optionally, an emergency stop button may be added to the layout of the operating console to cooperate with the operating method to issue the intervention operation instruction described in the method embodiment part.
[0089] Optionally, the automation controllers of the first quay crane and the second quay crane are communicatively connected with the controller of the operating console to form a control network of the quay crane control system; the first quay crane and the second quay crane are communicatively connected with the operating console through a server to form an information flow network of the quay crane control system.
[0090] Figure 5 This is an example of the quay crane operating system described in the embodiment. An operating console is networked with two quay cranes. The network structure of the entire system is divided into a control network and an information flow network, wherein the control network can use an industrial network configuration (such as profinet or profibus), and the automation controllers (ACCS) of the two quay cranes are connected to the controller (RCS) of the operating console (ROS); the information flow network can use Ethernet to interact with the central control core server for data (such as audio, video and other information flow data).
[0091] The fourth embodiment of the present application also provides an electronic device, see Figure 6 As shown, the device includes:
[0092] Memory 600 and processor 610;
[0093] The memory 600 is connected to the processor 610 and is used to store programs;
[0094] The processor 610 is used to implement the quay crane control method disclosed in any of the above embodiments by running the program stored in the memory 600.
[0095] Specifically, the electronic device may further include: a bus, a communication interface 620 , an input device 630 and an output device 640 .
[0096] The processor 610, the memory 600, the communication interface 620, the input device 630 and the output device 640 are connected to each other via a bus.
[0097] A bus may include a pathway that transfers information between components of a computer system.
[0098] The processor 610 may be a general-purpose processor, such as a general-purpose central processing unit (CPU), a microprocessor, etc., or an application-specific integrated circuit (ASIC), or one or more integrated circuits for controlling the execution of the program of the scheme of the present invention. It may also be a digital signal processor (DSP), an application-specific integrated circuit (ASIC), a field programmable gate array (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components.
[0099] The processor 610 may include a main processor, and may also include a baseband chip, a modem, and the like.
[0100] The memory 600 stores a program for executing the technical solution of the present invention, and may also store an operating system and other key services. Specifically, the program may include a program code, and the program code includes a computer operation instruction. More specifically, the memory 600 may include a read-only memory (ROM), other types of static storage devices that can store static information and instructions, a random access memory (RAM), other types of dynamic storage devices that can store information and instructions, a disk storage, a flash, and the like.
[0101] The input device 630 may include a device for receiving data and information input by a user, such as a keyboard, a mouse, a camera, a scanner, a light pen, a voice input device, a touch screen, a pedometer, or a gravity sensor.
[0102] Output device 640 may include a device that allows information to be output to a user, such as a display screen, printer, speaker, etc.
[0103] The communication interface 620 may include any transceiver or the like to communicate with other devices or communication networks, such as Ethernet, a radio access network (RAN), a wireless local area network (WLAN), etc.
[0104] The processor 610 executes the program stored in the memory 600 and calls other devices, which can be used to implement each step of any quay crane control method provided in the above embodiments of the present application.
[0105] For the aforementioned method embodiments, for the sake of simplicity, they are all described as a series of action combinations, but those skilled in the art should be aware that the present application is not limited by the order of the actions described, because according to the present application, some steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required by the present application.
[0106] It should be noted that each embodiment in this specification is described in a progressive manner, and each embodiment focuses on the differences from other embodiments, and the same or similar parts between the embodiments can be referred to each other. For the device embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment.
[0107] The steps in the methods of each embodiment of the present application can be adjusted in sequence, combined and deleted according to actual needs, and the technical features recorded in each embodiment can be replaced or combined.
[0108] The modules and sub-modules in the devices and terminals of the various embodiments of the present application can be combined, divided and deleted according to actual needs.
[0109] In the several embodiments provided in the present application, it should be understood that the disclosed terminals, devices and methods can be implemented in other ways. For example, the terminal embodiments described above are only schematic, for example, the division of modules or submodules is only a logical function division, and there may be other division methods in actual implementation, for example, multiple submodules or modules can be combined or integrated into another module, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be an indirect coupling or communication connection through some interfaces, devices or modules, which can be electrical, mechanical or other forms.
[0110] The modules or submodules described as separate components may or may not be physically separated, and the components of the modules or submodules may or may not be physical modules or submodules, that is, they may be located in one place, or they may be distributed on multiple network modules or submodules. Some or all of the modules or submodules may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0111] In addition, each functional module or submodule in each embodiment of the present application may be integrated into one processing module, or each module or submodule may exist physically separately, or two or more modules or submodules may be integrated into one module. The above-mentioned integrated modules or submodules may be implemented in the form of hardware or in the form of software functional modules or submodules.
[0112] Professionals may further appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, computer software, or a combination of the two. In order to clearly illustrate the interchangeability of hardware and software, the composition and steps of each example have been generally described in the above description according to function. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professionals and technicians may use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.
[0113] The steps of the method or algorithm described in conjunction with the embodiments disclosed herein may be implemented directly by hardware, software units executed by a processor, or a combination of the two. The software units may be placed in a random access memory (RAM), a memory, a read-only memory (ROM), an electrically programmable ROM, an electrically erasable programmable ROM, a register, a hard disk, a removable disk, a CD-ROM, or any other form of storage medium known in the art.
[0114] Finally, it should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.
[0115] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A quay crane control method, characterized in that: Applied to an operating platform, the operating platform is communicatively connected to a quay crane, the quay crane includes a first quay crane and a second quay crane, the method includes: When receiving a manual operation instruction, the control mode of the quay crane is switched from the monitoring mode to the manual operation mode and the manually operated quay crane is instructed to switch the working state from the automatic working state to the manual operation state, wherein the manual operation instruction includes selecting one of the first quay crane and the second quay crane as the manually operated quay crane, the manual operation mode is used to receive the operation instruction input by the operator to manually control the manually operated quay crane, and the monitoring mode is used to display the working information of the first quay crane and the second quay crane; When an automatic working instruction is received, the control mode of the quay crane is switched from the manual operation mode to the monitoring mode and the manually operated quay crane is instructed to switch the working state from the manual operation state to the automatic working state.
2. The quay crane control method according to claim 1, characterized in that: The manual operation instructions include active intervention operation instructions and passive intervention operation instructions; When receiving the manual operation instruction, switching the control mode of the quay crane from the monitoring mode to the manual operation mode and instructing the manually operated quay crane to switch the working state from the automatic working state to the manual operation state comprises: When receiving the active intervention operation instruction, the control mode of the quay crane is switched from the monitoring mode to the manual operation mode and the manually operated quay crane is instructed to forcibly stop the ongoing loading and unloading work, forcibly end the automatic working state and switch to the manual operation state; or, When the passive intervention operation instruction for responding to a manual operation request is received, the control mode of the quay crane is switched from the monitoring mode to the manual operation mode and the manually operated quay crane is instructed to switch from the automatic working state to the manual operation state. The manual operation request is used to request manual control from the operator when the loading and unloading work enters the sea side working stage.
3. The quay crane control method according to claim 2, characterized in that: The method further comprises: When a quick intervention operation instruction is received in the manual operation mode, the control mode of the quay crane is maintained in the manual operation mode, and the manual operation quay crane selected in the passive intervention operation instruction is instructed to switch the working state from the automatic working state to the manual operation state.
4. The quay crane control method according to claim 3, characterized in that: The method further comprises: When an intervention operation instruction is received, adding the manually operated quay crane selected in the intervention operation instruction to a manual operation request queue, wherein the intervention operation instruction is the active intervention operation instruction, the passive intervention operation instruction or the quick intervention operation instruction; When the manually operated quay crane selected in the intervention operation instruction is at the head of the manual operation request queue, the control mode of the quay crane is placed in the manual operation mode and the manually operated quay crane selected in the intervention operation instruction is instructed to switch the working state from the automatic working state to the manual operation state.
5. The quay crane control method according to claim 2, characterized in that: After the manual operation gantry crane is instructed to forcibly stop the ongoing loading and unloading work, forcibly end the automatic working state and switch to the manual operation state upon receiving the active intervention operation instruction, the method further includes: When the automatic work instruction is received, obtaining the interrupted work that is forcibly stopped by the active intervention operation instruction; The manually operated quay crane is instructed to start with the next stage of the interrupted work in the loading and unloading operation process, and the working state is switched from the manual operation state to the automatic working state.
6. The quay crane control method according to claim 1, characterized in that: The method further comprises: In the monitoring mode, setting the display area for displaying the working information of the first quay crane equal to the display area for displaying the working information of the second quay crane; In the manual operation mode, a display area for displaying the working information of the manually operated quay crane is set to be larger than a display area for displaying the working information of quay cranes other than the manually operated quay crane.
7. The quay crane control method according to claim 4, characterized in that: Receive intervention instructions, including: When it is detected that the lifting operating handle deviates to the left or right, and the deviation angle is greater than the preset angle, and the deviation time is greater than the preset time, the intervention operation instruction is received.
8. A quay crane control system, characterized in that: include: A quay crane and an operating platform, wherein the operating platform is communicatively connected with the quay crane, and the quay crane comprises a first quay crane and a second quay crane; The operating console is used to switch the control mode of the quay crane from the monitoring mode to the manual operation mode and instruct the manually operated quay crane to switch the working state from the automatic working state to the manual operation state when receiving a manual operation instruction. The manual operation instruction includes selecting one between the first quay crane and the second quay crane as the manually operated quay crane. The manual operation mode is used to receive the operation instructions input by the operator to manually control the manually operated quay crane. The monitoring mode is used to display the working information of the first quay crane and the second quay crane. When an automatic working instruction is received, the control mode of the quay crane is switched from the manual operation mode to the monitoring mode and the manually operated quay crane is instructing to switch the working state from the manual operation state to the automatic working state.
9. The quay crane control system according to claim 8, characterized in that: The automation controllers of the first quay crane and the second quay crane are communicatively connected with the controller of the operating console to form a control network of the quay crane control system; The first quay crane and the second quay crane are connected to the operating console through server communication, forming an information flow network of the quay crane control system.
10. An electronic device, characterized in that: including memory and processor; The memory is connected to the processor and is used to store programs; The processor is used to implement the quay crane control method as described in any one of claims 1 to 7 by running the program in the memory.