Leakage blocking mechanism for ultra-deep foundation pit supporting ground wall and construction method

By setting up water pumping holes and grouting holes at the leakage of the foundation pit ground wall, and using the telescopic grooves and spring mechanisms of the sealing plate and clamping plate, the simultaneous sealing of multiple leakage places is achieved, solving the existing solution The problem of low sealing efficiency in multiple leaks in the technology reduces soil loss and improves construction safety.

CN118997197APending Publication Date: 2024-11-22THE FIRST COMPARY OF CHINA EIGHTH ENG BUREAU LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411260431.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

When handling multiple leakage places in the prior art, grouting equipment can only seal one leakage place, resulting in the loss of soil on the foundation pit ground wall, affecting the stability of the foundation pit and surrounding buildings, and causing safety hazards.

Method used

A leakage sealing mechanism for super-deep foundation pit supporting floor wall is designed. By setting up water pumping holes and grouting holes at the leakage of the foundation pit floor wall body, the expansion and contraction of the sealing plate and the clamping plate are used. The groove and spring mechanism quickly fix and seal the pumping communication pipe and grouting communication pipe, achieving simultaneous sealing of multiple leakage places.

Benefits of technology

It effectively reduces soil loss in the foundation pit ground wall body, ensures the stability of the foundation pit and surrounding buildings, and improves the sealing efficiency and safety of the leakage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997197A_ABST
    Figure CN118997197A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of leakage blocking mechanisms for ultra-deep foundation pit supporting ground walls and construction methods, in particular to a leakage blocking mechanism for ultra-deep foundation pit supporting ground walls and a construction method. The leakage blocking mechanism comprises a blocking plate, a water pumping communicating pipe is arranged in the middle of the bottom end of the blocking plate, and a grouting communicating pipe is arranged in the middle of the top end of the blocking plate; first telescopic grooves are formed in the positions, on the outer sides of the water pumping communicating pipe and the grouting communicating pipe, of the foundation pit ground wall body at the same time, first springs are arranged on the two sides of each first telescopic groove, and the inner sides of the first springs are connected with the clamping plates. The interior of the foundation pit ground wall body is provided with a leakage part; the leakage blocking mechanism for the ultra-deep foundation pit supporting ground wall and the construction method have the beneficial effects that firstly, the water pumping hole and the grouting hole are formed in the upper end and the lower end of the position, with leakage, of the foundation pit ground wall body correspondingly, and then the water pumping communicating pipe and the grouting communicating pipe on the inner side of the blocking plate are aligned to the water pumping hole and the grouting hole.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of a leakage plugging mechanism and a construction method for an ultra-deep foundation pit supporting ground wall, and in particular to a leakage plugging mechanism and a construction method for an ultra-deep foundation pit supporting ground wall. Background Art

[0002] The foundation pit support structure is an underground concealed project. During its construction, it is impossible to know whether the entire support structure is sealed or water-stopping. The leaking locations and conditions of the supporting ground wall can only be discovered after the foundation pit is excavated. Foundation pit leakage will have varying degrees of impact on foundation pit construction. In severe cases, it will cause failure of foundation pit excavation and damage to the surrounding environment. In order to avoid the impact of foundation pit leakage on foundation pit construction and the surrounding environment, the leaking areas must be promptly plugged after foundation pit excavation.

[0003] In the prior art, holes are usually drilled at the leakage points of the foundation pit ground wall, and then the water in the leakage area is extracted, and then the leakage points are sealed by static pressure grouting using a 1:1 cement-water glass double liquid slurry.

[0004] However, there are often multiple leaks in the existing foundation pit walls, but the grouting equipment can only grout and seal one leak, while other leaks will continue to seep water, causing soil loss in the foundation pit, affecting the stability of the foundation pit and surrounding buildings, and causing safety hazards. Summary of the invention

[0005] The object of the present invention is to provide a leakage blocking mechanism and construction method for ultra-deep foundation pit supporting ground wall, so as to solve the specific problem proposed in the above background technology and to add the problem to be solved here.

[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a sealing plate, a water pumping connecting pipe is arranged in the middle of the bottom end of the sealing plate, a grouting connecting pipe is arranged in the middle of the top end of the sealing plate, a foundation pit ground wall body is provided with a first expansion groove on the outside of the water pumping connecting pipe and the grouting connecting pipe, a first spring is arranged on both sides of the first expansion groove, and the inner side of the first spring is connected to the clamping plate; and a foundation pit ground wall body, a leakage point is arranged inside the foundation pit ground wall body, a water pumping hole is arranged at the bottom end of the leakage point, a grouting hole is arranged at the top end of the leakage point, and the water pumping hole and the grouting hole are communicated with the sealing plate.

[0007] Preferably, the plugging plate can be placed on the outside of the leakage by inserting the grouting connecting pipe into the grouting hole and the pumping connecting pipe into the pumping hole, and the plugging plate can be fixed on the outside of the leakage by inserting fixing screws around the plugging plate.

[0008] Preferably, a second expansion groove is opened on the inner side of the clamping plate, a second spring is arranged in the second expansion groove, the inner side of the second spring is connected to the closing plate, and the second spring can pop out the two groups of closing plates from the second spring through tension, so that the two groups of closing plates can close the water pumping connecting pipe and the grouting connecting pipe to prevent moisture in the leakage from seeping out of the water pumping connecting pipe and the grouting connecting pipe.

[0009] Preferably, the sealing plate and the clamping plate are simultaneously provided with a toggle groove in the middle part of the outer side of the second telescopic groove, and a toggle block is provided in the toggle groove. The bottom of the toggle block is connected to the closing plate. By pulling the toggle block, the closing plate can squeeze the second spring and shrink into the second telescopic groove, thereby opening the closure of the water pumping connecting pipe and the grouting connecting pipe.

[0010] Preferably, a pumping pipe can be inserted into the pumping connecting pipe so that the pumping pipe can pump out the water in the leakage through the pumping connecting pipe. A filter is provided at the inner end of the pumping connecting pipe, which can block the soil in the water in the leakage and prevent the soil in the leakage from being pumped out.

[0011] Preferably, a grouting pipe can be inserted into the grouting connecting pipe, and the grouting pipe can inject grout into the leaking place through the grouting connecting pipe to seal the leaking place.

[0012] Preferably, the clamping plate can squeeze the first spring so that the clamping plate contracts into the first telescopic groove. When the grouting pipe is inserted into the grouting connecting pipe, the first spring can make the clamping plate close to the grouting pipe through tension, so that the clamping plate surrounds the grouting pipe and seals the space between the grouting connecting pipe and the grouting pipe.

[0013] Preferably, a fixing groove is opened in the middle of the toggle block, and the fixing groove passes through the clamping plate and the closing plate. Inserting the fixing bolt into the fixing groove can fix the expansion and contraction of the clamping plate and the closing plate, thereby preventing the clamping plate and the closing plate from expanding and contracting, resulting in the closing plate being unable to close the water pumping connecting pipe and the grouting connecting pipe.

[0014] A construction method for a leakage blocking mechanism for an ultra-deep foundation pit supporting ground wall comprises the following steps:

[0015] Step 1: Initial plugging: First, open a pumping hole and a grouting hole at the upper and lower ends of the leakage point of the foundation pit wall body, then align the pumping connecting pipe and the grouting connecting pipe on the inner side of the plugging plate with the pumping hole and the grouting hole, and quickly place the plugging plate on the outside of the leakage point. Then, insert the fixing screws around the plugging plate to fix the plugging plate on the outside of the leakage point. At this time, the second expansion slot is in the pop-up state, and the second expansion slot begins to perform preliminary plugging of the water seepage at the leakage point.

[0016] Step 2: Blocking. Insert the water pump into the water pump connecting pipe. At this time, pull the toggle block from the open position. The first spring rebounds the clamping plate through tension, so that the clamping plate surrounds the water pumping pipe to prevent water from flowing out from the gap between the water pumping connecting pipe and the water pumping pipe. The closing plate continues to shrink in the second expansion groove through the extrusion of the water pumping pipe. Then the water pumping pipe draws out the seepage water in the leakage through the water pumping connecting pipe. A filter is provided at the inner end of the water pumping connecting pipe. The filter can block the soil in the seepage water to prevent the seepage water from being drawn out with the soil. When the seepage water in the leakage is drawn out After that, the pumping pipe is pulled out. At this time, the second spring drives the closing plate back through the tension to close the pumping connecting pipe, and then the fixing bolt is inserted into the fixing groove to fix the clamping plate and the closing plate. Then, the grouting pipe is inserted into the grouting connecting pipe by repeating the above steps. The grouting pipe begins to inject sealing cement into the leakage through the grouting connecting pipe to seal the leakage. After the cement grouting is completed, the grouting pipe is pumped out, and then the fixing bolt is inserted into the fixing groove to fix the clamping plate and the second expansion groove, and the closing plate closes the grouting connecting pipe.

[0017] Compared with the prior art, the present invention has the following beneficial effects:

[0018] The present invention proposes a leakage plugging mechanism and construction method for an ultra-deep foundation pit supporting ground wall. First, a pumping hole and a grouting hole are respectively opened at the upper and lower ends of the leakage point of the foundation pit ground wall body. Then, the pumping connecting pipe and the grouting connecting pipe on the inner side of the plugging plate are aligned with the pumping hole and the grouting hole, and the plugging plate is quickly placed on the outside of the leakage point. Then, the plugging plate is fixed to the outside of the leakage point by inserting fixing screws around the plugging plate. At this time, the second expansion groove is in a pop-up state, and the second expansion groove begins to preliminarily plug the seepage at the leakage point. Then, the above steps are repeated to install the plugging plates on multiple leakage points, and all the leakage points in the area of ​​the foundation pit ground wall body are blocked, thereby reducing the soil loss of the foundation pit ground wall body. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the three-dimensional structure of the present invention;

[0020] Figure 2 for Figure 1 A schematic diagram of the structure enlargement in the middle;

[0021] Figure 3 It is a schematic diagram of the cross-sectional structure of the present invention;

[0022] Figure 4 for Figure 3 A magnified schematic diagram of the structure at B in the middle;

[0023] Figure 5 This is a schematic diagram of the three-dimensional structure of the blocking plate of the present invention;

[0024] Figure 6 This is a schematic diagram of the cross-sectional structure of the plugging plate of the present invention;

[0025] Figure 7 It is a schematic diagram of the cross-sectional structure of the clamping plate of the present invention.

[0026] In the figure: foundation pit ground wall body 1, blocking plate 2, fixing screws 3, leakage point 4, pumping hole 5, grouting hole 6, pumping connecting pipe 7, filter screen 8, grouting connecting pipe 9, first telescopic groove 10, first spring 11, clamping plate 12, second telescopic groove 13, second spring 14, closing plate 15, toggle groove 16, toggle block 17, fixing groove 18, fixing bolt 19. DETAILED DESCRIPTION

[0027] In order to make the purpose and technical solution of the present invention clearly and completely described, and the advantages more clearly understood, the embodiments of the present invention are further described in detail with reference to the accompanying drawings. It should be understood that the specific embodiments described herein are part of the embodiments of the present invention, rather than all of the embodiments, and are only used to explain the embodiments of the present invention, and are not used to limit the embodiments of the present invention. All other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0028] In the description of the present invention, it should be noted that the terms "center", "middle", "upper", "lower", "left", "right", "inner", "outer", "top", "bottom", "side", "vertical", "horizontal" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "one", "first", "second", "third", "fourth", "fifth", "sixth" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0029] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0030] For the purpose of simplicity and illustration, the principles of the embodiments are mainly described by reference to examples. In the following description, many specific details are proposed to provide a thorough understanding of the embodiments. However, it is obvious that for those of ordinary skill in the art, these embodiments may not be limited to these specific details in practice. In some instances, known methods and structures are not described in detail to avoid making these embodiments unnecessarily difficult to understand. In addition, all embodiments can be used in combination with each other.

[0031] Please refer to Figure 1 to Figure 2. The present invention provides a technical solution: a plugging plate, a pumping connecting pipe is arranged in the middle of the bottom end of the plugging plate, a grouting connecting pipe is arranged in the middle of the top end of the plugging plate, a foundation pit ground wall body is provided with a first telescopic groove on the outside of the pumping connecting pipe and the grouting connecting pipe, first springs are arranged on both sides of the first telescopic groove, and the inner side of the first spring is connected to the clamping plate; and a foundation pit ground wall body, a leakage point is arranged inside the foundation pit ground wall body, a pumping hole is arranged at the bottom end of the leakage point, a grouting hole is arranged at the top end of the leakage point, and the pumping hole and the grouting hole are connected to the plugging plate; the plugging plate can be placed on the outside of the leakage point by inserting the grouting connecting pipe into the grouting hole and the pumping connecting pipe into the pumping hole, and the plugging plate can be fixed on the outside of the leakage point by inserting fixing screws around the plugging plate;

[0032] A second expansion slot is provided on the inner side of the clamping plate, a second spring is provided in the second expansion slot, and a closing plate is connected to the inner side of the second spring. The second spring can pop out the two sets of closing plates from the second spring through tension, so that the two sets of closing plates can close the water pumping connecting pipe and the grouting connecting pipe to prevent water in the leakage from seeping out of the water pumping connecting pipe and the grouting connecting pipe; the sealing plate and the clamping plate are simultaneously provided with a toggle slot in the middle part of the outer side of the second expansion slot, a toggle block is provided in the toggle slot, and the bottom of the toggle block is connected to the closing plate, and the closing plate can be made to squeeze the second spring and shrink into the second expansion slot by pulling the toggle block to open the closure of the water pumping connecting pipe and the grouting connecting pipe; the water pumping connecting pipe can be plugged into the water pumping connecting pipe so that the water pumping connecting pipe can pump water from the leakage through the water pumping connecting pipe, and a filter is provided at the inner end of the water pumping connecting pipe, and the filter can block the soil in the water in the leakage to prevent the soil in the leakage from being pumped out;

[0033] The grouting pipe can be inserted into the grouting connecting pipe, and the grouting pipe can be used to inject grout into the leaking place through the grouting connecting pipe to seal the leaking place; the clamping plate can squeeze the first spring to shrink the clamping plate into the first expansion groove. When the grouting pipe is inserted into the grouting connecting pipe, the first spring can make the clamping plate close to the grouting pipe through tension, so that the clamping plate surrounds the grouting pipe and seals the grouting connecting pipe and the grouting pipe; a fixing groove is provided in the middle of the toggle block, and the fixing groove passes through the clamping plate and the closing plate. Inserting a fixing bolt into the fixing groove can fix the expansion and contraction of the clamping plate and the closing plate, thereby preventing the clamping plate and the closing plate from expanding and contracting, resulting in the closing plate being unable to seal the pumping connecting pipe and the grouting connecting pipe.

[0034] First, a pumping hole and a grouting hole are respectively opened at the upper and lower ends of the leakage point of the foundation pit ground wall body, and then the pumping connecting pipe and the grouting connecting pipe on the inner side of the plugging plate are aligned with the pumping hole and the grouting hole, and the plugging plate is quickly placed on the outside of the leakage point, and then the plugging plate is fixed to the outside of the leakage point by inserting fixing screws around the plugging plate. At this time, the second expansion groove is in a pop-up state, and the second expansion groove begins to preliminarily block the water seepage at the leakage point. Then, the above steps are repeated to install the plugging plates on multiple leakage points, and all the leakage points in the area of ​​the foundation pit ground wall body are blocked, thereby reducing the soil loss of the foundation pit ground wall body;

[0035] At the same time, when other operators install plugging plates at other leaking places, they pull out the fixing bolts inserted in the middle fixing groove of the toggle block on the outside of the water pumping connecting pipe, and then pull the toggle block to squeeze the second telescopic groove, so that the closing plate shrinks into the second telescopic groove. At the same time, by pulling the toggle block, the clamping plate can be linked and retracted to the first telescopic groove, and then the water pumping pipe is inserted into the water pumping connecting pipe. At this time, when the toggle block is pulled from the open position, the first spring rebounds the clamping plate through tension, so that the clamping plate surrounds the water pumping connecting pipe to prevent seepage from flowing out from the gap between the water pumping connecting pipe and the water pumping connecting pipe. The closing plate continues to shrink in the second telescopic groove through the squeezing of the water pumping connecting pipe, and then the water pumping pipe draws out the seepage in the leaking place through the water pumping connecting pipe. A filter is provided at the inner end of the water pumping connecting pipe, which can filter the seepage The soil in the water is blocked to prevent the seepage water from being pumped out with the soil. When the seepage water in the leakage place is completely pumped out, the pumping pipe is pulled out. At this time, the second spring drives the closing plate back through the tension to close the pumping connecting pipe, and then the fixing bolt is inserted into the fixing groove to fix the clamping plate and the closing plate. After that, the grouting pipe is inserted into the grouting connecting pipe by repeating the above steps. The grouting pipe begins to inject plugging cement into the leakage place through the grouting connecting pipe to block the leakage. After the cement grouting is completed, the grouting pipe is pumped out, and the fixing bolt is inserted into the fixing groove to fix the clamping plate and the second expansion groove. The closing plate closes the grouting connecting pipe. When one group of leakage places is blocked, the next group of leakage places is blocked. When the blocking cement solidifies, the blocking plate can be removed.

[0036] Although the above describes the illustrative specific implementation methods of the present application so that technicians in this technical field can understand the present application, the present application is not limited to the scope of the specific implementation methods. For ordinary technicians in this technical field, as long as various changes are within the spirit and scope of the present application defined and determined by the attached claims, all application creations using the concept of the present application are protected.

Claims

1. A leakage plugging mechanism for supporting ground walls of ultra-deep foundation pits, characterized in that: include: A plugging plate (2), a water pumping connecting pipe (7) is arranged in the middle of the bottom end of the plugging plate (2), a grouting connecting pipe (9) is arranged in the middle of the top end of the plugging plate (2), a first telescopic groove (10) is formed on the outer sides of the water pumping connecting pipe (7) and the grouting connecting pipe (9) of the foundation pit ground wall body (1), first springs (11) are arranged on both sides of the first telescopic groove (10), and the inner side of the first spring (11) is connected to the clamping plate (12); and A foundation pit ground wall body (1) is provided with a leakage point (4) inside the foundation pit ground wall body (1), a pumping hole (5) is provided at the bottom end of the leakage point (4) of the foundation pit ground wall body (1), and a grouting hole (6) is provided at the top end of the leakage point (4) of the foundation pit ground wall body (1), and the pumping hole (5) and the grouting hole (6) are in communication with a blocking plate (2).

2. The leakage blocking mechanism for supporting ground walls of ultra-deep foundation pits according to claim 1 is characterized in that: The plugging plate (2) can be placed outside the leakage point (4) by inserting the grouting connecting pipe (9) into the grouting hole (6) and the pumping connecting pipe (7) into the pumping hole (5), and the plugging plate (2) can be fixed outside the leakage point (4) by inserting fixing screws (3) around the plugging plate (2).

3. The leakage blocking mechanism for supporting ground walls of ultra-deep foundation pits according to claim 2 is characterized in that: A second telescopic groove (13) is provided on the inner side of the clamping plate (12), a second spring (14) is provided in the second telescopic groove (13), the inner side of the second spring (14) is connected to a closing plate (15), and the second spring (14) can eject the two groups of closing plates (15) from the second spring (14) by tension, so that the two groups of closing plates (15) close the water pumping connecting pipe (7) and the grouting connecting pipe (9), thereby preventing moisture in the leakage point (4) from seeping out of the water pumping connecting pipe (7) and the grouting connecting pipe (9).

4. The leakage blocking mechanism for supporting ground walls of ultra-deep foundation pits according to claim 3 is characterized in that: The blocking plate (2) and the clamping plate (12) are both provided with a toggle groove (16) in the middle of the outer side of the second telescopic groove (13), a toggle block (17) is provided in the toggle groove (16), the bottom of the toggle block (17) is connected to the closing plate (15), and by pulling the toggle block (17), the closing plate (15) can press the second spring (14) and shrink into the second telescopic groove (13), thereby opening the sealing of the water pumping connecting pipe (7) and the grouting connecting pipe (9).

5. The leakage blocking mechanism for supporting ground walls of ultra-deep foundation pits according to claim 4 is characterized in that: The pumping connecting pipe (7) can be plugged into a pumping pipe so that the pumping pipe can pump water from the leakage point (4) through the pumping connecting pipe (7). A filter screen (8) is provided at the inner end of the pumping connecting pipe (7). The filter screen (8) can block soil in the water in the leakage point (4) to prevent the soil in the leakage point (4) from being pumped out.

6. The leakage blocking mechanism for supporting ground walls of ultra-deep foundation pits according to claim 5 is characterized in that: A grouting pipe can be inserted into the grouting connecting pipe (9), and the grouting pipe can inject grout into the leakage point (4) through the grouting connecting pipe (9) to seal the leakage point (4).

7. The leakage blocking mechanism for supporting ground walls of ultra-deep foundation pits according to claim 6 is characterized in that: The clamping plate (12) can squeeze the first spring (11) so that the clamping plate (12) contracts into the first telescopic groove (10); when the grouting pipe is inserted into the grouting connecting pipe (9), the first spring (11) can use tension to make the clamping plate (12) close to the grouting pipe, so that the clamping plate (12) surrounds the grouting pipe and seals the space between the grouting connecting pipe (9) and the grouting pipe.

8. The leakage blocking mechanism for supporting ground walls of ultra-deep foundation pits according to claim 7 is characterized in that: A fixing groove (18) is provided in the middle of the toggle block (17), and the fixing groove (18) penetrates the clamping plate (12) and the closing plate (15). Inserting a fixing bolt (19) into the fixing groove (18) can fix the expansion and contraction of the clamping plate (12) and the closing plate (15), thereby preventing the clamping plate (12) and the closing plate (15) from expanding and contracting, resulting in the closing plate (15) being unable to close the pumping connecting pipe (7) and the grouting connecting pipe (9).

9. A construction method for a leakage plugging mechanism for an ultra-deep foundation pit supporting ground wall according to any one of claims 1 to 8, characterized in that: The following steps are involved: Step 1: Preliminary plugging: first, a pumping hole (5) and a grouting hole (6) are respectively opened at the upper and lower ends of the leakage point (4) of the foundation pit ground wall body (1), and then the pumping connecting pipe (7) and the grouting connecting pipe (9) on the inner side of the plugging plate (2) are aligned with the pumping hole (5) and the grouting hole (6), and the plugging plate (2) is quickly placed on the outside of the leakage point (4), and then the plugging plate (2) is fixed on the outside of the leakage point (4) by inserting fixing screws (3) around the plugging plate (2). At this time, the second telescopic groove (13) is in a pop-up state, and the second telescopic groove (13) begins to perform preliminary plugging of the water seepage at the leakage point (4). Step 2: Blocking, insert the water extraction pipe into the water extraction connecting pipe (7), at this time, pull the toggle block (17) from the opening, the first spring (11) rebounds the clamping plate (12) through tension, so that the clamping plate (12) surrounds the water extraction pipe, preventing the seepage water from flowing out from the gap between the water extraction connecting pipe (7) and the water extraction pipe, the closing plate (15) continues to shrink in the second telescopic groove (13) through the squeezing of the water extraction pipe, and then the water extraction pipe extracts the seepage water in the leakage point (4) through the water extraction connecting pipe (7), and the inner end of the water extraction connecting pipe (7) is provided with a filter screen (8), the filter screen (8) can block the soil in the seepage water, and prevent the seepage water from being extracted with the soil, when the seepage water in the leakage point (4) is completely extracted, the water extraction pipe is extracted again. At this time, the second spring (14) drives the closing plate (15) back and forth through the tension force to close the pumping connecting pipe (7), and then the fixing bolt (19) is inserted into the fixing groove (18) so that the fixing bolt (19) can fix the clamping plate (12) and the closing plate (15) to be telescopically fixed. Then, the grouting pipe is inserted into the grouting connecting pipe (9) by repeating the above steps, and the grouting pipe begins to inject plugging cement into the leakage point (4) through the grouting connecting pipe (9) to plug the leakage point (4). After the cement grouting is completed, the grouting pipe is pumped out, and then the fixing bolt (19) is inserted into the fixing groove (18) so that the clamping plate (12) and the second telescopic groove (13) are telescopically fixed, and the closing plate (15) closes the grouting connecting pipe (9).