Construction project whole-process automatic management and control method and system

By adjusting and expanding the coding rules for large airport construction and building cost management baselines and management solutions, the information isolation problem of cost management and contract management in large airport construction is solved, real-time cost control and early warning is achieved, and the transparency of construction projects is improved. and economic benefits.

CN118982201AActive Publication Date: 2024-11-19THREE GORGES HI TECH INFORMATION TECH CO LTD

Patent Information

Application Number
CN202411082919.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-08
Publication Date
2024-11-19
Estimated Expiration
2044-08-08

AI Technical Summary

Technical Problem

During the construction of large airports, cost management and contract management cannot be directly linked through system coding, resulting in difficulty in real-time induction and analysis of contract entry, cost control and fund use information, high probability of errors, and lack of transparency.

Method used

By adjusting the coding rules for large airport construction, adding automation functions, building a cost management baseline, using the contract bill of quantities for classification and analysis, establishing a cost management plan, and monitoring cost excess projects in real time, providing an early warning mechanism, and improving cost management accuracy and transparency sex.

Benefits of technology

It significantly improves the efficiency and transparency of project cost management, reduces manual errors, realizes real-time cost control and early warning of contract execution projects, and improves the competitiveness and economic benefits of construction projects.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118982201A_ABST
    Figure CN118982201A_ABST
Patent Text Reader

Abstract

The method comprises the following steps: analyzing a project preliminary design budget and a project preliminary execution budget of a large-scale airport construction project according to a coding structure of the large-scale airport construction project, constructing a cost management baseline, and obtaining a contract project quantity list of the large-scale airport construction project, classifying and analyzing the contract project quantity list by using the cost management baseline to obtain cost information corresponding to each contract execution project, constructing a cost control scheme corresponding to the contract execution project, and performing cost control verification on each contract execution project to obtain a cost management result; according to the management and control verification information corresponding to each contract execution project, the real-time cost of the large airport construction project is constructed, a target contract execution project with excess cost is positioned and early warning is carried out, the depth and the recognition capability of the code are expanded according to the national standard, and the automation function attribute of the code is increased, so that the automatic cost management and control are realized, and the efficiency is improved. And the transparency of a construction project is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of automated control, and in particular to a method and system for automated control of the entire process of a construction project. Background Art

[0002] At present, with the continuous promotion and improvement of infrastructure construction, various types of infrastructure projects are increasing, which also makes the construction difficulty in the infrastructure field increasing. In the construction and construction process of large-scale infrastructure projects, there are many risks and problems that need to be effectively controlled and solved. The risk in the construction stage is an important indicator that affects the project construction progress, quality, safety, cost and other factors. The construction project involves a wide range of aspects, including land, design, construction, materials, personnel and equipment management, etc., which affect each other and lead to overall risk changes. Therefore, high-quality management of the construction process has become an important means to ensure the quality and progress of the project. The construction index has become an important basis for evaluation management. Through the fine construction index control research, it is helpful to achieve risk control in the construction stage of the project, reduce the economic cost of the project, and improve the competitiveness and economic benefits of the project.

[0003] Due to the limitations of the current cost coding rules for large airport construction, the cost management and contract management of large airport construction cannot be directly linked through system coding, resulting in information isolation between contracts under the same budget approval in large airport construction, leading to the following specific problems in the use of large airport construction: 1. During the contract entry stage, the budget list needs to be manually decomposed and checked, and manually imported after matching according to the system coding rules, and then manually reviewed. Professionals need to spend a lot of time on this work, and the probability of error is high. 2. During the use stage, it is impossible to realize the real-time summary analysis and comprehensive query functions of various data information such as project investment completion, cost control, and fund use.

[0004] Therefore, the present invention provides a method and system for automated control of the entire process of a construction project. Summary of the invention

[0005] The present invention provides a method and system for automated control of the entire process of a construction project, which utilizes the existing coding rules for large-scale airport construction to carry out further functional upgrades, expand the depth and recognition capabilities of coding, and increase the automated functional attributes of coding. Specifically, the coding rules for the budget estimate of large-scale airport construction are adjusted to carry data standards such as engineering project division and bill of quantities pricing specifications, establish a cost management data standard system that runs through the entire process of engineering project planning, design, bidding, implementation, and acceptance, and improve the accuracy of engineering project cost management.

[0006] The present invention provides a method for automatic control of the entire process of a construction project, comprising:

[0007] Step 1: Analyze the preliminary design budget and preliminary execution budget of the large-scale airport construction project according to the coding structure of the large-scale airport construction project, and build a cost management baseline for the large-scale airport construction project;

[0008] Step 2: Obtain the contract bill of quantities of the large airport construction project, classify and analyze the contract bill of quantities using the cost management baseline, and obtain cost information corresponding to each contract execution item of the large airport construction project;

[0009] Step 3: Use the cost information to construct a cost control plan for the corresponding contract execution project, and conduct cost control verification for each of the contract execution projects;

[0010] Step 4: Construct the real-time cost of the large-scale airport construction project based on the management and control verification information corresponding to each of the contract execution projects, and locate the target contract execution projects with cost excesses in combination with the cost management baseline and issue early warnings.

[0011] In one practicable manner,

[0012] The step 1 comprises:

[0013] Step 11: Obtain the coding structure of the large airport construction project, determine the coding meaning corresponding to each structural bit according to the coding structure, and establish semantic decoding rules for the large airport construction project according to the preset national standard list and civil aviation standard list;

[0014] Step 12: obtaining several project codes of the large airport construction project, performing semantic analysis on each of the project codes using the semantic decoding rules, obtaining several semantic project information of the large airport construction project, and constructing a construction concept structure of the large airport construction project using the semantic project information;

[0015] Step 13: hierarchically process the construction concept structure to obtain a number of independent substructures, establish a number of structural logical relationships of the large-scale airport construction project according to the connection relationships between different independent substructures, and establish a preliminary design budget estimate of the large-scale airport construction project in combination with the structural foundation corresponding to each of the independent substructures;

[0016] Step 14: Analyze the construction material information corresponding to each of the independent substructures, determine the construction execution process corresponding to each of the independent substructures according to the construction method corresponding to each of the construction materials, and generate a preliminary execution budget estimate for the large airport construction project;

[0017] Step 15: Use the preliminary design estimate and the preliminary execution estimate to determine several construction steps of the large airport construction project, determine the cost information corresponding to each construction step, and establish a cost management baseline for the large airport construction project.

[0018] In one practicable manner,

[0019] The step 2 comprises:

[0020] Step 21: Obtain the contract bill of quantities and contract bill coding rules of the large airport construction project, divide the contract bill of quantities into several contract execution projects according to the contract bill coding rules, and respectively construct coding identification information corresponding to each of the contract execution projects;

[0021] Step 22: Use the coded identification information to establish a cost identification information chain for the large airport construction project, use the cost management baseline to perform a cost scan on the contract bill of quantities, obtain the execution cost corresponding to each of the contract execution items, and mark each of the execution costs in the cost identification information chain to establish a cost verification information chain;

[0022] Step 23: extracting the identification project cost value and the marking project cost value corresponding to each of the contract execution projects in the cost verification information chain, screening a category of contract execution projects whose identification project cost value and the marking project cost value are inconsistent, and establishing a first cost error range for the category of contract execution projects based on the corresponding project cost value differences;

[0023] Step 24: Filter the second category contract execution projects whose identified project cost values ​​are consistent with the marked project cost values, match the corresponding second cost error range for each of the second category contract execution projects based on the preset cost error ratio, construct the cost error range corresponding to each of the contract execution projects, and construct the cost information corresponding to each of the contract execution projects.

[0024] In one practicable manner,

[0025] The step 3 comprises:

[0026] Step 31: Determine the effective cost range corresponding to each of the contract execution items based on the cost information, construct an overall construction model of the large airport construction project according to the contract bill of quantities, run the overall construction model to determine the project execution steps corresponding to each of the contract execution items, and respectively determine the material quantity and material properties of the materials used corresponding to each of the project execution steps;

[0027] Step 32: Determine the material cost corresponding to each material based on the material attributes, determine the cost weight corresponding to each material in combination with the corresponding material quantity, count the number of materials corresponding to each contract execution project, and allocate the cost to each material based on the corresponding cost weight and the effective cost range corresponding to the contract execution project;

[0028] Step 33: Input the cost allocation result into the overall construction model for verification, obtain the material sufficiency characteristics corresponding to each of the project execution steps, adjust the cost of the used materials based on the material sufficiency characteristics, and generate a cost control plan corresponding to each of the contract execution projects;

[0029] Step 34: During construction, determine the current contract execution project corresponding to the current construction progress, locate the qualified cost corresponding to the current contract execution project in the cost control plan, and use the qualified cost to perform cost control verification on the current contract execution project.

[0030] In one practicable manner,

[0031] Also includes:

[0032] Determine the actual cost allocation corresponding to the current contract execution project based on the cost control verification results, and establish the cost qualification characteristics corresponding to each current project execution step;

[0033] When the cost qualification feature is abnormal, the current actual execution process is determined, and an early warning message is generated and played.

[0034] In one practicable manner,

[0035] The step 4 comprises:

[0036] Step 41: constructing the actual construction progress of the large airport construction project according to the execution start time corresponding to each of the contract execution items;

[0037] Step 42: respectively obtain the control and verification information corresponding to each of the contract execution projects, and determine the construction cost accumulation information of the large airport construction project in combination with the actual construction progress;

[0038] Step 43: Using the cost management baseline to perform cost evaluation on the construction cost accumulation information, and screening target contract execution projects with cost overruns;

[0039] Step 44: Obtain the excess amount corresponding to the target contract execution project, locate the execution address corresponding to the target contract execution project, and issue a corresponding warning to the execution address.

[0040] In one practicable manner,

[0041] Also includes:

[0042] Safety information is generated when the project is executed under the target contract without cost overruns.

[0043] In one practicable manner,

[0044] Also includes:

[0045] The execution workload corresponding to each contract execution project is obtained respectively, and corresponding construction personnel are matched for each contract execution project according to the execution workload, and the work details corresponding to each construction personnel are generated and displayed.

[0046] The present invention provides a construction project full-process automated management and control system, comprising:

[0047] A preliminary budget module is used to analyze the preliminary design budget and preliminary execution budget of the large-scale airport construction project according to the coding structure of the large-scale airport construction project, and to build a cost management baseline for the large-scale airport construction project;

[0048] A cost analysis module, used to obtain the contract bill of quantities of the large airport construction project, classify and analyze the contract bill of quantities using the cost management baseline, and obtain cost information corresponding to each contract execution item of the large airport construction project;

[0049] A cost verification module, used to construct a cost control plan for the corresponding contract execution project using the cost information, and to perform cost control verification on each of the contract execution projects;

[0050] The control and early warning module is used to construct the real-time cost of the large-scale airport construction project according to the control and verification information corresponding to each of the contract execution projects, locate the target contract execution projects with cost excesses in combination with the cost management baseline and issue early warnings.

[0051] In one practicable manner,

[0052] The preliminary budget module includes:

[0053] A first execution unit is used to obtain the coding structure of the large airport construction project, determine the coding meaning corresponding to each structure bit according to the coding structure, and establish a semantic decoding rule for the large airport construction project according to a preset national standard list and a civil aviation standard list;

[0054] The second execution unit is used to obtain several engineering codes of the large airport construction project, perform semantic analysis on each engineering code respectively by using the semantic decoding rule, obtain several semantic engineering information of the large airport construction project, and construct a construction concept structure of the large airport construction project by using the semantic engineering information;

[0055] The third execution unit is used to hierarchically process the construction concept structure to obtain a plurality of independent substructures, establish a plurality of structural logical relationships of the large-scale airport construction project according to the connection relationships between different independent substructures, and establish a preliminary design budget of the large-scale airport construction project in combination with the structural foundation corresponding to each of the independent substructures;

[0056] A fourth execution unit is used to analyze the construction material information corresponding to each of the independent substructures, determine the construction execution process corresponding to each of the independent substructures according to the construction method corresponding to each construction material, and generate a preliminary execution budget of the large airport construction project;

[0057] The fifth execution unit is used to determine several construction steps of the large-scale airport construction project by using the preliminary design estimate of the project and the preliminary execution estimate of the project, and determine the cost information corresponding to each of the construction steps to establish a cost management baseline for the large-scale airport construction project.

[0058] The achievable beneficial effects of the above technical solution are: in order to establish a cost management data standard system throughout the entire process of project planning, design, bidding, implementation, and acceptance, and significantly improve the efficiency of project cost management, first construct the preliminary design estimate and preliminary execution estimate of the project according to the coding structure of the large airport construction project, so as to build a cost management baseline, and then classify and analyze the contract bill of quantities to determine the cost information corresponding to each contract execution project, and then establish a cost control plan for each contract execution project, control and verify its execution process, calculate the real-time cost of the construction process, and make corresponding early warning work when necessary. In this way, according to national standards, the depth and recognition ability of coding can be expanded, and the automation function attributes of coding can be increased, thereby automating cost control within a time limit and improving the transparency of construction projects.

[0059] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or understood by practicing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures particularly pointed out in the written description, claims, and drawings.

[0060] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0061] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0062] Figure 1 A schematic diagram of a workflow of a method for automated control of the entire process of a construction project in an embodiment of the present invention;

[0063] Figure 2 A schematic diagram of coding rules for a method for automated control of the entire process of a construction project in an embodiment of the present invention;

[0064] Figure 3 The present invention is a schematic diagram of the composition of a construction project full-process automated control system in an embodiment of the present invention. DETAILED DESCRIPTION

[0065] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.

[0066] Example 1

[0067] This embodiment provides a method and system for automatic control of the entire process of a construction project. Figure 1 As shown, including:

[0068] Step 1: Analyze the preliminary design budget and preliminary execution budget of the large-scale airport construction project according to the coding structure of the large-scale airport construction project, and build a cost management baseline for the large-scale airport construction project;

[0069] Step 2: Obtain the contract bill of quantities of the large airport construction project, classify and analyze the contract bill of quantities using the cost management baseline, and obtain cost information corresponding to each contract execution item of the large airport construction project;

[0070] Step 3: Use the cost information to construct a cost control plan for the corresponding contract execution project, and conduct cost control verification for each of the contract execution projects;

[0071] Step 4: Construct the real-time cost of the large-scale airport construction project based on the management and control verification information corresponding to each of the contract execution projects, and locate the target contract execution projects with cost excesses in combination with the cost management baseline and issue early warnings.

[0072] In this example, the coding structure represents the addition of the national standard list of "Specifications for Pricing of Bill of Quantities" (GB50500-2013) and the civil aviation standard list of "Specifications for Pricing of Bill of Quantities for Civil Aviation Specialized Engineering Projects" (MH5028-2014) to the existing coding rules for large airport construction. The coding structure includes the system coding field to achieve the consistency and continuity of the data information of the estimate, budget, and settlement.

[0073] In this example, the preliminary design budget of the project refers to the project design conducted before the construction of a large airport, including the appearance of the large airport, the investment funds, the investment manpower, etc.;

[0074] In this example, the project preliminary execution estimate represents the construction allocation before the construction of a large airport, including the allocation and appointment of manpower;

[0075] In this example, the contract work list lists in detail the quantities and corresponding prices of the entire project, which is used for contract signing and project progress management;

[0076] In this instance, the cost management baseline represents the benchmark used to compare and monitor the actual cost performance of the project;

[0077] In this example, the contract execution project represents the project generated according to the contract engineering list and required to be executed when constructing a large airport;

[0078] In this example, real-time costs continue to increase as construction progresses.

[0079] The working principle and beneficial effects of the above technical solution: In order to establish a cost management data standard system throughout the entire process of project planning, design, bidding, implementation, and acceptance, and significantly improve the efficiency of project cost management, first construct the preliminary design estimate and preliminary execution estimate of the project according to the coding structure of the large airport construction project, so as to build a cost management baseline, and then classify and analyze the contract bill of quantities to determine the cost information corresponding to each contract execution project, and then establish a cost control plan for each contract execution project, control and verify its execution process, calculate the real-time cost of the construction process, and make corresponding early warnings when necessary. In this way, we can expand the depth and recognition ability of coding according to national standards, increase the automation function attributes of coding, thereby automating cost control within a time limit and improving the transparency of construction projects.

[0080] Example 2

[0081] On the basis of Example 1, the method for automated management and control of the entire process of a construction project, step 1, comprises:

[0082] Step 11: Obtain the coding structure of the large airport construction project, determine the coding meaning corresponding to each structural bit according to the coding structure, and establish semantic decoding rules for the large airport construction project according to the preset national standard list and civil aviation standard list;

[0083] Step 12: obtaining several project codes of the large airport construction project, performing semantic analysis on each of the project codes using the semantic decoding rules, obtaining several semantic project information of the large airport construction project, and constructing a construction concept structure of the large airport construction project using the semantic project information;

[0084] Step 13: hierarchically process the construction concept structure to obtain a number of independent substructures, establish a number of structural logical relationships of the large-scale airport construction project according to the connection relationships between different independent substructures, and establish a preliminary design budget estimate of the large-scale airport construction project in combination with the structural foundation corresponding to each of the independent substructures;

[0085] Step 14: Analyze the construction material information corresponding to each of the independent substructures, determine the construction execution process corresponding to each of the independent substructures according to the construction method corresponding to each of the construction materials, and generate a preliminary execution budget estimate for the large airport construction project;

[0086] Step 15: Use the preliminary design estimate and the preliminary execution estimate to determine several construction steps of the large airport construction project, determine the cost information corresponding to each construction step, and establish a cost management baseline for the large airport construction project.

[0087] In this example, the semantic decoding rule means expressing the encoded meaning in a semantic way, such as Figure 2 The code in is FX0101010101, and the corresponding meaning after decoding is: flight area\airport runway engineering\underpass corridor\earthwork excavation\site leveling\earthwork excavation and filling;

[0088] In this example, the coding identification information indicates a code corresponding to a contract execution item;

[0089] In this example, the cost representation information chain represents an information chain generated by statistics of the coding identification information corresponding to different contract execution items;

[0090] In this example, the preset cost error ratio is 0.12%.

[0091] The working principle and beneficial effects of the above technical solution are as follows: by utilizing the contract bill of quantities and contract list coding rules to construct the coding identification information corresponding to each contract execution item, thereby constructing a cost identification information chain, and then using the cost baseline to perform cost scanning, constructing a cost verification information chain, and classifying the contract execution items by analyzing the identified item cost value and the marked item cost value, and configuring different error ranges for different categories of contract execution items, and finally determining the cost information corresponding to each contract execution item. In this way, all contract execution items can be analyzed at the same time, and their corresponding errors are taken into account during the analysis process, which effectively improves the credibility of the cost information and provides strong reference evidence for construction.

[0092] Example 4

[0093] On the basis of Example 1, in the method for automated control of the entire process of a construction project, step 3 comprises:

[0094] Step 31: Determine the effective cost range corresponding to each of the contract execution items based on the cost information, construct an overall construction model of the large airport construction project according to the contract bill of quantities, run the overall construction model to determine the project execution steps corresponding to each of the contract execution items, and respectively determine the material quantity and material properties of the materials used corresponding to each of the project execution steps;

[0095] Step 32: Determine the material cost corresponding to each material based on the material attributes, determine the cost weight corresponding to each material in combination with the corresponding material quantity, count the number of materials corresponding to each contract execution project, and allocate the cost to each material based on the corresponding cost weight and the effective cost range corresponding to the contract execution project;

[0096] Step 33: Input the cost allocation result into the overall construction model for verification, obtain the material sufficiency characteristics corresponding to each of the project execution steps, adjust the cost of the used materials based on the material sufficiency characteristics, and generate a cost control plan corresponding to each of the contract execution projects;

[0097] Step 34: During construction, determine the current contract execution project corresponding to the current construction progress, locate the qualified cost corresponding to the current contract execution project in the cost control plan, and use the qualified cost to perform cost control verification on the current contract execution project.

[0098] In this example, the effective cost range represents the reasonable range of costs required to execute the project under the contract;

[0099] In this example, the overall construction model means expressing the contents of the contract bill of quantities by means of a model. The model can represent the model of a large airport construction project after completion;

[0100] In this example, a contract execution project may correspond to one or more project execution steps, and a project execution step represents the operations required to complete a contract execution project;

[0101] In this example, the materials used represent the materials needed when carrying out the project execution steps, such as: concrete and steel bars are needed when carrying out foundation construction;

[0102] In this example, the material quantity indicates the required amount of a material to be used, for example, 5 tons of concrete are required when constructing the foundation;

[0103] In this instance, material properties represent a physical property of a used material;

[0104] In this example, the cost weight indicates the input cost of the material used according to the material quantity. Generally speaking, the larger the material quantity, the greater the cost weight.

[0105] In this example, the material sufficiency feature indicates the sufficiency of the materials available for use when performing a project execution step;

[0106] In this example, cost adjustment refers to the process of adjusting the input costs for insufficient used materials.

[0107] The working principle and beneficial effects of the above technical solution are as follows: by constructing an overall construction model of a large-scale airport construction project to simulate the corresponding project execution steps when executing different contract execution projects, the materials and material quantities required for each project execution step are determined, and then the material properties are used to determine the cost of each material used, so as to reasonably allocate the effective cost of the contract execution project to the corresponding materials used, and then the overall construction model is used to verify the allocation results, and cost adjustments are made when necessary, thereby constructing a cost control plan. Finally, during construction, cost control verification is carried out according to the cost control plan, effectively avoiding the problem of uneven fund distribution.

[0108] Example 5

[0109] On the basis of Example 4, the method for automatic control of the entire process of a construction project further includes:

[0110] Determine the actual cost allocation corresponding to the current contract execution project based on the cost control verification results, and establish the cost qualification characteristics corresponding to each current project execution step;

[0111] When the cost qualification feature is abnormal, the current actual execution process is determined, and an early warning message is generated and played.

[0112] Example 6

[0113] On the basis of Example 1, in the method for automated management and control of the entire process of a construction project, step 4 comprises:

[0114] Step 41: constructing the actual construction progress of the large airport construction project according to the execution start time corresponding to each of the contract execution items;

[0115] Step 42: respectively obtain the control and verification information corresponding to each of the contract execution projects, and determine the construction cost accumulation information of the large airport construction project in combination with the actual construction progress;

[0116] Step 43: Using the cost management baseline to perform cost evaluation on the construction cost accumulation information, and screening target contract execution projects with cost overruns;

[0117] Step 44: Obtain the excess amount corresponding to the target contract execution project, locate the execution address corresponding to the target contract execution project, and issue a corresponding warning to the execution address.

[0118] The working principle and beneficial effects of the above technical solution are as follows: Based on the management and verification information of the contract execution projects, the cumulative construction cost information of the large airport construction is constructed, and then the cost evaluation is carried out, and the contract execution projects with cost excess are further screened and located, and corresponding early warnings are issued in combination with their corresponding excess amounts. In this way, the actual cost investment can be corrected to avoid the subsequent shortage of funds.

[0119] Example 7

[0120] Based on Example 6, the method for automatic control of the entire process of a construction project further includes:

[0121] Safety information is generated when the project is executed under the target contract without cost overruns.

[0122] The working principle and beneficial effects of the above technical solution are as follows: When all contract execution items are qualified, safety information is generated and the relevant personnel can continue construction.

[0123] Example 8

[0124] Based on Example 1, the method for automatic control of the entire process of a construction project further includes:

[0125] The execution workload corresponding to each contract execution project is obtained respectively, and corresponding construction personnel are matched for each contract execution project according to the execution workload, and the work details corresponding to each construction personnel are generated and displayed.

[0126] The working principle and beneficial effects of the above technical solution: Building workload to allocate different construction personnel to different contract execution projects can not only ensure the construction progress, but also reasonably arrange the construction personnel and reduce the investment in manpower costs.

[0127] Example 9

[0128] This example provides a construction project full process automation control system. Figure 3 As shown, including:

[0129] A preliminary budget module is used to analyze the preliminary design budget and preliminary execution budget of the large-scale airport construction project according to the coding structure of the large-scale airport construction project, and to build a cost management baseline for the large-scale airport construction project;

[0130] A cost analysis module, used to obtain the contract bill of quantities of the large airport construction project, classify and analyze the contract bill of quantities using the cost management baseline, and obtain cost information corresponding to each contract execution item of the large airport construction project;

[0131] A cost verification module, used to construct a cost control plan for the corresponding contract execution project using the cost information, and to perform cost control verification on each of the contract execution projects;

[0132] The control and early warning module is used to construct the real-time cost of the large-scale airport construction project according to the control and verification information corresponding to each of the contract execution projects, locate the target contract execution projects with cost excesses in combination with the cost management baseline and issue early warnings.

[0133] In this example, the coding structure represents the addition of the national standard list of the "Specifications for Pricing of Bill of Quantities" (GB50500-2013) and the civil aviation standard list of the "Specifications for Pricing of Bill of Quantities for Civil Aviation Specialized Engineering Projects" (MH5028-2014) to the existing coding rules for large airport construction. The coding structure includes the system coding field to achieve the consistency and continuity of the data information of the estimate, budget, and settlement.

[0134] In this example, the preliminary design budget of the project refers to the project design conducted before the construction of a large airport, including the appearance of the large airport, the investment funds, the investment manpower, etc.;

[0135] In this example, the project preliminary execution estimate represents the construction allocation before the construction of a large airport, including the allocation and appointment of manpower;

[0136] In this example, the contract work list lists in detail the quantities and corresponding prices of the entire project, which is used for contract signing and project progress management;

[0137] In this instance, the cost management baseline represents the benchmark used to compare and monitor the actual cost performance of the project;

[0138] In this example, the contract execution project represents the project generated according to the contract engineering list and required to be executed when constructing a large airport;

[0139] In this example, real-time costs continue to increase as construction progresses.

[0140] The working principle and beneficial effects of the above technical solution: In order to establish a cost management data standard system throughout the entire process of project planning, design, bidding, implementation, and acceptance, and significantly improve the efficiency of project cost management, the preliminary design estimate and preliminary execution estimate of the project are first constructed according to the coding structure of the large airport construction project, so as to build a cost management baseline. Then, the contract bill of quantities is classified and analyzed to determine the cost information corresponding to each contract execution project. Then, a cost control plan is established for each contract execution project, and its execution process is controlled and verified, as well as the real-time cost of the construction process. When necessary, corresponding early warning work is made. In this way, according to national standards, the depth and recognition ability of coding can be expanded, and the automation function attributes of coding can be increased, thereby automating cost control within a time limit and improving the transparency of construction projects.

[0141] Example 10

[0142] On the basis of Example 9, the preliminary budget module of the full-process automated management and control system for a construction project includes:

[0143] A first execution unit is used to obtain the coding structure of the large airport construction project, determine the coding meaning corresponding to each structure bit according to the coding structure, and establish a semantic decoding rule for the large airport construction project according to a preset national standard list and a civil aviation standard list;

[0144] The second execution unit is used to obtain several engineering codes of the large airport construction project, perform semantic analysis on each engineering code respectively by using the semantic decoding rule, obtain several semantic engineering information of the large airport construction project, and construct a construction concept structure of the large airport construction project by using the semantic engineering information;

[0145] The third execution unit is used to hierarchically process the construction concept structure to obtain a plurality of independent substructures, establish a plurality of structural logical relationships of the large-scale airport construction project according to the connection relationships between different independent substructures, and establish a preliminary design budget of the large-scale airport construction project in combination with the structural foundation corresponding to each of the independent substructures;

[0146] A fourth execution unit is used to analyze the construction material information corresponding to each of the independent substructures, determine the construction execution process corresponding to each of the independent substructures according to the construction method corresponding to each construction material, and generate a preliminary execution budget of the large airport construction project;

[0147] The fifth execution unit is used to determine several construction steps of the large-scale airport construction project by using the preliminary design estimate of the project and the preliminary execution estimate of the project, and determine the cost information corresponding to each of the construction steps to establish a cost management baseline for the large-scale airport construction project.

[0148] In this example, the semantic decoding rule means expressing the encoded meaning in a semantic way, such as Figure 2 The code in is FX0101010101, and the corresponding meaning after decoding is: flight area\airport runway engineering\underpass corridor\earthwork excavation\site leveling\earthwork excavation and filling;

[0149] In this example, the coding identification information indicates a code corresponding to a contract execution item;

[0150] In this example, the cost representation information chain represents an information chain generated by statistics of the coding identification information corresponding to different contract execution items;

[0151] In this example, the preset cost error ratio is 0.12%.

[0152] The working principle and beneficial effects of the above technical solution are as follows: by utilizing the contract bill of quantities and contract list coding rules to construct the coding identification information corresponding to each contract execution item, thereby constructing a cost identification information chain, and then using the cost baseline to perform cost scanning, constructing a cost verification information chain, and classifying the contract execution items by analyzing the identified item cost value and the marked item cost value, and configuring different error ranges for different categories of contract execution items, and finally determining the cost information corresponding to each contract execution item. In this way, all contract execution items can be analyzed at the same time, and their corresponding errors are taken into account during the analysis process, which effectively improves the credibility of the cost information and provides strong reference evidence for construction.

[0153] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. A method for automatic control of the entire process of a construction project, characterized in that: include: Step 1: Analyze the preliminary design budget and preliminary execution budget of the large-scale airport construction project according to the coding structure of the large-scale airport construction project, and build a cost management baseline for the large-scale airport construction project; Step 2: Obtain the contract bill of quantities of the large airport construction project, classify and analyze the contract bill of quantities using the cost management baseline, and obtain cost information corresponding to each contract execution item of the large airport construction project; Step 3: Use the cost information to construct a cost control plan for the corresponding contract execution project, and conduct cost control verification for each of the contract execution projects; Step 4: Construct the real-time cost of the large-scale airport construction project based on the management and control verification information corresponding to each of the contract execution projects, and locate the target contract execution projects with cost excesses in combination with the cost management baseline and issue early warnings.

2. A method for automatic control of the entire process of a construction project as claimed in claim 1, characterized in that: The step 1 comprises: Step 11: Obtain the coding structure of the large airport construction project, determine the coding meaning corresponding to each structural bit according to the coding structure, and establish semantic decoding rules for the large airport construction project according to the preset national standard list and civil aviation standard list; Step 12: obtaining several project codes of the large airport construction project, performing semantic analysis on each of the project codes using the semantic decoding rules, obtaining several semantic project information of the large airport construction project, and constructing a construction concept structure of the large airport construction project using the semantic project information; Step 13: hierarchically process the construction concept structure to obtain a number of independent substructures, establish a number of structural logical relationships of the large-scale airport construction project according to the connection relationships between different independent substructures, and establish a preliminary design budget estimate of the large-scale airport construction project in combination with the structural foundation corresponding to each of the independent substructures; Step 14: Analyze the construction material information corresponding to each of the independent substructures, determine the construction execution process corresponding to each of the independent substructures according to the construction method corresponding to each of the construction materials, and generate a preliminary execution budget estimate for the large airport construction project; Step 15: Use the preliminary design estimate and the preliminary execution estimate to determine several construction steps of the large airport construction project, determine the cost information corresponding to each construction step, and establish a cost management baseline for the large airport construction project.

3. A method for automatic control of the entire process of a construction project as claimed in claim 1, characterized in that: The step 2 comprises: Step 21: Obtain the contract bill of quantities and contract bill coding rules of the large airport construction project, divide the contract bill of quantities into several contract execution projects according to the contract bill coding rules, and respectively construct coding identification information corresponding to each of the contract execution projects; Step 22: Use the coded identification information to establish a cost identification information chain for the large airport construction project, use the cost management baseline to perform a cost scan on the contract bill of quantities, obtain the execution cost corresponding to each of the contract execution items, and mark each of the execution costs in the cost identification information chain to establish a cost verification information chain; Step 23: extracting the identification project cost value and the marking project cost value corresponding to each of the contract execution projects in the cost verification information chain, screening a category of contract execution projects whose identification project cost value and the marking project cost value are inconsistent, and establishing a first cost error range for the category of contract execution projects based on the corresponding project cost value differences; Step 24: Filter the second category contract execution projects whose identified project cost values ​​are consistent with the marked project cost values, match the corresponding second cost error range for each of the second category contract execution projects based on the preset cost error ratio, construct the cost error range corresponding to each of the contract execution projects, and construct the cost information corresponding to each of the contract execution projects.

4. A method for automatic control of the entire process of a construction project as claimed in claim 1, characterized in that: The step 3 comprises: Step 31: Determine the effective cost range corresponding to each of the contract execution items based on the cost information, construct an overall construction model of the large airport construction project according to the contract bill of quantities, run the overall construction model to determine the project execution steps corresponding to each of the contract execution items, and respectively determine the material quantity and material properties of the materials used corresponding to each of the project execution steps; Step 32: Determine the material cost corresponding to each material based on the material attributes, determine the cost weight corresponding to each material in combination with the corresponding material quantity, count the number of materials corresponding to each contract execution project, and allocate the cost to each material based on the corresponding cost weight and the effective cost range corresponding to the contract execution project; Step 33: Input the cost allocation result into the overall construction model for verification, obtain the material sufficiency characteristics corresponding to each of the project execution steps, adjust the cost of the used materials based on the material sufficiency characteristics, and generate a cost control plan corresponding to each of the contract execution projects; Step 34: During construction, determine the current contract execution project corresponding to the current construction progress, locate the qualified cost corresponding to the current contract execution project in the cost control plan, and use the qualified cost to perform cost control verification on the current contract execution project.

5. A method for automatic control of the entire process of a construction project as claimed in claim 4, characterized in that: Also includes: Determine the actual cost allocation corresponding to the current contract execution project based on the cost control verification results, and establish the cost qualification characteristics corresponding to each current project execution step; When the cost qualification feature is abnormal, the current actual execution process is determined, and an early warning message is generated and played.

6. A method for automatic control of the entire process of a construction project as claimed in claim 1, characterized in that: The step 4 comprises: Step 41: constructing the actual construction progress of the large airport construction project according to the execution start time corresponding to each of the contract execution items; Step 42: respectively obtain the control and verification information corresponding to each of the contract execution projects, and determine the construction cost accumulation information of the large airport construction project in combination with the actual construction progress; Step 43: Using the cost management baseline to perform cost evaluation on the construction cost accumulation information, and screening target contract execution projects with cost overruns; Step 44: Obtain the excess amount corresponding to the target contract execution project, locate the execution address corresponding to the target contract execution project, and issue a corresponding warning to the execution address.

7. A method for automatic control of the entire process of a construction project as claimed in claim 6, characterized in that: Also includes: Safety information is generated when the project is executed under the target contract without cost overruns.

8. A method for automatic control of the entire process of a construction project as claimed in claim 1, characterized in that: Also includes: The execution workload corresponding to each contract execution project is obtained respectively, and corresponding construction personnel are matched for each contract execution project according to the execution workload, and the work details corresponding to each construction personnel are generated and displayed.

9. A construction project full process automated control system, characterized in that: include: A preliminary budget module is used to analyze the preliminary design budget and preliminary execution budget of the large-scale airport construction project according to the coding structure of the large-scale airport construction project, and to build a cost management baseline for the large-scale airport construction project; A cost analysis module, used to obtain the contract bill of quantities of the large airport construction project, classify and analyze the contract bill of quantities using the cost management baseline, and obtain cost information corresponding to each contract execution item of the large airport construction project; A cost verification module, used to construct a cost control plan for the corresponding contract execution project using the cost information, and to perform cost control verification on each of the contract execution projects; The control and early warning module is used to construct the real-time cost of the large-scale airport construction project according to the control and verification information corresponding to each of the contract execution projects, locate the target contract execution projects with cost excesses in combination with the cost management baseline and issue early warnings.

10. A construction project full-process automated management and control system as claimed in claim 9, characterized in that: The preliminary budget module includes: A first execution unit is used to obtain the coding structure of the large airport construction project, determine the coding meaning corresponding to each structure bit according to the coding structure, and establish a semantic decoding rule for the large airport construction project according to a preset national standard list and a civil aviation standard list; The second execution unit is used to obtain several engineering codes of the large airport construction project, perform semantic analysis on each engineering code respectively by using the semantic decoding rule, obtain several semantic engineering information of the large airport construction project, and construct a construction concept structure of the large airport construction project by using the semantic engineering information; The third execution unit is used to hierarchically process the construction concept structure to obtain a plurality of independent substructures, establish a plurality of structural logical relationships of the large-scale airport construction project according to the connection relationships between different independent substructures, and establish a preliminary design budget of the large-scale airport construction project in combination with the structural foundation corresponding to each of the independent substructures; A fourth execution unit is used to analyze the construction material information corresponding to each of the independent substructures, determine the construction execution process corresponding to each of the independent substructures according to the construction method corresponding to each construction material, and generate a preliminary execution budget of the large airport construction project; The fifth execution unit is used to determine several construction steps of the large-scale airport construction project by using the preliminary design estimate of the project and the preliminary execution estimate of the project, and determine the cost information corresponding to each of the construction steps to establish a cost management baseline for the large-scale airport construction project.

Citation Information

Patent Citations

  • Systems and methods for project and program management using artificial intelligence

    CA3170083A1

  • Workflow control system of project implementation

    CN103177306A

  • Settlement control over-budget early warning method and system for engineering project

    CN112686579A

  • Cost refined management and control method and system based on bill of quantities

    CN116862597A

  • Engineering project cost control method and system based on EBS and bill of quantities

    CN117314120A

Cited By

  • Method and system for fully intelligently analyzing investment and progress deviation of engineering project