Through the double-hanging buckle construction method, the independent stress system of the upper chord beam and the lower chord arch is used to support the hanging basket and temporary cable tower, the impact of construction progress on the stress balance is solved, and the construction safety and efficiency of the beam-arch combination bridge is improved. .

CN118996995APending Publication Date: 2024-11-22贵州交通建设集团有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410900420.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-05
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The construction progress of the beam-arch combination bridge is difficult to strictly control the stress balance between the upper chord beam and the lower chord arch, which poses safety hazards, and is more prominent when constructing under complex geological conditions.

Method used

The double-hanging buckle construction method is adopted to make the stress system of the upper chord beam and the lower chord arch independent of each other. Through the casting of the hanging basket and the temporary cable tower support, the load on the lower chord arch is reduced, and the upper chord is prevented by connecting the upper chord cable and cable tower. The beam cantilever section is disturbed downward to avoid temporary prestressing.

Benefits of technology

The independence of the upper chord beam and lower chord arch is achieved, the load on the lower chord arch is reduced, the construction safety and efficiency are improved, the strict control needs for construction progress is avoided, and the convenience and safety of construction are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118996995A_ABST
    Figure CN118996995A_ABST
Patent Text Reader

Abstract

The invention relates to the field of beam-arch combined bridges, and discloses a double-hanging-buckle construction method of a beam-arch combined bridge, which comprises the following steps: step 1, completing pier construction, pouring a 0 # section of an upper chord beam at the top of a pier, and mounting an upper chord hanging basket on the 0 # section of the upper chord beam, and step 2, pouring the upper chord beam and a lower chord arch section by section by adopting the hanging basket. Meanwhile, a temporary cable bent tower is erected on the 0 # section of the upper chord beam, a plurality of upper buckling cables are installed on the temporary cable bent tower, and each section of the upper chord beam is connected with the lower ends of the two upper buckling cables; meanwhile, a lower buckle cable is installed on the segment of each lower chord arch, and the middle of each lower buckle cable penetrates through the bridge pier; and thirdly, the hanging basket on the lower chord arch is dismantled, and the folding section is poured through the hanging basket on the upper chord beam. The stress systems of the upper chord beam and the lower chord arch are mutually independent, and the stress balance is prevented from being influenced by the construction progress of the upper chord beam and the lower chord arch.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of beam-arch combination bridges, and in particular to a double-hanging buckle construction method for beam-arch combination bridges. Background Art

[0002] With the continuous construction and extension of western expressways, expressway construction has entered areas with high mountains, canyon rivers and more complex geological conditions. Large-span bridges across V-shaped river valleys have become key projects for expressways in the western region and a controlling factor in the entire project construction period and cost.

[0003] The beam-arch composite bridge adopts a combination of an upper chord beam and a lower chord arch, and the lower chord arch provides support for the upper chord beam, which reduces the phenomenon of mid-span deflection, increases the maximum span, and at the same time reduces the deadweight and improves economy.

[0004] For beam-arch combination bridges, our company has developed a variety of construction plans. The initial plan is: give priority to the construction of the lower chord arch, install the cable on the lower chord arch, set up a bracket on the lower chord arch, and then complete the construction of the upper chord beam on the bracket. This will increase the load on the lower chord arch and increase safety hazards. At the same time, it is necessary to strictly control the construction progress of the upper chord beam and the lower chord arch to ensure the balance between the cable tension and the upper chord beam load, so as to ensure the safety of construction. However, in actual operation, it is often difficult to strictly control the construction progress of the upper chord beam and the lower chord arch due to various external factors (material transportation, bad weather and superior inspection). Summary of the invention

[0005] The present invention aims to provide a double-hook construction method for a beam-arch composite bridge, so that the force systems of the upper chord beam and the lower chord arch are independent of each other, thereby preventing the construction progress of the upper chord beam and the lower chord arch from affecting the force balance.

[0006] To achieve the above object, the present invention adopts the following technical scheme: a double hanging buckle construction method for a beam-arch composite bridge, wherein the beam-arch composite bridge comprises an upper chord beam and a lower chord arch, both of which are constructed by hanging baskets, and are cantilevered from the central axis of the pier to both sides of the pier, one end of the upper chord beam and the arch foot of the lower chord arch are both connected to the pier, the other end of the upper chord beam is closed with the arch top of the lower chord arch, and both of the upper chord beam and the lower chord arch are cast in a plurality of sections;

[0007] The following steps are involved:

[0008] Step 1: Complete the construction of the bridge piers, cast the 0# section of the upper chord beam on the top of the piers, and install the hanging basket on the 0# section of the upper chord beam.

[0009] Step 2: Use a hanging basket to cast the upper chord beam and the lower chord arch in sections; at the same time, set up a temporary cable tower on the 0# section of the upper chord beam, install several upper cable ties on the temporary cable tower, and each section of the upper chord beam is connected to the lower ends of the two upper cable ties respectively; at the same time, install lower cable ties on each section of the lower chord arch, and the middle part of the lower cable ties passes through the bridge pier;

[0010] Step 3: Remove the hanging basket on the lower chord arch and use the hanging basket on the upper chord beam to cast the closing section.

[0011] The beneficial effects of this program are:

[0012] 1. During the construction process, the upper chord is connected to the tower through the upper cable, so that the weight of the cantilever section of the upper chord is vertically transferred to the pier through the tower. Compared with setting up a bracket on the lower chord as a support, this scheme avoids the influence of the upper chord force system on the lower chord, making the force systems of the upper chord and the lower chord independent of each other, reducing the bearing load of the lower chord, and ensuring the balance of the force system without strictly controlling the construction progress of the upper chord and the lower chord.

[0013] 2. This scheme installs the cable tower, and the upper cable generates an upward pulling force on the upper chord beam, thereby preventing the upper chord beam cantilever section from disturbing downward. Disturbance means downward deformation. Therefore, there is no need to apply longitudinal temporary prestressing through the steel strands to prevent the upper chord beam cantilever section from disturbing downward. At the same time, the direction of applying temporary prestressing is longitudinal, while the tension of the upper cable can be decomposed into longitudinal and vertical directions. Therefore, the effect of temporary prestressing in resisting the vertical gravity of the upper chord beam is far less than that of the tension of the upper cable. The tension of the upper cable is better in preventing the upper chord beam cantilever section from disturbing downward.

[0014] 3. Compared with setting up brackets on the lower chord arch as support, the lower cables are interspersed between the brackets; in this scheme, upper cables are used instead of brackets for support. The upper cables and lower cables are set separately, without crossing in space and without blocking the line of sight, which is not only convenient for installation, but also for maintenance and replacement.

[0015] Furthermore, the temporary cable tower includes a lower tower and an upper tower. The lower tower is fixed on the 0# section of the upper chord beam. The upper tower includes a plurality of tension units. The plurality of tension units are arranged vertically. The number of tension units on the upper tower increases with the construction progress of the upper chord beam.

[0016] Furthermore, the pulling units all include a rectangular frame, and two horizontal pull rods are respectively provided on two sides of the rectangular frame parallel to the upper buckle cable, and the two ends of the horizontal pull rods are respectively at the same height as the end of an upper buckle cable, and the number of the horizontal pull rods is the same as the number of upper buckle cables on one side of the cable tower; and truss plates are provided on two sides of the rectangular frame parallel to the upper buckle cable;

[0017] In step 2, after casting two sections of the upper chord beam, a new tension unit is installed on the upper end of the temporary cable tower.

[0018] Further, the lower tower includes a plurality of truss units, the upper and lower ends of adjacent truss units are connected by bolts, and each truss unit also includes a rectangular frame, and the four sides of the rectangular frame are provided with truss sheets;

[0019] In step 2, truss units are installed upward on the 0# section of the upper chord beam in sequence until the angle between the first upper cable and the horizontal line is greater than 30°.

[0020] Furthermore, the hanging basket is divided into an upper hanging basket and a lower hanging basket, and both the upper hanging basket and the lower hanging basket include a traveling system, a main truss system, a suspension system and a bottom basket system. The traveling system is installed on the upper surface of the upper chord beam or the lower chord arch, the main truss system is installed on the traveling system and extends toward the cantilever end, the upper end of the suspension system is detachably connected to the main truss system, and the lower end of the suspension system is connected to the bottom basket system, and the bottom basket system serves as a supporting platform to bear the construction load;

[0021] In step 2, the method of using a hanging basket to cast the upper chord beam and the lower chord arch in sections is as follows:

[0022] Step 2.1 Use the upper chord hanging basket to cast the upper chord beam section 1#, install the lifting system on the main truss system of the upper chord hanging basket, the lifting system can drive the bottom basket system to move downward, and remove the connection between the upper end of the suspension system and the main truss system;

[0023] Step 2.2, the lifting system drives the bottom basket system to move downward to the arch foot of the lower chord arch, and the upper end of the suspension system is extended to connect the upper end of the suspension system with the main truss system of the upper chord hanging basket, and the lower chord arch 1# section is cast with the bottom basket system as support;

[0024] Step 2.3, the walking system of the upper chord hanging basket drives the main truss system, the lifting system, the suspension system and the bottom basket system to move forward together, and the lower chord arch section 2# is cast with the bottom basket system as support;

[0025] Step 2.4, install the walking system and main truss system of the lower chord basket on the lower chord arch section 1# and section 2#, connect the main truss system of the lower chord basket with the upper end of the suspension system of the upper chord basket, and convert the suspension system and bottom basket system of the upper chord basket into the suspension system and bottom basket system of the lower chord basket;

[0026] Step 2.5, use the lower chord hanging basket to cast the lower chord arch section 3#, reinstall the suspension system and bottom basket system of the upper chord hanging basket, and use the upper chord hanging basket to cast the upper chord beam section 2#;

[0027] Step 2.6: Cast the remaining segments of the upper chord beam and the lower chord arch until the upper segment of the closed section of the lower chord arch.

[0028] Further, the lifting system includes a plurality of electric hoists;

[0029] In step 2.1, during the construction of the bridge pier, the horizontally set lower chord arch 0# section is reserved, the upper ends of the electric hoists are connected to the main truss system of the upper chord hanging basket, and the lower ends of the electric hoists are hung on the bottom basket system;

[0030] In step 2.2, when the electric hoist drives the bottom basket system to move downward, the upper end of the suspension system is temporarily fixed on the steel cable of the electric hoist; after the electric hoist drives the bottom basket system to move downward, the template of the lower chord arch section 1# is set up on the bottom basket system, the bottom basket system and the template of the lower chord arch section 1# are detachably connected, and the template of the lower chord arch section 1# is connected to the lower chord arch section 0#.

[0031] Furthermore, the suspension system of the upper chord hanging basket includes a plurality of suspension units, each of which includes a suspension rod and an extension rod, an upper connecting piece and a lower connecting piece are respectively provided at the upper and lower ends of the suspension rod, the upper end of the suspension rod passes through the main truss system of the upper chord hanging basket and is threadedly connected to the upper connecting piece, and the upper connecting piece is supported on the main truss system;

[0032] In step 2.2, the upper connector is removed, and the steel cables of the boom and the electric hoist are temporarily fixed by iron wire. The electric hoist drives the bottom basket system to move downward, and the upper end of the extension rod passes through the main truss system of the upper chord hanging basket and is threadedly connected to the upper connector. The upper connector is supported on the main truss system, and the extension connector is threadedly connected at the lower end of the extension rod. The lower end of the extension connector is threadedly connected to the upper end of the boom, and the iron wire on the steel cables of the boom and the electric hoist is removed.

[0033] Furthermore, the thread directions of the suspension rod and the extension rod are the same, a conversion pad is welded at the lower end of the extension connector, and the upper end of the suspension rod can pass through the conversion pad; the main truss system of the upper chord hanging basket and the lower chord hanging basket both include a main truss, a front crossbeam and a rear crossbeam are provided on the main truss, the front crossbeam or the rear crossbeam is composed of two parallel I-beams, and the distance between the two I-beams is less than the width of the conversion pad; the bottom basket system of the upper chord hanging basket includes a front cantilever beam and a rear cantilever beam, and a plurality of longitudinal beams are provided between the front cantilever beam and the rear cantilever beam; one end of the plurality of longitudinal beams are hinged to the front cantilever beam, and a plurality of horizontally arranged support tubes are provided on the rear cantilever beam, and the other end of the longitudinal beams is supported on the support tube, and the other end of the longitudinal beams can slide on the support tube;

[0034] In step 2.4, the method of converting the suspension system and bottom basket system of the upper string hanging basket into the suspension system and bottom basket system of the lower string hanging basket is:

[0035] Step 2.4.1, during the installation of the main truss system of the lower chord hanging basket, make the suspension rod of the upper chord hanging basket pass through the front beam or rear beam of the lower chord hanging basket, hang the upper end of the electric hoist on the front beam or rear beam, and hang the lower end of the electric hoist on the front cantilever beam or rear cantilever beam;

[0036] Step 2.4.2, rotate the extension connector so that the conversion pad at the lower end of the extension connector is supported on the main truss system of the lower chord hanging basket, remove the upper connector at the upper end of the extension rod, rotate the extension rod to separate the lower end of the extension rod from the extension connector, and remove the extension rod and the electric hoist.

[0037] Furthermore, the conversion pad is provided with four strip-shaped bolt holes, each of which can be equipped with a limit bolt;

[0038] In step 2.4.2, the conversion pad is supported on the front beam or rear beam of the main truss system of the lower chord hanging basket, and four limit bolts are installed on the conversion pad. The four limit bolts are evenly distributed and fit on both sides of the front beam or rear beam, thereby limiting the distance between the two I-beams constituting the front beam or rear beam.

[0039] This solution also has the following effects:

[0040] 1. The upper tower is divided into several tension units. They do not need to be installed all at once. They can be installed according to the number of upper cables required. For every two upper cables, one tension unit is installed. The horizontal component of the tension of the upper cables on both sides of the tower is balanced by horizontal pull rods. Each group of upper cables corresponds to a horizontal pull rod to avoid reducing the influence of the tension on other positions of the tension unit, avoid the tension causing bending moment in the rectangular frame, and avoid stress concentration in local areas, thereby improving the durability of the tension unit.

[0041] 2. In this scheme, the forward direction of the upper chord hanging basket is the cantilever end direction of the upper chord beam. The upper chord hanging basket is set up on the 0# section of the upper chord beam, and then the bottom basket of the upper chord hanging basket is lowered to the arch foot of the lower chord arch through the lifting system to provide a platform for the pouring of the 1# section of the lower chord arch. Compared with setting up a platform directly at the arch foot of the lower chord arch, this scheme sets up the upper chord hanging basket on the 0# section of the upper chord beam, which has sufficient operating space and footholds, and there is no need to worry about stepping on air and falling, and the operation is safer, so that the 1# section of the lower chord arch can be constructed more safely.

[0042] 3. The top of the pier can provide sufficient support for the upper chord hanging basket. Compared with the existing technology, there is no need to build a cantilever platform, and the construction process is safer and faster, so as to efficiently construct the lower chord arch section 1#.

[0043] 4. After pouring the lower chord arch section 2#, set up the lower chord hanging basket, and use the main truss system of the lower chord hanging basket to provide support for the bottom basket system, so that the bottom basket system of the upper chord hanging basket can be transferred to the lower chord hanging basket, eliminating the tedious steps of reinstalling the bottom basket system of the lower chord hanging basket, thereby improving the construction efficiency of the lower chord arch.

[0044] 5. In order to facilitate the material hoisting of the lower chord arch and ensure the construction space of the lower chord arch, the construction progress of the lower chord arch usually needs to be several sections ahead of the upper chord beam; the construction progress of the lower chord arch determines the overall construction progress. Therefore, in this plan, the bottom basket system of the upper chord hanging basket is directly transferred to the lower chord hanging basket, so that the construction of the lower chord arch can start in advance, and the upper chord beam takes the opportunity to reinstall the suspension system and the bottom basket system. After the installation is completed, the upper chord beam just lags behind the lower chord arch by several sections, and then the upper chord beam and the lower chord arch are constructed synchronously towards the cantilever end, which can not only ensure the construction progress, but also ensure the construction space of the lower chord arch.

[0045] 6. During the construction of the bridge piers, a horizontally set lower chord arch section 0# is reserved to reserve a connection position for the template of the lower chord arch section 1#.

[0046] 7. Compared with using a jack to drive the boom to move downward, this solution uses an electric hoist to drive the bottom basket system to move downward, which is faster and more convenient;

[0047] In addition, when constructing on high bridge piers, the wind load is large, the lower end of the hanger is in a free state, and it shakes violently; when the bottom basket system moves downward, the wind load on the hanger gradually increases, the hanger shakes more violently, and it is easy to deform and damage; in this solution, the steel cable of the electric hoist is more flexible than the hanger, and it can recover even if it is deformed under wind load. The upper end of the hanger is no longer fixed, and the hanger shakes with the steel cable, so it is not easy to deform; when the bottom basket system reaches the arch foot position of the lower chord arch and is connected to the 0# section of the lower chord arch through the template, the bottom basket system tends to be stable under the support of the 0# section of the lower chord arch. At this time, the shaking of the lower end of the hanger affected by the wind load is reduced. At this time, an extension rod is used to extend the hanger, and the hanger is not easy to deform.

[0048] 8. In step 2.4, since the boom is the main load-bearing component, if the boom and the extension rod are suddenly disconnected, the steel cable of the electric hoist becomes the main load-bearing component, and the steel cable is subjected to increased force and becomes longer, which can easily cause the electric hoist to be impacted and damaged; if the main truss system of the boom and the lower chord hanging basket is to be fixed first, the boom and the extension rod still need to be disconnected first, so as to connect the upper connector to the upper end of the boom;

[0049] In this solution, the bottom basket system of the upper-chord basket is transferred to the lower-chord basket without disconnecting the boom and the extension rod, and this function is achieved through a specially designed extension connector. The extension connector can connect the boom and the extension rod, and can also serve as a nut and a pad to support the lower-chord basket.

[0050] Specifically, in this solution, since the front crossbeam or the rear crossbeam is composed of two I-beams, when welding the front crossbeam, the hanger is located between the two I-beams, so that the hanger passes through the front crossbeam or the rear crossbeam without disconnecting the hanger and the extension rod; then, the extension connector is rotated to move the extension connector downward until the conversion pad at the lower end of the extension connector is supported on the front crossbeam or the rear crossbeam of the lower chord hanging basket. At this time, the hanger and the extension rod are still connected through the extension connector, and the conversion of the load-bearing part is realized in advance. At this time, if the connection between the hanger and the extension rod is disconnected, the electric hoist or other parts that can bear force will not be greatly impacted due to the conversion of the load-bearing part.

[0051] The extension connector in this solution is not a simple combination of nuts and pads. The extension connector needs to be long enough to not only connect the suspension rod and the extension rod at the same time, but also to move one end downward to allow the conversion pad to contact the front beam or the rear beam while maintaining the connection with the extension rod. Finally, the lower end of the extension rod is disengaged from the extension connector by rotating the extension rod.

[0052] 9. In step 2.1, mark the connection position between the upper end of the boom and the front beam or rear beam of the upper string hanging basket;

[0053] In step 2.2, the connection position of the extension rod and the front crossbeam or rear crossbeam of the upper chord hanging basket is also at the positioning mark. When installing the extension rod, a tower crane is used to fix the upper end of the extension rod. At this time, the extension rod remains vertical under the action of gravity. Only when there is no wind, the boom will also remain vertical, and the lower end of the extension rod can be aligned and connected with the upper end of the boom. Then, check whether the boom and the extension rod are in the same straight line, and adjust them in time. Since the connection position of the lower end of the boom and the front cantilever beam or rear cantilever beam of the bottom basket system remains unchanged, it is ensured that the extension rod and the boom always remain vertical in a windless state. The force direction in a windless state is always the axial direction of the rod, and there is no eccentric force, thereby ensuring the load-bearing capacity of the extension rod and the boom.

[0054] The higher the height of the bridge pier, the greater the wind load. Since the length of the hanger plus the extension rod is longer, it is more affected by the wind load. The verticality described in this plan can only ensure verticality in a windless state, and it is impossible to be vertical at all times. Therefore, it is impossible to wait until the wind stops to check the verticality every time. It can only ensure that the upper end of the hanger is always in a fixed state so that the verticality remains unchanged.

[0055] In step 2.4 of this scheme, before the upper end of the boom and the front crossbeam of the lower line hanging basket are fixed, the boom and the extended boom are always kept connected to prevent the upper end of the boom from changing its verticality due to loss of connection, thereby ensuring the vertical alignment of the central axes of the upper chord hanging basket and the lower chord hanging basket, and then ensuring the vertical alignment of the central axes of the cast upper chord beam and the lower chord arch, preventing the load of the upper chord beam from generating eccentric force on the lower chord arch.

[0056] 10. The upper chord beam is constructed after the lower chord arch, and the two sections are advanced synchronously to leave enough working space for the lower chord arch, to prevent the interference between the bracket and the lower chord hanging basket, and to prevent the collision with the upper chord beam when hoisting the materials of the lower chord arch; at the same time, to ensure the stability of the structure.

[0057] 11. In step 2.2, when the hoisting system drives the bottom rail system to move downward, due to the inclination of the bottom of the lower arch, the longitudinal beam in the bottom rail system needs to be tilted as well, and the template of the lower arch is supported on the longitudinal beam.

[0058] If the two connection positions of the longitudinal beam and the front and rear cantilever beams are fixed, after the longitudinal beam is tilted, the horizontal distance between the front and rear cantilever beams is reduced, resulting in a reduction in the distance between the lower ends of the suspension rods connected to the front and rear cantilever beams, causing the suspension rods to tilt. No matter how the operator makes adjustments, it is impossible to keep all the suspension rods vertical at the same time, which will lead to the following adverse effects:

[0059] a. At this time, the operator cannot judge whether there is wind by whether the suspension rod is vertical, and thus cannot adjust the construction progress of the lower chord arch formwork on the bottom rail system in time according to whether there is wind, thereby reducing the construction accuracy of the lower chord arch formwork.

[0060] b. In step 2.4, when installing the main truss of the lower chord basket, the two I-beams on the front and rear crossbeams on the main truss clamp the boom to prevent it from shaking. However, when the boom is no longer vertical, the two I-beams clamping the boom will pull the upper end of the boom back to a vertical state, while the lower end of the boom is still tilted, causing the boom to deform and a large internal force to exist, thereby reducing the durability of the boom.

[0061] In this solution, one end of the longitudinal beam is hinged to the front beam, and the other end is slidably connected to the rear beam (sliding can be ensured by applying lubricating oil on the contact surface), so that the horizontal distance between the front beam and the rear beam will not change when the longitudinal beam is tilted, and the suspension rod can still remain vertical under the action of gravity;

[0062] For adverse effect a, the operator can judge whether there is wind by whether the hanger is vertical, thereby ensuring the construction accuracy of the lower chord arch formwork; for adverse effect b, the hanger can be prevented from generating internal force, thereby ensuring the durability of the hanger.

[0063] 12. Regarding effect 11, during the process of adjusting the inclination of the longitudinal beam, if the friction increases and the sliding is abnormal due to insufficient lubricating oil on the contact surface between the longitudinal beam and the rear cantilever beam, or the friction increases and the rotation is abnormal due to rust at the hinge position between the longitudinal beam and the front cantilever beam, or the concrete falls on the connection position between the longitudinal beam and the front cantilever beam or the rear cantilever beam during the previous concrete pouring, the hanger cannot remain vertical. At this time, by clamping the hanger with the two I-beams that form the front cantilever beam or the rear cantilever beam, a reaction force can be provided for the longitudinal beam to overcome the friction; when the hanger connection position is near the end of the I-beam, the end of the I-beam is easily deformed due to the cantilever effect, and the distance between the two I-beams is easily enlarged when the hanger is tilted, and the I-beam cannot clamp the hanger, so that the hanger cannot remain vertical; and this solution uses a limit bolt to limit the distance between the two I-beams, thereby ensuring that the two I-beams can clamp the hanger and the distance is not enlarged as much as possible. BRIEF DESCRIPTION OF THE DRAWINGS

[0064] Figure 1 It is a schematic diagram of the overall structure of Example 1;

[0065] Figure 2 This is a schematic diagram of a temporary cable tower in Example 1;

[0066] Figure 3 for Figure 2 Schematic diagram of the truss element in ;

[0067] Figure 4 for Figure 2 Schematic diagram of the tension unit in ;

[0068] Figure 5 It is a three-dimensional axonometric view of the upper hanging basket of Example 1;

[0069] Figure 6 It is a three-dimensional axonometric diagram when the suspension system and bottom basket system of the upper hanging basket of Example 1 are transferred to the lower hanging basket;

[0070] Figure 7 for Figure 6 A in the enlarged view;

[0071] Figure 8 is a perspective view of the extension connector of Example 1;

[0072] Fig. 9 This is a schematic diagram of the structure of step 2.1 of Example 2;

[0073] Fig.10 This is a schematic diagram of the structure of step 2.2 of Example 2;

[0074] Fig.11 This is a schematic diagram of the structure of step 2.3 of Example 2;

[0075] Fig.12 This is a schematic diagram of the structure of step 2.4 of Example 2;

[0076] Fig.13 This is a schematic diagram of the structure of step 2.5 of Example 2;

[0077] Fig.14 This is a schematic diagram of the structure of step 3 of Example 2;

[0078] Fig.15 The conversion pad in the state of step 2.4.2 of Example 3;

[0079] Fig.16 Schematic diagram of point P in Example 3. DETAILED DESCRIPTION

[0080] The following is further described in detail through specific implementation methods:

[0081] The reference numerals in the drawings of the specification include: pier 1, upper chord beam 2, upper chord beam 0# segment 20, upper chord beam 1# segment 21, closing segment 22, lower chord arch 3, lower chord arch 0# segment 30, lower chord arch 1# segment 31, lower chord arch 2# segment 32, lower chord arch 3# segment 33, upper chord hanging basket 41, lower chord hanging basket 42, upper tie-down cable 43, lower tie-down cable 44, walking system 50, main truss 51, front crossbeam 52, rear crossbeam 53 , front cantilever beam 61, rear cantilever beam 62, longitudinal beam 63, connecting block 64, pin 65, electric hoist 7, upper connecting piece 81, upper nut 811, upper pad 812, extension connecting piece 82, conversion pad 83, strip bolt hole 831, limit bolt 832, hanger 84, extension rod 85, temporary cable tower 9, tension unit 91, truss unit 92, column 93, truss piece 94, horizontal pull rod 95.

[0082] Example 1

[0083] Example 1 is basically as Figure 1-Figure 8 As shown: a hanging basket for a beam-arch combination bridge, comprising an upper chord hanging basket 41 and a lower chord hanging basket 42, the beam-arch combination bridge is as follows Figure 1 As shown in FIG. 1 , with the center line of pier 1 as the axis of symmetry, both sides of pier 1 are constructed synchronously and symmetrically. Take the segment on the right side of pier 1 as an example: the segment includes an upper chord beam 2 and a lower chord arch 3. The left end of the upper chord beam 2 and the left arch foot of the lower chord arch 3 are both connected to pier 1. The right end of the upper chord beam 2 and the arch top of the lower chord arch 3 are closed. Figure 1As shown, the upper chord beam 2 and the lower chord arch 3 are cast in 13 sections, wherein the thirteenth section is the closing section 22 of the upper chord beam 2 and the lower chord arch 3, the upper chord beam 0# section 20 is above the pier 1, and the upper chord beam 1# section 21, the upper chord beam 2# section 22 are from near to far away from the upper chord beam 0# section 20, and so on; the lower chord arch 0# section 30 is cast on both sides of the pier 1 together with the pier 1, and the lower chord arch 1# section 31 is from near to far away from the lower chord arch 0# section 30. , lower chord arch 2# section 32, and so on; the purpose of casting the lower chord arch 0# section 30 and the bridge pier 1 together is to reserve in advance for connection with the lower chord arch 1# section 31; a plurality of lower tie cables 44 are arranged on the bridge pier 1, and the lower tie cables 44 all pass through the bridge pier 1, and the two ends of the lower tie cables 44 are respectively anchored in the lower chord arch 3 on both sides of the bridge pier 1, and from the lower chord arch 2# section 32, each section is cast and two lower tie cables 44 are constructed; the following are installed on the upper chord beam 0# section 20 Figure 2 The temporary cable tower 9 shown in the figure has an upper cable 43 disposed thereon. The temporary cable tower 9 includes a lower tower and an upper tower. The lower tower includes a plurality of truss units 92. The plurality of adjacent truss units 92 are arranged vertically. Figure 4 As shown, each truss unit 92 includes a rectangular frame, which is composed of four columns 93. The four sides of the rectangular frame are provided with truss plates 94, and the truss plates 94 are bolted to two adjacent columns 93; the upper end of the column 93 of each truss unit 92 is bolted to the bottom of the column 93 of the truss unit 92 above, and an embedded part is provided on the upper chord beam 0# section 20, and the lower end of the column 93 of the bottom truss unit 92 is bolted to the embedded part on the upper chord beam 0# section 20; the upper tower includes a plurality of tension units 91, and the plurality of tension units 91 are arranged vertically. The number of tension units 91 on the upper tower increases with the construction progress of the upper chord beam 2, as shown in FIG. Figure 3 As shown, the tension units 91 also include a rectangular frame. The difference between the rectangular frame of the tension unit 91 and the rectangular frame of the truss unit 92 is that two horizontal tie rods 95 are respectively provided on the two sides of the rectangular frame parallel to the upper tie cable 43, and the horizontal tie rods 95 are respectively bolted to two adjacent columns 93, and the upper end of the upper tie cable 43 is bolted to the column 93, and the ends of the horizontal tie rods 95 and the upper end of the upper tie cable 43 are located on both sides of the same height of the same column 93. The total number of horizontal tie rods 95 of all tension units 91 is the same as the number of upper tie cables 43 on one side of the cable tower; starting from the upper chord beam 1# section 21, each segment is cast, and two upper tie cables 43 are installed, and the lower ends of every two upper tie cables 43 are connected to a segment of the upper chord beam 2.

[0084] The upper chord beam 2 and the lower chord arch 3 are constructed by using an upper chord hanging basket 41 and a lower chord hanging basket 42 respectively, and the construction is cantilevered from the top of the pier 1 to both sides. The upper chord hanging basket 41 and the lower chord hanging basket 42 both include a walking system 50, a main girder system, a suspension system and a bottom basket system. The walking system 50 is installed on the upper surface of the upper chord beam 2 or the lower chord arch 3. The main girder system is installed on the walking system 50 and extends in the direction of the cantilever end. The upper end of the suspension system is detachably connected to the main girder system, and the lower end of the suspension system is connected to the bottom basket system. The bottom basket system serves as a supporting platform to bear the construction load. In this solution, the walking system 50 and the main girder system of the hanging basket are the same as those in the prior art. The hanging basket also includes a lifting system. The lifting system gives the upper chord hanging basket 41 a lifting function, so that the bottom basket system can move downward, so that the upper chord hanging basket 41 and the lower chord hanging basket 42 can alternately use the suspension system and the bottom basket system.

[0085] like Figure 5 , Figure 6 As shown, the main truss system of the upper chord hanging basket 41 and the lower chord hanging basket 42 both include a prismatic main truss 51, a front crossbeam 52 is welded to the front end of the main truss 51, and a rear crossbeam 53 is welded to the middle of the main truss 51. The front crossbeam 52 and the rear crossbeam 53 are both formed by combining two parallel I-beams, and a gap is left between the two parallel I-beams; Figure 7 As shown, the main truss systems of the upper chord cradle 41 and the lower chord cradle 42 differ in that the slopes of the bottoms of the main trusses 51 are different to accommodate walking on the upper chord beam 2 and the lower chord arch 3, respectively.

[0086] The bottom basket system of the upper string hanging basket 41 includes a front cantilever beam 61 and a rear cantilever beam 62. The front cantilever beam 61 is located directly below the front cross beam 52, and the rear cantilever beam 62 is located directly below the rear cross beam 53. Two longitudinal beams 63 are arranged between the front cantilever beam 61 and the rear cantilever beam 62. The front cantilever beam 61 and the rear cantilever beam 62 are both formed by a combination of two parallel I-beams, and a gap is left between the two parallel I-beams. Two hinged units are arranged on the front cantilever beam 61, and each hinged unit includes two connecting blocks 64. The two connecting blocks 64 are welded to the front cross beam 52. The left ends of the longitudinal beams 63 are slidably supported on the rear cantilever beam 62. A latch 65 is arranged at the right end of the longitudinal beam 63. The latch 65 passes through the right end of the longitudinal beam 63 and the two connecting blocks 64 at the same time and is rotatably connected to the three. The right end of the longitudinal beam 63 is arranged between the two connecting blocks 64.

[0087] The lifting system includes four lifting devices (not shown in the figure), the lifting devices are winches or electric hoists 7. In this embodiment, the lifting devices are electric hoists 7; the upper ends of the electric hoists 7 are bolted to the main truss system of the upper chord hanging basket 41, specifically located at the two ends of the front crossbeam 52 and the rear crossbeam 53, and the lower ends of the steel cables of the electric hoists 7 are hung at the two ends of the front cantilever beam 61 and the rear cantilever beam 62 respectively;

[0088] The suspension system of the upper chord hanging basket 41 includes four suspension units, and the positions of the suspension units and the electric hoists 7 correspond one to one. The suspension units all include a suspension rod 84 and an extension rod 85. The upper and lower ends of the suspension rod 84 are respectively provided with an upper connecting piece 81 and a lower connecting piece. The upper end of the suspension rod 84 passes through the front cross beam 52 or the rear cross beam 53 of the main truss system of the upper chord hanging basket 41. The upper connecting piece 81 includes an upper nut 811 and an upper pad 812. The upper pad 812 is supported on the front cross beam 52 or the rear cross beam 53 and is passed through by the suspension rod 84. The upper nut 811 is threadedly connected to the upper nut 811. Connect to the upper end of the suspension rod 84, tighten the upper nut 811, the upper nut 811 cooperates with the front cross beam 52 or the rear cross beam 53 to clamp the upper pad 812; similarly, the composition of the lower connecting member is the same as that of the upper nut 811, the lower connecting member includes a lower nut and a lower pad, the lower pad is arranged at the lower side of the front cantilever beam 61 or the rear cantilever beam 62 and is passed through by the lower end of the suspension rod 84, the lower nut is threadedly connected to the lower end of the suspension rod 84, tighten the lower nut, the lower nut cooperates with the front cantilever beam 61 or the rear cantilever beam 62 to clamp the lower pad, thereby providing support for the front cantilever beam 61 or the rear cantilever beam 62;

[0089] like Figure 8 As shown, when the suspension rod 84 is extended, the suspension rod 84 and the extension rod 85 can be connected by an extension connector 82. The extension connector 82 is a sleeve with an internal thread. The lower end of the extension connector 82 is threadedly connected to the upper end of the suspension rod 84. The threads on the suspension rod 84 and the extension rod 85 have the same direction. A conversion pad 83 is welded at the lower end of the extension connector 82, and the upper end of the suspension rod 84 can pass through the conversion pad 83.

[0090] Example 2

[0091] Double hanging buckle construction method for beam-arch composite bridge, such as Figure 9-14 As shown, the construction is carried out based on the hanging basket in Example 1, including the following steps:

[0092] Step 1: Fig. 9 As shown, the construction of the bridge pier 1 is completed. During the construction of the bridge pier 1, a horizontally arranged lower chord arch 0# section 30 is reserved on both sides of the bridge pier 1, an upper chord beam 0# section 20 is cast on the top of the bridge pier 1, and an upper chord hanging basket 41 is installed on the upper chord beam 0# section 20;

[0093] Step 2: Use a hanging basket to cast the upper chord beam 2 and the lower chord arch 3 in sections; at the same time, install a temporary cable tower 9 on the upper chord beam 20# section, install a number of upper cable ties 43 on the temporary cable tower 9, and each section of the upper chord beam 2 is connected to the lower ends of the two upper cable ties 43 respectively; at the same time, install a lower cable ties 44 on each section of the lower chord arch 3, and the middle part of the lower cable ties 44 passes through the bridge pier 1;

[0094] The method of using a hanging basket to cast the upper chord beam 2 and the lower chord arch 3 in sections is as follows:

[0095] Step 2.1, use the upper chord hanging basket 41 to cast the upper chord beam 1# segment 21, and at the same time install it on the lower tower of the temporary cable tower 9 on the chord beam 0# segment 20, install a tension unit 91 at the upper end of the lower tower, and install two upper tie cables 43 on both sides of the tension unit 91 to ensure that the angle between the first upper tie cable 43 and the horizontal line is greater than 30°, and the lower end of the upper tie cable 43 is connected to the upper chord beam 21# segment (the connection method of the tie cable and concrete is usually to pre-embed the connecting parts in the concrete, and then connect the connecting parts and the tie cable bolts).

[0096] A lifting system is installed on the main truss system of the upper chord hanging basket 41, and the lifting system can drive the bottom basket system to move downward, and remove the connection between the upper end of the suspension system and the main truss system;

[0097] Step 2.2, remove the upper connector 81 at the upper end of the suspension rod 84, temporarily tie and fix the suspension rod 84 and the steel cable of the electric hoist by wire, and the four electric hoists 7 jointly drive the bottom basket system to move downward, the lower end of the electric hoist on the rear crossbeam 53 descends faster than the lower end of the electric hoist 7 on the front crossbeam 52, and the right end of the longitudinal beam 63 rotates around the latch 65 on the front crossbeam 52, so that the slope of the longitudinal beam 63 of the bottom basket system is the same as the slope of the bottom of the lower chord arch 1# section 31, and the main truss system, the suspension system and the bottom basket system are driven backward by the walking mechanism of the upper chord hanging basket 41, and the bottom basket system is driven to move to the arch foot position of the lower chord arch 3, and the template of the lower chord arch 1# section 31 is set on the bottom basket system, and the bottom basket system and the template of the lower chord arch 1# section 31 are detachably connected by fasteners or other connecting parts, and the template of the lower chord arch 1# section 31 is connected to the lower chord arch 0# section 30;

[0098] like Fig.10 As shown, the upper end of the suspension system is extended to connect the upper end of the suspension system with the main truss system of the upper chord hanging basket 41: the upper end of the extension rod 85 passes through the main truss system of the upper chord hanging basket 41 and is threadedly connected to the upper connecting piece 81, the upper connecting piece 81 is supported on the main truss system, the extension connecting piece 82 is threadedly connected to the lower end of the extension rod 85, the iron wire on the suspension rod 84 and the steel cable of the electric hoist is removed, and the lower chord arch 1# section 31 is cast with the bottom basket system as support;

[0099] Step 2.3: Fig.11 As shown, the walking system 50 of the upper chord hanging basket 41 drives the main truss system, the lifting system, the suspension system and the bottom basket system to move forward together, and the lower chord arch 2# section 32 is cast with the bottom basket system as support; the two ends of a lower cable 44 are respectively anchored in the lower chord arch 2# section 32 on both sides of the pier 1;

[0100] Step 2.4: Fig.12As shown, the walking system 50 and the main truss system of the lower chord hanging basket 42 are installed on the lower chord arch 1# segment 31 and 2# segment, the main truss system of the lower chord hanging basket 42 is connected to the upper end of the suspension system of the upper chord hanging basket 41, and the suspension system and the bottom basket system of the upper chord hanging basket 41 are converted into the suspension system and the bottom basket system of the lower chord hanging basket 42;

[0101] The method for converting the suspension system and bottom basket system of the upper hanging basket 41 into the suspension system and bottom basket system of the lower hanging basket 42 is as follows:

[0102] Step 2.4.1, during the installation of the main truss system of the lower chord hanging basket 42, the suspension rod 84 of the upper chord hanging basket 41 is passed through the front cross beam 52 or the rear cross beam 53 of the lower chord hanging basket 42. Since the front cross beam 52 or the rear cross beam 53 is composed of two I-beams, when welding the front cross beam 52, the suspension rod 84 is located between the two I-beams, so that the suspension rod 84 can pass through the front cross beam 52 or the rear cross beam 53 without disconnecting the suspension rod 84 and the extension rod 85;

[0103] The upper end of the electric hoist 7 is bolted to the front crossbeam 52 or the rear crossbeam 53 of the lower string hanging basket 42, and the lower end of the electric hoist 7 is hung on the front cantilever beam 61 or the rear cantilever beam 62 of the upper line hanging basket;

[0104] Step 2.4.2, such as Figure 8 As shown, rotate the extension connector 82 to move it downward so that the conversion pad 83 at the lower end of the extension connector 82 is supported on the main truss system of the lower chord hanging basket 42, remove the upper connector 81 at the upper end of the extension rod 85, rotate the extension rod 85 to disengage the lower end of the extension rod 85 from the extension connector 82, and remove the extension rod 85 and the electric hoist 7.

[0105] Step 2.5: Fig.13 As shown, the lower chord arch 3# section 33 is cast, and the two ends of a lower cable 44 are respectively anchored in the lower chord arch 3# section 33 on both sides of the pier 1; the suspension system and the bottom basket system of the upper chord hanging basket 41 are reinstalled, and the upper chord hanging basket 41 is used to cast the upper chord beam 2# section 22;

[0106] Step 2.6: Fig.14 As shown, the remaining segments of the upper chord beam 2 and the lower chord arch 3 are cast until the upper segment of the closing segment 22 of the lower chord arch 3. When two segments of the upper chord beam 2 are cast, a tension unit 91 is newly installed at the upper end of the temporary cable tower 9. The upper chord beam 2 lags behind the lower chord arch 32 segments and is synchronously advanced in construction.

[0107] Step 3: remove the hanging basket on the lower chord arch 3, use the hanging basket on the upper chord beam 2 to cast the upper section of the closing section 22, and finally cast the closing section 22.

[0108] Example 3

[0109] Embodiment 3 is based on embodiment 2: four strip-shaped bolt holes 831 are opened on the conversion pad 83, and a limiting bolt 832 can be installed in each bolt hole;

[0110] In step 2.4.2, the conversion pad 83 is supported on the front crossbeam 52 or the rear crossbeam 53 of the main truss system of the lower chord hanging basket 42, and four limit bolts 832 are installed on the conversion pad 83. Taking the front crossbeam 52 as an example, Fig.15 As shown, four limit bolts 832 are evenly distributed and fit on both sides of the front cross beam 52, so as to limit the distance between the two I-beams constituting the front cross beam 52. The limit bolts 832 need to be fixed in the strip bolt holes 831 in cooperation with nuts. When limiting the distance between the two I-beams by the limit bolts 832, the size of the nuts needs to be considered.

[0111] The effect of Example 3 is as follows Fig.16 As shown in the figure, the weight of the formwork of the lower chord arch 3, the concrete, and the loads generated by various components will all be transmitted to the longitudinal beam 63. Since the longitudinal beam 63 and the front cantilever beam 61 are hinged, most of the load of the longitudinal beam 63 is transmitted to the front cantilever beam 61 through the latch 65. If only the latch 65 is considered to bear most of the load, the strength of the latch 65 is often difficult to bear. In this embodiment, the direct contact point P between the longitudinal beam 63 and the front cantilever beam 61 needs to be considered. When the longitudinal beam 63 rotates to a certain angle, the load of the longitudinal beam 63 The pressure is transmitted to the longitudinal beam 63 through point P. However, at this time, the longitudinal beam 63 generates a pressure perpendicular to the length direction of the longitudinal beam 63 on the front cantilever beam 61 (in the direction of the arrow in the figure), thereby driving the lower end of the suspension rod 84 to move to the right through the front cantilever beam 61, thereby driving the suspension rod 84 to tilt. The greater the pressure change, the greater the back-and-forth swing. In this solution, by setting a limit bolt 832, the upper end of the suspension rod 84 is clamped through the front cross beam 52 of the lower chord hanging basket 42 to limit the tilting of the suspension rod 84, thereby reducing this swing and ensuring construction safety.

[0112] The above is only an embodiment of the present invention, and the common knowledge such as the known specific technical solutions and / or characteristics in the solution is not described in detail here. It should be pointed out that for those skilled in the art, without departing from the technical solution of the present invention, several modifications and improvements can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.

Claims

1. Double-hook construction method for beam-arch composite bridge, characterized in that: The beam-arch composite bridge includes an upper chord beam and a lower chord arch. Both the upper chord beam and the lower chord arch are constructed by hanging baskets, which are cantilevered from the central axis of the pier to both sides of the pier. One end of the upper chord beam and the arch foot of the lower chord arch are connected to the pier, and the other end of the upper chord beam is closed with the arch top of the lower chord arch. Both the upper chord beam and the lower chord arch are cast in several sections. The following steps are involved: Step 1: Complete the construction of the bridge piers, cast the 0# section of the upper chord beam on the top of the piers, and install the hanging basket on the 0# section of the upper chord beam. Step 2: Use a hanging basket to cast the upper chord beam and the lower chord arch in sections; at the same time, set up a temporary cable tower on the 0# section of the upper chord beam, install several upper cable ties on the temporary cable tower, and each section of the upper chord beam is connected to the lower ends of the two upper cable ties respectively; at the same time, install lower cable ties on each section of the lower chord arch, and the middle part of the lower cable ties passes through the bridge pier; Step 3: Remove the hanging basket on the lower chord arch and use the hanging basket on the upper chord beam to cast the closing section.

2. The double-hook construction method for a beam-arch composite bridge according to claim 1, characterized in that: The temporary cable tower includes a lower tower and an upper tower. The lower tower is fixed on the 0# section of the upper chord beam. The upper tower includes a number of tension units. The number of tension units on the upper tower increases with the construction progress of the upper chord beam.

3. The double-hook construction method for a beam-arch composite bridge according to claim 2 is characterized in that: The tensioning units all include a rectangular frame, and two horizontal tie rods are respectively provided on the two sides of the rectangular frame parallel to the upper tie cables, and the two ends of the horizontal tie rods are respectively at the same height as the end of an upper tie cable, and the number of the horizontal tie rods is the same as the number of upper tie cables on one side of the cable tower; truss plates are provided on the two sides of the rectangular frame parallel to the upper tie cables; In step 2, after casting two sections of the upper chord beam, a new tension unit is installed on the upper end of the temporary cable tower.

4. The double-hook construction method for a beam-arch composite bridge according to claim 3 is characterized in that: The lower tower includes a plurality of truss units, the upper and lower ends of adjacent truss units are connected by bolts, and each truss unit also includes a rectangular frame, and truss plates are arranged on four sides of the rectangular frame; In step 2, truss units are installed upward on the 0# section of the upper chord beam in sequence until the angle between the first upper cable and the horizontal line is greater than 30°.

5. The double-hook construction method for a beam-arch composite bridge according to claim 4, characterized in that: The hanging basket is divided into an upper hanging basket and a lower hanging basket. Both the upper hanging basket and the lower hanging basket include a traveling system, a main truss system, a suspension system and a bottom basket system. The traveling system is installed on the upper surface of the upper chord beam or the lower chord arch. The main truss system is installed on the traveling system and extends toward the cantilever end. The upper end of the suspension system is detachably connected to the main truss system, and the lower end of the suspension system is connected to the bottom basket system. The bottom basket system serves as a supporting platform to bear the construction load. In step 2, the method of using a hanging basket to cast the upper chord beam and the lower chord arch in sections is as follows: Step 2.1 Use the upper chord hanging basket to cast the upper chord beam section 1#, install the lifting system on the main truss system of the upper chord hanging basket, the lifting system can drive the bottom basket system to move downward, and remove the connection between the upper end of the suspension system and the main truss system; Step 2.2, the lifting system drives the bottom basket system to move downward to the arch foot of the lower chord arch, and the upper end of the suspension system is extended to connect the upper end of the suspension system with the main truss system of the upper chord hanging basket, and the lower chord arch 1# section is cast with the bottom basket system as support; Step 2.3, the walking system of the upper chord hanging basket drives the main truss system, the lifting system, the suspension system and the bottom basket system to move forward together, and the lower chord arch section 2# is cast with the bottom basket system as support; Step 2.4, install the walking system and main truss system of the lower chord hanging basket on the lower chord arch section 1# and section 2#, connect the main truss system of the lower chord hanging basket with the upper end of the suspension system of the upper chord hanging basket, and convert the suspension system and bottom basket system of the upper chord hanging basket into the suspension system and bottom basket system of the lower chord hanging basket; Step 2.5, use the lower chord hanging basket to cast the lower chord arch section 3#, reinstall the suspension system and bottom basket system of the upper chord hanging basket, and use the upper chord hanging basket to cast the upper chord beam section 2#; Step 2.6: Cast the remaining segments of the upper chord beam and the lower chord arch until the upper segment of the closed section of the lower chord arch.

6. The double-hook construction method for a beam-arch composite bridge according to claim 5, characterized in that: The lifting system includes several electric hoists; In step 2.1, during the construction of the bridge pier, the horizontally set lower chord arch 0# section is reserved, the upper ends of the electric hoists are connected to the main truss system of the upper chord hanging basket, and the lower ends of the electric hoists are hung on the bottom basket system; In step 2.2, when the electric hoist drives the bottom basket system to move downward, the upper end of the suspension system is temporarily fixed on the steel cable of the electric hoist; after the electric hoist drives the bottom basket system to move downward, the template of the lower chord arch section 1# is set up on the bottom basket system, the bottom basket system and the template of the lower chord arch section 1# are detachably connected, and the template of the lower chord arch section 1# is connected to the lower chord arch section 0#.

7. The double-hook construction method for a beam-arch composite bridge according to claim 6, characterized in that: The suspension system of the upper chord hanging basket includes a plurality of suspension units, each of which includes a suspension rod and an extension rod. The upper and lower ends of the suspension rod are respectively provided with an upper connecting piece and a lower connecting piece. The upper end of the suspension rod passes through the main truss system of the upper chord hanging basket and is threadedly connected to the upper connecting piece. The upper connecting piece is supported on the main truss system. In step 2.2, the upper connector is removed, and the steel cables of the boom and the electric hoist are temporarily fixed by iron wire. The electric hoist drives the bottom basket system to move downward, and the upper end of the extension rod passes through the main truss system of the upper chord hanging basket and is threadedly connected to the upper connector. The upper connector is supported on the main truss system, and the extension connector is threadedly connected at the lower end of the extension rod. The lower end of the extension connector is threadedly connected to the upper end of the boom, and the iron wire on the steel cables of the boom and the electric hoist is removed.

8. The double-hook construction method for a beam-arch composite bridge according to claim 7, characterized in that: The thread directions of the suspension rod and the extension rod are the same, and a conversion pad is welded at the lower end of the extension connector, and the upper end of the suspension rod can pass through the conversion pad; the main truss system of the upper chord hanging basket and the lower chord hanging basket both include a main truss, and a front crossbeam and a rear crossbeam are provided on the main truss. The front crossbeam or the rear crossbeam is composed of two parallel I-beams, and the distance between the two I-beams is less than the width of the conversion pad; the bottom basket system of the upper chord hanging basket includes a front cantilever beam and a rear cantilever beam, and a plurality of longitudinal beams are provided between the front cantilever beam and the rear cantilever beam; one end of the plurality of longitudinal beams is hinged to the front cantilever beam, and a plurality of horizontally arranged support pipes are provided on the rear cantilever beam, and the other end of the longitudinal beam is supported on the support pipe, and the other end of the longitudinal beam can slide on the support pipe; In step 2.4, the method of converting the suspension system and bottom basket system of the upper string hanging basket into the suspension system and bottom basket system of the lower string hanging basket is: Step 2.4.1, during the installation of the main truss system of the lower chord hanging basket, make the suspension rod of the upper chord hanging basket pass through the front beam or rear beam of the lower chord hanging basket, hang the upper end of the electric hoist on the front beam or rear beam, and hang the lower end of the electric hoist on the front cantilever beam or rear cantilever beam; Step 2.4.2, rotate the extension connector so that the conversion pad at the lower end of the extension connector is supported on the main truss system of the lower chord hanging basket, remove the upper connector at the upper end of the extension rod, rotate the extension rod to separate the lower end of the extension rod from the extension connector, and remove the extension rod and the electric hoist.

9. The double-hook construction method for a beam-arch composite bridge according to claim 8, characterized in that: There are four strip-shaped bolt holes on the conversion pad, and a limit bolt can be installed in each bolt hole; In step 2.4.2, the conversion pad is supported on the front beam or rear beam of the main truss system of the lower chord hanging basket, and four limit bolts are installed on the conversion pad. The four limit bolts are evenly distributed and fit on both sides of the front beam or rear beam, thereby limiting the distance between the two I-beams constituting the front beam or rear beam.