Prefabricating and assembling method of integrated system function module

By using modular design and prioritizing relationships, the problem of low design and construction efficiency in prefabricated buildings is solved, realizing a modular prefabrication method for building construction that is efficient in construction and easy to adjust.

CN118979637APending Publication Date: 2024-11-19WUXI INDAL EQUIP INSTALLATION
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411181029.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-27
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

The lack of reasonable primary and secondary classification and modularization in existing prefabricated building structures leads to poor design efficiency, product reliability and construction efficiency.

Method used

The prefabrication and assembly method of integrated system functional modules is adopted. Through modular design, the building model is divided into building support modules, wall modules, decoration modules, ventilation modules, water supply modules and electromechanical modules. The modules are prefabricated and assembled according to their primary and secondary relationships to ensure the independence and connection accuracy between the modules.

Benefits of technology

Shorten construction time, improve construction efficiency, facilitate individual module adjustments and later repairs, and enhance design quality and reliability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979637A_ABST
    Figure CN118979637A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of building structures, and particularly relates to an integrated system function module prefabricating and assembling method which comprises the following steps: step 1, determining a building style, selecting a proper building scheme according to a building type, and constructing an overall model of a building; 2, according to the function of a building structure, modular division is conducted on the building model, and the building model comprises a building supporting module, a building wall module, a building decoration module, a building ventilation module, a building water supply module and a building electromechanical module; step 3, selecting required building modules, determining primary and secondary relations between the modules, taking the primary module as a support carrier, and assembling the secondary module on the primary module; 4, assembling according to the primary and secondary assembling relation; the integrated modular design is adopted, the modules are independent of one another and can be assembled, the construction time is shortened, the use efficiency is improved, meanwhile, the modules can be independently adjusted conveniently, fault tolerance is high, and later repair is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building structures, in particular to a prefabrication and assembly method of an integrated system functional module. Background Art

[0002] Building structure refers to a system composed of various components (roof trusses, beams, slabs, columns, etc.) in a building that can withstand various effects. The so-called effects refer to various factors that can cause the system to produce internal forces and deformations, such as loads, earthquakes, temperature changes, and foundation settlement.

[0003] The building structure is a skeleton structure formed by building components such as slabs, beams, columns, walls, and foundations, which has certain spatial functions and can safely withstand various normal loads of the building.

[0004] The plate is a planar component that directly bears the load in the building structure. It has a large plane size but a relatively small thickness. It is a bending component that transfers the load to the beam or wall through the plate. The beam generally refers to a linear component that bears the load perpendicular to its longitudinal axis. It is a supporting component between the plate and the column. It is a bending component that bears the load from the plate and transfers it to the column.

[0005] Prefabricated buildings refer to buildings that transfer a large amount of on-site work in traditional construction methods to factories, where building components and accessories (such as floor slabs, wall panels, stairs, balconies, etc.) are processed and manufactured in the factory, transported to the construction site, and assembled and installed on site through reliable connection methods.

[0006] At present, prefabricated building structures are divided into fully prefabricated concrete structures and prefabricated monolithic concrete structures. The main difference lies in the different prefabricated parts of the prefabricated components. Fully prefabricated structures refer to all structural components being produced in factories, while prefabricated monolithic structures refer to some structural components being produced in factories and then transported to the site and connected to the main vertical load-bearing components through overlapping layers or cast-in-place to form a whole.

[0007] Regardless of whether it is a fully prefabricated assembled concrete structure or a prefabricated assembled integral concrete structure, there is no reasonable primary and secondary division and modular classification between the structures, and the design efficiency, product reliability and design quality are poor, which affects the construction efficiency. For this reason, the present application proposes a prefabrication and assembly method of an integrated system functional module. Summary of the invention

[0008] The purpose of this section is to summarize some aspects of the embodiments of the present invention and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the specification abstract and the invention title of this application to avoid blurring the purpose of this section, the specification abstract and the invention title, and such simplifications or omissions cannot be used to limit the scope of the present invention.

[0009] In view of the above problems and / or problems existing in existing building structures, the present invention is proposed.

[0010] Therefore, the purpose of the present invention is to provide a prefabrication and assembly method for integrated system functional modules. After the design is completed, the modules required for the building are prefabricated, the prefabricated modules are transported to the construction site, and assembled according to the primary and secondary relationship. An integrated modular design is adopted, and each module is independent of each other and can be assembled, thereby shortening the construction time and improving the utilization efficiency. At the same time, it is easy to adjust the modules individually, with high fault tolerance and convenient for later repairs.

[0011] To solve the above technical problems, according to one aspect of the present invention, the present invention provides the following technical solutions:

[0012] A prefabrication and assembly method of an integrated system functional module, comprising the following steps:

[0013] Step 1: Determine the architectural style, select the appropriate architectural plan according to the building type, and construct the overall model of the building;

[0014] Step 2: According to the function of the building structure, the building model is modularized, including building support module, building wall module, building decoration module, building ventilation module, building water supply module and building mechanical and electrical module;

[0015] Step 3: Select the required building modules, establish the primary and secondary relationships between the modules, use the primary module as a support carrier, and assemble the secondary module on the primary module;

[0016] Step 4: Design the connection structure between modules according to the primary and secondary assembly relationship, so that the secondary module can be assembled on the primary module through a suitable connection structure;

[0017] Step 5: Prefabricate the modules required for the building, and reserve connection spaces and connection structures in the modules;

[0018] Step 6: Transport the prefabricated modules to the construction site, assemble them according to the primary and secondary relationships, and connect them on site during assembly.

[0019] As a preferred solution of the prefabrication and assembly method of an integrated system functional module described in the present invention, wherein: in the step 1, the architectural styles are divided into neoclassicism, modernism, exotic style, ordinary style and theme style.

[0020] As a preferred solution of the prefabrication and assembly method of an integrated system functional module described in the present invention, wherein: in the step one, the building model is constructed using D software. During the construction, the structures are independent of each other to facilitate the modular division of the building in the later stage.

[0021] As a preferred scheme of the prefabricated assembly method of an integrated system functional module described in the present invention, wherein: in the step 2, the building support module is the column and the beam, the building wall module is the side wall, the building decoration module is the carving and the wall panel, the building ventilation module is the door and window, the building water flow module is the drainage pipe, and the building electromechanical module is the mechanical circuit.

[0022] As a preferred scheme of the prefabricated assembly method of an integrated system functional module described in the present invention, wherein: in the step three, the building support module is the main module, and the building wall module is the secondary module; the building wall module is the main module, and the building decoration module and the building ventilation module are listed as secondary modules.

[0023] As a preferred scheme of the prefabricated assembly method of an integrated system functional module described in the present invention, wherein: in the step four, according to the different types of the primary module and the secondary module, the connection method is also different, a masonry groove is left between the building wall module and the building support module, a buckle groove is left between the building wall module and the building decoration module, and a pipe groove is left between the building wall module and the building ventilation module, the building water supply module and the building electromechanical module.

[0024] As a preferred solution of the prefabrication and assembly method of an integrated system functional module described in the present invention, wherein: in the step five, during prefabrication, the connection accuracy between the structures is guaranteed, and the connection space is the assembly operation space for the connectors to connect the corresponding primary and secondary modules.

[0025] As a preferred solution of the prefabricated assembly method of an integrated system functional module described in the present invention, in the step six, the on-site connection is mainly cast, including masonry, drilling, patching and embedding, to complete the connection between the modular structures.

[0026] Compared with the prior art: the present invention divides the building model into modules according to the function of the building structure, establishes the primary and secondary relationship between the modules according to the required building modules, and designs the connection structure between the modules according to the primary and secondary assembly relationship. After the design is completed, the modules required for the building are prefabricated, and the prefabricated modules are transported to the construction site and assembled according to the primary and secondary relationship. An integrated modular design is adopted, and each module is independent of each other and can be assembled, thereby shortening the construction time and improving the utilization efficiency. At the same time, it is easy to adjust the modules individually, with high fault tolerance and convenient for later repair. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the present invention will be described in detail below in combination with the accompanying drawings and detailed embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative labor. Among them:

[0028] Figure 1 It is a schematic diagram of the step flow structure of the present invention. DETAILED DESCRIPTION

[0029] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific embodiments of the present invention are described in detail below with reference to the accompanying drawings.

[0030] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0031] Secondly, the present invention is described in detail with reference to schematic diagrams. When describing the embodiments of the present invention in detail, for the sake of convenience, the cross-sectional diagrams showing the device structure will not be partially enlarged according to the general scale, and the schematic diagrams are only examples, which should not limit the scope of protection of the present invention. In addition, in actual production, the three-dimensional dimensions of length, width and depth should be included.

[0032] In order to make the objectives, technical solutions and advantages of the present invention more clear, the embodiments of the present invention will be further described in detail below with reference to the accompanying drawings.

[0033] The present invention provides a prefabrication and assembly method for integrated system functional modules. After the design is completed, the modules required for the building are prefabricated, and the prefabricated modules are transported to the construction site and assembled according to the primary and secondary relationship. The integrated modular design is adopted, and each module is independent of each other and can be assembled, which shortens the construction time and improves the use efficiency. At the same time, it is easy to adjust the modules individually, has high fault tolerance, and is easy to repair later. Please refer to Figure 1 , comprising the following method steps:

[0034] Step 1: Determine the architectural style, select the appropriate architectural plan according to the building type, and construct the overall model of the building;

[0035] In step 1, architectural styles are divided into neoclassicism, modernism, exotic style, common style and theme style. Architectural style refers to the characteristics reflected in the content and appearance of architectural design, mainly in the originality and perfect artistic conception shown in the plane layout, form composition, artistic treatment and technique application of the building. Architectural styles vary due to the constraints of the times' politics, society, economy, building materials and construction technology, as well as the influence of architectural design ideas, viewpoints and artistic accomplishment. Ancient palace buildings have rigorous and symmetrical planes, clear primary and secondary, brick walls and wooden beams, flying eaves, brackets, caissons and carved beams and painted buildings, forming a unique Chinese architectural style;

[0036] In step 1, the building model is constructed using 3D software. During construction, the structures are independent of each other, which allows for modular division of the building later.

[0037] Step 2: According to the function of the building structure, the building model is modularized, including building support module, building wall module, building decoration module, building ventilation module, building water supply module and building mechanical and electrical module;

[0038] In step two, the building support module is the column and the beam, the building wall module is the side wall, the building decoration module is the carving and the wall panel, the building ventilation module is the door and window, the building water supply module is the drainage pipe, and the building electromechanical module is the mechanical circuit. In the building, the building support module is used as the skeleton, and the building wall module is set on the basis of the building support module to divide the building space. The inside and outside of the space are decorated and beautified by the building decoration module. The building ventilation module, the building water supply module and the building electromechanical module are the pipelines required for daily use, and the assembly space (wall inner pipe) is reserved to facilitate the later installation.

[0039] Step 3: Select the required building modules, establish the primary and secondary relationships between the modules, use the primary module as a support carrier, and assemble the secondary module on the primary module;

[0040] In step three, if the building support module is the primary module, then the building wall module is the secondary module. If the building wall module is the primary module, then the building decoration module and the building ventilation module are listed as secondary modules. The primary and secondary relationship is only a simple bearing relationship. For example, if B is installed on A, then A is the primary module, used to bear B, and B is the secondary module. In a building, different secondary modules can be installed on the same primary module.

[0041] Step 4: Design the connection structure between modules according to the primary and secondary assembly relationship, so that the secondary module can be assembled on the primary module through a suitable connection structure;

[0042] In step 4, according to the different types of primary modules and secondary modules, the connection methods are also different. A masonry groove is left between the building wall module and the building support module, a buckle groove is left between the building wall module and the building decoration module, and a pipe groove is left between the building wall module and the building ventilation module, the building water supply module and the building electromechanical module;

[0043] Step 5: Prefabricate the modules required for the building, and reserve connection spaces and connection structures in the modules;

[0044] In step 5, during prefabrication, the connection accuracy between the structures is ensured, and the connection space is the assembly operation space for the connectors to connect the corresponding primary and secondary modules;

[0045] Step 6: Transport the prefabricated modules to the construction site, assemble them according to the primary and secondary relationships, and connect them on site during assembly.

[0046] In step six, on-site connection is mainly based on casting, including masonry, drilling, patching and embedding, to complete the connection between modular structures.

[0047] During specific use, the prefabricated structure is designed according to steps 1 to 6 above, the designed modules are standardized and prefabricated in batches, and then modularized according to functionality. After the differentiation, they are transported to the site and assembled in batches according to the primary and secondary relationships. An integrated modular design is adopted, and each module is independent of each other but can be assembled, which shortens the construction time and improves the efficiency of use. At the same time, it is easy to adjust the modules individually, has a high fault tolerance, and is convenient for later repairs.

[0048] Although the present invention has been described above with reference to the embodiments, various modifications may be made thereto and parts thereof may be replaced by equivalents without departing from the scope of the present invention. In particular, as long as there is no structural conflict, the various features in the embodiments disclosed in the present invention may be used in combination with each other in any manner, and the fact that these combinations are not exhaustively described in this specification is only for the sake of omitting space and saving resources. Therefore, the present invention is not limited to the specific embodiments disclosed herein, but includes all technical solutions falling within the scope of the claims.

Claims

1. A prefabrication and assembly method for an integrated system functional module, characterized in that: The method comprises the following steps: Step 1: Determine the architectural style, select the appropriate architectural plan according to the building type, and construct the overall model of the building; Step 2: According to the function of the building structure, the building model is modularized, including building support module, building wall module, building decoration module, building ventilation module, building water supply module and building mechanical and electrical module; Step 3: Select the required building modules, establish the primary and secondary relationships between the modules, use the primary module as a support carrier, and assemble the secondary module on the primary module; Step 4: Design the connection structure between modules according to the primary and secondary assembly relationship, so that the secondary module can be assembled on the primary module through a suitable connection structure; Step 5: Prefabricate the modules required for the building, and reserve connection spaces and connection structures in the modules; Step 6: Transport the prefabricated modules to the construction site, assemble them according to the primary and secondary relationships, and connect them on site during assembly.

2. The prefabrication and assembly method of an integrated system functional module according to claim 1, characterized in that: In the step 1, the architectural styles are divided into neoclassicism, modernism, exotic style, ordinary style and theme style.

3. The prefabrication and assembly method of an integrated system functional module according to claim 1, characterized in that: In the step 1, a building model is constructed using 3D software. During construction, the structures are independent of each other, so that the building can be modularized later.

4. The prefabrication and assembly method of an integrated system functional module according to claim 1, characterized in that: In the step 2, the building support module is the columns and beams, the building wall module is the side walls, the building decoration module is the carvings and wall panels, the building ventilation module is the doors and windows, the building water flow module is the drainage pipes, and the building electromechanical module is the mechanical circuit.

5. The prefabrication and assembly method of an integrated system functional module according to claim 1, characterized in that: In the step three, the building support module is the primary module, and the building wall module is the secondary module. The building wall module is the primary module, and the building decoration module and the building ventilation module are listed as secondary modules.

6. The prefabrication and assembly method of an integrated system functional module according to claim 1, characterized in that: In the step 4, according to the different types of the primary module and the secondary module, the connection method is also different. A masonry groove is left between the building wall module and the building support module, a buckle groove is left between the building wall module and the building decoration module, and a pipe groove is left between the building wall module and the building ventilation module, the building water supply module and the building mechanical and electrical module.

7. The prefabrication and assembly method of an integrated system functional module according to claim 1, characterized in that: In the step 5, during prefabrication, the connection accuracy between the structures is ensured, and the connection space is an assembly operation space for the connectors to connect the corresponding primary and secondary modules.

8. The prefabrication and assembly method of an integrated system functional module according to claim 1, characterized in that: In step six, the on-site connection is mainly based on casting, including masonry, drilling, patching and embedding, to complete the connection between the modular structures.