Roadbed lateral displacement monitoring method based on virtual datum line
By constructing virtual reference lines and precision total station measurements in highways, estimation of lateral displacement of the roadbed is solved, and the problems of low monitoring efficiency and difficult to ensure accuracy in the existing technology are achieved, efficient and accurate roadbed displacement monitoring is achieved, suitable for Highway and municipal engineering.
Patent Information
- Application Number
- CN202411082719.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-08
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2044-08-08
AI Technical Summary
The existing lateral displacement monitoring methods of roadbeds have problems such as low operating efficiency, difficulty in joint measurement of reference points, high risk of crossing the highway, long distance between monitoring sections, few measurement points, and long intervals in highways, making it difficult to ensure monitoring accuracy.
Using a monitoring method based on virtual reference line, the lateral displacement of the roadbed is calculated by constructing virtual reference line and precision total station measurement, which avoids dependence on known reference points and multi-test operation requirements, improves operation efficiency, and is applicable. Monitoring of horizontal displacement of foundation pit.
It significantly improves the operating efficiency and accuracy of monitoring, simplifies on-site operation, reduces errors, and is suitable for roadbed and foundation pit displacement monitoring in highways and municipal engineering.
Smart Images

Figure CN118980363A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to engineering monitoring technology, and in particular to a roadbed lateral displacement monitoring method based on a virtual reference line. Background Art
[0002] Highways, especially long and large highways, are inevitably faced with special sections such as high slopes, soft soil roadbeds, joint construction of roads and railways, and joint construction of river and roadbeds due to their long spans and complex and changeable terrain and geological conditions along the lines. The potential deformation risk of these sections is often large, which may cause wavy road surfaces, longitudinal cracking of the road surface, and even roadbed landslides and collapses, which seriously affect driving safety and the safety of people's lives and property. Therefore, during the construction and operation of highways, targeted roadbed monitoring is required for sections with higher risks. Roadbed monitoring often carries out multiple monitoring projects at the same time, among which a very important one is the monitoring of the lateral displacement of the roadbed, which is often used to judge the lateral safety status of the roadbed. The section spacing of the lateral displacement monitoring section of the roadbed is often set to 100m to 200m; each monitoring section is often set to 2 to 4 monitoring points; the monitoring frequency ranges from one week to one year; the operation period is often fully closed operation, etc. That is to say, the lateral displacement monitoring of highway roadbed often has many characteristics, such as long monitoring section, long distance between monitoring sections, few measuring points in the section, long monitoring interval, difficulty in joint measurement of benchmark points, and high risk of crossing the highway. At present, the lateral displacement monitoring of roadbed mainly adopts the method of combining GNSS static observation with total station traverse. This method requires the deployment of more working base points on the highway and joint measurement of known benchmark points through GNSS static observation. When the total station traverse is operated, multiple measurement operations must be strictly carried out, otherwise the accuracy will be difficult to guarantee, which greatly reduces the efficiency of this method.
[0003] Therefore, seeking a method for monitoring the lateral displacement of the roadbed with reliable accuracy and high efficiency has become a difficult problem that needs to be solved urgently by the majority of scientific and technological workers. Summary of the invention
[0004] The purpose of the present invention is to overcome the shortcomings of existing monitoring methods and propose a roadbed lateral displacement monitoring method based on a virtual reference line. The monitoring method is essentially a new method that constructs an accurate virtual reference line in a certain way and then calculates the lateral displacement of the roadbed according to the relative position relationship between the monitoring point and the virtual reference line plane. The method avoids the limitation of the existing method that the known reference point must be measured in conjunction before the monitoring operation can be carried out, and also avoids the requirement that the total station traverse method must perform multiple measurement operations, which greatly improves the operation efficiency, and the monitoring method is also suitable for the horizontal displacement monitoring of foundation pits.
[0005] A method for monitoring lateral displacement of roadbed based on a virtual reference line, comprising:
[0006] Step 1: Construct a rear-view aiming area and arrange monitoring points; determine a reference object outside the range of 3 times the width of the roadbed to be monitored on one side of the roadbed to be monitored, and set a straight line as a virtual reference line based on the principle that any point on a certain facade should be projected on the same straight line in an ideal state; and determine the first rear-view aiming area and the second rear-view aiming area on the plane facing the roadbed to be monitored;
[0007] Arrange multiple lateral displacement monitoring points on the cross section of the roadbed to be monitored;
[0008] Step 2: On-site measurement and storage: Set up a precision total station at a longitudinal distance of 20-50m from the lateral displacement monitoring point, and use the position of the central axis of the total station as the measuring station; use the free station setting without prism / reflector mode to measure and store any measuring point in the first rear-view aiming area, any measuring point in the second rear-view aiming area, and all lateral displacement monitoring points on the monitoring cross section in sequence, and measure and store the position data;
[0009] According to the measured and stored position data, the plan views of the measuring points of the first rear-view aiming area, the measuring points of the second rear-view aiming area and all the lateral displacement monitoring points are drawn using mapping software; the measuring points of the first rear-view aiming area and the measuring points of the second rear-view aiming area are connected to form a virtual reference line;
[0010] Draw a perpendicular line from each lateral displacement monitoring point to the virtual reference line through the mapping software, with the foot of the perpendicular being the corresponding virtual reference point, and obtain the perpendicular distance from each lateral displacement monitoring point to the virtual reference line through the distance measurement function;
[0011] Step 3: According to the preset monitoring frequency, perform step 2 at the same measuring station to obtain the vertical distance of each lateral displacement monitoring point. The vertical distance change can be obtained by subtracting the current vertical distance from the initial vertical distance. Since the vertical distance change is the projection of the lateral displacement of the roadbed on the vertical line from the lateral displacement monitoring point to the virtual baseline, the lateral displacement of the roadbed at each monitoring point can be calculated through the trigonometric relationship between the vertical distance change and the lateral displacement of the roadbed. Among them, the angle between the vertical line from the lateral displacement monitoring point to the virtual baseline and the roadbed edge line in the trigonometric relationship is a constant, which can be obtained by tools such as angle measuring tools.
[0012] Furthermore, in order to improve the reliability of the initial vertical distance, the step 2 further includes: independently measuring the vertical distance from each lateral displacement monitoring point to the virtual reference line for multiple times, and taking the average value of the vertical distances independently measured for multiple times as the initial vertical distance.
[0013] Optionally, step 2 and step 3 include the following steps:
[0014] Step 2: On-site measurement and storage: Set up a precision total station at a longitudinal distance of 20-50m from the lateral displacement monitoring point, and use the position of the central axis of the total station as the measuring station; use the free station setting without prism / reflector mode to measure and store any measuring point in the first rear-view aiming area, any measuring point in the second rear-view aiming area, and all lateral displacement monitoring points on the monitoring cross section in sequence, and measure and store the position data;
[0015] According to the measured and stored position data, the plan views of the measuring points of the first rear-view aiming area, the measuring points of the second rear-view aiming area and all the lateral displacement monitoring points are drawn using mapping software; the measuring points of the first rear-view aiming area and the measuring points of the second rear-view aiming area are connected to form a dotted reference line;
[0016] The direction of the line connecting any two monitoring points in the section can be regarded as the lateral displacement direction of the roadbed, and the intersection of the line connecting any two monitoring points in the section and the virtual reference line is the virtual reference point; the horizontal distance from the monitoring point to the virtual reference point can be obtained through the distance measurement function of the mapping software;
[0017] Step 3: According to the preset monitoring frequency, execute step 2 at the same measuring station to obtain the horizontal distance from the current monitoring point to the virtual reference point; the change between the current horizontal distance and the initial horizontal distance is the change in the lateral displacement of the roadbed.
[0018] Furthermore, the step 2 also includes: independently measuring the horizontal distance from the monitoring point to the virtual reference point multiple times, and taking the average value of the horizontal distances measured independently multiple times as the initial horizontal distance.
[0019] Preferably, the roadbed lateral displacement monitoring method based on the virtual reference line includes:
[0020] Step 1: Construct a rear-sight aiming area; artificially lay out two observation piers as reference objects outside the range of 3 times the width of the roadbed at the downslope angle of the monitoring roadbed slope on the extension line of the monitoring section. The distance between the observation piers is 20 to 50 meters. The first rear-sight aiming area and the second rear-sight aiming area are respectively located on one observation pier and the two rear-sight aiming areas are arranged facing the measuring station. In order to improve the accuracy and consistency of the virtual reference line, the line connecting the two observation piers is as perpendicular to the monitoring section line as possible to improve the shape of the figure. A reflector is arranged on each observation pier. The above two reflectors are the first and second rear-sight aiming areas of the method. The precision total station sight line method is used to make the reflectors as much as possible in the same vertical plane to weaken the influence of the aiming error, and at the same time, the reflection intensity of the aiming signal can also be improved.
[0021] Step 2: Set up monitoring points. Use GNSS to accurately lay out and set up lateral displacement monitoring points on the monitoring cross section; to improve the accuracy of monitoring data and avoid people crossing the road, the monitoring points should be in reflector mode, and the total station sight line method should be used to ensure that the reflectors of the monitoring points are in the same vertical plane as much as possible;
[0022] Step 3: On-site measurement and storage. Set up a total station about 30m away from the longitudinal direction of the monitored cross-section roadbed, and use the free station setting without prism / reflector mode to measure and store any measuring point in the first rear-sight aiming area, any measuring point in the second rear-sight aiming area, and all lateral displacement monitoring points on the section in sequence.
[0023] Step 4: Display and process the measuring points. The measured data can be obtained through the mapping software display tool to obtain the plan view of the first rear-sight aiming area measuring points, the second rear-sight aiming area measuring points and the lateral displacement monitoring points on the section; the virtual baseline can be constructed through the first rear-sight aiming area measuring points and the second rear-sight aiming area measuring points; the vertical line from each lateral displacement monitoring point to the virtual baseline is drawn through the mapping software, and the foot of the vertical is the corresponding virtual reference point. The vertical distance from each lateral displacement monitoring point to the virtual baseline can be obtained through the distance measurement function; in order to improve the reliability of the initial vertical distance, the average value of the vertical distance calculated after 3 independent measurements is taken as the initial value.
[0024] Step 5: According to the preset monitoring frequency, repeat steps 3 and 4 to obtain the vertical distance change of each lateral displacement monitoring point. Since the vertical distance change is the projection of the lateral displacement of the roadbed on the vertical line from the lateral displacement monitoring point to the virtual baseline, the lateral displacement of the roadbed at each monitoring point can be calculated through the trigonometric relationship between the vertical distance change and the lateral displacement of the roadbed.
[0025] When the reference objects are two artificially buried observation piers, this situation is for the case where there are no stable and regular structures outside the range of 3 times the roadbed width at the downslope foot of the roadbed to be monitored. In this case, the alternative method may also be two artificially arranged stable reflectors. The reflectors should be arranged in the same vertical plane as much as possible through the total station sight line method. The virtual reference point should be located between the two reflectors, with the reflector facing the measuring station.
[0026] Optionally, in step 1, the rear sight aiming area is constructed in the following manner:
[0027] It is assumed that there is a stable and regular structure outside the range of 3 times the width of the roadbed at the downslope foot of the roadbed to be monitored, and ideally, any point on its facade facing the roadbed to be monitored should be projected on the same straight line, which is the virtual baseline of the method; in order to maximize the consistency of the virtual baseline, a 5cm*5cm aiming area should be selected at the left and right ends of a facade of the building as the rear-view aiming area, and the aiming areas should be at the same height as much as possible to reduce the error caused by the inclination of the structure.
[0028] Optionally, the steps 3 to 5 include the following steps:
[0029] Step 3: On-site measurement and storage. Set up a total station about 30m away from the longitudinal direction of the monitored cross-section roadbed, and use the free station setting without prism / reflector mode to measure and store any measuring point in the first rear-sight aiming area, any measuring point in the second rear-sight aiming area, and all lateral displacement monitoring points on the section in sequence.
[0030] Step 4: Display and process the measuring points. The measured data can be obtained through the mapping software display tool to obtain the plan view of the first rear-sight sighting area measuring points, the second rear-sight sighting area measuring points and the lateral displacement monitoring points on the section; the virtual reference line can be constructed through the first rear-sight sighting area measuring points and the second rear-sight sighting area measuring points; the direction of the line connecting any two monitoring points in the section can be regarded as the lateral displacement direction of the roadbed, and the intersection of the line connecting any two monitoring points in the section and the virtual reference line is the virtual reference point; the horizontal distance from the monitoring point to the virtual reference point can be obtained through the distance measurement function. In order to improve the reliability of the initial horizontal distance to the ground, the average value of three independent horizontal distances is generally taken as the initial value.
[0031] Step 5: According to the preset monitoring frequency, repeat steps 3 and 4 to obtain the horizontal distance from the current monitoring point to the virtual reference point. The change between the current horizontal distance and the initial horizontal distance is the lateral displacement of the roadbed.
[0032] Preferably, the reference object is a stable building, and the first rear-view aiming area and the second rear-view aiming area are located at the same height.
[0033] Particularly preferably, reflective sheets are pasted at the locations of the first rear-view aiming area and the second rear-view aiming area to improve the consistency of the virtual reference line.
[0034] Preferably, the lateral displacement monitoring points are positioned using GNSS satellites, and the monitoring points are securely arranged on the road surface using a reflector pattern.
[0035] Furthermore, according to the roadbed lateral displacement monitoring method of the virtual baseline, a characteristic point on the building is selected as the reference point of the vertical displacement, and the vertical height difference between the reference point and each monitoring point is synchronously obtained in step three. In step five, the change in the current vertical height difference and the initial vertical height difference can be regarded as the vertical displacement of the roadbed.
[0036] Preferably, the vertical displacement reference point should be any measuring point on the first rear-view aiming area or the second rear-view aiming area.
[0037] Optionally, the vertical displacement reference point may be a certain characteristic point on the structure.
[0038] Compared with the prior art, the technical solution of the present invention has the following beneficial effects:
[0039] 1. Compared with conventional GNSS static observation method, traverse method, etc., conventional methods require the precise coordinates of the reference points to be known before the coordinates of the monitoring points can be calculated. The monitoring method described in the present invention has no special requirements for the reference points and the coordinates of the reference points, as long as the site to be measured has the conditions for constructing a virtual reference line; in addition, when the method is implemented, each monitoring cross section can be independently measured in a free station without prism / reflector mode, which can effectively avoid rear-sight sighting errors, cumulative errors, instrument height errors, etc., so that the operation accuracy, operation efficiency and field operability of the method are greatly improved, and it has strong practicality.
[0040] 2. This method simultaneously solves many problems such as difficulty in joint measurement of benchmark points, poor lateral visibility conditions, prohibition of crossing the road, and low operating efficiency. At the same time, under certain conditions, it can also be used for vertical displacement monitoring simultaneously, and can also be directly promoted and applied to horizontal and vertical displacement monitoring scenarios of foundation pits such as municipal engineering, and has strong universality. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] Figure 1 It is a monitoring schematic diagram using the monitoring method of the present invention;
[0042] Figure 2 is a top plan view obtained by using CAD software in Example 1;
[0043] Figure 3 is a schematic diagram of a perpendicular line and a foot of a perpendicular from a lateral displacement monitoring point to a virtual reference line in Example 1;
[0044] Figure 4 is a schematic diagram showing the change amount of the monitoring point in Example 1;
[0045] Figure 5 is a monitoring schematic diagram of the monitoring method described in Example 2;
[0046] Figure 6 is a top plan view obtained using CAD software in Example 2;
[0047] Figure 7 is a schematic diagram of a perpendicular line and a foot of a perpendicular from a lateral displacement monitoring point to a virtual reference line in Example 2;
[0048] Figure 8 is a schematic diagram showing the change amount of the monitoring point in Example 2;
[0049] Fig. 9 The length values of line segments XN-P1 and XN-P2 are obtained in Example 3.
[0050] in,
[0051] HS1: first rear sight point, any measuring point in the first rear sight aiming area; HS2: second rear sight point, any measuring point in the second rear sight aiming area
[0052] Any measuring point in the quasi-area;
[0053] XN: virtual reference point; P1: first monitoring point;
[0054] P2: second monitoring point; P3: third monitoring point; CZ: measuring station;
[0055] XN1: the first virtual reference point; XN2: the second virtual reference point; XN3: the third virtual reference point. DETAILED DESCRIPTION
[0056] The technical solution of the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. The specific embodiments described are only used to explain the present invention and are not intended to limit the present invention. The method is not only applicable to scenes with good lateral visibility conditions, but also to scenes with poor lateral visibility conditions, long section spacing, and difficult benchmark joint measurement, such as fully enclosed, high slopes, and large retaining walls.
[0057] Example 1
[0058] like Figure 1 As shown, a method for monitoring the lateral displacement of roadbed based on a virtual baseline is applied to monitoring the lateral displacement of highway roadbed. A monitoring cross section is set every 200 meters along the longitudinal direction of the roadbed, and each section has three lateral displacement monitoring points of the roadbed. Each section independently executes the monitoring method to monitor the lateral displacement of the roadbed. Specifically, the following steps are included:
[0059] Step 1: Construct the rear sight area and monitoring points
[0060] S11: Figure 1 In the middle and upper part, two stable observation piers are artificially arranged outside the range of 3 times the width of the roadbed at the downslope angle of the monitoring roadbed slope on the extension line of the monitoring section. The distance between the observation piers is 20 to 50 meters. In order to improve the accuracy and consistency of the virtual baseline, the line connecting the two observation piers is as perpendicular to the monitoring section line as possible to improve the shape of the graph. Reflectors are arranged on the observation piers and the total station sight line method is used to make the reflectors as much as possible in the same vertical plane to weaken the influence of the aiming error. At the same time, the consistency of aiming and the signal reflection intensity can also be improved. The above two reflectors are the first and second rear-sight aiming areas of the method. The measuring points are as follows: Figure 1 The first backsight point HS1 and the second backsight point HS2 are shown.
[0061] S12: According to the monitoring design plan, GNSS satellites are used for precise layout and stable reflectors are placed as monitoring points, such as Figure 1 As shown, a first monitoring point P1, a second monitoring point P2 and a third monitoring point P3 are arranged; the monitoring points are stably arranged on the road surface of the expressway in a reflective sheet mode, and are respectively arranged on the left and right slopes of the expressway and the central dividing strip.
[0062] Step 2: On-site measurement and measurement point display
[0063] S21: Set up a precision total station on the slope about 30 meters away from the longitudinal direction of the monitoring cross section. The position of the central axis of the precision total station is used as the measuring station CZ. The free station setting and prism-free / reflector-free mode are used to sequentially aim at the external first backsight point HS1, the second backsight point HS2, the first monitoring point P1, the second monitoring point P2 and the third monitoring point P3, and measure and store their relative positions.
[0064] S22: Use CAD software to draw the first backsight point HS1, the second backsight point HS2, the first monitoring point P1, the second monitoring point P2 and the third monitoring point P3, and obtain the following: Figure 2 The plane distribution diagram shown; connecting the measuring point HS1 of the first rear-view aiming area and the measuring point HS2 of the second rear-view aiming area to form a virtual reference line HS1-HS2;
[0065] Draw a perpendicular line from each lateral displacement monitoring point to the virtual reference line HS1-HS2 using the mapping software, with the foot of the perpendicular being the corresponding virtual reference point. The perpendicular distance from each lateral displacement monitoring point to the virtual reference line can be obtained using the distance measurement function, such as Figure 3 As shown in the figure, P1-XN1, P2-XN2, and P3-XN3 are the vertical distances from the lateral displacement monitoring points P1, P2, and P3 to the virtual reference line. In order to improve the reliability of the initial vertical distance, the average vertical distance calculated after three independent measurements is taken as the initial value.
[0066] Step 3: Regular monitoring
[0067] According to the preset monitoring frequency, the contents of steps S21 and S22 are executed to obtain the vertical distance change of each lateral displacement monitoring point. Since the vertical distance change is the projection of the lateral displacement of the roadbed on the vertical line from the lateral displacement monitoring point to the virtual baseline, the lateral displacement of the roadbed of each monitoring point can be calculated through the trigonometric function relationship between the vertical distance change and the lateral displacement of the roadbed.
[0068] refer to Figure 4 , since the vertical distance change Δh is the projection of the lateral displacement Δs of the roadbed on the vertical line, therefore:
[0069] Δs=Δh / sinα
[0070] Among them, Δs represents the change in the lateral displacement of the roadbed, Δh represents the change in the vertical distance from the current monitoring point to the virtual baseline, and α is the angle between the monitoring section line and the roadbed edge line.
[0071] According to the above steps, the lateral displacement of the roadbed at each monitoring point can be calculated.
[0072] Example 2
[0073] A method for monitoring lateral displacement of roadbed based on a virtual baseline, the monitoring method is similar to that of Example 1, only step 1 is different, and the remaining steps are the same as those of Example 1, which will not be repeated here.
[0074] Step 1: Set up rear-view points and monitoring points
[0075] In this embodiment, there are stable and regular structures outside the 3 times roadbed width of the downslope foot of the roadbed to be monitored. Figure 5 The gray cuboid in the middle and upper part is a stable building outside the roadbed. It is assumed that the building has a regular facade facing the roadbed, that is, in an ideal state, the projection of any point on its facade should be on the same straight line. It is assumed that the first rearview point HS1 and the second rearview point HS2 (i.e., any measuring point in the first rearview aiming area and any measuring point in the second rearview aiming area) are two points with any unknown coordinates on the left and right ends of the facade. The virtual reference line can be constructed through these two points. In order to improve the consistency of the virtual reference line, the two rearview points should be located at the same height at the left and right ends of the building facade, and reflective sheets should be attached to the first and second rearview aiming areas. At the same time, the virtual reference point P should be located between the projection lines of the first rearview point HS1 and the second rearview point HS2.
[0076] Figure 6-8 The plan view drawn by mapping software and the connection between the monitoring points and the virtual reference line on the plan view are shown.
[0077] Example 3
[0078] A method for monitoring horizontal displacement of a foundation pit based on a virtual baseline, wherein the monitoring method is substantially the same as that of Example 1.
[0079] On the plane distribution diagram obtained by plotting the first backsight point HS1, the second backsight point HS2, the first monitoring point P1, the second monitoring point P2 and the third monitoring point P3 using CAD software, the virtual reference point XN can be obtained by extending the P1-P2 line toward the building and intersecting it with the HS1-HS2 line. The P1-P2 line is the line connecting the first monitoring point P1 and the second monitoring point P2, and the HS1-HS2 line is the line connecting the first backsight point HS1 and the second backsight point HS2.
[0080] Use the distance measurement function of the CAD software to obtain the horizontal distance from the virtual reference point XN to the first monitoring point P1 (the length of the line segment XN1-P1) and the horizontal distance from the virtual reference point XN to the second monitoring point P2 (the length of the line segment XN-P2). Fig. 9 The measured data is shown. Similarly, the horizontal distance of point P3 to the virtual reference line in the transverse direction of the roadbed can also be obtained by the above method. In order to improve the reliability of the initial horizontal distance, the average value of three independent horizontal distances is generally taken as the value of the initial horizontal distance.
[0081] According to the preset monitoring frequency, the contents of steps S21 and S22 are executed, and the first backsight point HS1, the second backsight point HS2, the first monitoring point P1, the second monitoring point P2 and the third monitoring point P3 are measured at the same measuring station CZ using a precision total station, and the horizontal distances of the current line segments XN-P1, XN-P2 and XN-P3 are obtained using CAD software. The current horizontal distances of XN-P1, XN-P2 and XN-P3 are subtracted from the initial horizontal distances obtained in step 2 to obtain the lateral displacement of the roadbed.
[0082] Since the main direction of the horizontal displacement of the foundation pit is fixed, if displacement occurs, it is perpendicular to the maintenance structure of the foundation pit. In this embodiment, the monitoring points are set in the reflector mode and are located at the top of the pile / top of the wall of the foundation pit support structure. Then, two rear view points are reasonably selected outside 3 times the excavation depth of the foundation pit, and the horizontal displacement of the top of the pile / top of the wall of the foundation pit support structure can be obtained according to the method described in Example 1.
[0083] Example 4
[0084] A method for monitoring vertical displacement of roadbed, based on Example 1, uses a reflector measuring point in one of the rear-view aiming areas as a reference point for vertical displacement, such as using the first rear-view point HS1 (reflector measuring point) as the reference point, and synchronously obtains the vertical height difference between the first rear-view point HS1 (reflector measuring point) and each monitoring point in the method of Example 1, and the change between the current vertical height difference and the initial vertical height difference is the vertical displacement of the roadbed. In order to improve the accuracy of the measurement, the second rear-view point HS2 (reflector measuring point) can be used as a check point.
[0085] Although the preferred embodiments of the present invention have been described above in conjunction with the accompanying drawings, the present invention is not limited to the above-mentioned specific embodiments, which are merely illustrative and not restrictive. Other technicians in the field, inspired by the present invention, may also make other forms without departing from the scope of protection of the present invention and the claims, all of which fall within the scope of protection of the present invention.
Claims
1. A method for monitoring lateral displacement of roadbed based on a virtual baseline, characterized in that: include: Step 1: Construct the rear-view aiming area and arrange the monitoring points: determine a reference object outside the 3 times of the roadbed width at the downslope foot of the roadbed to be monitored, set a straight line as a virtual reference line; and determine the first rear-view aiming area and the second rear-view aiming area on the plane of the reference object facing the roadbed to be monitored; Arrange multiple lateral displacement monitoring points on the cross section of the roadbed to be monitored; Step 2: On-site measurement and storage: Set up a precision total station at a longitudinal distance of 20-50m from the lateral displacement monitoring point, and the position of the central axis of the total station is used as the measuring station (CZ); use the free station setting without prism / reflector mode to measure and store any measuring point (HS1) in the first rear-view aiming area, any measuring point (HS2) in the second rear-view aiming area, and all lateral displacement monitoring points on the cross section in turn, and measure and store the position data; According to the measured and stored position data, the plan view of the measuring points (HS1) of the first rear sight aiming area, the measuring points (HS2) of the second rear sight aiming area and all the lateral displacement monitoring points are drawn using mapping software; the measuring points of the first rear sight aiming area and the measuring points of the second rear sight aiming area are connected to form a dotted line reference line; Draw a perpendicular line from each lateral displacement monitoring point to the virtual reference line through the mapping software, with the foot of the perpendicular being the corresponding virtual reference point, and obtain the perpendicular distance from each lateral displacement monitoring point to the virtual reference line through the distance measurement function; Step 3: According to the preset monitoring frequency, execute step 2 at the same measuring station (CZ) to obtain the vertical distance change of each lateral displacement monitoring point, and calculate the lateral displacement of the roadbed at each monitoring point through the trigonometric function relationship between the vertical distance change and the lateral displacement of the roadbed.
2. The method for monitoring lateral displacement of roadbed based on virtual reference line according to claim 1 is characterized in that: The step 2 further comprises: independently measuring the vertical distance from each lateral displacement monitoring point to the virtual reference line for multiple times, and taking the average value of the vertical distances independently measured for multiple times as the initial vertical distance.
3. The method for monitoring lateral displacement of roadbed based on virtual reference line according to claim 1, characterized in that: Optionally, obtaining the lateral displacement of the roadbed at each monitoring point includes the following steps: Step 2: Using mapping software, draw the plane view of the measuring points (HS1) of the first rear sight aiming area, the measuring points (HS2) of the second rear sight aiming area, and all the lateral displacement monitoring points according to the measured and stored position data; connect the measuring points of the first rear sight aiming area and the measuring points of the second rear sight aiming area to form a dotted line reference line; Step 3: According to the preset monitoring frequency, execute step 2 at the same measuring station (CZ) to obtain the horizontal distance from the current monitoring point to the virtual reference line in the transverse direction of the roadbed. The change between the current horizontal distance and the initial horizontal distance is the lateral displacement of the roadbed.
4. The method for monitoring lateral displacement of roadbed based on virtual reference line according to claim 1, characterized in that: The reference object is a stable building, and the first rear-view aiming area and the second rear-view aiming area are located at the same height and are located in a certain facade of the building facing the measuring station.
5. The method for monitoring lateral displacement of roadbed based on virtual reference line according to claim 4 is characterized in that: Reflective sheets are pasted at the locations of the first rear-view aiming area and the second rear-view aiming area.
6. The method for monitoring lateral displacement of roadbed based on virtual reference line according to claim 1, characterized in that: The reference objects are two artificially arranged reflective sheets, the first rear-view aiming area and the second rear-view aiming area are respectively located on one reflective sheet and the two rear-view aiming areas are arranged facing the measuring station, and the virtual reference point is located between the two rear-view aiming areas.
7. The method for monitoring lateral displacement of roadbed based on virtual reference line according to claim 1, characterized in that: The lateral displacement monitoring points are precisely laid out using GNSS satellites. The lateral displacement monitoring points are arranged on the road surface in a reflector pattern, and the reflectors are arranged in the same facade using a total station sight line method.
8. The method for monitoring lateral displacement of roadbed based on virtual reference line according to claim 1, characterized in that: Select any characteristic point on the building as the vertical displacement reference point. In step 2, the vertical height difference between the vertical displacement reference point and each lateral displacement monitoring point is obtained synchronously. In step 3, the change between the current vertical height difference and the initial vertical height difference is the settlement of the roadbed monitoring.
9. The method for monitoring lateral displacement of roadbed based on virtual reference line according to claim 8, characterized in that: The reference point of the vertical displacement is any reflective sheet measuring point on the first rear-view aiming area or the second rear-view aiming area.
10. The method for monitoring lateral displacement of roadbed based on virtual reference line according to claim 1, characterized in that: The monitoring method is suitable for monitoring the lateral or vertical displacement of a highway roadbed or foundation pit.
Citation Information
Patent Citations
Method for measuring horizontal displacement of building foundation ditch
CN103526783A
Foundation pit horizontal displacement automatic monitoring method and system based on virtual center point