Whole-region 110kV high-voltage newly-installed power supply network capacity-increasing installation aided design management and control platform

Through the systematic management of the capacity-added and installed auxiliary design and control platform of the 110kV high-voltage new power supply network in the whole region, the problem that the management platform in the existing technology is unable to effectively manage the capacity-added and installed process of the 110kV high-voltage new power supply network is solved, and the project process is realized Standardization and risk monitoring improve the transparency and traceability of project management, ensuring the smooth completion of the project and data security.

CN118982330AInactive Publication Date: 2024-11-19STATE GRID ZHEJIANG ELECTRIC POWER CO LTD JINHUA POWER SUPPLY CO
View PDF 9 Cites 0 Cited by

Patent Information

Application Number
CN202411475225.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-22
Publication Date
2024-11-19
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing technology cannot effectively manage the capacity-added and installation process of the 110kV high-voltage new power supply network, resulting in difficulties in project feasibility judgment and completion implementation, and lack of effective management and monitoring methods.

Method used

A 110kV high-voltage new power supply network capacity-added auxiliary design management and control platform was designed in the region, including system management configuration module, target management module, resource management module, task process management module and risk management processing module, through which the project is realized Systematized management, resource allocation, progress monitoring and real-time monitoring and processing of potential risks.

Benefits of technology

The platform standardizes project processes, enhances the transparency and traceability of project management, ensures effective utilization of resources, improves the scientificity and foresight of project management, reduces information delays and misunderstandings, and ensures the smooth completion of the project and data security.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118982330A_ABST
    Figure CN118982330A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of engineering automation management, and aims to solve the problem that in the prior art, in the development process and the testing process, a management platform can only play a contact function and cannot realize effective management work. The invention discloses an area-wide 110kV high-voltage newly-installed power supply network capacity-increasing installation aided design management and control platform. The platform comprises a system management configuration module, a target management module, a resource management module, a task process management module and a risk management processing module. By the adoption of the technical scheme, it can be ensured that the started project is feasible, responsibilities and schedules of participating departments are allocated, possible problems in the middle are found in time, and it is ensured that the project can be completed smoothly. Once problems occur in the project execution process, records for corresponding processing are preset.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of engineering automation management, and in particular relates to an auxiliary design control platform for capacity increase reporting of a new 110kV high-voltage power supply network in the entire region. Background Art

[0002] The new installation and capacity increase of the 110kV power supply network is a difficult problem in the construction of the power grid, because the new installation and capacity increase of the higher voltage power supply network is studied and designed separately by the power design institute, and there is a comprehensive plan. Due to the particularity of the 110kV power supply network, its new installation and capacity increase registration authority requires coordination from multiple departments in the power system, such as the customer service department, development department, marketing department, construction department, operation and inspection department, material department, and control center. This involves a large number of departments, high professional requirements, and also involves the actual situation requirements of the location. In actual operation, it is necessary to temporarily establish a working group. Because the working group coordinates the work, but because of the large number of units involved, it is difficult to make decisions. The implementation of the entire plan also involves related tasks such as collecting funds and establishing an overall model, and sometimes there is a lack of specific implementation units.

[0003] The invention patent "A whole process control system for high voltage business expansion and installation in power marketing" with patent application number: 201510876622.5 in the prior art discloses a whole process control system for high voltage business expansion and installation in power marketing, which involves a control system. Business expansion and installation management is one of the traditional core businesses of power supply enterprises. The completion of its work directly affects the brand image and customer service level of power supply enterprises. With the increase of data, manual business expansion and installation work is no longer in line with development requirements. The invention includes: workbench function application module; project planning management module; project execution management module; project tracking management module; mobile terminal collaborative APP application module; project analysis management module. The technical solution cooperates with management responsibilities, carries out the multi-department joint collaboration process of business expansion and installation business, establishes a project-based planning management mechanism, optimizes and improves the existing business expansion and installation mode, carries out the whole process control of each link of high voltage business expansion and installation, and realizes milestone node management, thereby shortening the customer's power connection time, improving the completion rate of high voltage business expansion and installation capacity, and improving the satisfaction rate of high voltage business expansion customer return visits.

[0004] However, the whole system only plays a management role and is of no help in solving the technical problems encountered in the process of new installation and capacity increase of 110kV power supply network. Even if problems or hidden dangers are found in the project process, the construction party can only be reminded through early warning and urging. The construction party may ignore these warnings due to the progress of the project and maintenance costs, resulting in the early warning system being ineffective. In fact, for the power grid, there are two topics that need to be paid attention to in the process of new installation and capacity increase of 110kV power supply network. The first is to judge whether the project is really feasible before the project is established based on the existing conditions; the second is to ensure that the project can be completed normally and implemented to the end on the premise of confirming the feasibility of the project, but the existing technology management and control platform cannot ensure these two points. Summary of the invention

[0005] In order to solve the problem that the management platform can only play the role of communication and cannot achieve effective management work during the development and testing process of the existing technology, the solution proposed by the present invention is: an auxiliary design and control platform for capacity increase application of 110kV high-voltage new power supply network in the whole region, including a system management configuration module, a target management module, a resource management module, a task process management module, and a risk management processing module: the system management configuration module records the project login area and all the review departments and execution departments involved in the high-voltage new installation capacity increase application process in the region; The target management module obtains the requirements of a single project, collects the resources required for the approved 110kV power supply network and the workflow for executing the project, decomposes the workflow into specific nodes, and configures the resources required in each node. The resource management module finds the department information that can obtain the corresponding resources and perform the corresponding processing from the review department and execution department information in the system management configuration module, and obtains the target department that meets the requirements of the above project; conducts bidding work for the target department, and signs the corresponding contract with the winning bidder; After signing the contract with the target department, the system management configuration module receives the relevant contract for the capacity increase of the newly installed 110kV high-voltage power supply network, obtains the supplier and manager information of the resources required for the corresponding 110kV power supply network according to the content of the contract, and configures the review department and the execution department to each node according to the dependency relationship between the tasks and resources in each node. The nodes in the workflow are equipped with corresponding execution departments, and each execution department has a corresponding review department. When the resource configuration and the corresponding department configuration are completed, the project will be executed according to the project plan.

[0006] According to the contract information, a second bidding will be conducted from the units that did not win the bid, and the winning units of the second bidding will serve as the backup units for the corresponding nodes. In this way, when the first batch of winning units cannot complete the task according to the contract plan, the winning units of the second bidding will follow up the project progress. If the first batch of winning units successfully complete the task, the winning units of the second bidding will have priority to undertake the next type of project, thereby shortening the execution cycle of the next project.

[0007] Preferably, the specific method of configuring the resources required in each node is: set up X ij Indicates i Category of materials j The original data of the indicators i =1,2,..., n , j =1,2,..., m ,in n It is the category of materials. m is the number of indicators, and the data normalization formula is as follows: ; in, μ j It is j The mean of the indicators, σ j It is j The standard deviation of an indicator; p ij For the i The material is in j The ratio of the standardized value of an indicator to the total value of the indicator is calculated as follows: ; The first j Information entropy of an indicator H j The calculation formula is: ; where p ij Not 0; Calculate the coefficient of variation d j : ; The larger the coefficient of variation, the more important the indicator is in decision making; Calculate the weight of each indicator based on its coefficient of difference w j; ; A demand threshold is set for the highest-weighted materials, and the execution department will perform the work project after the materials that meet the demand threshold are prepared. In order to prevent the execution department from rashly carrying out work when the materials are ready, it is determined based on the characteristics of different projects whether the main materials preparation for the project is basically completed.

[0008] Preferably, a communication and coordination module is also provided, which is connected to the user's online chat, email, and conference software during the project through a desensitizing module, automatically obtains the organization and records of regular meetings, and automatically generates reports and sharing of work results from communication software. It should be noted that the information obtained by the communication and coordination module is approved by the relevant departments, and the source of information only involves part of the work content. The desensitizing module will automatically switch some private information to corresponding aliases, thereby taking into account convenience and privacy.

[0009] Preferably, the communication and coordination module is connected to the risk management processing module, and the risk management processing module has a monitoring and evaluation component: it realizes monitoring and evaluation of project progress and monitoring and evaluation of confidentiality at the same time. Monitor the progress of collaborative projects in real time and provide visual reports; support regular evaluation of collaborative effects and collect feedback from various departments. It also has the functions of providing system administrator tools to manage user permissions, system settings and backup and recovery, allowing the system to be customized and configured to meet the specific needs of different organizations. Most importantly, the risk management processing module compares the work reports actively submitted by the execution unit with the reports and sharing of work results automatically extracted by the communication and coordination module, and tries to find hidden dangers in the work progress. The audit department can also issue warnings or deal with hidden dangers as soon as possible.

[0010] Preferably, the following steps are performed on the platform: including a platform configuration stage and a platform use stage. In the platform configuration stage, after the system management configuration module determines to receive the task, it entrusts a qualified design unit to start the access system design work. Before starting the design, the project demander needs to log in to the platform first, verify the identity through the system management configuration module, and obtain submission authority. After obtaining the submission authority, the demander prepares materials and submits the application on the platform. This part of the work is usually reviewed by the Development Department, and the Customer Department then accepts the business and shares the acceptance information with the corresponding execution department; the design unit completes the design: the design content covers the overall planning and design of the access system to ensure that it meets the power grid operation requirements; thereafter, the access system design plan is reviewed, and the Development Department makes a system reply based on the review opinions; when the approval is a positive result, the feasibility study, project approval, and ERP project construction of the supporting power grid project are started simultaneously; otherwise, it is submitted to the superior management agency for review and approval.

[0011] Preferably, during the platform use phase, the task flow management module integrates the contract and the node to establish a project schedule with a timeline based on the contract information; the resource management module allocates permissions to each accessed user, and the review department and the execution department can only view part of their own work on the project schedule, and only the review department has the authority to edit the project schedule. The project schedule is provided with multiple time nodes, and the work on each time node has a completion threshold; The project progress management is carried out according to the project schedule. The project progress summary is carried out at the predetermined time or at predetermined intervals. Once the project progress is later than expected at a certain stage, the feasibility of the project catching up will be re-evaluated based on the nodes. If the feasible probability of the project catching up is lower than the preset threshold, the backup plan will be directly adopted.

[0012] Preferably, the audit department includes a main audit department and an auxiliary audit department. The main audit department includes at least the information and contact information of the department head and the daily work contact person. When the project progress enters different stages, the corresponding main audit department and auxiliary audit department at each time node will be adjusted accordingly.

[0013] Preferably, in a project schedule with a timeline, each review management department needs to use DS synthesis rules to ensure the accuracy of the project schedule.

[0014] Preferably, the basic steps of the DS synthesis rule include: S1: Define Basic Probability Assignment (BPA): Assign a basic trust assignment function, i.e., BPA, to each subset in a proposition set (identification framework Θ) for each source of evidence obtained by the audit department through its own functions and each source of evidence provided by the execution department. BPA satisfies the following conditions: Distrust of the empty set, that is ; The sum of trust is 1, that is ; S2: Calculate the conflict factor: When merging two BPAs, it is necessary to calculate the degree of conflict between them. The conflict factor is given by the following formula: ; Among them, m1 and m2 are the basic probability assignment functions of the two evidence sources, and the two evidence sources cannot belong to the audit department or the execution department at the same time. A and B are different propositions they support respectively; if k=1, it means that the two evidences are completely consistent; if k is close to 1, the conflict is small; if k is very small, the conflict is large. Apply DS synthesis rule: Dempster synthesis rule is the core part of DS synthesis rule, which defines the combination of the trust of two evidence sources. If k ≠0, the basic probability assignments of the two evidence sources can be combined by the following rules: ; Where m(C) is the combined basic probability assignment, which represents the degree of trust in proposition C under the joint support of proposition A and proposition B. Note that for the empty set , whose trust is always 0 (i.e. ).

[0015] Preferably, each module is maintained by a different audit department, and the maintenance includes regular maintenance and maintenance before project approval.

[0016] The present invention also includes a device, comprising: a processor, and a memory connected to the processor; The memory is used to store a computer program, and the computer program is used to execute a method for using a regional 110kV high-voltage new power supply network capacity increase reporting auxiliary design management and control platform.

[0017] Due to the adoption of the technical solution, the final beneficial effects that can be achieved by the technical solution mainly include the following aspects: Through the systematic management platform, the entire process of 110kV high-voltage new installation and capacity increase project is standardized, from project application, review, design, approval to implementation, each link has clear modules and process support. Most importantly, in this process, there is also a monitoring system for the entire process to avoid the problem of poor execution by the execution unit and the lack of handling means by the review unit.

[0018] Based on the project itself, the transparency and traceability of project management are enhanced. All project information and progress are recorded in the system. The review department and the execution department can view and edit relevant information at any time, which enhances the transparency of project management. By establishing a detailed project schedule and node monitoring, it is ensured that the work of each link is well documented, which improves the traceability of the project. In particular, based on this feature, the progress reported by the department is compared with the progress collected by the system itself, which can correct erroneous information in time and obtain the actual progress of the project more accurately.

[0019] Through the resource management module, resources are reasonably allocated according to project requirements, and each node is ensured to have a corresponding execution department and review department, which improves resource utilization efficiency. Cross-departmental collaboration is smoother, and departments share information and tasks through the system platform, reducing delays and misunderstandings in information transmission.

[0020] The risk management processing module monitors project progress and confidentiality in real time, provides visual reports and regular assessments, and helps management identify potential risks in a timely manner and take countermeasures. Through methods such as DS synthesis rules, the accuracy and reliability of project progress are ensured, and the scientificity and predictability of project management are improved. Strengthen data security and privacy protection, and ensure the security of user data and sensitive information during transmission and storage through information desensitization modules and other security measures. The system also has permission management functions to limit access rights of different users and prevent data leakage and illegal access.

[0021] In summary, the present invention can ensure that the initiated project is feasible, allocate the responsibilities and progress of the participating departments, timely discover the problems that may arise in the middle, and ensure that the project can be successfully completed. Once a problem occurs during the execution of the project, a corresponding processing record is preset. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings in the following description are only some embodiments of the present invention.

[0023] Figure 1 It is a schematic diagram of the overall architecture of the regional 110kV high-voltage new power supply network capacity increase reporting auxiliary design control platform of the present invention.

[0024] Figure 2 It is a schematic diagram of the work flow in the auxiliary design and control platform for capacity increase application of the new 110kV high-voltage power supply network in the whole region of the present invention. DETAILED DESCRIPTION

[0025] The following will be combined with the accompanying drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. It can be understood that the specific implementation methods described here are only used to explain the relevant content, rather than to limit the present disclosure.

[0026] First, the applicant explains the necessity of the application of the present invention. The power supply enterprise shall, in accordance with the provisions of the "Power Supply Business Rules" on power application and installation, the uniformly issued service commitments and service specifications, organize on-site surveys, formulate power supply plans of 10kV and above voltage levels, collect relevant business fees from users, track the establishment, design, drawing review, project budget, equipment supply, and construction process of power supply projects (external projects), organize drawing review, intermediate inspection, and completion acceptance of power receiving projects, sign power supply contracts with users, and provide meter installation and power transmission, completing the whole process of filing and household registration management. For example, the power planning of a certain area clearly states that it is necessary to build ahead of time and improve the power grid structure based on the principles of "safety, economy, more supply, and less loss". The planning goal is to form a relatively complete 110kV power grid to replace the original low-voltage power grid and become the main supply grid of the urban power grid. At the same time, it is also planned to build and renovate medium and low voltage power grids to complete the established planning tasks. In order to properly implement such project promotion, a unified management and control platform is needed to coordinate the ongoing power grid construction in the entire region, cover as comprehensively as possible and avoid duplication of construction. In fact, similar management and control platforms already exist in the existing technology, and modules are set in the platform to track and promote projects. However, such a management and control platform actually only has a display effect. Because the users have almost equal rights on the platform. Even if the audit department finds that the execution department has not been able to work in accordance with the contract agreement or the pre-established project schedule, it is actually unable to effectively manage the execution department. The audit department can only mark warnings in the project or urge the execution department to do their work through interviews, but it cannot force the execution department to provide further work, which will lead to the execution department If it is actually unable to fully perform the contract or implement the project according to the pre-agreed project schedule, the entire project will stagnate. At this time, if the execution department is temporarily replaced or the corresponding goods are purchased, some unexpected additional costs will be incurred and huge losses caused by the delay of the project schedule will be borne.

[0027] However, due to such characteristics, the relevant review department has greater authority in the whole process and has greater constraints on the execution department. This is also the premise for the implementation of the present invention.

[0028] Since the present invention involves a number of similar but different technical terms in the computer field, they are first explained one by one here: ERP project construction work: In this invention, it refers to the general term for a series of work carried out in the process of implementing the ERP (Enterprise Resource Planning) system. The ERP system is an integrated management information system that aims to help enterprises centrally manage various business data, including sales, procurement, inventory, production and other links, so as to achieve efficient management of the enterprise.

[0029] Regarding the audit department, the audit department involved in the present invention includes: Development Department: As the main department responsible for initially determining the project's principle opinions and initiating the access system design work, it is mainly responsible for reviewing the project's preliminary planning, feasibility studies, etc.

[0030] Marketing Department: Participate in the review of content related to user needs, electricity contracts, etc.

[0031] Ministry of Construction: Review the feasibility of the design plan, the rationality of the construction plan, the project quality standards, etc.

[0032] Operation and Maintenance Department: Assess the possible impact of operation and maintenance.

[0033] Control Center: The control center is responsible for the dispatching and operation control of the power grid, reviews the impact of the project on the dispatching and operation of the power grid, and ensures the safety and stability of the power grid during the implementation of the project.

[0034] The execution department includes the material department, as well as the actual construction units and outsourcing units. At different time points, the main audit department and the auxiliary audit department will switch with each other, and the audit department and the execution department will also switch with each other. The execution ability of the execution department will be monitored and verified accordingly. The specific method is to judge the actual ability of the execution department by defining evaluation dimensions and weights.

[0035] First, identify the dimensions to be evaluated (such as financial status, company size, past performance, etc.) and assign a weight (w_i) to each dimension. The sum of the weights should be 1.

[0036] Standardized scoring: For each evaluation dimension, a scoring standard is designed and a score (s_i) is given based on the company's actual performance. It is usually necessary to convert the original data into a numerical value between 0 and 1, or to grade the score according to certain standards.

[0037] Weighted summation: Multiply the score of each dimension by the corresponding weight and add them up to obtain the company's comprehensive contract performance ability score (S).

[0038] The formula is as follows: ; Where n is the number of evaluation dimensions, s_i is the score of the ith dimension, and w_i is the weight of the ith dimension.

[0039] Define evaluation dimensions and weights: Financial status (w_1 = 0.2) Firm size (w_2 = 0.15) Past performance (w_3 = 0.25) Management and technical team (w_4 = 0.15) Contract management and compliance (w_5 = 0.15) Supply Chain and Partners (w_6 = 0.1) Standardized scoring (financial status is used as an example here, and other dimensions are handled similarly): Set scoring criteria, such as giving a comprehensive score based on indicators such as debt-to-asset ratio and current ratio.

[0040] Input the actual financial indicators of the enterprise into the scoring criteria and obtain the financial status score s_1 (0 ≤ s_1 ≤ 1).

[0041] Weight allocation: The allocation of weights should be based on business understanding and expert judgment, and may need to be adjusted based on actual circumstances.

[0042] Scoring criteria: The formulation of scoring criteria needs to be detailed and fair to ensure that it accurately reflects the actual situation of the enterprise.

[0043] Data collection and verification: The effectiveness of the algorithm depends on the accuracy and completeness of the input data, so an effective data collection and verification mechanism needs to be established.

[0044] Algorithm iteration: As the business develops and the external environment changes, the algorithm may need to be iterated and optimized regularly.

[0045] like Figure 1 As shown, on the basis of the above, the present invention builds a regional 110kV high-voltage new power supply network capacity increase application auxiliary design management and control platform construction process: including system management configuration module, target management module, resource management module, task process management module, risk management processing module: the system management configuration module records the project login area and all the review departments and execution departments involved in the high-voltage new installation capacity increase application process in the area; The target management module obtains the requirements of a single project, collects the resources required for the approved 110kV power supply network and the workflow for executing the project, decomposes the workflow into specific nodes, and configures the resources required in each node; The resource management module finds the department information that can obtain corresponding resources and perform corresponding processing from the audit department and execution department information in the system management configuration module, and obtains the object department that meets the requirements of the above project.

[0046] All work related to capacity expansion of a single 110kV high-voltage new power supply network must be carried out after the contract is signed.

[0047] First, you need to upload the contract. The audit system analyzes and audits the uploaded contract. During the contract review process, at least the following information must be confirmed: Basic information of both parties: First, you need to confirm the basic information of both parties to the contract, including company name, address, legal representative, etc., to ensure that the contract subject is clear. In particular, as the actual design and construction party B, it needs to be a designated unit that has been registered in the platform. At the same time, it is necessary to determine whether the identity of the signatory is consistent with the content of the contract, whether the official seal is correct, and whether the seal is authentic, so as to avoid unnecessary losses caused by obtaining the wrong contract.

[0048] After confirming the contract, analyze the project scope and description: review the scope, scale, specific work content and other descriptions of the 110kV high-voltage new power supply network capacity increase application business in the contract in detail, and reflect them again in the platform's proprietary format for Party A to confirm again to avoid misunderstandings. After Party A confirms, the platform will analyze the scope, scale, and specific work content of the 110kV high-voltage new power supply network capacity increase application business and find the departments related to this project.

[0049] These departments have already registered in the platform, and reminders will be activated after the contract review is passed.

[0050] Through various departments. Review whether the technical standards, construction specifications, equipment specifications, etc. involved in the contract meet the industry standards and legal and regulatory requirements to ensure the professionalism and compliance of the project. On this basis, schedule and progress arrangements are made: extract and decompose the terms of the contract regarding the project schedule, progress plan, milestone nodes, etc., and implement them to the actual relevant departments, and anchor the relevant responsible persons of each department to ensure that the project can be completed on time, while clarifying the responsibilities and obligations of both parties. Finally, a node based on the confirmed project is formed.

[0051] If necessary, a third party can be introduced. The third party can be a superior unit or other qualified supervision unit to ensure the quality and safety of the project. The qualifications of the third party need to comply with the terms of the contract regarding quality standards and safety measures to ensure that the quality and safety of the project construction process are effectively guaranteed.

[0052] like Figure 2As shown, the specific method of using the present invention is as follows: the following steps are performed on the platform: including a platform configuration stage and a platform use stage. In the platform configuration stage, after the system management configuration module determines to receive the task, it entrusts a qualified design unit to start the access system design work. Before starting the design, the project demander needs to log in to the platform first, and verify the identity through the system management configuration module, and obtain the submission authority. After obtaining the submission authority, the demander prepares the materials and submits the application in the platform. After the business acceptance is passed and the acceptance information is shared with the corresponding execution department; the design unit completes the design: the design content covers the overall planning and design of the access system to ensure that it meets the power grid operation requirements; thereafter, the access system design plan is reviewed, and the system is approved according to the review opinions; when the approval is a positive result, the supporting power grid project feasibility study, project approval, and ERP project construction work are started simultaneously; otherwise, it is submitted to the superior management authority for review and approval.

[0053] During the platform use phase, the task process management module integrates contracts and nodes to establish a project schedule with a timeline based on contract information; the resource management module allocates permissions to each connected user, and the review department and the execution department can only view part of their own work on the project schedule. There are multiple time nodes on the project schedule, and the work on each time node has a completion threshold; The project progress management is carried out according to the project schedule. The project progress summary is carried out at the predetermined time or at predetermined intervals. Once the project progress is later than expected at a certain stage, the feasibility of the project catching up will be re-evaluated based on the nodes. If the feasible probability of the project catching up is lower than the preset threshold, the backup plan will be directly adopted.

[0054] During the construction process, the division of labor of each department and each person in a single department is clarified, and the project schedule is marked based on this information. Further arrangements are made for the construction organization of workers in different projects, and the specific time for completing a certain module is formulated. According to these time arrangements, the project schedule is finely cut and divided based on time to obtain multiple time-based nodes. As the construction progresses, each node is marked with different colors to determine whether it is in accordance with the time schedule. If a single node deviates too much from the progress, an alarm will be issued. Delaying progress will affect the re-registration of relevant departments in the platform later.

[0055] In this process, each audit management department needs to ensure accuracy through the DS synthesis rule. DS evidence theory (Dempster-Shafer theory of evidence) is a mathematical theory for processing uncertain information, which is very useful in the present invention for processing incomplete information and subjective judgment. Its core idea is to comprehensively evaluate the authenticity of a proposition through the degree of trust in a proposition by multiple sources of evidence. Based on the concept of a discernment framework, this discernment framework is a set of all possible answers to a question. In this set, each element (or subset) is regarded as a proposition, representing a possible result or state. DS evidence theory assigns a basic probability assignment function (BPA), also known as a mass function, to each proposition. This function maps a proposition to a value between [0,1], indicating the degree of trust in the proposition. The sum of the trust of all propositions is 1, and the trust of the empty set is 0. When there are multiple sources of evidence (i.e., the various departments in the present invention) providing trust in the construction progress, the DS synthesis rule is used to merge these trusts. Specifically, the DS synthesis rule achieves fusion by calculating the joint confidence of two or more evidence sources for the same proposition. This process involves performing an orthogonal sum operation on the confidence of the evidence sources to obtain a new confidence assignment.

[0056] The DS combination rule (Dempster's rule of combination) is a core part of the theory, which is used to combine evidence from different sources to form a unified trust distribution. In the present invention, the basic steps of the DS combination rule include: S1: Define Basic Probability Assignment (BPA): Assign each source of evidence obtained by the audit department through its own functions and each source of evidence provided by the execution department to a set of propositions (identification framework) ) is assigned a basic trust allocation function, namely BPA, which satisfies the following conditions: Distrust of the empty set, that is , The sum of trust is 1, that is ; At this time, it is necessary to determine the identification framework and clarify all possible states of the project progress, such as "on time completion", "delayed", "ahead of schedule", etc., to form the identification framework . And collect project progress information from different sources such as project managers, construction teams, supervisors, from their work logs, and the system automatically obtains information from sources such as chat records, which serves as corresponding evidence. For each source of evidence, define a basic trust allocation function based on its evaluation of the project progress status. For example, the project manager believes that the probability of "completing on time" is 0.8, and the probability of "delay" is 0.2. Use the Dempster synthesis rule to synthesize the basic trust allocation functions of multiple evidence sources into a new trust allocation function. In this process, conflicts between evidence need to be considered, and conflict resolution may be required.

[0057] S2: Calculate the conflict factor: When merging two BPAs, it is necessary to calculate the degree of conflict between them. The conflict factor is given by the following formula: ; Where m1 and m2 are the basic probability assignment functions of the two evidence sources, and the two evidence sources cannot be from the audit department or the execution department at the same time. A and B are different propositions they support respectively; if k=1, it means that the two evidences are completely consistent; if k is close to 1, the conflict is small; if k is very small, the conflict is large.

[0058] Apply DS synthesis rule: Dempster synthesis rule is the core part of DS synthesis rule, which defines the combination of the trust of two evidence sources. k ≠0, the basic probability assignments of the two evidence sources can be combined by the following rules: .

[0059] Here, m(C) is the combined basic probability assignment, which represents the degree of confidence in proposition C under the joint support of proposition A and proposition B. Note that for the empty set , whose trust is always 0 (i.e. ). Based on the synthesized trust allocation function, a comprehensive judgment on the overall project progress is formed. For example, if the synthesis result shows that the probability of "on time completion" is the highest, it can be considered that the overall progress of the project is in line with expectations. Feedback the comprehensive judgment results to relevant departments and personnel, and adjust or optimize the project progress according to the actual situation.

[0060] The DS synthesis rule allows for handling partial conflicts, that is, it allows for certain inconsistencies between evidence. k = 0, it means that the two pieces of evidence are completely in conflict, and the DS synthesis rule cannot be directly applied at this time. However, this situation will not occur in the present invention.

[0061] Through the DS synthesis rule, we can integrate uncertain information from different evidence sources in one node, thereby obtaining a more accurate and comprehensive trust evaluation of a proposition. This evaluation will be compared with the preset threshold to determine whether the work progress of the node is within the expected range.

[0062] If a single node works slower than expected during the construction process, the reason for the slow construction of the work on the node is recorded. Through the big data service, in the process of adding new construction, the possible situation that may cause the construction cycle to be lower than expected is predicted in advance, and a preliminary solution is automatically generated accordingly.

[0063] Each node contains multiple layers of information, and the information displayed varies depending on the identity of the visitor. The final complete model can be directly connected to the power control system for use.

[0064] Finally, obtain the current quality traceability requirements, find and determine the information that matches the requirements in the completed model based on the requirements, and verify that the quality traceability requirements are met from the model.

[0065] Responding to customer needs: The platform described in the present invention can meet the access of different users, including the customers who initially proposed the needs, and respond to customers' electricity service needs in a timely manner, including electricity application, solution consultation, etc. By placing the needs into the platform, automatic cross-departmental collaborative processing can be achieved. The marketing department no longer needs to convey customer needs to relevant departments. Each department can coordinate processing according to the tasks assigned by the platform and their own division of responsibilities to ensure the efficient advancement of the project.

[0066] This optimizes processes and mechanisms, improves service efficiency and reduces customer waiting time by optimizing workflows and establishing efficient collaboration mechanisms. During the entire service cycle, the platform regularly evaluates work performance: superiors can also access the platform at any time for spot checks, identify problems in a timely manner and make improvements.

[0067] The platform also has a separate feedback mechanism to establish a customer feedback channel. When customers are unable to communicate smoothly with the service department at the front end, the platform can collect and process customer opinions and suggestions in a timely manner to continuously improve the service process.

[0068] Take a company's application for a 110kV high-voltage new power supply network capacity expansion project as an example. In the prior art, similar projects usually take more than 320 days. By adopting the technical solution described in the present invention, it takes 270 days from the application for electricity to the commissioning, which actually saves nearly 2 months. In this process, the entire project involves the communication and coordination of the marketing department, development department, construction department, material department, control center, operation and inspection department, information and communication branch and other departments and relevant execution departments. But more importantly, many engineering projects in the prior art may be unfinished due to some reasons during the execution process, while the use of the system described in the present invention basically prevents the occurrence of unfinished projects.

[0069] In another project, although it took more than 400 days from the application for electricity to the commissioning, the first executing unit was unable to complete the project on schedule, and the second executing unit took over the work and completed it.

[0070] The present invention also relates to a device, comprising: a processor, and a memory connected to the processor; the memory is used to store a computer program, and the computer program is used to adopt the regional 110kV high-voltage new power supply network capacity increase reporting auxiliary design management and control platform; the processor is used to call and execute the computer program in the memory.

[0071] Although the present invention is disclosed as above with preferred embodiments, it is not intended to limit the scope of the present invention. Any person of ordinary skill in the art can make some improvements without departing from the scope of the present invention, that is, all equivalent improvements made in accordance with the present invention should be covered by the scope of the present invention. In the description of this specification, the description of reference terms "an embodiment / method", "some embodiments / methods", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment / method or example are included in at least one embodiment / method or example of the present application. In this specification, the schematic representation of the above terms does not necessarily target the same embodiment / method or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments / methods or examples in a suitable manner. In addition, without contradicting each other, a person of ordinary skill in the art can combine and combine the different embodiments / methods or examples described in this specification and the features of different embodiments / methods or examples.

[0072] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of this application, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0073] Those skilled in the art should understand that the above embodiments are only for the purpose of clearly illustrating the present disclosure, and are not intended to limit the scope of the present disclosure. For those skilled in the art, other changes or modifications may be made based on the above disclosure, and these changes or modifications are still within the scope of the present disclosure.

Claims

1. The regional 110kV high-voltage new power supply network capacity increase application auxiliary design control platform is characterized by: It includes system management configuration module, target management module, resource management module, task process management module and risk management processing module: the system management configuration module records the project login area and all the review departments and execution departments involved in the high-voltage new installation and capacity increase application process in the area; The target management module obtains the requirements of a single project, collects the resources required for the approved 110kV power supply network and the workflow for executing the project, decomposes the workflow into specific nodes, and configures the resources required in each node; The resource management module finds the department information that can obtain the corresponding resources and perform the corresponding processing from the review department and execution department information in the system management configuration module, and obtains the object department that meets the requirements of the above project; After signing the contract with the target department, the system management configuration module receives the relevant contract for the capacity increase of the newly installed 110kV high-voltage power supply network, obtains the supplier and manager information of the resources required for the corresponding 110kV power supply network according to the content of the contract, and configures the review department and the execution department to each node according to the dependency relationship between the tasks and resources in each node. The nodes in the workflow are equipped with corresponding execution departments, and each execution department has a corresponding review department. When the resource configuration and the corresponding department configuration are completed, the project will be executed according to the project plan.

2. The regional 110kV high-voltage new power supply network capacity increase application auxiliary design management and control platform as claimed in claim 1, characterized in that: The specific method of configuring the resources required in each node is: X ij Indicates i Category of materials j The original data of the indicators i =1,2,..., n , j =1,2,..., m ,in n It is the category of materials. m is the number of indicators, and the data normalization formula is as follows: ; in, μ j It is j The mean of the indicators, σ j It is j The standard deviation of an indicator; p ij For the i The material is in j The ratio of the standardized value of an indicator to the total value of the indicator is calculated as follows: ; The first j Information entropy of an indicator The calculation formula is: ; where p ij Not 0; Calculate the coefficient of variation: ; Calculate the weight of each indicator based on its coefficient of difference w j; ; A demand threshold is set for the materials with the highest weight, and the execution department performs the work project after the materials that meet the demand threshold are prepared.

3. The regional 110kV high-voltage new power supply network capacity increase application auxiliary design management and control platform as claimed in claim 1, characterized in that: There is also a communication and coordination module, which is connected to the user's online chat, email, and conference software during the project through a desensitizing module, automatically obtains the organization and records of regular meetings, and automatically generates reports and sharing of work results from the communication software.

4. The regional 110kV high-voltage new power supply network capacity increase application auxiliary design management and control platform as claimed in claim 3, characterized in that: The communication and coordination module is connected to the risk management processing module, and the risk management processing module has a monitoring and evaluation component: it simultaneously realizes the monitoring and evaluation of the project progress and the monitoring and evaluation of confidentiality, and the evaluation result is the basis for replacing the execution department of a single node.

5. A regional 110kV high-voltage new power supply network capacity increase application auxiliary design management and control platform as claimed in claim 1, characterized in that: The following steps are carried out on the platform: including the platform configuration stage and the platform use stage. In the platform configuration stage, after the system management configuration module determines the acceptance of the task, it entrusts a qualified design unit to start the access system design work. Before starting the design, the project demander needs to log in to the platform first, verify the identity through the system management configuration module, and obtain the submission authority. After obtaining the submission authority, the demander prepares the materials and submits the application on the platform. After the business acceptance is passed and the acceptance information is shared with the corresponding execution department; The design is completed by the design unit: the design content covers the overall planning and design of the access system to ensure that it meets the grid operation requirements; after that, the access system design plan is reviewed and the system is approved based on the review opinions; When the approval is positive, the feasibility study, project approval and ERP project establishment of the supporting power grid project will be started simultaneously; Otherwise, it shall be submitted to the superior management authority for review and approval.

6. A regional 110kV high-voltage new power supply network capacity increase application auxiliary design management and control platform as claimed in claim 5, characterized in that: During the platform use phase, the task flow management module integrates contracts and nodes to establish a project schedule with a timeline based on contract information; The resource management module assigns permissions to each user. The review department and the execution department can only view part of their own work on the project schedule. There are multiple time nodes on the project schedule, and the work at each time node has a completion threshold. The project progress management is carried out according to the project schedule. The project progress summary is carried out at the predetermined time or at predetermined intervals. Once the project progress is later than expected at a certain stage, the feasibility of the project catching up will be re-evaluated based on the nodes. If the feasible probability of the project catching up is lower than the preset threshold, the backup plan will be directly adopted.

7. A regional 110kV high-voltage new power supply network capacity increase application auxiliary design management and control platform as claimed in claim 5, characterized in that: The audit department includes the main audit department and the auxiliary audit department. The main audit department at least includes the information and contact information of the department head and the daily work contact person. When the project progress enters different stages, the main audit department corresponding to each time node will be adjusted accordingly.

8. A regional 110kV high-voltage new power supply network capacity increase application auxiliary design management and control platform as claimed in claim 7, characterized in that: In the project schedule with a timeline, each review management department needs to use the DS synthesis rule to ensure the accuracy of the project schedule. The basic steps of the DS synthesis rule include: S1: Define basic probability assignment: assign a basic trust assignment function, i.e., BPA, to each subset of a proposition set for each source of evidence obtained by the audit department through its own functions and each source of evidence provided by the execution department. BPA satisfies the following conditions: Distrust of the empty set, that is ; The sum of trust is 1, that is ; S2: Calculate the conflict degree: When merging two basic trust allocation functions, calculate the degree of conflict between them. The conflict degree is given by the following formula: ; Where m1 and m2 are basic probability assignment functions of two evidence sources, and the two evidence sources cannot be from the review department or the execution department at the same time, and A and B are different propositions they support respectively; Apply DS synthesis rules: k ≠0, the basic probability assignments of the two evidence sources are combined by the following rules: ; Where m(C) is the combined basic probability assignment, which represents the degree of trust in proposition C under the joint support of proposition A and proposition B.

9. A regional 110kV high-voltage new power supply network capacity increase application auxiliary design management and control platform as claimed in claim 5 or 6, characterized in that: Each module is maintained by a different review department, and the maintenance includes regular maintenance and maintenance before project approval.

10. A device, characterized in that: include: A processor, and a memory connected to the processor; The memory is used to store a computer program, and the computer program is used to execute the method for using a regional 110kV high-voltage new power supply network capacity increase reporting auxiliary design management and control platform as described in any one of claims 5-9.

Citation Information

Patent Citations

  • High-voltage business expansion overall process management and control system of power marketing

    CN105427091A

  • Progress monitoring method used for laboratory engineering construction

    CN107273587A

  • A power supply company project data management platform

    CN109685452A

  • Highway construction progress intelligent prediction method and system

    CN117829382A

  • Road construction project cooperative work system

    CN118134431A