New and old pavement splicing structure in highway extension and construction method

By setting up staggered support resistance components in the highway expansion, the problem of difficulty in controlling vertical deformation at road splicing in the prior art is solved, the shear resistance and stability at the joints of new and old roads is improved, and the bearing capacity of the road surface is ensured. and durability.

CN118996947APending Publication Date: 2024-11-22HEBEI JIAOJIAN ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411421471.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-12
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The prior art is difficult to effectively control the vertical deformation at the road splicing, resulting in insufficient shear strength at the road splicing, affecting the bearing capacity and durability of the road surface.

Method used

Using the new and old pavement splicing structure in the highway expansion including the first and second resistance components, the deformation resistance at the joints of the new and old roads is enhanced, and the vertical and horizontal directions are distributed. Deformation force.

Benefits of technology

It improves shear resistance and stability at the joints of old and new roads, enhances deformation resistance at the joints of road surfaces, and ensures the bearing capacity and durability of the road surface.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118996947A_ABST
    Figure CN118996947A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of road splicing, in particular to a new and old pavement splicing structure in highway extension and a construction method. Comprising a first resistance assembly arranged on the horizontal plane of a step, and a second resistance assembly is detachably arranged on the first resistance assembly and used for being matched with the vertical plane of the step; the first resistant component is provided with a first matching surface matched with the old pavement and a second matching surface matched with the new pavement, a deep part deep into the new pavement is arranged at the first resistant component, and the deep part forms staggered support in the vertical direction. In the invention, the first resistance assembly and the second resistance assembly which are located at the joint of the horizontal plane of the step and the vertical plane of the step can tie the deformation force at the joint of the new and old roads in the horizontal and vertical directions, so that the deformation resistance of the connection of the new and old roads is improved; and the second resistant component can support the deep part, deep into the new road surface, of the first resistant component to form staggered support.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of road splicing, and in particular to a new and old road surface splicing structure and a construction method in highway expansion. Background Art

[0002] With the rapid development of China's national economy, traffic volume has increased rapidly, and some roads are in urgent need of expansion and reconstruction. When the road is expanded, the old road surface needs to be spliced ​​with the new road surface. During the splicing construction of the new and old roads, the old road surface structure layer needs to be milled to present a stepped splicing part.

[0003] The steps at the pavement joints usually have a certain inclination angle, mainly to ensure the effective connection and overall stability of the new and old pavements. This inclination angle helps prevent the roadbed from sliding and increases the shear strength of the pavement joints, thereby improving the pavement's bearing capacity and durability.

[0004] In the prior art, in order to cope with the deformation generated at the pavement joint, a geogrid is usually set at the plane position of the stepped joint. Although this method can control the horizontal deformation of the newly filled roadbed, it cannot effectively control the vertical deformation of the pavement joint. Summary of the invention

[0005] The invention provides a new and old road surface splicing structure in highway expansion, which can overcome the defect in the prior art that it is difficult to effectively control the deformation of the road splicing portion.

[0006] According to the present invention, a new and old road surface splicing structure in highway expansion includes a step excavated in the old road surface structure layer, the step has a step horizontal surface and a step vertical surface, and is characterized in that it includes a first resistance component for being arranged at the step horizontal surface, a second resistance component is detachably arranged at the first resistance component, and the second resistance component is used to cooperate with the step vertical surface; The first resistance component has a first mating surface that matches with the old road surface and a second mating surface that matches with the new road surface. The first resistance component is provided with a deep portion that penetrates into the new road surface, and the deep portion forms a staggered support along the vertical direction.

[0007] In the present invention, the first resistance component and the second resistance component located at the connection between the horizontal surface of the step and the vertical surface of the step will pull the horizontal and vertical deformation forces of the connection between the new and old roads, so as to improve the anti-deformation ability of the connection between the new and old roads. The second resistance component will support the deep part of the first resistance component that penetrates into the new road surface, forming a staggered support. It can be understood that when the connection between the new road surface or the old road surface is subjected to stress, the deep part will drive the connection between the other side of the road surface that is not subjected to stress to be subjected to stress synchronously, thereby increasing the shear resistance of the connection between the new and old roads, and the second resistance component will disperse the stress of the new and old road surfaces into the connection between the new and old road surfaces at different steps, thereby improving the deformation resistance of the road connection.

[0008] Preferably, the first resistance component includes a first mounting rod installed on the horizontal plane of the step, multiple first mounting rods are arranged along the excavation direction of the horizontal plane of the step, a first earth grid is arranged between the multiple first mounting rods, a first fixing piece is arranged on the top of the outer wall of the first mounting rod, and the first earth grid is connected to the first fixing piece.

[0009] In the present invention, the first civil engineering grid is fixed between the first mounting rods by the first fixing member. After the new and old roads are connected, the first civil engineering grid will pull the horizontal deformation force of the new and old roads, thereby enhancing the horizontal deformation resistance of the road connection.

[0010] Preferably, the second resistance component includes a second mounting rod installed on the vertical surface of the step, multiple second mounting rods are arranged along the excavation direction of the vertical surface of the step, a second civil grid is arranged between the multiple second mounting rods, a second fixing piece is arranged on the top of the outer wall of the first mounting rod, and the second mounting rod is connected to the second fixing piece.

[0011] In the present invention, by installing the second mounting rod on the vertical surface of multiple steps, and installing the second civil grid between multiple second fixing members through the second fixing member, the second civil grid will pull the vertical deformation force of the new and old roads, thereby enhancing the vertical deformation resistance of the connection between the new and old roads.

[0012] Preferably, a connecting component is provided between the first resistance component and the second resistance component, and the connecting component is used to connect the first resistance component and the second resistance component to each other.

[0013] In the present invention, the second mounting rod on the second resistance component will support and fix the first mounting rod on the first resistance component, thereby improving the control effect of the first resistance component on vertical deformation, and the second mounting rod is connected to the first mounting rod. When the connection between the new and old roads is subjected to external force, the external force can be dispersed to steps of different heights through the second mounting rod, thereby improving the deformation resistance of the connection between the new and old roads.

[0014] Preferably, the first mounting rod has a first sliding groove and a second sliding groove at the upper and lower ends of the outer wall thereof, respectively, and the connecting assembly comprises a first sliding member and a second sliding member which are slidably arranged at the first sliding groove and the second sliding groove, respectively, and a first connecting member which is rotatably connected to the bottom of the second mounting rod is rotatably arranged at the first sliding member, and a second connecting member which is rotatably connected to the top of the second mounting rod is rotatably arranged at the second sliding member.

[0015] In the present invention, through the first connecting member and the second connecting member, the first mounting rods at different heights of the upper and lower layers can be fitted on the horizontal surface of the step while ensuring that the second mounting rod is in a vertical state, thereby achieving stable support for the first mounting rod. In addition, by adjusting the first sliding member and the second sliding member, the supporting position of the second mounting rod on the first mounting rod can be changed, thereby improving the applicability of the device when installed on the horizontal surfaces of steps of different sizes.

[0016] Preferably, a first anti-slip groove is provided on both sides of the first sliding groove and the second sliding groove, and both sides of the outer walls of the first sliding member and the second sliding member have a first anti-slip portion slidably connected to the first anti-slip groove, and a first positioning hole is provided between the first sliding groove and the second sliding groove, and a first positioning bolt for limiting the first sliding member and the second sliding member is provided in the first positioning hole.

[0017] In the present invention, after the first sliding member and the second sliding member slide to a fixed position, the first positioning bolt is driven into the first positioning hole to limit the positions of the first sliding member and the second sliding member.

[0018] Preferably, the first sliding member and the second sliding member both have a rotating cavity, and mounting columns are installed at the openings on both sides of the rotating cavity. The first connecting member and the second connecting member both include a first extension member rotatably arranged on the outer wall of the mounting column, and a second extension member is provided at the first extension member. The second extension member has a connecting portion rotatably connected to the second mounting rod.

[0019] In the present invention, the first extension piece is rotatably connected to the mounting column, and the mounting column is connected to the first sliding piece and the second sliding piece. The second extension piece on the first sliding piece and the second sliding piece will be rotatably connected to the bottom and the top of the second mounting rod respectively, ensuring that the second mounting rod can be in a vertical state when installed.

[0020] Preferably, an expansion cavity is provided at the first expansion piece, the second expansion piece slides in the expansion cavity, second anti-slip grooves are provided on both sides of the expansion cavity, and second anti-slip parts are provided on both sides of the second expansion piece for sliding with the second anti-slip grooves. A second positioning hole is opened through the outer wall of the second expansion piece, and a docking hole for connecting with the second positioning hole is provided at the expansion cavity, and a second positioning bolt is provided at the connection between the expansion cavity and the second positioning hole.

[0021] In the present invention, by pushing the second mounting rod to fit against the vertical surface of the step, the second mounting rod is fitted with the vertical surface of the step while ensuring vertical support of the second mounting rod. During the pushing process of the second mounting rod, the second expansion piece will slide in the expansion cavity to ensure that both ends of the second mounting rod can fit against the vertical surface of the step. During this period, the second anti-slip portion will slide in the second anti-slip groove to prevent the second expansion piece from detaching from the expansion cavity. After ensuring that the second mounting rod is fit, the second positioning bolt is inserted into the second positioning hole and the docking hole to limit and fix the second expansion piece.

[0022] Preferably, the deep-reaching portion includes a support portion formed at one end of the first mounting rod away from the vertical surface of the step, the support portion is used to penetrate into the new road surface to form a staggered support, and a plurality of protruding blocks for increasing the contact area are arranged on the outside of the support portion.

[0023] In the present invention, the support part on the first mounting rod is inserted into the position of the new road. When one side of the new and old roads is subjected to downward pressure and displaces, the support part can drive the other side to displace synchronously, thereby enhancing the shear resistance at the connection between the new and old roads and further improving the stability of the connection between the new and old roads. At the same time, the protruding block on the support part can further increase the contact area between the support part and the new road surface.

[0024] In addition, the present invention also provides a construction method for splicing new and old road surfaces in highway expansion, which is used to construct any of the above-mentioned new and old road surface splicing structures in highway expansion, and comprises the following steps: S1: Dig out steps at the joint of the old road and clean the surface of the steps; S2: Install the first resistive component at the level of the step; S3: Install the second resistance component on the vertical surface of the step; S4: installing the connection component between the first resistance component and the second resistance component to form a whole; S5: Casting is carried out at the old road steps and the splicing structure.

[0025] By installing the first resistance component and the second resistance component on the water surface of the step and the vertical surface of the step respectively, the vertical and horizontal deformation resistance of the connection between the new and old roads is improved. At the same time, the first resistance component and the second resistance component are fixed to each other so that the second resistance component provides additional support for the first resistance component. When the second resistance component and the first resistance component connected to each other are subjected to force at the connection between the new and old roads, the pressure can be dispersed to steps of different heights, thereby improving the deformation resistance of the road connection. At the same time, in order to ensure that the first resistance component fits the horizontal surface of the step with a certain inclination angle while the second resistance component provides firm support for the first resistance component, the connecting component is slid and adjusted on the first resistance component to ensure that the second resistance component remains vertical and fits the vertical surface of the step. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 A schematic diagram of the splicing of the new and old road surfaces in Example 1; Figure 2 For Example 1 Figure 1 Schematic diagram of the enlarged structure at A in the middle; Figure 3 is a schematic diagram of the first resistance component in Example 1; Figure 4 is a schematic diagram of the second mounting rod in Example 1; Figure 5 is a schematic diagram of the second civil engineering grid in Example 1; Figure 6 is a schematic diagram of the first mounting rod in Example 1; Figure 7 is a schematic diagram of the first sliding member in Example 1; Figure 8 This is a schematic diagram of the explosion structure of the first expansion piece and the second expansion piece in Example 1. DETAILED DESCRIPTION

[0027] In order to further understand the content of the present invention, the present invention is described in detail in conjunction with the embodiments. It should be understood that the embodiments are only for explaining the present invention and are not intended to limit it. Example

[0028] like Figure 1-2 As shown, this embodiment provides a new and old road surface splicing structure in highway expansion, including a step excavated in the old road surface structure layer, the step having a step horizontal surface and a step vertical surface, characterized in that it includes a first resistance component 110 for being arranged at the step horizontal surface, and a second resistance component 120 is detachably arranged at the first resistance component 110, and the second resistance component 120 is used to cooperate with the step vertical surface; The first resistance component 110 has a first matching surface 111 matching with the old road surface and a second matching surface 112 matching with the new road surface. The first resistance component 110 is provided with a deep portion 113 that penetrates into the new road surface, and the deep portion 113 forms a staggered support along the vertical direction.

[0029] The present invention discloses a new and old road surface splicing structure in highway expansion. When in use, the first resistance component 110 and the second resistance component 120 located at the connection of the horizontal surface of the step and the vertical surface of the step will tie the connection of the new and old roads in the horizontal and vertical directions, so as to improve the deformation resistance of the connection between the new and old roads. The second resistance component 120 will support the deep part 113 of the first resistance component 110 that penetrates into the new road surface, forming a staggered support; It can be understood that when the connection between the new road surface or the old road surface is subjected to stress, the deep portion 113 will drive the other side of the road surface connection that is not subjected to stress to be subjected to stress synchronously, thereby increasing the shear resistance of the connection between the new and old roads, and the second resistance component 120 will disperse the stress of the new and old road surfaces into the connection between the new and old road surfaces at different steps, thereby improving the deformation resistance of the road connection.

[0030] Combination Figure 1-6 As shown, in this embodiment, the first resistance component 110 includes a first mounting rod 310 installed on the horizontal surface of the step, and multiple first mounting rods 310 are arranged along the excavation direction of the horizontal surface of the step, and a first civil engineering grid 311 is arranged between the multiple first mounting rods 310, and a first fixing member 610 is provided on the top of the outer wall of the first mounting rod 310, and the first civil engineering grid 311 is connected to the first fixing member 610; the deep-going part 113 includes a support part 410 formed at one end of the first mounting rod 310 away from the vertical surface of the step, the support part 410 is used to penetrate into the new road surface to form a staggered support, and a plurality of protruding blocks for increasing the contact area are arranged on the outside of the support part 410; the second resistance component 120 includes a second mounting rod 320 installed on the vertical surface of the step, and multiple second mounting rods 320 are arranged along the excavation direction of the vertical surface of the step, and a second civil engineering grid 321 is arranged between the multiple second mounting rods 320, and a second fixing member 620 is provided on the top of the outer wall of the first mounting rod 310, and the second mounting rod 320 is connected to the second fixing member 620.

[0031] Through the above structure, a plurality of first mounting rods 310 are arranged on the upper surface of the step horizontal surface along the excavation direction, and the first earth grille 311 is fixed between the first mounting rods 310 through the first fixing member 610. After the new and old roads are connected, the first earth grille 311 will pull the horizontal deformation force of the new and old roads, so as to enhance the horizontal deformation resistance of the road connection; at the same time, the support part 410 on the first mounting rod 310 is inserted into the position of the new road. When one side of the new and old roads is subjected to downward pressure and displaced, the support part 410 can drive the other side to move. One side is displaced synchronously, thereby enhancing the shear resistance of the connection between the new and old roads, and further improving the stability of the connection between the new and old roads. At the same time, the protruding block on the support part 410 can further increase the contact area between the support part 410 and the new road surface; the second mounting rod 320 is installed on the vertical surface of multiple steps, and the second civil engineering grid 321 is installed between multiple second fixing parts 620 through the second fixing part 620. The second civil engineering grid 321 will pull the vertical deformation force of the new and old roads, thereby enhancing the vertical deformation resistance of the connection between the new and old roads.

[0032] Combination Figure 2-7As shown, in this embodiment, a connecting component 330 is provided between the first resistance component 110 and the second resistance component 120, and the connecting component 330 is used to connect the first resistance component 110 and the second resistance component 120 to each other; the first mounting rod 310 has a first sliding groove 710 and a second sliding groove 720 at the upper and lower ends of the outer wall respectively, and the connecting component 330 includes a first sliding member 210 and a second sliding member 220 which are slidably arranged at the first sliding groove 710 and the second sliding groove 720 respectively, and the first sliding member 210 is rotatably provided with a first connecting member 230 for rotatably connecting to the bottom of the second mounting rod 320, and the second sliding member 220 is rotatably provided with a second connecting member 240 for rotatably connecting to the top of the second mounting rod 320.

[0033] Through the above structure, the upper and lower ends of the second mounting rod 320 are respectively connected to the top and bottom of the first mounting rod 310 at different heights through the connecting component 330, so that when the new and old road connection is subjected to vertical deformation force, the second mounting rod 320 on the second resistance component 120 can support and fix the first mounting rod 310 on the first resistance component 110, thereby improving the control effect of the first resistance component 110 on vertical deformation, and the second mounting rod 320 is connected to the first mounting rod 310, when the new and old road connection is subjected to external force, the external force can be dispersed to steps of different heights through the second mounting rod 320, thereby improving the deformation resistance of the new and old road connection; considering that a certain inclination angle will be reserved for the horizontal surface of the step during the actual excavation process, the first mounting rod 310 and the second mounting rod 320 are connected. Before connection, the second mounting rod 320 needs to be rotated to ensure that the second mounting rod 320 vertically supports the first mounting rod 310. First, the first sliding member 210 and the second sliding member 220 on the connecting assembly 330 are slid on the first sliding groove 710 and the second sliding groove 720 respectively. After adjusting to the appropriate position, the first mounting rod 310 at different heights of the upper and lower layers can be attached to the horizontal surface of the step through the first connecting member 230 and the second connecting member 240, while ensuring that the second mounting rod 320 is in a vertical state, thereby achieving stable support for the first mounting rod 310. In addition, when the first sliding member 210 and the second sliding member 220 are adjusted, the supporting position of the second mounting rod 320 on the first mounting rod 310 can be changed, thereby improving the applicability of the device installed on the horizontal surfaces of steps of different sizes.

[0034] Combination Figure 2-7As shown, in the present embodiment, first anti-slip grooves 730 are provided on both sides of the first sliding groove 710 and the second sliding groove 720, first anti-slip portions 740 slidably connected to the first anti-slip grooves 730 are provided on both sides of the outer walls of the first sliding member 210 and the second sliding member 220, and a first positioning hole 750 is provided through the first sliding groove 710 and the second sliding groove 720, and a first positioning bolt 760 for limiting the first sliding member 210 and the second sliding member 220 is provided in the first positioning hole 750.

[0035] Through the above structure, when the first sliding member 210 and the second sliding member 220 slide, the first anti-slip portion 740 will slide in contact with the first anti-slip groove 730, so as to prevent the first sliding member 210 and the second sliding member 220 from escaping from the first sliding groove 710 and the second sliding groove 720 when sliding. After the first sliding member 210 and the second sliding member 220 are slid to a fixed position, the first positioning bolt 760 is driven into the first positioning hole 750 to limit the position of the first sliding member 210 and the second sliding member 220.

[0036] Combination Figure 2-8 As shown, in this embodiment, the first sliding member 210 and the second sliding member 220 both have a rotating cavity 810, and mounting columns 820 are installed at the openings on both sides of the rotating cavity 810. The first connecting member 230 and the second connecting member 240 both include a first expansion member 830 rotatably arranged at the outer wall of the mounting column 820, and a second expansion member 840 is provided at the first expansion member 830. The second expansion member 840 has a connecting portion 850 rotatably connected to the second mounting rod 320; an expansion cavity 831 is provided at the first expansion member 830, and the second expansion member 840 slides in the expansion cavity 831. Second anti-slip grooves 832 are provided on both sides of the expansion cavity 831, and second anti-slip portions 860 that slide with the second anti-slip grooves 832 are provided on both sides of the second expansion member 840. A second positioning hole 870 is opened through the outer wall of the second expansion member 840, and a docking hole 880 for communicating with the second positioning hole 870 is provided at the expansion cavity 831, and a second positioning bolt 890 is provided at the connection between the expansion cavity 831 and the second positioning hole 870.

[0037] Through the above structure, after the positions of the first sliding member 210 and the second sliding member 220 are fixed, the first extension member 830 is rotatably connected to the mounting column 820, and the mounting column 820 is connected to the first sliding member 210 and the second sliding member 220. The second extension member 840 on the first sliding member 210 and the second sliding member 220 will be rotatably connected to the bottom and the top of the second mounting rod 320 respectively, ensuring that the second mounting rod 320 can be in a vertical state during installation; at the same time, considering that the second mounting rod 320 can be in a vertical state after rotation, but because the first mounting rods 310 at different heights are all in an inclined state, it is difficult for the second mounting rod 320 to fit with the vertical surface of the step after being vertically erected, thereby affecting the control effect of the second resistance component 120 on the vertical deformation force Therefore, the second expansion piece 840 slides in the expansion cavity 831, and after the upper and lower ends of the second mounting rod 320 are rotated and connected with the connecting part 850, the second mounting rod 320 is pushed to fit against the vertical surface of the step, and fits against the vertical surface of the step while ensuring the vertical support of the second mounting rod 320. During the pushing process of the second mounting rod 320, the second expansion piece 840 will slide in the expansion cavity 831 to ensure that both ends of the second mounting rod 320 can fit against the vertical surface of the step. During this period, the second anti-slip part 860 will slide in the second anti-slip groove 832 to prevent the second expansion piece 840 from detaching from the expansion cavity 831. After ensuring that the second mounting rod 320 fits, the second positioning bolt 890 is inserted into the second positioning hole 870 and the docking hole 880 to limit and fix the second expansion piece 840.

[0038] In addition, this embodiment also provides a construction method for splicing new and old road surfaces in highway expansion, which is used to construct the new and old road surface splicing structure in highway expansion in any of the above embodiments, and includes the following steps: S1: Dig out steps at the joint of the old road and clean the surface of the steps; S2: Install the first resistive component at the level of the step; S3: Install the second resistance component on the vertical surface of the step; S4: installing the connection component between the first resistance component and the second resistance component to form a whole; S5: Casting is carried out at the old road steps and the splicing structure.

[0039] Through the above-mentioned construction method, the first resistance component 110 and the second resistance component 120 are respectively installed on the water surface of the step and the vertical surface of the step to improve the vertical and horizontal deformation resistance of the connection between the new and old roads. At the same time, the first resistance component 110 and the second resistance component 120 are fixed to each other, so that the second resistance component 120 forms an additional support for the first resistance component 110, and when the second resistance component 120 and the first resistance component 110 connected to each other are subjected to force at the connection between the new and old roads, the pressure can be dispersed to steps of different heights to improve the deformation resistance of the road connection. At the same time, in order to ensure that the first resistance component 110 is in contact with the horizontal surface of the step with a certain inclination angle while the second resistance component 120 realizes a firm support for the first resistance component 110, the connection component 330 is used to slide and adjust the first resistance component 110 to ensure that the second resistance component 120 remains vertical and in contact with the vertical surface of the step. It is easy to understand that those skilled in the art can combine, split, reorganize, etc. the embodiments of the present application to obtain other embodiments based on one or several embodiments provided in the present application, and these embodiments do not exceed the protection scope of the present application.

[0040] The present invention and its implementation methods are described schematically above, and the description is not restrictive. The embodiments shown in the embodiments are only part of the implementation methods of the present invention, and the actual structure is not limited thereto. Therefore, if a person skilled in the art is inspired by the embodiments and designs a structure and an implementation method similar to the technical solution without creativity without departing from the purpose of the invention, they should all fall within the protection scope of the present invention.

Claims

1. A new and old road surface splicing structure in highway expansion, comprising a step excavated in the old road surface structure layer, the step having a step horizontal surface and a step vertical surface, characterized in that: It comprises a first resistance component (110) for being arranged at a horizontal surface of a step, a second resistance component (120) being detachably arranged at the first resistance component (110), and the second resistance component (120) being used to cooperate with a vertical surface of the step; The first resistance component (110) has a first matching surface (111) matching with the old road surface and a second matching surface (112) matching with the new road surface. The first resistance component (110) is provided with a deep portion (113) that penetrates into the new road surface. The deep portion (113) forms a staggered support along the vertical direction.

2. The new and old road surface splicing structure in highway expansion according to claim 1 is characterized by: The first resistance component (110) comprises a first mounting rod (310) mounted on a horizontal surface of the step, a plurality of first mounting rods (310) are arranged along the excavation direction of the horizontal surface of the step, a first earthwork grille (311) is arranged between the plurality of first mounting rods (310), a first fixing member (610) is arranged at the top of the outer wall of the first mounting rod (310), and the first earthwork grille (311) is connected to the first fixing member (610).

3. The new and old road surface splicing structure in highway expansion according to claim 2 is characterized by: The second resistance component (120) comprises a second mounting rod (320) mounted on the vertical surface of the step, a plurality of second mounting rods (320) are arranged along the excavation direction of the vertical surface of the step, a second civil grid (321) is arranged between the plurality of second mounting rods (320), a second fixing member (620) is arranged at the top of the outer wall of the first mounting rod (310), and the second mounting rod (320) is connected to the second fixing member (620).

4. A new and old road surface splicing structure in highway expansion according to claim 2 or 3, characterized in that: A connection component (330) is provided between the first resistance component (110) and the second resistance component (120), and the connection component (330) is used to connect the first resistance component (110) and the second resistance component (120) to each other.

5. The new and old road surface splicing structure in highway expansion according to claim 4 is characterized by: The first mounting rod (310) has a first sliding groove (710) and a second sliding groove (720) respectively formed at the upper and lower ends of the outer wall thereof. The connecting assembly (330) comprises a first sliding member (210) and a second sliding member (220) respectively slidably disposed at the first sliding groove (710) and the second sliding groove (720). The first sliding member (210) has a first connecting member (230) rotatably connected to the bottom of the second mounting rod (320), and the second sliding member (220) has a second connecting member (240) rotatably connected to the top of the second mounting rod (320).

6. The new and old road surface splicing structure in highway expansion according to claim 5 is characterized by: First anti-slip grooves (730) are provided on both sides of the first sliding groove (710) and the second sliding groove (720); first anti-slip portions (740) are provided on both sides of the outer walls of the first sliding member (210) and the second sliding member (220) for sliding connection with the first anti-slip grooves (730); a first positioning hole (750) is provided between the first sliding groove (710) and the second sliding groove (720); a first positioning bolt (760) for limiting the position of the first sliding member (210) and the second sliding member (220) is provided in the first positioning hole (750).

7. A new and old road surface splicing structure in highway expansion according to claim 5 or 6, characterized in that: The first sliding member (210) and the second sliding member (220) both have a rotation cavity (810), and mounting columns (820) are installed at the openings on both sides of the rotation cavity (810). The first connecting member (230) and the second connecting member (240) both include a first extension member (830) rotatably arranged on the outer wall of the mounting column (820), and a second extension member (840) is arranged at the first extension member (830). The second extension member (840) has a connecting portion (850) rotatably connected to the second mounting rod (320).

8. The new and old road surface splicing structure in highway expansion according to claim 7 is characterized by: An expansion cavity (831) is provided at the first expansion piece (830), the second expansion piece (840) slides in the expansion cavity (831), second anti-slip grooves (832) are provided on both sides of the expansion cavity (831), and second anti-slip portions (860) are provided on both sides of the second expansion piece (840) for sliding with the second anti-slip grooves (832), a second positioning hole (870) is provided through the outer wall of the second expansion piece (840), a docking hole (880) for communicating with the second positioning hole (870) is provided at the expansion cavity (831), and a second positioning bolt (890) is provided at the connection between the expansion cavity (831) and the second positioning hole (870).

9. A new and old road surface splicing structure in highway expansion according to claim 1 or 2, characterized in that: The deep-reaching portion (113) comprises a support portion (410) formed at one end of the first mounting rod (310) away from the vertical surface of the step, the support portion (410) being used to penetrate into the new road surface to form a staggered support, and a plurality of protruding blocks for increasing the contact area are arranged outside the support portion (410).

10. A construction method for splicing new and old road surfaces in highway expansion, which is used to construct the new and old road surface splicing structure in highway expansion as claimed in any one of claims 1 to 9, comprising the following steps: S1: Dig out steps at the joint of the old road and clean the surface of the steps; S2: installing the first resistive component (110) at the level of the step; S3: Installing the second resistance component (120) on the vertical surface of the step; S4: installing the connection component (330) between the first resistance component (110) and the second resistance component (120) so as to form a whole; S5: Casting is carried out at the old road steps and the splicing structure.