Steel support and anchor cable combined advance support method for unstable ore rock roadway

By using a joint support method of steel brackets, anchor rods and anchor cables in mine tunnels, combined with the interlaced layout of steel rails, the complex and cost-effective construction of unstable ore rock tunnels is solved, and efficient and economical support effect is achieved , suitable for the needs of mining lanes with short service time.

CN118979772APending Publication Date: 2024-11-19河北钢铁集团沙河中关铁矿有限公司 +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410950884.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-16
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

When facing unstable ore rocks, the existing mine tunnel support methods are complex in construction, high in cost and cannot achieve advanced pre-support, making it difficult to meet the short service time requirements.

Method used

The joint support method of steel brackets, anchor rods and anchor cables is adopted. By erecting steel brackets at the front end of the tunnel, arranging anchor rods and anchor cables, and laying rails horizontally during the excavation process, an interlaced arrangement is formed to provide stable support.

Benefits of technology

Advanced support of unstable mineral rock tunnels with high construction efficiency, low cost and good support effect is achieved, ensuring tunnel safety and improving construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979772A_ABST
    Figure CN118979772A_ABST
Patent Text Reader

Abstract

The invention discloses an unstable ore rock roadway steel support and anchor cable combined advance support method which comprises the following steps: (1) tunneling a roadway in unstable ore rock, and erecting a steel support at the front end of the tunneling roadway before tunneling of the roadway at each footage; (2) arranging anchor rods at the outline boundary of the top plate at the front end of the roadway at each footage, and arranging anchor cables at the outline boundary of the top plate at the front end of the roadway at each footage or at intervals of a plurality of footage; the length directions of the anchor cables and the anchor rods are consistent with the tunneling direction of a roadway or obliquely extend upwards and forwards; (3) horizontally arranging a steel rail on a cross beam of the steel bracket along the tunneling direction of the roadway after the tunneling blasting of the current footage roadway is finished; and (4) the steps (1)-(3) are repeated, and the subsequent steel supports abut against the lower portions of the steel rails arranged on the previous steel supports till roadway tunneling construction is completed. By means of the method, the tunneling roadway can be effectively supported, the safety of the working environment of personnel can be guaranteed, and the method has the advantages of being low in economic cost, high in construction efficiency and good in supporting effect.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of mining, in particular to a method for combining steel support and anchor cable advance support in unstable rock tunnels. Background Art

[0002] In recent years, there are many methods for supporting mine tunnels. For medium-stable and above mine rocks, anchor support or shotcrete support is often used. For unstable mine rocks, anchor + anchor cable combined support or anchor + anchor cable + shotcrete combined support is often used. For extremely unstable mine rocks, steel arch support or pipe support + shotcrete support is often used. The stability of the mine rock is not only related to the size of the exposed area, but also to the length of the exposure time. The above support methods are all aimed at supporting the exposed mine rock, but lack advanced pre-support. At present, advanced support methods such as freezing method, grouting method and pre-lining method are often used in tunnel excavation, but these methods have relatively complex construction procedures and high costs. They are mainly used to support tunnels with a long service life. For mines, the service time of some mine rock tunnels is relatively short, and the requirements for the effective action time of the support are not high. Therefore, it is necessary to study a support method with high construction efficiency, low economic cost and moderate service time for the support of unstable rock tunnels in metal mines, which can not only ensure the safety of the tunnels within their service life, but also improve efficiency and reduce costs. Summary of the invention

[0003] The technical problem to be solved by the present invention is to provide a method for combining steel support anchor cables with advanced support in unstable mine rock tunnels which is easy to construct and has good support effect.

[0004] In order to solve the above technical problems, the technical solution adopted by the present invention includes the following steps: (1) When excavating a tunnel in unstable rock, a steel support is set up at the front end of the tunnel before each advance; (2) Anchor rods are arranged at the roof contour boundary of the front end of each tunnel advance, and anchor cables are arranged at the roof contour boundary of the front end of each tunnel advance or at intervals of several tunnel advances; the length direction of the anchor cables and anchor rods is consistent with the tunnel excavation direction or extends obliquely upward and forward; (3) After the current tunnel excavation blasting is completed, the rails are arranged horizontally along the tunnel excavation direction; (4) Repeat steps (1) to (3), with the subsequent steel supports resting on the lower part of the rails arranged by the previous steel supports until the tunnel excavation construction is completed.

[0005] Furthermore, in step (2), at least two anchor cables and at least two anchor rods are arranged; when the anchor rods and anchor cables are arranged at the same top plate contour boundary, the anchor rods and anchor cables are arranged alternately.

[0006] Furthermore, in the step (2), anchor cables are arranged at the top plate contour boundary at the front end of every 1 to 3 advances of the tunnel.

[0007] Furthermore, in step (1), the steel support is 0.3m to 0.5m away from the end face of the tunnel excavation.

[0008] Furthermore, in step (3), the front end of the rail is 0.2m to 0.3m away from the end face of the tunnel excavation.

[0009] Furthermore, in step (3), a plurality of rails are arranged.

[0010] Furthermore, the horizontal spacing between the rails is 0.3m to 0.8m.

[0011] Furthermore, in step (2), the angle between the anchor cable and the excavation horizontal plane is 5° to 8°, and the angle between the anchor rod and the excavation horizontal plane is 3° to 5°.

[0012] The beneficial effect of adopting the above technical solution is that the present invention can effectively support the excavation tunnel through the combined support of steel supports, anchor rods and anchor cables, and through the setting of steel rails, which can not only ensure the safety of the working environment of personnel, but also has the characteristics of low economic cost, high construction efficiency and good support effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0014] Figure 1 It is a schematic diagram of the structure of the present invention; Figure 2 yes Figure 1 A-A section in the figure; Figure 3 yes Figure 1 The B-B section in FIG. Figure 4 yes Figure 1 C-C section diagram in .

[0015] In the figure: steel support 1, wooden pad 2, steel rail 3, anchor cable 4, anchor rod 5. DETAILED DESCRIPTION

[0016] Figure 1-4 As shown, the method for combining steel support anchor cable and advance support for unstable rock tunnels includes the following steps: (1) The cross-sectional width of the tunnel is 2.5m to 3.0m, and the cross-sectional height of the tunnel is 2.5m to 3.0m; when excavating the tunnel in unstable ore and rock, the advance is 2.0m to 2.2m each time; before each advance of the tunnel, a steel support 1 is set up at the front end of the tunnel; the steel support 1 is 0.3m to 0.5m away from the end face of the tunnel; the steel support 1 is composed of waste rails, including columns on both sides and a beam fixed on the top of the two columns, the columns and the beam are connected by bolts and connecting plates, and a wooden pad 2 is set at the bottom of the column, the wooden pad 2 is 20cm to 25cm long, 20cm to 25cm wide, and 5cm to 8cm high. In this way, during the forward excavation process, a steel support 1 is set up at the front end of each advance, and the steel support of the next advance is located at the front end of the steel support of the current advance.

[0017] (2) Anchor rods 5 are arranged at the top contour boundary of each tunnel with each footage, and the ends of the anchor rods are located at the junction of the excavation end face and the top plate. It is best to arrange at least two anchor rods 5 at each top contour boundary, with the anchor rod spacing of 0.3m to 0.5m and the anchor rod length of 1.8m to 2.5m; anchor cables 4 are arranged at the top contour boundary of each tunnel with each footage or several footages, preferably at the top contour boundary of each tunnel with 1 to 3 footages, and the ends of the anchor cables are located at the junction of the excavation end face and the top plate. It is best to arrange one top contour boundary. At least two anchor cables 4 are arranged, with an anchor cable spacing of 1.0m to 1.2m and an anchor cable length of 6.0 to 8.0m; the length direction of the anchor cables 4 and anchor rods 5 is consistent with the tunnel excavation direction or extends obliquely upward and forward, preferably, the anchor cables 4 are 5° to 8° to the excavation horizontal plane, and the anchor rods 5 are 3° to 5° to the excavation horizontal plane; when the anchor cables 4 and anchor rods 5 are arranged at the top plate contour boundary at the same time, the anchor rods 5 and the anchor cables 4 are staggered, preferably 6 to 8 anchor rods are arranged, evenly distributed on the top of the tunnel, staggered with the anchor cables, and 2 to 3 anchor rods are arranged between every two anchor cables.

[0018] (3) After the blasting of the current advance tunnel is completed, the rail 3 is horizontally arranged at the lower part of the crossbeam of the steel support 1 along the tunnel excavation direction; the front end of the rail 3 is 0.2m to 0.3m away from the tunnel excavation end face and is placed on the crossbeam of the subsequent advance steel support 1; the rear end of the rail 3 is placed below the crossbeam of the current advance steel support and extends backward beyond the steel support by 0.3m to 0.5m; the length of the rail is 4.0m to 4.5m, and a plurality of rails 3 are arranged, with a horizontal spacing of 0.3m to 0.8m between the rails 3. After adopting such a structure, the rail 3 is erected between two steel supports of adjacent advancements, the rear end of the rail 3 is placed below the crossbeam of the steel support of the current advancement, the front end of the rail 3 is placed above the crossbeam of the steel support 1 of the next advancement, the middle and front ends of the rail 3 are erected on the upper part of the crossbeam of the front end steel support (i.e. the steel support of the next advancement), and the front end of the rail 3 is placed under the rock mass. The deformation of the rock mass will have a downward compression effect on the rail. In this way, the front end of the rail 3 and the front end steel support form a "seesaw" form, so that the rail that exceeds the front end steel support has the function of controlling the top plate of the excavation section, and the rear end of the rail 3 will not sag to the ground due to being under the crossbeam of the steel support.

[0019] (4) Repeat steps (1) to (3), with the subsequent steel support 1 placed on the lower part of the steel rail (3) arranged on the previous steel support, that is, the front end of the steel rail 3 is placed above the crossbeam of the front steel support 1, and the rear end is placed below the crossbeam of the rear steel support; repeat the construction until the tunnel excavation construction is completed.

[0020] Embodiment: The steel support anchor cable combined advance support method for unstable mine rock tunnel is specifically described as follows.

[0021] (1) A tunnel is excavated in unstable ore rock, with a tunnel cross-section width of 3.0 m and a tunnel cross-section height of 3.0 m. Before the first tunnel excavation, a set of steel supports 1 is erected at a position 0.4 m away from the end of the tunnel. The steel supports are composed of waste rails, including columns and beams. The column rails and the beam rails are connected by bolts and connecting plates. The bottom of the column rails is a wooden pad 2, which is 25 cm long, 25 cm wide and 5 cm high.

[0022] (2) After the first tunnel excavation blasting is completed, the rail 3 is quickly inserted under the crossbeam of the steel support 1. The front end of the rail is 0.3m away from the tunnel excavation end face, and the rear end of the rail 3 is placed under the crossbeam of the steel support 1, and the rear end protrudes 1.0m from the crossbeam; the rails are evenly and horizontally placed under the crossbeam of the steel support 1. The length of the first laid rail is 3.0m, and the horizontal spacing between the rails is 0.4m.

[0023] (3) After the rail frame 3 below the current advance steel support crossbeam is installed, another set of steel supports 1 is installed 0.4 m away from the tunnel excavation end face. The crossbeam of the steel support 1 contacts the rail 3 horizontally laid in step (2) and is placed below it. At the same time, anchor cables 4 and anchor rods 5 are arranged at the contour boundary of the top plate at the end of the tunnel. The anchor cables 4 and anchor rods 5 are arranged in a staggered manner. The length direction of the anchor cables 4 and anchor rods 5 is consistent with the tunnel excavation direction.

[0024] (4) In step (3), three anchor cables 4 are arranged, located in the middle and both sides of the tunnel top, with a spacing of 1.0 m and a length of 6.0 m. Anchor cables 4 are inclined upward, with an angle of 8° to the excavation horizontal plane, and the end of anchor cable 4 is located at the junction of the excavation end face and the top plate. Seven anchor rods 5 are arranged, evenly distributed on the tunnel top, staggered with anchor cables 4, with two and three anchor rods 5 arranged between two anchor cables 4, respectively. The spacing of anchor rods 5 is 0.3 m and the length of anchor rods 5 is 1.8 m. Anchor rods 5 are inclined upward, with an angle of 5° to the excavation horizontal plane, and the end of anchor rods 5 is located at the junction of the excavation end face and the top plate.

[0025] (5) After the first tunnel excavation support is completed, proceed to the next advance. After the blasting is completed, quickly lay the horizontal rail 3 under the crossbeam of the steel support 1 erected in step (3). The front end of the rail is 0.3m away from the tunnel excavation end face, the middle is placed above the crossbeam of the steel support 1 erected in step 3, and the rear end is placed under the crossbeam of the steel support 1 erected in step 1, and exceeds the crossbeam by 0.5m. At this time, the length of the laid rail 3 is 4.5m, and the horizontal spacing of the rail 3 is 0.4m. After the horizontal rail 3 is laid, step (3) is performed again, and the operation is repeated according to steps (3) and (5) until the construction is completed.

[0026] (6) Each time the tunnel excavation advances 2.0 m, the steel support 1 takes one advance as one working cycle, that is, each time the tunnel excavation advances 2.0 m, the steel support erection construction is carried out once; the anchor rod 5 construction takes one advance as one working cycle, that is, each time the tunnel excavation advances 2.0 m, the anchor rod support construction is carried out once; the anchor cable 4 construction takes three advances as one working cycle, that is, every time the tunnel excavation advances 3 feet, the anchor cable support construction is carried out once.

Claims

1. A method for combining steel support and anchor cable with advanced support in unstable mine rock tunnels. It is characterized in that The method comprises the following steps: (1) excavating a tunnel in unstable ore and rock, and setting up a steel support (1) at the front end of the tunnel before each advance of the tunnel; (2) Anchor rods (5) are arranged at the top contour boundary of the front end of each tunnel advance, and anchor cables (4) are arranged at the top contour boundary of the front end of each tunnel advance or at intervals of several tunnel advances; the length direction of the anchor cables (4) and anchor rods (5) is consistent with the tunnel excavation direction or extends obliquely upward and forward; (3) After the current tunnel excavation blasting is completed, the rails are arranged horizontally along the tunnel excavation direction (3); (4) Repeat steps (1) to (3), with the subsequent steel support (1) resting on the lower part of the steel rail (3) arranged by the previous steel support until the tunnel excavation construction is completed.

2. According to claim 1, a method for combining steel support and anchor cable advance support in unstable rock tunnels, Features: In the step (2), at least two anchor cables (4) are arranged, and at least two anchor rods (5) are arranged; when the anchor rods (5) and the anchor cables (4) are arranged at the same top plate contour boundary, the anchor rods (5) and the anchor cables (4) are arranged alternately.

3. A method for combining steel support and anchor cable advance support in unstable rock tunnels according to claim 1, Features: In the step (2), anchor cables (4) are arranged at the top plate contour boundary of the front end of each 1 to 3 advance lengths of the tunnel.

4. The method for combining steel support and anchor cable advance support in unstable rock tunnels according to claim 1, Features: In the step (1), the steel support (1) is 0.3 m to 0.5 m away from the tunnel excavation end face.

5. A method for combining steel support and anchor cable advance support in unstable rock tunnels according to claim 4, Features: In the step (3), the front end of the rail (3) is 0.2 m to 0.3 m away from the end face of the tunnel excavation.

6. A method for combining steel support and anchor cable advance support in unstable rock tunnels according to claim 1, Features: In the step (3), a plurality of rails (3) are arranged.

7. A method for combining steel support and anchor cable advance support in unstable rock tunnels according to claim 6, Features: The horizontal spacing of the steel rails (3) is 0.3 m to 0.8 m.

8. A method for combining steel support and anchor cable advance support in unstable rock tunnels according to any one of claims 1 to 7, Features: In the step (2), the anchor cable (4) is at an angle of 5° to 8° to the excavation horizontal plane, and the anchor rod (5) is at an angle of 3° to 5° to the excavation horizontal plane.